srs utility coordination word document - pages · real estate business analysis srs synergy utility...

15
Page 1 of 15 Tuesday, June 11, 2013 Ohio Department of Transportation Division of Engineering Office of Real Estate Synergy Real Estate Business Analysis Utility Coordination System Requirements Specification Version 1.02 Revision History Date Version Description Modified By 2/26/13 1.00 Initial Draft Cheryl Jacino 5/13/13 1.00 Define Real Estate Utility Coordination Process Cheryl Jacino 5/22/13 1.00 Finalize Utility Coordination SRS Cheryl Jacino 5/24/13 1.01 Add Utility Coordination to page headings. Cheryl Jacino 6/10/13 1.02 Add Ohio Utilities Protection Service to OUPS acronym. Cheryl Jacino

Upload: donga

Post on 16-Apr-2018

220 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: SRS Utility Coordination Word Document - Pages · Real Estate Business Analysis SRS Synergy Utility Coordination v. 1.00 Page 3 of 15 Tuesday, June 11, 2013 0 Synergy Utility Coordination

Page 1 of 15 Tuesday, June 11, 2013

Ohio Department of Transportation

Division of Engineering Office of Real Estate

Synergy Real Estate Business Analysis

Utility Coordination System Requirements Specification

Version 1.02

Revision History

Date Version Description Modified By

2/26/13 1.00 Initial Draft Cheryl Jacino

5/13/13 1.00 Define Real Estate Utility Coordination Process Cheryl Jacino

5/22/13 1.00 Finalize Utility Coordination SRS Cheryl Jacino

5/24/13 1.01 Add Utility Coordination to page headings. Cheryl Jacino

6/10/13 1.02 Add Ohio Utilities Protection Service to OUPS acronym. Cheryl Jacino

Page 2: SRS Utility Coordination Word Document - Pages · Real Estate Business Analysis SRS Synergy Utility Coordination v. 1.00 Page 3 of 15 Tuesday, June 11, 2013 0 Synergy Utility Coordination

Real Estate Business Analysis SRS Synergy Utility Coordination v. 1.00

Page 2 of 15 Tuesday, June 11, 2013

Table of Contents

0 Synergy Utility Coordination System Requirements Specification ........................................ 3 0.1 Purpose ....................................................................................................................... 3 0.2 Author(s) ...................................................................................................................... 3 0.3 Audience ...................................................................................................................... 3 0.4 Business Requirements ............................................................................................... 4 0.5 System Requirements Specifications Table: ................................................................ 4 0.6 Process Flow Chart: ..................................................................................................... 6

4 Utility Coordination Process ................................................................................................ 7 4.1 Pre-Planning Utilities .................................................................................................... 9 4.2 Confirm Utility Impact ..................................................................................................10 4.3 Request Utility Relocation Plan and Estimate .............................................................11 4.8 Fund Utility Relocation ................................................................................................12 4.10 Adjust Funding for Utility Relocation Changes ............................................................13 4.11 Review Billing .............................................................................................................14

Page 3: SRS Utility Coordination Word Document - Pages · Real Estate Business Analysis SRS Synergy Utility Coordination v. 1.00 Page 3 of 15 Tuesday, June 11, 2013 0 Synergy Utility Coordination

Real Estate Business Analysis SRS Synergy Utility Coordination v. 1.00

Page 3 of 15 Tuesday, June 11, 2013

0 Synergy Utility Coordination System Requirements Specification

0.1 Purpose

The System Requirements Specification (SRS) is to capture the business requirements for the Real Estate Right of Way System. The purpose of these requirements is three fold:

1) used to select a system to purchase 2) used to identify feature requirements during the system design phase 3) assist the business with identifying change management needs

The SRS document should also capture the non-functional requirements as well as system conversion requirements.

0.2 Author(s)

The Business Analyst is the owner of this document, with assistance from the Business Sponsors, Business Stakeholders, Business Subject Matter Experts, District Subject Matter Experts, and Project Management Office Manager.

0.3 Audience

The SRS is a useful tool for Business Users requesting the system to communicate the functions of the system with DoIT and vendors involved in creating the software or system. This document will also serve as a reference for any future development.

Page 4: SRS Utility Coordination Word Document - Pages · Real Estate Business Analysis SRS Synergy Utility Coordination v. 1.00 Page 3 of 15 Tuesday, June 11, 2013 0 Synergy Utility Coordination

Real Estate Business Analysis SRS Synergy Utility Coordination v. 1.00

Page 4 of 15 Tuesday, June 11, 2013

0.4 Business Requirements

A business requirement is a specific, actionable, testable directive that is under the control of the business and supports a business policy. Included in the document of SRS are the high-level lists of requirements that will be broken into features during the Systems Design Phase that follows Business Analysis. There may be more than one feature for each business requirement.

