FLEXI WCDMA BTS SITE FOLDER
1
FLEXI WCDMA BTS SITE FOLDER
REV 02
BHARTI AFRICA PROJECT (KENYA)
SITE NAME / SITE NUMBER
CURRENT CONFIGURATION
SITE TYPE
DATE
Acceptance Certificate
1 Installation Checks
2 Commissioning Checks
3 Integration Checks
Revision Date: 22-06-2011
-
FLEXI WCDMA BTS SITE FOLDER
2
Revision History
Date Rev. Originator Summary of Change
31-01-2011 01 SHUBHAM PRASAD Initial development 22-06-2011 02 SHUBHAM PRASAD Removed un-necessary pages
Document Approval
Rev. Role Name Signature Date
01 TI Manager, KENYA Kapadopoulos Vasileios 22-06-2011 TI Manager, KENYA Kenneth Owuor 26-Nov-2014
The information in this document is subject to change without notice and describes only the product defined in the introduction of this documentation. This document is intended for the use of Nokia Siemens Networks customers only for the purposes of the agreement under which the document is submitted, and no part of it may be used, reproduced, modified, or transmitted in any form or means without the prior written permission of Nokia Siemens Networks. The document has been prepared to be used by professional and properly trained personnel, and the customer assumes full responsibility when using it. Nokia Siemens Networks welcomes customer comments as part of the process of continuous development and improvement of the documentation.
The information or statements given in this document concerning the suitability, capacity, or performance of the mentioned hardware or software products are given as is and all liability arising in connection with such hardware or software products shall be defined conclusively in a separate agreement between Nokia Siemens Networks and the customer. However, Nokia Siemens Networks has made all reasonable efforts to ensure that the instructions contained in the document are adequate and free of material errors and omissions. Nokia Siemens Networks will, if deemed necessary by Nokia Siemens Networks, explain issues which may not be covered by the document.
Nokia Siemens Networks will correct errors in the document as soon as possible. IN NO EVENT WILL NOKIA SIEMENS NETWORKS BE LIABLE FOR ERRORS IN THIS DOCUMENT OR FOR ANY DAMAGES, INCLUDING BUT NOT LIMITED TO SPECIAL, DIRECT, INDIRECT, INCIDENTAL OR CONSEQUENTIAL OR ANY MONETARY LOSSES, SUCH AS BUT NOT LIMITED TO LOSS OF PROFIT, REVENUE, BUSINESS INTERRUPTION, BUSINESS OPPORTUNITY OR DATA THAT MAY ARISE FROM THE USE OF THIS DOCUMENT OR THE INFORMATION IN IT
This document and the product it describes are considered protected by copyrights and other intellectual property rights according to the applicable laws.
Wave logo is a trademark of Nokia Siemens Networks Oy. Nokia is a registered trademark of Nokia Corporation. Siemens is a registered trademark of Siemens AG.
Other product names mentioned in this document may be trademarks of their respective owners, and they are mentioned for identification purposes only.
Copyright Nokia Siemens Networks 2011. All rights reserved.
-
FLEXI WCDMA BTS SITE FOLDER
3
1. Site Acceptance Certificate
Customer Name: ______________________________________ Date: _______________________
Site Location/Number: __________________________________________________________________
Project Description: ____________________________________________________________________
Nokia Siemens PO #s: __________________________________________________________________
Customer PO #s: _______________________________________________________________________
The above referenced site project (i) has passed all applicable Acceptance Tests, (ii) has been installed properly, subject to resolution of outstanding SDR items, and (iii) is ready to be placed in service.
Any discrepancies are specified on the following SDR or attachment (s).
