sps 800 mhz rf power upgrade

26
LHC Inje ctor Upgr ade SPS 800 MHz RF Power upgrade Progress report December 2013

Upload: shilah

Post on 29-Jan-2016

33 views

Category:

Documents


0 download

DESCRIPTION

SPS 800 MHz RF Power upgrade. Progress report December 2013. Contents. IOTs CERN SPS 800 MHz system & why an upgrade to IOTs Major difficulties while commissioning the pre-series Series delivery Cavities New Antennae New Controls. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: SPS 800 MHz RF Power upgrade

LHC Inject

orUpgrade

SPS 800 MHzRF Power upgradeProgress reportDecember 2013

Page 2: SPS 800 MHz RF Power upgrade

LHC Inject

orUpgrade

LIU

-SPS

mee

ting,

12t

h D

ecem

ber 2

013

Contents

• IOTs• CERN SPS 800 MHz system

& why an upgrade to IOTs• Major difficulties

while commissioning the pre-series• Series delivery

• Cavities• New Antennae• New Controls

Eric

Mon

tesi

nos

2

Page 3: SPS 800 MHz RF Power upgrade

LHC Inject

orUpgrade

LIU

-SPS

mee

ting,

12t

h D

ecem

ber 2

013

CERN SPS 800 MHz system & why an upgrade to IOTs

800 MHz power plant• Since 1980 the system is

composed of 2 transmitters of 225 kW

• One transmitter has4 x 58 kW Valvo klystrons with 3 dB combiners

• Each transmitter is connected through~ 120 m waveguides to its Travelling Wave Cavity

Eric

Mon

tesi

nos

3

2 x 225 kWtransmitters

YL1198Klystron

800 MHz TWC

Page 4: SPS 800 MHz RF Power upgrade

LHC Inject

orUpgrade

LIU

-SPS

mee

ting,

12t

h D

ecem

ber 2

013

CERN SPS 800 MHz system & why an upgrade to IOTs

Obsolescence of the system

• This RF power system is getting very old

• We had major difficulties with klystron ceramic failures and with HV transformers

Eric

Mon

tesi

nos

4Effect of age on HV transformers

Broken ceramic window

of a klystron

Page 5: SPS 800 MHz RF Power upgrade

LHC Inject

orUpgrade

LIU

-SPS

mee

ting,

12t

h D

ecem

ber 2

013

CERN SPS 800 MHz system & why an upgrade to IOTs

Upgrade proposal• keep all existing

ancillaries and replaceKlystron Transmitters with new IOT Transmitters

• First and only IOT at CERN

• We wanted to get experience with this tube as it could be used for

• LHC upgrade (crab cavities)• new CERN accelerator RF

system (SPL ?)

Eric

Mon

tesi

nos

5

New IOT transmitter

Page 6: SPS 800 MHz RF Power upgrade

LHC Inject

orUpgrade

LIU

-SPS

mee

ting,

12t

h D

ecem

ber 2

013

CERN SPS 800 MHz system & why an upgrade to IOTs

Long purchasing process• 2009, 40 member states

companies have been contacted

• 2010, only six companies have been compliant to our specifications

• 2010, Electrosys has been selected

• 2011, we received the pre-serie transmitter at cern

Eric

Mon

tesi

nos

6

Two companies per member state have been contacted

Page 7: SPS 800 MHz RF Power upgrade

LHC Inject

orUpgrade

LIU

-SPS

mee

ting,

12t

h D

ecem

ber 2

013

Main difficulties while commissioning the pre-series

Major troubles

• All Factory Acceptance Tests have shown compliance

• Pre-series Amplifier at CERN was ok with short duration tests

• Long duration tests, we started to experience difficulties• HVSMPS• Conventional HVPS• Erratic faults from 3 to 6 am & from 4 to 7 pm

Eric

Mon

tesi

nos

7

Page 8: SPS 800 MHz RF Power upgrade

LHC Inject

orUpgrade

LIU

-SPS

mee

ting,

12t

h D

ecem

ber 2

013

Main difficulties while commissioning the pre-series

HVSMPS instabilities 2011

Eric

Mon

tesi

nos

8

IOT

HVSMPS

AM square

Repetition rate

RF Power load

600 Hz 17 kHz

HV DC(+ harmonics)

