site.iugaza.edu.pssite.iugaza.edu.ps/.../02/project-1-using-robot-old.docx · web viewis the span...
TRANSCRIPT
Design of residential buildingThis example will discuss the procedures for design of each structural element of
residential building.
The number of floors = 5 floors.
Compressive strength of used concrete = 240 kg/cm2 for beams and slabs and
280 kg/cm2 for columns and foundations.
Yield strength of used steel bars 4200 kg/cm2.
Live load = 200 kg/cm2.
γsoil=1.8 t /m3
γ Reinforced Concrete=2.5 t /m3 .
γmorter=2.1 t /m3 .
γ plaster=2.1t /m3 .
qall(gross)=2.3 Kg /c m2 .
Df =1.5 m.
Concrete cover:
Concrete cover = 7.5 cm for the underground element.
Concrete cover = 2.5 cm for slab.
Concrete cover = 4 cm for other elements.
Figure 1: Ground floor map (plan)
Figure 2: First floor map (plan)
Procedures1. Columns distribution.
2. Beams distribution.
3. Calculate slab thickness.
4. Calculate slab loads.
5. Design of ribs.
6. Design of beams.
7. Design of columns.
8. Design of footing.
9. Preparation of calculation sheet.
10. Preparation of structural drawing.
First: Columns distribution
- The distribution of columns must be appropriate to the architecture plan.
Figure 3: Distribution of columns on ground floor map
Second: Beams distribution
- Determine the direction of ribs in the slab.
- Draw the initial distribution of the beams.
- Draw ribs and blocks.
Notes:
The main beams is the beam perpendicular to the direction of ribs, secondary
beams is parallel to the direction of the ribs.
Ribs are not to be less than 10 cm in width (prefer 12 to facilate steel and
casting works).
Clear spacing between ribs is not to exceed 75.0 cm (usually used width of
block which equal 40 cm).
Figure 4: Distribution of beams and ribs
Third: Calculate slab thickness.
Minimum thickness of one-way ribbed slabs
ElementSimply
supportedOne end
continuousBoth ends continuous
Cantilever
One-way ribbed slabs
l/16l/18.5l/21l/8
where l is the span length in the direction of bending and measure center to center.
Notes:
The most common concrete hollow block sizes are 40 × 25 cm in plan and
heights of 14, 17, 20 and 24 cm.
Topping slab thickness is not to be less than 1/12 the clear distance between
ribs, nor less than 5.0 cm.
Calculate the thickness of (rib) slab:
Member Type Maximum Length Minimum Thickness (cm)
- Simply supported 363.5 363.516
=22.72 cm
- One end continuous 407.5407.518.5
=22.03 cm
- Both end continuous 383.5 383.521
=18.26 cm
- Cantilever 1501508
=18.75 cm
So minimum thickness for rib = 24.32 cm
Calculate the thickness of main beam:
Member Type Maximum Length Minimum Thickness (cm)
- Simply supported - -
C1C7 One end continuous 51051018.5
=27.57cm
C5C10 Both end continuous 54854821
=26.10 cm
- Cantilever - -
So minimum thickness for main beam = 27.57 cm
Calculate the thickness of secondary beam:
Member Type Maximum Length Minimum Thickness (cm)
C1C2 Simply supported 42042016
=26.25 cm
C13C14 One end continuous 42542518.5
=22.97 cm
C5C6 Both end continuous 28028021
=13.33cm
Cantilever Cantilever 1501508
=18.75 cm
So minimum thickness for secondary beam = 27.57 cm
So the minimum thickness for beam & slab = 28 cm.
Use block 40*25* 20 and ribs of 12 cm.
So the topping slab thickness = 28 - 20 = 8 cm.
Note:
Depth of rib not more than 3.5 times the minimum web width.
Fourth: Calculate slab loads
The load on ribs consists of:
1. The dead load:
Own weight of the slab.
Weight of the surface finish.
Equivalent partition load.
2. The live load is dependant on the intended use of the building.
Own weight of slab:
Figure 5: Section in rib
Total volume (hatched) = 0.52×0.25×0.3 = 0.0364 m³
Volume of one hollow block = 0.40×0.25×0.20 = 0.020 m³
Net concrete volume = 0.0364 - 0.020 = 0.0164 m³
Weight of concrete = 0.0164 ×2.5 = 0.041 ton
Weight of concrete /m² =0.041
0.52× 0.25=0.3153ton/m²
Weight of hollow block /m² = 20 /1000
0.52× 0.25=¿ 0.1538 ton/m²
Own weight = 0.3153 + 0.1538 = 0.4692 ton/m²
Weight of slab covering materials:
This weight per unit area depends on the type of finishing which is usually made of
Weight of layer = thickness × unit weight ton/m2
Weight of plaster = 0.015 × 2.1 = 0.0315 ton/m2
Weight of sand = 0.07× 1.8 = 0.126 ton/m2
Weight of mortar = 0.025 × 2.1 = 0.0525 ton/m2
Weight of tiles = 0.025 × 2.1 = 0.052 ton/m2
Total weight = 0.2625 ton/m2
6 6 cm
40
12 cm
12 6
24
6 cm
Weight of equivalent partition load:
- Number of blocks per meter square = 12.5 block.
- Two layers of plaster each layer have 1.5 cm thick.
- Height of wall = 2.95 m.
For block 10:
Weight of blocks = 12.5 × 10 = 125 kg/m2
Weight of plaster = 2×0.015×2100 = 63 kg/m2
Total weight / m2 = 125 + 63 = 188 kg/m2
Wu/m ' = 188*2.95 = 554.6 kg/m'
Length of wall 10 cm = 37.6 m
Total weight of block 10 = 0.5546 × 37.6 = 20.85296 ton
Figure 6-a: Section on partition
Figure 6-b: Partition view
Partial partition load calculations:
Total weight of all partition wall = 20.85296 ton
Total Area = 162 m2
Stairs Area = 8.12 m2
Equivalent partiton load (EPL) =20.85
162−8.12=0.1355 ton/m2
Total Service Dead Load = O.W +C.M + EPL
= 0.4692 + 0.2625 + 0.1355= 0.8672 t/m2.
