NATIONAL IRANIAN OIL COMPANYSOUTH PARS GAS FIELD
DEVELOPMENTPHASE 12
160417843.doc ONSHORE FACILITIES Page 1 of 23
PROJECT PLANNING SCHEDULINGAND CONTROL SYSTEM
PROCEDURE
D4
D3
D2D1 26/May/2010 FOR APPROVAL FEC SUA
D0 24/Feb/2010 FOR APPROVAL FEC SUA
Rev Date Purpose of Issue Prepd CheckdTNDG PPL
Approved
This document is the property of N.I.O.C.. Any unauthorised attempt to reproduce it, in any form, is strictly prohibited.
CONSORTIUM DOC. NO. 3546-PZ-PC-00000007 Filename: 160417843.doc
-
7/27/2019 SP12-2Y3-PC-PP-993-007
2/21
PROJECT PLANNING SCHEDULING Document No: 160417843.doc
AND CONTROL SYSTEM PROCEDURE Date: 26th May 2010
Page: 2 of 23
__________________________________________________________________________________________
TABULATION OF REVISED PAGES
This document is the property of N.I.O.C.. Any unauthorised attempt to reproduce it, in any form, is strictly prohibited.
CONSORTIUM DOC. NO. 3546-PZ-PC-00000007 Filename: 160417843.doc
SHEET Revision D SHEET Revision D0 1 2 3 4 5 6 7 0 1 2 3 4 5 6 7
1 X 51
2 X 52
3 X 534 X 54
5 X 55
6 X 56
7 X 57
8 X 58
9 X 59
10 X 60
11 X 61
12 X 62
13 X 63
14 X 64
15 X 65
16 X 66
17 X 67
18 X 68
19 X 69
20 X 70
21 X 71
22 72
23 73
24 74
25 75
26 76
27 77
28 78
29 79
30 80
31 81
32 82
33 83
34 84
35 85
36 86
37 87
38 88
39 89
40 90
41 91
42 92
43 93
44 9445 95
46 96
47 97
48 98
49 99
50 100
-
7/27/2019 SP12-2Y3-PC-PP-993-007
3/21
PROJECT PLANNING SCHEDULING Document No: 160417843.doc
AND CONTROL SYSTEM PROCEDURE Date: 26th May 2010
Page: 3 of 23
__________________________________________________________________________________________
TABLE OF CONTENTS
1 SCOPE...............................................................................................................................4
2. DEFINITIONS AND ABBREVIATIONS.............................................................................4
3 ORGANIZATION ................................................................................................................5
4 DUTIES AND RESPONSIBILITIES.....................................................................................6
5 PLANNING HIERARCHY....................................................................................................7
5.1 Level 1 Project Schedule Summary (PSS):................................................................85.2 Level 2 Project Master Schedule PMS....................................................................95.3 Level 3 Project Control Schedule PCS.....................................................................105.4 Level 4 Detailed Database and Control Documents.................................................12
6 PROGRESS MEASUREMENT CRITERIA........................................................................13
6.1 Engineering Progress Measurement...........................................................................136.2 Procurement Progress Measurement.........................................................................14
6.3 Construction, Pre-Commissioning and Commissioningprogress measurement.....................................................................................................14
7 PROGRESS CURVES AND MANPOWER HISTOGRAMS..............................................15
8 DOCUMENT MANAGEMENT SYSTEM...........................................................................16
8.1 CONSORTIUM Engineering Deliverables Management System (EDMS)...................168.2 Transmittals................................................................................................................178.3 Master Document Register (MDR)..............................................................................18
9 PROJECT CONTROL TOOLS..........................................................................................19
10 PROJECT REPORTING.................................................................................................21
This document is the property of N.I.O.C.. Any unauthorised attempt to reproduce it, in any form, is strictly prohibited.
CONSORTIUM DOC. NO. 3546-PZ-PC-00000007 Filename: 160417843.doc
-
7/27/2019 SP12-2Y3-PC-PP-993-007
4/21
PROJECT PLANNING SCHEDULING Document No: 160417843.doc
AND CONTROL SYSTEM PROCEDURE Date: 26th May 2010
Page: 4 of 23
__________________________________________________________________________________________
1 SCOPE
The purpose of this document is to illustrate planning, scheduling and control tasks tobe implemented during the execution of South Pars Gas Field Development Phase 12,
Onshore Facilities, Gas-EPC3.
2.DEFINITIONS AND ABBREVIATIONS
All the expressions appearing in capital letters, shall have the meaning set forth inAPPENDIX B General Conditions of CONTRACT, article 2 Definitions andSignificance of Expressions.
