site selection, invesigations

Upload: ashutoshvashishtha

Post on 03-Apr-2018

227 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 Site Selection, Invesigations

    1/50

    Presentation

    On

    Site Selection and Investigations for SHP

    Dr. S.K.Singal

    Alternate Hydro Energy Centre

    IIT Roorkee

  • 7/28/2019 Site Selection, Invesigations

    2/50

    TYPE OF SCHEMES

    RUN OF RIVER

    No storage.

    The output is subject to instantaneous flow.

    Reliability of discharge and geological conditions should be ensured.

    CANAL BASED

    Utilizes the fall and flow in the canals.

    May be planned in main canal or in bye-pass canal.

    Nearby drops should be clubbed in existing canals.

    In canals under planning concentrated drops should be considered.

    DAM BASED

    Dam toe schemes are most common in India.

    Water stored during monsoon is utilized for power generation.

    PUMP STORAGE

  • 7/28/2019 Site Selection, Invesigations

    3/50

  • 7/28/2019 Site Selection, Invesigations

    4/50

  • 7/28/2019 Site Selection, Invesigations

    5/50

  • 7/28/2019 Site Selection, Invesigations

    6/50

    Upper reservoir

    Lower reservoir

    Pumped storage

    power plant

    Pumping

    Generating

    Pumped Storage Scheme Configuration

  • 7/28/2019 Site Selection, Invesigations

    7/50Pum ed stora e ower s stem su or

  • 7/28/2019 Site Selection, Invesigations

    8/50

    Diversion and Intake structure

    Desilting chamber

    Water conductor system Forebay/balancing reservoir

    Penstock

    Surge tank

    Power house

    Turbine, generator and controls

    Tail Race

    Switchyard

    COMPONENTS OF SMALL HYDROPOWER SCHEME

  • 7/28/2019 Site Selection, Invesigations

    9/50

    INVESTIGATIONS

    Investigation Stages

    1. Reconnaissance level (preliminary/PFR)

    2. Feasibility/Detailed level (pre-investment/DPR)

    3. Execution

  • 7/28/2019 Site Selection, Invesigations

    10/50

    RECONNAISSANCE LEVEL

    At this level of investigations following should be

    determined

    Hydrological survey

    Topographical survey

    Geological survey

    Power load demand assessment

    Socio- economic survey

    Head and discharge.

    Technical feasibility of the project.

    Identification of critical issues and their possible

    solutions.

