sns superconducting linac: operational experiences and

38
ORNL is managed by UT-Battelle for the US Department of Energy SNS Superconducting Linac: Operational experiences and plans for performance improvement Presented at Jefferson Lab October 8, 2015 Sang-ho Kim SCL Systems Group SNS/ORNL

Upload: others

Post on 04-Jan-2022

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SNS Superconducting Linac: Operational experiences and

ORNL is managed by UT-Battelle

for the US Department of Energy

SNS Superconducting Linac:

Operational experiences

and plans for performance

improvement

Presented at Jefferson Lab October 8, 2015 Sang-ho Kim SCL Systems Group SNS/ORNL

Page 2: SNS Superconducting Linac: Operational experiences and

2 SNS, S-H. Kim, Accelerator Seminar at Jlab 10/8/2015

Overview

• SNS SCL brief history

• SNS SRF caivty characterization and operational status

• Performance degradation & recovery

• Performance improvement plan

• Summary

Page 3: SNS Superconducting Linac: Operational experiences and

3 SNS, S-H. Kim, Accelerator Seminar at Jlab 10/8/2015

Design evolution of SNS Complex

Concept for

NSNS (1997)

SNS (summer 1999)

Linac length: ~465m

All warm linac

Page 4: SNS Superconducting Linac: Operational experiences and

SNS superconducting linac (SCL)

Linac length: ~330m

Preliminary Design Report for SCL option (Nov. 1999):

Y. Cho lead a task force to investigate the feasibility to change to a SCL

• Dec. 1999 – Jan. 2000: SNS advisory panel and DOE

review panel approved the change, Jefferson Lab

joined the SNS collaboration

• June 2003 - First cryo-module delivered to Oak Ridge

• August 2004– First cryo-module cool-down

• March 2005 – July 2005: High power RF tests

• August 2005: Beam commissioning

• Jan.- Feb. 2006: Support Ring Commissioning

• Oct. 2006 – present: Support neutron production runs

Page 5: SNS Superconducting Linac: Operational experiences and

5 SNS, S-H. Kim, Accelerator Seminar at Jlab 10/8/2015

SNS Superconducting Linac

• Cryomodules and CHL are designed and built by JLAB

• The first SRF technology for large scale pulsed proton machine (relatively high duty factor and high beam current)

• Designed for H- beam acceleration from 186 MeV to 1000 MeV

• 157-m long, 81 independently powered 805-MHz SRF cavities in 23 cryomodules

• Two types of cavity geometries to cover board range of particle velocities

• 71-m long space is reserved for energy upgrade 2 K Cold Box

4 K Cold Box

Warm Compressor

SCL tunnel

Page 6: SNS Superconducting Linac: Operational experiences and

H- stripped to p

SNS Machine layout

2.5

DTL

86.8

CCL

402.5 MHz 805 MHz

SRF, b=0.61 SRF, b=0.81

186 387 1000 MeV

Linac; 1 GeV acceleration

Front-End:

Produce

a 1-msec long,

chopped, H-beam

at 60 Hz

upgrade

945 ns

1 ms macropulse

Average macropulse beam current: 26 mA

Cu

rre

nt

mini-pulse

Chopper system

makes gaps

Accumulator Ring: Compress 1 msec

long pulse to 700

nsec

Liquid Hg

Target

Cu

rre

nt

1ms

259 m

157 m 71 m

Page 7: SNS Superconducting Linac: Operational experiences and

7 SNS, S-H. Kim, Accelerator Seminar at Jlab 10/8/2015

SNS SRF cavity characterization

and operational status

Page 8: SNS Superconducting Linac: Operational experiences and

8 SNS, S-H. Kim, Accelerator Seminar at Jlab 10/8/2015

Cavity characterization

• Major limiting factor: electron loading (FE, MP)

– Heating RF surfaces & beam line components: resulting in ‘end-group quench’

– Following slides will show a few examples taken during qualifying tests in the test cave

• Other limiting factors

– HOM coupler: many HOM feedthroughs were taken out

• One cavity is not operable. Eacc of a few cavities are limited due to large coupling