Live Load:
- It depends on the purpose for which the floor is constructed. Table 7.2 shows typical
values used by the Uniform Building Code (UBC).
- Its equal 200 to 250 kg/m2 in residential building.
Live Load (L.L) = 0.20 ton /m2 (In this example).
Total factored load per meter square of the slab:
Wu= 1.2(0.8672) + 1.6(0.20) =1.3606 ton/m2
Total factored load on each rib:
Wu,rib= 1.3606 × 40+12100 = 0.7075 ton/m
Fifth: Design of ribs
- Take several strips of persistent rip representing all the ribs in the slab.
A. Check rib width for beam shear:
First rib:
The rib width must be adequate to resist beam shear by satisfying the equation
1.1ФVC>Vu max .
The shear force diagram is shown in Figure 7.
Figure 7: Shear force diagram for first rib
Vu max = 1.65 ton.
Assume Φ12 mm reinforcing bars and Φ6 mm U stirrups.
d= 28−2.5−0.6−1.22
=¿ 24.3 cm
1.1ΦVc = 1.1Φ×0.53×√F c×b×d
= 1.1 × (0.75 ) ×(0.53)× 12× 24.3×√240
= 1975.25/1000 = 1.975 ton > 1.65 ton. OK.
Though shear rainforcement is not required , but is recommended to use Φ6 mm @
25 cm U-stirrups to carry the bottom flexural rainforcement.
Second rib:
The rib width must be adequate to resist beam shear by satisfying the equation
1.1ФVC>Vu max .
The shear force diagram is shown in Figure 8.
Figure 8: Shear force diagram for second rib
Vu max= 1.78 ton
Assume Φ12 mm reinforcing bars and Φ6 mm U stirrups.
D = 28−2.5−0.6−1.22
=¿ 24.3 cm
1.1ΦVc = 1.1Φ×0.53×√F c×b×d
= 1.1 × (0.75 ) ×(0.53)× 12× 24.3×√240
= 1975.25/1000 = 1.975 ton > 1.78 ton. OK.
Though shear rainforcement is not required , but is recommended to use Φ6 mm @
25 cm U-stirrups to carry the bottom flexural rainforcement.
B. Design flexural rainforcement:
Design for shrinkage reinforcement:
Use the minimum value of shrinkage reinforcement as follows:
As min ¿0.0018 ×b× h
calculate for astrip of 1m wide (b =100 cm) , htopping = 8 cm.
As min ¿0.0018 ×100 ×8=1.44 cm2
Use Φ6 mm diameter with area of 0.2826 cm2
No. bars = 1.44 / 0.2826 = 5.0 though use 5Φ6 mm / m
So use Φ6 mm @ 20 cm
First rib:
The rib is designed as a rectangular section
The bending moment diagram is shown in Figure 9.
Figure 9: Bending moment diagram in first rib
Positive moment
Mu max = 0.93 ton.m
ρ=0 .85 f c
f y [1−√1−2 .353×105 M u
φ bd2 f c]
ρ=0 .85(240 )4200 [1−√1− 2 .353×105( 0. 93 )
0 . 9×12×(24 . 3 )2×240 ]ρreq = 0.003606
ρmin = 14fy
= 144200 = 0.00333 ρ req > ρ min OK.
ρmax=0.31875 ×fc × 1
fy 1= 0.85 since fc`= 240 < 280
ρmax=0.31875 ×240 ×0.85
4200=0.01548 ρ max > ρ req OK. the section is tension
controlled
Use ρ = ρ req = 0.003606
As,+ve ¿ ρ ×b× d = 0.003606×12× 24.3 = 1.051 cm2
Use Φ 10 mm diameter with area of 0.79 cm2 and Φ 12 mm diameter with area of
1.13 cm2.
No. bars = 1.051 / 0.79 = 1.33 though use 1 Φ10 mm and 1 Φ12 mm.
S = b−2 (concrete cover )−2 (φstirrup )−n(φbar)
n−1
S = 12−2 (2.5 )−2 (0.6 )−(1)−(1.2)
2−1 = 3.6 > 2.5 > 1.2 OK.
Negative moment
Mu max = -0.87 ton.m
ρ=0 .85 f c
f y [1−√1−2 .353×105 M u
φ bd2 f c]
ρ=0 .85(240 )4200 [1−√1− 2 .353×105( 0. 87 )
0 . 9×12×(24 . 3 )2×240 ]ρreq = 0.003365
ρmin = 14fy
= 144200 = 0.00333 ρ req > ρ min OK.
ρmax=0.31875 ×fc × 1
fy 1= 0.85 since fc`= 240 < 280
ρmax=0.31875 ×240 ×0.85
4200=0.01548 ρ max > ρ req OK. the section is tension
controlled.
Use ρ = ρ req =0.003365
As,+ve ¿ ρ ×b× d = 0.003365 ×12× 24.3 = 0.981 cm2
Use Φ 12 mm diameter with area of 1.13 cm2.
No. bars = 0.981 / 1.13 = 0.86 though use 1 Φ12 mm.
S = b−2 (concrete cover )−2 (φstirrup )−n(φbar)
n−1
S = 12−2 (2.5 )−2 (0.6 )−1(1.2)
2−1 = 4.6 > 2.5 > 1.2 OK.
Negative moment
Mu max = -0.20 ton.m
ρ=0 .85 f c
f y [1−√1−2 .353×105 M u
φ bd2 f c]
ρ=0 . 85(240 )4200 [1−√1− 2 .353×105 (0. 20 )
0 . 9×12×(24 . 3 )2×240 ]ρreq = 0.00075
ρmin = 14fy
= 144200 = 0.00333 ρ req < ρ min OK.
1= 0.85 since fc`= 240 < 280
Use ρ = ρ min = 0.003333
As,+ve ¿ ρ ×b× d = 0.003333 ×12× 24.3 = 0.972 cm2
Use Φ 12 mm diameter with area of 1.13 cm2.
No. bars = 0.972 / 1.13 = 0.86 though use 1 Φ12 mm.
