standard data book - rate analysis

313

Click here to load reader

Upload: relhanpk2793

Post on 28-Jan-2016

354 views

Category:

Documents


53 download

DESCRIPTION

Standard Data Book - Road Rate Analysis

TRANSCRIPT

Page 1: Standard Data Book - Rate Analysis

PUNJAB INFRASTRUCTURE DEVELOPMENT BOARD ANALYSIS OF RATE FOR BULK / PACKED BITUMEN SUPPLY VARIOUS TYPE COLLECTION OF BITUMEN FROM PANIPAT REFINERY

Product

Tota

l

Su

b T

ota

l

Gra

nd

Tota

l

Ad

d 1

% L

ab

ur

cess

1 2 3 4 5 6 7 8 9 10 11

IBulk 44205 6374.36 50579.36 ### 3060.05 54651.00 481.50 55132.50 0.00 55132 PMT BM

Packed 47305 6821.38 54126.38 ### 3274.65 58483.55 481.50 58965.05 0.00 58965 PMT

IIBulk 45005 6489.72 51494.72 ### 3115.43 55640.05 481.50 56121.55 0.00 56122 PMT DBM& BC

Packed 48105 6936.74 55041.74 ### 3330.03 59472.60 481.50 59954.10 0.00 59954 PMT

IIIBulk 44125 6362.83 50487.83 ### 3054.51 54552.09 481.50 55033.59 0.00 55034 PMT

Packed 47475 6845.90 54320.90 ### 3286.41 58693.73 481.50 59175.23 0.00 59175 PMT

IVBulk 44215 6375.80 50590.80 ### 3060.74 54663.36 481.50 55144.86 0.00 55145 PMT

Packed 41854 6035.35 47889.35 957.79 2897.31 51744.44 481.50 52225.94 0.00 52226 PMT

VBulk 44005 6345.52 50350.52 ### 3046.21 54403.74 481.50 54885.24 0.00 54885 PMT

Packed 42044 6062.74 48106.74 962.13 2910.46 51979.34 481.50 52460.84 0.00 52461 PMT

VIBulk 36035 5196.25 41231.25 824.62 2494.49 44550.36 481.50 45031.86 0.00 45032 PMT

Packed 39985 5765.84 45750.84 915.02 2767.93 49433.78 481.50 49915.28 0.00 49915 PMT TC

VIIBulk 36245 5226.53 41471.53 829.43 2509.03 44809.99 481.50 45291.49 0.00 45291 PMT

Packed 40195 5796.12 45991.12 919.82 2782.46 49693.40 481.50 50174.90 0.00 50175 PMT

VIIIBulk 34435 4965.53 39400.53 788.01 2383.73 42572.27 481.50 43053.77 0.00 43054 PMT

Packed 38385 5535.12 43920.12 878.40 2657.17 47455.69 481.50 47937.19 0.00 47937 PMT PRIMER

Lead Chart from Panipat to Plant & site of work

Total =388+2x2.80 394.00 Say 394 Kms

Sub Divisional Engineer , Executive Enginereer,

Bitumen rates Ex. Panipat w.e.f. 01/01/2014

Sl.Nr.

Basi

c R

ate

fro

m

Pan

ipat

Refi

nery

Add

@

14.4

2 %

Excis

e D

uty

(

inclu

siv

e o

f Ed

ucati

on

cess )

Add

@ 2 %

Cen

tral

Sale

Tax

Ad

d @

6.0

5%

P

un

jab

Sale

Tax

Cart

ag

e b

y R

oad

Pan

ipat

Refi

nery

to m

idd

le o

f th

e

reach

32

1 K

ms.@

R

s.1

.50

per.

Metr

ic t

on

ne

per

Km

s.

Rates for supply

( Amount in Rs.)

Viscosity Grade -10 ( 80/100 grade)

Viscosity Grade-30 ( 60/70 grade)

Crumb Rubber Modified Bitumen - 50Crumb Rubber Modified Bitumen - 55Crumb Rubber Modified Bitumen - 60Bitumen Emulsion - Rapid Setting

Bitumen Emulsion-Medium Setting

Bitumen Emulsion-Slow Setting

Panipat Ropar Bye pass RD 0.0 Site of work!_____388___ ! _____!_______________________5.60/2

Certified that the lead provided in the analysis of rate is the shortest lead and rate of bitumen provided in the analysis of rate is the latest rate.

Page 2: Standard Data Book - Rate Analysis

Const. Division PWD B&R

Roopnagar. Roopnagar.

Provincial Sub Division PWD B&R,

Page 3: Standard Data Book - Rate Analysis

CONVERSION FROM HOUR RATE TO TONNE-KM RATE1 Transit Mixer (4.0/4.5 cum)

Rate of transit mixer per hour 909Wt of concrete in one load 10.8 Tonne (2.4 tonne / cum)Analysis of time

Positioning of transit mixer at batching plant 1 MinLoading from batching plant 2 MinManeuvering, reversing, turning for return 2 MinWaiting time, unforseen contingencies etc. 2 MinTotal 7 MinSpeed with load 25 Km/hourSpeed while returning empty 35 Km/hourHence distance travelled in one hour 30 KmDistance travelled in 53 minutes 26.5 KmHence cost of (10.8 x 26.5) tonne-Km is 909Cost per tonne-Km = 3.176101

Say 3.2

2 Transit Mixer (3.0 cum)Rate of transit mixer per hour 833Wt of concrete in one load 7.2 Tonne (2.4 tonne / cum)Analysis of time

Positioning of transit mixer at batching plant 1 MinLoading from batching plant 2 MinManeuvering, reversing, turning for return 2 MinWaiting time, unforseen contingencies etc. 2 MinTotal 7 MinSpeed with load 25 Km/hourSpeed while returning empty 35 Km/hourHence distance travelled in one hour 30 KmDistance travelled in 53 minutes 26.5 KmHence cost of (7.2 x 26.5) tonne-Km is 833Cost per tonne-Km = 4.365828

Say 4.43 Truck 5.5 cum per 10 tonnes

Rate per tonne-Km 3.00Rate of one load per km= 22

Analysis of timePositioning of tipper at loading point 1 Min

13 MinManeuvering, reversing, dumping and turning for return 2 MinWaiting time, unforeseen contingencies etc 4 MinTotal 20 MinSpeed with load 25 Km/hourSpeed while returning empty 35 Km/hourHence distance travelled in one hour 30 KmDistance travelled effectively in 1 hour (in 40 minutes) 20 KmHence rate per hour 440

Say 440

3 Tipper 5 cum per 10 tonnesRate per tonne-Km 3.00Rate of one load per km= 24

Analysis of timePositioning of tipper at loading point 1 Min

Loading by front end loader 1 cum bucket capacity @ 25 cum per hour

Page 4: Standard Data Book - Rate Analysis

13 MinManeuvering, reversing, dumping and turning for return 2 MinWaiting time, unforeseen contingencies etc 4 MinTotal 20 MinSpeed with load 25 Km/hourSpeed while returning empty 35 Km/hourHence distance travelled in one hour 30 KmDistance travelled effectively in 1 hour (in 40 minutes) 20 KmHence rate per hour 480

Say 480

Loading by front end loader 1 cum bucket capacity @ 25 cum per hour

Page 5: Standard Data Book - Rate Analysis

DescriptionWater Tanker Wet Mix Plant

70- hp 75 TPH(A )OWNERSHIP CHARGES

i Factory cost including packing 800,000 2,000,000 ii deduct solvage value 15%( I) 120,000 300,000 iii Total investment to be depriciated (I)-(ii) 680,000 1,700,000 iv Economic life of machine in Hours 10,000 9,000 v Depreciation per hour iii/iv 68 189 vi storage charges per hour (1% of v) 1 2 vii Total ownership charges 69 191

(B) OPERATIONAL CHARGESi Repair chrges per hour including maintenance

and replacement of tyres (150% of v) 102 283

(C) RUNNING CHARGESi Operators (per month wage) 4,500 5,000 ii Cleaner/ Helper (per month wage) 3,000 3,000

vii Wages per hour 50 53

(D) CONSUMPTION CHARGES/HOURi Diesel consumption/electrical consumption Rs 42/ 37.41 224 748 ii Lubricating oil 10% of fuel cunsumption 22 75 iii Oil,grease,& cotton waste 10% of fuel consumption 22 75

269 898

(E) INTEREST & INSURANCE 10% 8 22

(F) OVERHEADS 8% on (A+B+C+D)(Included in item rate analysis)

Rate/Hour 498 1,448

Page 6: Standard Data Book - Rate Analysis

Generator Generator Generator Generator250 KVA 125 KVA 100 KVA 33 KVA

Ma

rke

t ra

te

1050000 700000 575000 180000 157,500 105,000 86,250 27,000 892,500 595,000 488,750 153,000

10000 10000 10000 10000 89 60 49 15 1 1 0 0 90 60 49 15

134 89 73 23

4,000 4,000 4,000 4,000 3,000 3,000 3,000 3,000 47 47 47 47

935 374 374 150 94 37 37 15 94 37 37 15 1,122 449 449 180

11 7 6 2

1,403 652 624 5000 266

Joint cutting machine

Page 7: Standard Data Book - Rate Analysis

Page 1 of 280

Sl. No. Description of Machine Activity Output Unit Rate

P&M-001 Air Compressor General Purpose capacity in cfm 170/250 hour 319

P&M-002 Batching and Mixing Plant (a) 30 cum capacity Concrete Mixing cum/hour 20 hour 2232

P&M-003 Concrete Mixing cum/hour 13 hour 1860

P&M-004 Bitumen Pressure Distributor Applying bitumen tack coat sqm/hour 1750 hour 1073

P&M-005 Bitumen Boiler oil fired Bitumen Spraying capacity in litre 1500 hour 198

P&M-006 Concrete Paver Finisher with 40 HP Motor Paving of concrete surface cum / hour 20 hour 2868

P&M-007 Concrete Pump of 45 & 30 cum capacity Pumping of concrete cum / hour 33 / 22 hour 256

P&M-008 Concrete Bucket For Pouring concrete capacity in cum 1 hour 16

P&M-009 Concrete Mixer (a) 0.4/0.28 cum Concrete Mixing cum/hour 2.5 hour 233

P&M-010 Concrete Mixer (b) 1 cum Concrete Mixing cum/hour 7.5 hour 233

P&M-011 Crane (a) 80 tonnes Lifting Purpose hour 1279

P&M-012 Cranes b) 35 tonnes Lifting Purpose hour 853

P&M-013 Cranes c) 3 tonnes Lifting Purpose hour 357

P&M-014 Dozer D - 80 - A 12 Spreading /Cutting / Clearing cum/hour 300/ 150/250 hour 3720

P&M-015 Dozer D - 50 - A 15 Spreading /Cutting / Clearing cum/hour 200/ 120/150 hour 2206

P&M-016 Emulsion Pressure Distributor Applying emulsion tack coat sqm/hour 1750 hour 800

P&M-017 Front End loader 1 cum bucket capacity cum/hour 60 /25 hour 806

P&M-018 Generator (a) 125 KVA Genration of electric Energy KVA 100 hour 652

P&M-019 Generator( b) 63 KVA Genration of electric Energy KVA 50 hour 535

P&M-020 GSB Plant 50 cum Producing GSB cum/hour 40 hour 1039

P&M-021 Hotmix Plant - 120 TPH capacity DBM/BM/SDC/ Premix cum/hour 40 hour 23405

P&M-022 Hotmix Plant - 100 TPH capacity DBM/BM/SDC/ Premix cum/hour 30 hour 17309

P&M-023 Hotmix Plant - 60 to 90 TPH capacity DBM/BM/SDC/ Premix cum/hour 25 hour 13842

P&M-024 Hotmix Plant - 40 to 60 TPH capacity DBM/BM/SDC/ Premix cum/hour 17 hour 11083

P&M-025 Hydraulic Chip Spreader Surface Dressing sqm/hour 1500 hour 2635

P&M-026 Hydraulic Excavator of 1 cum bucket cum/hour 60 /60 /60 hour 1302

P&M-027 Integrated Stone Crusher 100THP Crushing of Spalls TPH 100 hour 8665

P&M-028 Integrated Stone Crusher 200 HP Crushing of Spalls TPH 200 hour 18228

P&M-029 Kerb Casting Machine Kerb Making Rm/hour 80 hour 310

P&M-030 Mastic Cooker Mastic Wearing coat capacity in tonne 1 hour 62

P&M-031 Mechanical Broom Hydraulic Surface Cleaning sqm/hour 1250 hour 357

P&M-032 Motor Grader 3.35 mtr blade cum/hour 200/200/50/50 hour 2395

P&M-033 Mobile slurry seal equipment Mixing and laying slurry seal sqm/hour 2700 hour 1008

P&M-034 cum/hour 40 hour 2674

P&M-035 Paver Finisher Mechanical 100 TPH cum/hour 40/30 hour 975

P&M-036 Piling Rig with Bantonite Pump Rm/hour 2 to 3 hour 5464

P&M-037 Pneumatic Road Roller Rolling of Asphalt Surface cum/hour 25 hour 1243

P&M-038 Pneumatic Sinking Plant Pneumatic Sinking of wells cum/hour 1.5 to 2.00 hour 4170

P&M-039 Pot Hole Repair Machine Repair of potholes cum/hour 4 hour 907

P&M-040 Prestressing Jack with Pump & access Stressing of steel wires/stands hour 129

P&M-041 Ripper Scarifying cum/hour 60 hour 28

P&M-042 Rotavator Scarifying cum/hour 25 hour 17

P&M-043 Road marking machine Road marking Sqm/hour 100 hour 93

P&M-044 Smooth Wheeled Roller 8 tonne cum/hour 70/25 hour 460

P&M-045 Tandem Road Roller Rolling of Aspalt Surface cum/hour 30 hour 1144

P&M-046 Tipper - 5 cum Capacity in cum 5.5 km 6.78

P&M-047 Tipper - 5 cum Capacity in cum 5.5 tonne.km 0.678

P&M-048 Tipper - 5 cum Capacity in cum 5.5 hour 339

(A) Usage Rates of Plant and Machinery (based on 2010 Common Schedule of Rates, Public Works Department, Govt. of Punjab and

Premium @13% as on December 2011 as per notification dated 05 December 2011)

Output of Machine

Batching and Mixing Plant (b) 15 - 20 cum capacity

Soil loading / Aggregate loading

Soil Ordinary/Soil Marshy / Soil Unsuitable

Clearing /Spreading /GSB /WBM

Paver Finisher Hydrostatic with sensor control 100 TPH

Paving of DBM/ BM/SDC/ PremixPaving of WMM /Paving of DLC0.75 m dia to 1.2 m dia Boring attachment

Soil Compaction /BM Compaction

Transportation of soil, GSB, WMM, Hotmix etc.

Transportation of soil, GSB, WMM, Hotmix etc.

Transportation of soil, GSB, WMM, Hotmix etc.

Page 8: Standard Data Book - Rate Analysis

Page 2 of 280

P&M-049 Transit Mixer 4.0/4.5 cum cum/hour 4.5 hour 1017

P&M-050 Transit Mixer 4/4.5 cum cum/hour 4.5 tonne.km 2.034

P&M-051 Transit Mixer 3.0 cum cum/hour 3 hour 932.25

P&M-052 Transit Mixer 3.0 cum cum/hour 3 tonne.km 1.8645

P&M-053 Tractor Pulling capacity in HP 50 hour 282.5

P&M-054 Tractor with Rotevator Rate of Tractor + Rotevator hour 282.5

P&M-055 Tractor with Ripper Rate of Tractor 6+ Ripper hour 282.5

P&M-056 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 km 24.5775

P&M-057 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 hour 315.27

P&M-058 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 tonne.km 2.45775

P&M-059 Vibratory Roller 8 tonne Earth or soil / GSB / WBM cum/hour 100/60/60 hour 1541

P&M-060 Water Tanker Water Transport capacity in KL 6 hour 200

P&M-061 Water Tanker Water Transport capacity in KL 6 km 7.0625

P&M-062 Wet Mix Plant 60 TPH Wet Mix cum/hour 25 hour 1317.015

Sl. No. Description of Machine Unit Rate

P&M-063 Air compressor with pneumatic chisel attachment for cutting hard clay. hour 740.15

P&M-064 Batch type cold mixing plant 100-120 TPH capacity producing an average output of 75 tonne per hour hour 25594.5

P&M-065 Belt conveyor system hour 100

P&M-066 Boat to carry atleast 20 persons hour 100

P&M-067 Cement concrete batch mix plant @ 175 cum per hour (effective output) hour 14644.8

P&M-068 Cement concrete batch mix plant @ 75 cum per hour hour 9153

P&M-069 Cold milling machine @ 20 cum per hour hour 300

P&M-070 Crane 5 tonne capacity hour 116.53125

P&M-071 Crane 10 tonne capacity hour 233.0625

P&M-072 Crane 15 tonne capacity hour 349.59375

P&M-073 Crane 20 tonne capacity hour 466.125

P&M-074 Crane 40 T capacity hour 932.25

P&M-075 Crane with grab 0.75 cum capacity hour 1073.5

P&M-076 Compressor with guniting equipment along with accessories hour 349.17

P&M-077 Drum mix plant for cold mixes of appropriate capacity but not less than 75 tonnes/hour. hour 3661.2

P&M-078 Epoxy Injection gun hour 100

P&M-079 Generator 33 KVA hour 406.8

P&M-080 Generator 100 KVA hour 762.75

P&M-081 Generator 250 KVA hour 1906.875

P&M-082 hour 1000

P&M-083 Joint Cutting Machine with 2-3 blades (for rigid pavement) hour 200

P&M-084 Jack for Lifting 40 tonne lifting capacity. day 500

P&M-085 Piling rig Including double acting pile driving hammer (Hydraulic rig) hrs 5974.875

P&M-086 Plate compactor hour 101.7

P&M-087 Snow blower equipment 140 HP @ 600 cum per hour hour 1000

P&M-088 Texturing machine (for rigid pavement) hour 500

P&M-089 Truck Trailor 30 tonne capacity hour 847.50

P&M-090 Truck Trailor 30 tonne capacity t.km 0.678

P&M-091 Tunnel Boring machine hour 5000

P&M-092 Vibrating Pile driving hammer complete with power unit and accessories. hour 1000

P&M-093 Wet Mix Plant 100 TPH hour 2195.025

P&M-094 Wet Mix Plant 75 TPH 2195.025

Transportation of Concrete Mix to site

Transportation of Concrete Mix to site

Transportation of Concrete Mix to site

Transportation of Concrete Mix to site

Induction, deinduction and erection of plant and equipment including all components and accessories for pneumatic method of well sinking.

Page 9: Standard Data Book - Rate Analysis

Page 3 of 280

Sl. No. Description of Labour Unit Rate

L-01 Blacksmith (IInd class) day 230.00

L-02 Blacksmith (Ist class)/ Welder/ Plumber/ Electrician day 264.50

L-03 Blaster (Stone cutter) day 264.50

L-04 Carpenter I Class day 264.50

L-05 Chiseller (Head Mazdoor) day 264.50

L-06 Driller (Jumper) day 264.50

L-07 Diver day 264.50

L-08 Fitter day 230.00

L-09 Mali day 264.50

L-10 Mason (IInd class) day 230.00

L-11 Mason (Ist class) day 223.36

L-12 Mate / Supervisor day 151.44

L-13 Mazdoor day 136.69

L-14 Mazdoor/Dresser (Semi Skilled) day 230.00

L-15 Mazdoor/Dresser/Sinker (Skilled) day 164.69

L-16 Medical Officer day 304.20

L-17 Operator(grouting) day 264.50

L-18 Painter I class day 223.36

L-19 Para medical personnel day 264.50

(C) Materials

Sl. No. Description Unit Rate

M-001 Stone Boulder of size 150 mm and below at Cruser Plant cum 919

M-002 Supply of quarried stone 150 - 200 mm size for Hand Broken at site cum 494.68

M-003 Boulder with minimum size of 300 mm for Pitching at Site cum 494.68

M-004 Coarse sand at Mixing Plant cum 828

M-005 Coarse sand at Site cum 710.46

M-006 Fine sand at Site cum 476.8

M-007 Moorum at Site cum 461.9

M-008 Gravel/Quarry spall at Site Cum 921

M-009 Granular Material or hard murrum for GSB works at Site Cum 727.79

M-010 Granular Material or hard murrum for GSB works at Mixing Plant Cum 461.9

(B) Labour (based on PUNJAB GOVT. GAZ. (EXTRA), NOVEMBER 15,2012, DEPARTMENT OF LABOUR, (LABOUR BRANCH), No.

S.O. 94/C.A. 1111948/Ss.3and5/2012.-dated 15th November, 2012)

Page 10: Standard Data Book - Rate Analysis

Page 4 of 280

M-011 Fly ash conforming to IS: 3812 ( Part II & I) atHMP Plant / Batching Plant / Crushing Plant Cum 8.94

M-012 Filter media/Filter Material as per Table 300-3 (MoRT&H Specification) Cum 894

Description Unit Rate at Site

M-013 Close graded Granular sub-base Material 53 mm to 9.5 mm cum 867 836.17

M-014 Close graded Granular sub-base Material 37.5 mm to 9.5 mm cum 867 867

M-015 Close graded Granular sub-base Material 26.5 mm to 9.5 mm cum 867 867

M-016 Close graded Granular sub-base Material 9.5 mm to 4.75 mm cum 867 867

M-017 Close graded Granular sub-base Material 9.5 mm to 2.36 mm cum 867 836.17

M-018 Close graded Granular sub-base Material 4.75mm to 2.36 mm cum 867 867

M-019 Close graded Granular sub-base Material 4.75mm to 75 micron mm 867 867

M-020 Close graded Granular sub-base Material 2.36 mm cum 867 836.17

M-021 Stone crusher dust finer than 3mm with not more than 10% passing 0.075 sieve. cum 476.8 476.8

M-022 Coarse graded Granular sub-base Material 2.36 mm & below cum 992.3 867

M-023 Coarse graded Granular sub-base Material 4.75mm to 75 micron mm 867 867

M-024 Coarse graded Granular sub-base Material 4.75 mm to 2.36 mm cum 867 867

M-025 Coarse graded Granular sub-base Material 9.5 mm to 4.75 mm cum 867 867

M-026 Coarse graded Granular sub-base Material 26.5 mm to 4.75 mm cum 867 867

M-027 Coarse graded Granular sub-base Material 26.5 mm to 9.5 mm cum 867 867

M-028 Coarse graded Granular sub-base Material 37.5 mm to 9.5 mm cum 867 867

M-029 Coarse graded Granular sub-base Material 53 mm to 26 .5mm cum 867 867

M-030 Aggregates below 5.6 mm cum 992.3 1066.89

M-031 Aggregates 22.4 mm to 2.36 mm cum 1012 1001

M-032 Aggregates 22.4 mm to 5.6 mm cum 1001 1001

M-033 Aggregates 45 mm to 2.8 mm cum 968.6 968.6

M-034 Aggregates 45 mm to 22.4 mm cum 1007.77 920.5

M-035 Aggregates 53 mm to 2.8 mm 990.25 990.25

M-036 Aggregates 53 mm to 22.4 mm cum 959 959

M-037 Aggregates 63 mm to 2.8 mm cum 982 982

M-038 Aggregates 63 mm to 45 mm cum 949 949

M-039 Aggregates 90 mm to 45 mm cum 938 938

M-040 Aggregates 10 mm to 5 mm cum 1078.94 987

M-041 Aggregates 11.2 mm to 0.09 mm cum 987 987

M-042 Aggregates 13.2 mm to 0.09 mm cum 1001 1001

M-043 Aggregates 13.2 mm to 5.6 mm cum 998.5 998.5

M-044 Aggregates 13.2 mm to 10 mm cum 1103.6 1016.5

M-045 Aggregates 20 mm to 10 mm cum 1103.6 1016.5

M-046 Aggregates 25 mm to 10 mm cum 1103.6 986

M-047 Aggregates 19 mm to 6 mm cum 1001 1001

M-048 Aggregates 37.5 mm to 19 mm cum 956 956

M-049 Aggregates 37.5 mm to 25 mm cum 1011.94 920.5

M-050 Aggregates 6 mm nominal size cum 969 969

M-051 Aggregates 10 mm nominal size cum 1005 1005

M-052 Aggregates 13.2/12.5 mm nominal size cum 1028 1028

M-053 Aggregates 20 mm nominal size cum 1028 1028

M-054 Aggregates 25 mm nominal size cum 925 925

M-055 Aggregates 40 mm nominal size cum 916 916

Sl. No. Description Unit Rate

M-056 AC pipe 100 mm dia metre 65

M-057 Acrylic polymer bonding coat litre 485

M-058 Alluminium Paint litre 132.61

Rate at Plant (HMP/Batching

)

Page 11: Standard Data Book - Rate Analysis

Page 5 of 280

M-059 Aluminium alloy plate 2mm Thick sqm 425

M-060 Aluminium alloy/galvanised steel tonne 54574

M-061 sqm 6064

M-062 Aluminium studs 100 x 100 mm fitted with lense reflectors nos 546

M-063 Barbed wire kg 65.56

M-064 Bearing (Cost of parts) nos 1213

M-065 Bearing (Cast steel rocker bearing assembly of 250 tonne ) nos 50000

M-066 nos 15000

M-067 Bearing (Forged steel roller bearing of 250 tonne nos 41309

M-068 nos 41309

M-069 Bearing (PTFE sliding plate bearing assembly of 80 tonnes ) nos 16378

M-070 Bearing (Supply of sliding plate bearing of 80 tonne) nos 16378

M-071 Bentonite kg 4.1

M-072 Binding wire kg 100

M-073 Bitumen ( CRMB 55) tonne 55145

M-074 Bitumen (60-70 grade) VG -30 tonne 55132

M-075 Bitumen (80-100 grade ) VG-10 tonne 56122

M-076 Bitumen (Cutback ) tonne 47937

M-077 Bitumen (emulsion) tonne 49915

M-078 Bitumen (modified graded) tonne 38740

M-079 Brick each 4.41818

M-080 C.I.shoes for the pile kg 59.6

M-081 Cement tonne 5000

M-082 Cold twisted bars (HYSD Bars) tonne 45000

M-083 Coller for joints 300 mm dia nos 146

M-084 Compressible Fibre Board(20mm thick) sqm 486

M-085 Connectors/ Staples each 61

M-086 Copper Plate(12m long x 250mmwide) kg 290.55

M-087 Corrosion resistant Structural steel tonne 46526

M-088 Corrugated sheet, 3 mm thick, "Thrie" beam section railing kg 49

M-089 Credit for excavated rock found suitable for use cum 37

M-090 Curing compound liter 607

M-091 Delineators from ISI certified firm as per the standard drawing given in IRC - 79 each 834.4

M-092 Earth Cost or compensation for earth taken from private land cum 28

M-093 metre 6064

M-094 Electric Detonators @ 1 detonator for 1/2 gelatin stick of 125 gms each 100 nos 1456

M-095 Epoxy compound with accessories for preparing epoxy mortar kg 486

M-096 Epoxy mortar kg 425

M-097 Epoxy primer kg 417.2

M-098 Epoxy resin-hardner mix for prime coat kg 486

M-099 Flag of red color cloth 600 x 600 mm each 91

M-100 Flowering Plants each 61

M-101 Galvanised MS flat clamp nos 25

M-102 Galvanised steel wire crates of mesh size 100 mm x 100 mm woven with 4mm dia. GI wire in rolls of required size. sqm 122

M-103 Galvanised structural steel plate 200 mm wide, 6 mm thick, 24 m long kg 61

M-104 Gelatin 80% kg 146

M-105 Geo grids sqm 607

M-106 Geomembrane sqm 607

M-107 Geonets sqm 607

M-108 Geotextile sqm 37.25

M-109 Geotextile filter fabric sqm 37.25

M-110 GI bolt 10 mm Dia nos 13

M-111 Grouting pump with agitator hour 304

Aluminium sheeting fixed with encapsulated lens type reflective sheeting including 2% towards lettering, cost of angle iron, cost of drilling holes, nuts, bolts etc.and signs as applicable

Bearing (Elastomeric bearing assembly consisting of 7 internal layers of elastomer bonded to 6 nos. internal reinforcing steel laminates by the process of vulcanisation,)

Bearing (Pot type bearing assembly consisting of a metal piston supported by a disc, PTFE pads providing sliding surfaces against stainless steel mating together with cast steel assemblies/fabricated structural steel assemblies duly painted with all components

Elastomeric slab seal expansion joint assembly manufactured by using chloroprene, elastomer for elastomeric slab unit conforming to clause 915.1 of IRC: 83 (part II),

Page 12: Standard Data Book - Rate Analysis

Page 6 of 280

M-112 Grass (Doob) kg 7

M-113 Grass (Fine) kg 13

M-114 HDPE pipes 75mm dia metre 607

M-115 HDPE pipes 90mm dia metre 607

M-116 Hedge plants each 61

M-117 Helical pipes 600mm diameter metre 2426

M-118 Hot applied thermoplastic compound litre 150

M-119 HTS strand tonne 57453

M-120 Joint Sealant Compound kg 607

M-121 Jute netting, open weave, 2.5 cm square opening for seeding and Mulching sqm 61

M-122 LDO for steam curing litre 43

M-123 M.S. Clamps nos 13

M-124 M.S. Clamps kg 52.15

M-125 M.S.shoes @ 35 Kg per pile of 15 m kg 37

M-126 Mild Steel bars tonne 47307.5

M-127 metre 1820

M-128 metre 1820

M-129 Nipples 12mm nos 243

M-130 Nuts and bolts kg 64.07

M-131 Paint litre 192.81

M-132 Pavement Marking Paint litre 117.16

M-133 Paving Fabric sqm 225

M-134 Perforated geosynthetic pipe 150 mm dia metre 182

M-135 Perforated pipe of cement concrete, internal dia 100 mm metre 243

M-136 Pesticide kg 1820

M-137 Pipes 200 mm dia, 2.5 m long for drainage metre 243

M-138 Plastic sheath, 1.25 mm thick for dowel bars sqm 61

M-139 Plastic tubes 50 cm dia, 1.2 m high nos 3639

M-140 Polymer braids metre 364

M-141 Pre moulded Joint filler,25 mm thick for expansion joint. sqm 965

M-142 Pre-coated stone chips of 13.2 mm nominal size cum 1213

M-143 metre 668

M-144 Pre-moulded asphalt filler board sqm 425

M-145 Pre-packed cement based polymer concrete of strength 45 Mpa at 28 days kg 49

M-146 Primer kg 102.94

M-147 Quick setting compound kg 364

M-148 Random Rubble Stone cum 2604.51

M-149 RCC Pipe NP 4 heavy duty non presure pipe 1000 mm dia metre 5000

M-150 RCC Pipe NP 4 heavy duty non presure pipe 1200 mm dia metre 4452

M-151 RCC Pipe NP 4 heavy duty non presure pipe 300 mm dia metre 1149

M-152 Reflectorising glass beads kg 75

M-153 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Copper Strips) metre 364

M-154 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Galvanised carbon steel strips) metre 364

M-155 metre 364

M-156 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Stainless steel strips) metre 364

M-157 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. Aluminium strips) metre 364

M-158 Rivets each 101.32

M-159 Sand bags (Cost of sand and Empty cement bag) nos 7

M-160 Sapling 2 m high 25 mm dia each 25

M-161 Scrap tyres of size 900 x 20 nos 364

M-162 Seeds kg 243

M-163 Selected earth cum 43

Modular strip/box seal expansion joint including anchorage catering to a horizontal movement beyond 70 mm and upto 140mm assembly comprising of edge beams, central beam,2 modules chloroprene seal, anchorage elements, support and control system, all steel sections protected against corrosion and installed by the manufacturer or his authorised representative

Modular strip/box seal expansion joint catering to a horizontal movement beyond 140mm and upto 210mm box/box seal joint assembly containing 3 modules/cells and comprising of edge beams, two central beams, chloroprene seal, anchorage elements, support and control system, all steel sections protected against corrosion and installed by the manufacturer or his authorised representative

Preformed continuous chloroprene elastomer or closed cell foam sealing element with high tear strength, vulcanised in a single operation for the full length of a joint to ensure water tightness.

Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Glass reinforced polymer/fibre reinforced polymer/polymeric strips)

Page 13: Standard Data Book - Rate Analysis

Page 7 of 280

M-164 Separation Membrane of impermeable plastic sheeting 125 micron thick sqm 61

M-165 Sheathing duct metre 304

M-166 Shrubs each 7

M-167 Sludge / Farm yard manure @ 0.18 cum per 100 sqm at site of work for turfing cum 364

M-168 Sodium vapour lamp each 1213

M-169 Square Rubble Coursed Stone cum 2705.04

M-170 Steel circular hollow pole of standard specification for street lighting to mount light at 5 m height above deck level each 1213

M-171 Steel circular hollow pole of standard specification for street lighting to mount light at 9 m height above road level each 1820

M-172 Steel drum 300 mm dia 1.2 m high/empty bitumen drum nos 79

M-173 Steel helmet and cushion block on top of pile head during driving. kg 61

M-174 Steel pipe 25 mm external dia as per IS:1239 metre 182

M-175 Steel pipe 50 mm external dia as per IS:1239 metre 364

M-176 Steel wire rope 20 mm kg 61

M-177 Steel wire rope 40 mm kg 61

M-178 Strip seal expansion join metre 7500

M-179 Structural Steel tonne 45000

M-180 Super plastisizer admixture IS marked as per 9103-1999 kg 44.7

M-181 Synthetic Geogrids as per clause 3102.8 and approved design and specifications. sqm 607

M-182 Through and bond stone each 14.453

M-183 Tie rods 20mm diameter nos 49

M-184 Tiles size 300 x 300 mm and 25 mm thick each 15

M-185 Timber cum 24255

M-186 Traffic cones with 150 mm reflective sleeve nos 243

M-187 Tube anchorage set complete with bearing plate, permanent wedges etc nos 6064

M-188 Unstaked lime tonne 4500

M-189 Water KL 10

M-190 Water based cement paint litre 31

M-191 Welded steel wire fabric kg 61

M-192 Wire mesh 50mm x 50mm size of 3mm wire kg 61

M-193 Wooden ballies 2" Dia for bracing each 61

M-194 Wooden ballies 8" Dia and 9 m long each 91

M-195 Wooden packing cum 12000

M-196 Wooden staff for fastening of flag 25 mm dia, one m long each 122

Page 14: Standard Data Book - Rate Analysis

Page 8 of 280

Overheads for Road Works 10%

Contractors profit for Road Works 10%

Overheads for Bridge Works 20%

Overheads for Bridge Works (Rehabilitation) 25%

Contractors profit for Bridge Works 10%

Lead from Mixing Plant to working site 1 km

Lead for E/W borow area to site 20 km

Lead for fly ash from source to site 53 km

for input of Overheads or Contractors profit please type in collum C as like below

Type symble of apostrope(') then input value then one space then symble of percentage (%) for example '08 %

Page 15: Standard Data Book - Rate Analysis

Page 9 of 280

Items No. Summary of Rates calculated and used for analysis of rates of other items Unit Rate

Item 8.3 Printing new letter and figures of any shade (ii) English Roman 0.30

Item 8.8 Painting Two Coats on New Concrete Surfaces sqm 40.00

Item 8.9 Painting angle iron post two coats sqm 46.00

Item 12.6 (B) Cement mortor 1:2 (Excluding OH & CP) cum 4,152.00

Item 12.6 (A) Cement mortor 1:3 (Excluding OH & CP) cum 3,425.00

Item 12.6 (D) Cement mortor 1:6 (Excluding OH & CP) cum 2,422.00

Item 12.7 (A ) Course Rubble masonary in cement mortor 1:3 (including OH & CP) cum 6,211.00

Item 12.7 (Addl) B) Random Rubble masonary in cement mortor 1:6 (including OH & CP) cum 5,610.00

Item 12.8 (A) PCC Grade M15 including OH & CP for Open Foundation by Mixer cum 4,228.00

Item 12.8 (A) cum 3,080.00

Item 12.8 (B) PCC cum 3,390.00

Item 12.8 (C) cum 3,443.00

Item 12.8 (C) RCC RCC Grade M20 including OH & CP for Open Foundation by Batching Plant cum 4,650.00

Item 12.8 (C) cum 3,388.00

Item 12.8 (D) cum 3,667.00

Item 12.8 (D) PCC Grade M25 including OH & CP for Open Foundation by Batching Plant cum 4,949.00

Item 12.8 (D) cum 3,614.00

Item 12.8 (E) cum 3,723.00

Item 12.8 (E) cum 3,740.00

Item 12.8 (F) cum 3,697.00

Item 12.8 (F) cum 3,641.00

Item 12.8 (G) cum 3,740.00

Item 12.8 (G) cum 3,686.00

Item 12.8 (H) cum 3,816.00

Item 12.8 (H) RCC Grade M35 including OH & CP for Open Foundation by Batching Plant cum 3,952.00

Item 12.8 (H) RCC Grade M35 excluding OH & CP for Open Foundation by Batching Plant cum 5,217.00

Item 12.8 (H) cum 3,838.00

Item 12.11 (C) i cum 3,719.00

Item 12.11 (C) i cum 3,558.00

Item 12.11 (C) ii cum 3,874.00

Item 12.11 (C) ii cum 3,712.00

Item 12.11 (C) iii cum 3,904.00

Item 12.11 (C) iii cum 3,743.00

Item 12.11 (C) iv cum 3,974.00

Item 12.11 (C) iv PCC Grade M35 including OH & CP for Well Foundation (Bottom Plug) by Batching Plant cum 5,260.00

Item 12.11 (C) iv cum 3,812.00

Item 12.11 (F) iv PCC Grade M35 including OH & CP for Well Foundation (Well Cap) by Batching Plant cum 5,114.00

Item No. 3.13 Excavation for Structures (Manual Means) cum 138.00

Item No. 3.13 Excavation for Structures (Mechenical Meanse) cum 36.00

Item 14.1(A) RCC Grade M20 for super-structure including OH & CP by Batching Plant cum 5,317.00

Item 14.1(B) RCC Grade M20 for super-structure including OH & CP by Batching Plant cum 5,783.00

Item 14.1(E) RCC Grade M20 for super-structure including OH & CP by Batching Plant cum 6,171.83

Item 14.1(C) RCC Grade M30 for super-structure including formwork and excluding OH & CP by Batching Plant cum 4,428.00

Item 14.1(C) RCC Grade M30 for super-structure excluding formwork and excluding OH & CP by Batching Plant cum 3,690.00

Item 14.2 A Supplying ,fitting and placing HYSD bar reinforcement in super-structure exncluding OH & CP tonne 50,004.00

Item 13.6 Supplying, fitting and placing HYSD including OH & CP for sub-structure tonne 65,101.00

Item 5.17 Fog Seal sqm 53.00

Item 5.21 Case-I Crack Prevention courses. Case-I Stress Absorbing Membrane (SAM) crack width less than 6 mm sqm 57.00

Item 5.21 Case-II sqm 67.00

Item 5.21 Case-IV sqm 88.00

Item 5.21 Case-IV Crack Prevention courses. Case-IV Bitumen Impregnated Geotextile sqm 124.00

Item 5.15 Case-I Slurry Seal Case-I 5 mm thickness sqm 82.00

Item 5.15 Case-II Slurry Seal Case-II 3 mm thickness sqm 57.00

Item 5.15 Case-III Slurry Seal Case III 1.5 mm thickness sqm 35.00

Item 5.9 Case-I Surface Dressing Case-I 19 mm nominal chipping size sqm 104.00

per cm height per letter

PCC Grade M15 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by MixerPCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by MixerRCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching PlantPCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching PlantRCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by MixerRCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching PlantPCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by MixerPCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching PlantRCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by MixerRCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching PlantRCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching PlantPCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by MixerPCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by Batching PlantPCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by MixerPCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by Batching PlantPCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by MixerPCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by Batching PlantPCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant

Crack Prevention courses. Case-II Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mmCrack Prevention courses. Case-III Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked area above 50 %

Page 16: Standard Data Book - Rate Analysis

Page 10 of 280

Item 5.9 Case-II Surface Dressing Case-II 13 mm nominal size chipping sqm 85.00

Page 17: Standard Data Book - Rate Analysis

Page 11 of 280

Summary of Rate AnalysisItem No. Descriptions Unit Rate

CHAPTER-2

SITE CLEARANCE

2.1

(i) Girth from 300 mm to 600 mm each 137.00(ii) Girth from 600 mm to 900 mm each 259.00

(iii) Girth from 900 mm to 1800 mm each 482.00(iv) Girth above 1800 mm each 896.00

2.2 Clearing Grass and Removal of Rubbish hectare 8636.00

2.3

(ii) By Mechanical Means

A In area of light jungle hectare 49142.00

2.4

(i) Lime /Cement Concrete

I By Manual Means

A Lime Concrete, cement concrete grade M-10 and below cum 212.00B Cement Concrete Grade M-15 & M-20 cum 247.00C Prestressed / Reinforced cement concrete grade M-20 & above cum 623.00

II By Mechanical Means for items No. 202( b) & ( c)

A Cement Concrete Grade M-15 & M-20 cum 372.00B Prestressed / Reinforced cement concrete grade M-20 & above cum 634.00

(ii) Dismantling Brick / Tile work

A In lime mortar cum 143.00B In cement mortar cum 177.00C In mud mortar cum 129.00D Dry brick pitching or brick soling cum 122.00

(iii) Dismantling Stone Masonry

A Rubble stone masonry in lime mortar cum 157.00B Rubble stone masonry in cement mortar. cum 177.00C Rubble Stone Masonry in mud mortar. cum 143.00D Dry rubble masonry cum 136.00E Dismantling stone pitching/ dry stone spalls. cum 129.00F Dismantling boulders laid in wire crates including opening of crates and stacking dismantled materials. cum 143.00

(iv) Wood work wrought framed and fixed in frames of trusses upto a height of 5 m above plinth level cum 343.00(v) Steel work in all types of sections upto a height of 5 m above plinth level excluding cutting of rivet.

A Including dismembering tonne 836.00B Excluding dismembering. tonne 603.00C Extra over item No( V ) A and( V ) B for cutting rivets. tonne 6.00

(vi) Scraping of bricks dismantled from brick work including stacking.

AIn lime/Cement mortar

605.00

BIn mud mortar

216.00

(vii) Scraping of Stone from dismantled stone masonry

A In cement and lime mortar cum 243.00B In Mud mortar cum 51.00

(viii) Scarping plaster in lime or cement mortar from brick/ stone masonry sqm 8.00

(ix)

A Up to 600 mm dia metre 90.00B Above 600 mm to 900 mm dia metre 121.00C Above 900 mm metre 208.00

Cutting of Trees, including Cutting of Trunks, Branches and Removal (Cutting of trees, including cutting of trunks, branches and removal of stumps, roots, stacking of serviceable material with all lifts and up to a lead of 1000 mtrs and earth filling in the depression/pit.)

Clearing and Grubbing Road Land .(Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned up to a lead of 1000 metres including removal and disposal of top organic soil not exceeding 150 mm in thickness.)

Dismantling of Structures (Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 metres)

1000 numbers

1000 numbers

Removing all type of hume pipes and stacking within a lead of 1000 metres including earthwork and dismantling of masonry works.

Page 18: Standard Data Book - Rate Analysis

Page 12 of 280

Summary of Rate AnalysisItem No. Descriptions Unit Rate

2.5

I By Manual Means

A Bituminous courses cum 389.00B Granular courses cum 286.00

II By Mechanical Means

A Bituminous course cum 187.00

2.6 cum 992.00

2.7 metre 43.00

2.8 metre 10.00

2.9 metre 14.00

2.10

A 5th KM stone each 199.00B Ordinary KM Stone each 121.00C Hectometre Stone each 24.00

2.11 metre 27.00

2.12 metre 74.00

2.13 metre 86.00

2.14 each 101.00

Dismantling of Flexible Pavements (Dismantling of flexible pavements and disposal of dismantled materials up to a lead of 1000 metres, stacking serviceable and unserviceable materials separately)

Dismantling of Cement Concrete Pavement (Dismantling of cement concrete pavement by mechanical means using pneumatic tools, breaking to pieces not exceeding 0.02 cum in volume and stock piling at designated locations and disposal of dismantled materials up to a lead of 1000 metres, stacking serviceable and unserviceable materials separately)

Dismantling Guard Rails (Dismantling guard rails by manual means and disposal of dismantled material with all lifts and up to a lead of 1000 metres, stacking serviceable materials and unserviceable materials separately.)

Dismantling Kerb Stone (Dismantling kerb stone by manual means and disposal of dismantled material with all lifts and up to a lead of 1000 metre)

Dismantling Kerb Stone channel (Dismantling kerb stone channel by manual means and disposal of dismantled material with all lifts and up to a lead of 1000 metre)

Dismantling Kilometre Stone (Dismantling of kilometre stone including cutting of earth, foundation and disposal of dismantled material with all lifts and lead upto 1000 m and back filling of pit.)

Dismantling of Fencing (Dismantling of barbed wire fencing/ wire mesh fencing including posts, foundation concrete, back filling of pit by manual means including disposal of dismantled material with all lifts and up to a lead of 1000 metres, stacking serviceable material and unserviceable material separately. )

Dismantling of CI Water Pipe Line (Dismantling of CI water pipe line 600 mm dia including disposal with all lifts and lead upto 1000 metres and stacking of serviceable material and unserviceable material separately under supervision of concerned department)

Removal of Cement Concrete Pipe of Sewer Gutter (Removal of cement concrete pipe of sewer gutter 1500 mm dia under the supervision of concerned department including disposal with all lifts and up to a lead of 1000 metres and stacking of serviceable and unserviceable material separately but excluding earth excavation and dismantling of masonry works.)

Removal of Telephone / Electric Poles and Lines (Removal of telephone / Electric poles including excavation and dismantling of foundation concrete and lines under the supervision of concerned department, disposal with all lifts and up to a lead of 1000 metres and stacking the serviceable and unserviceable material separately)

Page 19: Standard Data Book - Rate Analysis

Page 13 of 280

Summary of Rate AnalysisItem No. Descriptions Unit Rate

CHAPTER-3

EARTH WORK, EROSION CONTROL AND DRAINAGE

3.1 cum 97.00

3.2 cum 133.00

3.3 cum 152.00

3.4 cum 255.00

3.5 cum 292.00

3.6 cum 45.00

3.7 cum 60.00

3.8

A Mechanised cum 362.00B Manual Method cum 736.00

3.9 cum 379.00

3.10 cum 51.00

3.11 cum 46.00

3.12 sqm 143.00

3.13

(i) Ordinary soil

A Manual Means (Depth upto 3 m) cum 138.00B Mechanical Means (Depth upto 3 m) cum 36.00

(ii) Ordinary rock (not requiring blasting)

A Manual Means (Depth upto 3 m) cum 173.00B Mechanical Means cum 49.00

(iii) Hard rock ( requiring blasting )

A Manual Means cum 360.00(iv) Hard rock ( blasting prohibited )

A Mechanical Means cum 472.00(v) Marshy soil

A Manual means ( upto 3 m depth) cum 290.00

Excavation in Soil by Manual Means. (Excavation for roadway in soil using manual means including loading in truck for carrying of cut earth to embankment site with all lifts and lead upto1000 metres.)

Excavation in ordinary rock by manual means (Excavation in ordinary rock using manual means including loading in a truck and carrying of excavated material to embankment site with in all lifts and leads upto 1000 metres )

Excavation in Soil with Dozer with lead upto 100 metres (Excavation for road way in soil by mechanical means including cutting and pushing the earth to site of embankment upto a distance of 100 metres (average lead50 metres), including trimming bottom and side slopes in accordance with requirements of lines, grades and cross sections.)

Excavation in Ordinary Rock with Dozer with lead upto 100 metres (Excavation for roadway in ordinary rock by deploying a dozer, 80 HP including cutting and pushing the cut earth to site of embankment upto a distance of 100 metres ( average lead 50 metres ), trimming bottom and side slopes in accordance with the requirements of lines, grades and cross sections.)

Excavation in Hard Rock (requiring blasting) with disposal upto 1000 metres (Excavation for roadway in hard rock (requiring blasting) by drilling, blasting and breaking, trimming of bottom and side slopes in accordance with requirements of lines, grades and cross sections, loading and disposal of cut road with in all lifts and leads upto 1000 metres )

Excavation in Soil using Hydraulic Excavator CK 90 and Tippers with disposal upto 1000 metres. (Excavation for roadwork in soil with hydraulic excavator of0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m)

Excavation in Ordinary Rockusing Hydraulic ExcavatorCK-90 and Tippers with disposal upto 1000 metres. (Excavation for roadway in ordinary rock with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, transporting to embankment site within all lifts and lead upto 1000 m, trimming bottom and side slopes in accordance with requirements of lines, grades and cross sections.)

Excavation in Hard Rock (blasting prohibited) (Excavation for roadway in hard rock (blasting prohibited) with rock breakers including breaking rock, loading in tippers and disposal within all lifts and lead upto 1000 metres, trimming bottom and side slopes in accordance with requirements of lines, grades and cross sections.)

Excavation in Hard Rock (controlled blasting) with disposal upto 1000 metres (Excavation for roadway in hard rock with controlled blasting by drilling, blasting and breaking, trimming of bottom and side slopes in accordance with requirements of lines, grades and cross sections, loading and disposal of cut road with in all lifts and leads upto 1000 metres )

Excavation in Marshy Soil (Excavation for roadway in marshy soil with hydraulic excavator 0.9 cum bucket capacity including cutting and loading in tippers and disposal with in all lifts and lead upto 1000 metres, trimming of bottom and side slopes in accordance with requirements of lines, grades and cross sections.)

