single-cavity module installation at mucool test area yağmur torun mice collaboration meeting...

Download Single-Cavity Module Installation at MuCool Test Area Yağmur Torun MICE Collaboration Meeting February 15, 2013

If you can't read please download the document

Upload: blaise-stevenson

Post on 24-Dec-2015

216 views

Category:

Documents


0 download

TRANSCRIPT

  • Slide 1
  • Single-Cavity Module Installation at MuCool Test Area Yamur Torun MICE Collaboration Meeting February 15, 2013
  • Slide 2
  • MTA 201-MHz Program Overview (Surface treatment, NF channel, MICE) 201-MHz MICE prototype cavity with SRF- like surface treatment (EP, HP rinse) Conditioned to design gradient quickly Demonstrated operation with curved Be windows Somewhat reduced performance in fringe field of solenoid No surface damage seen on cavity interior Some evidence for sparking in the coupler New design has been implemented Radiation output measured (MICE detector backgrounds) Future Install/operate single-cavity vessel Large diameter magnet (coupling coil) needed for field configuration closer to MICE/cooling channel February 15, 2013 Y. Torun | MICE cm352
  • Slide 3
  • 201-MHz Single-Cavity Module February 15, 2013 Y. Torun | MICE cm353 MICE cavity in vacuum vessel for MTA test Components 1 st MICE cavity EPed and now at Fermilab Be windows ready Tuner forks built Ready for fabrication of new couplers
  • Slide 4
  • 201-MHz Single-Cavity Module Assembly/integration Cavity and vessel at Lab-6 Clean room prepared Plan in place for handling and transport (R. Schultz, J. Volk) Assembly fixture designed (A. DeMello) Tuner control bench tested (P. Hanlet) Expect operation Summer 2013 beam test also under consideration Ultimately will be tested with the first Coupling Coil Magnet Requires 6-month MTA shutdown February 15, 2013 Y. Torun | MICE cm354
  • Slide 5
  • Current configuration Original prototype cavity still in the hall was lifted onto platform during long shutdown with shield wall out using temporary forklift No vacuum vessel, air outside end-plates for support Couplers already removed one cut up for inspection To be lifted off platform with new gantry crane span limited by entry maze and rolled out through labyrinth on casters Rails will be reused for new module Be windows will be transferred to new cavity February 15, 2013 Y. Torun | MICE cm355
  • Slide 6
  • Next -- Single-Cavity Vessel February 15, 2013 Y. Torun | MICE cm356
  • Slide 7
  • Final layout -- RFCC lite February 15, 2013 Y. Torun | MICE cm357
  • Slide 8
  • Cavity in Lab-6 February 15, 2013 Y. Torun | MICE cm358
  • Slide 9
  • Vacuum Vessel in Lab-6 February 15, 2013 Y. Torun | MICE cm359
  • Slide 10
  • Module Transport Will bring into MTA hall through labyrinth Vessel with heavily ribbed doors too wide for labyrinth Will remove and roll in doors separately Put on thin cover plate to keep module interior clean Module on stand too tall for clean room and labyrinth New transport stand is 10 shorter Tight fit checked with laser scan data February 15, 2013 Y. Torun | MICE cm3510
  • Slide 11
  • MTA Hall Layout February 15, 2013 Y. Torun | MICE cm3511
  • Slide 12
  • Laser scan data February 15, 2013 Y. Torun | MICE cm3512
  • Slide 13
  • Through the Maze February 15, 2013 Y. Torun | MICE cm3513
  • Slide 14
  • On Operational Stand
  • Slide 15
  • On Transport Stand, thin doors
  • Slide 16
  • Cover Plate Transport February 15, 2013 Y. Torun | MICE cm3516
  • Slide 17