– Lorentz force detuning: a few cavities show larger LFD

– Hot spots

– RF/controls related issues in early days

Page 9: SNS Superconducting Linac: Operational experiences and

9 SNS, S-H. Kim, Accelerator Seminar at Jlab 10/8/2015

Turning on cavities

First turn on must be closely watched and controlled (possible irreversible damage) Initial (the first) powering-up, pushing limits, increasing rep. rate

(extreme care, close attention)

Aggressive MP, burst of FE possibly damage weak components or RF surfaces

Similar situation after thermal cycle and after long shut down Also careful conditioning process is required to keep the same

cavity condition since behavior of the same cavity can be considerably different from one run to another (gas redistribution)

Page 10: SNS Superconducting Linac: Operational experiences and

Radiation/electron activity diagnostics

during qualifying tests in the test cave

PMT

Internal Ionization Chamber

Phosphor Screen, Camera,

Faraday Cup

D0

D1

D2 D3 D4 D5 D6

D7

IC-int

Phosphor Screen

& Faraday Cup

Phosphor Screen

& Faraday Cup

Cavity A Cavity B Cavity C Cavity D

After removal of HOM feedthrus,

Installed two diodes/HOM can

Page 11: SNS Superconducting Linac: Operational experiences and

11 SNS, S-H. Kim, Accelerator Seminar at Jlab 10/8/2015

Radiation Signals

• Field emission dominant case example

– HPRF test in open loop in the test cave

– Typical field emission response

Radiation patterns (I)

Eacc

us

In this example, measureable radiation started from 15 MV/m and the cavity was tested up to 20 MV/m.

Page 12: SNS Superconducting Linac: Operational experiences and

12 SNS, S-H. Kim, Accelerator Seminar at Jlab 10/8/2015

Radiation pattern (II)

• Multipacting (MP) dominant case

– Typical MP: from ~3MV/m up to ~15 MV/m (HOM cans, End groups, FPC, etc.)

– The waveforms below are taken after 5-hrs long conditioning

11.5 MV/m

0 1000

0 1000 us

0.025

0 1000

13.5 MV/m 0.3

15.0 MV/m

0 1000

0.3

0 1000

0.3

15.3 MV/m

0.08 17.0 MV/m

0 1000 0 1000

0.2 21.0 MV/m

Eacc

Page 13: SNS Superconducting Linac: Operational experiences and

13 SNS, S-H. Kim, Accelerator Seminar at Jlab 10/8/2015

Radiation pattern (III)

• Multipacting and field emission

– In this example, a cavity right below D4 0 1000 us

12.3 MV/m 12.8 MV/m 13.3 MV/m

13.4 MV/m 15.0 MV/m 16.0 MV/m

D4

D2

Time (us)

Rad

iati

on

Inte

nsi

ty (

au)

Eacc

Page 14: SNS Superconducting Linac: Operational experiences and

14 SNS, S-H. Kim, Accelerator Seminar at Jlab 10/8/2015

Electron activities

• Same radiation patterns (MP, FE) from both MB and HB cavities – MB cavities show less thermal loading from electron activities since electron

acceleration in MB structure is less efficient

• In general, x-ray levels are quite stable in the tunnel over time – SNS beam repetition rate is actually 59.9 Hz Measure background radiation every

10 sec. during operation

– A few cavities show slightly elevated x-ray levels resulting in reduction of Eacc by ~1MV/m

– Some MP has not been processed away after 10 yrs operation

• Collective behaviors at high duty factor – Electrons from one cavity hit other cavities in a cryomodule

• Not only depends on Eacc but also relative RF phases

– Operating gradients are lower at 60 Hz than those at low repetition rate

• Linac output energy: 940 MeV at 60 Hz vs. 1070 MeV at 10 Hz

Page 15: SNS Superconducting Linac: Operational experiences and

15 SNS, S-H. Kim, Accelerator Seminar at Jlab 10/8/2015

SRF cavity operating gradients today

• Average Eacc of medium and high beta cavities: 12 MV/m and 13 MV/m respectively