Removal of Unserviceable Soil with Disposal upto 1000 metres (Removal of unserviceable soil including excavation, loading and disposal upto 1000 metres lead but excluding replacement by suitable soil which shall be paid separately as per clause 305.)

Pre-splitting of Rock Excavation Slopes (Carrying out excavation in hard rock to achieve a specified slope of the rock face by controlled use of explosives and blasting accessories in properly aligned and spaced drill holes, collection of the excavated rock by a 80 HP dozer, loading in tipper by a front end loader and disposing of the material with all lifts and lead upto 1000 m, all as specified in clause No. 303)

Excavation for Structures (Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent required and utilising the remaining earth locally for road work.)

Page 20: Standard Data Book - Rate Analysis

Page 14 of 280

Summary of Rate AnalysisItem No. Descriptions Unit Rate

B Mechanical Means cum 106.00

3.14 sqm 14.00

3.15 sqm 4.00

3.16 cum 249.00

3.17 cum 84.00

3.18 cum 293.00

3.19 Compacting Original Ground

Case-I cum 60.00

Case-II :Compacting original ground supporting embankment cum 29.00

3.20 cum 131.00

3.21 cum 91.00

3.22 sqm 16.00

3.23 sqm 129.00

3.24

A Mechanical means metre 56.00B Manual Means metre 35.00

3.25

A Mechanical Means metre 114.00B Manual Means metre 52.00

3.26 metre

3.27 587.00

3.28 metre 171.00

3.29 metre 2356.00

3.30 sqm 1.00

3.31 cum 50.00

3.32 cum 149.00

Scarifying Existing Granular Surface to a Depth of 50 mm by Manual Means (Scarifying the existing granular road surface to a depth of 50 mm and disposal of scarified material within all lifts and leads upto 1000 metres. )

Scarifying existing bituminous surface to a depth of 50 mm by mechanical means (Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of scarified material with in all lifts and lead upto 1000 metres.)

Embankment Construction with Material Obtained from Borrow Pits (Construction of embankment with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2)

Construction of Embankment with Material Deposited from Roadway Cutting (Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of table 300-2)

Construction of Subgrade and Earthen Shoulders (Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2)

Compacting original ground supporting subgrade (Loosening of the ground upto a level of500 mm below the subgrade level, watered, graded and compacted in layers to meet requirement of table 300-2 for subgrade construction.)

Stripping and Storing Top Soil (Stripping, storing of top soil by road side at 15 m internal and re-application on embankment slopes, cut slopes and other areas in localities where the available embankment material is not conducive to plant growth)

Stripping, storing and re-laying top soil from borrow areas in agriculture fields. (Stripping of top soil from borrow areas located in agriculture fields, storing at a suitable place, spreading and re-laying after taking the borrow earth to maintain fertility of the agricultural field, finishing it to the required levels and satisfaction of the farmer.)

Turfing with Sods (Furnishing and laying of the live sods of perennial turf forming grass on embankment slope, verges or other locations shown on the drawing or as directed by the engineer including preparation of ground, fetching of rods and watering)

Seeding and Mulching (Preparation of seed bed on previously laid top soil, furnishing and placing of seeds, fertilizer, mulching material, applying bituminous emulsion at the rate of0.23 litres per sqm and laying and fixing jute netting, including watering for 3 months all as per clause 308)

Surface Drains in Soil (Construction of unlined surface drains of average cross sectional area 0.40 sqm in soil to specified lines, grades, levels and dimensions to the requirement of clause 301 and 309. Excavated material to be used in embankment within a lead of50 metres (average lead 25 metres))

Surface Drains in Ordinary Rock (Construction of unlined surface drain of average cross sectional area 0.4 sqm in ordinary rock to specified lines, grades, levels and dimensions as per approved design and to the requirement of clause 301 to 309. Excavated material to be used in embankment at site.)

Surface Drains in Hard Rock (Rate per metre may be worked out based on quantity of hard rock as per design.)

Sub Surface Drains with Perforated Pipe (Construction of subsurface drain with perforated pipe of 100 mm internal diameter of metal/ asbestos cement/ cement concrete/PVC, closely jointed, perforations ranging from 3 mm to 6 mm depending upon size of material surrounding the pipe, with 150 mm bedding below the pipe and 300 mm cushion above the pipe, cross section of excavation 450 x 550 mm. Excavated material to be utilised in roadway at site )

Aggregate Sub- Surface Drains (Construction of aggregate sub surface drain 300 mm x 450 mm with aggregates conforming to table 300-4, excavated material to be utilised in roadway )

Underground Drain at Edge of Pavement (Construction of an underground drain 1 m x 1 m (inside dimensions) lined with RCC-20 cm thick and covered with RCC slab10 cm in thickness on urban roads)

Preparation and Surface Treatment of formation. (Preparation and surface treatment of formation by removing mud and slurry, watering to the extent needed to maintain the desired moisture content, trimming to the required line, grade, profile and rolling with 8-10 tonne smooth wheeled roller, complete as per clause 310.)

Construction of Rock fill Embankment (Construction of rock fill embankment with broken hard rock fragments of size not exceeding 300 mm laid in layers not exceeding 500 mm thick including filling of surface voids with stone spalls, blinding top layer with granular material, rolled with vibratory road roller, all complete as per clause 313)

Excavation in Hill Area in Soil by Mechanical Means (Excavation in soil in hilly area by mechanical means including cutting and trimming of side slopes and disposing of excavated earth with all lifts and lead upto 1000 metres)

Page 21: Standard Data Book - Rate Analysis

Page 15 of 280

Summary of Rate AnalysisItem No. Descriptions Unit Rate

3.33 cum 224.00

3.34 cum 293.00

3.35

3.36 cum 314.00

Excavation in Hilly Area in Ordinary Rock by Mechanical Means not Requiring Blasting. (Excavation in hilly area in ordinary rock not requiring ballasting by mechanical means including cutting and trimming of slopes and disposal of cut material with all lift and lead upto 1000 metres )

Excavation in Hilly Areas in Hard Rock Requiring Blasting (Excavation in hilly areas in hard rock requiring blasting, by mechanical means including trimming of slopes and disposal of cut material with all lifts and lead upto 1000 metres.)

Work in Urban Roads (The cost of earth work in urban roads inhabited area will be comparatively higher due to following reasons:)

Embankment Construction with Fly ash/Pond ash available from coal or lignite burning Thermal Plants as waste material. (Construction of embankment with fly ash conforming to table 1 of IRC: SP: 58 - 2001 obtained from coal or lignite burning thermal power stations as waste material, spread and compacted in layer of 200mm thickness each at OMC, all as specified in IRC: SP: 58-2001 and as per approved plans.)

Page 22: Standard Data Book - Rate Analysis

Page 16 of 280

Summary of Rate AnalysisItem No. Descriptions Unit Rate

CHAPTER-4

SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS4.1 Granular Sub-base with Close Graded Material (Table:- 400-1)

A

(i) for grading- I Material cum 1606.00

4.3

A By Mechanical Means cum 400.00B By Manual Means cum 376.00

4.4 cum 561.00

4.5 cum 698.00

4.6

(i) For Sub-Base course cum 1953.00

(ii) For Base course cum 1953.00

4.7 sqm 404.00

4.8 cum 1266.00

4.9

A By Manual Means

(i) Grading- I (Using Screening Crushable type such as Moorum or Gravel)

(a) Using Screening Crushable type such as Moorum or Gravel cum 1714.00(b) Using Screening Type-A (13.2mm Agg.) cum 1927.03

(ii) Grading- II (Using Screening Crushable type such as Moorum or Gravel)

(a) Using Screening Crushable type such as Moorum or Gravel cum 1727.00(b) Using Screening Type-A (13.2mm Agg.) cum 1806.00(c) Using Screening Type-B (11.2mm Agg.) cum 1899.00

(iii) Grading- III (Using Screening Crushable type such as Moorum or Gravel)

(a) Using Screening Crushable type such as Moorum or Gravel cum 1741.00(b) Using Screening Type-B (11.2mm Agg.) cum 1914.00

B By Mechanical Means:

(i) Grading- I (Using Screening Crushable type such as Moorum or Gravel)

(a) Using Screening Crushable type such as Moorum or Gravel cum 1659.00(b) Using Screening Type-A (13.2mm Agg.) cum 1872.24

(ii) Grading- II (Using Screening Crushable type such as Moorum or Gravel)

(a) Using Screening Crushable type such as Moorum or Gravel cum 1672.00(b) Using Screening Type-A (13.2mm Agg.) cum 1752.00(c) Using Screening Type-B (11.2mm Agg.) cum 1844.00

(iii) Grading- III (Using Screening Crushable type such as Moorum or Gravel)

(a) Using Screening Crushable type such as Moorum or Gravel cum 1686.00(b) Using Screening Type-B (11.2mm Agg.) cum 1859.00

Plant Mix Method (Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401 )

Lime Stabilisation for Improving Subgrade (Laying and spreading available soil in the subgrade on a prepared surface, pulverising, mixing the spread soil in place with rotavator with 3 % slaked lime having minimum content of 70% of CaO, grading with motor grader and compacting with the road roller at OMC to the desired density to form a layer of improved sub grade)

Lime Treated Soil for Sub- Base (Providing, laying and spreading soil on a prepared sub grade, pulverising, mixing the spread soil in place with rotavator with 3 % slaked lime with minimum content of 70% of CaO, grading with motor grader and compacting with the road roller at OMC to achieve at least 98%of the max dry density to form a layer of sub base.)

Cement Treated Soil Sub Base/ Base (Providing, laying and spreading soil on a prepared sub grade, pulverising, adding the designed quantity of cement to the spread soil, mixing in place with rotavator, grading with the motor grader and compacting with the road roller at OMC to achieve the desired unconfined compressive strength and to form a layer of sub-base/base.)

Cement Treated Crushed Rock or combination as per clause 403.2 and table 400.4in Sub base/ Base (Providing, laying and spreading Material on a prepared sub grade, adding the designed quantity of cement to the spread Material, mixing in place with rotavator, grading with the motor grader and compacting with the road roller at OMC to achieve the desired unconfined compressive strength and to form a layer of sub-base/base.)

Making 50 mm x 50 mm Furrows (Making 50 mm x 50 mm furrows, 25mm deep, 450 to the center line of the road and at one metre interval in the existing thin bituminous wearing coarse including sweeping and disposal of excavated material within 1000 metres lead)

Inverted Choke (Construction of inverted choke by providing, laying, spreading and compacting screening B type/ coarse sand of specified grade in uniform layer on a prepared surface with motor grader and compacting with power roller etc)

Water Bound Macadam (Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with vibratory roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of screening/ binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the required density.)

Page 23: Standard Data Book - Rate Analysis

Page 17 of 280

Summary of Rate AnalysisItem No. Descriptions Unit Rate

4.10 cum 163.00

4.11 sqm 24.00

4.12 cum 1861.26

4.13 cum 99.00

4.14 cum 284.00

4.15

4.16 sqm 586.00

4.17

A By Mix in Place Method

(i) For 53 mm maximum size cum 1710.00

(ii) For 45 mm maximum size cum 1741.00B By Mixing Plant :

(i) For 53 mm maximum size cum 1868.00

(ii) For 45 mm maximum size cum 1188.00

4.18 cum 580.00

Crushed Cement Concrete Sub-base / Base (Breaking and crushing of material obtained by breaking damaged cement concrete slabs to size range not exceeding 75 mm as specified in table 400.7 transporting the aggregates obtained from breaking of cement concrete slabs at a lead of L km., laying and compacting the same as sub base/ base course, constructed as WBM to clause 404 except the use of screening or binding Material.)

Penetration Coat Over Top Layer of Crushed Cement Concrete Base (Spraying of bitumen over cleaned dry surface of crushed cement concrete base at the rate of 25 kg per 10 sqm by a bitumen pressure distributor, spreading of key aggregates at the rate of 0.13 cum per 10 sqm by a mechanical gritter and rolling the surface as per clause 506.3.8)

Wet Mix Macadam (Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density.)

Construction of Median and Island with Soil Taken from Roadway Cutting (Construction of Median and Island above road level with approved material deposited at site from roadway cutting and excavation for drain and foundation of other structures, spread, graded and compacted as per clause 407)

Construction of Median and Island with Soil Taken from Borrow Areas (Construction of median and Island above road level with approved material brought from borrow pits, spread, sloped and compacted as per clause 407)

Construction of Shoulders (A. Earthen Shoulders)

Footpaths and Separators (Construction of footpath/separator by providing a 150 mm compacted granular sub base as per clause 401 and 25 mm thick cement concrete grade M15, over laid with precast concrete tiles in cement mortar 1:3 including provision of all drainage arrangements but excluding kerb channel..)

Crusher Run Macadam Base (Providing crushed stone aggregate, depositing on a prepared surface by hauling vehicles, spreading and mixing with a motor grader, watering and compacting with a vibratory roller to clause 410 to form a layer of sub-base/Base)

Lime, Fly ash stabalised soil sub-base (Construction of Sub-base using lime - fly ash admixture with granular soil, free from organic matter/ deleterious material or clayey silts and low plasticity clays having PI between 5 and 20 and liquid limit less than 25 and commercial dry lime, slaked at site or pre-slaked with CaO content not less than 50%, fly ash to conform to gradation as per clause 4.3 of IRC: 88-1984, lime + fly ash content ranging between 10 to 30%, the minimum un-confined compressive strength and CBR value after 28 days curing and 4 days soaking to be 7.5kg/sq, cm and 25% respectively, all as specified in IRC: 88-1984. )

Page 24: Standard Data Book - Rate Analysis

Page 18 of 280

Summary of Rate AnalysisItem No. Descriptions Unit Rate

CHAPTER-5

BASES AND SURFACE COURSES (BITUMINOUS)

5.1 sqm 51.40

5.2 Tack coat

sqm 16.76

5.3

(i) for Grading I ( 40 mm nominal size ) cum 7863.79(ii) for GradingII(19 mm nominal size) cum 7871.54

5.4

A 50 mm thick sqm 432.00B 75 mm thick sqm 590.00

5.5 sqm 351.00

5.6

(i) for Grading I ( 40 mm nominal size ) cum 10006.88

5.7

(i) for Grading I ( 13 mm nominal size ) cum 9943.00(ii) for GradingII(10 mm nominal size) cum 10693.00

5.8

(i) for Grading-I ( 13 mm nominal size ) cum 11688.42

5.9

Case -1 :-19 mm nominal chipping size sqm 104.00Case - II 13 mm nominal size chipping sqm 85.00

5.10

(i) sqm 152.00

(ii) Case - II: Open-Graded Premix Surfacing using cationic Bitumen Emulsion sqm 186.00

Prime coat (Providing and applying primer coat with bitumen emulsion on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.60 kg/sqm using mechanical means.)

Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous/granular surface cleaned with mechanical broom.

Bituminous Macadam (Providing and laying bituminous macadam with 100-120 TPH hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading premixed with bituminous binder, transported to site, laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled as per clauses 501.6 and 501.7 to achieve the desired compaction)

Bituminous Penetration Macadam (Construction of penetration macadam over prepared Base by providing a layer of compacted crushed coarse aggregate using chips spreader with alternate applications of bituminous binder and key aggregates and rolling with a smooth wheeled steel roller 8-10 tonne capacity to achieve the desired degree of compaction)

Built-Up-Spray Grout (Providing, laying and rolling of built-up-spray grout layer over prepared base consisting of a two layer composite construction of compacted crushed coarse aggregates using motor grader for aggregates. key stone chips spreader may be used with application of bituminous binder after each layer, and with key aggregates placed on top of the second layer to serve as a Base conforming to the line, grades and cross-section specified, the compacted layer thickness being 75 mm)

Dense Graded Bituminous Macadam (Providing and laying dense bituminous macadam with 100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 4.0 to 4.5% by weight of total mix of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 507 complete in all respects.)

Semi - Dense Bituminous Concrete (Providing and laying semi dense bituminous concrete with 100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 4.5 to 5 % of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 508 complete in all respects)

Bituminous Concrete (Providing and laying bituminous concrete with 100-120 TPH batch type hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 5.4 to 5.6 % of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 509 complete in all respects)

Surface Dressing (Providing and laying surface dressing as wearing course in single coat using crushed stone aggregates of specified size on a layer of bituminous binder laid on prepared surface and rolling with 8-10 tonne smooth wheeled steel roller)

Open - Graded Premix Surfacing (Providing, laying and rolling of open - graded premix surfacing of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates either using penetration grade bitumen or cut-back or emulsion to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a smooth wheeled roller 8-10 tonne capacity, finished to required level and grades.)

Case - I: Mechanical method using Penetration grade Bitumen and HMP of appropriate capacity not less than 75 tonnes/hour .

Page 25: Standard Data Book - Rate Analysis

Page 19 of 280

Summary of Rate AnalysisItem No. Descriptions Unit Rate

5.11 sqm 200.00

5.12

(i) Case - I : Type A sqm 80.00

(ii) sqm 60.00

5.13 cum

5.14 sqm 592.00

5.15

(i) 5 mm thickness sqm 85.45(ii) 3 mm thickness sqm 58.00

(iii) 1.5 mm thickness sqm 35.00

5.16 cum 7908.00

5.17 Fog Spray sqm 47.00added 1.In case it is decided by the engineer to blind the fog spray, the following may be added sqm 6.00

5.18

(i) Using bitumen emulsion and 9.5 mm or 13.2 mm nominal size aggregate cum 12877.00(ii) Using bitumen emulsion and 19 mm or 26.5 mm nominal size aggregate cum 12772.00

(iii) Using cutback bitumen and 9.5 mm or 13.2 mm nominal size aggregate cum 8695.00(iv) Using cutback bitumen and 19 mm or 26.5 mm nominal size aggregate cum 8585.00

5.19 cum 9750.00

5.20 tonne

5.21 Crack Prevention Courses

(i) sqm 57.00

Close Graded Premix Surfacing/Mixed Seal Surfacing (Mechanical means using HMP of appropriate capacity not less than 75 tonnes/hour. Providing, laying and rolling of close-graded premix surfacing material of 20 mm thickness composed of 11.2 mm to 0.09 mm (Type-a) or 13.2 mm to 0.09 mm (Type-b) aggregates using penetration grade bitumen to the required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a Smooth wheeled roller 8-10 tonne capacity, and finishing to required level and grade. )

Seal Coat (Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type A and B seal coats)

Case - II : Type B (Providing and laying of premix sand seal coat with HMP of appropriate capacity not less than 75 tonnes/ hours using crushed stone chipping 6.7 mm size and penetration bitumen of suitable grade.)

Supply of Stone Aggregates for Pavement Courses (Supply of stone aggregates from approved sources confirming to the physical requirement, specified in the respective specified clauses, including royalties, fees rents, collection, transportation, stacking and testing and measured in cum as per clause 514.5 Competitive market rates to be ascertained. Alternatively, rates for stone crushing given in chapter 1may be adopted, if found economical. In case for supply of aggregates at site are not available, nearest crusher site may be ascertained. Loading and un-loading charges and cost of carriage may be added to these rates to arrive at the cost at site.)

Mastic Asphalt (Providing and laying 25 mm thick mastic asphalt wearing course with paving grade bitumen meeting the requirements given in table 500-29, prepared by using mastic cooker and laid to required level and slope after cleaning the surface, including providing antiskid surface with bitumen precoated fine-grained hard stone chipping of 13.2 mm nominal size at the rate of 0.005cum per 10 sqm and at an approximate spacing of 10 cm center to center in both directions, pressed into surface when the temperature of surfaces not less than 1000C, protruding 1 mm to 4 mm over mastic surface, all complete as per clause 515.)

Slurry Seal Providing and laying slurry seal consisting of a mixture of fine aggregates, portland cement filler, bituminous emulsion and water on a road surface including cleaning of surface, mixing of slurry seal in a suitable mobile plant, laying and compacting to provide even riding surface)

Recycling of Bituminous Pavement with Central Recycling Plant (Recycling pavement by cold milling of exiting bituminous layers, planning the surface after cold milling, reclaiming excavated material to the extent of 30 % of the required quantity, hauling and stock piling the reclaimed material near the central recycling plant after carrying out necessary checks and evaluation, adding fresh material including rejuvenators as required, mixing in a hot mix plant, transporting and laying at site and compacting to the required grade, level and thickness, all as specified in clause 517.)

Bituminous Cold Mix ( Including Gravel Emulsion) (Providing, laying and rolling of bituminous cold mix on prepared base consisting of a mixture of unheated mineral aggregate and emulsified or cutback bitumen, including mixing in a plant of suitable type and capacity, transporting, laying, compacting and finishing to specified grades and levels.)

Sand Asphalt Base Course (Providing, laying and rolling sand-asphalt base course composed of sand, mineral filler and bituminous binder on a prepared sub-grade or sub-base to the lines, levels, grades and cross sections as per the drawings including mixing in a plant of suitable type and capacity, transporting, laying, compacting and finishing.)

Modified Binder (Supply of modified binder produced by mixing bitumen with modifier such as natural rubber or crumb rubber or any other polymer found compatible with bitumen and which allows properties given in clause 521.3 and IRC: SP: 53 blending of modifier with bitumen to be done either at the refinery or at the site plant capable of producing the modified binder to be delivered in drums which shall be agitated in melted condition using suitable device before use to ensure uniform dispersion.)

Stress Absorbing Membrane (SAM) crack width less than 6 mm (Providing and laying of a stress absorbing membrane over a cracked road surface, with crack width below 6 mm after cleaning with a mechanical broom, using modified binder complying with clause 521, sprayed at the rate of 9 kg per 10 sqm and spreading 5.6 mm crushed stone aggregates @ 0.11 cum per 10 sqm with hydraulic chip spreader, sweeping the surface for uniform spread of aggregates and surface finished to conform to clause 902.)

Page 26: Standard Data Book - Rate Analysis

Page 20 of 280

Summary of Rate AnalysisItem No. Descriptions Unit Rate

(ii) sqm 67.00

(iii) sqm 88.00

(iv) sqm 124.00

5.22

(i) 75 mm thickness cum 8688.00(ii) 40 mm thickness cum 12138.00

(iii) 25 mm thickness cum 13930.00

Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm (Providing and laying of a stress absorbing membrane over a cracked road surface, with crack width 6 to 9 mm after cleaning with a mechanical broom, using modified binder complying with clause 521, sprayed at the rate of 11 kg per 10 sqm and spreading 11.2 mm crushed stone aggregates @ 0.12 cum per 10 sqm, sweeping the surface for uniform spread of aggregates and surface finished to conform to clause 902.)

Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked area above 50 % (Providing and laying a single coat of a stress absorbing membrane over a cracked road surface, with crack width above 9 mm and cracked area above 50 % after cleaning with a mechanical broom, using modified binder complying with clause 521, sprayed at the rate of 15 kg per 10 sqm and spreading 11.2 mm crushed stone aggregates @ 0.12 cum per 10 sqm, sweeping the surface for uniform spread of aggregates and surface finished to conform to clause 902.)

Case - IV : Bitumen Impregnated Geotextile (Providing and laying a bitumen impregnated geotextile layer after cleaning the road surface, geotextile conforming to requirements of clause 704.3, laid over a tack coat with 1.05 kg per sqm of paving grade bitumen 80 - 100 penetration and constructed to the requirement of clause 704.4.5)

Recipe Cold Mix (Providing and laying of premix of crushed stone aggregates and emulsion binder, mixed in a batch type cold mixing plant, laid over prepared surface, by paver finisher, rolled with a pneumatic tyred roller initially and finished with a smooth steel wheel roller, all as per clause 519.3)

Page 27: Standard Data Book - Rate Analysis

Page 21 of 280

Summary of Rate AnalysisItem No. Descriptions Unit Rate

CHAPTER-8

TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES

8.1

A Using Concrete Mixer metre 226.00B Using Concrete Batching and Mixing Plant metre 231.00

8.2

B Using Concrete Batching and Mixing Plant metre 439.00

8.3

(i) 0.60

(ii)English and Roman

0.30

8.4

( i ) 90 cm equilateral triangle each 4206.00( ii ) 60 cm equilateral triangle each 2783.00

( iii ) 60 cm circular each 3715.00( iv ) 80 mm x 60 mm rectangular each 5160.00( v ) 60 cm x 45 cm rectangular each 3619.00(vi ) 60 cm x 60 cm square each 4280.00

( vii ) 90 cm high octagon each 6569.00

8.5 sqm 9152.00

8.6 sqm 15825.00

8.7

A Truss and Vertical Support tonne 83366.00B Aluminium alloy plate for over head sign tonne 575.00

8.8 sqm 42.00

8.9 sqm 49.00

8.10 sqm 55.00

8.11

(i) Over 10 cm in width sqm 63.00(ii) Up to 10 cm in width sqm 54.00

Cast in Situ Cement Concrete M20 kerb (Construction of cement concrete kerb with top and bottom width 115 and 165 mm respectively, 250 mm high in M 20 grade PCC on M-10 grade foundation 150 mm thick, foundation having 50 mm projection beyond kerb stone, kerb stone laid with kerb laying machine, foundation concrete laid manually, all complete as per clause 408)

Cast in Situ Cement Concrete M 20 Kerb with Channel (Construction of cement concrete kerb with channel with top and bottom width 115 and 165 mm respectively, 250 mm high in M 20 grade PCC on M10 grade foundation 150 mm thick, kerb channel 300 mm wide, 50 mm thick in PCC M20 grade, sloped towards the kerb, kerb stone with channel laid with kerb laying machine, foundation concrete laid manually, all complete as per clause 408)

Printing new letter and figures of any shade (Printing new letter and figures of any shade with synthetic enamel paint black or any other approved colour to give an even shade)

Hindi ( Matras commas and the like not to be measured and paid for Half letter shall be counted as half ) cm height per letter

cm height per letter

Retro- reflectorised Traffic signs (Providing and fixing of retro- reflectorised cautionary, mandatory and informatory sign as per IRC :67 made of encapsulated lens type reflective sheeting vide clause 801.3, fixed over aluminium sheeting, 1.5 mm thick supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved drawing)

Direction and Place Identification signs upto 0.9 sqm size board. (Providing and erecting direction and place identification retro-reflectorised sign asper IRC:67 made of encapsulated lens type reflective sheeting vide clause 801.3, fixed over aluminium sheeting, 2 mm thick with area not exceeding 0.9 sqm supported on a mild steel single angle iron post 75 x 75 x 6 mm firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 45 x 45 x 60 cm, 60 cm below ground level as per approved drawing)

Direction and Place Identification signs with size more than 0.9 sqm size board. (Providing and erecting direction and place identification retro- reflectorised sign asper IRC :67 made of encapsulated lens type reflective sheeting vide clause 801.3, fixed over aluminium sheeting, 2 mm thick with area exceeding 0.9 sqm supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm, 2 Nos. firmly fixed to the ground by means of properly designed foundation with M 15 grade cement concrete45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved drawing)

Overhead Signs (Providing and erecting overhead signs with a corrosion resistant aluminium alloy sheet reflectorised with high intensity retro-reflective sheeting of encapsulated lense type with vertical and lateral clearance given in clause 802.2 and 802.3 and installed as per clause 802.7 over a designed support system of aluminium alloy or galvanised steel trestles and trusses of sections and type as per structural design requirements and approved plans)

Painting Two Coats on New Concrete Surfaces (Painting two coats after filling the surface with synthetic enamel paint in all shades on new plastered concrete surfaces)

Painting on Steel Surfaces (Providing and applying two coats of ready mix paint of approved brand on steel surface after through cleaning of surface to give an even shade)

Painting on Wood Surfaces (Providing and applying two coats of ready mix paint of approved brand on wood surface after through cleaning of surface to give an even shade)

Painting Lines, Dashes, Arrows etc on Roads in Two Coats on New Work (Painting lines, dashes, arrows etc on roads in two coats on new work with ready mixed road marking paint conforming to IS:164 on bituminous surface, including cleaning the surface of all dirt, dust and other foreign matter, demarcation at site and traffic control )

Page 28: Standard Data Book - Rate Analysis

Page 22 of 280

Summary of Rate AnalysisItem No. Descriptions Unit Rate

8.12

(i) Over 10 cm in width sqm 43.00(ii) Up to 10 cm in width sqm 46.00

8.13 sqm 607.78

8.14

(i) 5th kilometre stone (precast) each 2632.00(ii) Ordinary Kilometer stone (Precast) each 1610.00

(iii) Hectometer stone (Precast) each 460.00

8.15 each 1116.00

8.16 each 535.00

8.17 metre 251.00

8.18 metre 415.00

8.19 metre 647.00

8.20 metre 2270.00

8.21 metre 1820.00

8.22

(i) M 20 grade concrete metre 3469.008.23 Metal Beam Crash Barrier

A metre 2721.00

B metre 3525.00

Painting Lines, Dashes, Arrows etc on Roads in Two Coats on Old Work (Painting lines, dashes, arrows etc on roads in two coats on old work with ready mixed road marking paint confirming to IS: 164 on bituminous surface, including cleaning the surface of all dirt, dust and other foreign matter, demarcation at site and traffic control )

Road Marking with Hot Applied Thermoplastic Compound with Reflectorising Glass Beads on Bituminous Surface (Providing and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35 .The finished surface to be level, uniform and free from streaks and holes.)

Kilo Metre Stone (Reinforced cement concrete M15grade kilometre stone of standard design as per IRC:8-1980, fixing in position including painting and printing etc)

Road Delineators (Supplying and installation of delineators (road way indicators, hazard markers, object markers), 80-100 cm high above ground level, painted black and white in 15 cm wide stripes, fitted with 80 x 100 mm rectangular or 75 mm dia circular reflectorised panels at the top, buried or pressed into the ground and confirming toIRC-79 and the drawings.)

Boundary pillar (Reinforced cement concrete M15 grade boundary pillars of standard design as per IRC:25-1967, fixed in position including finishing and lettering but excluding painting)

G.I Barbed wire Fencing 1.2 metre high (Providing and fixing 1.2 metres high GI barbed wire fencing with 1.8 m angle iron posts 40 mm x 40 mm x 6 mm placed every 3 metres center to center founded in M15 grade cement concrete, 0.6 metre below ground level, every 15th post, last but one end post and corner post shall be strutted on both sides and end post on one side only and provided with 9 horizontal lines and 2 diagonals interwoven with horizontal wires, fixed with GI staples, turn buckles etc complete as per clause 807 )

G.I Barbed wire Fencing 1.8 metre high (Providing and fixing 1.8 metres high GI barbed wire fencing with 2.4 m angle iron posts 50 mm x 50 mm x 6 mm placed every 3 metres center to center founded in M15 grade cement concrete, 0.6 metre below ground level, every 15th post, last but one end post and corner post shall be strutted on both sides and end post on one side only and provided with 12 horizontal lines and 2 diagonals interwoven with horizontal wires, fixed with GI staples, turn buckles etc complete as per clause 807 )

Fencing with welded steel wire Fabric 75 mm x 50 mm (Suggestive) (Providing 1.20 metre high fencing with angle iron posts 50 mm x 50 mm x 6 mm at 3 metre center to center with 0.40 metre embedded in M15 grade cement concrete, corner, end and every 10th post to be strutted, provided with welded steel wire fabric of 75 mm x 50 mm mesh or 75 mm x 25 mm mesh and fixed to iron posts by flat iron 50 x 5 mm and bolts etc. complete in all respects.)

Tubular Steel Railing on Medium Weight steel channel ( ISMC series) 100 mm x 50 mm (Providing, fixing and erecting 50 mm dia steel pipe railing in 3 rows duly painted on medium weight steel channels (ISMC series) 100 mm x 50 mm, 1.2 metres high above ground, 2 m centre to centre, complete as per approved drawings)

Tubular Steel Railing on Precast RCC posts, 1.2 m high above ground level (Providing, fencing and erecting 50 mm dia painted steel pipe railing in 3 rows on precast M20 grade RCC vertical posts1.8 metres high (1.2 m above GL) with 3 holes 50 mm dia for pipe, fixed 2 metres centre to, complete as per approved drawing)

Reinforced Cement Concrete Crash Barrier (Provision of an Reinforced cement concrete crash barrier at the edges of the road, approaches to bridge structures and medians, constructed with M-20 grade concrete with HYSD reinforcement conforming to IRC:21 and dowel bars 25 mm dia, 450 mm long at expansion joints filled with pre-moulded asphalt filler board, keyed to the structure on which it is built and installed as per design given in the enclosure to MOST circular No. RW/NH - 33022/1/94-DO III dated 24 June 1994 as per dimensions in the approved drawing and at locations directed by the Engineer, all as specified)

Type - A, "W" : Metal Beam Crash Barrier (Providing and erecting a "W" metal beam crash barrier comprising of 3 mm thick corrugated sheet metal beam rail, 70 cm above road/ground level, fixed on ISMC series channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to centre, 1.8 m high, 1.1 m below ground/road level, all steel parts and fitments to be galvanised by hot dip process, all fittings to conform to IS:1367 and IS:1364, metal beam rail to be fixed on the vertical post with a spacer of channel section 150 x 75 x 5 mm, 330 mm long complete as per clause 810)

Type - B, "THRIE" : Metal Beam Crash Barrier (Providing and erecting a "Thrie" metal beam crash barrier comprising of 3 mm thick corrugated sheet metal beam rail, 85 cm above road/ground level, fixed on ISMC series channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to centre, 2 m high with 1.15 m below ground level, all steel parts and fitments to be galvanised by hot dip process, all fittings to conform to IS:1367 and IS:1364, metal beam rail to be fixed on the vertical post with a space of channel section 150 x 75 x 5 mm, 546 mm long complete as per clause 810)

Page 29: Standard Data Book - Rate Analysis

Page 23 of 280

Summary of Rate AnalysisItem No. Descriptions Unit Rate

8.24

8.25 metre 2055.00

8.26 Anti - Glare Devices in Median

A

B metre 4323.00

C metre 807.00

8.27

(i) For Fixing in Median each 4286.00(ii) For fixing in Footpath each 4235.00

8.28 each 3226.00

8.29

(i) Single Row for one utility service metre 2474.00(ii) Double Row for two utility services metre 4566.00

(iii) Triple Row for three utility services metre 6666.00

8.30

8.31

8.32

8.33

(i) Gantry Support System tonne 81484.00

(ii)

Road Traffic Signals electrically operated (Since it is a ready made item commercially produced and erected by specialised firm in the electrical and electronic field, rate may be taken based on market enquiry from firms specialised in this field and ISI certified for the approved design and drawing.)

Flexible Crash Barrier, Wire Rope Safety Barrier (Providing and erecting a wire rope safety barrier with vertical posts of medium weight RS Joist (ISMB series) 100 mm x 75 mm (11.50 kg/m), 1.50 m long 0.85 m above ground and 0.65 m below ground level, split at the bottom for better grip, embedded in M 15 grade cement concrete 450 x 450 x 450 mm, 1.50 m center to center and with 4 horizontal steel wire rope 40 mm dia and anchored at terminal posts 15 m apart. Terminal post to be embedded in M 15 gradecementconcretefoundation2400 x 450 x 900 mm (depth), strengthened by a strut of RS joist 100 x 75 mm, 2 m long at 450 inclination and a tie 100 x 8 mm, 1.50 m long at the bottom, all embedded in foundation concrete as per approved design and drawing, rate excluding excavation and cement concrete.)

Plantation (Plantation of shrubs and plants of approved species in the median. apart from cutting off glare from vehicle coming from opposite direction, these plants provide a pleasant envoirenment and are eco-friendly. The rate for this item is available in the chapter 11 on horticulture. )

Anti - Glare Screen with 25 mm steel pipe framework fixed with circular and rectangular vans (Providing and erecting an anti - glare screen with 25 mm dia vertical pipes fabricated and framed in the form of panels of one metre length and 1.75 mtr height fixed with circular vane 250 mm dia at top and rectangular vane 600 x 300 mm at the middle, made out of steel sheet of 3 mm thickness, end vertical pipes of the panel made larger for embedding in foundation concrete, applying 2 coats of paint on all exposed surfaces, all as per approved design and drawings.)

Anti - Glare Screen with Rectangular Vane of MS sheet (Providing and erecting anti - glare screen with rectangular vanes of size 750 x 500 mm made from MS sheet, 3 mm thick and fixed on MS angle 50 x 50 x 6 mm at an angle of 450 to the direction of flow of traffic, 1.5 m center to center, top edge of the screen 1.75 m above ground level, vertical post firmly embedded in cement concrete foundation 0.60 m below ground level, applying 2 coats of paint on exposed faces, all complete as per approved design and drawings)

Street Lighting (Providing and erecting street light mounted on a steel circular hollow pole of standard specifications for street lighting, 9 m high spaced 40 m apart, 1.8 m overhang on both sides if fixed in the median and on one side if fixed on the footpath, fitted with sodium vapour lamp and fixed firmly in concrete foundation.)

Lighting on Bridges (Providing and fixing lighting on bridges, mounted on steel hollow circular poles of standard specifications, 5 m high fixed on parapets with cement concrete, 20 m apart and fitted with sodium vapour lamp)

Cable Duct Across the Road (Providing and laying of a reinforced cement concrete pipe duct, 300 mm dia, across the road (new construction), extending from drain to drain in cuts and toe of slope to toe of slope in fills, constructing head walls at both ends, providing a minimum fill of granular material over top and sides of RCC pipe as per IRC:98-1997, bedded on a 0.3 m thick layer of granular material free of rock pieces, outer to outer distance of pipe at least half dia of pipe subject to minimum 450 mm in case of double and triple row ducts, joints to be made leak proof, invert level of duct to be above higher than ground level to prevent entry of water and dirt, all as per IRC: 98 - 1997 and approved drawings.)

Highway Patrolling and Traffic Aid Post (It is proposed to locate one Traffic Aid Post every 50-60 km of the highway. )

Items related to under pass/ subway/ overhead bridge/ overhead foot bridge (The items involved for underpass/ subway/ overhead bridge/ overhead foot bridge are earthwork, plain cement concrete, plastering, painting, information sign etc. The rates for these items are available in respective chapters which can be adopted for the quantities derived from the approved designs and drawings)

Traffic Control System and Communication system (Providing a traffic control centre and communication system including telecommunication facilities and related accessories, CCTV, radar, vehicle detection camera, central computer system These are specialised item of telecommunication system and are the commercial products. The designer is required to contact the manufacturers to ascertain market prices. In case of civil works required to be executed for these installations, pricing may be done as per rates in relevant chapters for quantities derived approved design and drawing.)

Gantry Mounted Variable Message Sign board (Providing and erecting gantry mounted variable message sign board electronically operated capable of flashing the desired message over a designed support system of aluminium alloy or galvanised steel, erected as per approved design and drawings and with lateral clearance as per clause 802.3)

Message Display (Message display board 6 sqm electronically operated with complete electronic fitments for flashing the pre-determined messages.)

Page 30: Standard Data Book - Rate Analysis

Page 24 of 280

Summary of Rate AnalysisItem No. Descriptions Unit Rate

8.34 Traffic Impact Attenuators at Abutments and Piers

A sqm 2389.00

B sqm 760.00

C sqm 18533.00

8.35 each 730.00

8.36 each 296.00

8.37 Roadside Amenities

A

B

C

8.38 sqm

8.39 each

8.40

8.41

8.42

8.43 each 2598.00

8.44 Permanent Type Barricade in Construction Zone

A each 4160.00

With Scrap Tyres (Provision and installation of traffic attenuators at abutment/pier of flyovers bridges using scrap tyres of size 100 x 20 retrieved from trucks laid in 2 rows and 4 tiers, one above the other and tied with 20 mm wire rope as per approved design and drawings.)

Using Plastic/Steel Barrel, Filled with Sand (Provision and installation of traffic impact attenuator at abutment/pier of flyovers bridges using plastic/steel barrels 0.60 m dia and 1.0 m in height, filled with sand in three rows and tied with20 mm steel wire rope as per approved design and drawings)

With HI - DRO cell Sandwich (Patented) ((In this patented HI - DRO cell system, water gets discharged from plastic tubes on impact over a pre-determined time, thus absorbing the energy))

Road Markers/Road Stud with Lense Reflector (Providing and fixing of road stud 100x 100 mm, die cast in aluminium, resistant to corrosive effect of salt and grit, fitted with lense reflectors, installed in concrete or asphaltic surface by drilling hole 30 mm upto a depth of 60 mm and bedded in a suitable bituminous grout or epoxy mortar, all as per BS 873 part 4:1973)

Traffic Cone (Provision of red fluorescent with white reflective sleeve traffic cone made of low density polyethylene (LDPE) material with a square base of 390 x 390 x 35 mm and a height of 770 mm, 4 kg in weight, placed at 1.5 m interval, all as per BS 873)

Rest Areas (Providing plainly furnished accommodation for rest rooms, dormitories, restaurants, stalls, shops, petrol pump, telephone booth, first aid room, traffic aid post, police assistance booth, including electricity, toilet and sewerage system Pricing may be done based on current plinth area rates approved by PWD/CPWD/MES for a particular zone. Area is required to be assessed for specific location as per actual site conditions)

Parking areas and Bus Laybyes for Trucks, Buses and Light vehicles (Pricing of parking areas may be done for the quantities of various items based on the approved dimensions and pavement design for a particular terrain and soil. Rates for items may be from respective chapters.)

Lawn (Providing a lawn planted with grass and its maintenance )

Rumble Strips (Provision of 15 nos rumble strips covered with premix bituminous carpet, 15-20 mm high at center, 250 mm wide placed at 1 m center to center at approved locations to control speed, marked with white strips of road marking paint.)

Policeman Umbrella (Provision of a 2 m high (floor to roof) umbrella for traffic policeman at road crossings, where necessary, installed on a raised platform, built on a central support of a steel pipe 100 mm dia, roof made of 25 mm dia steel pipe to provide covered area of 3 sqm, roofed with CGI sheets, all steel parts to be given 2 coats of paint)

High Mast Pole Lighting at Interchanges and Flyovers (Providing and erecting a high mast pole lighting with 30 m high hot dip galvanised mast designed to withstand forces exerted with wind speeds of 180 km per hour with 3 seconds gust, as per IS:875 (Part 3) - 1978, fitted with a base flange, door at the base of mast with heavy duty internal lock, lantern carriage, suitable winching arrangement for safe working load of 750 kg and high powered electrically driven power tools for raising and lowering of lantern carriage, flexible 8 core electric cable, lightening conductor, earthing terminal, and fixing 2 nos aviation obstruction lights on top of the mast, all complete as per approved design and drawings This is a specialised work and is generally done by firms who specialise in such jobs. The detailed designs and estimates are submitted by the firms alongwith their tender for checks by the Department. The cost of this work is required to be worked out based on approved design, drawings and estimate of the lowest tender. A separate contract for this work is concluded as the contractors for road and bridge works generally donot undertake such jobs.)

Toll Plaza (The construction, operation and maintenance of Toll Plaza can be broken into separate items of work as under based on the approved design and drawings:-)

Safety Devices and signs in Construction Zones (Provision and fixing of traffic signs for limited period at suitable locations in construction zone comprising of warning zone, approach transition zone, working zone and terminal transition zone with a minimum distance of 60 cm from the edge of the kerb in case of kerbed roads and 2 to 3 m from the edge of the carriageway in case of un-kerbed roads, the bottom edge of the lowest sign plate to be not less than 2 m above the road level, fixed on 60 mm x 60 mm x 6 mm angle iron post, founded and installed as per approved design and drawings, removed and disposed of after completion of construction work, all as per IRC:SP:55-2001)

Portable Barricade in Construction Zone (Installation of a steel portable barricade with horizontal rail 300 mm wide, 2.5 m in length fitted on a 'A' frame made with 45 x 45 x 5 mm angle iron section, 1.5 m in height, horizontal rail painted (2 coats) with yellow and white stripes, 150 mm in width at an angle of 450, 'A' frame painted with 2 coats of yellow paint, complete as per IRC:SP:55-2001 )

With Steel Components (Construction of a permanent type barricade made of steel components, 1.5 m high from road level, fitted with 3 horizontal rails 200 mm wide and 4 m long on 50 x 50 x 5 mm angle iron vertical support, painted with yellow and white strips, 150 mm in width at an angle of450, complete as per IRC:SP:55-2001 )

Page 31: Standard Data Book - Rate Analysis

Page 25 of 280

Summary of Rate AnalysisItem No. Descriptions Unit Rate

B each 5749.00

C each 11476.00

8.45 each 325.00

8.46 each 430.00

With Wooden Components (Construction of a permanent type barricade made of wooden components, 1.5 m high from road level, fitted with 3 horizontal planks 200 mm wide and 3.66 m long on 100 x 100mm wooden vertical post, painted with yellow and white striups, 150 mm in width at an angle of450, complete as per IRC:SP:55-2001 )

With Bricks (Construction of a permanent type barricade made with brick work in mud mortar, 1.5 m high, 4 m long, 600 mm thick, plastered with cement mortar 1:6, painted with yellow and white strips)

Drum Delineator in Construction Zone (Provision of metal drum/empty bitumen drum delineator, 300 mm in diameter, 800 mm high, filled with earth for stability, painted in circumferential strips of alternate black and white 100 mm wide fitted with reflectors 3 Nos of 7.5 cm dia, all as per IRC:SP:55-2001)

Flagman (Positioning of a smart flagman with a yellow vest and a yellow cap and a red flag 600 x 600 mm securely fastened to a staff 1 m in length for guiding the traffic)

Page 32: Standard Data Book - Rate Analysis

Page 26 of 280

Summary of Rate AnalysisItem No. Descriptions Unit Rate

CHAPTER-12

FOUNDATIONS

12.1

I Ordinary soil

A Manual Means

(i) upto 3 m depth cum 66.00(ii) 3 m to 6 m depth cum 85.00

(iii) Above 6 m depth cum 113.00B Mechanical Means

(i) Depth upto 3 m cum 49.00(ii) Depth 3 m to 6 m cum 56.00

(iii) Depth above 6m cum 68.00II Ordinary rock (not requiring blasting)

A Manual Means

(i) Depth upto 3 m cum 94.00B Mechanical Means cum 64.00III Hard rock ( requiring blasting )

A Manual Means cum 314.00IV Hard rock ( blasting prohibited )

A Mechanical Means cum 347.00V Marshy soil

(i) upto 3 m depth

A Manual means cum 288.00B Mechanical Means cum 67.00VI Back Filling in Marshy Foundation Pits cum 219.00

12.2

12.3 Sand Filling in Foundation Trenches as per Drawing & Technical Specification cum 811.00

12.4 cum 3626.00

12.5 cum 4545.00

12.6 A Cement mortar1:3 (1cement :3 sand) cum 3425.00B Cement mortar1:2 (1cement :2 sand) cum 4150.00C Cement mortar1:4 (1cement :4 sand) cum 2941.00D Cement mortar1:6 (1cement :6 sand) cum 2519.00

12.7 Stone masonry work in cement mortar 1:3 in foundation complete as drawing and Technical Specification

(a) Square Rubble Coursed rubble masonry( first sort ) cum 6211.00(b) Random Rubble Masonry cum 6020.00

12.8 Plain/Reinforced cement concrete in open foundation complete as per drawing and technical specifications

A PCC Grade M15 cum 4228.00B PCC Grade M20 cum 4653.00

C RCC Grade M20

Case I Using concrete mixer cum 4726.00Case II With Batching Plant, Transit Mixer and Concrete Pump cum 4650.00

D PCC Grade M25

Case I Using concrete Mixer cum 5021.00Case II With Batching Plant, Transit Mixer and Concrete Pump cum 4949.00

E RCC Grade M25

Case I Using concrete Mixer cum 5098.00Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5023.00

F PCC Grade M30

Case I Using Concrete Mixer cum 5050.00Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 4974.00

G RCC Grade M30

Case I Using Concrete Mixer cum 5108.00Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 5035.00

Excavation for Structures (Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material.)

Filling Annular Space Around Footing in Rock (Lean cement concrete 1:3:6 nominal mix. Rate may be taken as per items 13.4.)

PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.)

Brick masonry work in cement mortar 1:3 in foundation complete excluding pointing and plastering, as per drawing and technical specifications

Page 33: Standard Data Book - Rate Analysis

Page 27 of 280

Summary of Rate AnalysisItem No. Descriptions Unit Rate

H RCC Grade M35

Case I Using Concrete Mixer cum 5188.00Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 5114.00

12.9 Providing and constructing temporary island 16 m diameter for construction of well foundation for 8m dia. Well.

A Assuming depth of water 1.0 m and height of island to be 1.25m. each 42083.00B Assuming depth of water 4.0 m and height of island 4.5 m. each 203208.00

C metre 2060.00

12.10 tonne 79219.00

12.11 Plain/Reinforced cement concrete, in well foundation complete as per drawing and technical specification

A Well curb

(i) RCC M20 Grade

Case I Using concrete mixer cum 5454.00Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5367.00

(ii) RCC M25 Grade

Case I Using concrete mixer cum 5897.00Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5924.00

(iii) RCC M35 Grade

Case I Using concrete mixer cum 6045.00Case II With Batching Plant, Transit Mixer and Concrete Pump cum 6079.00

B Well steining

(I) PCC M15 Grade cum 4472.00(ii) PCC M20 Grade cum 4922.00(iii) RCC M20 Grade

Case I Using concrete mixer cum 4999.00Case II With Batching Plant, Transit Mixer and Concrete Pump cum 4919.00

(iv) PCC M25 Grade

Case I Using concrete mixer cum 5324.00Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5248.00

(v) RCC M25 Grade

Case I Using concrete mixer cum 5406.00Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5430.00

(vi) PCC M30 Grade

Case I Using concrete mixer cum 5368.00Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5287.00

(vii) RCC M30 Grade

Case I Using concrete mixer cum 5430.00Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5352.00

(viii) RCC M35 Grade

Case I Using concrete mixer cum 5541.00Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5573.00

(ix) RCC M40 Grade 5632.00C Bottom Plug

(i) PCC Grade M20

Case I Using Concrete Mixer cum 5127.00Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 4908.00

(ii) PCC Grade M25

Case I Using Concrete Mixer cum 5343.00Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 5122.00

(iii) PCC Grade M30

Case I Using Concrete Mixer cum 5384.00Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 5165.00

(iv) PCC Grade M35

Case I Using Concrete Mixer cum 5481.00Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 5260.00

D Intermediate plug

(I) Grade M20 PCC

Case I Using Concrete Mixer cum 4909.00

Providing and constructing one span service road to reach island location from one pier location to another pier location

Providing and laying cutting edge of mild steel weighing 40 kg per metre for well foundation complete as per drawing and technical specification.