0.5 System Requirements Specifications Table:

Each section of system requirements specification is included in a table with the following parts:

ID Description Requirements Source

Priority Change? Feature

ID – This is a numeric ID that will be used to track the requirement through all phases of the system development to ensure the requirement is designed, developed, tested, approved, and implemented.

Description – includes the title of the process and a definition of what is included in the process.

Requirements Source – Used to identify the source of the requirement. In this case the requirement is being tracked back to the requirements gathering session. RE-Acquisition-BA stands for Real Estate Acquisition Requirements Gathered during Business Analysis. RE-Appraisal-BA stands for Real Estate Appraisal Requirements Gathered during Business Analysis. RE-Acquisition-Type-BA stands for Real Estate Acquisition Type Requirements Gathering during Business Analysis. RE-Utility-BA stands for Real Estate Utility Coordination Requirements Gathering during Business Analysis. RE-Relocation-BA stands for Real Estate Relocation Requirements Gathering during Business Analysis. RE-Property-Mgmt-BA stands for Real Estate Property Management Requirements Gathering during Business Analysis. RE-Fiscal-BA stands for Real Estate Fiscal Requirements Gathering during Business Analysis. RE-General-BA stands for Real Estate Reporting, Records Retention, & Document Handling Requirements Gathering during Business Analysis. RE-Technical-BA stands for Real Estate Technical Requirements, System Interfaces, and Non-Functional Requirements Gathering during Business Analysis.

Page 5: SRS Utility Coordination Word Document - Pages · Real Estate Business Analysis SRS Synergy Utility Coordination v. 1.00 Page 3 of 15 Tuesday, June 11, 2013 0 Synergy Utility Coordination

Real Estate Business Analysis SRS Synergy Utility Coordination v. 1.00

Page 5 of 15 Tuesday, June 11, 2013

ID Description Requirements Source

Priority Change? Feature

Priority – Define the priority within the replacement New System for each requirement.

Required - Current Paradox System Process that is required in the New System.

Obsolete - Current Paradox System Process that is Obsolete and will not be present in the New System.

New - Process that is not in the Current Paradox System Process but is required in the New System.

Extra - Process that is not in the Current Paradox System Process and is an Unnecessary but desirable Extra Feature in the New System.

Future - Process that is not in the Current Paradox System Process and is a desirable Feature in a future version of the New System. Any necessary preliminary setup to easily provide this feature in the future is advised.

Manual – Process that is manual and does not lend itself to a system solution. See Detail – Priority is captured in a sub-process related to this process.

Change? – Does this need Change Management for implementation?

Feature – Used during Systems Design Phase to trace Functional Requirement related to the Business System Requirement.

Page 6: SRS Utility Coordination Word Document - Pages · Real Estate Business Analysis SRS Synergy Utility Coordination v. 1.00 Page 3 of 15 Tuesday, June 11, 2013 0 Synergy Utility Coordination

Real Estate Business Analysis SRS Synergy Utility Coordination v. 1.00

Page 6 of 15 Tuesday, June 11, 2013

0.6 Process Flow Chart:

Each Process is accompanied by a process flow chart. The legend below shows all of the shapes used in the flow charts and the meaning of the shapes. Although the process flow represents the general flow of the acquisition work, there is complete flexibility in the order each process is completed. Below is a legend describing the shapes used within the flow charts.

LEGEND

Process

Decision?

Start or End

Document

Document

Group Process

Process – A specific, actionable, testable activity that is under the control of the business and supports a business policy.

Decision – This is a point where the process splits into different processes based on the question shown in the diamond. Each directional arrow leaving the diamond is labeled with the answer to the question and points to the process that follows.

Start or end – A start or end point for the process flow that originates or ends at this point.

Group Process – A group of related processes that will be broken down into specific, actionable, testable activities. To see the breakdown of this group, an embedded link to the tab with the breakdown of processes is included.

Document – A paper copy of the named document. Documents can be input to a process or output from a process but it does not represent any activity related to the document.

C

Certified Mail

MailMail – A paper copy of the named document is mailed. Mail can be input to a process or output from a process but it does not represent any internal system activity, only the external activity of mailing a document.

Continue? Continue – This is a point where the process repeats until the answer allows the process to continue to the next step.

Manual Process – A specific, actionable, manual activity that cannot be replaced by system activity.

1.6.1

Search Public Records for

Owner

6.3.4 Enter

Encumbrance Into Ellis

External Process – An activity that is a necessary part of the business process flow but takes place in a system external to this Real Estate System.