For the purpose of this procedure, the following definitions/abbreviations, not consideredunder the relevant article, shall apply:
COMPANY means PETROPARS Ltd.
CONSORTIUM means the association of Tecnimont (TCM), Nargan Engineers &
Constructors (NEC), Dor Riz Engineering Company (DR) and Gamma Company(GM) for the performance of the WORK, acting as CONTRACTOR
MEMBERS mean TCM, NEC, DR, GM.
PROJECT DIRECTOR (PD) means the person appointed by CONSORTIUM as
CONTRACTOR REPRESENTATIVE in all matters related to the performance of theCONTRACT.
CMM means CoMmissioning Manager
CSC means Construction Standard Cycle
EDMS means Engineering Deliverables Management System
EPMS means Engineering Progress Measurement System
EPSC means Engineering and Procurement Standard Cycle
PCM means Project Control Manager
PEM means Project Engineering Manager
PEP means Project Execution Plan
PMMS&R means Project Material Management System & Reporting
PPM means Project Procurement Manager
PL means Discipline Project Leader
STM means SiTe Manager
WBS means Work Breakdown Structure
This document is the property of N.I.O.C.. Any unauthorised attempt to reproduce it, in any form, is strictly prohibited.
CONSORTIUM DOC. NO. 3546-PZ-PC-00000007 Filename: 160417843.doc
-
7/27/2019 SP12-2Y3-PC-PP-993-007
5/21
PROJECT PLANNING SCHEDULING Document No: 160417843.doc
AND CONTROL SYSTEM PROCEDURE Date: 26th May 2010
Page: 5 of 23
__________________________________________________________________________________________
3 ORGANIZATION
A qualified and experienced Project Control Manager (PCM) is assigned to the Projecton a full-time basis and responds to PROJECT DIRECTOR within CONSORTIUMProject Management Team.
He is fully supported and assisted by experienced team within each MEMBERorganization at Operating Centre, which operate all project controls activities, and eachled by dedicated Project Control Manager, on its turn responding to the respectiveProject Manager and assisted by Planning and Cost Control Engineers as required bythe size of the Project.
A typical Project Control Organization (Home and Site Offices) are shown here below.
* IN HOME OFFICE DURING EARLY PROJECT PHASE
TYPICAL PROJECT CONTROL ORGANIZATION FOR LARGE PROJECTS (HOME OFFICE)
Project Director /
Project Manager
Project Control Manager
Project Planner Engineer Project Cost Engineer
Project Planner Assistant Project Cost Assistant
Document Control
CoordinatorField Control Coordinator*
Document Control
Assistant Field Planner Engineer*
Field Cost Engineer*
TYPICAL PROJECT CONTROL ORGANIZATION FOR LARGE PROJECTS (SITE OFFICE)
Field Control Coordinator
Field Planner Engineer Field Cost Engineer
Field Planner Assistant Field Cost Assistant
Site Manager /
Project ManagerProject Control Manager
This document is the property of N.I.O.C.. Any unauthorised attempt to reproduce it, in any form, is strictly prohibited.
CONSORTIUM DOC. NO. 3546-PZ-PC-00000007 Filename: 160417843.doc
-
7/27/2019 SP12-2Y3-PC-PP-993-007
6/21
PROJECT PLANNING SCHEDULING Document No: 160417843.doc
AND CONTROL SYSTEM PROCEDURE Date: 26th May 2010
Page: 6 of 23
__________________________________________________________________________________________
4 DUTIES AND RESPONSIBILITIES
CONSORTIUM PCM is fully responsible of timely and effective coordination and
supervision of Project Controls activities of Operating teams and of interfacing Companyas required by the project and CONTRACT.
PROJECT DIRECTOR retains the prime responsibility for the Project (engineering,procurement, construction and pre-commissioning, Commissioning & Start up, GeneralServices).
Under PCM coordination and supervision, CONSORTIUM Project Control Team isresponsible for:
Ensuring that adopted Project Control Procedures fully comply with CONTRACT
requirements and CONSORTIUM coordination procedures.
Ensuring set-up and maintenance of project control tools to be adopted for theproject;
Ensuring the preparation of project schedules at the proper level of details as per
procedures and maintain the same for the whole duration of the project;
Track the critical path to ensure about the completion date of the Project;
Ensuring the assessment of physical progress detecting any deviations from the
plans;
Supporting Management in evaluating trends, suggesting corrective actions
when necessary;
Coordinating and collecting data to ensure the preparation of the weekly/monthlyprogress reports;
The Project Control Department within each Partners Corporate provides all necessaryresources to the Project Control Teams, in consideration of the needs highlighted by thePCM and supports the PCM in performing supervision activities to ensure uniformity andapplication of the latest techniques in the project control.