Page 34: Standard Data Book - Rate Analysis

Page 28 of 280

Summary of Rate AnalysisItem No. Descriptions Unit Rate

Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 4697.00(ii) Grade M25 PCC

Case I Using Concrete Mixer cum 5114.00Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 4900.00

(iii) Grade M30 PCC

Case I Using Concrete Mixer cum 5153.00Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 4941.00

E Top plug

(i) Grade M15 PCC

Case I Using Concrete Mixer cum 4066.00(ii) Grade M20 PCC

Case I Using Concrete Mixer cum 4475.00(iii) Grade M25 PCC

Case I Using Concrete Mixer cum 4840.00Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 4770.00

(iv) Grade M30 PCC

Case I Using Concrete Mixer cum 4880.00Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 4806.00

F Well cap

(i) RCC Grade M20

Case I Using concrete Mixer cum 4685.00Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 4608.00

(ii) RCC Grade M25

Case I Using concrete Mixer cum 5098.00Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 5024.00

(iii) RCC Grade M30

Case I Using Concrete Mixer cum 5108.00Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 5034.00

(iv) RCC Grade M35

Case I Using Concrete Mixer cum 5188.00Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 5114.00

(v) RCC M40 Grade cum 5307.00

12.12

A Sandy soil

(i) Depth below bed level upto 3.0 M metre 3966.00(ii) Beyond 3m upto 10m depth metre 5737.00(iii) Beyond 10m upto 20m

a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 7577.00(iv) Beyond 20m upto 30 m

a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 14212.00b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . 17054.00

(v) Beyond 30m upto 40 m metrea Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter 33768.00b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 40521.00

B Clayey soil ( 6m dia. Well )

(i) Depth below bed level upto 3.0 M metre 5715.00(ii) Beyond 3m upto 10m depth metre 13580.00(iii) Beyond 10 m upto 20 m

a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 17935.00b Add for dewatering @ 5% of cost, if required. metre 18832.00

(iv) Beyond 20m upto 30 m

a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 33640.00b Add 5% of cost for dewatering of the cost, if required metre 44153.00c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 42050.00

(v) Beyond 30m upto 40 m

a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 79925.00b Add 5% of cost for dewatering, if required metre 100705.00c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 95910.00

Sinking of 6 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is reckoned from bed level.

Page 35: Standard Data Book - Rate Analysis

Page 29 of 280

Summary of Rate AnalysisItem No. Descriptions Unit Rate

C Soft rock (6m dia well )

(i) Depth of soft rock strata upto 3m metre 17933.00D Hard rock (6m dia well )

(i) Depth of soft rock strata upto 3m metre 17480.00

12.13

A Sandy soil

(i) Depth below bed level upto 3.0 M metre 12067.00(ii) Beyond 3m upto 10m depth metre 8287.00(iii) Beyond 10m upto 20m

a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 10945.00(iv) Beyond 20m upto 30 m

a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 20529.00b Add 20% of cost for Kentledge including supports, loading arrangement and Labour) . metre 24634.00

(v) Beyond 30m upto 40 m

a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 48773.00b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 58528.00

B Clayey soil ( 7m dia. Well )

(I) Depth below bed level upto 3.0 M metre 8287.00(ii) Beyond 3m upto 10m depth metre 11989.00(iii) Beyond 10 m upto 20 m

a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 15833.00b Add for dewatering @ 5% of cost, if required. metre 16625.00

(iv) Beyond 20m upto 30 m

a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 29699.00b Add 5% of cost for dewatering on the cost, if required metre 38980.00c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 37124.00

(v) Beyond 30m upto 40 m

a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 70561.00b Add 5% of cost for dewatering, if required metre 88906.00c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). 84673.00

C Soft rock ( 7m dia well )

(i) Depth of soft rock strata upto 3m metre 16044.00D Hard rock ( 7m dia well )

(i) Depth upto 3 m metre 19697.00

12.14

A Sandy soil

(i) Depth below bed level upto 3.0 M metre 7508.00(ii) Beyond 3m upto 10m depth metre 9287.00(iii) Beyond 10m upto 20m

a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 12265.00(iv) Beyond 20m upto 30 m

a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 23006.00b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 27607.00

(v) Beyond 30m upto 40 m

a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 8087.00b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 9704.00

B Clayey soil ( 8m dia. Well )

(i) Depth upto 3.0 M metre 10114.00(ii) Beyond 3m upto 10m depth metre 15087.00(iii) Beyond 10 m upto 20 m

a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 19926.00b Add for dewatering @ 5% of cost, if required. metre 20923.00

(iv) Beyond 20m upto 30 m

a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 37377.00b Add 5% of cost for dewatering on the cost, if required metre 49058.00c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 46722.00

Sinking of 7 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is reckoned from bed level.

Sinking of 8 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is reckoned from bed level.

Page 36: Standard Data Book - Rate Analysis

Page 30 of 280

Summary of Rate AnalysisItem No. Descriptions Unit Rate

(v) Beyond 30m upto 40 m

a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 88802.00b Add 5% of cost for dewatering, if required metre 111890.00c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 106562.00

C Soft rock ( 8m dia well )

(i) Depth in soft rock strata upto 3m metre 17663.00D Hard rock ( 8m dia well )

(i) Depth in hard rock strata upto 3 m metre 19440.00

12.15

A Sandy soil

(i) Depth below bed level upto 3.0 M metre 7586.00(ii) Beyond 3m upto 10m depth metre 10222.00(iii) Beyond 10m upto 20m

a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 13501.00(iv) Beyond 20m upto 30 m

a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 25322.00b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 30387.00

(v) Beyond 30m upto 40 m

a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 60162.00b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 72195.00

B Clayey soil ( 9m dia. Well )

(i) Depth below bed level upto 3.0 M metre 10638.00(ii) Beyond 3m upto 10m depth metre 16291.00(iii) Beyond 10 m upto 20 m

a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 21516.00b Add for dewatering @ 5% of cost, if required. metre 22592.00

(iv) Beyond 20m upto 30 m

a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 40359.00b Add 5% of cost for dewatering on the cost, if required metre 52972.00c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 50449.00

(v) Beyond 30m upto 40 m

a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 95889.00b Add 5% of cost for dewatering, if required metre 120821.00c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 115067.00

C Soft rock ( 9m dia well )

(i) Depth upto 3m metre 22133.00D Hard rock ( 9m dia well )

(i) Depth of hard rock strata upto 3 m metre 22814.00

12.16

A Sandy soil

(i) Depth below bed level upto 3.0 M metre 9222.00(ii) Beyond 3m upto 10m depth metre 10750.00(iii) Beyond 10m upto 20m

a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 14196.00(iv) Beyond 20m upto 30 m

a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 26629.00b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 31954.00

(v) Beyond 30m upto 40 m

a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 63267.00b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 75921.00

B Clayey soil (10m dia. Well )

(i) Depth below bed level upto 3.0 M metre 11616.00(ii) Beyond 3m upto 10m depth metre 16053.00(iii) Beyond 10 m upto 20 m

a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 21201.00b Add for dewatering @ 5% of cost, if required. metre 22261.00

Sinking of 9 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is reckoned from bed level.

Sinking of 10 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is reckoned from bed level.

Page 37: Standard Data Book - Rate Analysis

Page 31 of 280

Summary of Rate AnalysisItem No. Descriptions Unit Rate

(iv) Beyond 20m upto 30 m

a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 39767.00'b Add 5% of cost for dewatering on the cost, if required metre 52194.00c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 49709.00

(v) Beyond 30m upto 40 m

a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 94479.00b Add 5% of cost for dewatering, if required metre 119044.00c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). 113375.00

C Soft rock (10m dia well )

(i) Depth of soft rock strata upto 3m metre 22640.00D Hard rock (10m dia well )

(i) Depth of hard rock strata upto 3 m metre 27126.00

12.17

A Sandy soil

(i) Depth from bed level upto 3.0 M metre 21445.00(ii) Beyond 3m upto 10m depth metre 16200.00(iii) Beyond 10m upto 20m

a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 21396.00(iv) Beyond 20m upto 30 m

a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 40136.00b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 48163.00

(v) Beyond 30m upto 40 m

a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 95358.00b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 114429.00

B Clayey soil (11 m dia. Well )

(i) Depth from bed level upto 3.0 M metre 19207.00(ii) Beyond 3m upto 10m depth metre 33025.00(iii) Beyond 10 m upto 20 m

a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 43617.00b Add for dewatering @ 5% of cost, if required. metre 45797.00

(iv) Beyond 20m upto 30 m

a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 81815.00b Add 5% of cost for dewatering on the cost, if required metre 107382.00c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 102268.00

(v) Beyond 30m upto 40 m

a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 194382.00b Add 5% of cost for dewatering, if required metre 244921.00c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 233258.00

C Soft rock (11m dia well )

(i) Depth of soft rock strata upto 3m metre 50547.00D Hard rock (11m dia well )

(i) Depth of hard rock upto 3 m metre 61482.00

12.18

A Sandy soil

(i) I) Depth below bed level upto 3.0 M metre 43965.00(ii) Beyond 3m upto 10m depth metre 48765.00(iii) Beyond 10m upto 20m

a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 64402.00(iv) Beyond 20m upto 30 m

a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 120802.00b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 144963.00

(v) Beyond 30m upto 40 m

a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 287009.00b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 344411.00

B Clayey soil (12 m dia. Well )

(i) Depth below bed level upto 3.0 M metre 47281.00

Sinking of 11 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is reckoned from bed level.

Sinking of 12 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is reckoned from bed level.

Page 38: Standard Data Book - Rate Analysis

Page 32 of 280

Summary of Rate AnalysisItem No. Descriptions Unit Rate

(ii) Beyond 3m upto 10m depth metre 82212.00(iii) Beyond 10 m upto 20 m

a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 108577.00b Add for dewatering @ 5% of cost, if required. metre 114006.00

(iv) Beyond 20m upto 30 m

a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 203661.00b Add 5% of cost for dewatering on the cost, if required metre 267305.00c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 254576.00

(v) Beyond 30m upto 40 m

a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 483870.00b Add 5% of cost for dewatering, if required metre 609677.00c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 580644.00

C Soft rock (12m dia well )

(i) Depth of soft rock strata upto 3m metre 118399.00D Hard rock (12m dia well )

(i) Depth of hard rock strata upto 3 m metre 143400.00

12.19

A Sandy soil

(i) Depth from bed level upto 3.0 M metre 10023.00(ii) Beyond 3m upto 10m depth metre 10766.00(iii) Beyond 10m upto 20m

a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 14217.00(iv) Beyond 20m upto 30 m

a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 26667.00b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 32000.00

(v) Beyond 30m upto 40 m

a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 63355.00b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 76027.00

B Clayey soil (Twin D Type Well )

(i) Depth below bed level upto 3.0 M metre 11552.00(ii) Beyond 3m upto 10m depth metre 17851.00(iii) Beyond 10 m upto 20 m

a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 23575.00b Add for dewatering @ 5% of cost, if required. metre 24753.00

(iv) Beyond 20m upto 30 m

a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 44220.00b Add 5% of cost for dewatering on the cost, if required metre 58040.00c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 55276.00

(v) Beyond 30m upto 40 m

a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 105060.00b Add 5% of cost for dewatering, if required metre 132376.00c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 126072.00

C Soft rock (Twin D Type well )

(i) Depth of soft rock strata upto 3m metre 26632.00D Hard rock (Twin D Type well )

(i) Depth of hard rock strata upto 3 m metre 29293.00

12.20

12.21 Sand filling in wells complete as per drawing and technical specifications cum 811.00

12.22 tonne 72626.00

Sinking of Twin D Type well ( other than pneumatic method of sinking ) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is reckoned from bed level.

Pneumatic sinking of wells with equipment of approved design, drawing and specifications worked by competent and trained personnel and comprising of compression and decompression chambers, reducers, two air locks separately for men and plant & materials, arrangement for supply of fresh air to working chambers, check valves, exhaust valves, shafts made from steel plates of riveted construction not less than 6 mm thick to withstand an air pressure of 0.50 MPa, controlled blasting of hard rock where required, staircases and 1 m wide landing plate forms with railing, arrangement for compression and decompression, electric lighting of 50 V maximum, proper rooms for rest and medical examinations and compliance with safety precautions as per IS:4138, all as per clause1207.6 of MoRTH Specifications.

Providing steel liner 10 mm thick for curbs and 6mm thick for steining of wells including fabricating and setting out as per detailed drawing

Page 39: Standard Data Book - Rate Analysis

Page 33 of 280

Summary of Rate AnalysisItem No. Descriptions Unit Rate

12.23 metre 5405.00

12.24 metre 8805.00

12.25 metre 11188.00

12.26 metre 4069.00

12.27 metre 6456.00

12.28 metre 9430.00

12.29 metre 1667.00

12.30 metre 3001.00

12.31 metre 5053.00

12.32 metre 1219.00

12.33 metre 1917.00

12.34 metre 3694.00

12.35 metre 5299.00

12.36 metre 5975.00

12.37 Pile load test on single vertical pile in accordance with IS:2911(Part-IV)

12.38 Cement concrete for reinforced concrete in pile cap complete as per drawing and Technical Specification

A RCC Grade M20

(i) Using Concrete Mixer cum 4699.00(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 4639.00

B RCC Grade M25

(i) Using concrete mixer. cum 5097.00(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 5029.00

C RCC Grade M30

(i) Using concrete mixer. cum 5147.00(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 5087.00

D RCC Grade M35

(i) Using concrete mixer. cum 5252.00(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 5185.00

12.39 Levelling course for Pile cap cum 3998.00

12.40 tonne 65023.00

12.41 tonne 68405.00

Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and technical specifications and removal of excavated earth with all lifts and lead upto 1000 m. (Pile diameter-750 mm)

Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and technical specifications and removal of excavated earth with all lifts and lead upto 1000 m. (Pile diameter-1000 mm)

Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and technical specifications and removal of excavated earth with all lifts and lead upto 1000 m. (Pile diameter-1200 mm)

Driven cast-in-place vertical M35 grade R.C.C. pile excluding reinforcement complete as per drawing and & Technical Specification (Pile diameter - 750 mm)

Driven cast-in-place vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical Specification (Pile diameter - 1000 mm)

Driven cast-in-place vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical Specification (Pile diameter - 1200 mm)

Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical Specification (Pile Diameter=500 mm)

Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical Specification (Pile Diameter=750 mm)

Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical Specification (Pile Diameter=1000 mm)

Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical Specification (Size of pile - 300 mm x 300 mm)

Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical Specification (Size of pile - 500 mm x 500 mm)

Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical Specification (Size of pile - 750 mm x 750 mm)

Driven vertical steel piles complete as per drawing and & Technical Specification (Section of the pile - H Section steel column 400 x 250 mm (ISHB Series) )

Driven vertical steel piles complete as per drawing and & Technical Specification (Section of the pile - H Section steel column 450 x 250 mm (ISHB Series) )

Supplying, fitting and placing un-coated HYSD bar reinforcement in foundation complete as per drawing and technical specifications

Supplying, fitting and placing un-coated Mild steel reinforcement complete in foundation as per drawing and technical specification

Page 40: Standard Data Book - Rate Analysis

Page 34 of 280

Summary of Rate AnalysisItem No. Descriptions Unit Rate

CHAPTER-13

SUB-STRUCTURE

13.1 cum 4365.00

13.2 Pointing with cement mortar (1:3 ) on brick work in substructure as per Technical specifications sqm 381.0013.3 Plastering with cement mortar (1:3 ) on brick work in sub-structure as per Technical specifications sqm 897.00

13.4Stone masonry work in cement mortar 1:3 for substructure complete as per drawing and Technical Specifications

A Random Rubble Masonry cum 5936.00B Coursed rubble masonry (first sort ) cum 6309.00C Ashlar masonry ( first sort ) cum 7158.00

13.5 Plain/Reinforced cement concrete in sub-structure complete as per drawing and technical specifications

A PCC Grade M15

(p) Height upto 5m cum 4472.00B PCC Grade M20

(p) Height upto 5m cum 4922.00C PCC Grade M25

(p) Height upto 5m

Case I Using concrete Mixer cum 5324.00Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5248.00

(q) Height 5m to 10m

Case I Using concrete Mixer cum 5518.00Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5438.00

(r) Height above 10m

Case I Using concrete Mixer cum 5760.00Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5677.00

D PCC Grade M30

(p) Height upto 5m

Case I Using concrete Mixer cum 5368.00Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5287.00

(q) Height 5m to 10m

Case I Using concrete Mixer cum 5563.00Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5479.00

(r) Height above 10m

Case I Using concrete Mixer cum 5807.00Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5719.00

E RCC Grade M20

(p) Height upto 5m

Case I Using concrete Mixer cum 4999.00Case II With Batching Plant, Transit Mixer and Concrete Pump cum 4919.00

(q) Height 5m to 10m

Case I Using concrete Mixer cum 5181.00Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5098.00

(r) Height above 10m

Case I Using concrete Mixer cum 5408.00Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5322.00

F RCC Grade M25

(p) Height upto 5m

Case I Using concrete Mixer cum 5406.00Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5430.00

(q) Height 5m to 10m

Case I Using concrete Mixer cum 5583.00Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5608.00

(r) Height above 10m

Case I Using concrete Mixer cum 5848.00Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5875.00

G RCC Grade M30

(p) Height upto 5m

Case I Using concrete Mixer cum 5430.00Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5352.00

Brick masonry work in 1:3 in sub-structure complete excluding pointing and plastering, as per drawing and technical specifications

Page 41: Standard Data Book - Rate Analysis

Page 35 of 280

Summary of Rate AnalysisItem No. Descriptions Unit Rate

(q) Height 5m to 10m

Case I Using concrete Mixer cum 5584.00Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5503.00

(r) Height above 10m

Case I Using concrete Mixer cum 5801.00Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5717.00

H RCC Grade M35

(p) Height upto 5m

Case I Using concrete Mixer cum 5541.00Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5573.00

(q) Height 5m to 10m

Case I Using concrete Mixer cum 5662.00Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5694.00

(r) Height above 10m

Case I Using concrete Mixer cum 5843.00Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5877.00

13.6 tonne 65101.00

13.7 tonne 67932.00

13.8 each 124.00

13.9Back filling behind abutment, wing wall and return wall complete as per drawing and Technical specification

A Granular material cum 1320.00B Sandy material cum 922.00

13.10 cum 1572.00

13.11 268.00

13.12 221.00

13.13 277.00

13.14 1.00

13.15 276.00

13.16 222.00

Supplying, fitting and placing HYSD bar reinforcement in sub-structure complete as per drawing and technical specifications

Supplying, fitting and placing Mild steel reinforcement complete in sub-structure as per drawing and technical specification

Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing wall/return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. Complete as per drawing and Technical specifications

Providing and laying of Filter media with granular materials/stone crushed aggregates satisfying the requirements laid down in clause 2504.2.2. of MoRTH specifications to a thickness of not less than 600 mm with smaller size towards the soil and bigger size towards the wall and provided over the entire surface behind abutment, wing wall and return wall to the full height compacted to a firm condition complete as per drawing and technical specification.

Supplying, fitting and fixing in position true to line and level cast steel rocker bearing conforming to IRC: 83(Pt.-1) section IX and clause 2003 of MoRTH specifications complete including all accessories as per drawing and Technical Specifications.

tonne capacity

Supplying, fitting and fixing in position true to line and level forged steel roller bearing conforming to IRC: 83(Pt.-1) section IX and clause 2003 of MoRTH specifications complete including all accessories as per drawing and Technical Specifications.

tonne capacity

Supplying, fitting and fixing in position true to line and level sliding plate bearing with PTFE surface sliding on stainless steel complete including all accessories as per drawing and Technical Specifications and BS: 5400, section 9.1 & 9.2 (for PTFE) and clause 2004 of MoRTH Specifications.

tonne capacity

Supplying, fitting and fixing in position true to line and level elastomeric bearing conforming to IRC: 83 (Part-II) section IX and clause 2005 of MoRTH specifications complete including all accessories as per drawing and Technical Specifications.

cubic centimetre

Supplying, fitting and fixing in position true to line and level sliding plate bearing with stainless steel plate sliding on stainless steel plate with mild steel matrix complete including all accessories as per drawing and Technical Specifications.

tonne capacity

Supplying, fitting and fixing in position true to line and level POT-PTFE bearing consisting of a metal piston supported by a disc or unreinforced elastomer confined within a metal cylinder, sealing rings, dust seals, PTFE surface sliding against stainless steel mating surface, completre assembly to be of cast steel/fabricated structural steel, metal and elastomer elements to be as per IRC: 83 part-I & II respectively and other parts conforming to BS: 5400, section 9.1 & 9.2 and clause 2006 of MoRTH Specifications complete asper drawing and approved technical specifications.

tonne capacity

Page 42: Standard Data Book - Rate Analysis

Page 36 of 280

Summary of Rate AnalysisItem No. Descriptions Unit Rate

CHAPTER-14

SUPER-STRUCTURE

14.1

A RCC Grade M20

Case I Using Concrete Mixer

(i) For solid slab super-structure, 20-30% of (a+b+c)

(p) Height upto 5m cum 5405.00(q) Height 5m to 10m cum 5631.00(r) Height above 10m cum 5856.00

(ii) For T-beam & slab, 25-35% of (a+b+c)

(p) Height upto 5m cum 5631.00(q) Height 5m to 10m cum 5856.00(r) Height above 10m cum 6081.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump

(i) For solid slab super-structure, 20-30% of (a+b+c)

(p) Height upto 5m cum 5317.00(q) Height 5m to 10m cum 5539.00(r) Height above 10m cum 5760.00

(ii) For T-beam & slab, 25-35% of (a+b+c)

(p) Height upto 5m cum 5539.00(q) Height 5m to 10m cum 5760.00(r) Height above 10m cum 5982.00

B RCC Grade M25

Case I Using Concrete Mixer

(i) For solid slab super-structure, 20-30% of (a+b+c)

(p) Height upto 5m cum 5865.00(q) Height 5m to 10m cum 6109.00(r) Height above 10m cum 6354.00

(ii) For T-beam & slab, 25-35% of (a+b+c)

(p) Height upto 5m cum 6109.00(q) Height 5m to 10m cum 6354.00(r) Height above 10m cum 6598.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump

(i) For solid slab super-structure, 20-30% of (a+b+c)

(p) Height upto 5m cum 5783.00(q) Height 5m to 10m cum 6024.00(r) Height above 10m cum 6265.00

(ii) For T-beam & slab, 25-35% of (a+b+c)

(p) Height upto 5m cum 6024.00(q) Height 5m to 10m cum 6265.00(r) Height above 10m cum 6506.00

C RCC Grade M 30

Case I Using Concrete Mixer

(i) For solid slab super-structure, 20-30% of (a+b+c)

(p) Height upto 5m cum 5938.00(q) Height 5m to 10m cum 6185.00(r) Height above 10m cum 6433.00

(ii) For T-beam & slab, 25-35% of (a+b+c)

(p) Height upto 5m cum 6185.00(q) Height 5m to 10m cum 6433.00(r) Height above 10m cum 6680.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump.

(i) For solid slab super-structure, 20-30% of (a+b+c)

(p) Height upto 5m cum 5845.00(q) Height 5m to 10m cum 6088.00(r) Height above 10m cum 6332.00

(ii) For T-beam & slab, 25-35% of (a+b+c)

(p) Height upto 5m cum 6088.00(q) Height 5m to 10m cum 6332.00

Furnishing and Placing Reinforced/Prestressed cement concrete in super-structure as per drawing and Technical Specification

Page 43: Standard Data Book - Rate Analysis

Page 37 of 280

Summary of Rate AnalysisItem No. Descriptions Unit Rate

(r) Height above 10m cum 6576.00D RCC/PSC Grade M35

Case 1 Using concrete mixer.

(i) For solid slab super-structure, 18-28% of (a+b+c)

(p) Height upto 5m cum 5958.00(q) Height 5m to 10m cum 6211.00(r) Height above 10m cum 6463.00

(ii) For T-beam & slab, 23-33% of (a+b+c)

(p) Height upto 5m cum 6211.00(q) Height 5m to 10m cum 6463.00(r) Height above 10m cum 6716.00

(iii) For box girder and balanced cantilever, 38-58% of cost of concrete.

(p) Height upto 5m cum 6968.00(q) Height 5m to 10m cum 7473.00(r) Height above 10m cum 7978.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump

(i) For solid slab super-structure, 18-28% of (a+b+c)

(p) Height upto 5m cum 5861.00(q) Height 5m to 10m cum 6109.00(r) Height above 10m cum 6358.00

(ii) For T-beam & slab, 23-33% of (a+b+c)

(p) Height upto 5m cum 6109.00(q) Height 5m to 10m cum 6358.00(r) Height above 10m cum 6606.00

(iii) For box girder and balanced cantilever, 38-58% of cost of concrete.

(p) Height upto 5m cum 6855.00(q) Height 5m to 10m cum 7351.00(r) Height above 10m cum 7848.00

E PSC Grade M-40

Case 1 Using concrete mixer.

(i) For solid slab super-structure, 20-30% of (a+b+c)

(p) Height upto 5m cum 6272.00(q) Height 5m to 10m cum 6533.00(r) Height above 10m cum 6794.00

(ii) For T-beam & slab, 25-35% of (a+b+c)

(p) Height upto 5m cum 6533.00(q) Height 5m to 10m cum 6794.00(r) Height above 10m cum 7056.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump

(i) For solid slab super-structure, 18-28% of (a+b+c)

(p) Height upto 5m cum 6047.00(q) Height 5m to 10m cum 6303.00(r) Height above 10m cum 6559.00

(ii) For T-beam & slab, 23-33% of (a+b+c)

(p) Height upto 5m cum 6303.00(q) Height 5m to 10m cum 6559.00(r) Height above 10m cum 6815.00

(iii) For box girder and balanced cantilever, 38-58% of cost of concrete.

(p) Height upto 5m cum 7071.00(q) Height 5m to 10m cum 7584.00(r) Height above 10m cum 8096.00

F PSC Grade M-45

(i) For solid slab/voided slab super-structure, 16-26% of cost of concrete (a+b+c)

(p) Height upto 5m cum 6222.00(q) Height 5m to 10m cum 6490.00(r) Height above 10m cum 6758.00

(ii)

(p) Height upto 5m cum 6490.00(q) Height 5m to 10m cum 6758.00

For I-beam & slab including launching of precast girders by launching truss upto 40 m span, 21-31% of cost of concrete.

Page 44: Standard Data Book - Rate Analysis

Page 38 of 280

Summary of Rate AnalysisItem No. Descriptions Unit Rate

(r) Height above 10m cum 7026.00(iii) For cast-in-situ box girder, segmental construction and balanced cantilever, 36-56% of cost of concrete.

(p) Height upto 5m cum 7294.00(q) Height 5m to 10m cum 7831.00(r) Height above 10m cum 8367.00

G PSC Grade M-50

(i) For cast-in-situ box girder, segmental construction and balanced cantilever, 35-55% of cost of concrete

(p) Height upto 5m cum 7471.00(q) Height 5m to 10m cum 8025.00(r) Height above 10m cum 8578.00

H PSC Grade M- 55

(i) For cast-in-situ box girder, segmental construction and balanced cantilever, 35-55% of cost of concrete

(p) Height upto 5m cum 7833.00(q) Height 5m to 10m cum 8413.00(r) Height above 10m cum 8993.19

14.2 tonne 66005.00

14.3 tonne 143718.00

14.4 cum 9848.00

14.5 sqm 316.00

14.6 metre 1707.00

14.7 metre 1655.00

14.8 Providing, fitting and fixing mild steel railing complete as per drawing and Technical Specification metre 2909.0014.9 Drainage Spouts complete as per drawing and Technical specification each 1034.0014.10 PCC M15 Grade leveling course below approach slab complete as per drawing and Technical specification cum 4066.00

14.11 cum 8263.00

14.12 tonne

14.13 cum 20993.00

14.14 Providing and fixing Helical pipes in voided concrete slabs metre 3484.00

14.15

14.16 metre 33.00

14.17 metre 1450.00

14.18 Filler joint

(i) metre 1775.00

(ii) metre 164.00

a) Supplying, fitting and placing HYSD bar reinforcement in super-structure complete as per drawing and technical specifications

High tensile steel wires/strands including all accessories for stressing, stressing operations and grouting complete as per drawing and Technical Specifications

Providing and laying Cement concrete wearing coat M-30 grade including reinforcement complete as per drawing and Technical Specifications

Mastic Asphalt (Providing and laying 12 mm thick mastic asphalt wearing course on top of deck slab excluding prime coat with paving grade bitumen meeting the requirements given in table 500-29, prepared by using mastic cooker and laid to required level and slope after cleaning the surface, including providing antiskid surface with bitumen precoated fine grained hard stone chipping of 9.5 mm nominal size at the rate of 0.005cum per 10 sqm and at an approximate spacing of 10 cm center to center in both directions, pressed into surface when the temperature of surfaces not less than 100 deg. C, protruding 1 mm to 4 mm over mastic surface, all complete as per clause 515.)

Construction of precast RCC railing of M30 Grade, aggregate size not exceeding 12 mm, true to line and grade, tolurence of vertical RCC post not to exceed 1 in 500, centre to centre spacing between vertical post not to exceed 2000 mm, leaving adequate space between vertical post for expansion, complete as per approved drawings and technical specifications.

Construction of RCC railing of M30 Grade in-situ with 20 mm nominal size aggregate, true to line and grade, tolurence of vertical RCC post not to exceed 1 in 500, centre to centre spacing between vertical post not to exceed 2000 mm, leaving adequate space between vertical post for expansion, complete as per approved drawings and technical specifications.

Reinforced cement concrete approach slab including reinforcement and formwork complete as per drawing and Technical specification

Providing anti-corrosive treatment to HYSD reinforcement with Fusion Bonded Epoxy Coating (FBEC) (To be taken as per the prevailing market rates.)

Precast - pretensioned Girders (Providing, precasting, transportation and placing in position precast pretensioned concrete girders as per drawing and technical specifications)

Crash Barriers (The rate analysis for rigid crash barrier in reinforced cement concrete, semi-rigid crash barrier with metal beam and flexible crash barrier with wire ropes have been made and included in chapter-8 on Traffic and Transportation.)

Painting on concrete surface (Providing and applying 2 coats of water based cement paint to unplastered concrete surface after cleaning the surface of dirt, dust, oil, grease, efflorescence and applying paint @ of 1 litre for 2 Sq.m. )

Burried Joint (Providing and laying a burried expansion joint, expansion gap being 20 mm, covered with 12 mm thick, 200 mm wide galvanised wieldable structural steel plate as per IS: 2062, placed symmetrical to centre line of the joint, resting freely over the top surface of the deck concrete, welding of 8 mm dia. 100 mm long galvanised nails spaced 300 mm c/c along the centre line of the plate, all as specified in clause 2604.)

Providing & fixing 2 mm thick corrugated copper plate in expansion joint complete as per drawing & Technical Specification.

Providing & fixing 20 mm thick compressible fibre board in expansion joint complete as per drawing & Technical Specification.

Page 45: Standard Data Book - Rate Analysis

Page 39 of 280

Summary of Rate AnalysisItem No. Descriptions Unit Rate

(iii) metre 387.00

(iv) metre 17.00

14.19 metre 1239.00

14.20 metre 8430.00

14.21 metre 4049.00

14.22 metre 10416.00

14.23 metre 2426.00

14.24 metre 2431.00

Providing and fixing in position 20 mm thick premoulded joint filler in expansion joint for fixed ends of simply supported spans not exceeding 10 m to cater for a horizontal movement upto 20 mm, covered with sealant complete as per drawing and technical specifications.

Providing and filling joint sealing compound as per drawings and technical specifications with coarse sand and 6% bitumen by weight

Asphaltic Plug joint (Providing and laying of asphaltic plug joint to provide for horizontal movement of 25 mm and vertical movement of 2 mm, depth of joint varying from 75 mm to 100 mm, width varying from 500 mm to 750 mm (in traffic direction), covered with a closure plate of 200mm x 6mm of wieldable structural steel conforming to IS: 2062, asphaltic plug to consist of polymer modified bitumen binder, carefully selected single size aggregate of 12.5 mm nominal size and a heat resistant foam caulking/backer rod, all as per approved drawings and specifications.)

Elastomeric Slab Steel Expansion Joint (Providing and laying of an elastomeric slab steel expansion joint, catering to right or skew (less than 20 deg., moderately curved with maximum horizontal movement upto 50 mm, complete as per approved drawings and standard specifications to be installed by the manufacturer/supplier or their authorised representative ensuring compliance to the manufacturer's instructions for installation and clause 2606 of MoRTH specifications for road & bridge works.)

Compression Seal Joint (Providing and laying of compression seal joint consisting of steel armoured nosing at two edges of the joint gap suitably anchored to the deck concrete and a preformed chloroprene elastomer or closed cell foam joint sealer compressed and fixed into the joint gap with special adhesive binder to cater for a horizontal movement upto 40 mm and vertical movement of 3 mm.)

Strip Seal Expansion Joint (Providing and laying of a strip seal expansion joint catering to maximum horizontal movement upto 70 mm, complete as per approved drawings and standard specifications to be installed by the manufacturer/supplier or their authorised representative ensuring compliance to the manufacturer's instructions for installation.)

Modular Strip / Box Seal Joint (Providing and laying of a modular strip Box steel expansion joint including anchorage catering to a horizontal movement beyond 70 mm and upto 140mm, complete as per approved drawings and standard specifications to be installed by the manufacturer/supplier or their authorised representative ensuring compliance to the manufacturer's instructions for installation.)

Modular Strip / Box Seal Joint (Providing and laying of a modular strip box seal expansion joint catering to a horizontal movement beyond 140mm and upto 210mm, complete as per approved drawings and standard specifications to be installed by the manufacturer/supplier or their authorised representative ensuring compliance to the manufacturer's instructions for installation.)

Page 46: Standard Data Book - Rate Analysis

Page 40 of 280

Summary of Rate AnalysisItem No. Descriptions Unit Rate

CHAPTER-15

RIVER TRAINING AND PROTECTION WORKS

15.1

A Boulder laid dry without wire crates. cum 1143.00

15.2 cum 1687.00

15.3 cum 4313.00

15.4

A Stone/Boulder cum 1143.00B Cement Concrete blocks of size 0.3x0.3 x0.3 m cast in cement concrete of Grade M15 cum 4313.00

15.5 cum 1661.00

15.6 sqm 889.00

15.7

15.8

A Rubble stone laid in cement mortar 1:3 cum 3860.00B Cement Concrete blocks Grade M15 cum 5679.00

15.9 Dry rubble Flooring cum 1339.0015.10 Curtain wall complete as per drawing and Technical specification

A Stone masonry in cement mortar (1:3) cum 6211.00B Cement concrete Grade M15 cum 4228.00

15.11 cum 1172.00

15.12 cum 1786.00

15.13 cum 2757.00

Providing and laying boulders apron on river bed for protection against scour with stone boulders weighing not less than 40 kg each complete as per drawing and Technical specification.

Boulder apron laid in wire crates (Providing and laying of boulder apron laid in wire crates made with 4mm dia GI wire conforming to IS: 280 & IS:4826 in 100mm x 100mm mesh (weaved diagonally) including 10% extra for laps and joints laid with stone boulders weighing not less than 40 kg each.)

Cement concrete blocks (size 0.5 x 0.5 x 0.5 m) (Providing and laying of apron with cement concrete blocks of size 0.5x0.5x0.5 m cast in-situ and made with nominal mix of M-15 grade cement concrete with a minimum cement content of 250 kg/cum as per IRC: 21-2000.)

Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in front of toe of embankment complete as per drawing and Technical specifications

Providing and laying Filter material underneath pitching in slopes complete as per drawing and Technical specification

Geotextile Filter (Laying of a geotextile filter between pitching and embankment slopes on which pitching is laid to prevent escape of the embankment material through the voids of the stone pitching/cement concrete blocks as well as to allow free movement of water without creating any uplift head on the pitching.)

Toe protection (A toe wall for toe protection can either be in dry rubble masonry in case of dry rubble pitching or pitching with stones in wire crates or it can be in PCC M15 nominal mix if cement concrete block have been used for pitching . Rates for toe wall can be adopted from respective clauses depending upon approved design. The rate for excavation for foundation, dry rubble masonry and PCC M15 have been analysed and given in respective chapters.)

Providing and laying Flooring complete as per drawing and Technical specifications laid over cement concrete bedding.

Flexible Apron :Construction of flexible apron 1 m thick comprising of loose stone boulders weighing not less than 40 kg beyond curtain wall.

Gabian Structure for Retaining Earth (Providing and construction of a gabain structure for retaining earth with segments of wire crates of size 7 m x 3 m x 0.6 m each divided into 1.5 m compartments by cross netting, made from 4 mm galvanised steel wire @ 32 kg per 10 sqm having minimum tensile strength of 300 Mpa conforming to IS:280 and galvanizing coating conforming to IS:4826, woven into mesh with double twist, mesh size not exceeding 100 x 100 mm, filled with boulders with least dimension of 200 mm, all loose ends to be tied with 4 mm galvanised steel wire)

Gabian Structure for Erosion Control, River Training Works and Protection works (Providing and constructing gabain structures for erosion control, river training works and protection works with wire crates of size 2 m x 1 m x 0.3 m each divided into 1m compartments by cross netting, made from 4 mm galvanised steel wire @ 32 kg per 10 sqm having minimum tensile strength of 300 Mpa conforming to IS:280 and galvanizing coating conforming to IS:4826, woven into mesh with double twist, mesh size not exceeding 100 mm x 100 mm, filled with boulders with least dimension of 200 mm, all loose ends to be securely tied with 4 mm galvanised steel wire.)

Page 47: Standard Data Book - Rate Analysis

Page 41 of 280

Summary of Rate AnalysisItem No. Descriptions Unit Rate

CHAPTER-16

REPAIR AND REHABILITATION

16.1 sqm 83.00

16.2 sqm 63.00

16.3 sqm 909.00

16.4 each 435.00

16.5

A Cement Grout kg 60.00B Cement mortar (1:1) Grouting kg 105.00

16.6 sqm 2238.00

16.7Sealing of crack / porous concrete with Epoxy Grout by injection through nipples complete as per clause 2803.1.

kg 807.00

16.8 sqm 464.00

16.9 sqm 354.00

16.10 sqm 201.00

16.11 Eproxy bonding of new concrete to old concrete sqm 572.00

16.12 tonne 462801.00

16.13 tonne 371286.00

16.14 tonne 330729.00

16.15 Replacement of bearings complete as per Technical specification each 71361.0016.16 Rectification of bearings as per Technical specifications each 4279.0016.17 Replacement of Expansion Joints complete as per drawings metre 2469.0016.18 Replacement of damaged concrete railing. metre 137.0016.19 Replacement of crash barrier. metre 235.0016.20 Replacement of damaged mild steel railing metre 117.00

16.21 metre 152.00

16.22 metre 113.0016.23 metre 271.00

Removal of existing cement concrete wearing coat including its disposal complete as per Technical specification without causing any detrimental effect to any part of the bridge structure and removal of dismantled material with all lifts and lead upto 1000m(Thickness 75 mm)

Removal of existing asphaltic wearing coat comprising of 50 mm thick asphaltic concrete laid over 12 mm thick mastic asphalt including disposal with all lift and lead upto 1000m.

Guniting concrete surface with cement mortar applied with compressor after cleaning surface and spraying with epoxy complete as per Technical specification

Providing and inserting nipples with approved fixing compound after drilling holes for grouting as per Technical specifications including subsequent cutting/removal and sealing of the hole as necessary of nipples after completion of grouting with Cement/Epoxy

Sealing of cracks/porous concrete by injection process through nipples/Grouting complete as per Technical specification.

Patching of damaged concrete surface with polymer concrete and curing compounds, initiator and promoter, available in present formulations, to be applied as per instructions of manufacturer and as approved by the Engineer.

Applying epoxy mortar over leached, honey combed and spalled concrete surface and exposed steel reinforcement complete as per Technical specification

Removal of defective concrete, cleaning the surface thoroughly, applying the shotcrete mixture mechanically with compressed air under pressure, comprising of cement, sand, coarse aggregates, water and quick setting compound in the proportion as per clause 2807.1., sand and coarse aggregates conforming to IS: 383 and table 1 of IS: 9012 respectively, water cement ratio ranging from 0.35 to 0.50, density of gunite not less than 2000 kg/cum, strength not less than 25 Mpa and workmanship conforming to clause 2807.6.

Applying pre-packed cement based polymer mortar of strength 45 Mpa at 28 days for replacement of spalled concrete

Providing external prestressing with high tensile steel wires/strands including drilling for passage of prestessing steel, all accessories for stressing and stressing operation and grouting complete as per drawing and Technical specification

Providing external prestressing with high tensile steel wires/strands including drilling for passage of prestessing steel, all accessories for stressing and stressing operation and grouting complete as per drawing and Technical specification

Providing external prestressing with high tensile steel wires/strands including drilling for passage of prestessing steel, all accessories for stressing and stressing operation and grouting complete as per drawing and Technical specification

Repair of crash barrier (Repair of concrete crash barrier with cement concrete of M-30 grade by cutting and trimming the damaged portion to a regular shape, cleaning the area to be repaired thoroughly, applying cement concrete after erection of proper form work.)

Repair of RCC Railing (Carrying out repair of RCC M30 railing to bring it to the original shape.)

Repair of steel Railing (Repair of steel railing to bring it to the original shape)

Page 48: Standard Data Book - Rate Analysis

Page 1 of 280

CHAPTER-1CARRIAGE OF MATERIALS

Sr No Description Unit Quantity Rate Rs Cost Rs

1.1 cum

Unit = cumTaking output = 5.5 cum Time required for

i) Positioning of tipper at loading point 1 Min13 Min

2 Min

iv) Waiting time, unforeseen contingencies etc 4 MinTotal 20 Min

a) MachineryTipper 5.5 tonnes capacity hour 0.330 339.00 111.87 P&M-048

hour 0.330 806.00 265.98 P&M-017

b) Overhead charges @ 0.1 on (a) 37.79 c) Contractor's profit @ 0.1 on (a+b) 41.56 Cost for 5.5 cum = a+b+c 457.20 Rate per cum = (a+b+c)/ 5.5 83.13

Note Unloading will be by tipping. say 83.00 1.2 Loading and Unloading of Boulders by Manual Means

Unit = cumTaking output = 5.5 cuma) Labour

Mate day 0.110 151.44 16.66 L-12Mazdoor for loading and unloading day 0.750 136.69 102.52 L-13

b) MachineryTipper 5.5 tonne capacity hour 0.750 339.00 254.25 P&M-048

c) Overhead charges @ 0.1 on (a+b) 37.34 d) Contractor's profit @ 0.1 on (a+b+c) 41.08 Cost for5.5 cum = a+b+c+d 451.85 Rate per cum = (a+b+c+d)/5.5 82.15

Note Unloading will be by tipping. say 82.00 1.3

Unit = tonneTaking output = 10 tonnesa) Labour

Mate day 0.080 151.44 12.12 L-12Mazdoor for loading and unloading day 2.000 136.69 273.38 L-13

b) MachineryTruck 10 tonne capacity hour 2.000 315.27 630.54 P&M-057

c) Overhead charges @ 0.1 on (a+b) 91.60 d) Contractor's profit @ 0.1 on (a+b+c) 100.76 Cost for10 tonnes = a+b+c+d 1108.40 Rate per tonnes = (a+b+c+d)/10 110.84

say 111.00 1.4 Cost of Haulage Excluding Loading and Unloading

Unit = t.kmTaking output 10 tonnes load and lead 10 km = 100 t.km

(i) Surfaced RoadSpeed with load : 25 km / hour.Speed while Returning empty :35 km / hour.a) Machinery.

Tipper 10 tonne capacityTime taken for onward haulage with load hour 0.400 339.00 135.60 P&M-048Time taken for empty return trip. hour 0.290 339.00 98.31 P&M-048

b) Overhead charges @ 0.1 on (a) 23.39 c) Contractor's profit @ 0.1 on (a+b) 25.73

Ref. to MoRTH Spec.

Remarks/ Input ref.

Loading and Unloading of Stone Boulder/Stone aggregates/Sand/Kanker/Moorum.

Placing tipper at loading point, loading with front end loader, dumping, turning for return trip, excluding time for haulage and return trip

ii) Loading by front end loader 1 cum bucket capacity @ 25 cum per hour

iii) Maneuvering, reversing, dumping and turning for return

Front end-loader 1 cum bucket capacity @ 25 cum/hour

Loading and Unloading of Cement or Steel by Manual Means and Stacking.

Haulage of materials by tipper excluding cost of loading, unloading and stacking.

Page 49: Standard Data Book - Rate Analysis

Page 2 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

cost for 100 t km = a+b+c 283.03 Rate per t.km = (a+b+c)/100 2.83

say 2.80

1.4 (ii) Unsurfaced Graveled Road

Speed with load: 20 km / hour

Speed for empty return trip :30 km / hour

a) Machinery

Tipper 10 tonnes capacity

Time taken for onward haulage with load hour 0.500 339.00 169.50 P&M-048

Time taken for empty return trip hour 0.330 339.00 111.87 P&M-048

b) Overhead charges @ 0.1 on (a) 28.14

c) Contractor's profit @ 0.1 on (a+b) 30.95

Cost for 100 t .km = a+b+c 340.46

Rate per t.Km = (a+b+c)/100 3.40

say 3.40

1.4 (iii)

Speed with load :10 km / hour

Speed while returning empty:15 km / hour

a) Machinery

Tipper 10 tonnes capacity

Time taken for onward haulage hour 1.000 339.00 339.00 P&M-048

Time taken for empty return trip hour 0.670 339.00 227.13 P&M-048

b) Overhead charges @ 0.1 on (a) 56.61

c) Contractor's profit @ 0.1 on (a+b) 62.27

Cost for 100 t .km = a+b+c 685.02

Rate per t.Km = (a+b+c)/100 6.85

say 6.90

1.5 Hand Broken Stone Aggregates 63 mm Nominal Size

Unit = cum

Taking output = 1 cum

a) Labour

Mate day 0.060 151.44 9.09 L-12

Mazdoor day 1.500 136.69 205.04 L-13

b) Material

Supply of quarried stone 150 - 200 mm size cum 1.100 494.68 544.15 M-002

c) Overhead charges @ 0.1 on (a+b) 75.83

d) Contractor's profit @ 0.1 on (a+b+c) 83.41

Rate per cum = a+b+c+d 917.51

say 918.00

1.6 Crushing of Stone Aggregates 13.2 mm Nominal Size.

Unit = cum

Taking Output = 600 cum at crusher location.

a) Labour

Mate day 0.760 151.44 115.09 L-12

Mazdoor Skilled day 2.000 230.00 460.00 L-14

Mazdoor including breaking of any oversize boulder. day 17.000 136.69 2323.73 L-13

b) Material

Stone Boulder of size 150 mm and below cum 800.000 919.00 735200.00 M-001

Katcha Track and Track in River Bed/Nallah Bed and Choe Bed.

Supply of quarried stone, hand breaking into coarse aggregate 63 mm nominal size (passing 80 mm and retained on 50 mm sieve) and stacking as directed

Crushing of stone boulders of 150 mm size in an integrated stone crushing unit of 200 tonnes per hour capacity comprising of primary and secondary crushing units, belt conveyor and vibrating screens to obtain stone aggregates of 13.2 mm nominal size.

Page 50: Standard Data Book - Rate Analysis

Page 3 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

c) Machinery

Hour 6.000 18228.00 109368.00 P&M-028

Front end loader 1 cum bucket capacity Hour 20.000 806.00 16120.00 P&M-017

Tipper 5.5 cum capacity Hour 20.000 339.00 6780.00 P&M-048

d) Overhead charges @ 0.1 on (a+b+c) 87036.68

e) Contractor's profit @ 0.1 on (a+b+c+d) 95740.35

Cost for 600 cum = a+b+c+d+e 1053143.86

Rate per cum = (a+b+c+d+e)*0.95/600 1667.48

say 1667.00

Note

1.7 Crushing of Stone Aggregates 20 mm Nominal Size

Unit = cum

Taking Output = 670 cum at crusher location.

a) Labour

Mate day 0.760 151.44 115.09 L-12

Mazdoor Skilled day 2.000 230.00 460.00 L-14

Mazdoor including breaking of any size boulder. day 17.000 136.69 2323.73 L-13

b) Material

Stone Boulder of size 150 mm and below cum 800.000 919.00 735200.00 M-001

c) Machinery

Hour 6.000 18228.00 109368.00 P&M-028

Front end loader 1 cum bucket capacity Hour 20.000 806.00 16120.00 P&M-017

Tipper 5.5 cum capacity Hour 20.000 339.00 6780.00 P&M-048

d) Overhead charges @ 0.1 on (a+b+c) 87036.68

e) Contractor's profit @ 0.1 on (a+b+c+d) 95740.35

Cost for 670 cum = a+b+c+d+e 1053143.86

Rate per cum = (a+b+c+d+e)*0.90/670 1414.67

say 1415.00

Note

1.8 Crushing of Stone Aggregates 40 mm Nominal Size

Unit = cum

Taking Output = 750 cum at crusher location.

a) Labour

Mate day 0.760 151.44 115.09 L-12

Mazdoor Skilled day 2.000 230.00 460.00 L-14

Integrated stone crusher of 200 TPH including belt conveyor and vibrating screens

1. 800 cum of stone boulders are needed to get 600 cum of stone chips of size 13.2 mm.