S = b−2 (concrete cover )−2 (φstirrup )−n(φbar)
n−1
S = 12−2 (2.5 )−2 (0.6 )−1(1.2)
2−1 = 4.6 > 2.5 > 1.2 OK.
Negative moment
Mu max = -0.94 ton.m
ρ=0 .85 f c
f y [1−√1−2 .353×105 M u
φ bd2 f c]
ρ=0 .85(240 )4200 [1−√1− 2 .353×105( 0. 87 )
0 . 9×12×(24 . 3 )2×240 ]ρreq = 0.003365
ρmin = 14fy
= 144200 = 0.00333 ρ req > ρ min OK.
ρmax=0.31875 ×fc × 1
fy 1= 0.85 since fc`= 240 < 280
ρmax=0.31875 ×240 ×0.85
4200=0.01548 ρ max > ρ req OK. the section is tension
controlled.
Use ρ = ρ req =0.003365
As,+ve ¿ ρ ×b× d = 0.003365 ×12× 24.3 = 0.981 cm2
Use Φ 10 mm diameter with area of 0.79 cm2 and Φ 12 mm diameter with area of
1.13 cm2.
No. bars = 0.981 / 0.79 = 1.24 though use 1 Φ10 mm and 1 Φ12 mm.
S = b−2 (concrete cover )−2 (φstirrup )−n(φbar)
n−1
S = 12−2 (2.5 )−2 (0.6 )−(1)−(1.2)
2−1 = 3.6 > 2.5 > 1.2 OK.
Positive moment
Mu max = 0.98 ton.m
ρ=0 .85 f c
f y [1−√1−2 .353×105 M u
φ bd2 f c]
ρ=0 . 85(240 )4200 [1−√1− 2 .353×105( 0. 98 )
0 . 9×12×(24 . 3 )2×240 ]ρreq = 0.003365
ρmin = 14fy
= 144200 = 0.00333 ρ req > ρ min OK.
ρmax=0.31875 ×fc × 1
fy 1= 0.85 since fc`= 240 < 280
ρmax=0.31875 ×240 ×0.85
4200=0.01548 ρ max > ρ req OK. the section is tension
controlled.
Use ρ = ρ req =0.003808
As,+ve ¿ ρ ×b× d = 0.003808 ×12× 24.3 = 1.11 cm2
Use Φ 10 mm diameter with area of 0.79 cm2.
No. bars = 1.11 / 0.79 = 1.40 though use 2 Φ10 mm.
S = b−2 (concrete cover )−2 (φstirrup )−n(φbar)
n−1
S = 12−2 (2.5 )−2 (0.6 )−2(1)
2−1 = 3.8 > 2.5 > 1 OK.
Sixth: Design of beams
There are two types of beams, main and secondary beams.
Main beams: the following loads affect it:
- Self weight = width × thickness × 2500 kg/m'
- Half of the ribs from each side.
- If the external beam, add weight of 1 linear meters of exterior walls.
- If one end of the beam is cantilever, take the all distance not half of it, and add the
weight of Crans.
Secondary beams: the following loads affect it:
- Self weight = width × thickness × 2500 kg/m'
- If the external beam, add weight of 1 linear meters of exterior walls.
Note:
If the live load is maximum, use the envelope moment in the anylsis of beams.
Design of beams for flexure:
Main beam (B1):
The bending moment diagram is shown Figure 11.
Figure 11: Bending moment diagram for main beam 1
h = 28 cm (thickness of slab) b = 70 cm
Assume Φ16 mm reinforcing bars and Φ8 mm stirrups.
d = 28−4−(0.8 )−¿1.2/2) = 22.6 cm
Load assigned to the beam:
1. Slab load = [Rib ¿
2+Rib¿
2]× Wu =[3.225
2+ 0
2 ]× 1.3606=2.1939 ton /m
2. Own wieght =
1.2 [ (0.7 ×0.28 ×2.5 )+(0.1335+0.2625)]+1.6 [ 0.7 ×0.2 ]=1.2872 ton /m
3. External wall load =1.2 ×0.92335=1.01802ton /m
Load assigned to the beam = [2.1939+1.2872+1.01802] =4.45 ton /m
Positive moment
Mu max = 9.07 ton.m
ρ=0 .85 f c
f y [1−√1−2 .353×105 M u
φ bd2 f c]
ρ=0 .85(240 )4200 [1−√1− 2. 353×105(9 .07 )
0 .9×70×(22 .6)2×240 ]ρreq = 0.007253
ρmin = 14fy
= 144200 = 0.00333 ρ req > ρ min OK.
ρmax=0.31875 ×fc × 1
fy 1= 0.85 since fc`= 240 < 280
ρmax=0.31875 ×240 ×0.85
4200=0.01548 ρ max > ρ req OK. the section is tension
controlled
Use ρ = ρ req = 0.007253
As,+ve ¿ ρ ×b× d = 0.007253×70× 22.6 = 11.47 cm2
Use Φ 12 mm diameter with area of 1.13 cm2.
No. bars = 11.47 / 1.13 = 10.15 though use 11 Φ12 mm.
S = b−2 (concrete cover )−2 (φstirrup )−n(φbar)
n−1
S = 70−2 (4 )−2 (0.8 )−11(1.2)
11−1 = 4.7 > 2.5 > 1.2 OK.
Negative moment
Mu max = -10.68 ton.m
ρ=0 .85 f c
f y [1−√1−2 .353×105 M u
φ bd2 f c]
ρ=0 .85(240 )4200 [1−√1− 2 .353×105 (10 .68 )
0 .9×70×(22 .6)2×240 ]
ρreq = 0.008678
ρmin = 14fy
= 144200 = 0.00333 ρ req > ρ min OK.
ρmax=0.31875 ×fc × 1
fy 1= 0.85 since fc`= 240 < 280
ρmax=0.31875 ×240 ×0.85
4200=0.01548 ρ max > ρ req OK. the section is tension
controlled
Use ρ = ρ req = 0.008678
As,+ve ¿ ρ ×b× d = 0.008678×70× 22.6 = 13.72 cm2
Use Φ 12 mm diameter with area of 1.13 cm2.