Multi-Process Multi-Process – Multiple distinct yet related activities are directly accessed from this entry point in the business process flow.

Deliver/Receive Document in person. This can be input to a process or output from a process but it does not represent any activity, only the external delivery or receipt a document.

Note: Title Process Note – This contains notes that are important to the business process flow.

RE101Excel Import or Export – An excel import or export file that allows information from the system to be shared between Excel spreadsheets and the Synergy system. This allows user control of the data and process used to create or report the data and prevents the duplicate entry and possible errors in the data between the Synergy System and the Excel spreadsheets .

Page 7: SRS Utility Coordination Word Document - Pages · Real Estate Business Analysis SRS Synergy Utility Coordination v. 1.00 Page 3 of 15 Tuesday, June 11, 2013 0 Synergy Utility Coordination

Real Estate Business Analysis SRS Synergy Utility Coordination v. 1.00

Page 7 of 15 Tuesday, June 11, 2013

4 Utility Coordination Process

This section contains the requirements for the process to relocate utilities for the purpose of Department of Transportation projects.

4.0 UTILITY COORDINATION

4.1Pre-Planning

Utilities

4.2 Confirm Utility

Impact

4.3 Request Utility Relocation Plan

and Estimate

4.9Begin Utility Relocation

4.10Adjust Funding for Utility Relocation

Changes

4.11 Review Billing

4.12Pay Utility

4.7Is Project ROW

Certified?

NO

Utility Note(As necessary)YES

4.4Review Utility

Relocation Plan and Estimate

4.5Is Utility

Relocation Compensable?

YES

4.6Send Letter

Informing Utility Non-reimbursable

NO

4.8Fund Utility Relocation

ID Description Requirements Source

Priority Change?

Feature

RE 4.1 Pre-Planning Utilities – Evaluate design impact on utility companies and give preliminary estimate.

RE-Utility-BA See Detail

RE 4.2 Confirm Utility Impact – Use information to confirm utility relocation impacts on project plan, schedule, and estimate.

RE-Utility-BA See Detail

RE 4.3 Request Utility Relocation Plan and Estimate

RE-Utility-BA See Detail

RE 4.4 Review Utility Relocation Plan and Estimate - Review Utility Relocation Plan and Estimate. District may track to make sure Utility Files Permit Application MR505.

RE-Utility-BA Required

RE 4.5 Is Utility Relocation Compensable? – When Utility provides an estimate based on property rights the Utility Relocation is compensable.

RE-Utility-BA Required

Page 8: SRS Utility Coordination Word Document - Pages · Real Estate Business Analysis SRS Synergy Utility Coordination v. 1.00 Page 3 of 15 Tuesday, June 11, 2013 0 Synergy Utility Coordination

Real Estate Business Analysis SRS Synergy Utility Coordination v. 1.00

Page 8 of 15 Tuesday, June 11, 2013

ID Description Requirements Source

Priority Change?

Feature

RE 4.6 Send letter informing Utility non-reimbursable – Send notice informing Utility Company that Utility Relocation costs cannot be reimbursed.

RE-Utility-BA New Yes

RE 4.7 Is Project ROW Certified? – When project ROW is certified, non-reimbursable utility relocation can begin.

RE-Utility-BA Required

RE 4.8 Fund Utility Relocation – CO reviews Utility Relocation Plans and Estimate before approving and encumbering funds.

RE-Utility-BA See Detail

RE 4.9 Begin Utility Relocation RE-Utility-BA Required

RE 4.10 Adjust Funding for Utility Relocation Changes – When Utility Relocation changes, review and approve utility relocation change order and adjust encumbrance.

RE-Utility-BA See Detail

RE 4.11 Review Billing – Make sure utility relocation bills are received and processed within established time frame.

RE-Utility-BA See Detail

RE 4.12 Pay Utility – Complete RE24 and issue warrant to pay Utility Relocation Bill.

RE-Utility-BA Required

Page 9: SRS Utility Coordination Word Document - Pages · Real Estate Business Analysis SRS Synergy Utility Coordination v. 1.00 Page 3 of 15 Tuesday, June 11, 2013 0 Synergy Utility Coordination

Real Estate Business Analysis SRS Synergy Utility Coordination v. 1.00

Page 9 of 15 Tuesday, June 11, 2013

4.1 Pre-Planning Utilities

Evaluate design impact on utility companies and give preliminary estimate of Utility Relocation cost.

4.1 Pre-Planning Utilities

4.1.2Identify Utility

Owner

4.1.1Conduct Field

Review

4.1.3Call OUPS and

Request As-Built Plan

4.1.4Prelim Estimate

ID Description Requirements Source

Priority Change? Feature

RE 4.1.1 Conduct Field Review – Attend field review with district team as needed.