2. 95 per cent of above cost will be attributed to the production of 600 cum of stone chips of 13.2 mm size and balance 5 per cent to the production of stone dust which comes out as a by-product.

3. The integrated stone crusher includes primary and secondary crushing units.

Crushing of stone boulders of 150 mm size in an integrated stone crushing unit of 200 tonnes per hour capacity comprising of primary and secondary crushing units, belt conveyor and vibrating screens to obtain stone aggregates of 20 mm nominal size.

Integrated stone crusher of 200 TPH including belt conveyor and vibrating screens

1. 800 cum of stone boulders are needed to get 600 cum of stone chips of size 20 and 40 mm.

2. 90 per cent of above cost will be attributed to the production of 670 cum of stone aggregates of 20mm size and balance 10 per cent will be for smaller size aggregates and stone dust which comes out as a by-product.

3. The integrated stone crusher includes primary and secondary crushing units.

Crushing of stone boulders of 150 mm size in an integrated stone crushing unit of 200 tonnes per hour capacity comprising of primary and secondary crushing units, belt conveyor and vibrating screens to obtain stone aggregates of 40 mm nominal size.

Page 51: Standard Data Book - Rate Analysis

Page 4 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Mazdoor day 17.000 136.69 2323.73 L-13

b) Material

Stone Boulder of size 150 mm and below cum 800.000 919.00 735200.00 M-001

c) Machinery

Hour 6.000 18228.00 109368.00 P&M-028

Front end loader 1 cum bucket capacity Hour 20.000 806.00 16120.00 P&M-017

Tipper 5.5 cum capacity Hour 20.000 339.00 6780.00 P&M-048

d) Overhead charges @ 0.1 on (a+b+c) 87036.68

e) Contractor's profit @ 0.1 on (a+b+c+d) 95740.35

Cost for 750 cum = (a+b+c+d+e)x0.85 895172.28

Rate per cum = (a+b+c+d+e)x0.85/750 1193.56

say 1194.00

Note

Integrated stone crusher of 200 TPH including belt conveyor and vibrating screens

1. 800 cum of stone boulders are needed to get 600 cum of stone chips of size 13.2 mm.

2. 85 per cent of above cost will be attributed to the production of 750 cum of stone aggregates of 40mm size and balance 15 per cent will be for smaller size aggregates and stone dust which comes out as a by-product.

3. The integrated stone crusher includes primary and secondary crushing units.

Page 52: Standard Data Book - Rate Analysis

Page 1 of 280

CHAPTER-2SITE CLEARANCE

Sr No Description Unit Quantity Rate Rs Cost Rs

2.1 201

Unit = Each(i) Girth from 300 mm to 600 mm

a) Labour

Mate day 0.020 151.44 3.03 L-12

day 0.600 136.69 82.01 L-13

b) Machinery

Tractor-trolley hour 0.100 282.50 28.25 P&M-053

c) Overhead charges @ 0.1 on (a+b) 11.33

d) Contractor's profit @ 0.1 on (a+b+c) 12.46

Rate for each tree = a+b+c+d 137.08

say 137.00

2.1 (ii) Girth from 600 mm to 900 mma) Labour

Mate day 0.040 151.44 6.06 L-12

day 0.900 136.69 123.02 L-13

b) Machinery

Tractor-trolley hour 0.300 282.50 84.75 P&M-053

c) Overhead charges @ 0.1 on (a+b) 21.38

d) Contractor's profit @ 0.1 on (a+b+c) 23.52

Rate for each tree = a+b+c+d 258.73

say 259.00

2.1 (iii) Girth from 900 mm to 1800 mma) Labour

Mate day 0.080 151.44 12.12 L-12

day 2.000 136.69 273.38 L-13

b) Machinery

Tractor-trolley hour 0.400 282.50 113.00 P&M-053

c) Overhead charges @ 0.1 on (a+b) 39.85

d) Contractor's profit @ 0.1 on (a+b+c) 43.83

Rate for each tree = a+b+c+d 482.18

say 482.00

2.1 (iv) Girth above 1800 mm a) Labour

Mate day 0.160 151.44 24.23 L-12day 4.000 136.69 546.76 L-13

b) MachineryTractor-trolley hour 0.600 282.50 169.50 P&M-053

c) Overhead charges @ 0.1 on (a+b) 74.05 d) Contractor's profit @ 0.1 on (a+b+c) 81.45 Rate for each tree = a+b+c+d 895.99

say 896.00 2.2 201 Clearing Grass and Removal of Rubbish

By Manual MeansUnit = HectareTaking output = 1 Hectare

Ref. to MoRTH Spec.

Remarks/ Input ref.

Cutting of Trees, including cutting of Trunks, Branches and Removal

Cutting of trees, including cutting of trunks, branches and removal of stumps, roots, stacking of serviceable material with all lifts and up to a lead of 1000 metres and earth filling in the depression/pit.

Mazdoors for cutting trees including cutting, refilling, compaction of backfilling and stacking of serviceable materials within 1000 metres lead by manual means.

Mazdoors for cutting trees including cutting, refilling, compaction of backfilling, and stacking of serviceable materials within 1000 metres lead by manual means

Mazdoors for cutting trees including cutting, refilling, compaction of backfilling and stacking of serviceable materials within 1000 metres

Mazdoors for cutting trees including cutting, refilling, compaction of backfilling and stacking of serviceable materials within 1000 metres

Clearing grass and removal of rubbish up to a distance of 50 metres outside the periphery of the area .

Page 53: Standard Data Book - Rate Analysis

Page 2 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

a) LabourMate day 2.000 151.44 302.88 L-12Mazdoor day 50.000 136.69 6834.50 L-13

b) Overhead charges @ 0.1 on (a) 713.74 c) Contractor's profit @ 0.1 on (a+b) 785.11 Rate per Hectare = a+b+c 8636.23

say 8636.00 2.3 201 Clearing and Grubbing Road Land .

Unit = HectareTaking output = 1 Hectare

(i) By Manual Means:-

A In area of light jungle

a) Labour

Mate day 6.000 151.44 908.64 L-12

Mazdoor day 150.000 136.69 20503.50 L-13

b) Machinery

Tractor-trolley hour 1.000 282.50 282.50 P&M-053

c) Overhead charges @ 0.1 on (a+b) 2169.46

d) Contractor's profit @ 0.1 on (a+b+c) 2386.41

Rate per Hectare = a+b+c+d 26250.51

say 34411.00

2.3 (i) B In area of thorny jungle

a) Labour

Mate day 8.000 151.44 1211.52 L-12

Mazdoor day 200.000 136.69 27338.00 L-13

b) Machinery

Tractor-trolley hour 2.000 282.50 565.00 P&M-053

c) Overhead charges @ 0.1 on (a+b) 2911.45

d) Contractor's profit @ 0.1 on (a+b+c) 3202.60

Rate per Hectare = a+b+c+d 35228.57

say 35229.00

2.3 (ii) By Mechanical Means

A In area of light jungle

a) Labour

Mate day 0.160 151.44 24.23 L-12

Mazdoor day 4.000 136.69 546.76 L-13

b) Machinery

hour 10.000 3720.00 37200.00 P&M-014

Tractor-trolley hour 1.000 282.50 282.50 P&M-053

c) Overhead charges @ 0.1 on (a+b) 3805.35

d) Contractor's profit @ 0.1 on (a+b+c) 4185.88

Rate per Hectare = a+b+c+d 46044.72

Add 12% Premium 5525.37

Total = 51570.09

say 49142.00

2.3 (ii) B In area of thorny jungle

a) Labour

Mate day 0.240 151.44 36.35 L-12

Mazdoor day 6.000 136.69 820.14 L-13

b) Machinery

hour 12.000 3720.00 44640.00 P&M-014

Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, up to a lead of 1000 metres including removal and disposal of top organic soil not exceeding 150 mm in thickness.

Dozer 80 HP with attachment for removal of trees & stumps

Dozer 80 HP with attachment for removal of trees & stumps

Page 54: Standard Data Book - Rate Analysis

Page 3 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Tractor-trolley hour 1.500 282.50 423.75 P&M-053

c) Overhead charges @ 0.1 on (a+b) 4592.02

d) Contractor's profit @ 0.1 on (a+b+c) 5051.23

Rate per Hectare = a+b+c+d 55563.49

say 55563.00

2.4 202 Dismantling of Structures

Unit = cum

Taking output = 1.25 cum

(i) Lime /Cement Concrete

I By Manual Means

A Lime Concrete, cement concrete grade M-10 and below

a) Labour

Mate day 0.040 151.44 6.06 L-12

Mazdoor for dismantling and loading day 1.000 136.69 136.69 L-13

b) Machinery

Tractor-trolley hour 0.270 282.50 76.28 P&M-053

c) Overhead charges @ 0.1 on (a+b) 21.90

d) Contractor's profit @ 0.1 on (a+b+c) 24.09

Cost for 1.25 cum = a+b+c+d 265.02

Rate per cum = (a+b+c+d)/ 1.25 212.01

say 212.00

2.4 (i) B Cement Concrete Grade M-15 & M-20

a) Labour

Mate day 0.050 151.44 7.57 L-12

Mazdoor for dismantling and loading day 1.250 136.69 170.86 L-13

b) Machinery

Tractor-trolley hour 0.270 282.50 76.28 P&M-053

c) Overhead charges @ 0.1 on (a+b) 25.47

d) Contractor's profit @ 0.1 on (a+b+c) 28.02

Cost for 1.25 cum = a+b+c+d 308.20

Rate per cum = (a+b+c+d)/ 1.25 246.56

say 247.00

2.4 (i) C

a) Labour

Mate day 0.150 151.44 22.72 L-12

Blacksmith day 0.250 264.50 66.13 L-02

Mazdoor for dismantling, loading and unloading day 3.500 136.69 478.41 L-13

b) Machinery

Tractor-trolley hour 0.270 282.50 76.28 P&M-053

c) Overhead charges @ 0.1 on (a+b) 64.35

d) Contractor's profit @ 0.1 on (a+b+c) 70.79

Cost for 1.25 cum = a+b+c+d 778.67

Rate per cum = (a+b+c+d)/ 1.25 622.94

say 623.00

2.4 II By Mechanical Means for items No. 202( b)& ( c)

A Cement Concrete Grade M-15 & M-20

a) Labour

Mate day 0.020 151.44 3.03 L-12

Mazdoor for loading and unloading day 0.250 136.69 34.17 L-13

Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 metres

Prestressed / Reinforced cement concrete grade M-20 & above

Page 55: Standard Data Book - Rate Analysis

Page 4 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Mazdoor with Pneumatic breaker day 0.250 230.00 57.50 L-14

b) Machinery

hour 0.670 319.00 213.73 P&M-001

Tractor-trolley hour 0.270 282.50 76.28 P&M-053

c) Overhead charges @ 0.1 on (a+b) 38.47

d) Contractor's profit @ 0.1 on (a+b+c) 42.32

Cost for 1.25 cum = a+b+c+d 465.49

Rate per cum = (a+b+c+d)/ 1.25 372.40

say 372.00

2.4 II B

a) Labour

Mate day 0.050 151.44 7.57 L-12

Mazdoor with Pneumatic breaker day 0.660 230.00 151.80 L-14

Blacksmith day 0.250 264.50 66.13 L-02

Mazdoor for loading and unloading day 0.250 136.69 34.17 L-13

b) Machinery

hour 1.000 319.00 319.00 P&M-001

Tractor-trolley hour 0.270 282.50 76.28 P&M-053

c) Overhead charges @ 0.1 on (a+b) 65.49

d) Contractor's profit @ 0.1 on (a+b+c) 72.04

Cost for 1.25 cum = a+b+c+d 792.48

Rate per cum = (a+b+c+d)/ 1.25 633.99

say 634.00

2.4 (ii) Dismantling Brick / Tile work

A In lime mortar

a) Labour

Mate day 0.020 151.44 3.03 L-12

Mazdoor for dismantling, loading and unloading day 0.500 136.69 68.35 L-13

b) Machinery

Tractor-trolley hour 0.270 282.50 76.28 P&M-053

c) Overhead charges @ 0.1 on (a+b) 14.76

d) Contractor's profit @ 0.1 on (a+b+c) 16.24

Cost for 1.25 cum = a+b+c+d 178.66

Rate per cum = (a+b+c+d)/ 1.25 142.92

say 143.00

2.4 (ii) B In cement mortar

a) Labour

Mate day 0.030 151.44 4.54 L-12

Mazdoor for dismantling, loading and unloading day 0.750 136.69 102.52 L-13

b) Machinery

Tractor-trolley hour 0.270 282.50 76.28 P&M-053

c) Overhead charges @ 0.1 on (a+b) 18.33

d) Contractor's profit @ 0.1 on (a+b+c) 20.17

Cost for 1.25 cum = a+b+c+d 221.84

Rate per cum = (a+b+c+d)/ 1.25 177.47

say 177.00

2.4 (ii) C In mud mortar

a) Labour

Mate day 0.016 151.44 2.42 L-12

Mazdoor for dismantling and loading day 0.400 136.69 54.68 L-13

b) Machinery

Tractor-trolley hour 0.270 282.50 76.28 P&M-053

c) Overhead charges @ 0.1 on (a+b) 13.34

d) Contractor's profit @ 0.1 on (a+b+c) 14.67

Air Compressor 250 cfm with 2 leads of pneumatic breaker @ 1.5 cum per hour

Prestressed / reinforced cement concrete grade M-20 & above

Air Compressor 250 cfm with 2 leads of pneumatic breaker @ 1.00 cum per hour

Page 56: Standard Data Book - Rate Analysis

Page 5 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Cost for 1.25 cum = a+b+c+d 161.38

Rate per cum = (a+b+c+d)/ 1.25 129.11

say 129.00

2.4 (ii) D Dry brick pitching or brick soling

a) Labour

Mate day 0.014 151.44 2.12 L-12

Mazdoor for Dismantling, loading and unloading day 0.350 136.69 47.84 L-13

b) Machinery

Tractor-trolley hour 0.270 282.50 76.28 P&M-053

c) Overhead charges @ 0.1 on (a+b) 12.62

d) Contractor's profit @ 0.1 on (a+b+c) 13.89

Cost for 1.25 cum = a+b+c+d 152.75

Rate per cum = (a+b+c+d)/ 1.25 122.20

say 122.00

2.4 (iii) Dismantling Stone Masonry

A Rubble stone masonry in lime mortar

a) Labour

Mate day 0.024 151.44 3.63 L-12

Mazdoor for dismantling, loading and unloading. day 0.600 136.69 82.01 L-13

b) Machinery

Tractor-trolley hour 0.270 282.50 76.28 P&M-053

c) Overhead charges @ 0.1 on (a+b) 16.19

d) Contractor's profit @ 0.1 on (a+b+c) 17.81

Cost for 1.25 cum = a+b+c+d 195.93

Rate per cum = (a+b+c+d)/ 1.25 156.74

say 157.00

2.4 (iii) B Rubble stone masonry in cement mortar.

a) Labour

Mate day 0.030 151.44 4.54 L-12

Mazdoor for dismantling, loading and unloading. day 0.750 136.69 102.52 L-13

b) Machinery

Tractor-trolley hour 0.270 282.50 76.28 P&M-053

c) Overhead charges @ 0.1 on (a+b) 18.33

d) Contractor's profit @ 0.1 on (a+b+c) 20.17

Cost for 1.25 cum = a+b+c+d 221.84

Rate per cum = (a+b+c+d)/ 1.25 177.47

say 177.00

2.4 (iii) C Rubble Stone Masonry in mud mortar.

a) Labour

Mate day 0.020 151.44 3.03 L-12

Mazdoor for dismantling, loading and unloading. day 0.500 136.69 68.35 L-13

b) Machinery

Tractor-trolley hour 0.270 282.50 76.28 P&M-053

c) Overhead charges @ 0.1 on (a+b) 14.76

d) Contractor's profit @ 0.1 on (a+b+c) 16.24

Cost for 1.25 cum = a+b+c+d 178.66

Rate per cum = (a+b+c+d)/ 1.25 142.92

say 143.00

2.4 (iii) D Dry rubble masonry

a) Labour

Mate day 0.018 151.44 2.73 L-12

Mazdoor for dismantling, loading and unloading. day 0.450 136.69 61.51 L-13

b) Machinery

Tractor-trolley hour 0.270 282.50 76.28 P&M-053

c) Overhead charges @ 0.1 on (a+b) 14.05

d) Contractor's profit @ 0.1 on (a+b+c) 15.46

Page 57: Standard Data Book - Rate Analysis

Page 6 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Cost for 1.25 cum = a+b+c+d 170.02

Rate per cum = (a+b+c+d)/ 1.25 136.02

say 136.00

2.4 (iii) E Dismantling stone pitching/ dry stone spalls.

a) Labour

Mate day 0.016 151.44 2.42 L-12

Mazdoor for dismantling, loading and unloading. day 0.400 136.69 54.68 L-13

b) Machinery

Tractor-trolley hour 0.270 282.50 76.28 P&M-053

c) Overhead charges @ 0.1 on (a+b) 13.34

d) Contractor's profit @ 0.1 on (a+b+c) 14.67

Cost for 1.25 cum = a+b+c+d 161.38

Rate per cum = (a+b+c+d)/ 1.25 129.11

say 129.00

2.4 (iii) F

a) Labour

Mate day 0.020 151.44 3.03 L-12

Mazdoor for dismantling, loading and unloading day 0.500 136.69 68.35 L-13

b) Machinery

Tractor-trolley hour 0.270 282.50 76.28 P&M-053

c) Overhead charges @ 0.1 on (a+b) 14.76

d) Contractor's profit @ 0.1 on (a+b+c) 16.24

Cost for 1.25 cum = a+b+c+d 178.66

Rate per cum = (a+b+c+d)/ 1.25 142.92

say 143.00

2.4 (iv)

a) Labour

Mate day 0.060 151.44 9.09 L-12

Carpenter day 0.500 264.50 132.25 L-04

Mazdoor for dismantling, loading and unloading. day 1.000 136.69 136.69 L-13

b) Machinery

Tractor-trolley hour 0.270 282.50 76.28 P&M-053

c) Overhead charges @ 0.1 on (a+b) 35.43

d) Contractor's profit @ 0.1 on (a+b+c) 38.97

Cost for 1.25 cum = a+b+c+d 428.70

Rate per cum = (a+b+c+d)/ 1.25 342.96

say 343.00

2.4 (v)

Unit = tonne

Taking output = 1 tonne

A Including dismembering

a) Labour

Mate day 0.140 151.44 21.20 L-12

Blacksmith day 1.000 264.50 264.50 L-02

Mazdoor for dismantling, loading and unloading day 2.500 136.69 341.73 L-13

15.69

b) Machinery

Tractor-trolley hour 0.170 282.50 48.03 P&M-053

c) Overhead charges @ 0.1 on (a+b) 69.11

d) Contractor's profit @ 0.1 on (a+b+c) 76.03

Rate per tonne = a+b+c+d 836.28

say 836.00

2.4 (v) B Excluding dismembering.

Dismantling boulders laid in wire crates including opening of crates and stacking dismantled materials.

Wood Work wrought framed and fixed in frames of trusses upto a height of 5 m above plinth level

Steel Work in all types of sections upto a height of 5 m above plinth level excluding cutting of rivet.

Add 2.5 per cent of cost of labour for gas cutting, ropes, pulleys etc.

Page 58: Standard Data Book - Rate Analysis

Page 7 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

a) Labour

Mate day 0.220 151.44 33.32 L-12

Mazdoor for dismantling, loading and unloading day 2.000 136.69 273.38 L-13

Blacksmith day 0.500 264.50 132.25 L-02

10.97

b) Machinery

Tractor-trolley hour 0.170 282.50 48.03 P&M-053

c) Overhead charges @ 0.1 on (a+b) 49.79

d) Contractor's profit @ 0.1 on (a+b+c) 54.77

Rate per tonne = a+b+c+d 602.51

say 603.00

2.4 (v) C Extra over item No( v ) A and( v ) B for cutting rivets.

Unit = each

Taking output = 10 rivets

a) Labour

Mate day 0.010 151.44 1.51 L-12

Blacksmith day 0.130 264.50 34.39 L-02

Mazdoor day 0.130 136.69 17.77 L-13

b) Overhead charges @ 0.1 on (a) 5.37

c) Contractor's profit @ 0.1 on (a+b) 5.90

Cost for 10 rivets = a+b+c 64.94

Rate for each rivet = ( a+b+c)/10 6.49

say 6.00

2.4 (vi)

Unit = numbers

Taking output = 1000 numbers

A In lime/Cement mortar

a) Labour

Mate day 0.140 151.44 21.20 L-12

Mazdoor day 3.500 136.69 478.41 L-13

b) Overhead charges @ 0.1 on (a) 49.96

c) Contractor's profit @ 0.1 on (a+b) 54.96

Rate per1000 Nos = a+b+c 604.54

say 605.00

2.4 (iv) B In mud mortar

a) Labour

Mate day 0.050 151.44 7.57 L-12

Mazdoor day 1.250 136.69 170.86 L-13

b) Overhead charges @ 0.1 on (a) 17.84

c) Contractor's profit @ 0.1 on (a+b) 19.63

Rate per1000 Nos = a+b+c 215.91

say 216.00

2.4 (vii) Scraping of Stone from Dismantled Stone Masonry

Unit = cum

Taking output = 1 cum

A In cement and lime mortar

a) Labour

Mate day 0.060 151.44 9.09 L-12

Mazdoor day 1.400 136.69 191.37 L-13

b) Overhead charges @ 0.1 on (a) 20.05

c) Contractor's profit @ 0.1 on (a+b) 22.05

Rate per cum = a+b+c 242.55

say 243.00

2.4 (vii) B In Mud mortar

Add 2.5 per cent of cost of labour for gas cutting, ropes, pulleys etc.

Scraping of Bricks Dismantled from Brick Work including Stacking.

Page 59: Standard Data Book - Rate Analysis

Page 8 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

a) Labour

Mate day 0.010 151.44 1.51 L-12

Mazdoor day 0.300 136.69 41.01 L-13

b) Overhead charges @ 0.1 on (a) 4.25

c) Contractor's profit @ 0.1 on (a+b) 4.68

Rate per cum = a+b+c 51.45

say 51.00

2.4 (viii)

Unit = sqm

Taking output = 100 sqm

a) Labour

Mate day 0.160 151.44 24.23 L-12

Mazdoor for scarping and loading day 4.000 136.69 546.76 L-13

b) Machinery

Tractor-trolley hour 0.320 282.50 90.40 P&M-053

c) Overhead charges @ 0.1 on (a+b) 66.14

d) Contractor's profit @ 0.1 on (a+b+c) 72.75

Cost for 100 sqm = a+b+c+d 800.28

Rate per sqm = (a+b+c+d)/100 8.00

say 8.00

2.4 (ix)

Unit = metre

Taking output = 1 metre

A Up to 600 mm dia

a) Labour

Mate day 0.020 151.44 3.03 L-12

Mazdoor day 0.520 136.69 71.08 L-13

b) Overhead charges @ 0.1 on (a) 7.41

c) Contractor's profit @ 0.1 on (a+b) 8.15

Rate per metre = a+b+c 89.67

say 90.00

2.4 (ix) B Above 600 mm to 900 mm dia

a) Labour

Mate day 0.030 151.44 4.54 L-12

Mazdoor day 0.700 136.69 95.68 L-13

b) Overhead charges @ 0.1 on (a) 10.02

c) Contractor's profit @ 0.1 on (a+b) 11.02

Rate per metre = a+b+c 121.27

say 121.00

2.4 (ix) C Above 900 mm

a) Labour

Mate day 0.050 151.44 7.57 L-12

Mazdoor day 1.200 136.69 164.03 L-13

b) Overhead charges @ 0.1 on (a) 17.16

c) Contractor's profit @ 0.1 on (a+b) 18.88

Rate per metre = a+b+c 207.64

say 208.00

Note

2.5 202 Dismantling of Flexible Pavements

Scarping Plaster in Lime or Cement Mortar from Brick/ Stone Masonry

Removing all type of Hume Pipes and Stacking within a lead of 1000 metres including Earthwork and Dismantling of Masonry Works.

1. The excavation of earth, dismantling of stone masonry work in head walls and protection works is not included which is to be measured and paid separately.

2. Credit for retrieved stone from masonry work may be taken as per actual availability.

Dismantling of flexible pavements and disposal of dismantled materials up to a lead of 1000 metres, stacking serviceable and unserviceable materials separately

Page 60: Standard Data Book - Rate Analysis

Page 9 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Unit = cum

Taking output = 1 cum

I By Manual Means

A Bituminous courses

a) Labour

Mate day 0.060 151.44 9.09 L-12

Mazdoor for dismantling, loading and unloading day 1.500 136.69 205.04 L-13

b) Machinery

Tractor-trolley hour 0.380 282.50 107.35 P&M-053

c) Overhead charges @ 0.1 on (a+b) 32.15

d) Contractor's profit @ 0.1 on (a+b+c) 35.36

Rate per cum = a+b+c+d 388.98

say 389.00

2.5 I B Granular courses

a) Labour

Mate day 0.040 151.44 6.06 L-12

Mazdoor for dismantling, loading and unloading. day 1.000 136.69 136.69 L-13

b) Machinery

Tractor-trolley hour 0.330 282.50 93.23 P&M-053

c) Overhead charges @ 0.1 on (a+b) 23.60

d) Contractor's profit @ 0.1 on (a+b+c) 25.96

Rate per cum = a+b+c+d 285.53

say 286.00

2.5 II By Mechanical Means

A Bituminous course

a) Labour

Mate day 0.010 151.44 1.51 L-12

Mazdoor day 0.300 136.69 41.01 L-13

b) Machinery

Tractor-trolley hour 0.380 282.50 107.35 P&M-053

Farm tractor with ripper @ 60 cum per hour hour 0.017 282.50 4.80 P&M-055

c) Overhead charges @ 0.1 on (a+b) 15.47

d) Contractor's profit @ 0.1 on (a+b+c) 17.01

Rate per cum = a+b+c+d 187.16

say 187.00

2.6 202 Dismantling of Cement Concrete Pavement

Unit = cum

Taking output = 1 cum

a) Labour

Mate day 0.030 151.44 4.54 L-12

Semi skilled mazdoor for operating pneumatic tools day 0.500 230.00 115.00 L-14

Mazdoors as helpers including loading and unloading day 0.500 136.69 68.35 L-13

b) Machinery

hour 1.000 319.00 319.00 P&M-001

Tractor-trolley hour 0.400 282.50 113.00 P&M-053

Joint Cutting Machine with 2-3 blades hour 1.000 200.00 200.00 P&M-083

c) Overhead charges @ 0.1 on (a+b) 81.99

d) Contractor's profit @ 0.1 on (a+b+c) 90.19

Rate per cum = a+b+c+d 992.06

say 992.00

Dismantling of cement concrete pavement by mechanical means using pneumatic tools, breaking to pieces not exceeding 0.02 cum in volume and stock piling at designated locations and disposal of dismantled materials up to a lead of 1000 metres, stacking serviceable and unserviceable materials separately

Air compressor 250 cfm with two leads for pneumatic cutters/ hammers @ 1 cum per hour

Page 61: Standard Data Book - Rate Analysis

Page 10 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Note

2.7 202 Dismantling of Guard Rails

Unit = running metre

Taking output = 1 metre

a) Labour

Mate day 0.006 151.44 0.91 L-12

Mazdoor including loading and unloading day 0.150 136.69 20.50 L-13

b) Machinery

Tractor-trolley hour 0.050 282.50 14.13 P&M-053

c) Overhead charges @ 0.1 on (a+b) 3.55

d) Contractor's profit @ 0.1 on (a+b+c) 3.91

Rate per metre = a+b+c+d 43.00

say 43.00

2.8 202 Dismantling of Kerb Stone

Unit = running metre

Taking output = 10 metre

a) Labour

Mate day 0.010 151.44 1.51 L-12

Mazdoor including loading and unloading day 0.150 136.69 20.50 L-13

b) Machinery

Tractor-trolley hour 0.200 282.50 56.50 P&M-053

c) Overhead charges @ 0.1 on (a+b) 7.85

d) Contractor's profit @ 0.1 on (a+b+c) 8.64

Cost for 10 m = a+b+c+d 95.01

Rate per metre = (a+b+c+d)/10 9.50

say 10.00

2.9 202 Dismantling of Kerb Stone Channel

Unit = running metre

Taking output = 10 metre

a) Labour

Mate day 0.015 151.44 2.27 L-12

Mazdoor including loading and unloading day 0.225 136.69 30.76 L-13

b) Machinery

Tractor-trolley hour 0.300 282.50 84.75 P&M-053

c) Overhead charges @ 0.1 on (a+b) 11.78

d) Contractor's profit @ 0.1 on (a+b+c) 12.96

Cost for 10 m = a+b+c+d 142.51

Rate per metre = (a+b+c+d)/10 14.25

say 14.00

2.10 202 Dismantling of Kilometre Stone

Unit = Each

Taking output = one KM stone

A 5th KM stone

The above analysis is for removal of complete pavement. In case full depth repair work is required to be done after dismantling, provision of a concrete cutting and sawing machine may be added for 0.25 hours.

Dismantling guard rails by manual means and disposal of dismantled material with all lifts and up to a lead of 1000 metres, stacking serviceable materials and unserviceable materials separately.

Dismantling kerb stone by manual means and disposal of dismantled material with all lifts and up to a lead of 1000 metre

Dismantling kerb stone channel by manual means and disposal of dismantled material with all lifts and up to a lead of 1000 metre

Dismantling of kilometre stone including cutting of earth, foundation and disposal of dismantled material with all lifts and lead upto 1000 m and back filling of pit.

Page 62: Standard Data Book - Rate Analysis

Page 11 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Quantity of cement concrete = 0.392 cum

a) Labour

Mate day 0.130 151.44 19.69 L-12

Mazdoor day 0.750 136.69 102.52 L-13

b) Machinery

Tractor-trolley hour 0.150 282.50 42.38 P&M-053

c) Overhead charges @ 0.1 on (a+b) 16.46

d) Contractor's profit @ 0.1 on (a+b+c) 18.10

Rate for one 5th KM stone = a+b+c+d 199.14

say 199.00

B Ordinary KM Stone

Quantity of cement concrete = 0.269 cum

a) Labour

Mate day 0.020 151.44 3.03 L-12

Mazdoor day 0.500 136.69 68.35 L-13

b) Machinery

Tractor-trolley hour 0.100 282.50 28.25 P&M-053

c) Overhead charges @ 0.1 on (a+b) 9.96

d) Contractor's profit @ 0.1 on (a+b+c) 10.96

Rate for one ordinary KM stone = a+b+c+d 120.54

say 121.00

C Hectometre Stone

Quantity of cement concrete = 0.048 cum

a) Labour

Mate day 0.004 151.44 0.61 L-12

Mazdoor day 0.100 136.69 13.67 L-13

b) Machinery

Tractor-trolley hour 0.020 282.50 5.65 P&M-053

c) Overhead charges @ 0.1 on (a+b) 1.99

d) Contractor's profit @ 0.1 on (a+b+c) 2.19

Rate for one Hectometre stone = a+b+c+d 24.11

say 24.00

2.11 202 Dismantling of Fencing

Unit = running metre

Taking output = 30 metres

a) Labour

Mate day 0.150 151.44 22.72 L-12

Mazdoor including loading and unloading day 3.000 136.69 410.07 L-13

Blacksmith day 0.750 264.50 198.38 L-02

b) Machinery

Tractor-trolley hour 0.150 282.50 42.38 P&M-053

c) Overhead charges @ 0.1 on (a+b) 67.35

d) Contractor's profit @ 0.1 on (a+b+c) 74.09

Cost for 30 metres = a+b+c+d 814.98

Rate per metre = (a+b+c+d)/30 27.17

say 27.00

2.12 202 Dismantling of CI Water Pipe Line

Dismantling of barbed wire fencing/ wire mesh fencing including posts, foundation concrete, back filling of pit by manual means including disposal of dismantled material with all lifts and up to a lead of 1000 metres, stacking serviceable material and unserviceable material separately.

Dismantling of CI water pipe line 600 mm dia including disposal with all lifts and lead upto 1000 metres and stacking of serviceable material and unserviceable material separately under supervision of concerned department

Page 63: Standard Data Book - Rate Analysis

Page 12 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Unit = running metre

Taking output = 10 metres

a) Labour

Mate day 0.090 151.44 13.63 L-12

Mazdoor day 2.000 136.69 273.38 L-13

Plumber day 0.250 264.50 66.13 L-02

b) Machinery

Truck 10 tonne capacity hour 0.250 315.27 78.82 P&M-057

Light Crane 3 tonne capacity hour 0.500 357.00 178.50 P&M-013

c) Overhead charges @ 0.1 on (a+b) 61.05

d) Contractor's profit @ 0.1 on (a+b+c) 67.15

Cost for 10 metres = a+b+c+d 738.65

Rate per metre = (a+b+c+d)/10 73.86

say 74.00

Note

2.13 202 Removal of Cement Concrete Pipe of Sewer Gutter

Unit = running metre

Taking output = 10 metres

a) Labour

Mate day 0.100 151.44 15.14 L-12

Mazdoor day 2.500 136.69 341.73 L-13

b) Machinery

Crane 5 tonne capacity hour 0.300 116.53 34.96 P&M-070

Truck flat body 10 tonne hour 1.000 315.27 315.27 P&M-057

c) Overhead charges @ 0.1 on (a+b) 70.71

d) Contractor's profit @ 0.1 on (a+b+c) 77.78

Cost for 10 metres = a+b+c+d 855.59

Rate per metre = (a+b+c+d)/10 85.56

say 86.00

Note

2.14 202 Removal of Telephone / Electric Poles and Lines

Unit = each

Taking output = 30 Nos

a) Labour

Mate day 0.480 151.44 72.69 L-12

Mazdoor day 10.000 136.69 1366.90 L-13

Electrician/Lineman day 2.000 264.50 529.00 L-02

b) Machinery

Tractor-trolley hour 1.500 282.50 423.75 P&M-053

c) Overhead charges @ 0.1 on (a+b) 239.23

d) Contractor's profit @ 0.1 on (a+b+c) 263.16

Cost for 30 poles = a+b+c+d 2894.73

Rate per pole = (a+b+c+d)/30 96.49

Add 5% Premium 4.82

The rate analysis does not include any excavation in earth or dismantling of masonry works which are to be measured and paid separately.

Removal of cement concrete pipe of sewer gutter 1500 mm dia under the supervision of concerned department including disposal with all lifts and up to a lead of 1000 metres and stacking of serviceable and unserviceable material separately but excluding earth excavation and dismantling of masonry works.

The rate analysis does not include any excavation in earth or dismantling of masonry works which are to be measured and paid separately.

Removal of telephone / Electric poles including excavation and dismantling of foundation concrete and lines under the supervision of concerned department, disposal with all lifts and up to a lead of 1000 metres and stacking the serviceable and unserviceable material separately

Page 64: Standard Data Book - Rate Analysis

Page 13 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Total = 101.32

say 101.00

Page 65: Standard Data Book - Rate Analysis

Page 1 of 280

CHAPTER - 3EARTH WORK, EROSION CONTROL AND DRAINAGE

Sr No Description Unit Quantity Rate Rs Cost Rs

3.1 301 Excavation in Soil by Manual Means .

Unit = cumTaking output = 120 cuma) Labour

Mate day 1.800 151.44 272.59 L-12Mazdoor day 45.000 136.69 6151.05 L-13

b) MachineryTruck 5.5 cum capacity hour 10.000 315.27 3152.70 P&M-057

c) Overhead charges @ 0.1 on (a+b) 957.63 d) Contractor's profit @ 0.1 on (a+b+c) 1053.40 Cost of 120 cum = a+b+c+d 11587.37 Rate per cum = (a+b+c+d)/120 96.56

say 97.00 Note

3.2 301 Excavation in Ordinary Rock by Manual Means

Unit = cumTaking output = 120 cuma) Labour

Mate day 2.800 151.44 424.03 L-12Mazdoor day 70.000 136.69 9568.30 L-13

b) MachineryTruck 5.5 cum capacity hour 10.000 315.27 3152.70 P&M-057

c) Overhead charges @ 0.1 on (a+b) 1314.50 d) Contractor's profit @ 0.1 on (a+b+c) 1445.95 Cost for 120 cum = a+b+c+d 15905.49 Rate per cum = (a+b+c+d)/120 132.55

say 133.00 Note

3.3 301 Excavation in Soil with Dozer with lead upto 100 metres

Unit = cumTaking output = 180 cuma) Labour

Mate day 0.080 151.44 12.12 L-12Mazdoor day 2.000 136.69 273.38 L-13

b) MachineryDozer, 80 HP @ 30 cum per hour hour 6.000 3720.00 22320.00 P&M-014

c) Overhead charges @ 0.1 on (a+b) 2260.55 d) Contractor's profit @ 0.1 on (a+b+c) 2486.60 Cost for 180 cum = a+b+c+d 27352.65 Rate per cum = (a+b+c+d)/180 151.96

say 152.00

Ref. to MoRTH Spec.

Remarks/ Input ref.

Excavation for roadway in soil using manual means including loading in truck for carrying of cut earth to embankment site with all lifts and lead upto1000 metres.

In case there is a situation where the cross-section is of cut and fill and cut earth is required to be used in embankment in the immediate vicinity, the item of carriage in the truck shall be omitted.

Excavation in ordinary rock using manual means including loading in a truck and carrying of excavated material to embankment site with in all lifts and leads upto 1000 metres

In case there is a situation where the cross-section is of cut and fill and cut earth is required to be used in embankment in the immediate vicinity, the item of carriage in the truck shall be omitted.

Excavation for road way in soil by mechanical means including cutting and pushing the earth to site of embankment upto a distance of 100 metres (average lead50 metres), including trimming bottom and side slopes in accordance with requirements of lines, grades and cross sections.

Page 66: Standard Data Book - Rate Analysis

Page 2 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

3.4 301

Unit = cumTaking output = 108 cuma) Labour

Mate day 0.120 151.44 18.17 L-12Mazdoor day 3.000 136.69 410.07 L-13

b) MachineryDozer, 80 HP @ 20 cum per hour hour 6.000 3720.00 22320.00 P&M-014

c) Overhead charges @ 0.1 on (a+b) 2274.82 d) Contractor's profit @ 0.1 on (a+b+c) 2502.31 Cost for 108 cum = a+b+c+d 27525.37 Rate per cum = (a+b+c+d)/108 254.86

say 255.00 3.5 301

Unit = cum

Taking 0utput = 180 cum

a) Labour

Mate day 0.220 151.44 33.32 L-12

Mazdoor day 3.000 136.69 410.07 L-13

Driller day 2.000 264.50 529.00 L-06

Blaster day 0.250 264.50 66.13 L-03

b) Machinery

Dozer, 80 HP @ 30 cum per hour hour 6.000 3720.00 22320.00 P&M-014

Air compressor, 250 cfm with 2 jack hammer hour 6.000 319.00 1914.00 P&M-001

Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017

Tipper10 tonne capacity hour 11.250 339.00 3813.75 P&M-048

c) Materials

Gelatin 80 per cent kg 63.000 146.00 9198.00 M-104

each 252.000 14.56 3669.12 M-094 /100

cum 90.000 (37.00) (3330.00) M-089

d) Overhead charges @ 0.1 on (a+b+c) 4345.94

e) Contractor's profit @ 0.1 on (a+b+c+d) 4780.53

Cost for 180 cum = a+b+c+d+e 52585.85

Rate per cum = (a+b+c+d+e)/180 292.14

say 292.00

Note

Excavation in Ordinary Rock with Dozer with lead upto 100 metres

Excavation for roadway in ordinary rock by deploying a dozer, 80 HP including cutting and pushing the cut earth to site of embankment upto a distance of 100 metres ( average lead 50 metres ), trimming bottom and side slopes in accordance with the requirements of lines, grades and cross sections.

Excavation in Hard Rock (requiring blasting) with disposal upto 1000 metres

Excavation for roadway in hard rock (requiring blasting) by drilling, blasting and breaking, trimming of bottom and side slopes in accordance with requirements of lines, grades and cross sections, loading and disposal of cut road with in all lifts and leads upto 1000 metres

Electric Detonators @ 1 detonator for 2 gelatin sticks of 125 gms each

Credit for excavated rock found suitable for use @ 50 per cent quantity blasted

1. The quality and availability of rock shall be checked before affording credit.

2. In case some rock is issued to the contractor at site, the item of carriage shall be reduced/restricted to that extent.

Page 67: Standard Data Book - Rate Analysis

Page 3 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

3.6 301

Unit = cum

Taking output = 360 cum

a) Labour

Mate day 0.080 151.44 12.12 L-12

Mazdoor day 2.000 136.69 273.38 L-13

b) Machinery

hour 6.000 1302.00 7812.00 P&M-026

Tipper 5.5 cum capacity, 4 trips per hour. hour 16.000 339.00 5424.00 P&M-048

c) Overhead charges @ 0.1 on (a+b) 1352.15

d) Contractor's profit @ 0.1 on (a+b+c) 1487.36

Cost for 360 cum = a+b+c+d 16361.01

Rate per cum = (a+b+c+d)/360 45.45

say 45.00

3.7 301

Unit = cum

Taking output = 240 cum

a) Labour

Mate day 0.080 151.44 12.12 L-12

Mazdoor day 2.000 136.69 273.38 L-13

b) Machinery

hour 6.000 1302.00 7812.00 P&M-026

Tipper 5.5 cum capacity, 4 trips per hour. hour 11.000 339.00 3729.00 P&M-048

c) Overhead charges @ 0.1 on (a+b) 1182.65

d) Contractor's profit @ 0.1 on (a+b+c) 1300.91

Cost for 240 cum = a+b+c+d 14310.06

Rate per cum = (a+b+c+d)/240 59.63

say 60.00

3.8 301 Excavation in Hard Rock (blasting prohibited)

A Mechanised

Unit = cum

Taking output = 36 cum

a) Labour

Mate day 0.400 151.44 60.58 L-12

day 10.000 136.69 1366.90 L-13

b) Machinery

hour 6.000 1302.00 7812.00 P&M-026

Tipper 5.5 cum capacity, 1 trip per hour. hour 6.500 339.00 2203.50 P&M-048

cum 18.000 (37.00) (666.00) M-089

c) Overhead charges @ 0.1 on (a+b) 1077.70

d) Contractor's profit @ 0.1 on (a+b+c) 1185.47

Cost for 36 cum = a+b+c+d 13040.14

Rate per cum = (a+b+c+d)/36 362.23

say 362.00

Note

Excavation in Soil using Hydraulic Excavator CK 90 and Tippers with Disposal upto 1000 metres.

Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m

Hydraulic excavator 0.9 cum bucket capacity @ 60 cum per hour

Excavation in Ordinary Rock using Hydraulic Excavator CK-90 and Tippers with Disposal upto 1000 metres.

Excavation for roadway in ordinary rock with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, transporting to embankment site within all lifts and lead upto 1000 m, trimming bottom and side slopes in accordance with requirements of lines, grades and cross sections.

Hydraulic Excavator 0.90 cum bucket capacity @ 36 cum per hour

Excavation for roadway in hard rock (blasting prohibited) with rock breakers including breaking rock, loading in tippers and disposal within all lifts and lead upto 1000 metres, trimming bottom and side slopes in accordance with requirements of lines, grades and cross sections.

Mazdoor for trimming slopes including mannul loading in truck

Hydraulic excavator with rock breaker attachment @ 6 cum per hour

Credit for excavated rock found suitable for use @ 50 per cent of excavated quantity

1. The quality and availability of rock shall be checked before affording credit.

2. In case some rock is issued to the contractor at site, the item of carriage shall be restricted/reduced to that extent.

3.Being small quantity, manual loading will be economical in this case and has been provided accordingly.

Page 68: Standard Data Book - Rate Analysis

Page 4 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

3.8 B Manual Method

Unit = cum

Taking output = 16 cum

a) Labour

Mate day 1.640 151.44 248.36 L-12

Mazdoor including loading in truck day 16.000 136.69 2187.04 L-13

Chiseller day 24.000 264.50 6348.00 L-05

Blacksmith day 1.000 264.50 264.50 L-02

b) Machinery

Tipper 5.5 cum capacity, 1 trip per hour. hour 2.900 339.00 983.10 P&M-048

cum 8.000 (37.00) (296.00) M-089

c) Overhead charges @ 0.1 on (a+b) 973.50

d) Contractor's profit @ 0.1 on (a+b+c) 1070.85

Cost for 16 cum = a+b+c+d 11779.35

Rate per cum = (a+b+c+d)/16 736.21

say 736.00

Note 1. Credit is considered for 50 per cent of quantity of work.

3.9 301

Unit = cum

Taking output = 180 cum

a) Labour

Mate day 0.220 151.44 33.32 L-12

Mazdoor day 3.000 136.69 410.07 L-13

Driller day 2.000 264.50 529.00 L-06

Blaster day 0.500 264.50 132.25 L-03

b) Machinery

Dozer 80 HP @ 30 cum per hour hour 6.000 3720.00 22320.00 P&M-014

Air compressor, 250 cfm with 2 jack hammers hour 6.000 319.00 1914.00 P&M-001

Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017

Tipper 5.5 cum capacity, 4 trips per hour. hour 8.200 339.00 2779.80 P&M-048

c) Materials

Gelatin 80 per cent kg 63.000 146.00 9198.00 M-104

each 1008.000 14.56 14676.48 M-094 /100

cum 90.000 (37.00) (3330.00) M-089

2841.45

d) Overhead charges @ 0.1 on (a+b+c) 5634.04

e) Contractor's profit @ 0.1 on (a+b+c+d) 6197.44

Cost for 180 cum = a+b+c+d+e 68171.84

Rate per cum = (a+b+c+d+e)/180 378.73

say 379.00

Note

3.10 301 Excavation in Marshy Soil

Unit = cum

Taking output = 300 cum

a) Labour

Mate day 0.080 151.44 12.12 L-12

Mazdoor day 2.000 136.69 273.38 L-13

b) Machinery

hour 6.000 1302.00 7812.00 P&M-026

Tipper 5.5 cum capacity, 4 trips per hour. hour 13.640 339.00 4623.96 P&M-048

c) Overhead charges @ 0.1 on (a+b) 1272.15

d) Contractor's profit @ 0.1 on (a+b+c) 1399.36

Cost for 300 cum = a+b+c+d 15392.96

Rate per cum = (a+b+c+d)/300 51.31

say 51.00

Credit for excavated rock found suitable for use @ 50 per cent of excavated

2. Loading for disposal will be done manually, being small quantity.

3. In case some rock is issued to contractor at site, the item of carriage shall be omitted to the extent of quantity issued to the contractor.

Excavation in Hard Rock (controlled blasting) with disposal upto 1000 metres

Excavation for roadway in hard rock with controlled blasting by drilling, blasting and breaking, trimming of bottom and side slopes in accordance with requirements of lines, grades and cross sections, loading and disposal of cut road with in all lifts and leads upto 1000 metres

Electric Detonators @ 1 detonator for1/2 gelatin stick of 125 gms each

Credit for excavated rock found suitable for use @ 50 per cent quantity blasted

Add 5 per cent of cost of a+b+c towards muffling arrangements to guard against any rock fly off during blasting

1. Credit is considered for 50 per cent of quantity of blastered rock, if found suitable for construction..

2. In case some rock is issued to the contractor at site, the item of carriage shall be reduced to that extent.

Excavation for roadway in marshy soil with hydraulic excavator 0.9 cum bucket capacity including cutting and loading in tippers and disposal with in all lifts and lead upto 1000 metres, trimming of bottom and side slopes in accordance with requirements of lines, grades and cross sections.

Hydraulic excavator 0.90 cum bucket capacity @ 50 cum per hour

Page 69: Standard Data Book - Rate Analysis

Page 5 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

3.11 301

Unit = cum

Taking output = 360 cum

a) Labour

Mate day 0.080 151.44 12.12 L-12

Mazdoor day 2.000 136.69 273.38 L-13

b) Machinery

Excavator0.90 cum bucket capacity @ 60 cum per hour hour 6.000 1302.00 7812.00 P&M-026

Tipper 5.5 cum capacity, 4 trips per hour. hour 16.360 339.00 5546.04 P&M-048

c) Overhead charges @ 0.1 on (a+b) 1364.35

d) Contractor's profit @ 0.1 on (a+b+c) 1500.79

Cost for 360 cum = a+b+c+d 16508.68

Rate per cum = (a+b+c+d)/360 45.86

say 46.00

Note

3.12 303 Presplitting of Rock Excavation Slopes

Unit = sqm

a) Labour

Mate day 0.600 151.44 90.86 L-12

Mazdoor day 15.000 136.69 2050.35 L-13

b) Machinery

hour 6.000 319.00 1914.00 P&M-001

Dozer, 80 HP hour 6.000 3720.00 22320.00 P&M-014

Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017

c) Materials

Gelatin 80 per cent kg 42.000 146.00 6132.00 M-104

each 672.000 14.56 9784.32 M-094 /100

d) Overhead charges @ 0.1 on (a+b+c) 4712.75

e) Contractor's profit @ 0.1 on (a+b+c+d) 5184.03

Cost for 400 sqm = a+b+c+d+e 57024.32

Rate per sqm = (a+b+c+d+e)/400 142.56

say 143.00

Note

3.13 304 Excavation for Structures

(i) Ordinary soil

Unit = cum

Taking output = 10 cum

A Manual Means (Depth upto 3 m)

a) Labour

Mate day 0.320 151.44 48.46 L-12

Mazdoor day 8.000 136.69 1093.52 L-13

b) Overhead charges @ 0.1 on (a) 114.20

c) Contractor's profit @ 0.1 on (a+b) 125.62

Cost for 10 cum = a+b+c 1381.80

Rate per cum = (a+b+c)/10 138.18

say 138.00

Note

3.13 (i) B Mechanical Means (Depth upto 3 m)

Unit = cum

Taking output = 300 cum

a) Labour

Mate day 0.320 151.44 48.46 L-12

Removal of Unserviceable Soil with Disposal upto 1000 metres

Removal of unserviceable soil including excavation, loading and disposal upto 1000 metres lead but excluding replacement by suitable soil which shall be paid separately as per clause 305.