This document is the property of N.I.O.C.. Any unauthorised attempt to reproduce it, in any form, is strictly prohibited.
CONSORTIUM DOC. NO. 3546-PZ-PC-00000007 Filename: 160417843.doc
-
7/27/2019 SP12-2Y3-PC-PP-993-007
7/21
PROJECT PLANNING SCHEDULING Document No: 160417843.doc
AND CONTROL SYSTEM PROCEDURE Date: 26th May 2010
Page: 7 of 23
__________________________________________________________________________________________
5 PLANNING HIERARCHY
The standard planning and scheduling hierarchy, developed in tune with Project WBS,consists of the following levels:
Level 1
Level 2
Level 3
Level 4
Engineering
-Piping
P.& I Diagrams
Layouts
3D Modeling
Isometrics
MTO
Construction
-Civil works Area AA
Foundations
-Civil works Area BB
Foundations
Engineering
-Piping
-P.& I Diagrams
Wet End
Extrusion
Cooling Towers
Flare
Construction
-Civil works Area AA
-Foundations
Loop Reactor
Pumps
Steel Structures
Vessels
Engineering
Procurement
Construction
Commissioning
Engineering
-Process
-Piping
-Civil
Construction
-Civil works
-Mechanical Works
Pla
nnin
gPha
se=Top
-Dow
n
Control
Pha
se=Bottom
-Up
The standard planning and scheduling hierarchy, developed in tune with Project WBS,foresees the following levels:
Level 1 Project Schedule Summary (PSS)
Level 2 Project Master Schedule (PMS) Level 3 Project Control Schedule (PCS)
Level 4 Detailed Database and Control Documents
This document is the property of N.I.O.C.. Any unauthorised attempt to reproduce it, in any form, is strictly prohibited.
CONSORTIUM DOC. NO. 3546-PZ-PC-00000007 Filename: 160417843.doc
-
7/27/2019 SP12-2Y3-PC-PP-993-007
8/21
PROJECT PLANNING SCHEDULING Document No: 160417843.doc
AND CONTROL SYSTEM PROCEDURE Date: 26th May 2010
Page: 8 of 23
__________________________________________________________________________________________
5.1 Level 1 Project Schedule Summary (PSS):
This schedule illustrates how the completion date of the work can be achieved andcontractual milestones met.
The main task of this level is to identify the main Project targets (e.g. Phases etc.) toestablish the constraints for the lower level of Planning and Control.
The outputs of Level 1 consist of the following documents:
The Overall Project Time Schedule (relating to level 2 of agreed WBS);
Progress Curves for Engineering, Procurement, Construction & Pre-
commissioning, Commissioning phases & General Services;
Manpower histograms for Engineering, Construction & Pre-commissioning,
Commissioning & General Services;
The Overall Project Time Schedule, issued in a bar-chart format, includes the aboveitems which Progress Curves and Manpower Histograms would be prepared for.
For PSS the status of Level 2 of WBS is adequate, which contains Detail Engineering,Procurement Engineering, Final Documentation Sub-Phase and also the status of MainEquipment and Bulk Material, Construction Works by Trains, Commissioning and Startup, General Services and Facilities, main Project and Interface Milestone with EPC1 andEPC2 CONTRACTORS.
Duration of Engineering Phase.
Duration of Material Supply Cycle for Company Items
Duration of Material Supply Cycle for Main Items
Duration of Material Supply Cycle for Bulk Materials
General Services duration
Duration of Construction and Pre-Commissioning works by trains
Duration of Commissioning and Start-up phase by trains
Main Project and Interface Milestones
The content of Level 1 schedule is based on the information available for the project andis supported by statistical references as far as the curves and histograms is concerned.
Subsequently, the content of Level 1 Planning is verified and reconciled through a roll-upof Level 2 planning as soon as available.
The control phase is managed through a bottom-up aggregation from Level 2.
This document is the property of N.I.O.C.. Any unauthorised attempt to reproduce it, in any form, is strictly prohibited.
CONSORTIUM DOC. NO. 3546-PZ-PC-00000007 Filename: 160417843.doc
-
7/27/2019 SP12-2Y3-PC-PP-993-007
9/21
PROJECT PLANNING SCHEDULING Document No: 160417843.doc
AND CONTROL SYSTEM PROCEDURE Date: 26th May 2010
Page: 9 of 23
__________________________________________________________________________________________
5.2 Level 2 Project Master Schedule PMS
The Level 2 is usually an expansion of Level 1 Schedule to a level of detail necessary,within the main elements of WBS, to highlight all major Project Milestones, and providesufficient information to define the implementation strategies to achieve Targets andidentify the constraints for the lower level of Planning and Control.