0.1 1100

15001700

20002500

1

10

100 Time Between Failure

[Hz]

[hours]

RF

Page 9: SPS 800 MHz RF Power upgrade

LHC Inject

orUpgrade

LIU

-SPS

mee

ting,

12t

h D

ecem

ber 2

013

Main difficulties while commissioning the pre-series

HVPS troubles 1st half 2012

• HV monitoring transformers

• Ferrites in the IOT input circuit

Eric

Mon

tesi

nos

9

IOT

HVPS

RF

AM square

Repetition rate

RF Power load

Burnt HV monitoring transformers for di/dt

protection

HV transformer

MainsDiodes rectifier

Capacitors stack Thyratron

HV DC

Page 10: SPS 800 MHz RF Power upgrade

LHC Inject

orUpgrade

LIU

-SPS

mee

ting,

12t

h D

ecem

ber 2

013

Main difficulties while commissioning the pre-series

HVPS troubles 2nd half 2012

• Repetitive faults from• 3:00 to 6:00 am• 4:00 to 7:00 pm

Eric

Mon

tesi

nos

10

IOT

HVPS

RF

AM square

Repetition rate

RF Power load

0:00 1:59 3:59 5:59 7:59 9:59 11:59 13:59 15:59 17:59 19:59 21:59 23:590

200

400

600Noise immunity

Time of the day the fault occurs [h]Ti

me

betw

een

faul

ts [h

]

Page 11: SPS 800 MHz RF Power upgrade

LHC Inject

orUpgrade

LIU

-SPS

mee

ting,

12t

h D

ecem

ber 2

013

Main difficulties while commissioning the pre-series

HVPS troubles 2nd half 2012

• We were not able to link it with any external ‘perturbation’• CERN workers, security people or firemen checking the building• Automatic lighting of the building• GSM or Wifi antenna in the building• Traffic lights close to the building• Public lighting day & night light detection• Airport traffic: no planes before 7 am at Geneva airport• Train: old story with TGV disturbing LEP beams, not able to link with any

train timetable• Etc…

Eric

Mon

tesi

nos

11

0:00 1:59 3:59 5:59 7:59 9:59 11:59 13:59 15:59 17:59 19:59 21:59 23:590

200

400

600Noise immunity

Tim

e be

twee

n fa

ults

[h]

Time of the day the fault occurs [h]

Page 12: SPS 800 MHz RF Power upgrade

LHC Inject

orUpgrade

LIU

-SPS

mee

ting,

12t

h D

ecem

ber 2

013

Main difficulties while commissioning the pre-series

HVPS troubles 2nd half 2012

• Not always detected by the Driver overdrive protection

• Always triggering the di/dt tube protection

Eric

Mon

tesi

nos

12

IOT

HVPS

RF

AM square

Repetition rate

RF Power load

• Faulty RF generator• Glitch on top of the RF pulse• Equivalent to 10 x power

Page 13: SPS 800 MHz RF Power upgrade

LHC Inject

orUpgrade

LIU

-SPS

mee

ting,

12t

h D

ecem

ber 2

013

Main difficulties while commissioning the pre-series

HVPS troubles 2nd half 2012

• We solve the problem simply by replacing the RF generator

• We were able to perform2,800 hours without a fault

• We had to stop the test as we started LS1

Eric

Mon

tesi

nos

13

IOT

HVPS

RF

AM square

Repetition rate

RF Power load

12/13/2011 3/12/2012 6/10/2012 9/8/2012 12/7/2012 3/7/20130

500

1000

1500

2000

2500

3000Time between Failure

Date

hours

Page 14: SPS 800 MHz RF Power upgrade

LHC Inject

orUpgrade

LIU

-SPS

mee

ting,

12t

h D

ecem

ber 2

013

6/1/2011 8/30/2011 11/28/2011 2/26/2012 5/26/2012 8/24/2012 11/22/2012 2/20/20130

