socio-economic analyses in perspective: uncertainties and ... · pdf filesocio-economic...

24
Socio-economic analyses in perspective: Uncertainties and bias in decision support Associate Professor, PhD Kim Bang Salling DTU Transport Traffic days in Aalborg 2012 – Special session: “Uncertainties in Transport Project Evaluation (UNITE)”

Upload: vokiet

Post on 05-Feb-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Socio-economic analyses in perspective: Uncertainties and ... · PDF fileSocio-economic analyses in perspective: Uncertainties and bias in decision support ... ”Chunnel” in 1987

Socio-economic analyses in perspective: Uncertainties and bias in decision support

Associate Professor, PhD Kim Bang Salling DTU Transport Traffic days in Aalborg 2012 – Special session: “Uncertainties in Transport Project Evaluation (UNITE)”

Page 2: Socio-economic analyses in perspective: Uncertainties and ... · PDF fileSocio-economic analyses in perspective: Uncertainties and bias in decision support ... ”Chunnel” in 1987

DTU Transport, Technical University of Denmark 2

Project Plan of UNITE

Uncertainties in Transport Project Evaluation (UNITE): the five Work-Packages

(5) Evaluation methodologyWP5 project leader: Steen Leleur (DMG)

(4) Uncertainty calculation in transport modelsWP4 project leader: Otto Anker Nielsen (TMG)

(2) Organizational context of Modelling, an empirical study

WP2 project leader: Petter Næss (AAU)

(3) Uncertainty calculation of cost estimates

WP3 project leader: Bo Friis Nielsen (DTU Informatics)

(1) Systematic biases in transport models (recognized ignorance), an empirical studyWP1 project leader: Petter Næss (AAU)

Page 3: Socio-economic analyses in perspective: Uncertainties and ... · PDF fileSocio-economic analyses in perspective: Uncertainties and bias in decision support ... ”Chunnel” in 1987

DTU Transport, Technical University of Denmark 3

How do we evaluate transport projects?

• Various existing guideline report: –Denmark, Sweden, UK, European Union, ....

• Socio-economic analysis by the use of Cost-Benefit

Analysis (CBA)

• Produces single point estimates such as Net Present Values (NPV), Benefit Cost Ratios (BCR), etc

• However, no common rule have been set in order to acommodate the uncertainties in CBA!

–Recent conducted PhD dissertation proved this point

Page 4: Socio-economic analyses in perspective: Uncertainties and ... · PDF fileSocio-economic analyses in perspective: Uncertainties and bias in decision support ... ”Chunnel” in 1987

DTU Transport, Technical University of Denmark 4

Background & Motivation

• The Manual for socio-economic analysis in the transport sector (2003)

–Unique guidelines for evaluating transport infrastructure projects

–Lack of uncertainty handling –Expected revision 2012-2013

Page 5: Socio-economic analyses in perspective: Uncertainties and ... · PDF fileSocio-economic analyses in perspective: Uncertainties and bias in decision support ... ”Chunnel” in 1987

DTU Transport, Technical University of Denmark 5

How do we evaluate transport projects?

• However, no common rule have been set in order to acommodate the uncertainties in CBA!

–Recent conducted PhD dissertation proved this point

Page 6: Socio-economic analyses in perspective: Uncertainties and ... · PDF fileSocio-economic analyses in perspective: Uncertainties and bias in decision support ... ”Chunnel” in 1987

DTU Transport, Technical University of Denmark 6

The Case Study: HH-Connection • Connecting Denmark with Sweden: Scandinavian link

–Currently, close to the capacity limit on Oresund

HH-Connection (alternatives*)

Description (Alignment of connection)

Cost (million DKK)

Alternative 1 Tunnel for rail (2 tracks) person traffic only 7,700

Alternative 2 Tunnel for rail (1 track) goods traffic only 5,500

Alternative 3 Bridge for road and rail (2x2 lanes & 2 tracks) 11,500

Alternative 4 Bridge for road (2x2 lanes) 6,000

* Larsen, L.A. & Skougaard, B.Z. (2010). Vurdering af alternativer for en fast forbindelse Helsingør-Helsingborg, M.Sc. thesis, Department of Transport, Technical University of Denmark (in Danish)