Installation SDR Dated
No Discrepancies
Quantity of SDR Items
Not Applicable
Site Test Data Forms Dated
No Discrepancies
Quantity of SDR Items
Not Applicable
Customer Representative Nokia Siemens Networks Representative
Signature: ________________________________ Signature: _________________________________
Printed Name: _____________________________ Printed Name: ______________________________
Title: _____________________________________ Title: _____________________________________
Date: ____________________________________ Date: _____________________________________
Distribution: Customer Accounting Project Manager
-
FLEXI WCDMA BTS SITE FOLDER
4
Outstanding Tasks
Item Description of Outstanding Work Raised by: Completed by:
Sig. Sig. 1 Name Name
Date Date
Sig. Sig. 2 Name Name
Date Date
Sig. Sig. 3 Name Name
Date Date
Sig. Sig. 4 Name Name
Date Date
Sig. Sig. 5 Name Name
Date Date
Sig. Sig. 6 Name Name
Date Date
Sig. Sig. 7 Name Name
Date Date
Sig. Sig. 8 Name Name
Date Date
Sig. Sig. 9 Name Name
Date Date
Sig. Sig. 10 Name Name
Date Date
Sig. Sig. 11 Name Name
Date Date
Sig. Sig. 12 Name Name
Date Date
Sig. Sig. 13 Name Name
Date Date
Sig. Sig. 14 Name Name
Date Date
Sig. Sig. 15 Name Name
Date Date
-
FLEXI WCDMA BTS SITE FOLDER
5
1. FLEXI WCDMA BTS INSTALLATION CHECKLIST
The Installation Team is to carry out the Flexi WCDMA BTS Installation in accordance with the Flexi WCDMA BTS User Manual. The Installation Team Supervisor is responsible for:
Ensuring that each team member has the correct tools, installation materials, and User Manual. Checking the delivery against the packing list and placing it in Section 5 of the Site Folder. Completing this checklist, including the signature and date. Completing the necessary Site Deficiency Reports. Completing the necessary Fault Reports. Informing the Installation Manager/Site Manager of work progress, including any problems as they arise. Completing the Certificate of Completion and placing it in Section 1.9 of the Site Folder.
-
FLEXI WCDMA BTS SITE FOLDER
6
1.1 Site Ready Checklist
INSTALLATION PHASE & RELATED DOCUMENTS SDR # COMPLETED
Access/usage permission to building or area is arranged (e.g., keys, security clearance). OK
Lightning protection for antenna system checked. OK Cable ladder/support structure from antenna to entry point to cabinets checked. OK
BTS cabinet position and layout in accordance with Nokia Siemens site-specific documents. OK
Cable ladder position and cable access to top proper side of cabinets for antenna feeder cables, power, and PCM cables checked. OK
Flexi WCDMA BTS equipment grounding busbar or ground cables installed and connected to the main site grounding system. OK
AC power distribution board with clearly labeled fuses/circuit breakers for each cabinet AC checked. OK
Availability of AC mains supply checked. OK Alarm systems installed with cables labeled and run to the Alarm Terminal Block location. OK
1.2 Antenna & Feeder System Installation
INSTALLATION PHASE & RELATED DOCUMENTS SDR # COMPLETED
Deliveries are complete & checked, shortcomings recorded. OK Equipment is not damaged. OK Antenna layout checked for differences to the drawings and recorded. OK Antenna steelworks grounding checked. OK
Feeder cable routes checked. OK
Feeder wall-throughs checked. NA Feeder cable trays checked. OK Antenna mounting height checked according to the final site configuration. OK Antennas mounted according to site-specific documents. OK Lobe direction checked according to the final site configuration. OK Mechanical tilt angle checked according to the final site configuration. OK Electrical tilt angle checked according to the final site configuration. OK Antenna mounting clamps checked, all screws tightened. OK Connectors mounted according to the mounting instruction of the connector manufacturer. OK
-
FLEXI WCDMA BTS SITE FOLDER
7
INSTALLATION PHASE & RELATED DOCUMENTS SDR # COMPLETED
Feeder cables mounted according to site-specific documents. NA Feeders grounded and groundings weatherproofed according to grounding instructions. NA
Feeder cables secured on their base. NA Feeder cables marked correctly. NA Jumper connections checked and tightened in the both end of the jumper. OK All external connections checked and sealed. OK BTS jumper connections checked and tightened in the both end of the jumper. OK Jumper cables marked correctly. OK
1.2.1 Antenna / Feeder System Information
SECTOR 1 SECTOR 2 SECTOR 3
Antenna TX/RX RXD TX/RX RXD TX/RX RXD
Line Marked
Tilt Angle
Lobe Direction
Feeder Length
Grounding Kits Used (pcs)
-
FLEXI WCDMA BTS SITE FOLDER
8
1.3 Antenna & Feeder System Test
1.3.1 Antenna VSWR Measurement
Measured VSWR
Sector 1/A Sector 1/B Sector 2/A Sector 2/B Sector 3/A Sector 3/B
NA NA NA NA NA NA
1.3.2 Cable Loss Measurement
Cable loss measurement
Sector 1/A Sector 1/B Sector 2/A Sector 2/B Sector 3/A Sector 3/B
NA NA NA NA NA NA
1.4 Module & Flexi WCDMA BTS Plug-In Unit Inventory
INSTALLATION PHASE Initials & SDR #
Flexi WCDMA BTS plug-in units scanned to file, soft and hard copy attached.