  • Lab 6 Clean Room Once doors removed & transport stand installed Cavity installation Vertical In Lab 6 clean room Class 100 Insertion picture shown in clean room is old design New design (A. DeMello) hot off the press All mechanical assembly and RF testing in clean room February 15, 2013 Y. Torun | MICE cm3517
  • Slide 18
  • Cavity handling Detailed procedure available from LBNL February 15, 2013 Y. Torun | MICE cm3518
  • Slide 19
  • Tuner installation Initial concept horizontal layout February 15, 2013 Y. Torun | MICE cm3519
  • Slide 20
  • Cavity installation Vertical layout selected Smaller footprint better suited to available clean room space Similar to MICE RFCC Simplified (one-sided) February 15, 2013 Y. Torun | MICE cm3520
  • Slide 21
  • Insertion Fixture in Clean Room February 15, 2013 Y. Torun | MICE cm3521
  • Slide 22
  • Assembly in MTA Hall Remove transport stand, install operational stand In MTA Clean Room Install doors RF Couplers Other vacuum hardware February 15, 2013 Y. Torun | MICE cm3522
  • Slide 23
  • Put on doors in MTA clean room February 15, 2013 Y. Torun | MICE cm3523
  • Slide 24
  • Rough schedule February 15, 2013 Y. Torun | MICE cm3524 Date complete TaskCalendar time Augoperation with B3 w Juloperation at B=03 w JunRF commissioning2 w MayLLRF measurements3 d instrumentation3 d compressed air plumbing4 w water plumbing4 w leak-check/pumpdown2 d RF plumbing4 w align/survey in place1 d lift onto platform1 d swap stands1 d Install couplers1 d install windows, cover plates1 d clean MTA clean rm1 d remove old cavity3 d Maymove big crane into MTA1 d
  • Slide 25
  • Rough schedule February 15, 2013 Y. Torun | MICE cm3525 Date complet e TaskCalendar time Aprdisassy/move MTA crane to MTA1 d move to MTA1 w replace cover plates1 d remove windows1 d coupler conditioning2 w mount couplers on conditioning stand1 d leak check2 d LLRF measurements2 d install couplers1 d coupler fabrication8 w install cover plates1 d LLRF measurements1 w test tuner control2 w install actuators2 d install windows1 d Date complete TaskCalendar time remove windows1 d survey cavity in vessel1 d install cavity in vessel1 w remove cover plates1 d vessel into clean room1 d install tuning forks1 d tuning fork machining1 w Aprcavity on stand in clean rm1 d
  • Slide 26
  • Rough schedule February 15, 2013 Y. Torun | MICE cm3526 Date completeTaskCalendar time Marcoupler conditioning stand4 w clean clean room and parts3 d disassy/move MTA crane to Lab61 d cavity in Lab6 clean rm1 d replace cover plates1 d leak check2 d vacuum system3 w safety doc/review4 w diagnostics design/fab6 w Marfixture design/fab8 w Febflat cover plates2 w Lab6 clean rm prep1 w support stand mods1 w swap stands1 d survey vessel1 d transport stand3 w
  • Slide 27
  • Other issues Couplers preferable to test/condition before installation on cavity couplers for prototype were conditioned at SNS on custom stand looking into locating leftover parts to it back together (R. Rimmer) or designing a new stand Diagnostics will build top plate with RF and vacuum pickups acoustic sensors under test may be useful (P. Lane, P. Snopok) RF controls plan in place to upgrade Linac 201-MHz station (R. Pasquinelli) February 15, 2013 Y. Torun | MICE cm3527
  • Slide 28
  • Outlook On track for results from operation of single-cavity module at MTA by cm37 tight schedule and lots of work to do resource availability critical Installation will provide valuable experience for MICE RFCC module assembly There may be an opportunity to test MICE RF phase measurement concept February 15, 2013 Y. Torun | MICE cm3528
  • Slide 29
  • Credits Most mechanical engineering material from Ryan Schultz (FNAL) & Allan DeMello (LBNL) February 15, 2013 Y. Torun | MICE cm3529