RE-Utility-BA New Yes

RE 4.1.2 Identify Utility Owners – From field review and preliminary plans, begin to identify known utilities.

RE-Utility-BA Required

RE 4.1.3 Call OUPS and Request As-Built Plan – Call Ohio Utilities Protection Service (OUPS) to request “As Built” plans for the utility in the project ROW.

RE-Utility-BA New Yes

RE 4.1.4 Prelim Estimate – Enter Preliminary Estimate of Utility Cost into Ellis.

RE-Utility-BA New Yes

Page 10: SRS Utility Coordination Word Document - Pages · Real Estate Business Analysis SRS Synergy Utility Coordination v. 1.00 Page 3 of 15 Tuesday, June 11, 2013 0 Synergy Utility Coordination

Real Estate Business Analysis SRS Synergy Utility Coordination v. 1.00

Page 10 of 15 Tuesday, June 11, 2013

4.2 Confirm Utility Impact

Use information to confirm utility relocation impacts on project plan, schedule, and estimate.

4.2 Confirm Utility Impact

4.2.1Send Plans with

Alignment to Utility Company

4.2.2Receive Feedback

from Utilities

4.2.3Evaluate Potential for Construction Impact on Utility

4.2.5Update Utility

Estimate

4.2.4Did Updated

Estimate change from Prelim Estimate?

YES

Nothing

NO

ID Description Requirements Source

Priority Change? Feature

RE 4.2.1 Send Plans with Alignment to Utility Company

RE-Utility-BA Required

RE 4.2.2 Receive Feedback from Utilities – Utilities provide information on what facilities exist within the project plan.

RE-Utility-BA New Yes

RE 4.2.3 Evaluate Potential for Construction Impact on Utility – District evaluates utility impacts from construction plans.

RE-Utility-BA Manual

RE 4.2.4 Did Updated Estimate change from Prelim Estimate?

RE-Utility-BA New Yes

RE 4.2.5 Update Utility Estimate – Update Preliminary Estimate of Utility Cost in Ellis based on feedback from utility evaluation.

RE-Utility-BA New Yes

Page 11: SRS Utility Coordination Word Document - Pages · Real Estate Business Analysis SRS Synergy Utility Coordination v. 1.00 Page 3 of 15 Tuesday, June 11, 2013 0 Synergy Utility Coordination

Real Estate Business Analysis SRS Synergy Utility Coordination v. 1.00

Page 11 of 15 Tuesday, June 11, 2013

4.3 Request Utility Relocation Plan and Estimate

Request Utility Relocation Plan and Estimate.

4.3 Request Utility Relocation Plan and Estimate

4.3.1Send Stage 2

Plans to Utility Company

4.3.2Request Utility

Relocation Plans and Estimate

ID Description Requirements Source

Priority Change? Feature

RE 4.3.1 Send Stage 2 Plans to Utility Company

RE-Utility-BA New Yes

RE 4.3.2 Request Utility Relocation Plans and Estimate

RE-Utility-BA New Yes

Page 12: SRS Utility Coordination Word Document - Pages · Real Estate Business Analysis SRS Synergy Utility Coordination v. 1.00 Page 3 of 15 Tuesday, June 11, 2013 0 Synergy Utility Coordination

Real Estate Business Analysis SRS Synergy Utility Coordination v. 1.00

Page 12 of 15 Tuesday, June 11, 2013

4.8 Fund Utility Relocation

CO reviews Utility Relocation Plans and Estimate before approving and encumbering funds.

4.8 Fund Utility Relocation

4.8.1Send Utility Relocation Plans and Estimate to

CO for Approval

4.8.4Encumber Utility Relocation Funds

4.8.3Send letter

informing Utility reimbursable

4.8.2Did CO

Approve?YES

4.8.5Resolve Issues

with Utility Company

NO

ID Description Requirements Source

Priority Change? Feature

RE 4.8.1 Send to CO for Approval RE-Utility-BA Required

RE 4.8.2 Did CO Approve? – Did CO approve Utility Relocation Plans and Estimate?

RE-Utility-BA Required

RE 4.8.3 Send letter informing Utility reimbursable – Send letter to Utility Company approving the Utility Relocation plans and estimate and authorize relocation to begin.

RE-Utility-BA Required

RE 4.8.4 Encumber Utility Relocation Funds

RE-Utility-BA Required

RE 4.8.5 Resolve Issues with Utility Company – Work to address any contingencies prior to approving plans and estimates.