1.5 Site Install Preparation Refer to Nokia Siemens Networks Flexi WCDMA Base Station User Manual.
INSTALLATION PHASE Initials & SDR #
Site safety is acceptable for work to commence. Site survey is available and complete. Site layout according to drawing. Access permit from owner or authorities available. Grounding busbar for Flexi WCDMA BTS is available. Emplacement for BTS is ready and conforms to Nokia Siemens standards. AC power distribution panel correctly installed and connected to AC mains. Power supply and interface cables ready and conforms to Nokia Siemens standards. Transmission equipment and cables ready and conform to Nokia Siemens standards
Feeders and antenna ready and conform to Nokia Siemens standards BTS delivery is complete and conform to Nokia Siemens standards
-
FLEXI WCDMA BTS SITE FOLDER
9
1.5.1 Delivery
INSTALLATION PHASE Initials & SDR #
Delivery complete and undamaged. Delivery conforms to site-specific requirements. Delivery conforms to the packing list. Details of any damages/shortages entered into SSD. Packing list placed in SSD.
1.6 Cabinet Installation (if applicable) INSTALLATION PHASE Initials & SDR #
I-Beams / Raised platform installed. Back panel and rear cover installed. NA Cover plate removed. Fixing hole positions on floor marked and drilled. Shims or washers attached to the anchor bolts. BTS installed and tightened to recommended torque settings. BTS level after installation. Door panel installed.
1.7 Cabling Modules in Cabinet Installation
INSTALLATION PHASE Initials & SDR # Grounding cables connected from the BTS to the equipment ground bar. BTS Grounding measured (
-
FLEXI WCDMA BTS SITE FOLDER
10
INSTALLATION PHASE Initials & SDR # Cables are routed correctly. Empty slots are covered with dummy panels (in FCOA installations only). All boots and caps are properly connected and IP-sealed. Only Nokia provided cables are used. Cabinet roof is installed if applicable (in FCOA installations only
1.7.1 Internal Cabling
Flexi WCDMA System Module Front Panel Connector & Labels
-
FLEXI WCDMA BTS SITE FOLDER
11
Flexi WCDMA RF Module Front Panel Connectors
1.8 Finish Installation
INSTALLATION PHASE Initials & SDR #
Doors installed.
All cables related to BTS are properly labeled.
Main Power supply is switched off.
Power supply units are switched off.
All connectors are tightened with the correct torque recommendation.
Unit install completed.
All spare dummy panels and unused pieces packaged for return to Nokia Siemens.
Packing materials removed from the site.
Rubbish removed and site cleaned and tidy.
-
FLEXI WCDMA BTS SITE FOLDER
12
1.9 Flexi WCDMA Installation Certificate of Completion PO NO:
Customer Name:
Site Name:
Site NO:
Site Address:
Equipment Type:
Configuration ./ Site Type:
Equipment SW Version :
Shipment ID:
The equipment on this site has been installed in accordance with:
DOCUMENT TITLE Nokia Flexi WCDMA Base Station Rel. Flexi WBTS 4.0, (471449A) Document # Issue
STAGE: (Where Applicable) Complete/OK Comments / Deficiency / Outstanding Tasks Equipment / Area/ Customer-specific Instructions followed
Site Installation type & specific instructions followed
Site Prep Complete (T1, Power, Ground, Antenna System)
Transmission check complete & confirmed by RIC
Outstanding Task or Deficiencies:
-
FLEXI WCDMA BTS SITE FOLDER
13
INSTALLATION STAGE COMPLETE / CHECKED (INITIALS) Site Ready Checklist
Delivery is complete and undamaged. Correct P/O and Packing List
Minimum Clearances are met.