– Based on 60 Hz collective limits

Eacc (

MV

/m)

Cavity number

MB design gradient HB design gradient

Page 16: SNS Superconducting Linac: Operational experiences and

16 SNS, S-H. Kim, Accelerator Seminar at Jlab 10/8/2015

SNS SRF cavity RF operation

• 60 Hz: 5.2 M pulses/day

• Filling: 250 us, feed forward

– Forward power: ~3 times higher than power during the flattop without beam loading

• Flattop: 1 ms, feedback

– With beam: + adaptive feed forward

– Forward power at full beam loading (26mA): 2.5-3.5 times higher than power for RF only

Page 17: SNS Superconducting Linac: Operational experiences and

17 SNS, S-H. Kim, Accelerator Seminar at Jlab 10/8/2015

SNS SCL Operation Status

• Stable and reliable operation Average trip (downtime):

< 1 trip/day (<5 min./day)

Availability last 4 years:

• Whole SCL system including RF, HVCM, Control, Vacuum, etc.: 98 %

• SRF cavities, cryomodules, and CHL: 99.5 %

Couple

r Tem

p.

Perf

orm

ance

Issues

Bad e

quip

ment

part

s

Tru

ncation b

y H

PR

F

During C

on

ditio

nin

g

During A

rc

de

tecto

r te

st

hours Downtime for cavity trips

Page 18: SNS Superconducting Linac: Operational experiences and

High availability while keeping high

power beam operation

• Understand machine & reliable machine setup as a whole

• Make systems as simple as possible

• Develop adequate diagnostics/protection

• Have energy margin to take advantage of operational flexibility

– to circumvent problems that can’t be addressed during operation and

to minimize a down time

• Conduct proactive/preventative maintenance

• Keep good communication between machine experts and

machine operators

Page 19: SNS Superconducting Linac: Operational experiences and

19 SNS, S-H. Kim, Accelerator Seminar at Jlab 10/8/2015

Performance Degradation and

Recovery

Page 20: SNS Superconducting Linac: Operational experiences and

20 SNS, S-H. Kim, Accelerator Seminar at Jlab 10/8/2015

Linac Output Energy History at 60Hz

Additional HVCM

Recognized Errant Beam

Lin

ac O

utp

ut

Energ

y (

MeV

)

RF/Control improvement Two CM Repairs Other misc.

Full pulse length for 1.4 MW 3 cavities

Turned off (errant beam)

CM6, CM20 out for repair

High beta spare CM in for slot 20

CM6 in

Worst performing CM (CM19) out, CM 20 in for slot 19

Changes of output energies are the result from specific activities and events

Page 21: SNS Superconducting Linac: Operational experiences and

21 SNS, S-H. Kim, Accelerator Seminar at Jlab 10/8/2015

Performance degradation during operation

• Degradation related to vacuum activity

– Observed performance degradations from ten cavities

– Beam halo, errant beam, e- activity and ion pump pressure spike

• Desorption and redistribution of gas could create conditions for vacuum breakdown or hot spots

• Main event: Interaction with RF (one of the worst case is surface damage and particulate contamination)

• Not every event makes a cavity trip. But the probability for degradation increases with frequency and intensity of events

• Other potential degradation related to particulate contamination

– Gate valve operation

• When a cavity shows a symptom of performance degradation, the gradient is lowered slightly (typically lowered by 1 MV/m or less) to avoid further degradation and to minimize downtime

– Early diagnostics and prompt involvement from system experts are the key to minimize additional degradation

Page 22: SNS Superconducting Linac: Operational experiences and

22 SNS, S-H. Kim, Accelerator Seminar at Jlab 10/8/2015

RF waveforms at cavity trip

• Very useful to understand the trip event

HVCM Voltage Fluctuation or Instability of HPRF

LLRF Drive

HPRF Forward Eacc

Eacc LLRF Drive

HPRF Forward

Cavity partial quench

In both cases, cavities tripped because cavity field did not reach set-point during filling time

Trip 1

Trip 2

Page 23: SNS Superconducting Linac: Operational experiences and

23 SNS, S-H. Kim, Accelerator Seminar at Jlab 10/8/2015

Ion pump pressure spike example

• A cavity was tripping with ion pump pressure spikes. Slight performance degradation (~1 MV/m) was observed.