RE-Utility-BA Manual

Page 13: SRS Utility Coordination Word Document - Pages · Real Estate Business Analysis SRS Synergy Utility Coordination v. 1.00 Page 3 of 15 Tuesday, June 11, 2013 0 Synergy Utility Coordination

Real Estate Business Analysis SRS Synergy Utility Coordination v. 1.00

Page 13 of 15 Tuesday, June 11, 2013

4.10 Adjust Funding for Utility Relocation Changes

When Utility Relocation plans change, District and CO reviews and approves utility relocation changes and adjusts encumbrance.

4.10 Adjust Funding for Utility Relocation Changes

4.10.1Did Utility

Work Incur Cost Overruns?

4.10.2Did Utility

Inform District of Changes?

4.10.6Send Notice to

Utility informing not reimbursable

Nothing

NO NO

YES YES

4.10.3District Sends Utility Relocation Change

Notice to CO

4.10.4Did CO

Approve Change Notice?

NO

4.10.5Adjust

EncumbranceYES

4.10.7Send Notice to

Utility informing reimbursable

ID Description Requirements Source

Priority Change? Feature

RE 4.10.1 Did Utility Work Incur Cost Overruns? – Utilities monitor work and notify the District when cost overruns are probable.

RE-Utility-BA Manual

RE 4.10.2 Did Utility Inform District of Changes? – Did the Utility company inform the district of plan changes or unforeseen relocation adjustments?

RE-Utility-BA New Yes

RE 4.10.3 District Sends Utility Relocation Change Notice to CO

RE-Utility-BA Required

RE 4.10.4 Did CO Approve Change Notice? RE-Utility-BA Required

RE 4.10.5 Adjust Encumbrance – Make adjustments to original Encumbrance to reflect approved changes.

RE-Utility-BA Required

RE 4.10.6 Send Notice to Utility informing not reimbursable – Send notice to Utility company that Cost Overrun is not reimbursable.

RE-Utility-BA New Yes

RE 4.10.7 Send Notice to Utility informing reimbursable – Send notice to Utility company that Cost Overrun is reimbursable.

RE-Utility-BA Required

Page 14: SRS Utility Coordination Word Document - Pages · Real Estate Business Analysis SRS Synergy Utility Coordination v. 1.00 Page 3 of 15 Tuesday, June 11, 2013 0 Synergy Utility Coordination

Real Estate Business Analysis SRS Synergy Utility Coordination v. 1.00

Page 14 of 15 Tuesday, June 11, 2013

4.11 Review Billing

Make sure utility relocation bills are received and processed within established time frame.

4.11 Review Billing

4.11.1Did District

Receive Final Bill?

NO

4.11.2Is Anniversary of

Utility Relocation in 90 days?

4.11.3Send warning

“Final Bill due in 90 days”.

YES

Nothing

NO

4.11.5District Sends Final

Bill to CO

YES

4.11.6Did CO

Approve Final Bill?

4.11.9Resolve Issues

with Utility Company

NO

4.11.7Continue with 4.12 Pay Utility

YES

4.11.4Did Final Bill Arrive Before Anniversary ?

4.11.8Send Certified Letter of Reimbursement Forfeiture to Utility

NO

YES

ID Description Requirements Source

Priority Change? Feature

RE 4.11.1 Did District Receive Final Bill? RE-Utility-BA Required

RE 4.11.2 Is Anniversary of Utility Relocation in 90 days? – Is Utility Relocation 90 days prior to anniversary of completion?

RE-Utility-BA Required

RE 4.11.3 Send Letter warning “Final Bill is due in 90 days”.

RE-Utility-BA Required

RE 4.11.4 Did District receive Final Billing before Utility Relocation anniversary?

RE-Utility-BA Manual

RE 4.11.5 District Sends Final Bill to CO RE-Utility-BA Required

RE 4.11.6 Did CO Approve Final Bill? RE-Utility-BA Required

RE 4.11.7 Continue with 4.12 Pay Utility RE-Utility-BA

Page 15: SRS Utility Coordination Word Document - Pages · Real Estate Business Analysis SRS Synergy Utility Coordination v. 1.00 Page 3 of 15 Tuesday, June 11, 2013 0 Synergy Utility Coordination

Real Estate Business Analysis SRS Synergy Utility Coordination v. 1.00

Page 15 of 15 Tuesday, June 11, 2013

ID Description Requirements Source

Priority Change? Feature

RE 4.11.8 Resolve Issues with Utility Company - Work to address any billing issues prior to approving Final Bill payment.

RE-Utility-BA Manual

RE 4.11.9 Send Certified Letter of Reimbursement Forfeiture to Utility

RE-Utility-BA Required