The Level 2 Planning foresees the following documents:
Project Time Schedule
Progress Curves for each Discipline (Engineering, Procurement, Construction)
Progress Curves for Procurement Itemized and Procurement Bulk Materials
Construction Progress Curves for each train and work package
Manpower histograms for each discipline
The Project Time Schedule, issued in a bar-chart format, generally shows:
Duration of Engineering, Procurement and Construction by Discipline
Identification of interfaces and timing for engineering and procurement activities
to define the tasks of the various disciplines and assign the responsibilities.
Duration of Material Supply Cycle for each Discipline
Temporary Facilities installation and Camp Preparation duration
Duration of Construction and Pre-Commissioning works by Work Package
Duration of Commissioning and Start-up phase for each system Project Milestones in detail
The content of Level 2 schedule is based on the information available for the project andis supported by statistical references as far as the curves, histograms and cash flowprofiles is concerned.
Subsequently, the content of Level 2 Planning is verified and reconciled through a roll-upof Level 3 planning as soon as available.
The control phase is managed through a bottom-up aggregation from Level 3.
This document is the property of N.I.O.C.. Any unauthorised attempt to reproduce it, in any form, is strictly prohibited.
CONSORTIUM DOC. NO. 3546-PZ-PC-00000007 Filename: 160417843.doc
-
7/27/2019 SP12-2Y3-PC-PP-993-007
10/21
PROJECT PLANNING SCHEDULING Document No: 160417843.doc
AND CONTROL SYSTEM PROCEDURE Date: 26th May 2010
Page: 10 of 23
__________________________________________________________________________________________
5.3 Level 3 Project Control Schedule PCS
The Level 3 Schedule is prepared as an integrated critical path network showing theactivities and the interfaces between Engineering, Procurement Construction andCommissioning phases.
Work schedules for each phase of the Work show the time required to complete theWork. This Level 3 Schedule is to be prepared using a suitable computerized logicnetworking program to identify the critical and sub-critical paths linked to the CompletionDate. Normally the Level 3 Project Schedule consists of a Logic Network analysisthrough Primavera for Enterprise and the outputs are presented in a bar-chart formatevidencing duration, criticality floats and logic sequence of the involved activities.
The network must be in sufficient detail to identify all major activities and constraintsalong the critical and sub-critical.
It is organized in accordance with the agreed WBS and shows Activities as appropriate
and embraces the total life and work scope of the Project to allow the project monitoringsystem based on a defined hierarchy of control information in respect of time andresources (Phase wise / Discipline wise etc.).
The Project Time Schedule at Level 3, based on the established WBS and following theexecution strategy highlighted in the Project Execution Plan, normally is produced basedon:
An extent of basic/FEED and endorsement for the existing basic/FEED
A number of relationships around 2-3 times the activities
A network of activities and relationships to be defined in order to optimize and
ensure and properly network analysis A maximized number of finish/start relationships to ensure meaningful float
calculation in time analysis
Intermediate Project Targets
List of pre-awarded Purchase orders
List of materials that will be purchased by lots
List of critical items, as identified in the proposal schedule and confirmed by early
evaluation at project start-up.
Client approved cycles Purchase Orders for itemized and bulk materials
Average time of transportation (from final inspection to arrival at site)
Procurement strategy for bulk materials
Split of Scope of Works between the involved Parties, evidencing the relevant
responsibilities
Assignment and leveling of manpower resource at discipline level
Any other useful information to qualify the schedule
The Level 3 Planning and Control represents the lowest level of breakdown where theProject has seen as a whole.
This document is the property of N.I.O.C.. Any unauthorised attempt to reproduce it, in any form, is strictly prohibited.
CONSORTIUM DOC. NO. 3546-PZ-PC-00000007 Filename: 160417843.doc
-
7/27/2019 SP12-2Y3-PC-PP-993-007
11/21
-
7/27/2019 SP12-2Y3-PC-PP-993-007
12/21
PROJECT PLANNING SCHEDULING Document No: 160417843.doc
AND CONTROL SYSTEM PROCEDURE Date: 26th May 2010
Page: 12 of 23
__________________________________________________________________________________________
5.4 Level 4 Detailed Database and Control Documents
Level 4 Detailed Schedule is based on the control documents (deliverables list).Thesedocuments and their data base shall describe in detail the scope of work in terms ofquantity and schedule.