• The cavity trips and pressure spikes became more frequent

– What is the root cause?

• To verify the cause we turned off one ion pump after interlock logic changes

– No trip since summer 2014

Cavity field

Vacuum reading from ion pumps

Page 24: SNS Superconducting Linac: Operational experiences and

24 SNS, S-H. Kim, Accelerator Seminar at Jlab 10/8/2015

Gate valve

• Valve actuations causing pressure spikes: observed from a few valves in the tunnel

• Particulate generation are measured on the test bench – Tested gate valves from three vendors

• Valve verification before installation

• During operation: Minimize valve actuation

Valve closed open open

Warm section IP CM IP

Vendor 1

Vendor 3

Page 25: SNS Superconducting Linac: Operational experiences and

25 SNS, S-H. Kim, Accelerator Seminar at Jlab 10/8/2015

Errant beam (I)

• Our definition:

– Off-energy beam generated from a fault condition

– Beam transported downstream and lost until beam abortion by MPS system

• Mani sources of errant beam

– Warm linac RF truncation: arc, pressure burst, etc.

– Ion source/LEBT: arc, unstable plasma, etc.

• SCL beam loss monitors (BLM) are the primary indication of errant beam event

• MPS delay: time between RF truncation/BLM trips and beam abortion

– It was recognized that MPS delay was too long in 2009 :~300 us

– MPS circuit was fixed in 2010 MPS delay: 25 us

Page 26: SNS Superconducting Linac: Operational experiences and

26 SNS, S-H. Kim, Accelerator Seminar at Jlab 10/8/2015

Errant beam (II)

• Errant beam hitting a cavity surface desorbs gas and could create vacuum breakdown environment

• Errant beam events before 2012: 35 per day

– Performance degradations by errant beam were observed

Warm linac RF truncation

Abnormal beam from ion source

20-25 us beam lost in SCL – More diagnostics were added to detect errant beam

event

– Due to this, more careful operation/conditioning of all warm linac structures and front end

• Errant beam events after 2012: 15 per day

– Dedicated MPS circuit for errant beam event is recently installed: MPS delay 12 us

• Errant beam events since 08/2015: 5 per day

– Warm linac vacuum system was improved last summer

Page 27: SNS Superconducting Linac: Operational experiences and

27 SNS, S-H. Kim, Accelerator Seminar at Jlab 10/8/2015

Beam halo

• Performance degradation from beam halo is observed in the first few cryomodules of the SC linac

• It is difficult to diagnose since the process is very slow

– BLM is less sensitive at low energy region

– Temperature diodes sometimes indicate slight temperature increment before quench

– Degradation seems to develop over a long time

– Cavity becomes very sensitive to small changes of operating conditions

• Beam scraping in the front-end helps

• More sensitive BLMs for low energy region are being prepared

Page 28: SNS Superconducting Linac: Operational experiences and

28 SNS, S-H. Kim, Accelerator Seminar at Jlab 10/8/2015

Performance degradation, component

damages and recovery

• Most frequent symptom is hot spot creation in the end group

– Dynamic load changes 10 times higher

• Some cavities run in this condition

• Some others need lower Eacc by <1MV/m

– No changes of x-rays

– Once hot spot is developed, no correlation with beam

– Recovery

• RF conditioning starting from low repetition rate

• Thermal cycling

• Other degradation/component damage

– Two FPC windows showed leak after errant beam events

• ~10-6 torr l/s leaks, both were replaced with new FPCs at the SNS test facility and reinstalled in the tunnel

– Another cavity is arcing around FPC/end group: turned off for now.