500

1000

1500

2000

2500

3000Time between Failure

Date

hours

Main difficulties while commissioning the pre-series

Time spent per problem

Eric

Mon

tesi

nos

14

6 months 5 months 4 months

HVSMPS HV monitoring transformers

&Input circuit

ferrites

RFGenerator

&Faulty

Overdrive protection

20 months before launching the series production

24.06.12 green light for Series production

Page 15: SPS 800 MHz RF Power upgrade

LHC Inject

orUpgrade

LIU

-SPS

mee

ting,

12t

h D

ecem

ber 2

013

Series delivery

Series production• We asked for several

modifications

• Driver overdrive protection

• Additional air cooling for coaxial lines

• Direct access to hardware interlocks through a monitoring panel with ‘blinking first fault’

Eric

Mon

tesi

nos

15

Hardware Electronic PLC

Remote GUI

Hardware Electronic PLC

Local GUI &

First faultRemote

GUI

PLC clock, minimum ms

Real time

Page 16: SPS 800 MHz RF Power upgrade

LHC Inject

orUpgrade

LIU

-SPS

mee

ting,

12t

h D

ecem

ber 2

013

Series delivery

Series production

Eric

Mon

tesi

nos

16

Remote GUI

External probes with risky possible false contacts

In addition we have a panel for quick

identification of faults (LEDs)

& with direct access to hardware interlocks

(BNC) for real time monitoring

Page 17: SPS 800 MHz RF Power upgrade

LHC Inject

orUpgrade

LIU

-SPS

mee

ting,

12t

h D

ecem

ber 2

013

Series delivery

Series tests at CERN• Due to LS1, lack of

water has limited tests up to 60 kW total maximum, i.e. one transmitter at a time

• Between June and December 2013 we received all eight transmitters and commissioned them individually

Eric

Mon

tesi

nos

17

• Transmitter #1 connected to main combiners

• Transmitter #2 connected to RF load for CERN Acceptance Test

• Transmitter #3 not yet connected

#1#2

#3

Page 18: SPS 800 MHz RF Power upgrade

LHC Inject

orUpgrade

LIU

-SPS

mee

ting,

12t

h D

ecem

ber 2

013

Series delivery

Series tests• Seven transmitters

have been fully commissioned

• We miss the tube for the last transmitter, should be delivered before end 2013

• It has already been validated with the tube of transmitter 7

Eric

Mon

tesi

nos

18

Gino testing one of the transmitter

All eight transmitters in BB3

Page 19: SPS 800 MHz RF Power upgrade

LHC Inject

orUpgrade

LIU

-SPS

mee

ting,

12t

h D

ecem

ber 2

013

Series delivery

What is a commissioning ?• Long and detailed reception

process

• Static tests• Mechanical inspection• Water pressure test• Ancillaries checks

• Electrical tests• Emergency stop test• HV test with an external HVPS by

steps of 5 kV per minutes• Crowbar without tube and with

tube (thin wire in short circuit)

• RF Low Power tests• Tuning the amplifier

Eric

Mon

tesi

nos

19

BW-1dB must be > 6 MHz (+/- 3 MHz)

with Ibeam = 0.45 A

Phase variation < +/- 30°over 6 MHz (+/- 3 MHz)

Page 20: SPS 800 MHz RF Power upgrade

LHC Inject

orUpgrade

LIU

-SPS

mee

ting,

12t

h D

ecem

ber 2

013

Series delivery

What is a commissioning ?• RF High Power tests

• Increase the power by step of 10 kW up to 60 kW

• Check all values, Vbeam, Ibeam, Pfwd, Prev, Pdriver, Ibody, Vfocus, Ifocus

• At mid power, retune the cavity for Pmax

• Measure • Thermal power load• Efficiency = RFout / HVin

• Long duration tests with several cycles

• Minimum four hours per cycle• Observe any characteristic variation

Eric

Mon

tesi

nos

20Long duration test description

Measurements to be made with each Power Amplifier AND

with the whole Transmitter (i.e. four Power Amplifiers combined together) Continuous operation 24/24 hours CW Very Long Pulses operation Fc = 800.888 MHz +/ - 0.5 MHz : 100% from 0 to 60kW with rise and fall time < 0.5 µs 5 seconds ON / 5 seconds OFF

