Skyline Heights. City of Corona Scoping Meeting March 4, 2014. Skyline Heights. Introductions Jason Moquin, Senior Planner, City of Corona Role: City Project Manager/Point of Contact David A. Crook, AICP, Principal Planner, PCR Services Corporation - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Skyline Heights

City of CoronaScoping Meeting

March 4, 2014

Skyline Heights

Page 2: Skyline Heights

Skyline Heights

Introductions

Jason Moquin, Senior Planner, City of Corona

• Role: City Project Manager/Point of Contact

David A. Crook, AICP, Principal Planner, PCR Services Corporation

• Role: City’s Environmental Impact Report (EIR) Consultant

Page 3: Skyline Heights

Skyline Heights

Overview of Scoping Meeting/Process

Overview of the Project

CEQA (California Environmental Quality Act).

Timeline

We are here to LISTEN!

Page 4: Skyline Heights

Skyline Heights

Project Area

Page 5: Skyline Heights

Skyline Heights

Overview of the Project

Applications

Annexation

421.25 acres

General Plan Amendment

Designate 384 acres as LDR and 37 acres as Open Space

Change of Zone

Pre-zone the project site

270.91 acres – R-1-7.2 (Single Family Residential. Minimum Lot Size 7,200 square feet).

113.56 acres – Agriculture

36.73 acres –Open Space

Page 6: Skyline Heights

Skyline Heights

Overview of the Project

Tentative Tract Map

Subdivide 270.91 acres into 292 lots

Lot Sizes

Range from 7,242 to 31,010 Sq. Ft. in area

Open Space

Approximately 149 acres

48 acres of manufactured slopes

101 acres of natural open space

Page 7: Skyline Heights

Skyline Heights

Proposed Project

Page 8: Skyline Heights

Skyline Heights

CEQA Overview

CEQA Process Overview

CEQA Timeline

• Notice of Preparation (30-day comment period): February 4, 2013 – March 5, 2014 (extended to March 10th)

• Public Scoping Meeting: March 4, 2014

• Draft EIR Public Review (45 day comment period): early July 2014 – mid/late August 2014

• Preparation of Final EIR: late August 2014

• Planning Commission Meeting: September 2014

• City Council Meeting: October 2014

Page 9: Skyline Heights

Skyline Heights

Environmental Topics of Study

Aesthetics – visual simulations

Agricultural & Forestry Resources

Air Quality – traffic, global climate change

Biological Resources – direct and indirect impacts

Cultural and Paleontological Resources – direct and indirect impacts

Geology and Soils

Greehouse Gas Emissions

Hazards and Hazardous Materials

BEFORE AFTER

Page 10: Skyline Heights

Skyline Heights

Environmental Topics of Study (continued)

Hydrology/Water Quality

Land Use

Noise – construction, post-construction

Population and Housing

Public Services

Traffic, Circulation

Utilities

Cumulative Impacts and Alternative

Page 11: Skyline Heights

Skyline Heights

Closing

Questions? Comments?

Your Contact Information – please sign in

City Contact Information:

Jason Moquin, City of Corona Community Development Department

400 South Vicentia Avenue

Corona, California 92882

Phone: 951-736-2268

Fax: 951-279-3550

Email: [email protected]