No. bars = 13.72 / 1.13 = 12.14 though use 13 Φ12 mm.
S = b−2 (concrete cover )−2 (φstirrup )−n(φbar)
n−1
S = 70−2 (4 )−2 (0.8 )−13(1.2)
13−1 = 3.73 > 2.5 > 1.2 OK.
Positive moment
Mu max = 1.7 ton.m
ρ=0 .85 f c
f y [1−√1−2 .353×105 M u
φ bd2 f c]
ρ=0 .85(240 )4200 [1−√1− 2 .353×105 (1.7)
0 .9×70×(22 .6)2×240 ]ρreq = 0.001275
ρmin = 14fy
= 144200 = 0.00333 ρ req < ρ min OK.
1= 0.85 since fc`= 240 < 280
Use ρ = ρ req = 0.001275
As,+ve ¿ ρ ×b× d = 0.00333×70× 22.6 = 5.26 cm2
Use Φ 12 mm diameter with area of 1.13 cm2.
No. bars = 5.26 / 1.13 = 4.66 though use 5 Φ12 mm.
S = b−2 (concrete cover )−2 (φstirrup )−n(φbar)
n−1
S = 70−2 (4 )−2 (0.8 )−5(1.2)
5−1 = 13.6 > 2.5 > 1.2 OK.
Negative moment
Mu max = -6.68 ton.m
ρ=0 .85 f c
f y [1−√1−2 .353×105 M u
φ bd2 f c]
ρ=0 .85(240 )4200 [1−√1− 2 .353×105(6 .68 )
0 .9×70×(22 .6)2×240 ]ρreq = 0.005224
ρmin = 14fy
= 144200 = 0.00333 ρ req > ρ min OK.
ρmax=0.31875 ×fc × 1
fy 1= 0.85 since fc`= 240 < 280
ρmax=0.31875 ×240 ×0.85
4200=0.01548 ρ max > ρ req OK. the section is tension
controlled
Use ρ = ρ req = 0.005224
As,+ve ¿ ρ ×b× d = 0.005224 ×70× 22.6 = 8.26 cm2
Use Φ 12 mm diameter with area of 1.13 cm2.
No. bars = 8.26 / 1.13 = 7.31 though use 8 Φ12 mm.
S = b−2 (concrete cover )−2 (φstirrup )−n(φbar)
n−1
S = 70−2 (4 )−2 (0.8 )−8(1.2)
8−1 = 7.25 > 2.5 > 1.2 OK.
Positive moment
Mu max = 5.57 ton.m
ρ=0 .85 f c
f y [1−√1−2 .353×105 M u
φ bd2 f c]
ρ=0 .85(240 )4200 [1−√1− 2 .353×105 (5 .57 )
0 .9×70×(22 .6)2×240 ]
ρreq = 0.004313
ρmin = 14fy
= 144200 = 0.00333 ρ req > ρ min OK.
ρmax=0.31875 ×fc × 1
fy 1= 0.85 since fc`= 240 < 280
ρmax=0.31875 ×240 ×0.85
4200=0.01548 ρ max > ρ req OK. the section is tension
controlled
Use ρ = ρ req = 0.004313
As,+ve ¿ ρ ×b× d = 0.004313 ×70× 22.6 = 6.82 cm2
Use Φ 12 mm diameter with area of 1.13 cm2.
No. bars = 6.82 / 1.13 = 6.03 though use 7 Φ12 mm.
S = b−2 (concrete cover )−2 (φstirrup )−n(φbar)
n−1
S = 70−2 (4 )−2 (0.8 )−7(1.2)
7−1 = 8.66 > 2.5 > 1.2 OK.
Design of beams for shear
Main beam (B1):
The shear force diagram is shown in Figure 13.
Figure 13: Shear force diagram for main beam 3
Beam width (B1) = 70 cm.
Assume Φ12 mm reinforcing bars and Φ8 mm stirrups.
d = 28−4−(0.8 )−¿1.2/2) = 22.6 cm.
Vu max, d =12.30
ФVC= 0 .75(0 . 53)1000
×√240×70×22 .6=9.74 ton .
Check ductile mode of failure:
2.2×√ fc ' ×b×d = 2.2×√240×70×22.6× 10-3 = 53.91 ton.
Vs= V u, d−Ф V C
Ф = 12.30−9.74
0.75 = 3.41 ton < 2.2×√ fc ' ×b×d C
Now assume 4 legged Φ8 mm stirrups
Av = 4 × π4
× 0.82 = 2 cm2 , d = 22.6 cm , bw = 70 cm , Vs = 3.41 ton.
1.1×√ fc ' ×b×d = 1.1×√240×70×22.6×10-3 = 26.959 > Vs
S = 22.6 ×2 ×4200
3.41 ×1000=¿55.67 cm, Smax =
2× 42003.5 ×70
=¿ 34.2 cm.
d2=22.6
2=11.3cm.
The smallest value is 11.3 cm so that (d2 = max value of S)
The value of S = 11 cm will be taken for the whole sections of B1.
Seventh: Design of columns
- The loads of columns can be determined by two methods reaction method and area
method. (In this example area method are used)
- Calculate the bounded area as show in Figure 17.
- After finished the design of columns, draw the final dimensions of columns on the
maps.