Page 7: Socio-economic analyses in perspective: Uncertainties and ... · PDF fileSocio-economic analyses in perspective: Uncertainties and bias in decision support ... ”Chunnel” in 1987

DTU Transport, Technical University of Denmark 7

The UNITE-DSS Modelling Framework Todays Outline

Page 8: Socio-economic analyses in perspective: Uncertainties and ... · PDF fileSocio-economic analyses in perspective: Uncertainties and bias in decision support ... ”Chunnel” in 1987

DTU Transport, Technical University of Denmark 8

Results: Cost-Benefit Analysis

• Construction costs – by far the largest contributor of costs

• User Benefits – by far the largest contributor of benefits – Consists of Ticket revenue and time savings – Relies on the prognosis of future number of passengers i.e.

demand forecasts

HH-Connection (alternatives)

Cost (million DKK)

BCR NPV (million DKK)

Alternative 1 7,700 1.50 5,530

Alternative 2 5,500 0.16 -6,640

Alternative 3 11,500 2.71 28,240

Alternative 4 6,000 3.08 17,860

Page 9: Socio-economic analyses in perspective: Uncertainties and ... · PDF fileSocio-economic analyses in perspective: Uncertainties and bias in decision support ... ”Chunnel” in 1987

DTU Transport, Technical University of Denmark 9

Are we telling the truth?!?!

Construction cost overruns

0%

200%

400%

600%

800%

1000%

1200%

1400%

1600%

1800%

2000%

Suez

Can

al

Sydn

eyO

pera

Hou

se

Con

cord

eSu

pers

onic

Aero

plan

eBo

ston

'sAr

tery

/Tun

nel

Proj

ect,

USA

Hum

ber

Brid

ge, U

K

Bost

on-

Was

hing

ton-

New

Yor

kG

reat

Bel

tR

ail T

unne

l,D

KA6

Mot

orw

ayC

hape

l-en-

le-

Frith

/Wha

ley

Shin

kans

enJo

etsu

Rai

llin

e, J

apan

Was

hing

ton

met

ro, U

SA

Cha

nnel

Tunn

el, U

K &

Fran

ceKa

rlsru

he-

Bret

ten

light

rail,

Ger

man

resu

ndAc

cess

link

s,D

K &

Swed

enM

exic

o ci

tym

etro

line

,M

exic

oPa

ris-A

uber

-N

ante

rre

rail

line,

Fra

nce

Cos

t Ove

rrun

s (%

)

Q: Have we learned anything from history?

”Chunnel” in 1987 £2,600 million (’85 prices) Completion 1994 £4,650 million (’85 prices) Total cost overrun of approx. 80%

”Øresund access link” in 1991 3.2 billion DKK (’90 prices) Completion 1998 5.4 billion DKK (’90 prices) Total cost overrun of approx. 68%

Page 10: Socio-economic analyses in perspective: Uncertainties and ... · PDF fileSocio-economic analyses in perspective: Uncertainties and bias in decision support ... ”Chunnel” in 1987

DTU Transport, Technical University of Denmark 10

Theoretical anchoring The Transport Planning Phase: Adapted from the British Department for Transport (DfT) (2004)

Reference Class Forecasting: Optimism Bias

Inside View Outside View

”Uniqueness” of Project

”The Planning Fallacy”

Reference Class Forecasting

Forecasting of particular projects

Forecasting from a group of projects

(1) Identification of relevant reference

classes

(2) Establishing probability distribution

(3) Placing and comparing the

project

Optimism Bias UpliftsCurrent Situation

Page 11: Socio-economic analyses in perspective: Uncertainties and ... · PDF fileSocio-economic analyses in perspective: Uncertainties and bias in decision support ... ”Chunnel” in 1987