This item does not include replacement of unsuitable soil by suitable soil. Replacement, where required, is to be provided and paid separately under clause 305.

Carrying out excavation in hard rock to achieve a specified slope of the rock face by controlled use of explosives and blasting accessories in properly aligned and spaced drill holes, collection of the excavated rock by a 80 HP dozer, loading in tipper by a front end loader and disposing of the material with all lifts and lead upto 1000 m, all as specified in clause No. 303

Taking output = 400 sqm( 120 cum considering 300mm average depth of excavation over the existing rock face)

Air compressor 250 cfm with 2 leads @ 20 cum per hour

Electric Detonators @ 1 detonator for 1/2 gelatin stick of 125 gms each

In case blasted rock is used to the contractor against payment for constructed work, the cost of carriage shall be reduced to that extent.

Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent required and utilising the remaining earth locally for road work.

Cost of dewatering may be added where required upto 10 per cent of labour cost Assessment for dewatering shall be made as per site conditions..

Page 70: Standard Data Book - Rate Analysis

Page 6 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Mazdoor day 8.000 136.69 1093.52 L-13

b) Machinery

Hydraulic excavator 1.0 cum bucket capacity hour 6.000 1302.00 7812.00 P&M-026

c) Overhead charges @ 0.1 on (a+b) 895.40

d) Contractor's profit @ 0.1 on (a+b+c) 984.94

Cost for 300 cum = a+b+c+d 10834.32

Rate per cum = (a+b+c+d)/300 36.11

say 36.00

Note

3.13 (ii) Ordinary Rock (not requiring blasting)

A Manual Means (Depth upto 3 m)

Unit = cum

Taking output = 10 cum

a) Labour

Mate day 0.400 151.44 60.58 L-12

Mazdoor day 10.000 136.69 1366.90 L-13

b) Overhead charges @ 0.1 on (a) 142.75

c) Contractor's profit @ 0.1 on (a+b) 157.02

Cost for 10 cum = a+b+c 1727.25

Rate per cum = (a+b+c)/10 172.72

say 173.00

Note

3.13 (ii) B Mechanical Means

Unit = cum

Taking output = 216 cum

a) Labour

Mate day 0.240 151.44 36.35 L-12

Mazdoor day 6.000 136.69 820.14 L-13

b) Machinery

Hydraulic excavator 1.0 cum bucket capacity hour 6.000 1302.00 7812.00 P&M-026

c) Overhead charges @ 0.1 on (a+b) 866.85

d) Contractor's profit @ 0.1 on (a+b+c) 953.53

Cost for 216 cum = a+b+c+d 10488.87

Rate per cum = (a+b+c+d)/216 48.56

say 49.00

Note

3.13 (iii) Hard Rock ( requiring blasting )

A Manual Means

Unit = cum

Taking output = 10 cum

a) Labour

i) Mate day 0.530 151.44 80.26 L-12

ii) Driller day 0.840 264.50 222.18 L-06

iii) Blaster day 0.400 264.50 105.80 L-03

iv) Mazdoor day 12.000 136.69 1640.28 L-13

b) Machinery

hour 0.667 319.00 212.67 P&M-001

c) Material

Blasting Material kg 3.500 146.00 511.00 M-104

Detonator electric each 14.000 14.56 203.84 M-094 /100

d) Overhead charges @ 0.1 on (a+b+c) 297.60

e) Contractor's profit @ 0.1 on (a+b+c+d) 327.36

Cost for 10 cum = a+b+c+d+e 3601.00

Rate per cum = (a+b+c+d+e)/10 360.10

say 360.00

Note

3.13 (iv) Hard Rock ( blasting prohibited )

Unit = cum

Taking output = 10 cum

A Mechanical Means

a) Labour

Mate day 0.200 151.44 30.29 L-12

Mazdoor day 5.000 136.69 683.45 L-13

b) Machinery

hour 10.000 319.00 3190.00 P&M-001

Cost of dewatering upto 5 per cent of (a+b) may be added, where required. Assessment for dewatering shall be made as per site conditions..

Cost of dewatering upto 10 per cent of labour cost may be added, where required. Assessment for dewatering shall be made as per site conditions..

1.Cost of dewatering upto 5 per cent of (a+b), may be added, where required Assessment for dewatering shall be made as per site conditions.

2.In case of rock, foundation beyond3 m is not dug and hence not included.

Air Compressor 250 cfm with 2 jack hammer @ 15 cum per hour

Cost of dewatering @ 10 per cent of labour cost may be added, where required Assessment for dewatering shall be made as per site conditions.

Air Compressor 250 cfm with 2 leads of pneumatic breaker @ 1 cum per hour

Page 71: Standard Data Book - Rate Analysis

Page 7 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

c) Overhead charges @ 0.1 on (a+b) 390.37

d) Contractor's profit @ 0.1 on (a+b+c) 429.41

Cost for 10 cum = a+b+c+d 4723.52

Rate per cum = (a+b+c+d)/10 472.35

say 472.00

Note

3.13 (v) Marshy soil

Unit = cum

Taking output = 10 cum

A Manual means ( upto 3 m depth)

a) Labour

Mate/Supervisor day 0.400 151.44 60.58 L-12

Mazdoor day 10.000 136.69 1366.90 L-13

b) Machinery

Tractor-trolley hour 2.670 282.50 754.28 P&M-053

c) Material

Selected earth for refilling cum 5.000 43.00 215.00 M-163

d) Overhead charges @ 0.1 on (a+b+c) 239.68

e) Contractor's profit @ 0.1 on (a+b+c+d) 263.64

Cost for 10 cum = a+b+c+d+e 2900.07

Rate per cum = ( a+b+c+d+e)/ 10 290.01

say 290.00

Note

3.13 (v) B Mechanical Means

a) Labour

i) Mate day 0.080 151.44 12.12 L-12

ii) Mazdoor for dressing sides, bottom and backfilling day 2.000 136.69 273.38 L-13

b) Machinery

hour 0.170 1302.00 221.34 P&M-026

Tipper 5.5 cum capacity, 4 trips per hour. hour 0.450 339.00 152.55 P&M-048

c) Material

Selected earth for refilling cum 5.000 43.00 215.00 M-163

d) Overhead charges @ 0.1 on (a+b+c) 87.44

e) Contractor's profit @ 0.1 on (a+b+c+d) 96.18

Cost for 10 cum = a+b+c+d+e 1058.01

Rate per cum = (a+b+c+d+e)/10 105.80

say 106.00

Note

3.14 305.4.3

Unit = sqm

Taking output = 100 sqm

a) Labour

Mate day 0.200 151.44 30.29 L-12

Mazdoor including loading and unloading day 5.000 136.69 683.45 L-13

b) Machinery

Tractor-trolley hour 1.670 282.50 471.78 P&M-053

d) Overhead charges @ 0.1 on (a+b+c) 118.55

e) Contractor's profit @ 0.1 on (a+b+c+d) 130.41

Cost for 100 sqm = a+b+c+d 1434.47

Rate per sqm = (a+b+c+d)/100 14.34

say 14.00

Note

3.15 305.4.3

Unit = sqm

1. Cost of dewatering upto 5 per cent of (a+b), may be added, where required Assessment for dewatering shall be made as per site conditions.

2.In case of rock, foundation beyond 3 m is not dug and hence not included.

1. Cost of dewatering @ 30 per cent of (a), may be added, where required Assessment for dewatering shall be made as per site conditions.

2. Shoring & strutting 20 per cent of (a), where required may be added

3. It is assumed that Marshy Soil will be available upto 3 m depth only. For deeper excavation below 3 m depth, refer analysis in item (i) to (iv) for ordinary soil

Hydraulic excavator 1.0 cum bucket capacity @ 60 cum per hour

1. Cost of dewatering @ 20 per cent of (a+b) may be added, where required

2. Shoring & strutting @ 10 per cent of (a+b), where required may be added

3. It is assumed that Marshy Soil will be available upto 3 m depth only. For deeper excavation below 3 m depth, refer analysis in item (i) to (iv) for ordinary soil

Scarifying Existing Granular Surface to a Depth of 50 mm by Manual Means

Scarifying the existing granular road surface to a depth of 50 mm and disposal of scarified material within all lifts and leads upto 1000 metres.

In case material is to be reused at site, transportation cost catered above for disposal shall be deleted.

Scarifying Existing Bituminous Surface to a depth of 50 mm by Mechanical Means

Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of scarified material with in all lifts and lead upto 1000 metres.

Page 72: Standard Data Book - Rate Analysis

Page 8 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Taking output = 100 sqm

a) Labour

Mate day 0.010 151.44 1.51 L-12

Mazdoor day 0.250 136.69 34.17 L-13

b) Machinery

Tractor with ripper attachment @ 60 cum per hour hour 0.080 282.50 22.60 P&M-055

hour 0.200 806.00 161.20 P&M-017

Tipper 5.5 cum capacity, 4 trips per hour. hour 0.230 339.00 77.97 P&M-048

c) Overhead charges @ 0.1 on (a+b) 29.75

d) Contractor's profit @ 0.1 on (a+b+c) 32.72

Cost for 100 sqm = a+b+c+d 359.92

Rate per sqm = (a+b+c+d)/100 3.60

say 4.00

3.16 305

Unit = cum

Taking output = 100 cum

a) Labour

Mate day 0.040 151.44 6.06 L-12

Mazdoor day 1.000 136.69 136.69 L-13

b) Machinery

hour 1.670 1302.00 2174.34 P&M-026

Tipper 10 tonne capacity tonne.km 160 x L 2.46 7864.80

786.48

Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 3720.00 1860.00 P&M-014

Motor grader for grading @ 100 cum per hour hour 1.000 2395.00 2395.00 P&M-032

Water tanker6 KL capacity hour 4.000 200.00 800.00 P&M-060

Vibratory roller 8 -10 tonnes @ 100 cum per hour hour 1.000 1541.00 1541.00 P&M-059

c) Material

Cost of water KL 24.000 10.00 240.00 M-189

Compensation for earth taken from private land cum 100.000 28.00 2800.00 M-092

d) Overhead charges @ 0.1 on (a+b+c) 2060.44

e) Contractor's profit @ 0.1 on (a+b+c+d) 2266.48

Cost for 100 cum = a+b+c+d+e 24931.28

Rate per cum = (a+b+c+d+e)/100 249.31

say 249.00

Note

3.17 305

Unit = cum

Taking output = 100 cum

a) Labour

Mate day 0.020 151.44 3.03 L-12

Mazdoor day 0.500 136.69 68.35 L-13

b) Machinery

Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 3720.00 1860.00 P&M-014

Motor grader for grading @ 100 cum per hour hour 1.000 2395.00 2395.00 P&M-032

Water tanker6 KL capacity hour 4.000 200.00 800.00 P&M-060

Vibratory roller 8-10 tonnes @ 100 cum per hour hour 1.000 1541.00 1541.00 P&M-059

c) Material

Cost of water KL 24.000 10.00 240.00 M-189

d) Overhead charges @ 0.1 on (a+b+c) 690.74

e) Contractor's profit @ 0.1 on (a+b+c+d) 759.81

Rate for 100 cum = a+b+c+d+e 8357.92

Rate per cum = (a+b+c+d+e)/100 83.58

say 84.00

Note

3.18 305 Construction of Subgrade and Earthen Shoulders

Front end loader 1 cum bucket capacity @ 25 cum per hour

Construction of Embankment with Material obtained from Borrowpits

Construction of embankment with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2.

Hydraulic Excavator1 cum bucket capacity @ 60 cum per hour

Lead =20 km & P&M-

058

Add 10 per cent of cost of carriage to cover cost of loading and unloading

Compensation for earth will vary from place to place and will have to be assessed realistically as per particular ground situation. In case earth is available from Govt. land, compensation for earth will not be required. The position is required to be clearly stated in the cost estimate.

Construction of Embankment with Material Deposited from Roadway Cutting

Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of table 300-2.

In case the earth cutting is done by dozer and pushed for filling in the embankment, the input of dozer in the cost of embankment shall be deleted as the same is already provided in the cost of excavation. However, if the earth is dumped by tippers from roadway cutting, the input of dozer for spreading is required to be provided.

Page 73: Standard Data Book - Rate Analysis

Page 9 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Unit = cum

Taking output = 100 cum

a) Labour

Mate day 0.040 151.44 6.06 L-12

Mazdoor day 1.000 136.69 136.69 L-13

b) Machinery

hour 1.670 1302.00 2174.34 P&M-026

Tipper 10 tonne capacity tonne.km 175xL 2.46 8602.13

860.21

Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 3720.00 1860.00 P&M-014

Motor grader for grading @ 50 cum per hour hour 2.000 2395.00 4790.00 P&M-032

Water tanker with 6 km lead hour 4.000 200.00 800.00 P&M-060

Vibratory roller 8-10 tonnes @ 80 cum per hour hour 1.250 1541.00 1926.25 P&M-059

c) Material

Cost of water KL 24.000 10.00 240.00 M-189

Compensation for earth taken from private land cum 100.000 28.00 2800.00 M-092

d) Overhead charges @ 0.1 on (a+b+c) 2419.57

e) Contractor's profit @ 0.1 on (a+b+c+d) 2661.52

Cost for 100 cum = a+b+c+d+e 29276.77

Rate per cum = (a+b+c+d+e)/100 292.77

say 293.00

3.19 305.3.4 Compacting Original Ground

Case-I Compacting original ground supporting sub-grade

Unit = cum

Taking output = 600 cum

a) Labour

Mate day 0.120 151.44 18.17 L-12

Mazdoor day 3.000 136.69 410.07 L-13

b) Machinery

Tractor with ripper attachment hour 9.000 282.50 2542.50 P&M-055

Motor grader for grading hour 6.000 2395.00 14370.00 P&M-032

Water tanker 6 KL capacity hour 4.000 200.00 800.00 P&M-060

Vibratory roller 8-10 tonne @ 80 cum/hour hour 7.500 1541.00 11557.50 P&M-059

c) Material

Cost of water KL 24.000 10.00 240.00 M-189

d) Overhead charges @ 0.1 on (a+b+c) 2993.82

e) Contractor's profit @ 0.1 on (a+b+c+d) 3293.21

Cost for 600 cum = a+b+c+d+e 36225.27

Rate per cum = (a+b+c+d+e)/600 60.38

say 60.00

3.19 Case-II :Compacting original ground supporting embankment

Unit = cum

Taking output = 600 cum

a) Labour

Mate day 0.080 151.44 12.12 L-12

Mazdoor day 2.000 136.69 273.38 L-13

b) Machinery

Tractor with ripper attachment hour 6.000 282.50 1695.00 P&M-055

Vibratory road roller 8-10 tonne capacity hour 7.500 1541.00 11557.50 P&M-059

Water tanker6 KL capacity hour 4.000 200.00 800.00 P&M-060

c) Material

Cost of water KL 24.000 10.00 240.00 M-189

d) Overhead charges @ 0.1 on (a+b+c) 1457.80

e) Contractor's profit @ 0.1 on (a+b+c+d) 1603.58

Cost for 600 cum = (a+b+c+d+e) 17639.37

Rate per sqm = (a+b+c+d+e)/600 29.40

say 29.00

3.20 305 Stripping and Storing Top Soil

Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2

Hydraulic excavator1 cum bucket capacity @ 60 cum per hour

Lead =20 km & P&M-

058

Add 10 per cent of cost of carriage to cover cost of loading and unloading

Loosening of the ground upto a level of 500 mm below the sub-grade level, watered, graded and compacted in layers to meet requirement of table 300-2 for sub-grade construction.

Loosening, leveling and Compacting original ground supporting embankment to facilitate placement of first layer of embankment, scarified to a depth of 150 mm, mixed with water at OMC and then compacted by rolling so as to achieve minimum dry density as given in Table 300-2 for embankment construction.

Page 74: Standard Data Book - Rate Analysis

Page 10 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Unit = cum

Taking output = 10 cum

a) Labour

Mate day 0.200 151.44 30.29 L-12

Mazdoor day 5.000 136.69 683.45 L-13

b) Machinery

Dozer 80 HP @ 100 cum per hour hour 0.100 3720.00 372.00 P&M-014

c) Overhead charges @ 0.1 on (a+b) 108.57

d) Contractor's profit @ 0.1 on (a+b+c) 119.43

Cost for 10 cum = (a+b+c+d) 1313.74

Rate per cum = (a+b+c+d)/10 131.37

say 131.00

3.21

Unit = cum

Taking output = 300 cum

a) Labour

Mate day 0.080 151.44 12.12 L-12

Mazdoor day 2.000 136.69 273.38 L-13

b) Machinery

Dozer, 80 HP hour 6.000 3720.00 22320.00 P&M-014

c) Overhead charges @ 0.1 on (a+b) 2260.55

d) Contractor's profit @ 0.1 on (a+b+c) 2486.60

Cost for 300 cum = (a+b+c+d) 27352.65

Rate per cum = (a+b+c+d)/300 91.18

say 91.00

3.22 307 Turfing with Sods

Unit = sqm

Taking output = 100 sqm

a) Labour

Mate day 0.120 151.44 18.17 L-12

Mazdoor for preparation of ground and fetching of sods day 3.000 136.69 410.07 L-13

b) Machinery

Water tanker including watering for 3 months hour 2.000 200.00 400.00 P&M-060

Tractor-trolley hour 1.000 282.50 282.50 P&M-053

c) Material

cum 0.180 364.00 65.52 M-167

Cost of water KL 12.000 10.00 120.00 M-189

d) Overhead charges @ 0.1 on (a+b+c) 129.63

e) Contractor's profit @ 0.1 on (a+b+c+d) 142.59

Cost for 100 sqm = a+b+c+d+e 1568.48

Rate per 100 sqm = (a+b+c+d+e)/100 15.68

say 16.00

3.23 308 Seeding and Mulching

Unit = sqm

Taking output = 240 sqm

a) Labour

Mate day 0.400 151.44 60.58 L-12

Mazdoor day 10.000 136.69 1366.90 L-13

b) Machinery

hour 14.000 200.00 2800.00 P&M-060

Tractor-trolley hour 2.400 282.50 678.00 P&M-053

c) Material

Seeds kg 3.600 243.00 874.80 M-162

Sludge/Farm yard manure @ 0.18 cum per 100 sqm cum 0.430 364.00 156.52 M-167

Bitumen Emulsion litre 55.200 49.92 2755.31 M-077

Jute netting, open weave, 2.5 cm square opening sqm 264.000 61.00 16104.00 M-121

Cost of water for 3 months KL 84.000 10.00 840.00 M-189

Stripping, storing of top soil by road side at 15 m internal and re-application on embankment slopes, cut slopes and other areas in localities where the available embankment material is not conducive to plant growth.

Stripping, Storing and Re-laying Top Soil from Borrow Areas in Agriculture Fields.

Stripping of top soil from borrow areas located in agriculture fields, storing at a suitable place, spreading and re-laying after taking the borrow earth to maintain fertility of the agricultural field, finishing it to the required levels and satisfaction of the farmer.

Furnishing and laying of the live sods of perennial turf forming grass on embankment slope, verges or other locations shown on the drawing or as directed by the engineer including preparation of ground, fetching of sods and watering.

Farm yard manure @ 0.18 cum per 100 sqm at site of work

Preparation of seed bed on previously laid top soil, furnishing and placing of seeds, fertilizer, mulching material, applying bituminous emulsion at the rate of 0.23 litres per sqm and laying and fixing jute netting, including watering for 3 months all as per clause 308.

Water tanker 6 KL capacity including watering for 3 months

Page 75: Standard Data Book - Rate Analysis

Page 11 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

d) Overhead charges @ 0.1 on (a+b+c) 2563.61

e) Contractor's profit @ 0.1 on (a+b+c+d) 2819.97

Cost for 240 sqm = a+b+c+d+e 31019.69

Rate per sqm = (a+b+c+d+e)/240 129.25

say 129.00

3.24 309 Surface Drains in Soil

Unit = metre

Taking output = 10 metres

A Mechanical means

a) Labour

Mate day 0.010 151.44 1.51 L-12

Mazdoor for dressing of bed and side of drain day 0.250 136.69 34.17 L-13

b) Machinery

hour 0.330 1302.00 429.66 P&M-026

c) Overhead charges @ 0.1 on (a+b) 46.53

d) Contractor's profit @ 0.1 on (a+b+c) 51.19

Cost for 10 metres = a+b+c+d 563.07

Rate per metre = (a+b+c+d)/10 56.31

say 56.00

3.24 B Manual Means

a) Labour

Mate day 0.080 151.44 12.12 L-12

Mazdoor day 2.000 136.69 273.38 L-13

b) Overhead charges @ 0.1 on (a) 28.55

c) Contractor's profit @ 0.1 on (a+b) 31.40

Cost for 10 metres = a+b+c 345.45

Rate per metre = (a+b+c)/10 34.54

say 35.00

Note

3.25 309 Surface Drains in Ordinary Rock

Unit = metre

Taking output = 10 metres

A Mechanical Means

a) Labour

Mate day 0.020 151.44 3.03 L-12

Mazdoor for dressing of bed and side of drain day 0.500 136.69 68.35 L-13

b) Machinery

hour 0.670 1302.00 872.34 P&M-026

c) Overhead charges @ 0.1 on (a+b) 94.37

d) Contractor's profit @ 0.1 on (a+b+c) 103.81

Cost for 10 metres = a+b+c+d 1141.89

Rate per metre = (a+b+c+d)/10 114.19

say 114.00

3.25 B Manual Means

a) Labour

Mate day 0.120 151.44 18.17 L-12

Mazdoor day 3.000 136.69 410.07 L-13

b) Overhead charges @ 0.1 on (a) 42.82

c) Contractor's profit @ 0.1 on (a+b) 47.11

Cost for 10 metres = a+b+c 518.17

Rate per metre = (a+b+c)/10 51.82

say 52.00

3.26 309 Surface Drains in Hard Rock

3.27 309 Sub-Surface Drains with Perforated Pipe

Construction of unlined surface drains of average cross sectional area 0.40 sqm in soil to specified lines, grades, levels and dimensions to the requirement of clause 301 and 309. Excavated material to be used in embankment within a lead of 50 metres (average lead 25 metres)

Hydraulic Excavator 0.3 cum bucket capacity @ 30 metres per hour

Where lining of drain is provided, quantity shall be worked out based on approved design and drawing and priced on rate of cement concrete of approved grade or stone/brick masonry as the case may be.

Construction of unlined surface drain of average cross sectional area 0.4 sqm in ordinary rock to specified lines, grades, levels and dimensions as per approved design and to the requirement of clause 301 to 309. Excavated material to be used in embankment at site.

Hydraulic Excavator 0.3 cum bucket capacity @ 15 metres per hour

Rate per metre may be worked out based on quantity of hard rock as per design.

For rate of hard rock cutting, refer relevant item in this chapter

Page 76: Standard Data Book - Rate Analysis

Page 12 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Unit = metre

Taking output = 10 metres

a) Labour

Mate day 0.040 151.44 6.06 L-12

Mazdoor for excavation and back filling day 2.000 136.69 273.38 L-13

c) Material

metre 10.000 243.00 2430.00 M-135

Crushed stone as per table 300-3 cum 2.400 894.00 2145.60 M-012

d) Overhead charges @ 0.1 on (a+b+c) 485.50

e) Contractor's profit @ 0.1 on (a+b+c+d) 534.05

Cost for 10 metres = a+b+c+d+e 5874.60

Rate per metre = (a+b+c+d+e)/10 587.46

say 587.00

Note

3.28 309 Aggregate Sub-Surface Drains

Unit = metre

Taking output = 10 metres

a) Labour

Mate day 0.020 151.44 3.03 L-12

Mazdoor for excavation and back filling with aggregates day 1.500 136.69 205.04 L-13

b) Material

Crushed stone as per table 300-3 cum 1.350 894.00 1206.90 M-012

c) Overhead charges @ 0.1 on (a+b) 141.50

d) Contractor's profit @ 0.1 on (a+b+c) 155.65

Cost for 10 metres = a+b+c+d 1712.11

Rate per metre = (a+b+c+d)/10 171.21

say 171.00

3.29 309 Underground Drain at Edge of Pavement

Unit = Running metre

Taking output = one metre

a) Earthwork in soil cum 1.500 36.00 54.00

b) RCC work M-20 cum 0.495 4650.00 2301.75

Rate per metre = (a+b) 2355.75

say 2356.00

3.30 310 Preparation and Surface Treatment of Formation.

Unit = sqm

Taking output = 3500sqm

a) Labour

Mate day 0.280 151.44 42.40 L-12

Mazdoor day 6.000 136.69 820.14 L-13

Mazdoor skilled day 1.000 164.69 164.69 L-15

b) Machinery

Smooth 3 wheeled steel roller 8-10 tonnes hour 3.000 460.00 1380.00 P&M-044

Water tanker 6 KL, one trip per hour hour 3.000 200.00 600.00 P&M-060

c) Material

Cost of water KL 18.000 10.00 180.00 M-189

d) Overhead charges @ 0.1 on (a+b+c) 318.72

e) Contractor's profit @ 0.1 on (a+b+c+d) 350.60

Cost for 3500 sqm = a+b+c+d+e 3856.55

Rate per sqm = (a+b+c+d+e)/3500 1.10

say 1.00

3.31 313 Construction of Rock fill Embankment

Construction of subsurface drain with perforated pipe of 100 mm internal diameter of metal/ asbestos cement/ cement concrete/PVC, closely jointed, perforations ranging from 3 mm to 6 mm depending upon size of material surrounding the pipe, with 150 mm bedding below the pipe and 300 mm cushion above the pipe, cross section of excavation 450 x 550 mm. Excavated material to be utilised in roadway at site.

Perforated pipe of cement concrete, internal dia 100 mm

Type of pipe may be modified depending upon provision in design.

Construction of aggregate sub surface drain 300 mm x 450 mm with aggregates conforming to table 300-4, excavated material to be utilised in roadway.

Construction of an underground drain 1 m x 1 m (inside dimensions) lined with RCC-20 cm thick and covered with RCC slab10 cm in thickness on urban roads.

Item No. 3.13

Item 12.8 (C) RCC

Rates for these items may be taken from chapters on earth work and substructures respectively.

Preparation and surface treatment of formation by removing mud and slurry, watering to the extent needed to maintain the desired moisture content, trimming to the required line, grade, profile and rolling with 8-10 tonne smooth wheeled roller, complete as per clause 310.

Page 77: Standard Data Book - Rate Analysis

Page 13 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Unit = cum

Taking output = 100 cum

a) Labour

Mate day 0.040 151.44 6.06 L-12

Mazdoor day 1.500 136.69 205.04 L-13

b) Machinery

Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 3720.00 1860.00 P&M-014

Vibratory road roller 8-10 tonnes @ 100 cum per hour hour 1.000 1541.00 1541.00 P&M-059

Water tanker 6 KL, one trip per hour hour 2.000 200.00 400.00 P&M-060

c) Material

Cost of water KL 12.000 10.00 120.00 M-189

d) Overhead charges @ 0.1 on (a+b+c) 413.21

e) Contractor's profit @ 0.1 on (a+b+c+d) 454.53

Cost for 100 cum = a+b+c+d+e 4999.83

Rate per cum = (a+b+c+d+e)/100 50.00

say 50.00

Note

EARTH WORK ON HILL ROAD

3.32 301 Excavation in Hill Area in Soil by Mechanical Means

Unit = cum

Taking output = 260 cum

a) Labour

Mate day 0.240 151.44 36.35 L-12

day 6.000 136.69 820.14 L-13

b) Machinery

Dozer 80 HP (D-80 A 12)@ 43.28 cum per hour hour 6.000 3720.00 22320.00 P&M-014

Front end loader hour 6.000 806.00 4836.00 P&M-017

Tipper 5.5cum capacity, 4 trips per hour. hour 12.000 339.00 4068.00 P&M-048

c) Overhead charges @ 0.1 on (a+b) 3208.05

d) Contractor's profit @ 0.1 on (a+b+c) 3528.85

Cost for 260 cum = a+b+c+d 38817.39

Rate per cum = (a+b+c+d)/260 149.30

say 149.00

Note

3.33 301

Unit = cum

Taking output = 170 cum

a) Labour

Mate day 0.320 151.44 48.46 L-12

Mazdoor day 8.000 136.69 1093.52 L-13

b) Machinery

Dozer 80 HP (D-80 A 12)@ 28.32 cum per hour hour 6.000 3720.00 22320.00 P&M-014

Front end loader hour 7.000 806.00 5642.00 P&M-017

Tipper 5.5cum capacity, 4 trips per hour. hour 7.000 339.00 2373.00 P&M-048

c) Overhead charges @ 0.1 on (a+b) 3147.70

d) Contractor's profit @ 0.1 on (a+b+c) 3462.47

Cost for 170 cum = a+b+c+d 38087.15

Rate per cum = (a+b+c+d)/170 224.04

say 224.00

Note

3.34 301

Construction of rock fill embankment with broken hard rock fragments of size not exceeding 300 mm laid in layers not exceeding 500 mm thick including filling of surface voids with stone spalls, blinding top layer with granular material, rolled with vibratory road roller, all complete as per clause 313.

It is assumed that rock is available locally at site from roadway cutting. In case, portion of the rock requires breaking to acceptable size of 300 mm, breaking charges will have to be added.

Excavation in soil in hilly area by mechanical means including cutting and trimming of side slopes and disposing of excavated earth with all lifts and lead upto 1000 metres.

Mazdoor for trimming slopes and helping in excavation etc.

In case the land on the valley side is barren and there is no objection for disposing of excavated earth on the valley side, the provision of front end loader and tipper shall be deleted as excavated earth shall be disposed off on the valley side.

Excavation in Hilly Area in Ordinary Rock by Mechanical Means not Requiring Blasting.

Excavation in hilly area in ordinary rock not requiring blasting by mechanical means including cutting and trimming of slopes and disposal of cut material with all lift and lead upto 1000 metres.

In case the land on the valley side is barren and there is no objection for disposing of excavated earth on the valley side, the provision of front end loader and tipper shall be deleted as excavated earth can be disposed off on the valley side.

Excavation in Hilly Areas in Hard Rock Requiring Blasting

Page 78: Standard Data Book - Rate Analysis

Page 14 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Unit = cum

Taking output = 170 cum

a) Labour

Mate day 0.490 151.44 74.21 L-12

Mazdoor day 10.000 136.69 1366.90 L-13

Driller day 2.000 264.50 529.00 L-06

Blaster day 0.250 264.50 66.13 L-03

b) Machinery

Dozer 80 HP (D-80 A 12)@ 28.32 cum per hour hour 6.000 3720.00 22320.00 P&M-014

hour 5.000 319.00 1595.00 P&M-001

Front end loader hour 7.000 806.00 5642.00 P&M-017

Tipper 5.5cum capacity, 4 trips per hour. hour 7.000 339.00 2373.00 P&M-048

c) Materials

Gelatine 80 per cent kg 35.000 146.00 5110.00 M-104

each 140.000 14.56 2038.40 M-094 /100

d) Overhead charges @ 0.1 on (a+b+c) 4111.46

e) Contractor's profit @ 0.1 on (a+b+c+d) 4522.61

Cost for 170 cum = a+b+c+d+e 49748.70

Rate per cum = (a+b+c+d+e)/170 292.64

say 293.00

Note

3.35 Work in Urban Roads

3.36

Unit = cum

Taking output = 360 cum

a) Labour

Mate day 0.160 151.44 24.23 L-12

Mazdoor day 4.000 136.69 546.76 L-13

b) Machinery

hour 6.000 1302.00 7812.00 P&M-026

Tipper 10Tcapacity flyash 360 x 1.2 = 432 tonnes tonne.km 432 x L 2.46 56272.64

5627.26

Excavation in hilly areas in hard rock requiring blasting, by mechanical means including trimming of slopes and disposal of cut material with all lifts and lead upto 1000 metres.

Air compressor 250 cfm with two jack hammer @ 20 cum per hour

Electric Detonators @ 1 Detonator for 2 Gelatine sticks of 125 gms each

In case the land on the valley side is barren and there is no objection for disposing of excavated earth on the valley side, the provision of front end loader and tipper shall be deleted as excavated earth can be disposed off on the valley side.

In case of hill roads, the altitude effect comes into play. The output of men and machines decreases progressively after 2100 m elevation leading to increase in cost . High altitude effect has been explained in the basic approach.

The cost of earth work in urban roads inhabited area will be comparatively higher due to following reasons:

a) There is mixed traffic on urban roads like slow moving hand and animal driven carts, rickshaws, cycles, two/ three wheeler apart from the usual vehicular traffic resulting into traffic jams. This causes loss of working time which may be in the range of 10 -15 per cent

b) There is considerable disruption of traffic adversely affecting the efficiency of the working parties including machines due to congestion caused by pedestrian traffic, local road side venders, parking of vehicles by the road side, encroachments by the shopkeepers and local shops who make use of the berms of the road in front of these shops and unauthorised conversion of road berms into mini local market The output of manpower and machines is substantially reduced due to factors mentioned above.

c) Cost of living in urban areas is comparatively more resulting into higher wages.

d) At times, work is executed during night time due to heavy traffic during day time. This involves extra expenditure by way of making arrangement for lighting and special transport for working parties due to odd hour

In the light of above, the authorities engaged in preparing the cost estimates may exercise their judgment and cater for the additional cost to the extent of 2 to 3 per cent, keeping in view the severity of factors mentioned above. Supporting details for the extra cost based on the actual conditions in specific cases will have to give in justification.

Suggestive

Embankment Construction with Flyash/Pond ash available from coal or lignite burning Thermal Plants as waste material.

Construction of embankment with Flyash conforming to table 1 of IRC: SP: 58 - 2001 obtained from coal or lignite burning thermal power stations as waste material, spread and compacted in layer of 200mm thickness each at OMC, all as specified in IRC: SP: 58-2001 and as per approved plans.

Hydraulic Excavator 0.9 cum bucket capacity @ 60 cum/hour

Lead =53 km & P&M-

058

Add 10 per cent of cost of carriagefor loading and unloading

Page 79: Standard Data Book - Rate Analysis

Page 15 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Dozer 80 HP for spreading @ 200 cum/hour hour 1.800 3720.00 6696.00 P&M-014

Motor Grader for grading @ 100 cum/hour hour 3.600 2395.00 8622.00 P&M-032

Water tanker6 KL capacity hour 12.000 200.00 2400.00 P&M-060

Vibratory Roller 8-10 tonne @ 100 cum/hour hour 3.600 1541.00 5547.60 P&M-059

c) Overhead charges @ 0.1 on (a+b) 9354.85

d) Contractor's profit @ 0.1 on (a+b+c) 10290.33

Cost for 360 cum = a+b+c+d 113193.68

Rate per cum = (a+b+c+d)/360 314.43

say 314.00

Note 1.As flyash is available free of cost as waste material from Thermal Plants, cost of material has not been added.

2.The earth cover on sides and intermediate layers of earth sandwiching the flyash have not been included in this analysis. The same are required to be provided as per approved design and priced separately as embankment construction.

Page 80: Standard Data Book - Rate Analysis

Page 1 of 280

CHAPTER - 4 SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS

Sr No Description Unit Quantity Rate Rs Cost Rs

4.1 401

A Plant Mix Method

Unit = cumTaking output = 225 cum (450 tonne)a) Labour

Mate day 0.400 151.44 60.58 L-12Mazdoor skilled day 2.000 164.69 329.38 L-15Mazdoor day 8.000 136.69 1093.52 L-13

b) MachineryWet mix plant @ 75 tonne capacity per hour hour 6.000 2195.03 13170.15 P&M-093Electric generator 125 KVA hour 6.000 652.00 3912.00 P&M-018

hour 4.500 200.00 900.00 P&M-060

Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017Tipper 10 tonne tonne.km 450 x L 2.46 1105.99

110.60

Motor Grader 110 HP hour 6.000 2395.00 14370.00 P&M-032Vibratory roller 8-10 t hour 6.000 1541.00 9246.00 P&M-059

c) MaterialClose graded Granular sub-base Material as per table 400-1

For Grading-I Material53 mm to 9.5 mm @ 50 per cent cum 144.000 867.00 124848.00 M-0139.5 mm to 2.36 mm @ 20 per cent cum 57.000 867.00 49419.00 M-0172.36 mm below @ 30 per cent cum 86.400 867.00 74908.80 M-020Cost of water KL 27.000 10.00 270.00 M-189

ORFor Grading-II Material

26.5 mm to 9.5 mm @ 35 per cent cum 100.800 867.00 87393.60 M-0159.5 mm to 2.36 mm @ 25 per cent cum 72.000 867.00 62424.00 M-0172.36 mm below @ 40 per cent cum 115.200 867.00 99878.40 M-020Cost of water KL 27.000 10.00 270.00 M-189

ORFor Grading-III Material

9.5 mm to 4.75 mm @ 35 per cent cum 100.800 867.00 87393.60 M-0164.75 mm to 2.36 mm @ 12.5 per cent cum 36.000 867.00 31212.00 M-0182.36 mm below @ 52.5 per cent cum 151.200 867.00 131090.40 M-020Cost of water KL 27.000 10.00 270.00 M-189

4.1A (i) Rate per cum for grading-I Materiald) Overhead charges @ 0.1 on (a+b+c) 29858.00 e) Contractor's profit @ 0.1 on (a+b+c+d) 32843.80 Cost for 225 cum = a+b+c+d+e 361281.81 Rate per cum = (a+b+c+d+e)/225 1605.70

say 1606.00 4.1A (ii) Rate per cum for grading-II Material

d) Overhead charges @ 0.1 on (a+b+c) 29910.02 e) Contractor's profit @ 0.1 on (a+b+c+d) 32901.02 Cost for 225 cum = a+b+c+d+e 361911.26 Rate per cum = (a+b+c+d+e)/225 1608.49

say 1608.00 4.1A (iii) Rate per cum for grading-III Material

d) Overhead charges @ 0.1 on (a+b+c) 29910.02 e) Contractor's profit @ 0.1 on (a+b+c+d) 32901.02 Cost for 225 cum = a+b+c+d+e 361911.26 Rate per cum = (a+b+c+d+e)/225 1608.49

say 1608.00

Ref. to MoRTH Spec.

Remarks/ Input ref.

Granular Sub-Base with Close Graded Material (Table:- 400-1)

Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401

Water tanker 6 KL capacity 5 km lead with one trip per hour

Lead =1 km & P&M-

058

Add 10 per cent of cost of carriage to cover loading and unloading

Page 81: Standard Data Book - Rate Analysis

Page 2 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Note Any one of the grading for material may be adopted as per design

Page 82: Standard Data Book - Rate Analysis

Page 3 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

4.1 B By Mix in Place Method

Unit = cumTaking output = 300 cum

a) Labour

Mate day 0.480 151.44 72.69 L-12

Mazdoor skilled day 2.000 164.69 329.38 L-15

Mazdoor unskilled day 10.000 136.69 1366.90 L-13

b) Machinery

Motor Grader 110 HP @ 50 cum hour 6.000 2395.00 14370.00 P&M-032

Vibratory roller 8 -10 tonne hour 6.000 1541.00 9246.00 P&M-059

Tractor - Rotavator hour 12.000 0.00 0.00 P&M-054

Water tanker 6 KL capacity hour 3.000 200.00 600.00 P&M-060

c) Material

Close graded Granular sub-base Material as per table 400-1

For Grading-I Material

53 mm to 9.5 mm @ 50 per cent cum 384.000 836.17 321089.28 M-013

9.5 mm to 2.36 mm @ 20 per cent cum 0.000 836.17 0.00 M-017

2.36 mm below @ 30 per cent cum 0.000 836.17 0.00 M-020

Cost of water KL 18.000 10.00 180.00 M-189

OR

4.1B (i) Rate per cum for grading-I Material

d) Overhead charges @ 0.1 on (a+b+c) 34725.43

e) Contractor's profit @ 0.1 on (a+b+c+d) 38197.97

Cost for 300 cum = a+b+c+d+e 420177.64

Rate per cum = (a+b+c+d+e)/300 1400.59

Add 1 % labour Cess 14.01

1414.60

say 1414.60

4.1B (ii) Rate per cum for grading-II Material

d) Overhead charges @ 0.1 on (a+b+c) 35139.78

e) Contractor's profit @ 0.1 on (a+b+c+d) 38653.76

Cost for 300 cum = a+b+c+d+e 425191.34

Rate per cum = (a+b+c+d+e)/300 1417.30

Add 1 % labour Cess 14.17

1431.48

say 1431.48

4.1B (iii) Rate per cum for grading-III Material

d) Overhead charges @ 0.1 on (a+b+c) 35287.76

e) Contractor's profit @ 0.1 on (a+b+c+d) 38816.54

Cost for 300 cum = a+b+c+d+e 426981.95

Rate per cum = (a+b+c+d+e)/300 1423.27

Add 1 % labour Cess 14.23

1437.51

say 1437.51

Note

Construction of granular sub-base by providing close graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401

Any one of the grading for material may be adopted as per design

Page 83: Standard Data Book - Rate Analysis

Page 4 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

4.2 401

Unit = cum

Taking output = 300 cum

a) Labour

Mate day 0.400 151.44 60.58 L-12

Mazdoor skilled day 2.000 164.69 329.38 L-15

Mazdoor day 8.000 136.69 1093.52 L-13

b) Machinery

Mortar Grader 110 HP @ 50 cum per hour hour 6.000 2395.00 14370.00 P&M-032

Vibratory roller 8 -10 tonne hour 6.000 1541.00 9246.00 P&M-059

Water tanker 6 KL capacity hour 3.000 200.00 600.00 P&M-060

c) Material

For grading-I Material

53 mm to 26.5 mm @ 35 per cent cum 134.400 867.00 116524.80 M-029

26.5 mm to 4.75 mm @ 45 per cent cum 172.800 867.00 149817.60 M-026

2.36 mm below @ 20 per cent (Coarse Sand) cum 76.800 992.30 76208.64 M-022

Cost of water KL 18.000 10.00 180.00 M-189

OR

For Grading-II Material

26.5 mm to 4.75 mm @ 75 per cent cum 288.000 867.00 249696.00 M-026

2.36 mm below @ 25 per cent cum 96.000 992.30 95260.80 M-022

Cost of water KL 18.000 10.00 180.00 M-189

OR

For Grading-III Material

9.5 mm to 4.75 mm @ 66 per cent cum 255.000 867.00 221085.00 M-025

2.36 mm below @ 34 per cent cum 129.000 992.30 128006.70 M-022

Cost of water KL 18.000 10.00 180.00 M-189

4.2 (i) Rate per cum for grading-I Material

d) Overhead charges @ 0.1 on (a+b+c) 36843.05

e) Contractor's profit @ 0.1 on (a+b+c+d) 40527.36

Cost for 300 cum = a+b+c+d+e 445800.92

Rate per cum = (a+b+c+d+e)/300 1486.00

say 1486.00

4.2 (ii) Rate per cum for grading-II Material

d) Overhead charges @ 0.1 on (a+b+c) 37083.63

e) Contractor's profit @ 0.1 on (a+b+c+d) 40791.99

Cost for 300 cum = a+b+c+d+e 448711.89

Rate per cum = (a+b+c+d+e)/300 1495.71

say 1496.00

4.2 (iii) Rate per cum for grading-III Material

d) Overhead charges @ 0.1 on (a+b+c) 37497.12

e) Contractor's profit @ 0.1 on (a+b+c+d) 41246.83

Cost for 300 cum = a+b+c+d+e 453715.12

Rate per cum = (a+b+c+d+e)/300 1512.38

say 1512.00

Note

Granular Sub-Base with Coarse Graded Material (Table:- 400- 2)

Construction of granular sub-base by providing coarse graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401.

For coarse graded Granular sub-base Materials per table 400-2

Any one of the grading for material may be adopted as per design

Page 84: Standard Data Book - Rate Analysis

Page 5 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

4.12 406 Wet Mix Macadam

Unit = cum

Taking output = 225 cum (495 tonnes)

a) Labour

Mate day 0.480 151.44 72.69 L-12

Mazdoor skilled day 2.000 164.69 329.38 L-15

Mazdoor day 10.000 136.69 1366.90 L-13

b) Machinery

Wet mix plant of 75 tonne hourly capacity hour 9.000 2195.03 19755.23 P&M-094

Electric generator 125 KVA hour 6.000 652.00 3912.00 P&M-018

Front end loader 1 cum capacity hour 6.000 806.00 4836.00 P&M-017

Paver finisher hour 6.000 975.00 5850.00 P&M-035

Vibratory roller 8 - 10 tonne hour 6x0.65 1541.00 6009.90 P&M-059

or

Smooth 3 wheeled steel roller @ 8-10 tonnes. hour 12.000

Water tanker 6 KL capacity hour 3.000 200.00 600.00 P&M-060

Tipper tonne.km 495 x L 2.46 1216.59

121.66

c) Material ( Table 400-11)

45 mm to 22.4 mm@ 30 per cent cum 89.100 1007.77 89792.31 M-034

22.4 mm to 2.36 mm @ 40 per cent cum 118.800 1011.94 120218.47 M-031

2.36 mm to 75 micron@ 30 per cent cum 89.100 992.30 88413.93 M-022

Cost of water KL 18.000 10.00 180.00 M-189

d) Overhead charges @ 0.1 on (a+b+c) 34267.51

e) Contractor's profit @ 0.1 on (a+b+c+d) 37694.26

Cost for 225 cum = a+b+c+d+e 414636.81

Rate per cum = (a+b+c+d+e)/225 1842.83

Add 1 % labour Cess 18.43

1861.26

say 1861.26

Note

4.13 407

Unit = cum

Taking output =21 cum

a) Labour

Mate day 0.240 151.44 36.35 L-12

Mazdoor day 6.000 136.69 820.14 L-13

b) Machinery

Water tanker 6 KL with 5 km lead and 1 trip per hour hour 1.000 200.00 200.00 P&M-060

Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density.

Lead =1 km & P&M-

058

Add 10 per cent of cost of carriage to cover cost of loading and unloading

1. Though vibratory roller is required only for 3 hours as per norms, the same is required to be available at site for 6 hours to match with other machines. The usage rates of vibratory roller may be multiplied with a factor of 0.65

2. As three wheeled smooth steel rollers are commonly in use, the same has been provided as an alternative which can be used if the thickness of individual layer does not exceed 100 mm..

Construction of Median and Island with Soil Taken from Roadway Cutting

Construction of Median and Island above road level with approved material deposited at site from roadway cutting and excavation for drain and foundation of other structures, spread, graded and compacted as per clause 407

Page 85: Standard Data Book - Rate Analysis

Page 6 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Plate compactor @ 3.5 cum per hour hour 6.000 101.70 610.20 P&M-086

c) Material

Cost of water KL 6.000 10.00 60.00 M-189

d) Overhead charges @ 0.1 on (a+b+c) 172.67

e) Contractor's profit @ 0.1 on (a+b+c+d) 189.94

Cost for 21 cum = a+b+c+d+e 2089.29

Rate per cum = (a+b+c+d+e)/21 99.49

say 99.00

Note

4.14 407

Unit = cum

Taking output = 21 cum

a) Labour

Mate day 0.160 151.44 24.23 L-12

Mazdoor day 4.000 136.69 546.76 L-13

b) Machinery

Water tanker with 5 km lead hour 1.000 200.00 200.00 P&M-060

Plate Compactor @ 3.5 cum per hour hour 6.000 101.70 610.20 P&M-086

hour 0.500 1302.00 651.00 P&M-026

Tipper 10 tonne capacity tonne.km 52.5 x L 2.46 2580.64

258.06

c) Material

Cost of water KL 6.000 10.00 60.00 M-189

d) Overhead charges @ 0.1 on (a+b+c) 493.09

e) Contractor's profit @ 0.1 on (a+b+c+d) 542.40

Cost for 21 cum = a+b+c+d+e 5966.38

Rate per cum = (a+b+c+d+e)/ 21 284.11

say 284.00

Note

4.15 Construction of Shoulders

A. Earthen Shoulders

B. Hard Shoulders

C. Paved shoulders

4.16 409 Footpaths and Separators

This analysis provides for median and island with earthen top. In case the surface is required to be turfed or planted with shrubs, the same is required to be provided separately as per analysis given in the chapter on horticulture. In case granular fill is required to be paved, quantities of paving are required to be calculated as per approved design and paid separately.