Figure 17: Area of columns
Calculation of loads
Table 1: Loads on columns
Design of tied column:
Columns 1, Columns Group (3):
Ribs area = 6.345 −¿ 2.517 = 3.828 m2
Own weight of one column =2.5×0.4×0.2×2.95 = 0.59 ton
Slab Load = 3.828 ×0.867245 + 2.517 × (0.28× 2.5 + 0.1355 + 0.2625) = 6.083 ton
External walls load = 5.05 × 0.92335 = 4.6629 ton
Total Dead load = 0.59 + 6.083 + 4.6629 =11.336 ton
Total live load = 0.20 ×6.345 = 1.269 ton
Pu = 5 × (1.2 × 11.336 +1.6 ×1.269 ) = 78.17 ton
B = 20 cm , ρg=1 %
Ag=Pu
0.52 [0.85 fc +ρg ( fy−0.85 fc ) ]
Ag=78170
0.52[0.85× 280+0.01 (4200−0.85 ×280 )]=541.49 cm2
h=541.4920
=27.07 cm
The minimum column dimension is 20 cm× 40 cm So, use h = 40 cm
A s=0.01 ×541.49=5.4149 cm2
use6∅ 12mm
Check spacing:
Col no. Total area Beam area Ribs area Own wt. External wall length Total DL Total L.L DL service LL service Pu C1 6.35 2.52 3.828 0.59 5.05 11.34 1.27 56.68 6.35 15.63C2 10.11 2.24 7.871 0.59 6.5 15.87 2.02 79.36 10.11 22.28C3 10.04 2.23 7.809 0.59 6.45 15.77 2.01 78.84 10.04 22.14C4 6.73 2.66 4.072 0.59 5.2 11.84 1.35 59.19 6.73 16.36C5 16.32 4.44 11.876 0.59 0 15.77 3.26 78.84 16.32 24.15C6 16.08 4.43 11.649 0.59 0 15.56 3.22 77.79 16.08 23.82C7 11.28 3.29 3.36 0.59 4.8 11.55 2.26 57.74 11.28 17.47C8 13.45 4.04 9.41 0.59 4.6 17.43 2.69 87.17 13.45 25.22C9 9.69 2.89 6.8068 0.59 4.13 13.48 1.94 67.38 9.69 19.27C10 16.15 3.80 12.35 0.59 0 15.47 3.23 77.36 16.15 23.74C11 15.91 3.80 12.112 0.59 0 15.27 3.18 76.33 15.91 23.41C12 12.71 3.56 9.153 0.59 4.13 16.24 2.54 81.22 12.71 23.56C13 5.11 2.35 2.764 0.59 4.5 9.72 1.02 48.60 5.11 13.30C14 7.40 3.03 4.37 0.59 3.4 10.84 1.48 54.20 7.40 15.38C15 7.29 3.03 4.261 0.59 3.35 10.70 1.46 53.50 7.29 15.17C16 5.00 2.33 2.67 0.59 4.45 9.58 1.00 47.88 5.00 13.09
Sclear=40−2× 4−2×0.8−6 ×1.2
6−1=4.64 cmOK .
Sties = Smallest of (16×1.2 or 48×0.8 or 20) = 19 cm
Use One (ties) 8 mm @ 19 cm
Table 2: Detailed design of columns
Col no. Pu Factor Ag Req. As b h required h actual Dimenition ф # of Bars Space Smax of ties C1 78.17 541.49 5.41 20 28 40 20x40 12 5 6.50 19C2 111.40 771.68 7.72 20 39 40 20x40 12 7 3.81 19C3 110.68 766.67 7.67 20 39 40 20x40 12 7 3.85 19C4 81.79 566.57 5.67 20 29 40 20x40 12 5 6.08 19C5 120.73 836.27 8.36 20 42 45 20x45 12 7 4.15 19C6 119.08 824.83 8.25 20 42 45 20x45 12 7 4.23 19C7 87.34 605.00 6.05 20 31 40 20x40 12 5 5.51 19C8 126.12 873.67 8.74 20 44 45 20x45 12 8 3.88 19C9 96.37 667.55 6.68 20 34 40 20x40 12 6 4.75 19C10 118.68 822.08 8.22 20 42 45 20x45 12 7 4.25 19C11 117.06 810.86 8.11 20 41 45 20x45 12 7 4.34 19C12 117.80 816.01 8.16 20 41 45 20x45 12 7 4.30 19C13 66.49 460.60 4.61 20 24 40 20x40 12 4 8.30 19C14 76.88 532.52 5.33 20 27 40 20x40 12 5 6.67 19C15 75.86 525.47 5.25 20 27 40 20x40 12 5 6.80 19C16 65.45 453.40 4.53 20 23 40 20x40 12 4 8.50 19
Table 3: Groups of columns
Eighth: Design of footing
There are three groups of footings according the groups of columns.
Design of the first group:
The unfactored load of column (Pservice) = 100.62 ton.
The factored load of column (Pu) = 126.125 ton.
Assume footing thickness (h = 45 cm) & Φ12 mm reinforcing bars.
hc= 45 cm , hs = 150 - 45 = 105 cm , C1=25 cm , C2 =45 cm.
qall(net) = qall, (gross) −¿hc c −¿ hs s
q all(net )=20−0.45× 2.5−1.05×1.8=¿19.985 ton/m2
davg = 45−7.5−1.2= 36.3 cm
Areq = P service
qall , net=100.62
19.985 = 5.034 m2
Assume L= 2.25 m B= 5.0342.25 = 2.237 ~ 2.25 m.
qu,net = Pu
Anew= 126.1252
2.25 × 2.25=¿ 24.913 ton/m2
Check footing thickness for punching shear:
This condition must be satisfies Vu≤ ΦVc
Vu = qu ,net ×[ (B × L )−(C1+davg ) (C2+davg )]
= 24.913 ×[(2.25 ×2.25 )−(0.25+0.363 ) (0.45+0.363 ) ]
= 113.70 ton.
bo = 2 (C1+davg )+2 (C2+davg )
= 2 (0.25+0.363) +2(0.45+0.363) = 2.852 m
The value of ΦVc is taken as the smaller of the following tow equations:
1. ФVC = Ф× 0.53× √ fc ' ×[1+ 2β]× bo ×d
2 .ФVC = Ф× √ fc ' × bo ×d
1=C longC short
=4525
=1.8
ΦVc, min¿0.75 ×× 285.2× 36.3/1000= 129.926 > Vu OK.
i.e. The footing thickness is aduqate for resisting punching shear.
Check footing thickness for beam shear:
This condition must be satisfies Vu≤ ΦVc
Long direction:
Vu =qu ,net ×[ L×( B−C 1
2−davg)]
Vu = 24.913 ×[2.25 ×( 2.25−0.252
−0.363)]=¿ 35.71 ton.