time

Power

5 s

0.5 us 0.5 us

240 kW

0 kW

10 s

AM modulation #1 Fc = 800.888 MHz +/ - 0.5 MHz : 100% from 0 to 60kW with rise and fall time < 0.5 µs Repetition time 10 µs (100kHz)

time

Power

10 us

0.5 us0.5 us

240 kW

0 kW

AM modulation #2 Fc = 800.888 MHz +/ - 0.5 MHz : 0 to 60kW with 4 MHz triangle AM 25 % in power Rise and fall time < 0.5 µs Flat top pulse and off pulse length of 11 us Repetition time 23 µs (100kHz) This cycle for 20 second then 1 second OFF.

time

Power

11 us

0.5 us 0.5 us

240 kW

0 kW

11 us

23 us

20 s 1 s

4 MHz triangle

25 %

Page 21: SPS 800 MHz RF Power upgrade

LHC Inject

orUpgrade

LIU

-SPS

mee

ting,

12t

h D

ecem

ber 2

013

Series delivery

Circulator• Thales asked us to protect

the tubes with a circulator against full reflection that could occur while conditioning the couplers

• We fully approved it regarding other applications difficulties (ESRF, ALBA, …)

• We kept our Waveguide switch to allow quick test onto a power load

Eric

Mon

tesi

nos

21

Cavity

Load

Short

Circulator – WG switch (cavity or short) – Power load

Circulator

TCU

Short

To cavityWG switch

Load

WG switch

Page 22: SPS 800 MHz RF Power upgrade

LHC Inject

orUpgrade

LIU

-SPS

mee

ting,

12t

h D

ecem

ber 2

013

Series delivery

Still to be done• Test of the four

amplifiers together with both systems

• Onto the load• Onto the cavity

• Beginning 2014 with a low total power of60 kW (lack of water)

• From April 2014 with full total power of240 kW (water back)

Eric

Mon

tesi

nos

22

Cavity #2Load

Short

Cavity #1

Load

Short

~

2014

Page 23: SPS 800 MHz RF Power upgrade

LHC Inject

orUpgrade

LIU

-SPS

mee

ting,

12t

h D

ecem

ber 2

013

Cavities

New Antennae• A new antenna has been re-

designed

• It is fully compatible with the existing model and with the TWC 200 MHz

• There were two antennae per cavity, LLRF asked for one per iris

• 100 antennae have been produced

• 37 cells per cavity have been equipped

Eric

Mon

tesi

nos

23

New antenna design

Sébastien adding a new antenna on all 66 cells

Page 24: SPS 800 MHz RF Power upgrade

LHC Inject

orUpgrade

LIU

-SPS

mee

ting,

12t

h D

ecem

ber 2

013

Cavities

New Controls

• With the obsolescence of the ECAs and controls of the TWC 200 MHz systems, as we were upgrading Power Amplifiers, we decide to also upgrade TWC 800 MHz controls

• This is underway, and we will have a new system ready beginning 2014

Eric

Mon

tesi

nos

24

New controls unit front panel

New controls unit PLC

Page 25: SPS 800 MHz RF Power upgrade

LHC Inject

orUpgrade

LIU

-SPS

mee

ting,

12t

h D

ecem

ber 2

013

Schedule

Eric

Mon

tesi

nos

25

2014

Jan Feb Mar Apr May Jun Jul AugDec

8 Individual transmitters

TWC 160 kW total

TWC 260 kW total TWC 1

220 kW total

TWC 2220 kW total

TWC 1 & 22 x 220 kW total

+Cavity

conditioning

LLRF commissioning

SPS setup with beam

SPS closed

LLRF antennae calibration

Page 26: SPS 800 MHz RF Power upgrade

LHC Inject

orUpgrade

LIU

-SPS

mee

ting,

12t

h D

ecem

ber 2

013

Conclusion

All 8 systems are expected to be operational before the end of this year

Even if it has not been easy, High Power systems are pretty well as scheduled

Eric

Mon

tesi

nos

26