The Level-4 schedule is the principle control tool, that provides the basis for thePrimavera Level-3 network analysis and the progress measurement.
The Level-4 detailed database includes:
Design drawings and documentation indices
Vendor Documents index
Requisition Index
Request for quotation and Receipt of quotations list
Technical bid evaluations index Purchase order Index
Vendor manufacturing data and schedule
Materials ex-work delivery schedule
Materials site receipt schedule
Construction activity schedule
Commissioning sub-system
Any other specific items requested by the Project
This document is the property of N.I.O.C.. Any unauthorised attempt to reproduce it, in any form, is strictly prohibited.
CONSORTIUM DOC. NO. 3546-PZ-PC-00000007 Filename: 160417843.doc
-
7/27/2019 SP12-2Y3-PC-PP-993-007
13/21
PROJECT PLANNING SCHEDULING Document No: 160417843.doc
AND CONTROL SYSTEM PROCEDURE Date: 26th May 2010
Page: 13 of 23
__________________________________________________________________________________________
6 PROGRESS MEASUREMENT CRITERIA
The Progress Measurement system is based on the following criteria:
Progress is calculated and reported at project level by means of man-hours related tothe physical work of each activity. The physical progress is measured and reported foreach activity on the basis of physical work performance. Physical work performance ismeasured through achievement of specific milestones representing the key stages of thework process for the activity as per Level 4 breakdown.
6.1 Engineering Progress Measurement
The relevant activities are planned and controlled within the timeframe allowed by Level3 Schedules.
The WBS is codified according to a downwards "father-son" relationship carried out levelby level. This structure allows for easy aggregation at all levels of any work unit includedin the WBS, from activity Level to overall CONTRACT level.
This structure shall apply to all planning and progress reporting documents.
Considering the weight factors at the various levels it is possible to aggregate scheduledand actual progress starting from Lev. 4 (i.e. deliverables) to Lev. 0 (overall project). Asan example for the Engineering activities actual progress, the formulas are:
a) Progress Aggregation from Lev. 4 to Lev. 3(EA)3 = S D4 (WD)4Where:(EA)3 is the actual progress of Lev. 3 elementary engineering activityD4 is the actual progress of the deliverables to be produced by
(EA)3 activity(WD)4 are the weight factors of each D4 deliverable related to (EA)3
elementary activity
b) Progress Aggregation from Lev. 3 to Lev. 2(PLA)2 = S (EA)3 (WEA)3Where:(PLA)2 is the actual progress of Lev. 2 planning group(EA)3 is the actual progress of Lev. 3 elementary engineering activity
relevant to EMC calculated as per point a) above(WEA)3 are the weight factors of each elementary engineering activityrelated to (EA)3
c) Progress Aggregation from Lev. 2 to Lev. 1(ED)1 = S (EMC)2 (WEMC)2Where:(ED)1 is the actual progress of a discipline(PLA)2 is the actual progress of each planning group relevant to the
discipline calculated as per point b) above(WPLA)2 are the weight factors of each planning group related to the
discipline.
d) Progress Aggregation from Lev. 1 to Engineering Phase
This document is the property of N.I.O.C.. Any unauthorised attempt to reproduce it, in any form, is strictly prohibited.
CONSORTIUM DOC. NO. 3546-PZ-PC-00000007 Filename: 160417843.doc
-
7/27/2019 SP12-2Y3-PC-PP-993-007
14/21
PROJECT PLANNING SCHEDULING Document No: 160417843.doc
AND CONTROL SYSTEM PROCEDURE Date: 26th May 2010
Page: 14 of 23
__________________________________________________________________________________________
(EJ) = S (ED)1 (WU)1Where:(EJ) is the overall engineering actual progress(ED)1 is the actual progress of each engineering discipline, calculated
as per point c) above
(WU)1 are the weight factors of each discipline.
e) Overall project progressPU = S EJ WJWhere:PU is the overall project actual progressEJ is the overall actual progress for each project phaseWJ is the weight factor of each project phase
Detailed Engineering is measured and aggregated from individual deliverables defined inthe Level 4 Schedule. Each deliverable, document, drawing is linked to a specific activity
of Level 3 Schedule. The deliverable progress is rolled-up at appropriate level for feedingthe Level 3 Schedule and evaluating the activity progress from the updated deliverablestatus reported in Document Management System.
The Engineering achieved progress will be calculated and reported to Company at WPand Unit level.
Proposed milestone set, progress weights and breakdown system template are detailedin the Progress Measurement Procedure.