Construction of Median and Island with Soil Taken from Borrow Areas

Construction of median and Island above road level with approved material brought from borrow pits, spread, sloped and compacted as per clause 407

Hydraulic Excavator1.0 cum bucket capacity @60 cum per hour

Lead =20 km & P&M-

058

Add 10 per cent of cost of transportation to cover cost of loading and unloading

This analysis provides for median and island with earthen top. In case the surface is required to be turfed or planted with shrubs, the same is required to be provided separately as per analysis given in the chapter on horticulture. In case surface finish is of hard type, the same may be provided separately as per approved design.

The rate as applicable for sub-grade construction may be adopted.

Rate as applicable for sub-base and or base may be adopted as per approved design.

The rate may be adopted as applicable for different layers of pavement depending upon approved design of paved shoulders.

Page 86: Standard Data Book - Rate Analysis

Page 7 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Unit = sqm

Taking output = 300 sqm

a) Labour

Mate day 1.360 151.44 205.96 L-12

Mason day 4.000 223.36 893.44 L-11

Mazdoor day 30.000 136.69 4100.70 L-13

b) Machinery

Vibratory road roller 8 -10 tonnes @60 cum per hour hour 0.750 1541.00 1155.75 P&M-059

Water tanker 6 KL capacity @ 1 trip per hour hour 2.000 200.00 400.00 P&M-060

Concrete mixer 0.4/0.28 cum per hour hour 6.000 233.00 1398.00 P&M-009

c) Material

i) For Granular sub base material

53 mm to 26.5 mm @ 35 per cent cum 20.790 867.00 18024.93 M-029

26.5 mm to 4.75 mm @ 45 per cent cum 26.730 867.00 23174.91 M-026

2.36 mm below @ 20 per cent cum 11.880 867.00 10299.96 M-022

ii) For cement concrete grade M157.5 cum

Aggregate 12 mm crushed @ 0.9 cum of concrete cum 6.750 1028.00 6939.00 M-052

Sand @ 0.45 cum/cum of concrete cum 3.380 710.46 2401.35 M-005

Cement tonne 1.880 5000.00 9400.00 M-081

iii) For cement plaster 1:3

Sand cum 3.840 710.46 2728.17 M-005

Cement tonne 1.830 5000.00 9150.00 M-081

iv) Pre-cast cement concrete tiles

Tiles size 300 x 300 mm and 25 mm thick each 3300.000 15.00 49500.00 M-184

v) RCC pipes

Pipes 200 mm dia,2.5 m long for drainage metre 22.500 243.00 5467.50 M-137

vi) Cost of water KL 12.000 10.00 120.00 M-189

d) Overhead charges @ 0.1 on (a+b+c) 14535.97

e) Contractor's profit @ 0.1 on (a+b+c+d) 15989.56

Cost for 300 sqm = a+b+c+d+e 175885.20

Rate per sqm = (a+b+c+d+e)/300 586.28

say 586.00

4.17 410 Crusher Run Macadam Base

Unit = cum

Taking output = 360 cum

A By Mix in Place Method

a) Labour

Mate day 0.480 151.44 72.69 L-12

Mazdoor skilled day 2.000 164.69 329.38 L-15

Mazdoor day 10.000 136.69 1366.90 L-13

b) Machinery

Tractor attached with rotavator @ 25 cum per hour hour 12.000 282.50 3390.00 P&M-054

Motor grader 110 HP hour 6.000 2395.00 14370.00 P&M-032

Vibratory roller 8 -10 tonnes @ 60 cum per hour hour 6.000 1541.00 9246.00 P&M-059

Water tanker 6 KL capacity hour 6.000 200.00 1200.00 P&M-060

c) Material

Aggregate at site

i) For 53 mm maximum size

Construction of footpath/separator by providing a 150 mm compacted granular sub base as per clause 401 and 25 mm thick cement concrete grade M15, over laid with pre-cast concrete tiles in cement mortar 1:3 including provision of all drainage arrangements but excluding kerb channel..

Providing crushed stone aggregate, depositing on a prepared surface by hauling vehicles, spreading and mixing with a motor grader, watering and compacting with a vibratory roller to clause 410 to form a layer of sub-base/Base

Page 87: Standard Data Book - Rate Analysis

Page 8 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

63 mm to 45 mm @ 33 per cent cum 157.460 949.00 149429.54 M-038

22.5 mm to 5.6 mm@ 32 per cent cum 151.060 1000.67 151160.71 M-032

Below 5.6 mm @ 35 per cent cum 166.680 1066.89 177829.23 M-030

Cost of water KL 36.000 10.00 360.00 M-189

Or

ii) For 45 mm maximum size

45 mm to 22.5 mm@ 5 per cent cum 24.120 920.50 22202.46 M-034

22.4 mm to 5.6 mm@ 50 per cent cum 237.600 1000.67 237758.40 M-032

Below 5.6 mm@ 45 per cent cum 213.480 1066.89 227759.68 M-030

Cost of water KL 36.000 10.00 360.00 M-189

4.17A (i) For 53 mm maximum size

d) Overhead charges @ 0.1 on (a+b+c) 50875.44

e) Contractor's profit @ 0.1 on (a+b+c+d) 55962.99

Cost for 360.0cum = a+b+c+d+e 615592.88

Rate per cum = (a+b+c+d+e)/360 1709.98

or say 1710.00

4.17A (ii) For 45 mm maximum size

d) Overhead charges @ 0.1 on (a+b+c) 51805.55

e) Contractor's profit @ 0.1 on (a+b+c+d) 56986.11

Cost for 360.0cum = a+b+c+d+e 626847.17

Rate per cum = (a+b+c+d+e)/360 1741.24

say 1741.00

Note Any one of the aggregate grading may be adopted

4.17 B By Mixing Plant :

Unit = cum

Taking output = 225 cum (450 tonnes)

a) Labour

Mate day 0.280 151.44 42.40 L-12

Mazdoor skilled day 1.000 164.69 164.69 L-15

Mazdoor day 6.000 136.69 820.14 L-13

b) Machinery

Wet mix plant @ 75 tonne per hour hour 6.000 2195.03 13170.15 P&M-093

Electric generator 125 KVA hour 6.000 652.00 3912.00 P&M-018

Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017

Motor grader 110 HP hour 6.000 2395.00 14370.00 P&M-032

Vibratory roller 8 - 10 tonne hour 6.000 1541.00 9246.00 P&M-059

Water tanker 6 KL capacity hour 3.000 200.00 600.00 P&M-060

Tipper 10 tonne capacity tonne.km 450 x L 2.46 1105.99

110.60

c) Material

Aggregate at site

i) For 53 mm maximum size

63 mm to 45 mm @ 33 per cent cum 98.400 949.00 93381.60 M-038

22.5 mm to 5.6 mm@ 32 per cent cum 94.410 1000.67 94472.94 M-032

Below 5.6 mm @ 35 per cent cum 104.180 1066.89 111148.60 M-030

Or

ii) For 45 mm maximum size

45 mm to 22.5 mm@ 5 per cent cum 15.060 920.50 13862.73 M-034

22.4 mm to 5.6 mm@ 50 per cent cum 148.500 1000.67 148599.00 M-032

Below 5.6 mm@ 45 per cent cum 133.430 1066.89 142355.13 M-030

Cost of water KL 18.000 10.00 180.00 M-189

4.17 B (i) For 53 mm maximum size

d) Overhead charges @ 0.1 on (a+b+c) 34738.11

e) Contractor's profit @ 0.1 on (a+b+c+d) 38211.92

Lead =1 km & P&M-

058

Add 10 per cent of cost of carriage to cover cost of loading and unloading

Page 88: Standard Data Book - Rate Analysis

Page 9 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Cost for 225cum = a+b+c+d+e 420331.14

Rate per cum = (a+b+c+d+e)/225 1868.14

say 1868.00

4.17 B (ii) For 45 mm maximum size

d) Overhead charges @ 0.1 on (a+b+c) 35337.48

e) Contractor's profit @ 0.1 on (a+b+c+d) 38871.23

Cost for 360.0cum = a+b+c+d+e 427583.55

Rate per cum = (a+b+c+d+e)/360 1187.73

say 1188.00

4.18 Lime, Flyash Stabilised Soil Sub-Base

Unit = cum

Taking output = 480 cum (720 tonnes, density 1.50 t/cum)

Assumptions made

Total mass taken for analysis = 720 t

Lime + Flyash admixture @ 20 per cent = 0.2 x 720=144 t

Soil = 720 -144 = 576 t

576 /1.6 = 360 cum

Lime + Flyash = 144 t

Ratio Lime 4 : Flyash 16

Lime = 29 kg.

Flyash = 115 kg.

a) Labour

Mate day 0.240 151.44 36.35 L-12

Mazdoor day 6.000 136.69 820.14 L-13

Mazdoor (Skilled) day 1.000 164.69 164.69 L-15

b) Machinery

hour 6.000 1302.00 7812.00 P&M-026

Tipper 10T capacity for carriage of soil 576 tonnes tonne.km 576 x L 2.46 28411.59

Tipper 10T capacity for carriage of 115 tonnes Flyash tonne.km 115 x L 2.46 14979.99

hour 3.000 339.00 1017.00 P&M-048

101.70

Tractor with disc harrows for pulverisation hour 6.000 282.50 1695.00 P&M-053

hour 9.600 2395.00 22992.00 P&M-032

Vibratory roller 8 - 10 tonne hour 6.000 1541.00 9246.00 P&M-059

Water tanker 6 KL capacity hour 12.000 200.00 2400.00 P&M-060

c) Material

Slaked Lime tonne 29.000 4500.00 130500.00 M-188

Compensation for earth taken from private source cum 360.000 28.00 10080.00 M-092

d) Overhead charges @ 0.1 on (a+b+c) 23025.65

e) Contractor's profit @ 0.1 on (a+b+c+d) 25328.21

Cost for 480 cum = a+b+c+d+e 278610.31

Suggestive

Construction of Sub-base using lime - Flyash admixture with granular soil, free from organic matter/ deleterious material or clayey silts and low plasticity clays having PI between 5 and 20 and liquid limit less than 25 and commercial dry lime, slaked at site or pre-slaked with CaO content not less than 50 per cent, Flyash to conform to gradation as per clause 4.3 of IRC: 88-1984, lime + Flyash content ranging between 10 to 30 per cent, the minimum un-confined compressive strength and CBR value after 28 days curing and 4 days soaking to be 7.5kg/sq, cm and 25 per cent respectively, all as specified in IRC: 88-1984.

Hydraulic Excavator 0.90 cum bucket capacity @ 60cum/hr. for 360 cum soil

Lead =20 km & P&M-

058

Lead =53 km & P&M-

058

Tipper 10T capacity for carriage of 29 tonnes of lime from store to work site

Add 10 per cent of cost of carriage to cover cost of loading and unloading

Motor Grader 110 HP @ 50 cum per hour for mixing in-place and grading

Page 89: Standard Data Book - Rate Analysis

Page 10 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Rate per cum= (a+b+c+d+e)/480 580.44

say 580.00

Note 1.Compensation for earth will vary from place to place and will have to be assessed realistically as per particular ground situation. In case earth is available from Govt. land, compensation for earth will not be required. The position is required to be clearly stated in the cost estimate.

2.Cost of Flyash has not been considered as same will be available free of cost. Only carriage of Flyash has been provided.

3.Lime + Flyash has been taken as 20 per cent of total mass and ratio of lime and Flyash as 1:4 for estimating purposes. Total quantities will be as per approved design.

Page 90: Standard Data Book - Rate Analysis

Page 1 of 280

CHAPTER - 5BASES AND SURFACE COURSES (BITUMINOUS)

Sr No Description Unit Quantity Rate Rs Cost Rs

5.1 502 Prime Coat

Unit = sqmTaking output = 3500 sqma) Labour

Mate day 0.080 151.44 12.12 L-12Mazdoor day 2.000 136.69 273.38 L-13

b) MachineryMechanical broom @ 1250 sqm per hour hour 2.800 357.00 999.60 P&M-031Air compressor 250 cfm hour 2.800 319.00 893.20 P&M-001Bitumen pressure distributor @ 1750 sqm per hour hour 2.000 1073.00 2146.00 P&M-004Water tanker 6 KL capacity @ 1 trip per hour hour 1.000 200.00 200.00 P&M-060

c) MaterialBitumen emulsion @ 0.85 kg per sqm tonne 2.975 47937.00 142612.58 M-077Cost of water KL 6.000 10.00 60.00 M-189

d) Overhead charges @ 0.1 on (a+b+c) 14719.69 e) Contractor's profit @ 0.1 on (a+b+c+d) 16191.66 Cost for 3500 sqm = a+b+c+d+e 178108.21 Rate per sqm = (a+b+c+d+e)/3500 50.89 Add 1 % labour Cess 0.51

51.40 say 51.40

Note

Ref. to MoRTH Spec.

Remarks/ Input ref.

Providing and applying primer coat with bitumen emulsion on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.85 kg/sqm using mechanical means.

Bitumen primer has been provided @ 0.850 kg per sqm as per clause 502.8. Payment shall be made with adjustment, plus or minus, for the variation between this quantity and the actual quantity approved by the Engineer after the preliminary trials referred to in clause No. 502.4.3.

Page 91: Standard Data Book - Rate Analysis

Page 2 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

5.2 503 Tack Coat

Unit = sqmTaking output = 3500 sqma) Labour

Mate day 0.080 151.44 12.12 L-12Mazdoor day 2.000 136.69 273.38 L-13

b) MachineryMechanical broom @ 1250 sqm per hour hour 2.800 357.00 999.60 P&M-031Air compressor 250 cfm hour 2.800 319.00 893.20 P&M-001Bitumen pressure distributor @ 1750 sqm per hour hour 2.000 1073.00 2146.00 P&M-004

c) MaterialBitumen emulsion @ 0.25 kg per sqm tonne 0.875 49915.00 43675.63 M-077

d) Overhead charges @ 0.1 on (a+b+c) 4799.99 e) Contractor's profit @ 0.1 on (a+b+c+d) 5279.99 Cost for 3500 sqm = a+b+c+d+e 58079.90 Rate per sqm = (a+b+c+d+e)/3500 16.59 Add 1 % labour Cess 0.17

16.76 say 16.76

Note

Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous/granular surface cleaned with mechanical broom.

1. Bitumen emulsion has been provided @ 0.20 kg per sqm as per clause 503.8. Payment shall be made with adjustment, plus or minus, for the variation between this quantity and actual quantity approved by the Engineer after preliminary trials referred to in clause No. 503.4.3

2. An output of 3500 sqm has been considered in case of prime coat and tack coat which can be covered by bituminous courses on the same day.

Page 92: Standard Data Book - Rate Analysis

Page 3 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

5.3 504 Bituminous Macadam

Unit = cum

Taking output = 205 cum (450 tonnes)

a) Labour

Mate day 0.840 151.44 127.21 L-12

day 16.000 136.69 2187.04 L-13

Skilled mazdoor for checking line & levels day 5.000 164.69 823.45 L-15

b) Machinery

hour 6.000 23405.00 140430.00 P&M-021

Mechanical broom hydraulic @ 1250 sqm per hour hour 2.200 357.00 785.40 P&M-031

Air compressor 250 cfm hour 2.200 319.00 701.80 P&M-001

hour 6.000 2674.00 16044.00 P&M-034

Generator 250 KVA hour 6.000 1906.88 11441.25 P&M-081

Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017

Tipper 10 tonne capacity tonne.km 450 x L 2.46 1105.99

110.60

hour 6.00x0.65* 460.00 1794.00 P&M-044

Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1541.00 6009.90 P&M-059

hour 6.00x0.65* 1144.00 4461.60 P&M-045

c) Material

i) Bitumen@ 3.3 per cent of mix tonne 14.850 55132.00 818710.20 M-074

weight of mix = 205 x 2.2 = 450 tonne

ii) Aggregate

Total weight of mix = 450 tonnes

Weight of bitumen = 14.85 tonnes

Weight of aggregate = 450 -14.85 = 435.15 tonnes

Taking density of aggregate = 1.5 ton/cum

Volume of aggregate = 290.1 cum

*Grading I ( 40 mm nominal size )

37.5 - 25 mm 15 per cent cum 43.510 1011.94 44029.51 M-049

25 - 10 mm 45 per cent cum 130.550 1103.60 144074.98 M-046

10 - 5 mm 25 per cent cum 72.530 1078.94 78255.52 M-040

5 mm and below15 per cent cum 43.510 992.30 43174.97 M-030

or

GradingII(19 mm nominal size)

25 - 10 mm 40 per cent cum 116.040 1103.60 128061.74 M-046

10 - 5 mm 40 per cent cum 116.040 1078.94 125200.20 M-040

5 mm and below 20 per cent cum 58.020 992.30 57573.25 M-030

(i) for Grading I ( 40 mm nominal size )

d) Overhead charges @ 0.1 on (a+b+c) 131910.34

e) Contractor's profit @ 0.1 on (a+b+c+d) 145101.38

Cost for 205 cum = a+b+c+d+e 1596115.13

Rate per cum = (a+b+c+d+e)/205 (For Grading I) 7785.93

Add 1 % labour Cess 77.86

7863.79

say 7863.79

(ii) for GradingII(19 mm nominal size)

d) Overhead charges @ 0.1 on (a+b+c) 132040.36

e) Contractor's profit @ 0.1 on (a+b+c+d) 145244.40

Cost for 205 cum = a+b+c+d+e 1597688.38

Providing and laying bituminous macadam with 100-120 TPH hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading premixed with bituminous binder, transported to site, laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled as per clauses 501.6 and 501.7 to achieve the desired compaction

Mazdoor working with HMP, mechanical broom, paver, roller, asphalt cutter and assistance for setting out lines, levels and layout of construction

Batch mix HMP 100-120 TPH @ 75 tonne per hour actual output

Paver finisher hydrostatic with sensor control @ 75 cum per hour

Lead =1 km & P&M-

058

Add 10 per cent of cost of carriage to cover cost of loading and unloading

Smooth wheeled roller 8-10 tonnes for initial break down rolling.

Finish rolling with 6-8 tonnes smooth wheeled tandem roller.

* Any one of the alternative may be adopted as per approved design

Page 93: Standard Data Book - Rate Analysis

Page 4 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Rate per cum = (a+b+c+d+e)/205 (For Grading-II) 7793.60

Add 1 % labour Cess 77.94

7871.54

say 7871.54

Page 94: Standard Data Book - Rate Analysis

Page 5 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Note

5.4 505 Bituminous Penetration Macadam

A 50 mm thick

Unit = sqm

Taking output = 4500 sqm (225 cum)

a) Labour

Mate day 0.320 151.44 48.46 L-12

Mazdoor including for brooming of key aggregates day 6.000 136.69 820.14 L-13

Mazdoor skilled day 2.000 164.69 329.38 L-15

b) Machinery

hour 6.000 2635.00 15810.00 P&M-025

Bitumen pressure distributor for @ 1750 sqm per hour hour 2.570 1073.00 2757.61 P&M-004

hour 10.000 339.00 3390.00 P&M-048

Vibratory roller 8 tonnes hour 6.000 1541.00 9246.00 P&M-059

Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017

c) Material

Bitumen@ 5 kg per sqm tonne 22.500 55132.00 1240470.00 M-074

cum 270.000 968.60 261522.00 M-033

cum 67.500 1000.67 67545.00 M-031

d) Overhead charges @ 0.1 on (a+b+c) 160677.46

*1. Although the rollers are required only for 3 hours as per norms of output, but the same have to be available at site for six hours as the hot mix plant and paver will take six hours for mixing and paving the output of 450 tonnes considered in this analysis. To cater for the idle period of these rollers, their usage rates have been multiplied by a factor of 0.65.

2.Quantity of Bitumen has been taken for analysis purpose. The actual quantity will depend upon job mix formula.

3. Labour for traffic control, watch and ward and other miscellaneous duties at site including sundries have been included in administrative overheads of the contractor.

4. In case BM is laid over freshly laid tack coat, provision of Mechanical broom and 2 mazdoors for the same shall be deleted as the same has been included in the cost of tack coat.

Construction of penetration macadam over prepared Base by providing a layer of compacted crushed coarse aggregate using chips spreader with alternate applications of bituminous binder and key aggregates and rolling with a smooth wheeled steel roller 8-10 tonne capacity to achieve the desired degree of compaction

Hydraulic self propelled chip spreader both for aggregates and key aggregates@ 1500 sqm per hour for 4500 x 2 sqm = 9000 sqm

Tipper 5.5 cum capacity for carriage of aggregates from stockpile to chip spreader

Crushed stone coarse aggregate passing 45 mm and retained on 2.8 mm sieve @ 0.06 cum per sqm

Key aggregates passing 22.4 mm and retained on 2.8 mm sieve @ 0.015 cum per sqm

Page 95: Standard Data Book - Rate Analysis

Page 6 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

e) Contractor's profit @ 0.1 on (a+b+c+d) 176745.20

Cost for 4500 sqm = a+b+c+d+e 1944197.25

Rate per sqm = (a+b+c+d+e)/4500 432.04

say 432.00

Note

5.4 B 75 mm thick

Unit = sqm

Taking output = 4500 sqm (337.5 cum compacted).

a) Labour

Mate day 0.400 151.44 60.58 L-12

Mazdoor including for brooming of key aggregates day 8.000 136.69 1093.52 L-13

Mazdoor skilled day 2.000 164.69 329.38 L-15

b) Machinery

hour 6.000 2635.00 15810.00 P&M-025

Bitumen pressure distributor for@ 1750 sqm per hour hour 2.570 1073.00 2757.61 P&M-004

hour 10.000 339.00 3390.00 P&M-048

Vibratory roller 8 tonnes hour 6.000 1541.00 9246.00 P&M-059

Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017

c) Material

Bitumen@ 6.8 kg per sqm tonne 30.600 55132.00 1687039.20 M-074

cum 405.000 982.00 397710.00 M-037

cum 81.000 867.00 70227.00 M-026

d) Overhead charges @ 0.1 on (a+b+c) 219249.93

e) Contractor's profit @ 0.1 on (a+b+c+d) 241174.92

Cost for 4500 sqm = a+b+c+d+e 2652924.14

Rate per sqm = (a+b+c+d+e)/4500 589.54

say 590.00

Note

5.5 506 Built-up-Spray Grout

Unit = sqm

Taking output = 3000 sqm (225 cum)

a) Labour

Mate day 0.400 151.44 60.58 L-12

Mazdoor including for brooming of key aggregates day 8.000 136.69 1093.52 L-13

Mazdoor skilled day 2.000 164.69 329.38 L-15

b) Machinery

hour 6.000 2635.00 15810.00 P&M-025

hour 3.430 1073.00 3680.39 P&M-004

Tipper 5.5 cum capacity hour 10.000 339.00 3390.00 P&M-048

Vibratory roller 8 tonnes hour 6.000 1541.00 9246.00 P&M-059

Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017

c) Material

tonne 9.000 55132.00 496188.00 M-074

cum 300.000 990.25 297075.00 M-035

cum 39.000 1000.67 39026.00 M-031

d) Overhead charges @ 0.1 on (a+b+c) 87073.49

2 tippers will be needed to match the capacity of chip spreader and front end loader.

Hydraulic self propelled chip spreader both for aggregates and key aggregates@ 1500 sqm per hour for 4500 x 2 sqm

Tipper 5.5 cum capacity for carriage of aggregates from stockpile to chip spreader

Crushed stone coarse aggregate (loose passing 63 mm and retained on 2.8 mm sieve @ 0.09 cum per sqm

Key aggregates passing 26.5 mm and retained on 2.8 mm sieve @ 0.018 cum per sqm

2 tippers and 2 rollers will be needed to match the capacity of chip spreader and front end loader.

Providing, laying and rolling of built-up-spray grout layer over prepared base consisting of a two layer composite construction of compacted crushed coarse aggregates using motor grader for aggregates. key stone chips spreader may be used with application of bituminous binder after each layer, and with key aggregates placed on top of the second layer to serve as a Base conforming to the line, grades and cross-section specified, the compacted layer thickness being 75 mm

Hydraulic self propelled chip spreader both for aggregates and key aggregates@ 1500 sqm per hour for 3000 x 3 sqm

Bitumen pressure distributor for 3000 x 2 sqm @ 1750 sqm per hour

Bitumen30 kg per 10 sqm @ 15 kg per 10 sqm for each layer

Crushed stone coarse aggregate passing 53 mm and retained on 2.8 mm sieve @ 0.5 cum per 10 sqm for each layer

Key aggregates passing 22.4 mm and retained on 2.8 mm sieve @ 0.13 cum per 10 sqm

Page 96: Standard Data Book - Rate Analysis

Page 7 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

e) Contractor's profit @ 0.1 on (a+b+c+d) 95780.84

Cost for 3000 sqm = a+b+c+d+e 1053589.19

Rate per sqm = (a+b+c+d+e)/3000 351.20

say 351.00

Note 2 tippers will be needed to match the capacity of hydraulic chip spreader and front end loader.

Page 97: Standard Data Book - Rate Analysis

Page 8 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

5.6 505 Dense Graded Bituminous Macadam

Unit = cum

Taking output = 195 cum (450 tonnes)

a) Labour

Mate day 0.840 151.44 127.21 L-12

day 16.000 136.69 2187.04 L-13

Skilled mazdoor for checking line & levels day 5.000 164.69 823.45 L-15

b) Machinery

Batch mix HMP @ 75 tonne per hour hour 6.000 13842.00 83052.00 P&M-022

hour 6.000 2674.00 16044.00 P&M-034

Generator 250 KVA hour 6.000 1906.88 11441.25 P&M-081

Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017

Tipper 10 tonne capacity tonne.km 450 x L 2.46 1105.99

110.60

hour 6.00x0.65* 460.00 1794.00 P&M-044

Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1541.00 6009.90 P&M-059

hour 6.00x0.65* 1144.00 4461.60 P&M-045

c) Materials

Bitumen @ 4.50 per cent of weight of mix tonne 20.250 56122.00 1136470.50 M-074

Aggregate

Total weight of mix = 450 tonnes

Weight of bitumen = 20.25 tonnes

Weight of aggregate = 450 -20.25 = 429.75 tonnes

Taking density of aggregate = 1.5 ton/cum

Volume of aggregate = 286.50 cum

Grading - 2 26.5 mm (Nominal Size) 50-75 mm

25 - 10 mm 30 per cent cum 85.950 1103.60 94854.42 M-046

10 - 5 mm 28 per cent cum 80.220 1078.94 86552.57 M-040

5 mm and below 40 per cent cum 114.600 992.30 113717.58 M-030

Filler @ 2 per cent of weight of aggregates. tonne 8.595 4500.00 38677.50 M-188

(i) For Grading 1 ( 37.5 mm nominal size ) 75-100 mm

d) Overhead charges @ 0.1 on (a+b+c) 159671.18

e) Contractor's profit @ 0.1 on (a+b+c+d) 175638.30

Cost for 205 cum = a+b+c+d+e 1932021.27

Rate per cum = (a+b+c+d+e)/195 (For Grading I) 9907.80

Add 1 % labour Cess 99.08

10006.88

say 10006.88

(ii) For Grading 2 ( 26.5 mm nominal size) 50-75 mm

d) Overhead charges @ 0.1 on (a+b+c) 160226.56

e) Contractor's profit @ 0.1 on (a+b+c+d) 176249.22

Cost for 205 cum = a+b+c+d+e 1938741.38

Rate per cum = (a+b+c+d+e)/195 (For Grading-II) 9942.26

Add 1 % labour Cess 99.42

10041.69

say 10041.69

Providing and laying dense graded bituminous macadam with 100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 4.5 per cent by weight of total mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 505 complete in all respects.

Mazdoor working with HMP, mechanical broom, paver, roller, asphalt cutter and assistance for setting out lines, levels and layout of construction

Paver finisher hydrostatic with sensor control @ 75 cum per hour

Lead =1 km & P&M-

058

Add 10 per cent of cost of carriage to cover cost of loading and unloading

smooth wheeled roller 8-10 tonnes for initial break down rolling.

Finish rolling with 6-8 tonnes smooth wheeled tandem roller.

* Any one of the alternative may be adopted as per approved design

Page 98: Standard Data Book - Rate Analysis

Page 9 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Note

5.7 508 Semi-Dense Bituminous Concrete

Unit = cum

Taking output = 195 cum (450 tonnes)

a) Labour

Mate day 0.840 151.44 127.21 L-12

day 16.000 136.69 2187.04 L-13

Skilled mazdoor for checking line & levels day 5.000 164.69 823.45 L-15

b) Machinery

Batch mix HMP @ 75 tonne per hour hour 6.000 17309.00 103854.00 P&M-022

hour 6.000 2674.00 16044.00 P&M-034

Generator 250 KVA hour 6.000 1906.88 11441.25 P&M-081

Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017

Tipper 10 tonne capacity tonne.km 450 x L 2.46 1105.99

110.60

hour 6.00x0.65* 460.00 1794.00 P&M-044

Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1541.00 6009.90 P&M-059

hour 6.00x0.65* 1144.00 4461.60 P&M-045

c) Material

* Grading I: 13 mm (Nominal Size)

i) Bitumen@ 4.5 per cent of weight of mix tonne 20.250 55132.00 1116423.00 M-074

ii) Aggregate

Total weight of mix = 450 tonnes

Weight of bitumen = 20.25 tonnes

Weight of aggregate = 450-20.25 = 429.75 tonnes

Taking density of aggregate = 1.5 ton/cum

Volume of aggregate = 286.5 cum

13.2 - 10 mm20 per cent cum 57.300 1103.60 63236.28 M-044

10 - 5 mm 38 per cent cum 108.870 1078.94 117464.20 M-040

*1. Although the roller are required only for 3 hours as per norms of output, but the same have to be available at site for six hours as the hot mix plant and paver will take six hours for mixing and paving the output of 450 tonnes considered in this analysis. To cater for the idle period of these rollers, their usage rates have been multiplied by a factor of 0.65.

2.Quantity of Bitumen has been taken for analysis purpose. The actual quantity will depend upon job mix formula.

3. Labour for traffic control, watch and ward and other miscellaneous duties at site including sundries have been included in administrative overheads of the contractor.

4. In case DBM is laid over freshly laid tack coat, provision of mechanical broom and 2 mazdoors shall be deleted as the same has been included in the cost of tack coat.

5. The individual density for each size of aggregates to be used for construction I.e. 37.5-25 mm, 25-10 mm etc. should be found in the laboratory and accordingly the quantities should be ammended for use in field. The average density of 1.5 tonne/cum is only a reference density in this Data Book.

6. The individual percentage of aggregates should be calculated from the total weight of dry aggregates i.e.. excluding the weight of bitumen. The weight of filler will also be 2 per cent by weight of dry aggregates.

Providing and laying semi dense bituminous concrete with 100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 4.5 to 5 per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 508 complete in all respects

Mazdoor working with HMP, mechanical broom, paver, roller, asphalt cutter and assistance for setting out lines, levels and layout of construction

Paver finisher hydrostatic with sensor control @ 75 cum per hour

Lead =1 km & P&M-

058

Add 10 per cent of cost of carriage to cover cost of loading and unloading

Smooth wheeled roller 8-10 tonnes for initial break down rolling.

Finish rolling with 6-8 tonnes smooth wheeled tandem roller

Page 99: Standard Data Book - Rate Analysis

Page 10 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

5 mm and below 40 per cent cum 114.600 992.30 113717.58 M-030

Filler @ 2 per cent of weight of aggregates. tonne 8.620 4500.00 38790.00 M-188

or

Grading II: 10 mm (Nominal Size)

Bitumen@5 per cent of weight of mix tonne 22.500 55132.00 1240470.00 M-074

weight of mix = 450 tonne

Aggregate

Total weight of mix = 450 tonnes

Weight of bitumen = 22.5 tonnes

Weight of aggregate = 450 -22.50 = 427.50 tonnes

Taking density of aggregate = 1.5 ton/cum

Volume of aggregate = 285 cum

9.5 - 4.75 mm@ 57 per cent cum 162.450 1078.94 175273.80 M-040

4.75 and below@ 41 per cent cum 116.850 992.30 115950.25 M-030

Filler @ 2 per cent of weight of aggregates. tonne 8.620 4500.00 38790.00 M-188

(i) for Grading I ( 13 mm nominal size )

d) Overhead charges @ 0.1 on (a+b+c) 160242.61

e) Contractor's profit @ 0.1 on (a+b+c+d) 176266.87

Cost for 205 cum = a+b+c+d+e 1938935.57

Rate per cum = (a+b+c+d+e)/195 (For Grading I) 9943.26

say 9943.00

5.7 (ii) for GradingII(10 mm nominal size)

d) Overhead charges @ 0.1 on (a+b+c) 172327.91

e) Contractor's profit @ 0.1 on (a+b+c+d) 189560.70

Cost for 205 cum = a+b+c+d+e 2085167.70

Rate per cum = (a+b+c+d+e)/195 (For Grading-II) 10693.17

say 10693.00

Note

*Any one of the alternative may be adopted as per approved design

*1. Although the rollers are required only for 3 hours as per norms of output, but the same have to be available at site for six hours as the hot mix plant and paver will take six hours for mixing and paving the output of 450 tonnes considered in this analysis. To cater for the idle period of these rollers, their usage rates have been multiplied by a factor of 0.65

2.Quantity of Bitumen has been taken for analysis purpose. The actual quantity will depend upon job mix formula.

3. Labour for traffic control, watch and ward and other miscellaneous duties at site including sundries have been included in administrative overheads of the contractor.

4. In case SDBC is laid over freshly laid tack coat, provision of broom and 2 mazdoor shall be deleted as the same has been included in the cost of tack coat.

5. The quantity of Bitumen to be adjusted as per job mix formula.

Page 100: Standard Data Book - Rate Analysis

Page 11 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

5.8 509 / 507 Bituminous Concrete

Unit = cum

Taking output = 191 cum (450 tonnes)

a) Labour

Mate day 0.840 151.44 127.21 L-12

day 16.000 136.69 2187.04 L-13

Skilled mazdoor for checking line & levels day 5.000 164.69 823.45 L-15

b) Machinery

Batch mix HMP @ 75 tonne per hour hour 6.000 13842.00 83052.00 P&M-022

hour 6.000 2674.00 16044.00 P&M-034

Generator 250 KVA hour 6.000 1906.88 11441.25 P&M-081

Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017

Tipper 10 tonne capacity tonne.km 450 x L 2.46 1105.99

110.60

hour 6.00x0.65* 460.00 1794.00 P&M-044

Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1541.00 6009.90 P&M-059

hour 6.00x0.65* 1144.00 4461.60 P&M-045

c) Material

i) Bitumen@ 5.4 per cent of weight of mix tonne 24.300 56122.00 1363764.60 M-074

ii) Aggregate

Total weight of mix = 450 tonnes

Weight of bitumen = 24.30 tonnes

Weight of aggregate = 450 -24.30 = 425.70 tonnes

Taking density of aggregate = 1.5 ton/cum

Volume of aggregate = 283.80 cum

* Grading - 1-19 mm (Nominal Size) 50 mm

20 - 10 mm 35 per cent cum 99.330 1103.60 109620.59 M-045

10 - 5 mm 23 per cent cum 65.274 1078.94 70426.73 M-040

5 mm and below 40 per cent cum 113.520 992.30 112645.90 M-030

Filler @ 2 per cent of weight of aggregates. tonne 8.514 4500.00 38313.00 M-188

or

Grading - 2-13.2 mm (Nominal Size) 30-40 mm

13.2 - 10 mm30 per cent cum 85.500 1103.60 94357.80 M-044

10 - 5 mm 25 per cent cum 71.250 1078.94 76874.48 M-040

5 mm and below43 per cent cum 122.550 992.30 121606.36 M-030

Filler @ 2 per cent of weight of aggregates. tonne 8.620 4500.00 38790.00 M-188

(i) for Grading-I ( 13 mm nominal size )

d) Overhead charges @ 0.1 on (a+b+c) 182676.38

e) Contractor's profit @ 0.1 on (a+b+c+d) 200944.02

Cost for 205 cum = a+b+c+d+e 2210384.26

Rate per cum = (a+b+c+d+e)/191 11572.69

Add 1 % labour Cess 115.73

11688.42

say 11688.42

5.8 (ii) for Grading-II(10 mm nominal size)

d) Overhead charges @ 0.1 on (a+b+c) 182738.63

e) Contractor's profit @ 0.1 on (a+b+c+d) 201012.49

Cost for 205 cum = a+b+c+d+e 2211137.39

Providing and laying bituminous concrete with 100-120 TPH batch type hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 5.4 to 5.6 per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all respects

Mazdoor working with HMP, mechanical broom, paver, roller, asphalt cutter and assistance for setting out lines, levels and layout of construction

Paver finisher hydrostatic with sensor control @ 75 cum per hour

Lead =1 km & P&M-

058

Add 10 per cent of cost of carriage to cover cost of loading and unloading

Smooth wheeled roller 8-10 tonnes for initial break down rolling.

Finish rolling with 6-8 tonnes smooth wheeled tandem roller.

*Any one of the alternative may be adopted as per approved design

Page 101: Standard Data Book - Rate Analysis

Page 12 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Rate per cum = (a+b+c+d+e)/191 (For Grading-II) 11576.64

Add 1 % labour Cess 115.77

11692.40

say 11692.40

Note

5.9 510 Surface Dressing

Unit = sqm

Taking output = 9000 sqm

Case -1 :-19 mm nominal chipping size

a) Labour

Mate day 0.440 151.44 66.63 L-12

Mazdoor day 9.000 136.69 1230.21 L-13

Mazdoor skilled day 2.000 164.69 329.38 L-15

b) Machinery

Mechanical broom @ 1250 sqm per hour hour 7.200 357.00 2570.40 P&M-031

Air compressor 250 cfm hour 7.200 319.00 2296.80 P&M-001

hour 6.000 2635.00 15810.00 P&M-025

hour 6.000 339.00 2034.00 P&M-048

Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017

Bitumen pressure distributor hour 6.000 1073.00 6438.00 P&M-004

Smooth wheeled roller 8-10 tonne weight hour 6.000 460.00 2760.00 P&M-044

c) Material

Bitumen@ 1.20 kg per sqm tonne 10.800 55132.00 595425.60 M-074

cum 135.000 1028.00 138780.00 M-053

d) Overhead charges @ 0.1 on (a+b+c) 77257.70

e) Contractor's profit @ 0.1 on (a+b+c+d) 84983.47

Cost for 9000 sqm = a+b+c+d+e 934818.20

Rate per sqm = (a+b+c+d+e)/9000 103.87

say 104.00

5.9 Case - II 13 mm nominal size chipping

a) Labour

Mate day 0.440 151.44 66.63 L-12

Mazdoor day 9.000 136.69 1230.21 L-13

Mazdoor skilled day 2.000 164.69 329.38 L-15

b) Machinery

Mechanical broom @ 1250 sqm per hour hour 7.200 357.00 2570.40 P&M-031

Air compressor 250 cfm hour 7.200 319.00 2296.80 P&M-001

*1. Although the rollers are required only for 3 hours as per norms of output, but the same have to be available at site for six hours as the hot mix plant and paver will take six hours for mixing and paving the output of 450 tonnes considered in this analysis. To cater for the idle period of these rollers, their usage rates have been multiplied by a factor of 0.65

2.Quantity of Bitumen has been taken for analysis purpose. The actual quantity will depend upon job mix formula.

3. Labour for traffic control, watch and ward and other miscellaneous duties at site including sundries have been included in administrative overheads of the contractor.

4. In case BC is laid over freshly laid tack coat, provision of mechanical broom and 2 mazdoors shall be deleted as the same has been included in the cost of tack coat.

5. The individual density for each size of aggregates to be used for construction i.e. 37.5-25 mm, 25-10 mm etc. should be found in the laboratory and accordingly the quantities should be ammended for use in field. The average density of 1.5 tonne/cum is only a reference density in this Data Book.

6. The individual percentage of aggregates should be calculated from the total weight of dry aggregates i.e.. excluding the weight of bitumen. The weight of filler will also be 2 per cent by weight of dry aggregates.

Providing and laying surface dressing as wearing course in single coat using crushed stone aggregates of specified size on a layer of bituminous binder laid on prepared surface and rolling with 8-10 tonne smooth wheeled steel roller

Hydraulic self propelled chip spreader @ 1500 sqm per hour

Tipper 10 tonne capacity for carriage of stone chips from stockpile on road side to chip spreader

Crushed stone chipping,19 mm nominal size @ 0.015 cum per sqm

Page 102: Standard Data Book - Rate Analysis

Page 13 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

hour 6.000 2635.00 15810.00 P&M-025

hour 6.000 339.00 2034.00 P&M-048

Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017

Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 1073.00 6438.00 P&M-004

Vibratory roller 8-10 tonne weight hour 6.000 1541.00 9246.00 P&M-059

c) Material

Bitumen@ 1.00 kg per sqm tonne 9.000 55132.00 496188.00 M-074

cum 90.000 1028.00 92520.00 M-052

d) Overhead charges @ 0.1 on (a+b+c) 63356.54

e) Contractor's profit @ 0.1 on (a+b+c+d) 69692.20

Cost for 9000 sqm = a+b+c+d+e 766614.16

Rate per sqm = (a+b+c+d+e)/9000 85.18

say 85.00

Note

5.10 511 Open - Graded Premix Surfacing

Unit = sqm

Taking output = 10250 sqm (205 cum)

(i)

a) Labour

Mate day 0.840 151.44 127.21 L-12

day 16.000 136.69 2187.04 L-13

Skilled mazdoor for checking line & levels day 5.000 164.69 823.45 L-15

b) Machinery

i) Batch type HMP 75 tonne per hour hour 6.000 23405.00 140430.00 P&M-021

ii) Electric Generator Set 250 KVA hour 6.000 1906.88 11441.25 P&M-081

iii) Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017

iv) Tipper 10 tonne capacity tonne.km 450 x L 2.46 1105.99

110.60

v) Paver finisher hydrostatic with sensor attachment hour 6.000 2674.00 16044.00 P&M-034

iv) Smooth wheeled/tandom roller 8-10 tonnes weight hour 6.000 1144.00 6864.00 P&M-045

c) Material

Bitumen@ 14.60 kg per 10 sqm tonne 14.970 55132.00 825326.04 M-074

cum 276.750 998.50 276334.88 M-043

d) Overhead charges @ 0.1 on (a+b+c) 128563.05

e) Contractor's profit @ 0.1 on (a+b+c+d) 141419.35

Cost for 10250 sqm = a+b+c+d+e 1555612.85

Rate per sqm = (a+b+c+d+e)/10250 151.77

say 152.00

Hydraulic self propelled chip spreader @ 1500 sqm per hour

Tipper 10 tonne capacity for carriage of stone chips from stockpile on road side to chip spreader

Crushed stone chipping,13 mm nominal size @ 0.01 cum per sqm

1.Where the proposed aggregate fails to pass the stripping test, an approved adhesion agent may be added to the binder as per clause 510.2.4. Alternatively, chips may be pre-coated as per clause 510.2.5

2.Input for the second coat, where required, will be the same as per the Ist coat mentioned above

Providing, laying and rolling of open - graded premix surfacing of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates either using penetration grade bitumen or cut-back or emulsion to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a smooth wheeled roller 8-10 tonne capacity, finished to required level and grades.

Case - I: Mechanical method using Penetration grade Bitumen and HMP of appropriate capacity not less than 75 tonnes/hour .

Mazdoor working with HMP, road sweeper, paver and roller

Lead =1 km & P&M-

058

Add 10 per cent of cost of carriage to cover cost of loading and unloading

Crushed stone chipping,13.2 mm to 5.6 mm @ 0.27 cum per 10 sqm

Page 103: Standard Data Book - Rate Analysis

Page 14 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Note

5.10 (ii)

Unit = sqm

Taking output = 900 sqm (24.3 cum)

a) Labour

Mate day 0.800 151.44 121.15 L-12

Mazdoor day 18.000 136.69 2460.42 L-13

Mazdoor skilled day 2.000 164.69 329.38 L-15

b) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 6.000 233.00 1398.00 P&M-009

Smooth wheeled steel roller 8-10 tonne hour 6.000 460.00 2760.00 P&M-044

c) Material

Cationic Bitumen Emulsion @ 21.50 kg per 10 sqm tonne 1.940 55145.00 106981.30 M-073

cum 24.300 998.50 24263.55 M-043

d) Overhead charges @ 0.1 on (a+b+c) 13831.38

e) Contractor's profit @ 0.1 on (a+b+c+d) 15214.52

Cost for 900 sqm = a+b+c+d+e 167359.70

Rate per sqm = (a+b+c+d+e)/900 185.96

say 186.00

5.11 512 Close Graded Premix Surfacing/Mixed Seal Surfacing

Case I

Unit = sqm

Taking output = 10250 sqm (205 cum)

a) Labour

Mate day 0.840 151.44 127.21 L-12

day 16.000 136.69 2187.04 L-13

Skilled mazdoor for checking line & levels day 5.000 164.69 823.45 L-15

b) Machinery

i) HMP of appropicate capacity. hour 6.000 23405.00 140430.00 P&M-021

ii) Electric Generator Set 250 KVA hour 6.000 1906.88 11441.25 P&M-081

iii) Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017

iv) Tipper 10 tonne capacity tonne.km 450 x L 2.46 1105.99

110.60

v) Paver finisher hydrostatic with sensor attachment hour 6.000 2674.00 16044.00 P&M-034

iv) Smooth wheeled8-10 tonnes weight hour 6.000 460.00 2760.00 P&M-044

c) Material

Type - A

* Bitumen@ 22 kg per 10 sqm tonne 22.500 55132.00 1240470.00 M-074

cum 276.750 987.00 273152.25 M-041

or

Type - B

If a premix sand seal coat of 'B' type is proposed, the same is required to be provided over the open graded premix carpet immediately on the same day. As the same HMP and other machines will be used for laying of premix sand seal coat, out of 6 effective working hours, 4.00 hours may be utilised for laying of premix carpet and balance 2.00 hours for the seal coat. The rate for the premix sand seal coat under clause 513 (case II) has been worked out accordingly by utilising the HMP for 2.00 hours for the purpose of seal coat. In case type 'A' seal coat is proposed, HMP can be worked for six hours for the premix carpet as type 'A' seal coat does not require the use of HMP.

Case - II: Open-Graded Premix Surfacing using cationic Bitumen Emulsion

Crushed stone aggregates 13.2 mm to 5.6 mm @ 0.27 cum per 10 sqm

Mechanical means using HMP of appropriate capacity not less than 75 tonnes/hour.

Providing, laying and rolling of close-graded premix surfacing material of 20 mm thickness composed of 11.2 mm to 0.09 mm (Type-a) or 13.2 mm to 0.09 mm (Type-b) aggregates using penetration grade bitumen to the required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a Smooth wheeled roller 8-10 tonne capacity, and finishing to required level and grade.

Mazdoor working with HMP, road sweeper, paver and roller

Lead =1 km & P&M-

058

Add 10 per cent of cost of carriage to cover cost of loading and unloading

Stone crushed aggregates 11.2 mm to 0.09 @ 0.27 cum per 10 sqm

Page 104: Standard Data Book - Rate Analysis

Page 15 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Bitumen @ 19 kg per 10 sqm tonne 19.480 55132.00 1073971.36 M-074

cum 276.750 1000.67 276934.50 M-042

d) Overhead charges @ 0.1 on (a+b+c) 169348.78

e) Contractor's profit @ 0.1 on (a+b+c+d) 186283.66

Cost for 10250 sqm = a+b+c+d+e 2049120.22

Rate per sqm = (a+b+c+d+e)/10250 199.91

say 200.00

5.12 513 Seal Coat

Unit = sqm

Taking output = 10250 sqm (92.25 cum)

(i)

a) Labour

Mate day 0.240 151.44 36.35 L-12

Mazdoor day 6.000 136.69 820.14 L-13

b) Machinery

Hydraulic self propelled chip spreader hour 6.000 2635.00 15810.00 P&M-025

Tipper 5.5 cum capacity hour 6.000 339.00 2034.00 P&M-048

Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017

Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 1073.00 6438.00 P&M-004

Smooth wheeled roller 8 -10 tonne weight hour 6.000 460.00 2760.00 P&M-044

c) Material

Bitumen@ 9.80 kg per 10 sqm tonne 10.050 55132.00 554076.60 M-074

cum 92.250 969.00 89390.25 M-050

d) Overhead charges @ 0.1 on (a+b+c) 67620.13

e) Contractor's profit @ 0.1 on (a+b+c+d) 74382.15

Cost for 10250 sqm = a+b+c+d+e 818203.62

Rate per sqm = (a+b+c+d+e)/10250 79.82

say 80.00

Note

5.12 (ii)

Unit = sqm

Taking output = 7858 sqm (47.16 cum)

a) Labour

Mate day 0.160 151.44 24.23 L-12

Mazdoor day 4.000 136.69 546.76 L-13

b) Machinery

HMP of 75 tonnes/hour. hour 2.000 17309.00 34618.00 P&M-022

Electric Generator Set 250 KVA hour 2.000 1906.88 3813.75 P&M-081

Front end loader 1 cum bucket capacity hour 2.000 806.00 1612.00 P&M-017

Tipper 10 tonne capacity tonne.km 104 x 'L' 2.46 255.61

25.56

Paver finisher hydrostatic with sensor attachment hour 2.000 2674.00 5348.00 P&M-034

Smooth wheeled 8-10 tonnes capacity hour 2.000 460.00 920.00 P&M-044

c) Material

Bitumen@ 6.80 kg per 10 sqm tonne 5.340 55132.00 294404.88 M-074

cum 47.160 969.00 45698.04 M-050

d) Overhead charges @ 0.1 on (a+b+c) 38726.68

e) Contractor's profit @ 0.1 on (a+b+c+d) 42599.35

Cost for 7858 sqm = a+b+c+d+e 468592.86

Rate per sqm = (a+b+c+d+e)/7858 59.63

Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27 cum per 10 sqm

* Any one of the alternative may be adopted

Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type A and B seal coats

Case - I : Type A

Crushed stone chipping of 6.7 mm size defined as 100 per cent passing 11.2 mm sieve and retained on 2.36 mm sieve applied @ 0.09 cum per 10 sqm

Since seal coat is provided immediately over the bituminous layers, mechanical broom for clearing has not been catered.