  • 7/28/2019 Site Selection, Invesigations

    11/50

    FEASIBILITY/DETAILED PROJECT

    REPORT-INVESTIGATIONS

    Hydrological survey

    Topographical survey

    Geological surveyPower load demand assessment

    Socio- economic survey

    Meteorological survey

    Environmental survey

    Survey for construction material

    Power Evacuation Line Survey

  • 7/28/2019 Site Selection, Invesigations

    12/50

    DURING AND FOR EXECUTION

    STAGE Sub soil exploration/geo-technical investigation for knowing

    soil parameters for structural designs

    Setting of the pillars with levels for controls of levels for

    excavation and structure

    Testing of construction material

  • 7/28/2019 Site Selection, Invesigations

    13/50

    TOPOGRAPHICAL SURVEY

  • 7/28/2019 Site Selection, Invesigations

    14/50

    DETERMINATION OF HEAD

    By altimeter

    By GPS

    By Dumpy level

    By total station

  • 7/28/2019 Site Selection, Invesigations

    15/50

    Distances

    Angles

    Directions

    Elevations

    Coordinates

    TOPOGRAPHICAL

    SURVEYS

  • 7/28/2019 Site Selection, Invesigations

    16/50

    RUN-OF-RIVER: River with rapids and

    drops

  • 7/28/2019 Site Selection, Invesigations

    17/50

    RUN-OF-RIVER: River with mild slope

  • 7/28/2019 Site Selection, Invesigations

    18/50

    LAYOUT PLAN OF RUN-OF-RIVER

    SITE

  • 7/28/2019 Site Selection, Invesigations

    19/50

    L-SECTION OF RIVER

  • 7/28/2019 Site Selection, Invesigations

    20/50

    DETERMINATION OF HEAD

    By altimetervery approximate

    By GPS approximate

    By Engineering level reasonable

    Theodolite and Total Station accurate

    Map very rough

    Water filled tube crude but accurate

    O O OG S O A

  • 7/28/2019 Site Selection, Invesigations

    21/50

    METHODOLOGIES FOR HEAD

    ESTIMATION1. USING DETAILED MAPS

    Detailed topographic maps are useful for locating potential sites andfor obtaining a rough estimate of head levels.

  • 7/28/2019 Site Selection, Invesigations

    22/50

    2. WATER-FILLED TUBE AND ROD

    METHOD

    This method is suitable for low-head sites. It is reliable, reasonably

    accurate and inexpensive.

  • 7/28/2019 Site Selection, Invesigations

    23/50

    ENGINEERS LEVEL

    A telescope mounted so that it can be levelled tomake the axis horizontal only

  • 7/28/2019 Site Selection, Invesigations

    24/50

    3. VERNIER THEODOLITE

    TOTAL STATION

  • 7/28/2019 Site Selection, Invesigations

    25/50

    TOTAL STATION

    Main Body

  • 7/28/2019 Site Selection, Invesigations

    26/50

    CONTOUR MAP OF PROJECT SITE

  • 7/28/2019 Site Selection, Invesigations

    27/50

    TOTAL POINTS COLLECTED

  • 7/28/2019 Site Selection, Invesigations

    28/50

    Global Position System

    HANDHELD

    MOUNTED

  • 7/28/2019 Site Selection, Invesigations

    29/50

    FLOW MEASUREMENT

    Velocity-area method

    Weir method

  • 7/28/2019 Site Selection, Invesigations

    30/50

    RECTANGULAR NOTCH

    Q = 1.8 (L-0.2H) H3/2

    Where,Q is discharge in cumecs

    L is the length of the rectangular notch.

    H is the height of water in notch

  • 7/28/2019 Site Selection, Invesigations

    31/50

    V - NOTCH

    Q = 1.417 H5/2

    Where,Q is discharge in cumecs

    H is the height of water meters

  • 7/28/2019 Site Selection, Invesigations

    32/50

    AREA VELOCITY METHOD

  • 7/28/2019 Site Selection, Invesigations

    33/50

    FLOW MEASUREMENT OF

    TURBULENT STREAM

    InstrumentFlow Stream

    RangeUpto 4000 l/s

    Accuracy1% PrincipleConductivity of the water

    Q = M/(K x A) cumec

    M = Mass of salt (Kg)K = Conversion factor (Kg/m3/ohm-1)

    A = Area under curve (ohm-1S)

  • 7/28/2019 Site Selection, Invesigations

    34/50

    Time (Seconds)

    Cond

    uctivity

    (10ohm

    )

    -6

    -1

    Area underCurve

    Back ground Conductivity

    SUITABILITY OF THE

  • 7/28/2019 Site Selection, Invesigations

    35/50

    SUITABILITY OF THE

    INSTRUMENT

    SUITABLE TO MEASURE THE FLOW OFTURBULENT STREAM

    MEASURE THE DISCHARGE OF THETURBULENT STREAM ACCURATELY ASCOMPARED TO OTHER METHODS

    NO SITE CONSTRUCTION IS REQUIRED

    SINGLE PERSON OPERTATION

    SELECTION OF DISCHARGE

  • 7/28/2019 Site Selection, Invesigations

    36/50

    SELECTION OF DISCHARGE

    MEASUREMENTSECTION &

    POURING POSITION Discharge measurement section should be

    turbulent with no stagnant pools (water

    velocity less than 0.1 m/s). The measuringposition should be in moving but not fast

    flowing water

    The pouring position should be at least 25 times

    the width of stream at discharge measurement

    section and the flow should be highly turbulent

    for better mixing of salt solution.