6.2 Procurement Progress Measurement
Procurement progress is measured for equipment, bulk materials and company items.Each activity of the supply chain represents a point associated to a pre-defined progressvalue. The weighting of equipment and materials is determined according to their valueas per contract price breakdown. The percent complete against the pre-defined pointscombined to the weighting enables the progress calculation at the summary levels ofProject WBS.
The Procurement achieved progress will be calculated and reported to Company at WPand Unit levels.
Proposed milestone set, progress weights and breakdown system template are detailed
in the Progress Measurement Procedure.
6.3 Construction, Pre-Commissioning and Commissioningprogress measurement
Construction and Pre-commissioning activities are broken down by WP, unit, disciplineaccording to the project WBS. Commissioning activities are broken down by Sub-systemand system.
Construction, Pre-Commissioning and Commissioning activities will be scheduled incompliance to the built-in start-up logic sequence.
The Construction and Pre-Commissioning activities are measured in Standard Man
Hours (SMH). SMH will be calculated as product between estimated quantities andstandard efficiency.
This document is the property of N.I.O.C.. Any unauthorised attempt to reproduce it, in any form, is strictly prohibited.
CONSORTIUM DOC. NO. 3546-PZ-PC-00000007 Filename: 160417843.doc
-
7/27/2019 SP12-2Y3-PC-PP-993-007
15/21
PROJECT PLANNING SCHEDULING Document No: 160417843.doc
AND CONTROL SYSTEM PROCEDURE Date: 26th May 2010
Page: 15 of 23
__________________________________________________________________________________________
The Construction and Pre-Commissioning activity weight factors will be calculated asratio between SMH of each activity and overall SMH according to the WBS levelweightings.
The Commissioning activity weight factors will be based on systems complexity.
The Construction, Pre-Commissioning and Commissioning activities percent completewill be calculated basin on physical work performed as per Level-4 breakdown.
Proposed milestone set, progress weights and breakdown system template are detailedin the Progress Measurement Procedure.
7 PROGRESS CURVES AND MANPOWER HISTOGRAMS
A series of progress curves and manpower histograms will be developed and updatedthrough to entire project duration, in order to report the progress status.
The progress curves and will be generated, at the proper level, from the approvedschedule and will be considered as baseline progress curves.
According to the early/late activity dates resulting from the network analysis and theweight factors system, the baseline progress curves will shown the monthly plannedprogress.
Distribution characteristics of the baseline progress curves are in accordance withresource distribution and are based on the MEMBERS past experience in analogousProjects.
The baseline curves it will be considered as basis of the progress control system. Duringthe execution of the work, the actual progress shall be compared with the planned. Aforecast shall be introduced if there is any significant deviation from the baseline
schedule.
The curves will be updated monthly basis to display actual versus planned progress aswell as the trend planned for the remaining period. The curves will be included in themonthly progress report.
Level 2 progress curves will be produced in graphical and tabular format for thefollowing phases: Engineering, Procurement, Construction/Pre-commissioning andCommissioning/Start-up.
Engineering curves includes a series of graphs and tables produced by discipline. Forthe Level-2 Engineering progress curves, a compatible manpower histogram will beprovided showing the monthly planned equivalent staff.
Procurement curves include a series of graphs and tables for itemized materials ,bulkmaterials and company items.
Construction/Pre-commissioning curves includes a series of graphs and tablesproduced by discipline.
Level-1 progress curves will be produced as summation of the Level-2 curves incompliance to weight factors system and project WBS. The Level-1 progress curveinclude a series of graphs and tables produced by Engineering, Procurement,Construction and Pre-Commissioning, Commissioning and Start-up, General Services.
An Overall Project curve will be calculated as sum of the phase curves in compliance toWBS level weightings.
For the Level-1 progress curves, will be provided compatible manpower histograms
This document is the property of N.I.O.C.. Any unauthorised attempt to reproduce it, in any form, is strictly prohibited.
CONSORTIUM DOC. NO. 3546-PZ-PC-00000007 Filename: 160417843.doc
-
7/27/2019 SP12-2Y3-PC-PP-993-007
16/21
PROJECT PLANNING SCHEDULING Document No: 160417843.doc
AND CONTROL SYSTEM PROCEDURE Date: 26th May 2010
Page: 16 of 23
__________________________________________________________________________________________
related to the Engineering, Construction/Pre-Commissioning and Commissioning andStart-up phases.
8 DOCUMENT MANAGEMENT SYSTEM
A detailed schedule is prepared for all engineering documents to be developed in theproject by each engineering activity. Based on level 3 network, schedule requirementdates shall be incorporated for each document.