Case - II : Type B

Providing and laying of premix sand seal coat with HMP of appropriate capacity not less than 75 tonnes/ hours using crushed stone chipping 6.7 mm size and penetration bitumen of suitable grade.

Lead =1 km & P&M-

058

Add 10 per cent of cost of carriage to cover cost of loading and unloading

Crushed stone chipping of 6.7 mm size defined as passing 11.2 mm sieve and retained on 2.36 mm sieve applied @ 0.06 cum per 10 sqm

Page 105: Standard Data Book - Rate Analysis

Page 16 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

say 60.00

Note

5.13 514 Supply of Stone Aggregates for Pavement Courses

5.14 515 Mastic Asphalt

Unit = sqm

a) Labour

Mate day 0.440 151.44 66.63 L-12

Mazdoor day 10.000 136.69 1366.90 L-13

Mazdoor skilled day 1.000 164.69 164.69 L-15

b) Machinery

Mechanical broom @ 1250 sqm per hour hour 0.060 357.00 21.42 P&M-031

Air compressor 250 cfm hour 0.060 319.00 19.14 P&M-001

Mastic cooker 1 tonne capacity hour 6.000 62.00 372.00 P&M-030

Bitumen boiler 1500 litres capacity hour 6.000 198.00 1188.00 P&M-005

hour 1.000 282.50 282.50 P&M-053

c) Material

Base mastic (without coarse aggregates) = 60 per cent

Coarse aggregate (6.3mm to 13.2 mm) = 40 per cent .

tonne 0.204 55132.00 11246.93 M-074

cum 0.390 476.80 185.95 M-021

tonne 0.360 4500.00 1620.00 M-188

cum 0.550 998.50 549.18 M-043

cum 0.018 1213.00 21.83 M-142

kg 0.500 55.00 27.50 M-074

d) Overhead charges @ 0.1 on (a+b+c) 1713.27

e) Contractor's profit @ 0.1 on (a+b+c+d) 1884.59

Cost for 35.00 sqm = a+b+c+d+e 20730.53

Rate per sqm = (a+b+c+d+e)/35 592.30

Since seal coat is required to be provided over the premix carpet on the same day, out of the 6 working hours of the HMP, 4.00 hours are proposed to be utilised for the premix carpet and the balance 2.00 hours for the seal coat. Hence 2.00 hours have been considered for this case. This may be linked to rate analysis worked out under clause 511.

Supply of stone aggregates from approved sources conforming to the physical requirement, specified in the respective specified clauses, including royalties, fees rents, collection, transportation, stacking and testing and measured in cum as per clause 514.5

Competitive market rates to be as certained. Alternatively, rates for stone crushing given in chapter 1may be adopted, if found economical. In case for supply of aggregates at site are not available, nearest crusher site may be as certained. Loading and un-loading charges and cost of carriage may be added to these rates to arrive at the cost at site.

Providing and laying 25 mm thick mastic asphalt wearing course with paving grade bitumen meeting the requirements given in table 500-29, prepared by using mastic cooker and laid to required level and slope after cleaning the surface, including providing antiskid surface with bitumen precoated finegrained hard stone chipping of 13.2 mm nominal size at the rate of 0.005cum per 10 sqm and at an approximate spacing of 10 cm center to center in both directions, pressed into surface when the temperature of surfaces is not less than 1000C, protruding 1 mm to 4 mm over mastic surface, all complete as per clause 515.

Taking output = 35.00 sqm (0.87 cum ) assuming a density of 2.3 tonnes/cum.-2 tonnes

Tractor for towing and positioning of mastic cooker and bitumen boiler

Proportion of material required for mastic asphalt with coarse aggregates (based on mix design done by CRRI for a specific case)

I) Bitumen 85/25 or 30/40 @ 10.2 per cent by weight of mix. 2 x 10.2/100 = 0.204

ii) Fine aggregate passing 2.36mm and retained on 0.075mm sieve @ 31.9 per cent by weight of mix = 2 x 31.9/100 = 0.638 tonnes = 0.638/1.625 = 0.39

iii) Lime stone dust filler with calcium content not less than 80 per cent by weight @ 17.92 per cent by weight of mix = 2 x 17.92/100 = 0.36

iv) Coarse aggregates 6.3 mm to 13.2 mm @ 40 per cent by weight of mix = 2 x 40/100 = 0.8 MT = 0.8/1.456 = 0.55

v) Pre-coated stone chips of 13.2 mm nominal size for skid resistance = 35 x 0.005/10 = 0.018

vi) Bitumen for coating of chips @ 2 per cent by weight = 0.018 x 1.456 x 2/100 = 0.0005 MT = 0.5kg

Page 106: Standard Data Book - Rate Analysis

Page 17 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

say 592.00

Note 1.The rates for 50 mm & 40 mm thick layers may be worked out on pro-rata basis.

2.Where tack coat is required to be provided before laying mastic asphalt, the same is required to be measured and paid separately.

3.The quantities of binder, filler and aggregates are for estimating purpose. Exact quantities shall be as per mix design.

4.This rate analysis is based on design made by CRRI for a specific case and is meant for estimating purposes only. Actual design is required to be done for each case.

Page 107: Standard Data Book - Rate Analysis

Page 18 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

5.15 516 Slurry Seal

512

(i) 5 mm thickness

Unit = sqm

Taking output = 16000 sqm (80 cum)

Taking density of 2.2 tonnes per cum

weight of mix = 176 tonnes

a) Labour

Mate day 0.240 151.44 36.35 L-12

Mazdoor day 6.000 136.69 820.14 L-13

b) Machinery

Mechanical broom hour 6.000 357.00 2142.00 P&M-031

Air compressor 250 cfm hour 6.000 319.00 1914.00 P&M-001

Mobile slurry seal equipment hour 6.000 1008.00 6048.00 P&M-033

Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017

hour 6.000 339.00 2034.00 P&M-048

hour 6.000 1243.00 7458.00 P&M-037

Water tanker6 KL capacity hour 2.000 200.00 400.00 P&M-060

c) Material

Residual Binder @ 11 per cent of mix 80 x 2.2 x 0.11 tonne 19.360 49915.00 966354.40 M-077

cum 102.080 1066.89 108908.13 M-030

tonne 3.520 5000.00 17600.00 M-188

Cost of water KL 12.000 10.00 120.00 M-189

d) Overhead charges @ 0.1 on (a+b+c) 111867.10

e) Contractor's profit @ 0.1 on (a+b+c+d) 123053.81

Cost for 16000 sqm = a+b+c+d+e 1353591.93

Rate per sqm = (a+b+c+d+e)/16000 84.60

Add 1 % labour Cess 0.85

85.45

say 85.45

Providing and laying slurry seal consisting of a mixture of fine aggregates, portland cement filler, bituminous emulsion and water on a road surface including cleaning of surface, mixing of slurry seal in a suitable mobile plant, laying and compacting to provide even riding surface

Tipper 5.5 cum capacity for carriage of aggregate from stockpile on road side to slurry equipment, bitumen emulsion and filler.

Pneumatic tyred roller with individual wheel load not exceeding 1.5 tonnes

Fine aggregate 4.75 mm and below 87 per cent of total mix,80 x 2.2 x 0.87 = 153.12 tonnes. Taking density1.5, = 153.12/1.5 = 102.08 cum

Filler (ordinary Portland Cement) @ 2 per cent of total mix = 80 x 2.2 x 0.02

Page 108: Standard Data Book - Rate Analysis

Page 19 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

5.15 (ii) 3 mm thickness

Unit = sqm

Taking output = 20000 sqm (60 cum)

a) Labour

Mate day 0.200 151.44 30.29 L-12

Mazdoor day 5.000 136.69 683.45 L-13

b) Machinery

Mechanical broom hour 6.000 357.00 2142.00 P&M-031

Air compressor 250 cfm hour 6.000 319.00 1914.00 P&M-001

Mobile slurry seal equipment hour 6.000 1008.00 6048.00 P&M-033

Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017

hour 6.000 339.00 2034.00 P&M-048

Water tanker6 KL capacity hour 2.000 200.00 400.00 P&M-060

c) Material

tonne 17.160 49915.00 856541.40 M-077

cum 74.800 867.00 64851.60 M-022

Filler @ 2 per cent of total mix = 60x 2.2 x 0.02 tonne 2.640 4500.00 11880.00 M-188

Cost of water KL 12.000 10.00 120.00 M-189

d) Overhead charges @ 0.1 on (a+b+c) 95148.07

e) Contractor's profit @ 0.1 on (a+b+c+d) 104662.88

Cost for 30000 sqm = a+b+c+d+e 1151291.69

Rate per sqm = (a+b+c+d+e)/20000 57.56

say 58.00

5.15 (iii) 1.5 mm thickness

Unit = sqm

Taking output = 24000 sqm (36 cum)

a) Labour

Mate day 0.200 151.44 30.29 L-12

Mazdoor day 5.000 136.69 683.45 L-13

b) Machinery

Mechanical broom hour 6.000 357.00 2142.00 P&M-031

Air compressor 250 cfm hour 6.000 319.00 1914.00 P&M-001

Mobile slurry seal equipment hour 6.000 1008.00 6048.00 P&M-033

Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017

hour 6.000 339.00 2034.00 P&M-048

Water tanker6 KL capacity hour 2.000 200.00 400.00 P&M-060

c) Material

Residual Binder @ 16 per cent of mix, 36 x 2.2 x 0.16 tonne 12.670 49915.00 632423.05 M-077

cum 43.300 867.00 37541.10 M-022

Filler @ 2 per cent of total mix = 36x 2.2 x 0.02 tonne 1.580 4500.00 7110.00 M-188

Cost of water KL 12.000 10.00 120.00 M-189

d) Overhead charges @ 0.1 on (a+b+c) 69528.19

e) Contractor's profit @ 0.1 on (a+b+c+d) 76481.01

Cost for 24000 sqm = a+b+c+d+e 841291.08

Rate per sqm = (a+b+c+d+e)/24000 35.05

say 35.00

Note

Tipper 5.5 cum capacity for carriage of aggregate from stockpile on road side to slurry equipment, bitumen emulsion and filler

Residual Binder @ 13 per cent of mix = 60 x 2.2 x 0.13

Fine aggregate 3 mm and below 85 per cent of total mix, 60x 2.2 x 0.85 = 112.2 tonnes. Taking density 1.5,

Tipper 5.5 cum capacity for carriage of aggregate from stockpile on road side to slurry equipment, bitumen emulsion and filler.

Fine aggregate 2.36 mm and below,82 per cent of total mix,36x 2.2 x 0.82 = 64.94 tonnes. Taking density 1.5

1.Tack coat, if required to be provided, before laying slurry seal may be measured and paid separately

Page 109: Standard Data Book - Rate Analysis

Page 20 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

5.16 517

Unit = cum

Taking output = 120 cum (276 tonnes)

a) Labour

Mate day 0.480 151.44 72.69 L-12

Mazdoor day 10.000 136.69 1366.90 L-13

Mazdoor skilled day 2.000 164.69 329.38 L-15

b) Machinery

Cold milling machine @ 20 cum per hour hour 6.000 300.00 1800.00 P&M-069

Mechanical broom @ 1250 sqm per hour hour 1.280 357.00 456.96 P&M-031

Air compressor 250 cfm hour 1.280 319.00 408.32 P&M-001

Bitumen pressure distributor @ 1750 sqm per hour hour 0.910 1073.00 976.43 P&M-004

hour 3.000 23405.00 70215.00 P&M-021

Electric generator set 250 KVA hour 3.000 1906.88 5720.63 P&M-081

Front end loader 1.00 cum bucket capacity hour 3.000 806.00 2418.00 P&M-017

Tipper 5.5 cum capacity hour 18.000 339.00 6102.00 P&M-048

Smooth wheeled roller 8-10 tonnes hour 3.00x0.65* 460.00 897.00 P&M-044

Vibratory roller 8 tonnes hour 3.00x0.65* 1541.00 3004.95 P&M-059

Smooth wheeled tandem roller 6-8 tonnes hour 3.00x0.65* 1144.00 2230.80 P&M-045

c) Material

i) Bitumen

tonne 1.987 55132.00 109558.31 M-074

tonne 7.728 55132.00 426060.10 M-074

ii) Aggregates

Percentage of mix requiring fresh aggregates - 70 per cent

Weight of fresh mix = 276 x 0.70 = 193.2 tonne

Size wise requirement of fresh aggregates

37.5 - 25 mm @ 23 per cent cum 28.440 1011.94 28779.57 M-049

25 - 10 mm @ 15 per cent cum 18.550 1103.60 20471.78 M-046

10- 5 mm @ 20 per cent cum 24.730 1078.94 26682.19 M-040

Below 5 mm @40 per cent cum 49.460 992.30 49079.16 M-030

Filler (cement) @ 2 per cent = 5.52tonnes of 276 tonne tonne 5.520 5000.00 27600.00 M-081

d) Overhead charges @ 0.1 on (a+b+c) 78423.02

e) Contractor's profit @ 0.1 on (a+b+c+d) 86265.32

Cost for 120 cum of DBM = a+b+c+d+e 948918.49

Rate per cum = (a+b+c+d+e)/120 7907.65

say 7908.00

Note

5.17 518 Fog Spray

Recycling of Bituminous Pavement with Central Recycling Plant

Recycling pavement by cold milling of existing bituminous layers, planning the surface after cold milling, reclaiming excavated material to the extent of 30 per cent of the required quantity, hauling and stock piling the reclaimed material near the central recycling plant after carrying out necessary checks and evaluation, adding fresh material including rejuvenators as required, mixing in a hot mix plant, transporting and laying at site and compacting to the required grade, level and thickness, all as specified in clause 517.

Hot mix plant 100-120 TPH producing an average of 75 tonnes per hour

A bitumen content is 4.5 per cent bitumen weight of mix. For reclaimed material, fresh bitumen will be required to the extent of 60 per cent of normal requirement.

In a mix of 276 tonnes, 82.8 tonne is reclaimed and balance 193.2 tonne is fresh mix.

Bitumen required for reclaimed mix of 82.8 tonne @ 60 per cent = 82.8 x 0.60 x0.04 = 1.99

Bitumen required for fresh mix of 193.2 tonnes = 193.2 x 0.04 = 7.73

Weight of fresh aggregate in the mix = 193.2 x 0.96 = 185.47 tonne

Taking average density of 1.5 tonnes/cum, total volume of aggregate = 123.65 cum.

Although the total rolling time is only 4 hours as per norms, all the three rollers have to be available at site for 3 hours each to match with the output of re-cycling plant. To cater for their idling time, these have been multiplied with a factor of 0.65.

Providing and applying low viscosity bitumen emulsion for sealing cracks less than 3 mm wide or incipient fretting or disintegration in an existing bituminous surfacing.

Page 110: Standard Data Book - Rate Analysis

Page 21 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Unit = sqm

Taking output = 10500 sqm

a) Labour

Mate day 0.120 151.44 18.17 L-12

Mazdoor day 3.000 136.69 410.07 L-13

b) Machinery

Mechanical broom @ 1250 sqm per hour hour 6.000 357.00 2142.00 P&M-031

Air compressor 250 cfm hour 6.000 319.00 1914.00 P&M-001

tonne 6.000 1073.00 6438.00 P&M-004

c) Material

Bitumen emulsion @ 0.75 kg per sqm tonne 7.880 49915.00 393330.20 M-077

d) Overhead charges @ 0.1 on (a+b+c) 40425.24

e) Contractor's profit @ 0.1 on (a+b+c+d) 44467.77

Cost for 10500 sqm = a+b+c+d+e 489145.46

Rate per sqm = (a+b+c+d+e)/10500 46.59

say 47.00

a) Labour

Mate day 0.160 151.44 24.23 L-12

Mazdoor for precoating of grit day 4.000 136.69 546.76 L-13

b) Material

Crushed stone grit 3 mm size @ 3.75 kg per sqm cum 26.250 867.00 22758.75 M-024

tonne 0.790 49915.00 39432.85 M-077

62762.59

5.98

say 6.00

5.18 519 Bituminous Cold Mix ( Including Gravel Emulsion)

Unit = cum

Taking output = 205 cum (450 tonne)

(i)

Bitumen Emulsion 8 per cent

Filler2 per cent

Total aggregates 90 per cent

Proportion of aggregates

19 mm to 9.5 mm25 per cent

9.5 mm to 6 mm29 per cent

6 mm to 0.075 mm 36 per cent

a) Labour

Mate day 0.840 151.44 127.21 L-12

Mazdoor day 16.000 136.69 2187.04 L-13

Mazdoor skilled day 5.000 164.69 823.45 L-15

b) Machinery

hour 6.000 3661.20 21967.20 P&M-077

Electric generator 125 KVA hour 6.000 652.00 3912.00 P&M-018

Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017

Tipper 10 tonne capacity tonne.km 450 x L 2.46 1105.99

110.60

Paver finisher hour 6.000 2674.00 16044.00 P&M-034

Pneumatic tyred roller 12-15 tonnes hour 6.00x0.65* 1243.00 4847.70 P&M-037

Smooth wheeled steel tandem roller 6-8 tonnes hour 6.00x0.65* 1144.00 4461.60 P&M-045

c) Material

Bitumen emulsion @ 8 per cent tonne 36.000 49915.00 1796940.00 M-077

Bitumen emulsion pressure distributor @ 1750 sqm per hour

1.In case it is decided by the engineer to blind the fog spray, the following may be added

Bitumen emulsion for precoating grit @ 2 per cent of grit,39.38 x 0.02

Providing, laying and rolling of bituminous cold mix on prepared base consisting of a mixture of unheated mineral aggregate and emulsified or cutback bitumen, including mixing in a plant of suitable type and capacity, transporting, laying, compacting and finishing to specified grades and levels.

Using bitumen emulsion and 9.5 mm or 13.2 mm size aggregate

Composition of mix (450 tonne) is assumed to be as under:-

By weight of total mix

Drum mix plant for cold mixes of appropriate capacity but not less than 75 tonnes/hour.

Lead =1 km & P&M-

058

Add 10 per cent of cost of carriage to cover cost of loading and unloading

Page 111: Standard Data Book - Rate Analysis

Page 22 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Filler (lime)@ 2 per cent tonne 9.000 4500.00 40500.00 M-188

Aggregates size 19 to 9.5 mm - 450 x 0.25 x 1/1.5 cum 75.000 1103.60 82770.00 M-045

Aggregates size 9.5 to 6 mm - 450 x 0.29 x 1/1.5 cum 87.000 1078.94 93867.78 M-040

Aggregates size 6 to 0.075 mm - 450 x 0.36 x 1/1.5 cum 108.000 992.30 107168.40 M-030

d) Overhead charges @ 0.1 on (a+b+c) 218166.90

e) Contractor's profit @ 0.1 on (a+b+c+d) 239983.59

Cost for 205 cum = a+b+c+d+e 2639819.45

Rate per cum = (a+b+c+d+e)/205 12877.17

say 12877.00

(Applicable to cases I to IV)

Note 1.Density of aggregates has been assumed 1.5 gms/cc

5.18 (ii)

Bitumen Emulsion 8 per cent

Filler2 per cent

Total aggregates 90 per cent

Proportion of aggregates

37.5 mm to 19 mm25 per cent

19 mm to 6 mm 30 per cent

6 mm to 0.075 mm 35 per cent

a) Labour

Mate day 0.840 151.44 127.21 L-12

Mazdoor day 16.000 136.69 2187.04 L-13

Mazdoor skilled day 5.000 164.69 823.45 L-15

b) Machinery

hour 6.000 3661.20 21967.20 P&M-077

Electric generator 125 KVA hour 6.000 652.00 3912.00 P&M-018

Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017

Tipper 10 tonne capacity tonne.km 450 x L 2.46 1105.99

110.60

Paver finisher hour 6.000 2674.00 16044.00 P&M-034

Pneumatic tyred roller 12-15 tonnes hour 6.00x0.65* 1243.00 4847.70 P&M-037

Smooth wheeled steel tandom roller 6-8 tonnes hour 6.00x0.65* 1144.00 4461.60 P&M-045

c) Material

Bitumen emulsion @ 8 per cent tonne 36.000 49915.00 1796940.00 M-077

Filler (lime)@ 2 per cent tonne 9.000 4500.00 40500.00 M-188

Aggregates size 37.5 to 19 mm - 450 x 0.25 x 1/1.5 cum 75.000 956.33 71725.00 M-048

Aggregates size 19 to 6 mm - 450 x 0.3 x 1/1.5 cum 90.000 1000.67 90060.00 M-047

Aggregates size 6 to 0.075 mm - 450 x 0.35 x 1/1.5 cum 105.000 992.30 104191.50 M-030

d) Overhead charges @ 0.1 on (a+b+c) 216383.93

e) Contractor's profit @ 0.1 on (a+b+c+d) 238022.32

Cost for 205 cum = a+b+c+d+e 2618245.54

Rate per cum = (a+b+c+d+e)/205 12771.93

say 12772.00

Note 1.Density of aggregates has been assumed 1.5 gms/cc

5.18 (iii)

2. Tack coat where provided will be measured and paid separately.

*3. Though the rollers are required only for 3.5 hours each as per norms of output, but these are required to be available at site for 6 hours as the drum mix plant and the paver would take 6 hours for mixing and paving. To cater for the idle period, their usage rates have been multiplied by a factor of 0.65

Using bitumen emulsion and 19 mm or 26.5 mm nominal size aggregate

Composition of mix (450 tonne) is assumed to be as under:-

Drum mix plant for cold mixes 60-90 tonne per hour producing average output of 75 tonnes per hour

Lead =1 km & P&M-

058

Add 10 per cent of cost of carriage to cover cost of loading and unloading

2. Tack coat where provided will be measured and paid separately.

*3. Though the rollers are required only for 3.5 hours each as per norms of output, but these are required to be available at site for 6 hours as the drum mix plant and the paver would take 6 hours for mixing and paving. To cater for the idle period, their usage rates have been multiplied by a factor of 0.65

Using cutback bitumen and 9.5 mm or 13.2 mm nominal size aggregate

Page 112: Standard Data Book - Rate Analysis

Page 23 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Cutback bitumen 5 per cent

Filler (lime) 2 per cent

Total aggregates 93 per cent

Proportion of aggregates

19 mm to 9.5 mm26 per cent

9.5 mm to 6 mm31 per cent

6 mm to 0.075 mm 36 per cent

a) Labour

Mate day 0.840 151.44 127.21 L-12

Mazdoor day 16.000 136.69 2187.04 L-13

Mazdoor skilled day 5.000 164.69 823.45 L-15

b) Machinery

hour 6.000 3661.20 21967.20 P&M-077

Electric generator 125 KVA hour 6.000 652.00 3912.00 P&M-018

Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017

Tipper 10 tonne capacity tonne.km 450 x L 2.46 1105.99

110.60

Paver finisher hour 6.000 2674.00 16044.00 P&M-034

Pneumatic tyred roller 12-15 tonnes hour 6.00x0.65* 1243.00 4847.70 P&M-037

Smooth wheeled steel tandem roller 6-8 tonnes hour 6.00x0.65* 1144.00 4461.60 P&M-045

c) Material

Cutback bitumen @ 5 per cent tonne 22.500 47937.00 1078582.50 M-076

Filler (lime)@ 2 per cent tonne 9.000 4500.00 40500.00 M-188

Aggregates size 19 to 9.5 mm - 450 x 0.26 x 1/1.5 cum 78.000 1103.60 86080.80 M-045

Aggregates size 9.5 to 6 mm - 450 x 0..31 x 1/1.5 cum 93.000 1078.94 100341.42 M-040

Aggregates size 6 to 0.075 mm - 450 x 0.36 x 1/1.5 cum 108.000 992.30 107168.40 M-030

d) Overhead charges @ 0.1 on (a+b+c) 147309.59

e) Contractor's profit @ 0.1 on (a+b+c+d) 162040.55

Cost for 205 cum = a+b+c+d+e 1782446.05

Rate per cum = (a+b+c+d+e)/205 8694.86

say 8695.00

Note 1.Density of aggregates has been assumed 1.5 gms/cc

5.18 (iv)

Cutback bitumen 5 per cent

Filler2 per cent

Total aggregates 93 per cent

Proportion of aggregates

37.5 mm to 19 mm25 per cent

19 mm to 6 mm 30 per cent

6 mm to 0.075 mm 38 per cent

a) Labour

Mate day 0.840 151.44 127.21 L-12

Mazdoor day 16.000 136.69 2187.04 L-13

Mazdoor skilled day 5.000 164.69 823.45 L-15

b) Machinery

hour 6.000 3661.20 21967.20 P&M-077

Electric generator 125 KVA hour 6.000 652.00 3912.00 P&M-018

Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017

Tipper 10 tonne capacity tonne.km 450 x L 2.46 1105.99

Composition of mix (450 tonne) is assumed to be as under:-

Drum mix plant for cold mixes 60-90 tonne per hour producing average output of 75 tonnes per hour

Lead =1 km & P&M-

058

Add 10 per cent of cost of carriage to cover cost of loading and unloading

2. Tack coat where provided will be measured and paid separately.

*3. Though the rollers are required only for 3.5 hours each as per norms of output, but these are required to be available at site for 6 hours as the drum mix plant and the paver would take 6 hours for mixing and paving. To cater for the idle period, their usage rates have been multiplied by a factor of 0.65

Using cutback bitumen and 19 mm or 26.5 mm nominal size aggregate

Composition of mix (450 tonne) is assumed to be as under:-

Drum mix plant for cold mixes 60-90 tonne per hour producing output of 75 tonnes per hour

Lead =1 km & P&M-

058

Page 113: Standard Data Book - Rate Analysis

Page 24 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

110.60

Paver finisher hour 6.000 2674.00 16044.00 P&M-034

Pneumatic tyred roller 12-15 tonnes. hour 6.00x0.65* 1243.00 4847.70 P&M-037

Smooth wheeled steel tandem roller 6-8 tonnes hour 6.00x0.65* 1144.00 4461.60 P&M-045

c) Material

Cutback bitumen on @ 5 per cent tonne 22.500 47937.00 1078582.50 M-076

Filler (lime)@ 2 per cent tonne 9.000 4500.00 40500.00 M-188

Aggregates size 37.5 to 19 mm - 450 x 0.25 x 1/1.5 cum 75.000 956.33 71725.00 M-048

Aggregates size 19 to 6 mm - 450 x 0.3 x 1/1.5 cum 90.000 1000.67 90060.00 M-047

Aggregates size 6 to 0.075 mm - 450 x0.38 x 1/1.5 cum 114.000 992.30 113122.20 M-030

d) Overhead charges @ 0.1 on (a+b+c) 145441.25

e) Contractor's profit @ 0.1 on (a+b+c+d) 159985.37

Cost for 205 cum = a+b+c+d+e 1759839.11

Rate per cum = (a+b+c+d+e)/205 8584.58

say 8585.00

Note 1.Density of aggregates has been assumed 1.5 gms/cc

5.19 520 Sand Asphalt Base Course

Unit = cum

Taking output = 205 cum (450 tonne)

a) Labour

Mate day 0.840 151.44 127.21 L-12

Mazdoor day 16.000 136.69 2187.04 L-13

Mazdoor skilled day 5.000 164.69 823.45 L-15

b) Machinery

hour 6.000 13842.00 83052.00 P&M-023

Electric generator set 250 KVA hour 6.000 1906.88 11441.25 P&M-081

Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017

Tipper 10 tonne capacity tonne.km 450 x L 2.46 1105.99

110.60

Paver finisher hour 6.000 2674.00 16044.00 P&M-034

hour 6.00x0.65 460.00 1794.00 P&M-044

Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65 1541.00 6009.90 P&M-059

hour 6.00x0.65 1144.00 4461.60 P&M-045

c) Material

Density 2.20 tonne per cum

Weight450 tonne

Bitumen5 per cent

Filler2 per cent

Sand of size 4.75 to 0.075 mm 93 per cent

Bitumen@ 5 per cent tonne 22.500 55132.00 1240470.00 M-074

Filler (lime)@ 2 per cent tonne 9.000 4500.00 40500.00 M-188

Sand of size 4.75 to 0.075 mm - 450 x 0.93 x 1/1.5 cum 288.620 828.00 238977.36 M-004

d) Overhead charges @ 0.1 on (a+b+c) 165194.04

e) Contractor's profit @ 0.1 on (a+b+c+d) 181713.44

Cost for 205 cum = a+b+c+d+e 1998847.88

Rate per cum = (a+b+c+d+e)/205 9750.48

Add 10 per cent of cost of carriage to cover cost of loading and unloading

2. Tack coat where provided will be measured and paid separately.

*3. Though the rollers are required only for 3.5 hours each as per norms of output, but these are required to be available at site for 6 hours as the drum mix plant and the paver would take 6 hours for mixing and paving. To cater for the idle period, their usage rates have been multiplied by a factor of 0.65

Providing, laying and rolling sand-asphalt base course composed of sand, mineral filler and bituminous binder on a prepared sub-grade or sub-base to the lines, levels, grades and cross sections as per the drawings including mixing in a plant of suitable type and capacity, transporting, laying, compacting and finishing.

Hot Mix Plant of appropriate capacity but not less than 75 tonnes/hour

Lead =1 km & P&M-

058

Add 10 per cent of cost of carriage to cover cost of loading and unloading

smooth wheeled roller 8-10 tonnes for initial break down rolling.

Finish rolling with 6-8 tonnes smooth wheeled tandom rollers.

Composition of mix (450 tonne) is assumed to be as under:-

Page 114: Standard Data Book - Rate Analysis

Page 25 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

say 9750.00

Note 1. Tack coat will be measured and paid separately

5.20 521 Modified Binder

Unit = tonne

Note `

5.21 522 Crack Prevention Courses

(i)

2. Although the rollers are required only for 3 hours as per norms of output, but the same have to be available at site for six hours as the hot mix plant and paver will take six hours for mixing and paving the output of 450 tonnes considered in this analysis. To cater for the idle period of this roller, their usage rates has been multiplied by a factor of 0.65

Supply of modified binder produced by mixing bitumen with modifier such as natural rubber or crumb rubber or any other polymer found compatible with bitumen and which allows properties given in clause 521.3 and IRC:SP: 53 blending of modifier with bitumen to be done either at the refinery or at central unit with all facilities by proper industrial process, is essential.

The use of modified binder is expected to result in an extended service life of bituminous pavements subject to heavy traffic loads in extreme climatic conditions, thus justifying the entire cost of adding modifiers/fibres. Other advantages include lower temperature susceptibility, higher resistance to aging, higher fatigue life, higher resistance to cracking and better adhesion between aggregates and binder.

Detailed information and inductive dose level on the use of polymer modified binder is available in IRC : SP-53 / 2002. A number of proprietary products are now available in the market. For such proprietary products, test reports and cost effectiveness should be the basis for their selection in road works.

The modifier, in the required quantity shall be blended at the refinery or at central unit with all facilities by proper industrial process, is essential. If supplied in drums it shall be agitated in melted condition with suitable device for achieving homogeneity

Proposals to use glass fibre, polypropylene fibres or any other similar material in a bituminous mixture should be substantiated, complete with all details including test results, manufacturer's recommendations for addition or means of incorporating the fibres, homogeneously, without segregation, into the mixture.

Before agreeing to the use of a fibre, it should have been proved to be satisfactory in use under circumstances, similar to the work, elsewhere or it would have under gone appropriate performance trials. Documented evidence of use and trials of the fibre, in any country having conditions similar to Indian will be acceptable.

where information on use of trials is inadequate or lacking, trials may be required to be under taken before agreeing to the use of the fibre.

1. The modified binder is usually manufactured by specialised firms as a proprietary product. The rate for this product is required to be as certained from the market.

2.The specifications for various item of road works using polymer/rubber modified bitumens are same as those for penetration grade bitumen except those for any special conditions which the manufacturer may indicate

3.The other controls during mixing, laying shall be same as specified in IRC - 14, 29, 94 and 95 for open graded premix carpet, bituminous concrete, DBM and SDBC respectively

4.The temperature of mixing and rolling will be slightly higher than conventional bituminous mixes as indicated in Table 8 of IRC: SP: 53 - 2002

Stress absorbing membrane (SAM) crack width less than 6 mm

Providing and laying of a stress absorbing membrane over a cracked road surface, with crack width below 6 mm after cleaning with a mechanical broom, using modified binder complying with clause 521, sprayed at the rate of 9 kg per 10 sqm and spreading 5.6 mm crushed stone aggregates @ 0.11 cum per 10 sqm with hydraulic chip spreader, sweeping the surface for uniform spread of aggregates and surface finished to conform to clause 902.

Page 115: Standard Data Book - Rate Analysis

Page 26 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Unit = sqm

Taking output = 10500 sqm

a) Labour

Mate day 0.240 151.44 36.35 L-12

Mazdoor day 6.000 136.69 820.14 L-13

b) Machinery

Mechanical broom @ 1250 sqm per hour hour 6.000 357.00 2142.00 P&M-031

Air compressor 250 cfm hour 6.000 319.00 1914.00 P&M-001

Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 1073.00 6438.00 P&M-004

Hydraulic Chip spreader hour 6.000 2635.00 15810.00 P&M-025

Smooth wheeled road roller 8-10 tonne hour 6.000 460.00 2760.00 P&M-044

c) Material

Modified binder tonne 9.450 38740.00 366093.00 M-078

Crushed stone aggregates 5.6 mm size cum 105.000 969.00 101745.00 M-050

d) Overhead charges @ 0.1 on (a+b+c) 49775.85

e) Contractor's profit @ 0.1 on (a+b+c+d) 54753.43

Cost for 10500 sqm = a+b+c+d+e 602287.77

Rate per sqm = (a+b+c+d+e)/10500 57.36

say 57.00

5.21 (ii)

Unit = sqm

Taking output = 10500 sqm

a) Labour

Mate day 0.240 151.44 36.35 L-12

Mazdoor day 6.000 136.69 820.14 L-13

b) Machinery

Mechanical broom @ 1250 sqm per hour hour 6.000 357.00 2142.00 P&M-031

Air compressor 250 cfm capacity hour 6.000 319.00 1914.00 P&M-001

Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 1073.00 6438.00 P&M-004

Hydraulic Chip spreader hour 6.000 2635.00 15810.00 P&M-025

Smooth wheeled road roller 8-10 tonne hour 6.000 460.00 2760.00 P&M-044

c) Material

Modified binder tonne 11.550 38740.00 447447.00 M-078

Crushed stone chipping 11.2 mm size cum 105.000 1005.00 105525.00 M-051

d) Overhead charges @ 0.1 on (a+b+c) 58289.25

e) Contractor's profit @ 0.1 on (a+b+c+d) 64118.17

Cost for 10500 sqm = a+b+c+d+e 705299.91

Rate per sqm = (a+b+c+d+e)/10500 67.17

say 67.00

5.21 (iii)

Unit = sqm

Taking output = 10500 sqm

a) Labour

Mate day 0.240 151.44 36.35 L-12

Mazdoor day 6.000 136.69 820.14 L-13

Mazdoor skilled day 2.000 164.69 329.38 L-15

b) Machinery

Mechanical broom @ 1250 sqm per hour hour 6.000 357.00 2142.00 P&M-031

Air compressor 250 cfm capacity hour 6.000 319.00 1914.00 P&M-001

Stress absorbing membrane (SAM) with crack width 6 mm to 9 mm

Providing and laying of a stress absorbing membrane over a cracked road surface, with crack width 6 to 9 mm after cleaning with a mechanical broom, using modified binder complying with clause 521, sprayed at the rate of 11 kg per 10 sqm and spreading 11.2 mm crushed stone aggregates @ 0.12 cum per 10 sqm, sweeping the surface for uniform spread of aggregates and surface finished to conform to clause 902.

Stress absorbing membrane (SAM) crack width above 9 mm and cracked area above 50 per cent

Providing and laying a single coat of a stress absorbing membrane over a cracked road surface, with crack width above 9 mm and cracked area above 50 per cent after cleaning with a mechanical broom, using modified binder complying with clause 521, sprayed at the rate of 15 kg per 10 sqm and spreading 11.2 mm crushed stone aggregates @ 0.12 cum per 10 sqm, sweeping the surface for uniform spread of aggregates and surface finished to conform to clause 902.

Page 116: Standard Data Book - Rate Analysis

Page 27 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 1073.00 6438.00 P&M-004

Hydraulic Chip spreader hour 6.000 2635.00 15810.00 P&M-025

Smooth wheeled road roller 8-10 tonne hour 6.000 460.00 2760.00 P&M-044

c) Material

Modified binder tonne 15.750 38740.00 610155.00 M-078

Crushed stone aggregates 11.2 mm size cum 126.000 1005.00 126630.00 M-051

d) Overhead charges @ 0.1 on (a+b+c) 76703.49

e) Contractor's profit @ 0.1 on (a+b+c+d) 84373.84

Cost for 10500 sqm = a+b+c+d+e 928112.19

Rate per sqm = (a+b+c+d+e)/10500 88.39

say 88.00

Note

5.21 (iv) Case - IV : Bitumen impregnated geotextile

Unit = sqm

Taking output = 3500 sqm

a) Labour

Mate day 0.560 151.44 84.81 L-12

Mazdoor day 12.000 136.69 1640.28 L-13

Mazdoor skilled day 2.000 164.69 329.38 L-15

b) Machinery

Mechanical broom @ 1250 sqm per hour hour 2.800 357.00 999.60 P&M-031

Air compressor 250 cfm capacity hour 2.800 319.00 893.20 P&M-001

Bitumen pressure distributor @ 1750 sqm per hour tonne 2.000 1073.00 2146.00 P&M-004

Pneumatic roller hour 2.000 1243.00 2486.00 P&M-037

c) Material

tonne 3.680 56122.00 206528.96 M-075

Geotextile including 10 per cent for overlaps sqm 3850.000 37.25 143412.50 M-108

d) Overhead charges @ 0.1 on (a+b+c) 35852.07

e) Contractor's profit @ 0.1 on (a+b+c+d) 39437.28

Cost for 10500 sqm = a+b+c+d+e 433810.08

Rate per sqm = (a+b+c+d+e)/3500 123.95

say 124.00

NOTE

5.22 519.3 Recipe Cold Mix

Unit = cum

Taking output = 205 cum (450 tonnes)

(i) 75 mm thickness

a) Labour

Mate day 1.000 151.44 151.44 L-12

Mazdoor day 12.000 136.69 1640.28 L-13

Mazdoor skilled day 5.000 164.69 823.45 L-15

b) Machinery

hour 6.000 25594.50 153567.00 P&M-064

Electric generator 125 KVA hour 6.000 652.00 3912.00 P&M-018

Front end loader 1 cum capacity hour 6.000 806.00 4836.00 P&M-017

hour 6.000 2674.00 16044.00 P&M-034

In case 2nd coat is also required to be provided, material provided for the 2nd coat shall be as per table 500-47.

Providing and laying a bitumen impregnated geotextile layer after cleaning the road surface, geotextile conforming to requirements of clause 703.3, laid over a tack coat with 1.05 kg per sqm of paving grade bitumen 80 - 100 penetration and constructed to the requirement of clause 703.4.5

Paving grade bitumen of 80 - 100 penetration @ 1.05 kg per sqm

As bitumen overlay construction shall follow closely the fabric placement on the same day, an output of 3500 sqm only has been considered for the analysis which will cover a length of 500 m, of 7 m wide carriagway. This can be conveniently overlaid by a bitumenious course in a day

Providing and laying of premix of crushed stone aggregates and emulsion binder, mixed in a batch type cold mixing plant, laid over prepared surface, by paver finisher, rolled with a pneumatic tyred roller initially and finished with a smooth steel wheel roller, all as per clause 519.3

Batch type cold mixing plant 100-120 TPH capacity producing an average output of 75 tonne per hour

Paver finisher hydrostatic with sensor control @ 75 cum per hour

Page 117: Standard Data Book - Rate Analysis

Page 28 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Tipper 10 tonne capacity tonne.km 450 x L 2.46 1105.99

110.60

Pneumatic tyred roller12-15 tonnes. hour 6.00x0.65* 1243.00 4847.70 P&M-037

Smooth wheeled steel roller6-8 tonnes. hour 6.00x0.65* 460.00 1794.00 P&M-044

Water tanker6 KL capacity hour 1.000 200.00 200.00 P&M-060

c) Material

Bitumen emulsion @ 45 litres per tonne tonne 20.250 49915.00 1010778.75 M-077

Crushed stone aggregates 40 mm nominal size cum 297.000 916.00 272052.00 M-055

Cost of water KL 6.000 10.00 60.00 M-189

d) Overhead charges @ 0.1 on (a+b+c) 147192.32

e) Contractor's profit @ 0.1 on (a+b+c+d) 161911.55

Cost for 10500 sqm = a+b+c+d+e 1781027.08

Rate per sqm = (a+b+c+d+e)/205 8687.94

say 8688.00

Note (Case I to III)

5.22 (ii) 40 mm thickness

a) Labour

Mate day 1.000 151.44 151.44 L-12

Mazdoor day 12.000 136.69 1640.28 L-13

Mazdoor skilled day 5.000 164.69 823.45 L-15

b) Machinery

hour 6.000 25594.50 153567.00 P&M-064

Electric generator 125 KVA hour 6.000 652.00 3912.00 P&M-018

Front end loader 1 cum capacity hour 6.000 806.00 4836.00 P&M-017

hour 6.000 2674.00 16044.00 P&M-034

Tipper 10 tonne capacity tonne.km 450 x L 2.46 1105.99

110.60

Pneumatic tyred roller 12-15 tonnes. hour 6.00x0.65* 1243.00 4847.70 P&M-037

Smooth wheeled steel roller 6-8 tonnes. hour 6.00x0.65* 460.00 1794.00 P&M-044

Water tanker6 KL capacity hour 1.000 200.00 200.00 P&M-060

c) Material

Bitumen emulsion @ 70 litres per tonne tonne 31.500 49915.00 1572322.50 M-077

Crushed stone aggregates 14 mm nominal size cum 287.000 1028.00 295036.00 M-052

Cost of water KL 6.000 10.00 60.00 M-189

d) Overhead charges @ 0.1 on (a+b+c) 205645.10

e) Contractor's profit @ 0.1 on (a+b+c+d) 226209.61

Cost for 10500 sqm = a+b+c+d+e 2488305.66

Rate per sqm = (a+b+c+d+e)/205 12138.08

say 12138.00

5.22 (iii) 25 mm thickness

a) Labour

Mate day 1.000 151.44 151.44 L-12

Mazdoor day 12.000 136.69 1640.28 L-13

Mazdoor skilled day 5.000 164.69 823.45 L-15

b) Machinery

hour 6.000 25594.50 153567.00 P&M-064

Electric generator 125 KVA hour 6.000 652.00 3912.00 P&M-018

Front end loader 1 cum capacity hour 6.000 806.00 4836.00 P&M-017

Lead =1 km & P&M-

058

Add 10 per cent of cost of carriage to cover cost of loading and unloading

1. These mixes are considered suitable for minor repair work and temporary road surface improvement.

2. In case concrete mixtures are required to be used for mixing, a number of these will be needed to match the capacity of road rollers.

3. Tack coat, where provided, will be measured and paid separately.

*4.Both the rollers have to be available at site to match with the output of batch mixing plant and paver finisher. A multiplying factor of 0.65 has been adopted to cater for the idling period of road rollers.

Batch type cold mixing plant100-120 TPH capacity producing an average output of 75 tonne per hour

Paver finisher hydrostatic with sensor control @ 75 cum per hour

Lead =1 km & P&M-

058

Add 10 per cent of cost of carriage to cover cost of loading and unloading

Batch type cold mixing plant 100-120 TPH capacity producing an average output of 75 tonne per hour

Page 118: Standard Data Book - Rate Analysis

Page 29 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

hour 6.000 2674.00 16044.00 P&M-034

Tipper 10 tonne capacity tonne.km 450 x L 2.46 1105.99

110.60

Pneumatic tyred roller hour 6.00x0.65* 1243.00 4847.70 P&M-037

Smooth wheeled steel roller hour 6.00x0.65* 460.00 1794.00 P&M-044

Water tanker6 KL capacity hour 1.000 200.00 200.00 P&M-060

c) Material

Bitumen emulsion @ 85 litres per tonne tonne 38.250 49915.00 1909248.75 M-077

Crushed stone aggregates 6 mm nominal size cum 270.000 969.00 261630.00 M-050

Cost of water KL 6.000 10.00 60.00 M-189

d) Overhead charges @ 0.1 on (a+b+c) 235997.12

e) Contractor's profit @ 0.1 on (a+b+c+d) 259596.83

Cost for 10500 sqm = a+b+c+d+e 2855565.16

Rate per sqm = (a+b+c+d+e)/205 13929.59

say 13930.00

Paver finisher hydrostatic with sensor control @ 75 cum per hour

Lead =1 km & P&M-

058

Add 10 per cent of cost of carriage to cover cost of loading and unloading

Page 119: Standard Data Book - Rate Analysis

Page 1 of 280

CHAPTER-7GEOSYNTHETICS AND REINFORCED EARTH

Sr No Description Unit Quantity Rate Rs Cost Rs

7.1 702 Sub-Surface Drain with Geotextiles

Unit = Running metre Taking output = one metre a) Labour

Mate day 0.040 151.44 6.06 L-12Mazdoor skilled day 0.250 164.69 41.17 L-15Mazdoor day 0.500 136.69 68.35 L-13

b) Material

Geonets sqm 1.000 607.00 607.00 M-107Geomembrane sqm 1.000 607.00 607.00 M-106Geotextile sqm 2.000 37.25 74.50 M-108

25.77

c) Overhead charges @ 0.1 on (a+b) 142.98 d) Contractor's profit @ 0.1 on (a+b+c) 157.28 Rate per metre = a+b+c+d 1730.11

say 1730.00 Note

7.2 702.4 Narrow Filter Sub-Surface Drain

Unit = Running metre lengthTaking output = one metre a) Labour

Mate day 0.040 151.44 6.06 L-12Mazdoor skilled day 0.250 164.69 41.17 L-15Mazdoor day 0.500 136.69 68.35 L-13

b) MaterialPerforated geosynthetic pipe 150 mm dia metre 1.000 182.00 182.00 M-134Geotextile filter fabric sqm 1.250 37.25 46.56 M-109

4.57

c) Overhead charges @ 0.1 on (a+b) 34.87 d) Contractor's profit @ 0.1 on (a+b+c) 38.36 Rate per metre = a+b+c+d 421.94

say 422.00 Note

Ref. to MoRTH Spec.

Remarks/ Input ref.

Construction of sub surface drain 200 mm dia using geotextiles treated with carbon black with physical properties as given in clause 702.2.3 formed in to a stable network and a planar geocomposite structure, joints wrapped with geotextile to prevent ingress of soil, all as per clause 702 and approved drawings including excavation and backfilling

Geonets, geomembrane and geotextile to make planar geocomposite stable network for sub surface drain including wrapping of joints with 160 mm over lapping with geotextile .

Add 2 per cent cost of material for miscellaneous items like synthetic cord

Surplus excavated material to be used at site. Hence seprate cost for disposal not added.

Construction of a narrow filter sub- surface drain consisting of porous or perforated pipe laid in narrow trench surrounded by a geotextile filter fabric, with a minimum of 450 mm overlap of fabric and installed as per clause 702.3 and 309.3.5 including excavation and backfilling

Add 2 per cent cost of material for miscellaneous item like synthetic cord

Surplus excavated material to be used at site. Hence Separate cost for disposal not added.

Page 120: Standard Data Book - Rate Analysis

Page 2 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

7.3 703 Laying Paving Fabric Beneath a Pavement Overlay

Unit = sqmTaking output = 2800 sqm a) Labour

Mate day 0.800 151.44 121.15 L-12Mazdoor day 20.000 136.69 2733.80 L-13

b) MachineryRoad sweeper 1250 sqm per hour hour 2.240 357.00 799.68 P&M-031Pneumatic roller 14 tonnes 2000 sqm per hour hour 1.400 1243.00 1740.20 P&M-037Bitumen pressure distributor 1750 sqm per hour hour 1.680 1073.00 1802.64 P&M-004

c) MaterialPaving Fabric sqm 2940.000 225.00 661500.00 M-133 Paving Bitumen 80-100 tonne 2.800 56122.00 157141.60 M-075

c) Overhead charges @ 0.1 on (a+b) 82583.91 d) Contractor's profit @ 0.1 on (a+b+c) 90842.30 Cost for 2800 sqm = a+b+c+d+e 999265.28 Rate per sqm =(a+b+c+d+e)/2800 356.88

say 356.88 7.4 704 Laying Boulder Apron in Crates of Synthetic Geogrids

Unit = cumTaking output = 3.00 cum a) Labour

Mate day 0.060 151.44 9.09 L-12

Mazdoor skilled day 0.500 164.69 82.35 L-15

Mazdoor day 1.500 136.69 205.04 L-13

b) Material

Geo grids sqm 21.000 607.00 12747.00 M-105

Connectors/ Staples each 50.000 61.00 3050.00 M-085

Polymer braids metre 20.000 364.00 7280.00 M-140

Stones with minimum size of 200 mm cum 3.450 494.68 1706.65 M-003

Stones spall for filling voids cum 0.450 921.00 414.45 M-008

c) Overhead charges @ 0.1 on (a+b) 2549.46

d) Contractor's profit @ 0.1 on (a+b+c) 2804.40

Cost for 3 cum = a+b+c+d 30848.42

Rate per cum = (a+b+c+d)/ 3 2372.96

say 2373.00

7.5 3100 Reinforced Earth Structures

Providing and laying paving fabric with physical requirements as per table 704-2 over a tack coat of paving grade Bitumen 80-100 penetration, laid at the rate of 1 kg per sqm over thoroughly cleaned and repaired surface to provide a water resistant membrane and crack retarding layer. Paving fabric to be free of wrinkling and folding and to be laid before cooling of tack coat, brooming and rolling of surface with pneumatic roller to maximise paving fabric contact with pavement surface

Providing, preparing and laying of geogrid crated apron 1 m x 5 m, 600 mm thick including excavation and backfilling with baffles at 1 metre interval, made with geogrids having characteristics as per clause 704.2, joining sides with connectors/ring staples, top corners to be tie tensioned, placing of suitable cross interval ties in layers of 300 mm connecting opposite side with lateral braces and tied with polymer braids to avoid bulging, constructed as per clause 704.3. filled with stone with minimum size of 200 mm and specific gravity not less than 2.65, packed with stone spalls, keyed to the foundation recess in case of sloping ground and laid over a layer of geotextile to prevent migration of fines, all as per clause 704 and laid as per clause 2503.3 and approved design.