Adaptor mechanics are installed. (For Cabinets, walls, H-Frame & pole mounts) Plinth is installed according to the instructions.
Plinth is grounded.
Anti-static wrist strap is connected and used when handling the modules
Modules are installed according to the instructions.
Modules are grounded to the plinth.
Module front and back covers are installed.
Power supply cables are installed per specifications.
Cable entries are installed.
Internal power cables are connected.
Transmission cables are connected.
Optical fiber cables are connected.
Cables between modules on the same plinth are routed via internal cable entries.
BTS external cables or cables b/t modules on different plinths are routed via external cable entries.
IP Connector seals are firmly in place.
Unused connectors are covered with IP seals.
BTS can be started and all LEDs are lit - part of Commissioning activity!
Antenna cables are connected according to the configuration.
Antenna cables are tightened to the correct torque - 25Nm - as per specifications.
Antenna & Feeder System Installation Complete
Antenna & Feeder System Test
Module & Flexi WCDMA BTS Plug-In Unit Inventory
Site Install Preparation
Cabinet Installation (if applicable) Cabling Modules in Cabinet Installation per user Manual
Finish Installation: site is clean and Installation is complete.
-
FLEXI WCDMA BTS SITE FOLDER
14
Nokia Siemens Networks hereby states that the whole of supplies detailed above have been inspected, tested and unless otherwise stated conform to the specified requirements in the contract or order identified above.
Nokia Siemens Site Representative (print name): Date:
PTID No:
Company:
Nokia Siemens Site Representative (signature): Date:
PTID No:
Company
Customer Representative (print name): Date:
Customer Site Representative (signature):
-
FLEXI WCDMA BTS SITE FOLDER
15
2. COMMISSIONING CHECKLIST
The Commissioning Engineer is to carry out all commissioning tests in accordance with the Flexi WCDMA BTS Commissioning Procedure, using the Flexi WCDMA BTS User Manual and other approved reference material. Customer-specific parameters are to be used where applicable. A signed Certificate of Completion for the installation work must be included in Section 1.9 of the Site Folder, certifying that the installation work has been completed to the required standard. The Commissioning Engineer is responsible for:
Checking the quality of the installation. Correcting any installation problems/faults or deficiencies. Familiarization with current Technical Notes.
Commissioning the Flexi WCDMA BTS system in preparation for integration. Completing this checklist, including signature and date. Completing the necessary Site Deficiency Reports. Completing the necessary Fault Reports. Informing the Site Manager of work progress, including any problems as they arise. Completing the Certificate of Completion and placing it in Section 0 of the Site Folder.
-
FLEXI WCDMA BTS SITE FOLDER
16
2.1 Commissioning Overview Site Information
2.1.1 General Information
ITEM VALUE
BTS Name BTS ID BTS IP Address BTS Port # BTS Q1 Address BTS Polling Timeout Recommended Laptop settings (customer) IP Subnet Mask Default Gateway
2.1.2 Software Versions
ITEM VALUE
Module AXC SW Version BTS SW Version
2.1.3 AXC Settings
ITEM VALUE
AXC Configuration soft copy file used and filename recorded
AXC FILENAME AXC Configuration parameters checked and verified
2.1.4 WCDMA Commissioning
ITEM VALUE
WCDMA Commissioning file is available WCDMA Commissioning filename WCDMA Commissioning Events report filed
-
FLEXI WCDMA BTS SITE FOLDER
17
2.1.5 FSMB System Module Settings
ITEM VALUE
Module SW File Module Configuration Module Cross-Connect
2.2 FSMD Module Configuration Views
ITEM VALUE
RF Connection Configuration FSMB Configuration E1/T1 Unit Configuration
2.3 Flexi WCDMA BTS Commissioning Test
ITEM VALUE
Flexi WCDMA BTS Comm. SCF file Flexi WCDMA BTS Comm. Report Flexi WCDMA BTS Hardware report Flexi WCDMA BTS Software report Flexi WCDMA BTS Alarm Log Flexi WCDMA BTS Loop Test report
2.4 Transmitter Measurement
2.4.1 Transmitter Output Power Level
Enter Power Level in W (measured from WAFx Main antenna connector).