ФVC = Ф× 0.53× √ fc ' × bo ×d
ΦVc = 0.75 ×0.53 ×√280 × 225× 36.3× 10−3=¿ 54.33 ton > Vu OK.
i.e. The footing thickness is aduqate for resisting beam shear in the long direction.
short direction:
Vu =qu ,net ×[B ×( L−C 2
2−davg)]
Vu = 24.913 ×[2.25 ×( 2.25−0.452
−0.363)]=¿ 30.10 ton.
ФVC = Ф× 0.53 ×√ fc ' × bo ×d
ΦVc = 0.75 ×0.53 ×√280 × 225× 36.3× 10−3=¿ 54.33 ton > Vu OK.
i.e. The footing thickness is aduqate for resisting beam shear in the short direction.
Design of footings for flexure:
Long direction:
Mu = qu ,net ×B2
× ¿
Mu =24.913 × 2.252
× ¿ 22.70 ton.m
Now design the footing as arectangular section with b = 225 cm.
davg = 45−7.5−1.2= 36.3 cm.
ρ=0 .85 f c
f y [1−√1−2 .353×105 M u
φ bd2 f c]
ρ=0 . 85(280 )4200 [1−√1− 2 .353×105 (22. 7 )
0 . 9×225×(36 . 3 )2×280 ]ρreq = 0.00206
As,req ¿0.00206 ×225 ×36.3 = 16.85 cm2
As,min ¿0.0018 ×b× h=0.0018× 225× 45=¿ 18.225 cm2
As,min >As,req so ues As,min = 18.225 cm2
Use Φ 12 mm diameter with area of 1.13 cm2
No. bars = 18.225 / 1.13= 16.12 though use 17 Φ12 mm.
Short direction:
Mu = qu ,net ×L2
× ¿
Mu =24.913 × 2.252
× ¿ 28.03 ton.m
Now design the footing as arectangular section with b = 225 cm.
davg = 45−7.5−1.2= 36.3 cm.
ρ=0 .85 f c
f y [1−√1−2 .353×105 M u
φ bd2 f c]
ρ=0 . 85(280 )4200 [1−√1− 2 .353×105 (28. 03 )
0 . 9×225×(36 . 3 )2×280 ]ρreq = 0.00256
As,req ¿0.00256 ×225 ×36.3 = 20.908 cm2
As,min ¿0.0018 ×b× h=0.0018× 225× 45=¿ 18.225 cm2
As,min < As,req so ues As,req = 20.908 cm2
Use Φ 12 mm diameter with area of 1.13 cm2
No. bars = 20.908 / 1.13 = 18.5 though use 19 Φ12 mm.
Table 4: Groups of footings
Ninth: Preparation of calculation sheet
Calculation Sheet
Design of Multi Story Building Using ACI 318-08 Code
Determination of slab thickness
To control deflection the min. thickness required must be calculated from this table :
ElementSimply
supportedOne end
continuousBoth ends continuous
Cantilever
One-way ribbed slabs
l/16l/18.5l/21l/8
where l is the span length in the direction of bending and measure center to center.
Calculate the thickness of (rib) slab:
Member Type Maximum Length Minimum Thickness (cm)
- Simply supported 363.5 363.516
=22.72 cm
- One end continuous 407.5407.518.5
=22.03 cm
- Both end continuous 383.5 383.521
=18.26 cm
- Cantilever 1501508
=18.75 cm
So minimum thickness for rib = 24.32 cm
Calculate the thickness of main beam:
Member Type Maximum Length Minimum Thickness (cm)
- Simply supported - -
C1C7 One end continuous 51051018.5
=27.57cm
C5C10 Both end continuous 54854821
=26.10 cm
- Cantilever - -
So minimum thickness for main beam = 27.57 cm
Calculate the thickness of secondary beam:
Member Type Maximum Length Minimum Thickness (cm)
C1C2 Simply supported 42042016
=26.25 cm
C13C14 One end continuous 42542518.5
=22.97 cm
C5C6 Both end continuous 28028021
=13.33cm
Cantilever Cantilever 1501508
=18.75 cm
So minimum thickness for secondary beam = 27.57 cm
So the minimum thickness for beam & slab = 28 cm.
Use block 40*25* 20 and ribs of 12 cm.
So the topping slab thickness = 28 - 20 = 8 cm.
Load calculation for 1 m2 of slab
Own weight of slab:
Total volume (hatched) = 0.52×0.25×0.3 = 0.0364 m³
Volume of one hollow block = 0.40×0.25×0.20 = 0.020 m³
Net concrete volume = 0.0364 - 0.020 = 0.0164 m³
Weight of concrete = 0.0164 ×2.5 = 0.041 ton
Weight of concrete /m² =0.041
0.52× 0.25=0.3153ton/m²
6 6 cm
40
12 cm
12 6
24
6 cm
Weight of hollow block /m² = 20 /1000
0.52× 0.25=¿ 0.1538 ton/m²
Own weight = 0.3153 + 0.1538 = 0.4692 ton/m²
Weight of slab covering materials:
Weight of layer = thickness × unit weight ton/m2
Weight of plaster = 0.015 × 2.1 = 0.0315 ton/m2
Weight of sand = 0.07× 1.8 = 0.126 ton/m2
Weight of mortar = 0.025 × 2.1 = 0.0525 ton/m2
Weight of tiles = 0.025 × 2.1 = 0.052 ton/m2
Total covering material weight = 0.2625 ton/m2
Weight of equivalent partition load:
- Number of blocks per meter square = 12.5 block.
- Two layers of plaster each layer have 1.5 cm thick.
- Height of wall = 2.95 m.
For block 10:
Weight of blocks = 12.5 × 10 = 125 kg/m2
Weight of plaster = 2×0.015×2100 = 63 kg/m2
Total weight / m2 = 125 + 63 = 188 kg/m2
Wu/m ' = 188*2.95 = 554.6 kg/m'
Length of wall 10 cm = 37.6 m
Total weight of block 10 = 0.5546 × 37.6 = 20.85296 ton
Partial partition load calculations:
Total weight of all partition wall = 20.85296 ton
Total Area = 162 m2
Stairs Area = 8.12 m2
Equivalent partiton load (EPL) =20.85
162−8.12=0.1355 ton/m2
Total Service Dead Load = O.W +C.M + EPL
Total Service Dead Load = 0.4692 + 0.2625 + 0.1355= 0.8672 t/m2.
