Siri Caisson Permanent Support - A Unique Challenge 11 th February 2015 Alan Cassie, Subsea 7 Project Manager

Upload: vuongdiep

Post on 03-Nov-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Siri Caisson Permanent Support - A Unique Challenge · Siri Caisson Permanent Support - A Unique Challenge 11th February 2015 Alan Cassie, Subsea 7 Project Manager

Siri Caisson Permanent Support- A Unique Challenge

11th February 2015

Alan Cassie, Subsea 7 Project Manager

Page 2: Siri Caisson Permanent Support - A Unique Challenge · Siri Caisson Permanent Support - A Unique Challenge 11th February 2015 Alan Cassie, Subsea 7 Project Manager

2Page 9-Feb-15

• Project Overview• Challenges• Outcome• Lessons Learnt

Agenda

Page 3: Siri Caisson Permanent Support - A Unique Challenge · Siri Caisson Permanent Support - A Unique Challenge 11th February 2015 Alan Cassie, Subsea 7 Project Manager

3Page 9-Feb-15

• Platform Status• Design Concept• Design Basis

Project Overview

Page 4: Siri Caisson Permanent Support - A Unique Challenge · Siri Caisson Permanent Support - A Unique Challenge 11th February 2015 Alan Cassie, Subsea 7 Project Manager

4Page 9-Feb-15

DONG Siri Permanent Support Project• Siri Platform operated by Danish Oil

and Natural Gas (DONG) • DONG Siri platform located in North

Sea – Danish Sector (approx. 220km from coast)

• Water depth: 60-65m approx.

Denmark

Siri Caisson Permanent SupportProject Overview

Page 5: Siri Caisson Permanent Support - A Unique Challenge · Siri Caisson Permanent Support - A Unique Challenge 11th February 2015 Alan Cassie, Subsea 7 Project Manager

5Page 9-Feb-15

Siri Caisson Permanent SupportProject Overview – Platform Status

West Leg

• Innovative low cost design

• Topsides supported by three unbraced legs (denoted North, South and West)

• Main oil storage tank forms gravity base structure for the platform

• Support structure for the well caisson (Sponson) forms part of the overall gravity base structure

North Leg

South LegMain

Storage Tank

Sponson and Caisson

Page 6: Siri Caisson Permanent Support - A Unique Challenge · Siri Caisson Permanent Support - A Unique Challenge 11th February 2015 Alan Cassie, Subsea 7 Project Manager

6Page 9-Feb-15

Siri Caisson Permanent SupportProject Overview Temporary Solution - Jacking Beam

Beam interfaces with lip of caisson underneath sponson

• A temporary support was required ASAP

• Jacking beam installed under Sponson

• Installed and jacked-up during winter 2009/10

• 4 x 300 Te jacks take load of caisson

Page 7: Siri Caisson Permanent Support - A Unique Challenge · Siri Caisson Permanent Support - A Unique Challenge 11th February 2015 Alan Cassie, Subsea 7 Project Manager

7Page 9-Feb-15

• Following installation of the Jacking System,

Subsea 7 supported concept selection and FEED

engineering for a permanent solution

• Key considerations:– Reduce platform natural sway period to circa 3 seconds, to

reduce dynamic response/loading

– Remove/reduce environmental loading on the caisson

– Minimise production downtime

– Design life of 12 years

– Minimise additional weight.

• On concept selection Subsea 7 were then appointed

as the EPIC contractor and had full responsibility for

the design, fabrication and installation of a

permanent support for the Siri platform and caisson.

Siri Caisson Permanent SupportDesign Concept Selection

Page 8: Siri Caisson Permanent Support - A Unique Challenge · Siri Caisson Permanent Support - A Unique Challenge 11th February 2015 Alan Cassie, Subsea 7 Project Manager

8Page 9-Feb-15

• Clamps– Nominal weights 150 tonne– Split half shell with castellation– Height 6.4 m– 56 M90 bolts per clamp

• Cable Stays– 169 Cohestrand– End anchorage c/w bearing plate– Cross-overs– Monitoring system

• Platform Response– Reduce platform period from 6.5 sec

to 3 sec – with associated reduction in platform motion

• Design Basis– Design Life 13 years, with DFF of 10 – Design Code ISO 199002

Siri Caisson Permanent SupportProject Overview - Design Concept / Specification

Page 9: Siri Caisson Permanent Support - A Unique Challenge · Siri Caisson Permanent Support - A Unique Challenge 11th February 2015 Alan Cassie, Subsea 7 Project Manager

9Page 9-Feb-15

• Design • Clamp Fabrication• Cable Stay Fabrication• Installation

Project Challenges

Page 10: Siri Caisson Permanent Support - A Unique Challenge · Siri Caisson Permanent Support - A Unique Challenge 11th February 2015 Alan Cassie, Subsea 7 Project Manager