Power Level (db)(W)
WTR 1 WTR 2 WTR 3 WTR 4 WTR 5 WTR 6
2.5 Equipment Measurement
MANUFACTURER MODEL SERIAL # LAST CALIBRATION DATE
-
FLEXI WCDMA BTS SITE FOLDER
18
2.6 Finishing
COMMISSIONING PHASE SDR # CHECKED BY
Fill in the Commissioning Certificate of Completion.
Notes on Commissioning
-
FLEXI WCDMA BTS SITE FOLDER
19
Commissioning Certificate of Completion PO NO:
Customer Name:
Site Name:
Site NO:
Site Address:
Equipment Type:
Configuration ./ Site Type:
Equipment SW Version :
Shipment ID:
The equipment on this site has been commissioned in accordance with:
DOCUMENT TITLE Nokia Flexi WCDMA Base Station Rel. Flexi WBTS 4.0, (471449A) Document # Issue
STAGE: (Where Applicable) Complete/OK Comments / Deficiency / Outstanding Tasks Equipment / Area/ Customer-specific Instructions followed
Site Installation type & specific instructions followed
Site Prep Complete (T1, Power, Ground, Antenna System)
Transmission check complete & confirmed by RIC
Site left clean & tidy
Outstanding Task or Deficiencies:
-
FLEXI WCDMA BTS SITE FOLDER
20
COMMISSIONING STAGE Basic Checks Pass/Fail
Transmission Check Complete
BTS Grounded Correctly
AC/DC Input Cabled Correctly
Modules cabled correctly
Visual inspection of Modules, Cables, Connectors
Correct Torque Values set on all RF Connectors Proper Installation material used (outdoor rated cabling, power & Ground) Per SE specifications
NSN approved RF Jumper per PL specifications
SW Levels Version BTS SW Release
RNC Adapter SW Release
Java Engine
Site Manager
Site Configuration File
Software update Needed?
External Alarms if applicable (see alarms tab) Pass / Fail External Alarms Configured
External Alarms Tested
File Management Complete Commissioning report reviewed and Uploaded
Bar coding files Uploaded
Site photographs taken and Uploaded
Planned Commissioning Default method Complete View Parameters
Save Parameters
Parameters sent to BTS
-
FLEXI WCDMA BTS SITE FOLDER
21
COMMISSIONING STAGE Manual Commissioning Under direction of RIC Complete
IP Settings
Interface Settings
Transmission Module Settings
Local Call Resources
WCDMA Carrier & Scrambling code settings
Feeder Loss
Parameters saved
BTS Testing Complete BTS Test State Site Tests
BTS Loop Test Performed
BTS BER Test Performed
BTS Restart Parameters consistent!
Mains Fail! 20W / 40W
Finishing Checked (Initials) Comments Site Information
System Module Configuration Views
Flexi WCDMA BTS Commissioning Test
Transmitter Measurement
Equipment Measurement
Finish Commissioning
Nokia Siemens Networks hereby states that the whole of supplies detailed above have been inspected, tested and unless otherwise stated conform to the specified requirements in the contract or order identified above.
Nokia Siemens Site Representative (print name): Date:
PTID No:
Company:
Nokia Siemens Site Representative (signature): Date:
PTID No:
Company
RIC Engineer Date:
Customer Site Representative (signature):
-
FLEXI WCDMA BTS SITE FOLDER
22
3. INTEGRATION CHECKLIST
The Flexi WCDMA BTS Integration Engineer is to carry out all integration tests in accordance with the Flexi WCDMA BTS User Manual and other approved Integration Procedure. The Integration Engineer is to ensure that a signed Certificate of Completion is produced, certifying that the Flexi WCDMA BTS system has been commissioned and is ready for Integration. The Integration Engineer is responsible for:
Clearing any Installation/Commissioning problems, faults, or deficiencies. Familiarization with current Technical Notes.
Checking that Site Folder documentation is complete. Completing this checklist including signature and date. Completing the necessary Site Deficiency Reports. Completing the necessary Fault Reports. Informing the Site Manager of work progress, including any problems as they arise. Completing the Certificate of Completion and placing it in Section 0 of the Site Folder Completing the Site Acceptance Certificate and placing it in Section 1 of the Site Folder.