Live load:
Live load (L.L) = 0.20 ton /m2.
Total factored load per meter square of the slab:
Wu= 1.2(0.8672) + 1.6(0.20) =1.3606 ton/m2
Total factored load on each rib:
Wu,rib= 1.3606 × 40+12100 = 0.7075 ton/m
Check slab thickness for beam shear
Vu max= 1.78 ton
Assume Φ12 mm reinforcing bars and Φ6 mm U stirrups.
D = 28−2.5−0.6−1.22
=¿ 24.3 cm
1.1ΦVc = 1.1Φ×0.53×√F c×b×d
= 1.1 × (0.75 ) ×(0.53)× 12× 24.3×√240
= 1975.25/1000 = 1.975 ton > 1.78 ton. OK.
Though shear rainforcement is not required , but is recommended to use Φ6 mm @
25 cm U-stirrups to carry the bottom flexural rainforcement.
Design of beams
Design of beams for flexure:
Main beam (B1):
f c=240 kg/cm2 fy = 4200 kg/cm2
h = 28 cm (thickness of slab) b = 70 cm cover = 4 cm
Assume Φ12 mm reinforcing bars and Φ8 mm stirrups.
d = 28−4−(0.8 )−¿1.2/2) = 22.6 cm
Load assigned to the beam:
1. Slab load = [Rib ¿
2+Rib¿
2]× Wu =[3.225
2+ 0
2 ]× 1.3606=2.1939 ton /m
2. Own wieght = =
1.2 [ (0.7 ×0.28 ×2.5 )+(0.1335+0.2625) ]+1.6 [ 0.7 ×0.2 ]=1.2872 ton /m
3. External wall load =1.2 ×0.92335=1.01802ton /m
Load assigned to the beam = [2.1939+1.2872+1.01802] =4.45 ton /m
Positive moment
Mu max = 9.07 ton.m
ρ=0 . 85 f c
f y [1−√1−2 .353×105 M u
φ bd2 f c]
ρ=0 .85(240 )4200 [1−√1− 2. 353×105(9 .07 )
0 .9×70×(22 .6)2×240 ]ρreq = 0.007253
ρmin = 14fy
= 144200 = 0.00333 ρ req > ρ min OK.
ρmax=0.31875 ×fc × 1
fy 1= 0.85 since fc`= 240 < 280
ρmax=0.31875 ×240 ×0.85
4200=0.01548 ρ max > ρ req OK. the section is tension
controlled
Use ρ = ρ req = 0.007253
As,+ve ¿ ρ ×b× d = 0.007253×70× 22.6 = 11.47 cm2
Use Φ 12 mm diameter with area of 1.13 cm2.
No. bars = 11.47 / 1.13 = 10.15 though use 11 Φ12 mm.
S = b−2 (concrete cover )−2 (φstirrup )−n(φbar)
n−1
S = 70−2 (4 )−2 (0.8 )−11(1.2)
11−1 = 4.7 > 2.5 > 1.2 OK.
Negative moment
Mu max = -10.68 ton.m
ρ=0 .85 f c
f y [1−√1−2 .353×105 M u
φ bd2 f c]
ρ=0 .85(240 )4200 [1−√1− 2 .353×105 (10 .68 )
0 .9×70×(22 .6)2×240 ]ρreq = 0.008678
ρmin = 14fy
= 144200 = 0.00333 ρ req > ρ min OK.
ρmax=0.31875 ×fc × 1
fy 1= 0.85 since fc`= 240 < 280
ρmax=0.31875 ×240 ×0.85
4200=0.01548 ρ max > ρ req OK. the section is tension
controlled
Use ρ = ρ req = 0.008678
As,+ve ¿ ρ ×b× d = 0.008678×70× 22.6 = 13.72 cm2
Use Φ 12 mm diameter with area of 1.13 cm2.
No. bars = 13.72 / 1.13 = 12.14 though use 13 Φ12 mm.
S = b−2 (concrete cover )−2 (φstirrup )−n(φbar)
n−1
S = 70−2 (4 )−2 (0.8 )−13(1.2)
13−1 = 3.73 > 2.5 > 1.2 OK.
Design of beams for shear
Main beam (B1):
f c=240 kg/cm2 fy = 4200 kg/cm2
h = 28 cm (thickness of slab) b = 70 cm cover = 4 cm
Assume Φ12 mm reinforcing bars and Φ8 mm stirrups.
d = 28−4−(0.8 )−¿1.2/2) = 22.6 cm
Vu max, d =12.30
ФVC= 0 .75(0 . 53)1000
×√240×70×22 .6=9.74 ton .
Check ductile mode of failure:
2.2×√ fc ' ×b×d = 2.2×√240×70×22.6× 10-3 = 53.91 ton.
Vs= V u, d−Ф V C
Ф = 12.30−9.74
0.75 = 3.41 ton < 2.2×√ fc ' ×b×d C
Now assume 4 legged Φ8 mm stirrups
Av = 4 × π4
× 0.82 = 2 cm2 , d = 22.6 cm , bw = 70 cm , Vs = 3.41 ton.
1.1×√ fc ' ×b×d = 1.1×√240×70×22.6×10-3 = 26.959 > Vs
S = 22.6 ×2 ×4200
3.41 ×1000=¿55.67 cm, Smax =
2× 42003.5 ×70
=¿ 34.2 cm.
d2=22.6
2=11.3cm.
The smallest value is 11.3 cm so that (d2 = max value of S)
The value of S = 11 cm will be taken for the whole sections of B1.
