south central district engineer's reportaztransportationboard.gov › ... › presentations ›...
TRANSCRIPT
![Page 1: South Central District Engineer's Reportaztransportationboard.gov › ... › Presentations › 2016... · Presentation by Rod Lane, P.E. South Central District Engineer . March 18,](https://reader034.vdocuments.net/reader034/viewer/2022042401/5f101f627e708231d4478eda/html5/thumbnails/1.jpg)
1
Presentation by Rod Lane, P.E. South Central District Engineer
March 18, 2016
WELCOME TO THE SOUTH CENTRAL DISTRICT
Transportation Board Presentation
![Page 2: South Central District Engineer's Reportaztransportationboard.gov › ... › Presentations › 2016... · Presentation by Rod Lane, P.E. South Central District Engineer . March 18,](https://reader034.vdocuments.net/reader034/viewer/2022042401/5f101f627e708231d4478eda/html5/thumbnails/2.jpg)
2
SR77: Tangerine to Pinal County line
• Contractor: Granite Construction Company • Contract Amount: $33.8M • Approx. 2 year contract to widen SR77 to 6 lane divided
section from Tangerine Rd to Pinal County Line • Expected completion Spring 2016
![Page 3: South Central District Engineer's Reportaztransportationboard.gov › ... › Presentations › 2016... · Presentation by Rod Lane, P.E. South Central District Engineer . March 18,](https://reader034.vdocuments.net/reader034/viewer/2022042401/5f101f627e708231d4478eda/html5/thumbnails/3.jpg)
3
I-10: Quad Project (SR83 to SR 90)
• Contractor: FNF Construction, Inc. • Contract Amount: $15.2M • 3 Pavement Preservation Projects and a superstructure
replacement over Davidson Canyon. • Completion expected Summer 2016
![Page 4: South Central District Engineer's Reportaztransportationboard.gov › ... › Presentations › 2016... · Presentation by Rod Lane, P.E. South Central District Engineer . March 18,](https://reader034.vdocuments.net/reader034/viewer/2022042401/5f101f627e708231d4478eda/html5/thumbnails/4.jpg)
4
I-19: Ajo TI (Phase I)
• Contractor: Ames Construction Inc. • Contract Amount: $39.9M • Replace existing Interchange with S.P.U.I. • Expected completion Fall 2017
![Page 5: South Central District Engineer's Reportaztransportationboard.gov › ... › Presentations › 2016... · Presentation by Rod Lane, P.E. South Central District Engineer . March 18,](https://reader034.vdocuments.net/reader034/viewer/2022042401/5f101f627e708231d4478eda/html5/thumbnails/5.jpg)
5
SR 86: Valencia to Kinney
• Contractor: The Ashton Company, Inc. • Contract Amount: $40.9M • Approx. 2 year contract to widen SR86 to 4 lane divided section from
Kinney to Valencia. • Expected completion Early 2018
![Page 6: South Central District Engineer's Reportaztransportationboard.gov › ... › Presentations › 2016... · Presentation by Rod Lane, P.E. South Central District Engineer . March 18,](https://reader034.vdocuments.net/reader034/viewer/2022042401/5f101f627e708231d4478eda/html5/thumbnails/6.jpg)
6
FY 16 I-10: Kino Parkway TI Bridge Deck Rehab $ 2 M
FY 16 I-10: Ina Rd TI, Phase I Interchange Reconstruction (CMAR) $ 34 M
Upcoming Construction within P.A.G.
![Page 7: South Central District Engineer's Reportaztransportationboard.gov › ... › Presentations › 2016... · Presentation by Rod Lane, P.E. South Central District Engineer . March 18,](https://reader034.vdocuments.net/reader034/viewer/2022042401/5f101f627e708231d4478eda/html5/thumbnails/7.jpg)
7
Ina Road Traffic Interchange
• CMAR project • Designer: Psomas • Contractor: Sundt/Kiewit JV • Expecting Phase I to start early this summer, Phase 2 to start late fall. • The interchange is expected to be closed for 2 years.