-
FLEXI WCDMA BTS SITE FOLDER
23
3.1 Site Integration Test
3.1.1 Integration Tests
ITEM VALUE
Parameters set up SW download done remotely All Alarms tested and cleared Test calls done and recorded to table 1 below Verification of remote access for each Flexi WCDMA Module at the site
All Individual Modules SW and HW version recorded in table 2 below
SECTORS CALL TYPES
MOC/MTC Speech CALL SETUP
HANDOVER TO S1
HANDOVER TO S2
HANDOVER TO S3
Sector 1
Sector 2
Sector 3
Speech Test calls
WCDMA FLEXI TYPE (FIU, LMU, ETC.) SW VERSION HW VERSION
SW and HW version check
-
FLEXI WCDMA BTS SITE FOLDER
24
3.2 Finish Integration Was the Customer present for Integration Activities? Yes No
If yes, Customer Representative Name:
Notes on Integration, Outstanding SDRs:
Completed By: Signature: Date:
-
FLEXI WCDMA BTS SITE FOLDER
25
Integration Certificate of Completion PO NO:
Customer Name:
Site Name:
Site NO:
Site Address:
Equipment Type:
Configuration ./ Site Type:
Equipment SW Version :
Shipment ID:
The equipment on this site has been Call Tested & Integrated in accordance with:
DOCUMENT TITLE Nokia Flexi WCDMA Base Station Rel. Flexi WBTS 4.0, (471449A) Document # Issue
STAGE: (Where Applicable) Complete/OK Comments / Deficiency / Outstanding Tasks Equipment / Area/ Customer-specific Instructions followed
Site Installation type & specific instructions followed
Site Prep Complete (T1, Power, Ground, Antenna System)
Transmission check complete & confirmed by RIC
Site left clean & tidy
Outstanding Task or Deficiencies:
-
FLEXI WCDMA BTS SITE FOLDER
26
INTEGRATION STAGE Basic Checks Pass/Fail
Transmission Check Complete
BTS Grounded Correctly
AC/DC Input Cabled Correctly
Modules cabled correctly
Visual inspection of Modules, Cables, Connectors
Correct Torque Values set on all RF Connectors Proper Installation material used (outdoor rated cabling, power & Ground) Per SE specifications
NSN approved RF Jumper per PL specifications
SW Levels Version BTS SW Release
RNC Adapter SW Release
Java Engine
Site Manager
Site Configuration File
Software update needed?
External Alarms if applicable (see alarms tab) Pass/Fail External Alarms Configured
External Alarms Tested
File Management Complete Commissioning report reviewed and Uploaded
Bar coding files Checked
Site photographs Checked
BTS Testing Complete BTS Test State Site Tests
BTS Loop Test Performed
BTS BER Test Performed
BTS Restart Parameters consistent!
Mains Fail! 20W / 40W
Integration Complete BTS Integrated to the Packet Core Network
BTS Integrated to the OSS
Site Integrated with no alarms
-
FLEXI WCDMA BTS SITE FOLDER
27
CALL TESTING STAGE LCR ID Scrambling Code ARFCN
MNC MCC RAC
Voice Call LCR ID Success out of 5 RAC Scrambling Code
Mobile to Land Call Land to Mobile Call Calling Number Called Number Called Number Calling Number
FTP File Data Transfer (time) LCR ID Time to Download (50Mb) Time to Upload (2Mb)
INTRA-BTS Handovers From / To LCR ID Correct Handover A _ B
B _ C
C _ A
A C
C B
B _ A
Emergency Call (A-gps, CI+RTT when available) LCR ID
-
FLEXI WCDMA BTS SITE FOLDER
28
INTEGRATION STAGE CHECKED (INITIALS) COMMENTS
Site Information
System Module Configuration Views
Flexi WCDMA BTS Commissioning Test
Flexi WCDMA BTS Integration Test
Transmitter Measurement
Equipment Measurement
Finish Integration
Nokia Siemens Networks hereby states that the whole of supplies detailed above have been inspected, tested and unless otherwise stated conform to the specified requirements in the contract or order identified above.
Nokia Siemens Site Representative (print name): Date:
PTID No:
Company:
Nokia Siemens Site Representative (signature): Date:
PTID No:
Company
RIC Engineer Date:
Customer Site Representative (signature):