Design of short columns
Design of tied column:
Columns 1, Columns Group (3):
Ribs area = 6.345 −¿ 2.517 = 3.828 m2
Own weight of one column =2.5×0.4×0.2×2.95 = 0.59 ton
Slab Load = 3.828 ×0.867245 + 2.517 × (0.28× 2.5 + 0.1355 + 0.2625) = 6.083 ton
External walls load = 5.05 × 0.92335 = 4.6629 ton
Total Dead load = 0.59 + 6.083 + 4.6629 =11.336 ton
Total live load = 0.20 ×6.345 = 1.269 ton
Number of stories = 5
Pu = 5 × (1.2 × 11.336 +1.6 ×1.269 ) = 78.17 ton
f c=240 kg/cm2 fy = 4200 kg/cm2
B = 20 cm ρg=1% cover = 4 cm
Ag=Pu
0.52 [0.85 fc +ρg ( fy−0.85 fc ) ]
Ag=78170
0.52[0.85× 280+0.01 (4200−0.85 ×280 )]=541.49 cm2
h=541.4920
=27.07 cm
The column dimension is 20cm× 40 cm So, use h = 40 cm
A s=0.01 ×541.49=5.4149 cm2
use6∅ 12mm
Check spacing:
Sclear=40−2× 4−2×0.8−6 ×1.2
6−1=4.64 cmOK .
Sties = Smallest of (16×1.2 or 48×0.8 or 20) = 19 cm
Use One (ties) 8 mm @ 19 cm
Design of footing
Design of the first group:
f c=240 kg/cm2 fy = 4200 kg/cm2
c= 2.5 ton /m3 s = 1.8 ton/m3
The unfactored load of column (Pservice) = 100.62 ton.
The factored load of column (Pu) = 126.125 ton.
Assume footing thickness (h = 45 cm) & Φ12 mm reinforcing bars.
hc= 45 cm hs = 150 - 45 = 105 cm
C1=25 cm C2 =45 cm.
qall(net) = qall, (gross) −¿hc c −¿ hs s
q all(net )=20−0.45× 2.5−1.05×1.8=¿19.985 ton/m2
davg = 45−7.5−1.2= 36.3 cm
Areq = P service
qall , net=100.62
19.985 = 5.034 m2
Assume L= 2.25 m B= 5.0342.25 = 2.237 ~ 2.25 m.
qu,net = Pu
Anew= 126.1252
2.25 × 2.25=¿ 24.913 ton/m2
Check footing thickness for punching shear:
This condition must be satisfies Vu≤ ΦVc
Vu = qu ,net ×[ (B × L )−(C1+davg ) (C2+davg )]
= 24.913 ×[(2.25 ×2.25 )−(0.25+0.363 ) (0.45+0.363 ) ]
= 113.70 ton.
bo = 2 (C1+davg )+2 (C2+davg )
= 2 (0.25+0.363) +2(0.45+0.363) = 2.852 m
The value of ΦVc is taken as the smaller of the following tow equations:
1. ФVC = Ф× 0.53× √ fc ' ×[1+ 2β]× bo ×d
2 .ФVC = Ф× √ fc ' × bo ×d
1=C longC short
=4525
=1.8
ΦVc, min¿0.75 ×× 285.2× 36.3/1000= 129.926 > Vu OK.
i.e. The footing thickness is aduqate for resisting punching shear.
Check footing thickness for beam shear:
This condition must be satisfies Vu≤ ΦVc
Long direction:
Vu =qu ,net ×[ L×( B−C 1
2−davg)]
Vu = 24.913 ×[2.25 ×( 2.25−0.252
−0.363)]=¿ 35.71 ton.
ФVC = Ф× 0.53× √ fc ' × bo ×d
ΦVc = 0.75 ×0.53 ×√280 × 225× 36.3× 10−3=¿ 54.33 ton > Vu OK.
i.e. The footing thickness is aduqate for resisting beam shear in the long direction.
short direction:
Vu =qu ,net ×[B ×( L−C 2
2−davg)]
Vu = 24.913 ×[2.25 ×( 2.25−0.452
−0.363)]=¿ 30.10 ton.
ФVC = Ф× 0.53 ×√ fc ' × bo ×d
ΦVc = 0.75 ×0.53 ×√280 × 225× 36.3× 10−3=¿ 54.33 ton > Vu OK.
i.e. The footing thickness is aduqate for resisting beam shear in the short direction.
Design of footings for flexure:
Long direction:
Mu = qu ,net ×B2
× ¿
Mu =24.913 × 2.252
× ¿ 22.70 ton.m
Now design the footing as arectangular section with b = 225 cm.
davg = 45−7.5−1.2= 36.3 cm.
ρ=0 .85 f c
f y [1−√1−2 .353×105 M u
φ bd2 f c]
ρ=0 . 85(280 )4200 [1−√1− 2 .353×105 (22. 7 )
0 . 9×225×(36 . 3 )2×280 ]ρreq = 0.00206
As,req ¿0.00206 ×225 ×36.3 = 16.85 cm2
As,min ¿0.0018 ×b× h=0.0018× 225× 45=¿ 18.225 cm2
As,min >As,req so ues As,min = 18.225 cm2
Use Φ 12 mm diameter with area of 1.13 cm2
No. bars = 18.225 / 1.13= 16.12 though use 17 Φ12 mm.
Short direction:
Mu = qu ,net ×L2
× ¿
Mu =24.913 × 2.252
× ¿ 28.03 ton.m
Now design the footing as arectangular section with b = 225 cm.
davg = 45−7.5−1.2= 36.3 cm.
ρ=0 .85 f c
f y [1−√1−2 .353×105 M u
φ bd2 f c]
ρ=0 . 85(280 )4200 [1−√1− 2 .353×105 (28. 03 )
0 . 9×225×(36 . 3 )2×280 ]ρreq = 0.00256
As,req ¿0.00256 ×225 ×36.3 = 20.908 cm2
As,min ¿0.0018 ×b× h=0.0018× 225× 45=¿ 18.225 cm2
As,min < As,req so ues As,req = 20.908 cm2
Use Φ 12 mm diameter with area of 1.13 cm2
No. bars = 20.908 / 1.13 = 18.5 though use 19 Φ12 mm.
Tenth: Preparation of structural drawing