8.1 CONSORTIUM Engineering Deliverables ManagementSystem (EDMS)
EDMS shows for each deliverable of the engineering activities:
Number
Description
Planned and actual dates
The weight factor
The percent complete
For the purchasing documents analogous information are shown.
Wherever the schedule date cannot be met, this will determine a variation in the forecastdate. The System shall include all studies/reports, data sheets, specifications, drawings,spec. for material requisitions and other documents to be produced by engineering
disciplines. This schedule shall also be computerized to enable generation of reports forCompanys requirements.
Document monitoring and control are performed by the Project Control Manager andproject management by a series of standard excel sheet which include (but not limitedto) the following:
Summary table by discipline of document planned together with actual
cumulative achievements i.e. % complete of each document;
Documents already completed and issued;
Documents planned for completion but not complete;
List of overdue documents;
List of awaiting approval documents;
List of transmitted documents;
List of approved documents;
Documents to be issued next period.
All technical documents generated by CONSORTIUM and VENDORS shall be preparedaccording to the Project Documents Numbering Procedure, the Project Co-ordinationand to the Distribution Matrix and for the timing in line with the P6e schedule .In particular, all documents will report the hand-written signatures of the review cycle:Prepared By, Checked By and Approved By.
The documents managed by EDMS can be of the following types (but not limited to):
technical documents as specifications, also native file, CAD models, drawings and
manuals
This document is the property of N.I.O.C.. Any unauthorised attempt to reproduce it, in any form, is strictly prohibited.
CONSORTIUM DOC. NO. 3546-PZ-PC-00000007 Filename: 160417843.doc
-
7/27/2019 SP12-2Y3-PC-PP-993-007
17/21
-
7/27/2019 SP12-2Y3-PC-PP-993-007
18/21
PROJECT PLANNING SCHEDULING Document No: 160417843.doc
AND CONTROL SYSTEM PROCEDURE Date: 26th May 2010
Page: 18 of 23
__________________________________________________________________________________________
Comments due date, Number of copies transmitted.
The list of documents shall indicate as a minimum the following information:
Document Title, Contract Number, Vendor Number (for vendor document) Revision.
Documents shall be grouped under separate transmittals according to the reason of
issue and the originating discipline or Vendor.
CONSORTIUM shall collate properly sets of drawings on one transmittal such that theentire package can be distributed without the need for further collation.
All paper copies of documents and drawings shall be provided in different format from A0to A4.
External transmittals shall indicate the attached documents by number, revision status,title and, if applicable, action code and required return date. External transmittals shallbe issued in duplicate: the second copy being for acknowledgment purposes.
8.3 Master Document Register (MDR)
This register will provide, at any time, accurate and up-to-date information on the currentstatus of all documents issued by CONSORTIUM, VENDORS andSUBCONTRACTORS (if any).
Distribution and timing of documents will be managed according to the distribution matrixand the schedule of the project.
EDMS will produce a computer-based master document register which maintain as acomplete listing of all documents/drawings relating to the CONTRACT. The register willbe in excel format.
EDMS will produce different kind of report including all the important information relatingto the Status of the documentation.
EDMS and Primavera extract will feed MDR that will provide the Engineering Progressby levels.
Project Documentation will be classified according to the COMPANY classificationsystem, detailed in the project procedure Document Classification Procedure.
This document is the property of N.I.O.C.. Any unauthorised attempt to reproduce it, in any form, is strictly prohibited.
CONSORTIUM DOC. NO. 3546-PZ-PC-00000007 Filename: 160417843.doc
-
7/27/2019 SP12-2Y3-PC-PP-993-007
19/21
PROJECT PLANNING SCHEDULING Document No: 160417843.doc
AND CONTROL SYSTEM PROCEDURE Date: 26th May 2010
Page: 19 of 23
__________________________________________________________________________________________
9 PROJECT CONTROL TOOLS
CONSORTIUM is approaching the project taking advantage from both the commonalityof systems and the specific expertise that each MEMBER has on its own systems.
Independently from the location where detailed planning and control activities areoperated and the tools that are used, a homogeneous and integrated reporting system atCONSORTIUM level is maintained and provided to COMPANY according toCONTRACT requirements.
Detailed control is assured by the usage of each Partner standard tools in order topopulate Consortiums project control tools and reports.
Document transmission will be flown from the Consortium Document ManagementSystem.
Overall planning and control is guaranteed by the use of one common, single systembased on the use of Primavera. Primavera is connected with WBS, EngineeringDeliverables Managing System (EDMS), Master Document Register (MDR), risk analysistools, construction/pre-commissioning and commissioning activities control systems.
Primavera Schedule will be managed at CONSORTIUM level.