  • 7/28/2019 Site Selection, Invesigations

    37/50

    DETERMINATION OF QUANTITY

    OF SALT Measure the Av. Width and Av. Depth of

    the discharge measurement section and

    multiply the two together.

    Select the quantity of salt to use from the

    Table.

  • 7/28/2019 Site Selection, Invesigations

    38/50

    Table

    Width (m) X

    Depth (m)

    Back Ground Conductivity

    0-100 s 100-500 s 500-2000 s< 0.1 250 g 500 g 750 g

    0.1 to 1.0 500 g 750 g 1000 g

    > 1.0 1000 g 1500 g 1500 g

  • 7/28/2019 Site Selection, Invesigations

    39/50

    Procedure for Discharge measurement

    1. Choose a turbulent section for pouring salt solution2. Choose a measuring position. Check that the conductivity probe can be

    submerged in the water without air bubbles being trapped by theprobe

    3. Switch on the Flow stream

    4. Find out background conductivity

    5. Find out salt quantity and add to water in a bucket6. Pour the solution slowly in the stream but within 15 seconds.

    7. Measure conductivity at measuring position

    8. When test is completed get

    Mass of salt

    Elapsed time Background conductivity

    Peak conductivity

    Discharge in l/s.

  • 7/28/2019 Site Selection, Invesigations

    40/50

    L 25 B>

    POURING POSITION

    MEASURING POSITION

    FLOW

  • 7/28/2019 Site Selection, Invesigations

    41/50

    GEOLOGICAL INVESTIGATIONS -

    HYDROPOWER PROJECTS

    STABILITY OF WEIRS

    The foundation mass should be impermeable (non-jointed,

    non-fractured and thoroughly crystalline igneous rocks,

    claystones, massive sandstones and massive limestones) toavoid leakage.

    Narrow river valley is suited most for construction of weir

    Stable hillslopes attribute to the long life and stability of the

    reservoir.

    Sites should be selected carefully so as to be free from

    defects which could result to leakage from reservoirs

    Leakage may threat the safety and stability of the weir/dam.

  • 7/28/2019 Site Selection, Invesigations

    42/50

    GEOLOGICAL STRUCTURES

    Bed: A sedimentary layer whose thickness is more than acentimeter.

    Dip: The maximum angle of inclination of a bed with the

    horizontal.

    Fault: A fracture along which it shows evidence of

    relative movements.

    Fold: Bends or curvature or undulations developed in the

    rocks of the earths crust as a result of stresses to which

    these rocks have been subjected from time to time.

  • 7/28/2019 Site Selection, Invesigations

    43/50

    DEFECTIVE FEATURES

  • 7/28/2019 Site Selection, Invesigations

    44/50

    SITE SELECTION

    INTAKE

    Should be at narrow valley. Bends should be avoided.

    Banks should be stable.

    No land slides.

    Minimum turbulence in flow.

  • 7/28/2019 Site Selection, Invesigations

    45/50

    DIVERSION WEIR AND INTAKE SITE

  • 7/28/2019 Site Selection, Invesigations

    46/50

    DESILTING TANK AND CHANNEL

    Flatter land.

    Free from cross drainages.

    No active slide zone.

    Slopes should be stable.

  • 7/28/2019 Site Selection, Invesigations

    47/50

    FOREBAY AND SPILLWAY

    Flatter land.

    Filling of land should be avoided.

    Slopes should be stable. Natural stream should be nearby for spill water.

  • 7/28/2019 Site Selection, Invesigations

    48/50

    PENSTOCK

    Alignment should be along the ridge. Shortest length.

    Minimum bends.

    POWER HOUSE

    Easy accessibility.

    Flatter ground.

    Above high flood level.

    Stable slope.

  • 7/28/2019 Site Selection, Invesigations

    49/50

  • 7/28/2019 Site Selection, Invesigations

    50/50