DTU Transport, Technical University of Denmark 11

Optimism Bias and uplifts

• Deriving uplifts is highly dependet on large data-sets –Flyvbjerg from (AAU) has since 2003 developed a large

database –Unfortunately, it looks upon mega-projects

• The basis is Reference Class Forecasting i.e. statistical measurements on various project pools

Source: Flyvbjerg and COWI (2004)

Page 12: Socio-economic analyses in perspective: Uncertainties and ... · PDF fileSocio-economic analyses in perspective: Uncertainties and bias in decision support ... ”Chunnel” in 1987

DTU Transport, Technical University of Denmark 12

Results : Optimism Bias Uplifts

• The BCR are lower, however, still point estimates towards DM –Moreover an advanced form of sensitivity analysis

• Imply to introduce risk analysis and Monte Carlo simulation

HH-Connection (alternatives)

Cost (uplifted) (million DKK)

BCR (orig.) (from slide 8)

BCR (uplifts): 80% uplift

Alternative 1 12,090 1.50 0.97

Alternative 2 8,640 0.16 0.10

Alternative 3 15,180 2.71 1.75

Alternative 4 7,920 3.08 1.98

Page 13: Socio-economic analyses in perspective: Uncertainties and ... · PDF fileSocio-economic analyses in perspective: Uncertainties and bias in decision support ... ”Chunnel” in 1987

DTU Transport, Technical University of Denmark 13

The UNITE Project Database (UPD)

• The convention used is as follows: ( )( )

forecasted

forecastedactual

XXX

U100×−

=

Over estimation of Demand

Page 14: Socio-economic analyses in perspective: Uncertainties and ... · PDF fileSocio-economic analyses in perspective: Uncertainties and bias in decision support ... ”Chunnel” in 1987

DTU Transport, Technical University of Denmark 14

• Demand forecasts (user benefits) are derived: – U is percent inaccuracy, – Xa is the actual traffic after the project is opened – Xf is the forecasted traffic on the decision to build

• Combination of two database samples

0

5

10

15

20

25

30

(-12

0;-1

00)

(-10

0;-8

0)

(-80

;-60)

(-60

;-40)

(-40

;-20)

(-20

;0)

(0;2

0)

(20;

40)

(40;

60)

(60;

80)

(80;

100)

(100

;120

)

(120

;140

)

(140

;160

)

(160

;180

)

(180

;200

)

(200

;220

)

(220

;240

)

Freq

uenc

y of

occ

uren

ce (%

)

Inaccuracies in demand forecasts (%)

Inaccuracies in demand forecasts (road projects)

Salling et al. (2012)

Flyvbjerg et al. (2003)

Nicolaisen et al. (2012)

Page 15: Socio-economic analyses in perspective: Uncertainties and ... · PDF fileSocio-economic analyses in perspective: Uncertainties and bias in decision support ... ”Chunnel” in 1987

DTU Transport, Technical University of Denmark 15

The UNITE Project Database (UPD)

• The convention used is as follows: ( )( )

forecasted

forecastedactual

XXX

U100×−

=

Under estimation of costs

Page 16: Socio-economic analyses in perspective: Uncertainties and ... · PDF fileSocio-economic analyses in perspective: Uncertainties and bias in decision support ... ”Chunnel” in 1987

DTU Transport, Technical University of Denmark 16

• Construction costs bias derived similarly: – U is percent inaccuracy, – Xa is the actual traffic after the project is opened – Xf is the forecasted traffic on the decision to build

• Combination of two database samples

0

10

20

30

40

50

(-10

0;-8

0)

(-80

;-60)

(-60

;-40)

(-40

;-20)

(-20

;0)

(0;2

0)

(20;

40)

(40;

60)

(60;

80)

(80;

100)

(100

;120

)

(120

;140

)

(140

;160

)

(160

;180

)

(180

;200

)

(200

;220

)

(220

;240

)

Freq

uenc

y of

occ

uren

ce (%

)

Inaccuracies in construction costs (%)