![Page 8: South Central District Engineer's Reportaztransportationboard.gov › ... › Presentations › 2016... · Presentation by Rod Lane, P.E. South Central District Engineer . March 18,](https://reader034.vdocuments.net/reader034/viewer/2022042401/5f101f627e708231d4478eda/html5/thumbnails/8.jpg)
8
Interstate 10 (Tentative 5 yr plan within P.A.G.)
FY 17 I-10: Ina Rd TI, Phase II Interchange Reconstruction (CMAR) $ 57 M
FY 17 I-10: Craycroft & Wilmot Rd TI Bridge Deck Rehab $ 9 M
FY 17 I-10 TI’s (Wilmot, Kolb, Rita, Vail) Traffic Signalization $ 2 M
FY 17 I-10: Houghton Rd TI Traffic Signalization $ 400 K
FY 18 I-10: Ruthrauff Rd TI Interchange Reconstruction $ 87 M
FY 18 I-10: Ajo Way Phase II Interchange Reconstruction $ 30 M
![Page 9: South Central District Engineer's Reportaztransportationboard.gov › ... › Presentations › 2016... · Presentation by Rod Lane, P.E. South Central District Engineer . March 18,](https://reader034.vdocuments.net/reader034/viewer/2022042401/5f101f627e708231d4478eda/html5/thumbnails/9.jpg)
9
FY 19 I-10: Ruthrauff Rd TI Interchange Reconstruction $ 87 M
FY 19 I-10: Wash Bridge #646 @ MP 277 Scour Retrofit $ 350 K
FY 19 I-10: Vail Rd & Mtn View Bridge Deck Rehab $ 5 M
FY 19 I-10: Houghton Rd TI Interchange Reconstruction $ 30 M
FY 20 I-10: SR 587 to SR 387 Pavement Preservation $ 23 M
FY 20 I-10: Country Club Rd TI Interchange Reconstruction $ 50 M
FY 20 I-10: Houghton Road TI Interchange Reconstruction $ 40 M
FY 21 I-10: Kino Pkwy TI Interchange Reconstruction $ 32 M
Interstate 10 (Tentative 5 yr plan within P.A.G.)
![Page 10: South Central District Engineer's Reportaztransportationboard.gov › ... › Presentations › 2016... · Presentation by Rod Lane, P.E. South Central District Engineer . March 18,](https://reader034.vdocuments.net/reader034/viewer/2022042401/5f101f627e708231d4478eda/html5/thumbnails/10.jpg)
10
FY 17 I-19: Pima Mine Rd TI Bridge Deck Rehab $ 6 M
FY 18 I-19: Ajo Way TI (Phase 2) Roadway Capacity $ 23 M
FY 18 I-19: Canoa Ranch RA– Duval Mine Rd TI Pavement Preservation $ 13 M
Interstate 19 (Tentative 5 yr plan within P.A.G.)
![Page 11: South Central District Engineer's Reportaztransportationboard.gov › ... › Presentations › 2016... · Presentation by Rod Lane, P.E. South Central District Engineer . March 18,](https://reader034.vdocuments.net/reader034/viewer/2022042401/5f101f627e708231d4478eda/html5/thumbnails/11.jpg)
11
Pima County (Tentative 5 yr plan)
FY 17 SR 86: Fuller Rd – Valencia Rd Pavement Preservation $ 4.6 M
FY 18 SR 86: Fresnal to MP 123.6 Shoulder Widening $ 10 M
FY 18 SR 86: MP 82 – 102 Fence Replacement $ 1.5 M
FY 18 SR 86: MP 148 – 159 Pavement Preservation $ 9 M
FY 19 SR 77: River Road to Suffolk Pedestrian Sidewalks and Lighting $ 12 M
FY 20 SR 77: Genematas – Calle Concordia Pavement Preservation $ 11 M