This way, the overall project is kept under tight control with a unique system, well knownto each PARTNER and which can provide warning and integration data and reportwhenever necessary. At the same time each PARTNER utilizes well known andconsolidated tools within its own organization to keep under tight monitoring on detailedactivities, which are of paramount importance to avoid disruptions at higher level.
Where detailed backup data are necessary to demonstrate, support and analyze in detail
reported CONSORTIUMs report, support documentation may be usefully produced anda homogeneous report will be presented to COMPANY.
Here follows brief summary description of project control system that are commonlyunder Partner using.
CONSORTIUM Project Control Team will be located in Teheran and will manage all theactivities from there.
Primavera for Enterprise
The key tool governing the Integrated Project Control System is Primavera for Enterprise
(P6e). It is a comprehensive multi-project planning and control software, based onMicrosoft platform for Operating System and Application Server, and the OracleDatabase, that enables enterprise-wide project management.
P6e is a multi-user, multi-project system with scheduling and resource controlcapabilities supporting multi-tiered project hierarchies, resource scheduling with a focuson roles, recording of actual data, customized views and user-definable data.
It enables to plan and control overall the project. Data are stores in a centralized projectmanager database and then they are available for anybody needs of them. Differentsecurity profiles manage the right access to these data.
This document is the property of N.I.O.C.. Any unauthorised attempt to reproduce it, in any form, is strictly prohibited.
CONSORTIUM DOC. NO. 3546-PZ-PC-00000007 Filename: 160417843.doc
-
7/27/2019 SP12-2Y3-PC-PP-993-007
20/21
PROJECT PLANNING SCHEDULING Document No: 160417843.doc
AND CONTROL SYSTEM PROCEDURE Date: 26th May 2010
Page: 20 of 23
__________________________________________________________________________________________
The application uses the Precedence Diagram Method (PDM) as Network DiagramMethod and Critical Path Method (CPM) with Resource Leveling as ScheduleDevelopment Technique.
Its tracking features enable to perform dynamic cross-project roll-ups of costs, scheduleand earned value.
Project planning and control are also achieved through the interfaces, developed inMicrosoft Visual Basic, within P3e and the following application areas:
Engineering Deliverables Management System (EDMS)
Master Document Register (MDR)
Project Material Management System & Reporting (PMMS&R)
risk analysis tools
construction/pre-commissioning and commissioning activities control systems
EDMS / MDR
EDMS manages the whole list of the project deliverables.
In the planning phase, MDR takes out from EDMS the list of deliverables and assigns toeach of them the Activity ID of the corresponding P3e activity.
During the planning phase in MDR, it will be assigned a relative weight to eachdeliverable and translate into the corresponding P3e activity.
In the control phase, MDR takes out from EDMS the actual dates and the physicalprogress for the deliverables based on pre-defined steps of issue defined in the ProgressMeasurement Procedure. MDR enables the users to calculate the P3e activity percent
complete starting from the deliverables physical progress.
In the control phase, MDR takes out from EDMS the forecast dates and translate into thecorresponding P3e activity.
PMMS&R
PMMS&R enables the users to track the whole material procurement cycle from thedefinition of the material requisition list up to the arrival at site of the materials.
The system will provide the Actual Dates for each procurement deliverables.
In the planning phase, the interface with P3e enables to move, from this last to
PMMS&R, the Planned Dates for each deliverable and to assign to each one a relativeweight into the corresponding P6e activity.
In the control phase, the interface with P3e enables to move, from PMMS&R to P3e, theActual Dates or the Forecast Dates and the Physical Progress, based on the relativeweight.
This document is the property of N.I.O.C.. Any unauthorised attempt to reproduce it, in any form, is strictly prohibited.
CONSORTIUM DOC. NO. 3546-PZ-PC-00000007 Filename: 160417843.doc
-
7/27/2019 SP12-2Y3-PC-PP-993-007
21/21
PROJECT PLANNING SCHEDULING Document No: 160417843.doc
AND CONTROL SYSTEM PROCEDURE Date: 26th May 2010
Page: 21 of 23
__________________________________________________________________________________________
10PROJECT REPORTING
Project Reporting System will be implemented by CONSORTIUM for the Project in orderto highlight and report to COMPANY how the Project is progressing at each ending
reporting period during the execution of the Project.
Project Reporting System is based on weekly and monthly reports having the formalmeans of recording the status of the Works at the cutoff date. It shall envisage narrativesof current Project status, areas of concern, actual versus planned progress.
The Progress Reporting system is described in Progress Reporting Procedure SP12-2Y-PC-PP-993-006.