Page 29: SNS Superconducting Linac: Operational experiences and

29 SNS, S-H. Kim, Accelerator Seminar at Jlab 10/8/2015

Hot spot example 1: meta-stable

condition at the same gradient

• Some part in the end group (must be very low field region) must be normal conducting but still operable

• Additional cryogenic load at 2K is about 50W more from one cavity (would be 800W in CW)

JT valve position (10% more: 50-60 W)

Cavity gradient

Coupler flange temperature

(not hottest spot)

Page 30: SNS Superconducting Linac: Operational experiences and

30 SNS, S-H. Kim, Accelerator Seminar at Jlab 10/8/2015

• Reduce gradient during operation by 0.5-1MV/m due to end group quench • Cavity still unstable have to wait 10-15 min. for cool-down • Performance recovered by thermal cycle during long-maintenance period

JT valve position (10% more 50-60 W)

Cavity gradient

Coupler flange temperature

(not hottest spot)

Hot spot example 2: unstable condition

Page 31: SNS Superconducting Linac: Operational experiences and

31 SNS, S-H. Kim, Accelerator Seminar at Jlab 10/8/2015

Plan for performance

Improvement

Page 32: SNS Superconducting Linac: Operational experiences and

32 SNS, S-H. Kim, Accelerator Seminar at Jlab 10/8/2015

In-situ processing in the tunnel

• Develop a cost effective processing method with minimal impact on machine operation

– Goal is 15-20% improvement on average

– In-situ plasma processing R&D

• Preliminary attempts in 2009

• Focused on removing of residual hydro-carbons

• Medium term goal

– Reach 1GeV + energy reserve (Increase high beta cavity gradients by about 2 MV/m in average)

• Long term goal

– 38-mA beam loading with 2nd target station: Need narrower performance scattering Efficient utilization of RF power (ideally constant RF power/cavity is preferred)

– Pertains mostly to medium beta cavities

Page 33: SNS Superconducting Linac: Operational experiences and

33 SNS, S-H. Kim, Accelerator Seminar at Jlab 10/8/2015

In-situ Plasma processing

• Low density reactive plasma at room temperature to clean residual hydrocarbons on RF surfaces

– Demonstration of performance improvement with single cavities in Horizontal Test Apparatus and in offline cryomodule

– Increase of Eacc at 60 Hz after processing: >25 %

– Observed reduced FE, MP, vacuum activities, thermal load in the end group

• Deployment in SNS tunnel planned during shutdown periods starting FY16

Plasma in a

cryomodule !

Plasma in

HTA

Page 34: SNS Superconducting Linac: Operational experiences and

34 SNS, S-H. Kim, Accelerator Seminar at Jlab 10/8/2015

Summary

• The SNS SCL is providing stable operation for the neutron production up to 1.4 MW beam power on target

– Understanding of system as a whole leads to the most efficient and reliable operation

• Causes for performance degradation during operation at SNS are identified

– Continuous development of dedicated diagnostics and protection systems

– Recovery actions including thermal cycling and offline repair are ongoing

• R&D is ongoing to improve the current SRF cavities performance

– Plasma cleaning technique was demonstrated with performance improvement of offline cavities in HTA and cavities in offline cryomodule

– Plan on deploying plasma processing in the linac tunnel in FY16 and FY17

Page 35: SNS Superconducting Linac: Operational experiences and

35 SNS, S-H. Kim, Accelerator Seminar at Jlab 10/8/2015

Backup Slides

Page 36: SNS Superconducting Linac: Operational experiences and

36 SNS, S-H. Kim, Accelerator Seminar at Jlab 10/8/2015

FY15 Operation

Page 37: SNS Superconducting Linac: Operational experiences and

37 SNS, S-H. Kim, Accelerator Seminar at Jlab 10/8/2015

0

5

10

15

20

25

30

35

40

45

50

400 400.05 400.1 400.15 400.2 400.25 400.3 400.35 400.4 400.45

Time (sec)

Te

me

ratu

re (

K)

1 (HOM Ant. Tip)

2 (100 mm)

t1 t2 t4t3

t=t2

t=t3

t=t1

t=t4

2

1

2

1

2

1

2

1

Page 38: SNS Superconducting Linac: Operational experiences and

38 SNS, S-H. Kim, Accelerator Seminar at Jlab 10/8/2015

SNS Beam Power History