10Page 9-Feb-15

Siri Permanent Caisson SupportDesign Context• Fast track design and fabrication

– weight and dimensional growth of clamps and cables

– difficult to finalise installation procedures with design not complete

• Cable stay technology unproven in subsea environment

– programme of component testing performed

• Clamp and cable design feed-in to overall platform integrity analysis

• Introduction of design changes

– water tight duct

– crossover requirement

• DNV verification

– verification of design and fabrication activities in parallel

– lack of appropriate codes and standards for some elements

Page 11: Siri Caisson Permanent Support - A Unique Challenge · Siri Caisson Permanent Support - A Unique Challenge 11th February 2015 Alan Cassie, Subsea 7 Project Manager

11Page 9-Feb-15

Siri Permanent Caisson SupportDesign and Fabrication

• Design considerations– code based requirements for ALS, FLS and ULS

– missing cable, ship impact, VIV, natural frequency

– integrity of platform during installation; additional mass added before platform stabilised

– bearing plates unique to each clamp/cable, to counteract tolerances achieved during clamp fabrication

– cathodic protection design

– cable tensioning sequence - applying tension to one cable changes the tension in all cables

– crossover wear

– demanding and time consuming analysis effort

Page 12: Siri Caisson Permanent Support - A Unique Challenge · Siri Caisson Permanent Support - A Unique Challenge 11th February 2015 Alan Cassie, Subsea 7 Project Manager

12Page 9-Feb-15

Siri Permanent Caisson SupportDesign for Installation• Installation considerations

– weight growth as design evolved

– north leg riser in close proximity to north upper clamp

– ensure castellation contact between clamp halves

– design requirement to install upper clamps to with 0.15o of design heading

– unknown handling characteristics of cable

– eccentric loading of anchorage nut

– polarising shim settings

– alignment control on tensioning system

Page 13: Siri Caisson Permanent Support - A Unique Challenge · Siri Caisson Permanent Support - A Unique Challenge 11th February 2015 Alan Cassie, Subsea 7 Project Manager

13Page 9-Feb-15

Siri Permanent Caisson SupportClamp Fabrication – Welding Engineering

Page 14: Siri Caisson Permanent Support - A Unique Challenge · Siri Caisson Permanent Support - A Unique Challenge 11th February 2015 Alan Cassie, Subsea 7 Project Manager

14Page 9-Feb-15

Siri Permanent Caisson SupportCable Stay Fabrication and Assembly• The 169 strand stay was a catalogue product,

but had never been manufactured

• The application in a subsea context required significant changes to the design of the standard cable stay including:

– Bend stiffeners

– Telescopic joints

– Fexjoints Large and Small

– Anchorage sealing

– Crossover

– Filler

• All of the above required to be designed and tested as part of the verification process.

Crossover

Upper Anchorage

Lower Anchorage

Page 15: Siri Caisson Permanent Support - A Unique Challenge · Siri Caisson Permanent Support - A Unique Challenge 11th February 2015 Alan Cassie, Subsea 7 Project Manager

15Page 9-Feb-15

Siri Permanent Caisson SupportCable Stay Fabrication and Assembly• Individual components manufactured in

France, Italy, Norway and UK

• Cable stays assembled in Scotland - suitable covered facilities with quayside access, proximity to Aberdeen for ease of project over site.

Page 16: Siri Caisson Permanent Support - A Unique Challenge · Siri Caisson Permanent Support - A Unique Challenge 11th February 2015 Alan Cassie, Subsea 7 Project Manager

16Page 9-Feb-15

• Installation Tolerances• Cable Tensioning• Platform Motion• Platform Operation

Project Outcomes

Page 17: Siri Caisson Permanent Support - A Unique Challenge · Siri Caisson Permanent Support - A Unique Challenge 11th February 2015 Alan Cassie, Subsea 7 Project Manager

17Page 9-Feb-15

• Upper Clamps installed within tolerance • South 0.02 degrees• West 0.15 degrees • North 0.47 degrees

• Cable Stays installed and tensioned to 1250 tonnes, without damage to the thread or the water tight duct

• Platform natural period reduced from 6.5 seconds to circa 3 seconds, with corresponding reduction in platform motion

Siri Caisson Permanent SupportProject Outcomes

Before Cables

With Cables installed

Page 18: Siri Caisson Permanent Support - A Unique Challenge · Siri Caisson Permanent Support - A Unique Challenge 11th February 2015 Alan Cassie, Subsea 7 Project Manager

18Page 9-Feb-15

Lessons Learnt

Page 19: Siri Caisson Permanent Support - A Unique Challenge · Siri Caisson Permanent Support - A Unique Challenge 11th February 2015 Alan Cassie, Subsea 7 Project Manager

19Page 9-Feb-15

Lessons Learnt

• Don’t underestimate the complexity and challenge associated with delivery of an innovative solution

• Don’t under estimate the ability of good engineers to overcome these challenges

• Sound design, robust procedures and comprehensive testing were key in achieving success.