Inaccuracies in construction cost (road projects)

Salling et al (2012)

Flyvbjerg et al. (2003)

Nicolaisen et al. (2012)

Page 17: Socio-economic analyses in perspective: Uncertainties and ... · PDF fileSocio-economic analyses in perspective: Uncertainties and bias in decision support ... ”Chunnel” in 1987

DTU Transport, Technical University of Denmark 17

Results (RCF): Monte Carlo simulation

Page 18: Socio-economic analyses in perspective: Uncertainties and ... · PDF fileSocio-economic analyses in perspective: Uncertainties and bias in decision support ... ”Chunnel” in 1987

DTU Transport, Technical University of Denmark 18

Conclusions

• Feasibility risk assessment can be carried out by using historical experience stemming from RCF in order to obtain interval results

• An important aspect in RCF and UNITE is to set and validate input parameters. Hence, empirical data enter the assessment.

• The RCF approach has been illustrated on a case example concerning the construction of a new fixed link, the HH-Connection, between Denmark and Sweden.

• Clearly vital to include uncertainties within socio-economic analyses in order to validate results

Page 19: Socio-economic analyses in perspective: Uncertainties and ... · PDF fileSocio-economic analyses in perspective: Uncertainties and bias in decision support ... ”Chunnel” in 1987

DTU Transport, Technical University of Denmark 19

Perspectives

• Recovering of further data (UPD) with regard to both the demand forecast uncertainty as well as the construction costs through large-scale research study

• Producing so-called decision conferences in order to achieve better input parameters to the UNITE-DSS Model combined with overconfidence theory allows for expert opinions (SIMSIGHT)

• More info on UNITE can be found: (www.transport.dtu.dk/unite)

• An international conference on the topic is scheduled in September 2013 – a specific call will be posted in the upcoming month.

Page 20: Socio-economic analyses in perspective: Uncertainties and ... · PDF fileSocio-economic analyses in perspective: Uncertainties and bias in decision support ... ”Chunnel” in 1987

DTU Transport, Technical University of Denmark

SIMSIGHT: Decision Conferencing (DC)

20

• Producing so-called decision conferences in order to achieve better input parameters to the UNITE-DSS Model

• Enables to include Stakeholders and Decision-makers in an early stage, i.e. to include experts opinion on MIN and MAX values as entries to the Monte Carlo simulation

Page 21: Socio-economic analyses in perspective: Uncertainties and ... · PDF fileSocio-economic analyses in perspective: Uncertainties and bias in decision support ... ”Chunnel” in 1987

DTU Transport, Technical University of Denmark 21

Results from DC and RSF

Page 22: Socio-economic analyses in perspective: Uncertainties and ... · PDF fileSocio-economic analyses in perspective: Uncertainties and bias in decision support ... ”Chunnel” in 1987

DTU Transport, Technical University of Denmark

SIMSIGHT: Overconfidence

22

Page 23: Socio-economic analyses in perspective: Uncertainties and ... · PDF fileSocio-economic analyses in perspective: Uncertainties and bias in decision support ... ”Chunnel” in 1987

DTU Transport, Technical University of Denmark 23

Perspectives

• Recovering of further data (UPD) with regard to both the demand forecast uncertainty as well as the construction costs through large-scale research study

• Producing so-called decision conferences in order to achieve better input parameters to the UNITE-DSS Model combined with overconfidence theory allows for expert opinions (SIMSIGHT)

• More info on UNITE can be found: (www.transport.dtu.dk/unite)

• An international conference on the topic is scheduled in September 2013 – a specific call will be posted in the upcoming month.

Page 24: Socio-economic analyses in perspective: Uncertainties and ... · PDF fileSocio-economic analyses in perspective: Uncertainties and bias in decision support ... ”Chunnel” in 1987

DTU Transport, Technical University of Denmark 24

Thank you for your attention!

Affiliation:

Associate Professor, PhD Kim Bang Salling

Department of Transport Technical University of Denmark

[email protected]