Reinforced earth Structures have four main components as under:

a) Excavation for foundation, foundation concrete and cement concrete grooved seating in the foundation for facing elements (facia material).

Page 121: Standard Data Book - Rate Analysis

Page 3 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

b) Facia material and its placement.

Each component is analysed separately as under:

considering Average height of wall = 8 m.

7.5 3102 (i) Assembling, joining and laying of reinforcing elements.

A

Unit = Running Metre

Taking Output = 450 m

a) Labour

Mate day 0.360 151.44 54.52 L-12

Mazdoor day 6.000 136.69 820.14 L-13

Mazdoor skilled day 3.000 164.69 494.07 L-15

b) Material

1.Galvanised carbon steel strips metre 450*1.1 364.00 180180.00 M-154

or

2.Copper Strips metre 450*1.1 364.00 180180.00 M-153

or

3.Aluminium Strips metre 450*1.1 364.00 180180.00 M-157

or

4.Stainless steel strips metre 450*1.1 364.00 180180.00 M-156

or

metre 450*1.1 364.00 180180.00 M-155

Type 1 1.Galvanised carbon steel strips

c) Overhead charges @ 0.1 on (a+b) 18154.87

d) Contractor's profit @ 0.1 on (a+b+c) 18154.87

Cost of 450 m = a+b+c+d 217858.47

Rate per metre =(a+b+c+d)/450 484.13

say 484.00

Type 2 2.Copper Strips

c) Overhead charges @ 0.1 on (a+b) 18154.87

d) Contractor's profit @ 0.1 on (a+b+c) 18154.87

Cost of 450 m = a+b+c+d 217858.47

Rate per metre =(a+b+c+d)/450 484.13

say 484.00

Type 3 3.Aluminium Strips

c) Overhead charges @ 0.1 on (a+b) 18154.87

d) Contractor's profit @ 0.1 on (a+b+c) 18154.87

Cost of 450 m = a+b+c+d 217858.47

Rate per metre =(a+b+c+d)/450 484.13

say 484.00

Type 4 4.Stainless steel strips

c) Overhead charges @ 0.1 on (a+b) 18154.87

d) Contractor's profit @ 0.1 on (a+b+c) 18154.87

Cost of 450 m = a+b+c+d 217858.47

Rate per metre =(a+b+c+d)/450 484.13

say 484.00

c) Assembling, joining with facing elements and laying of the reinforcing elements.

d) Earth fill with granular material which is to be retained by the wall.

With reinforcing element of steel / Aluminium strips / polymeric strips.

@ Reinforcement strips 60 mm wide 5 mm thick as per clause 3102.

5.Glass reinforced polymer/fibre reinforced polymer/polymeric strips

@ Any one of the above alternative may be adopted as per approved design.

Add 10 per cent of the cost of reinforcing strip towards accessories like tie-strips, nuts and bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps, heat bonding or extension.

Page 122: Standard Data Book - Rate Analysis

Page 4 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Type 5

c) Overhead charges @ 0.1 on (a+b) 18154.87

d) Contractor's profit @ 0.1 on (a+b+c) 18154.87

Cost of 450 m = a+b+c+d 217858.47

Rate per metre =(a+b+c+d)/450 484.13

say 484.00

7.5(i) B With reinforcing elements of synthetic geogrids

Unit = sqm

Taking output = 300 sqm

a) Labour

Mate day 0.360 151.44 54.52 L-12

Mazdoor day 6.000 136.69 820.14 L-13

Mazdoor skilled day 3.000 164.69 494.07 L-15

b) Material

sqm 300.000 607.00 182100.00 M-181

18210.00

c) Overhead charges @ 0.1 on (a+b) 20167.87

d) Contractor's profit @ 0.1 on (a+b+c) 22184.66

Cost of 300 sqm of Synthetic geogrids = a+b+c+d 244031.26

Rate per sqm = (a+b+c+d)/ 300 813.44

say 813.00

7.5 3104 (ii) Facing elements of RCC

Unit = sqm

Taking output = 75 sqm

a) Labour

Mate day 0.180 151.44 27.26 L-12

Mazdoor day 3.000 136.69 410.07 L-13

Mazdoor skilled day 1.500 164.69 247.04 L-15

b) Machinery

Light crane with lifting capacity upto 3 tonne hour 6.000 357.00 2142.00 P&M-013

c) Material

cu.m 13.500 3952.00 53352.00

HYSD steel @ 5 kg / sqm (Refer Item 12.6) tonnes 0.380 65101.00 24738.38 Item 13.6

1561.81

d) Overhead charges @ 0.1 on (a+b) 282.64

e) Contractor's profit @ 0.1 on (a+b+d) 310.90

Cost for 75 sqm = a+b+c+d+e 83072.09

Rate per sqm = (a+b+c+d+e)/ 75 1107.63

say 1108.00

Note

5.Glass reinforced polymer/fibre reinforced polymer/polymeric strips

Synthetic Geogrids as per clause 3102.8 and approved design and specifications.

Add 10 per cent of the cost of reinforcing elements (synthetic geogrids) for accessories like tie-strips, nuts and bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geogrids.

Pre-cast RCC M-35 facing elements of size as per design and 18 cm thick for 75 sqm. (Refer Item 12.8 (H))

Item 12.8 (H)

Add 2 per cent of cost of facia pannels, for all necessary temporary form work, scaffolding and provision of loops/lugs for lifting of pannels and joining the reinforcing elements.

1.The specification and construction details to be adopted shall be as per section 3100 of MoRTH Specification.

2.Drainage arrangement shall be made as per approved design and drawings.

3.The quantity of filler media shall be calculated as per approved design and specifications and shall be priced separately.The rate for same to be adopted from chapter 15.

Page 123: Standard Data Book - Rate Analysis

Page 5 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

,

(I) Excavation for foundation including backfilling.

(ii) Foundation concrete as per approved design.

(iii) Cost of facial pannels and their erection .

4.Excavation for foundation including foundation concrete and groove in the foundation for seating of bottom most facia panel and capping beam to be calculated as per design and priced separately. The rates for excavation and foundation concrete shall be taken from the chapter 12 & 13 in bridge section.

5.The earth fill to be retained is not included in this analysis. The same is to be worked out and provided separately complete as per clause 305.

6.For compaction of Earthwork, attention is invited to clause 3105.5 of MoRTH Specification.

7.Length of reinforcing strips will vary with the height of wall and will be as per approved design and drawings.8.The type of reinforcing elements to be adopted shall be as per approved design and specifications.

9.The market rate for supply of reinforcing elements and their accessories are to be ascertained from reputed firms in the field of earth reinforcement.

10.The earth fill material shall be clean, free draining, granular with high friction and low cohesion, non-corrosive, coarse grained with not 10 per cent of particles passing 75 micron sieve, free of any deleterious matter, chlorides, salts, acids, alkalies, mineral oil, fungus and microbes and shall be of specified PH value.

11.Capping beam is to be priced separately as per approved design. The rate for cement concrete shall be taken from the chapter of sub-structure in bridge section.

12.The cost of reinforced earth retaining wall shall include following:

(iv) Cost of reinforcing elements including their fixing and joining with the facial pannels.

(v) Drainage arrangement including filter media as per approved design and drawings.

13. The compacted earth filling to be retained shall form part of embankment.

Page 124: Standard Data Book - Rate Analysis

Page 1 of 280

CHAPTER-8TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES

Sr No Description Unit Quantity Rate Rs Cost Rs

8.1 408 Cast in Situ Cement Concrete M20 Kerb

Unit = Running metreTaking output = 360 metre

A. Using Concrete Mixer

Cement ConcreteCement concrete of grade M20 = 12.60 cumCement concrete of grade M10 for base= 11.61 cum

a) LabourMate day 0.720 151.44 109.04 L-12Mason day 2.000 223.36 446.72 L-11Mazdoor day 16.000 136.69 2187.04 L-13

b) MachineryKerb casting machine @ 60 metres/hour hour 6.000 310.00 1860.00 P&M-029Concrete mixer 0.48/0.28 cum capacity hour 12.000 233.00 2796.00 P&M-009Water tanker6 KL capacity hour 5.000 200.00 1000.00 P&M-060

c) Material

cum 21.790 1028.00 22400.12 M-053

Coarse sand 30 per cent cum 10.900 710.46 7744.01 M-005Cement 11 per cent tonne 5.700 5000.00 28500.00 M-081Cost of water KL 30.000 10.00 300.00 M-189

d) Overhead charges @ 0.1 on (a+b+c) 6734.29 e) Contractor's profit @ 0.1 on (a+b+c+d) 7407.72 Cost for 360 meter = a+b+c+d+e 81484.95 Rate per metre = (a+b+c+d+e)/360 226.35

say 226.00

B Using Concrete Batching and Mixing Plant

Cement ConcreteCement concrete of grade M20 = 12.60 cumCement concrete of grade M10 for base = 11.61 cum

a) LabourMate day 0.120 151.44 18.17 L-12Mason day 1.000 223.36 223.36 L-11Mazdoor day 2.000 136.69 273.38 L-13

b) MachineryKerb casting machine @ 60 metres/hour hour 6.000 310.00 1860.00 P&M-029Concrete batching and mixing plant @ 15 cum/hr. hour 1.600 1860.00 2976.00 P&M-003Water tanker6 KL capacity hour 5.000 200.00 1000.00 P&M-060Tipper 5.5 cum capacity hour 6.000 339.00 2034.00 P&M-048

c) Material

cum 21.790 1028.00 22400.12 M-053

Coarse sand 30 per cent cum 10.900 828.00 9025.20 M-004Cement 11 per cent tonne 5.700 5000.00 28500.00 M-081Cost of water KL 30.000 10.00 300.00 M-189

d) Overhead charges @ 0.1 on (a+b+c) 6861.02 e) Contractor's profit @ 0.1 on (a+b+c+d) 7547.13 Cost for 360 meter = a+b+c+d+e 83018.38 Rate per metre = (a+b+c+d+e)/360 230.61

say 231.00

8.2 408 Cast in Situ Cement Concrete M 20 Kerb with Channel

A Using Concrete Mixer

Unit = Running metreTaking output = 300 metre lengthCement Concrete

Ref. to MoRTH Spec.

Remarks/ Input ref.

Construction of cement concrete kerb with top and bottom width 115 and 165 mm respectively, 250 mm high in M 20 grade PCC on M-10 grade foundation 150 mm thick, foundation having 50 mm projection beyond kerb stone, kerb stone laid with kerb laying machine, foundation concrete laid manually, all complete as per clause 408

Total Concrete = 24.21 cu.m

Crushed stone aggregate 20 mm nominal size 59 per cent

Total Concrete = 24.21 cu.m

Crushed stone aggregate 20 mm nominal size 59 per cent

Construction of cement concrete kerb with channel with top and bottom width 115 and 165 mm respectively, 250 mm high in M 20 grade PCC on M10 grade foundation 150 mm thick, kerb channel 300 mm wide, 50 mm thick in PCCM20 grade, sloped towards the kerb, kerb stone with channel laid with kerb laying machine, foundation concrete laid manually, all complete as per clause 408

Page 125: Standard Data Book - Rate Analysis

Page 2 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Cement concrete of grade M20= 17.48 cumCement concrete of grade M10 for base = 23.18 cum

a) Labour

Mate day 0.720 151.44 109.04 L-12

Mason day 2.000 223.36 446.72 L-11

Mazdoor day 16.000 136.69 2187.04 L-13

b) Machinery

hour 6.000 310.00 1860.00 P&M-029

Concrete mixer 0.48/0.28 hour 16.000 233.00 3728.00 P&M-009

Water tanker6 KL capacity hour 6.000 200.00 1200.00 P&M-060

c) Material

cum 36.590 1028.00 37614.52 M-053

Coarse sand 30 per cent cum 18.300 710.46 13001.42 M-005

Cement 10 per cent tonne 9.010 5000.00 45050.00 M-081

Cost of water KL 36.000 10.00 360.00 M-189

d) Overhead charges @ 0.1 on (a+b+c) 10555.67

e) Contractor's profit @ 0.1 on (a+b+c+d) 11611.24

Cost for 360 meter = a+b+c+d+e 127723.65

Rate per metre = (a+b+c+d+e)/300 425.75 Add 1 % labour Cess 4.26

430.00

say 430.00

8.2 B Using Concrete Batching and Mixing Plant

Unit = Running metre

Taking output = 300 metre length

Cement Concrete

Cement concrete of grade M20= 17.48 cum

Cement concrete of grade M10 for base = 23.18 cum

a) Labour

Mate day 0.120 151.44 18.17 L-12

Mason day 1.000 223.36 223.36 L-11

Mazdoor day 2.000 136.69 273.38 L-13

b) Machinery

hour 6.000 310.00 1860.00 P&M-029

Concrete batching and mixing plant @ 15 cum/hr. hour 2.700 1860.00 5022.00 P&M-003

Water tanker6 KL capacity hour 6.000 200.00 1200.00 P&M-060

Tipper of 5.5 cum capacity hour 6.000 339.00 2034.00 P&M-048

c) Material

cum 36.590 1028.00 37614.52 M-053

Coarse sand 30 per cent cum 18.300 828.00 15152.40 M-004

Cement 10 per cent tonne 9.010 5000.00 45050.00 M-081

Cost of water KL 36.000 10.00 360.00 M-189

d) Overhead charges @ 0.1 on (a+b+c) 10880.78

e) Contractor's profit @ 0.1 on (a+b+c+d) 11968.86

Cost for 300 meter = a+b+c+d+e 131657.48

Rate per metre = (a+b+c+d+e)/300 438.86 say 439.00

8.3 801 Printing New Letter and Figures of any Shade

(i)

Details for 100 letters of 16 cm height i.e. 1600 cm

Unit = per cm height per letter

a) Labour

Total Concrete = 40.66 cum

Kerb casting machine @ 50 metres/hour for laying kerb and channel

Crushed stone aggregate 20 mm nominal size 60 per cent

Total Concrete = 40.66 cum

Kerb casting machine @ 50 metres/hour for laying kerb and channel

Crushed stone aggregate 20 mm nominal size 60 per cent

Printing new letter and figures of any shade with synthetic enamel paint black or any other approved colour to give an even shade

Hindi ( Matras commas and the like not to be measured and paid for Half letter shall be counted as half )

Page 126: Standard Data Book - Rate Analysis

Page 3 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Mate day 0.120 151.44 18.17 L-12

Painter day 2.000 223.36 446.72 L-18

Mazdoor day 1.000 136.69 136.69 L-13

b) Material

Paint Litre 0.700 192.81 134.97 M-131

c) Overhead charges @ 0.1 on (a+b) 73.65

d) Contractor's profit @ 0.1 on (a+b+c) 81.02

Cost for 1600 cm = a+b+c+d 891.23

Rate per cm height per letter = (a+b+c+ d)/1600 0.56 say 0.60

8.3 (ii) English and Roman

Hyphens and the like not to be measured and paid for

Detail for 100 letters of 16 cm height. i.e.1600 cm

Unit = per cm height per letter

a) Labour

Mate day 0.070 151.44 10.60 L-12

Painter Ist class day 1.250 223.36 279.20 L-18

Mazdoor day 0.500 136.69 68.35 L-13

b) Material

Paint Litre 0.500 192.81 96.41 M-131

c) Overhead charges @ 0.1 on (a+b) 45.46

d) Contractor's profit @ 0.1 on (a+b+c) 50.00

Cost for 1600 cm = a+b+c+d 550.01

Rate per cm height per letter = (a+b+c +d)/1600 0.34 say 0.30

8.4 801 Retro-Reflectorised Traffic Signs

Unit = Each

Taking output = one traffic sign

i) Excavation for foundation cum 0.216 138.00 29.81

ii) Cement concrete M15 grade cum 0.120 4228.00 507.36

iii) Painting angle iron post two coats sqm 0.430 46.00 19.78 Item 8.9

a) Labour (For fixing at site)

Mate day 0.010 151.44 1.51 L-12

Mazdoor day 0.250 136.69 34.17 L-13

b) Material

Mild steel angle iron 75 x 75 x 6 mm kg 19.000 45.00 855.00

( i ) 90 cm equilateral triangle sqm 0.350 6064.00 2122.40 M-061

or

( ii ) 60 cm equilateral triangle sqm 0.156 6064.00 945.98 M-061

or

( iii ) 60 cm circular sqm 0.283 6064.00 1716.11 M-061

or

( iv ) 80 mm x 60 mm rectangular sqm 0.480 6064.00 2910.72 M-061

or

( v ) 60 cm x 45 cm rectangular sqm 0.270 6064.00 1637.28 M-061

or

(vi ) 60 cm x 60 cm square sqm 0.360 6064.00 2183.04 M-061

Providing and fixing of retro- reflectorised cautionary, mandatory and informatory sign as per IRC :67 made of high intensity grade sheeting vide clause 801.3, fixed over aluminium sheeting, 1.5 mm thick supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved drawing

Item No. 3.13

Item 12.8 (A)

M-179 /1000

Aluminium sheeting fixed with encapsulated lens type reflective sheeting of size including lettering and signs as applicable

Add 2 per cent of cost of angle iron towards cost of drilling holes, nuts, bolts etc.

Page 127: Standard Data Book - Rate Analysis

Page 4 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

or

( vii ) 90 cm high octagon sqm 0.672 6064.00 4075.01 M-061

c) Machinery

Tractor-trolley hour 0.010 282.50 2.83 P&M-053

( i ) 90 cm equilateral triangle

d) Overhead charges @ 0.1 on (a+b+c) 301.59

e) Contractor's profit @ 0.1 on (a+b+c+d) 331.75

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 4206.20 say 4206.00

( ii ) 60 cm equilateral triangle

d) Overhead charges @ 0.1 on (a+b+c) 183.95

e) Contractor's profit @ 0.1 on (a+b+c+d) 202.34

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 2782.74 say 2783.00

( iii ) 60 cm circular

d) Overhead charges @ 0.1 on (a+b+c) 260.96

e) Contractor's profit @ 0.1 on (a+b+c+d) 287.06

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 3714.59 say 3715.00

( iv ) 80 mm x 60 mm rectangular

d) Overhead charges @ 0.1 on (a+b+c) 380.42

e) Contractor's profit @ 0.1 on (a+b+c+d) 418.47

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 5160.07 say 5160.00

( v ) 60 cm x 45 cm rectangular

d) Overhead charges @ 0.1 on (a+b+c) 253.08

e) Contractor's profit @ 0.1 on (a+b+c+d) 278.39

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 3619.21 say 3619.00

(vi ) 60 cm x 60 cm square

d) Overhead charges @ 0.1 on (a+b+c) 307.66

e) Contractor's profit @ 0.1 on (a+b+c+d) 338.42

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 4279.58 say 4280.00

( vii ) 90 cm high octagon

d) Overhead charges @ 0.1 on (a+b+c) 496.85

e) Contractor's profit @ 0.1 on (a+b+c+d) 546.54

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 6568.86 say 6569.00

Note

8.5 801

Unit = sqm

Taking output = 0.9 sqm

i) Excavation for foundation cum 0.216 138.00 29.81

1.Any one area of aluminium sheeting given at (i) to (vii) may be adopted as per site requirement and in accordance with IRC : 67

2.Rate for excavation, cement concrete M-15 and painting may be taken from respective chapters

3. The depth of foundation and quantity of cement concrete in the foundation are indicative. These may be increased for areas having higher wind velocities like in coastal areas. This is applicable to all road signs and directions boards.

Direction and Place Identification Signs upto 0.9 sqm Size Board.

Providing and erecting direction and place identification retro-reflectorised sign as per IRC:67 made of high intensity grade sheeting vide clause 801.3, fixed over aluminium sheeting, 2 mm thick with area not exceeding 0.9 sqm supported on a mild steel single angle iron post 75 x 75 x 6 mm firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 45 x 45 x 60 cm, 60 cm below ground level as per approved drawing

Item No. 3.13

Page 128: Standard Data Book - Rate Analysis

Page 5 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

ii) Cement concrete M15 grade cum 0.120 4228.00 507.36

iii) Painting angle iron post two coats sqm 0.430 46.00 19.78 Item 8.9

a) Labour (For fixing at site)

Mate day 0.010 151.44 1.51 L-12

Mazdoor day 0.200 136.69 27.34 L-13

b) Material

kg 19.000 45.00 855.00

sqm 0.900 6064.00 5457.60 M-061

c) Machinery

Tractor-trolley hour 0.020 282.50 5.65 P&M-053

d) Overhead charges @ 0.1 on (a+b+c) 634.71

e) Contractor's profit @ 0.1 on (a+b+c+d) 698.18

Cost for 0.9 sqm =I+ii+ii+ a+b+c+d+e 8236.94

9152.16

say 9152.00

Note

8.6 801

Unit = sqm

Taking output = 1.50 sqm

i) Excavation for foundation cum 0.430 138.00 59.34

ii) Cement concrete M15 grade cum 0.240 4228.00 1014.72

iii) Painting angle iron post 2 coats sqm 0.860 46.00 39.56 Item 8.9

a) Labour (For fixing at site)

Mate day 0.010 151.44 1.51 L-12

Mazdoor day 0.300 136.69 41.01 L-13

b) Material

kg 38.000 45.00 1710.00

sqm 1.500 6064.00 9096.00 M-061

Item 12.8 (A)

Mild steel angle iron 75 mm x 75 mm x 6 mm,2.85 metres long

M-179 /1000

Aluminium sheeting fixed with encapsulated lens type reflective sheeting of size 0.9 sqm

Add 2 per cent of cost of materials for drilling holes, nuts, bolts, fabrication etc.

Rate per sqm (for sign having area upto 0.9 sqm) = (I+ii+iii+a+b+c+d+e)/0.90

I) Lettering and arrow marks on sign board to be provided separately as per actual requirement. Rates for these items have been analysed separately

ii) Rate for excavation, cement concrete M-15 and painting may be taken from respective chapters

Direction and Place Identification Signs with size more than 0.9 sqm size Board.

Providing and erecting direction and place identification retro- reflectorised sign as per IRC :67 made of high intensity grade sheeting vide clause 801.3, fixed over aluminium sheeting, 2 mm thick with area exceeding 0.9 sqm supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm, 2 Nos. firmly fixed to the ground by means of properly designed foundation with M 15 grade cement concrete45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved drawing

Item No. 3.13

Item 12.8 (A)

Mild steel angle iron 75 mm x 75 mm x 6 mm, 2.85 metres long, 2 nos

M-179 /1000

Aluminium sheeting fixed with encapsulated lens type reflective sheeting

Add 2 per cent of cost of materials for drilling holes, nuts, bolts, fabrication etc.

Page 129: Standard Data Book - Rate Analysis

Page 6 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

c) Machinery

Tractor-trolley hour 0.020 282.50 5.65 P&M-053

d) Overhead charges @ 0.1 on (a+b+c) 1081.17

e) Contractor's profit @ 0.1 on (a+b+c+d) 1193.53

Cost for 1.5 sqm =I+ii+ii+ a+b+c+d+e 14242.49

15824.99

say 15825.00

Note

8.7 802 Overhead Signs

A Truss and Vertical Support

Unit = tonne

Taking output = 1 tonne

a) Labour

Mate day 0.240 151.44 36.35 L-12

Blacksmith day 2.000 264.50 529.00 L-02

Mazdoor including for handling & fixing at site. day 4.000 136.69 546.76 L-13

b) Material

tonne 1.050 54574.00 57302.70 M-060

573.03

8681.36

c) Machinery

Crane 3 tonne capacity hour 3.000 357.00 1071.00 P&M-013

Truck hour 0.500 315.27 157.64 P&M-057

d) Overhead charges @ 0.1 on (a+b+c) 6889.78

e) Contractor's profit @ 0.1 on (a+b+c+d) 7578.76

Rate per tonne = (a+b+c+d+e) 83366.37 say 83366.00

8.7 B Aluminium Alloy Plate for Over Head Sign

Unit = sqm

Taking output = 1 sqm

a) Labour

Mate day 0.020 151.44 3.03 L-12

Blacksmith day 0.100 264.50 26.45 L-02

Mazdoor day 0.150 136.69 20.50 L-13

b) Material

sqm 1.000 425.00 425.00 M-059

Miscellaneous

0.50

c) Overhead charges @ 0.1 on (a+b) 47.55

d) Contractor's profit @ 0.1 on (a+b+c) 52.30

Rate per sqm = (a+b+c+d) 575.33 say 575.00

Note

Rate per sqm ( for sign having area more than 0.9 sqm) = ( i+ii+iii+a+b+c+d+e)/1.50

i) Lettering and arrow marks on sign board to be provided separately as per actual requirement. Rates for these items have been analysed separately

ii) Rate for excavation, cement concrete M-15 and painting may be taken from respective chapters

Providing and erecting overhead signs with a corrosion resistant 2mm thick aluminium alloy sheet reflectorised with high intensity retro-reflective sheeting of encapsulated lense type with vertical and lateral clearance given in clause 802.2 and 802.3 and installed as per clause 802.7 over a designed support system of aluminium alloy or galvanised steel trestles and trusses of sections and type as per structural design requirements and approved plans

Aluminium alloy/galvanised steel including 5 per cent wastage

Add 1 per cent on cost of material for nuts, bolts and drilling and welding consumables

Add 15 per cent on cost of material for fabrication of trusses as per approved design

Aluminium alloy plate,2 mm thick, fixed with high intensity grade sheeting vide clause 801.3

Add 1 per cent of cost of labour for lifting arrangement, like ladders, pulleys, ropes etc

1. The cost of excavation and foundation concrete for fixing of vertical support system to be worked out separately as per the approved drawing/design and to be included in the estimate.

Page 130: Standard Data Book - Rate Analysis

Page 7 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

2. Lettering and arrow marks on sign board to be provided separately as per actual requirement. Rates for these items have been included separately in this chapter.

Page 131: Standard Data Book - Rate Analysis

Page 8 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

8.8 803 Painting Two Coats on New Concrete Surfaces

Unit = sqm

Taking output = 40 sqm

a) Labour

Mate day 0.120 151.44 18.17 L-12

Painter day 2.000 223.36 446.72 L-18

Mazdoor day 1.000 136.69 136.69 L-13

b) Material

Paint conforming to requirement of clause 803.3. Litre 6.000 117.16 702.96 M-132

7.03

65.23

c) Overhead charges @ 0.1 on (a+b) 137.68

d) Contractor's profit @ 0.1 on (a+b+c) 151.45

Cost for 40 sqm = a+b+c+d 1665.93

Rate per sqm = (a+b+c+d)/40 41.65

say 42.00

8.9 803 Painting on Steel Surfaces

Unit = sqm

Taking output = 10 sqm

a) Labour

Mate day 0.030 151.44 4.54 L-12

Painter day 0.450 223.36 100.51 L-18

Mazdoor day 0.250 136.69 34.17 L-13

b) Material

Paint ready mixed approved brand. Litre 1.250 192.81 241.01 M-131

Add @ 1 per cent on cost of material for scaffolding 2.41 19.01

c) Overhead charges @ 0.1 on (a+b) 40.17

d) Contractor's profit @ 0.1 on (a+b+c) 44.18

Cost for 10 sqm = a+b+c+d 486.01

Rate per sqm= (a+b+c+d)/10 48.60 say 49.00

8.10 803 Painting on Wood Surfaces

Unit = sqm

Taking output = 10 sqm

a) Labour

Mate day 0.030 151.44 4.54 L-12

Painter day 0.500 223.36 111.68 L-18

Mazdoor day 0.200 136.69 27.34 L-13

b) Material

Paint ready mixed of approved brand. Litre 1.500 192.81 289.22 M-131

Add @ 1 per cent on cost of material for scaffolding 2.89 21.64

Painting two coats after filling the surface with synthetic enamel paint in all shades on new plastered concrete surfaces

Add for scaffolding @ 1 per cent of labour cost where required

Add @ 5 per cent cost of labour and materials to prepare the surface by filling minuts roughness on the surface and priming the surface before laying 2 coats of painting.

Providing and applying two coats of ready mix paint of approved brand on steel surface after through cleaning of surface to give an even shade

Add @ 5 per cent cost of labour and materials to prepare the surface by filling minuts roughness on the surface and priming the surface before laying 2 coats of painting.

Providing and applying two coats of ready mix paint of approved brand on wood surface after thorough cleaning of surface to give an even shade

Add @ 5 per cent cost of labour and materials to prepare the surface by filling minuts roughness on the surface and priming the surface before laying 2 coats of painting.

Page 132: Standard Data Book - Rate Analysis

Page 9 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

c) Overhead charges @ 0.1 on (a+b) 45.73

d) Contractor's profit @ 0.1 on (a+b+c) 50.30

Cost for 10 sqm = a+b+c+d 553.34

Rate per sqm = (a+b+c+d)/10 55.33 say 55.00

8.11 803

(i) Over 10 cm in width

Unit = sqm

Taking output = 10 sqm

a) Labour

Mate day 0.090 151.44 13.63 L-12

Painter day 0.550 223.36 122.85 L-18

Mazdoor day 1.550 136.69 211.87 L-13

b) Material

Road marking Paint as per IS :164 Litre 1.480 117.16 173.40 M-132

c) Overhead charges @ 0.1 on (a+b) 52.17

d) Contractor's profit @ 0.1 on (a+b+c) 57.39

Cost for 10 sqm = a+b+c+d 631.31

Rate per sqm= (a+b+c+d)/10 63.13 say 63.00

8.11 (ii) Up to 10 cm in width

Unit = sqm

Taking output = 10 sqm

a) Labour

Mate day 0.070 151.44 10.60 L-12

Painter day 0.350 223.36 78.18 L-18

Mazdoor day 1.350 136.69 184.53 L-13

b) Material

Road marking paint Litre 1.480 117.16 173.40 M-132

c) Overhead charges @ 0.1 on (a+b) 44.67

d) Contractor's profit @ 0.1 on (a+b+c) 49.14

Cost for 10 sqm = a+b+c+d 540.51

Rate per sqm = (a+b+c+d)/10 54.05 say 54.00

8.12 803

(i) Over 10 cm in width

Unit = sqm

Taking output = 10 sqm

a) Labour

Mate day 0.060 151.44 9.09 L-12

Painter Ist class day 0.300 223.36 67.01 L-18

Mazdoor day 1.250 136.69 170.86 L-13

b) Material

Road marking paint Litre 0.900 117.16 105.44 M-132

c) Overhead charges @ 0.1 on (a+b) 35.24

d) Contractor's profit @ 0.1 on (a+b+c) 38.76

Cost for 10 sqm = a+b+c+d 426.41

Rate per sqm = (a+b+c+d)/10 42.64 say 43.00

8.12 (ii) Up to 10 cm in width

Painting Lines, Dashes, Arrows etc on Roads in Two Coats on New Work

Painting lines, dashes, arrows etc on roads in two coats on new work with ready mixed road marking paint conforming to IS:164 on bituminous surface, including cleaning the surface of all dirt, dust and other foreign matter, demarcation at site and traffic control

Painting Lines, Dashes, Arrows etc on Roads in Two Coats on Old Work

Painting lines, dashes, arrows etc on roads in two coats on old work with ready mixed road marking paint conforming to IS: 164 on bituminous surface, including cleaning the surface of all dirt, dust and other foreign matter, demarcation at site and traffic control

Page 133: Standard Data Book - Rate Analysis

Page 10 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Unit = sqm

Taking output = 10 sqm

a) Labour

Mate day 0.070 151.44 10.60 L-12

Painter Ist class day 0.350 223.36 78.18 L-18

Mazdoor day 1.350 136.69 184.53 L-13

b) Material

Road marking Paint Litre 0.900 117.16 105.44 M-132

c) Overhead charges @ 0.1 on (a+b) 37.88

d) Contractor's profit @ 0.1 on (a+b+c) 41.66

Cost for 10 sqm= a+b+c+d 458.29

Rate per sqm = (a+b+c+d)/10 45.83 say 46.00

8.13 803

Unit = sqm

Taking output = 640 sqm

a) Labour

Mate day 0.050 151.44 7.57 L-12

Mazdoor day 2.000 136.69 273.38 L-13

b) Machinery

Road marking machine @ 80 sqm per hour hour 8.000 93.00 744.00 P&M-043

Tractor-trolley hour 8.000 282.50 2260.00 P&M-053

c) Material

Hot applied thermoplastic compound Litre 2000.000 150.00 300000.00 M-118

Reflectorising glass beads kg 200.000 75.00 15000.00 M-152

d) Overhead charges @ 0.1 on (a+b+c) 31828.50

e) Contractor's profit @ 0.1 on (a+b+c+d) 35011.34

Cost for 640 sqm = a+b+c+d+e 385124.79

Rate per sqm = a+b+c+d+e)/640 601.76 Add 1 % labour Cess 6.02

607.78

say 607.78

Note

8.14 804 Kilometre Stone

(i) 5th kilometre stone (precast)

Unit = Nos.

Taking output = 6 Nos.

a) M-15 grade of concrete cum 2.350 4228.00 9935.80

b) Steel reinforcement @ 5 kg per sqm kg 22.080 65.10 1437.43

c) Excavation in soil for foundation cum 1.680 138.00 231.84

d) Painting two coats on concrete surface sqm 9.850 40.00 394.00 Item 8.8

1800.000 0.30 540.00 Item 8.3

Transportation and fixing

f) Labour

Mate day 0.260 151.44 39.37 L-12

Road Marking with Hot Applied Thermoplastic Compound with Reflectorising Glass Beads on Bituminous Surface

Providing and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35 .The finished surface to be level, uniform and free from streaks and holes.

1. A sealing primer may be applied in advance on cement concrete pavement to ensure proper bonding. Any laitance and/or curing compound to be removed where paint is required to be applied on concrete surface.

2.Cost of painter is already included in hire charges of road marking machine.

Reinforced cement concrete M15grade kilometre stone of standard design as per IRC:8-1980, fixing in position including painting and printing etc

Item 12.8 (A)

Item 13.6 /1000

Item No. 3.13

e) Lettering on km post (average 30 letters of 10 cm height each)

per cm per letter

Page 134: Standard Data Book - Rate Analysis

Page 11 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Mason day 0.600 223.36 134.02 L-11

Mazdoor including loading/unloading day 6.000 136.69 820.14 L-13

g) Machinery

Tractor-trolley hour 6.000 282.50 1695.00 P&M-053

h) Overhead charges @ 0.1 on (f+g) 268.85

i) Contractor's profit @ 0.1 on (f+g+h) 295.74

Cost for 6 Nos. 5th km stone = a+b+c+ d+e +f+g+h +i 15792.19

2632.03

say 2632.00

8.14 (ii) Ordinary kilometer stone (precast)

Unit = Nos.

Taking output = 14 Nos.

a) M-15 grade of concrete cum 3.770 4228.00 15939.56

b) Steel reinforcement @ 5 kg per sqm kg 26.320 65.10 1713.46

c) Excavation in soil for foundation cum 2.770 138.00 382.26

d) Painting two coats on concrete surface sqm 11.410 40.00 456.40 Item 8.8

1680.000 0.30 504.00 Item 8.3

Transportation and fixing

f) Labour

Mate day 0.320 151.44 48.46 L-12

Mason day 1.000 223.36 223.36 L-11

Mazdoor day 7.000 136.69 956.83 L-13

g) Machinery

Tractor-trolley hour 6.000 282.50 1695.00 P&M-053

h) Overhead charges @ 0.1 on (f+g) 292.37

i) Contractor's profit @ 0.1 on (f+g+h) 321.60

22533.30

1609.52

say 1610.00

8.14 (iii) Hectometer stone (precast)

Unit = Nos.

Taking output = 33 Nos.

a) M-15 grade of concrete cum 1.580 4228.00 6680.24

b) Steel reinforcement @ 5 kg per sqm kg 66.000 65.10 4296.67

c) Excavation in soil for foundation cum 1.390 138.00 191.82

d) Painting two coats on concrete surface sqm 6.270 40.00 250.80 Item 8.8

330.000 0.30 99.00 Item 8.3

Transportation and fixing

f) Labour

Mate day 0.340 151.44 51.49 L-12

Mason day 1.500 223.36 335.04 L-11

Mazdoor day 7.000 136.69 956.83 L-13

g) Machinery

Tractor-trolley hour 6.000 282.50 1695.00 P&M-053

h) Overhead charges @ 0.1 on (f+g) 303.84

i) Contractor's profit @ 0.1 on (f+g+h) 334.22

15194.94

460.45

say 460.00

Note

Rate for each 5th km stone = (a+b+c+ d+e +f+g+h +i ) /6

Item 12.8 (A)

Item 13.6 /1000

Item No. 3.13

e) Lettering on km post ( average 12 letters of 10 cm height each)

per cm per letter

Cost for 14 Nos. ordinary km stone = (a+b+ c +d+e+f+g+h+i)

Rate for each ordinary km stone = (a+b+ c +d+e+f+g+h+j) /14

Item 12.8 (A)

Item 13.6 /1000

Item No. 3.13

e) Lettering on km post (average 1 letter of 10 cm height each)

per cm per letter

Cost for 33 Nos. Hectometer stone = (a+b +c +d+e+f+ g+h+i)

Rate for each Hectometer stone = (a+b +c +d+e+f+ g+h+i) 33

The rate for excavation, cement concrete, steel reinforcement, painting and lettering may be taken from respective chapters.

Page 135: Standard Data Book - Rate Analysis

Page 12 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

8.15 805 Road Delineators

Unit = Each

Taking output= 30 Nos.

a) Labour

Mate day 0.040 151.44 6.06 L-12

Mazdoor for fixing day 1.000 136.69 136.69 L-13

b) Material

each 30.000 834.40 25032.00 M-091

Add 10 per cent cost of material for installation 2503.20

c) Overhead charges @ 0.1 on (a+b) 2767.79

d) Contractor's profit @ 0.1 on (a+b+c) 3044.57

Cost for 30 Nos. delineators = (a+b+ c+d) 33490.32

Rate per delineators = (a+b+c+d) /30 1116.34 say 1116.00

Note

8.16 806 Boundary pillar

Unit = Each

Taking output = 57 Nos.

a) M-15 grade of the boundary stone cum 1.250 4228.00 5285.00

b) Steel reinforcement kg 79.800 65.10 5195.06

c) Excavation in soil cum 10.720 138.00 1479.36

d) Lettering, each 10 cm high 2280.000 0.30 684.00 Item 8.3

Transportation and fixing

e) Labour

Mate day 0.570 151.44 86.32 L-12

Mazdoor day 14.250 136.69 1947.83 L-13

f) Machinery

Tractor-trolley hour 6.000 282.50 1695.00 P&M-053

g) Material

Stone spall cum 11.970 921.00 11024.37 M-008

h) Overhead charges @ 0.1 on (e+f+g) 1475.35

i) Contractor's profit @ 0.1 on (e+f+g+h) 1622.89

30495.18

535.00

say 535.00

Note

8.17 807 G.I Barbed Wire Fencing 1.2 Metre High

Supplying and installation of delineators (road way indicators, hazard markers, object markers), 80-100 cm high above ground level, painted black and white in 15 cm wide strips, fitted with 80 x 100 mm rectangular or 75 mm dia circular reflectorised panels at the top, buried or pressed into the ground and conforming toIRC-79 and the drawings.

Cost of approved type of delineators from ISI certified firm as per the standard drawing given in IRC - 79

In case of soft ground, a proper foundation may be provided as per approved design. In case foundation is required to be provided, the items of excavation and foundation concrete are required to be measured and paid separately.

Reinforced cement concrete M15 grade boundary pillars of standard design as per IRC:25-1967, fixed in position including finishing and lettering but excluding painting

Item 12.8 (A)

Item 13.6 /1000

Item No. 3.13

per letter per cm high

Cost for 57 Nos. boundary pillar = (a+b +c+d +e+ f+g+h+i )

Rate for each boundary pillar = (a+b+c+d+e+ f+g+h+i)/57

In case of soft ground, a proper foundation may be provided as per approved design. In case foundation is required to be provided, the items of excavation and foundation concrete are required to be measured and paid separately.

Page 136: Standard Data Book - Rate Analysis

Page 13 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Unit = per running metre

Taking output = 30 metres

a) Labour

Mate day 0.090 151.44 13.63 L-12

Blacksmith day 0.250 264.50 66.13 L-02

Mazdoor day 2.000 136.69 273.38 L-13

b) Material

kg 31.420 65.56 2059.90 M-063

kg 80.500 45.00 3622.50

113.65

c) Painting

sqm 2.110 46.00 97.06 Item 8.9

d) Overhead charges @ 0.1 on (a+b) 614.92

e) Contractor's profit @ 0.1 on (a+b+d) 676.41

Cost for 30 metres fencing = a+b+c+d+e 7537.57

Rate per metre = (a+b+c+d+e)/30 251.25 say 251.00

Note

8.18 807 G.I Barbed Wire Fencing 1.8 Metre High

Unit = per running metre

Taking output = 30 metres

a) Labour

Mate day 0.120 151.44 18.17 L-12

Blacksmith day 0.400 264.50 105.80 L-02

Mazdoor day 2.500 136.69 341.73 L-13

b) Material

kg 40.150 65.56 2632.23 M-063

kg 152.000 45.00 6840.00

189.44

c) Painting

sqm 3.960 46.00 182.16 Item 8.9

d) Overhead charges @ 0.1 on (a+b) 1012.74

e) Contractor's profit @ 0.1 on (a+b+d) 1114.01

Cost for 30 metres fencing = a+b+c+d+e 12436.29

Rate per metre fencing = (a+b+c +d+e)/30 414.54 say 415.00

Providing and fixing 1.2 metres high GI barbed wire fencing with 1.8 m angle iron posts 40 mm x 40 mm x 6 mm placed every 3 metres center to center founded in M15 grade cement concrete, 0.6 metre below ground level, every 15th post, last but one end post and corner post shall be strutted on both sides and end post on one side only and provided with 9 horizontal lines and 2 diagonals interwoven with horizontal wires, fixed with GI staples, turn buckles etc complete as per clause 807

Barbed wire 335 metres length @ 9.38 kg per 100 metres

MS angle iron 40 mm x 40mm x 6 mm, 23 metres in length @ 3.5 kg per metre

M-179 /1000

Add for GI staple binding wire, drilling holes etc. @ 2 per cent of the cost of material

Applying two coats of painting on exposed surface of angle iron posts ( Rate as per item no. 8.9)

Cost of excavation for foundation and foundation concrete to be added separately in the cost estimate as per approved design. The rate for these items may be taken from respective chapters.

Providing and fixing 1.8 metres high GI barbed wire fencing with 2.4 m angle iron posts 50 mm x 50 mm x 6 mm placed every 3 metres center to center founded in M15 grade cement concrete, 0.6 metre below ground level, every 15th post, last but one end post and corner post shall be strutted on both sides and end post on one side only and provided with 12 horizontal lines and 2 diagonals interwoven with horizontal wires, fixed with GI staples, turn buckles etc complete as per clause 807

Barbed wire 428 metres length @ 9.38 kg per 100 metres

MS angle iron 50 mm x 50 mm x 6 mm,33.8 metres in length @ 4.5 kg per metre

M-179 /1000

Add for GI staple, binding wire, drilling holes etc. @ 2 per cent of the cost of material

Applying two coats of painting on exposed surface of angle iron posts

Page 137: Standard Data Book - Rate Analysis

Page 14 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Note

8.19 Fencing With Welded Steel Wire Fabric 75 mm x 50 mm

Unit = Running metre

Taking output = 30 m

a) Labour

Mate day 0.120 151.44 18.17 L-12

Welder day 1.000 264.50 264.50 L-02

Mazdoor day 2.000 136.69 273.38 L-13

b) Material

i) Angle iron for posts 50 x 50 x 6 mm kg 106.000 45.00 4770.00

ii) Runner flat 50 x 5 mm kg 26.000 45.00 1170.00

kg 151.000 61.00 9211.00 M-191

OR

kg 293.000

c) Machinery

Tractor-trolley hour 0.100 282.50 28.25 P&M-053

d) Painting

Painting two coats including priming sqm 8.000 46.00 368.00 Item 8.9

e) Overhead charges @ 0.1 on (a+b+c) 1573.53

f) Contractor's profit @ 0.1 on (a+b+c+e) 1730.88

Cost for 30 metre = a+b+c+d+e+f 19407.72

Rate per metre = (a+b+c+d+e+f)/30 646.92 say 647.00

Note

8.20 808

Unit = Running metre

Taking output = 10metres

cum 1.296 138.00 178.85

cum 0.648 4228.00 2739.74

iii) Painting of pipe sqm 4.710 46.00 216.66 Item 8.9

sqm 2.160 46.00 99.36 Item 8.9

a) Labour (For fixing at site)

Mate day 0.010 151.44 1.51 L-12

Mazdoor day 0.250 136.69 34.17 L-13

Plumber day 0.010 264.50 2.65 L-02

b) Material

Steel pipe 50 mm external dia as per IS:1239 metre 30.000 364.00 10920.00 M-175

Cost of excavation for foundation and foundation concrete to be added separately in the cost estimate as per approved design. The rate for these items may be taken from respective chapters.

Suggest

ive

Providing 1.20 metre high fencing with angle iron posts 50 mm x 50 mm x 6 mm at 3 metre center to center with 0.40 metre embedded in M15 grade cement concrete, corner, end and every 10th post to be strutted, provided with welded steel wire fabric of 75 mm x 50 mm mesh or 75 mm x 25 mm mesh and fixed to iron posts by flat iron 50 x 5 mm and bolts etc. complete in all respects.

M-179 /1000

M-179 /1000

iii) Welded steel wire fabric 75x50 mm mesh @ 4 kg/sqm,4 x 30 x 1.2 + 5 per cent wastage

Welded steel wire fabric 75 x 25 mm mesh @ 7.75 kg/sqm, 7.75 x 30 x 1.2 + 5 per cent wastage

Add 2.5 per cent of cost of material for drilling holes in angles, flats, splitting angle at bottom, nuts and bolts and welded consumables

i) Adopt any one type of welded steel wire fabric 75 x 50 mm or 75 x 25 mm as per approved design.

ii) The item of excavation and cement concrete in foundation shall be measured and paid separately

Tubular Steel Railing on Medium Weight Steel Channel ( ISMC series) 100 mm x 50 mm

Providing, fixing and erecting 50 mm dia steel pipe railing in 3 rows duly painted on medium weight steel channels (ISMC series) 100 mm x 50 mm, 1.2 metres high above ground, 2 m centre to centre, complete as per approved drawings

i) Excavation for foundation (6 Nos)6 x 0.6 x 0.6 x 0.6

Item No. 3.13

ii) Foundation concrete M-15 grade PCC 6 x 0.6 x 0.6 x 0.3

Item 12.8 (A)

iv) Painting of channel section 6 nos,1.8 metres each 0.2 x 1.8 x 6 = 2.16

Page 138: Standard Data Book - Rate Analysis

Page 15 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

kg 99.360 45.00 4471.20

Add for drilling holes @ 2 per cent of cost of channels 89.42

c) Machinery

Tractor-trolley hour 0.040 282.50 11.30 P&M-053

d) Overhead charges @ 0.1 on (a+b+c) 1875.36

e) Contractor's profit @ 0.1 on (a+b+c+d) 2062.89

Cost for 10 metre =i+ii+iii+iv+ a+b+c+d+e 22703.12

Rate per metre = (i+ii+iii+iv+a+b+c+d+e)/10 2270.31 say 2270.00

8.21 808

Unit = Running metre

Taking output = 10metres

cum 1.296 138.00 178.85

cum 0.648 4228.00 2739.74

cum 0.320 5317.00 1701.44

iv) Painting of pipe sqm 4.710 46.00 216.66 Item 8.9

a) Labour

Mate day 0.014 151.44 2.12 L-12

Mazdoor day 0.350 136.69 47.84 L-13

Plumber day 0.010 264.50 2.65 L-02

b) Material

Steel pipe 50 mm dia as per IS:1239 metre 30.000 364.00 10920.00 M-175

c) Machinery

Tractor-trolley hour 0.250 282.50 70.63 P&M-053

d) Overhead charges @ 0.1 on (a+b+c) 1104.32

e) Contractor's profit @ 0.1 on (a+b+c+d) 1214.76

Cost for 10 metre =i+ii+iii+iv+ a+b+c+d+e 18199.00

Rate per metre = (i+ii+iii+iv+a+b+c+d+e)/10 1819.90 say 1820.00

8.22 809 Reinforced Cement Concrete Crash Barrier

Unit = Linear metre

Taking output = 10 m

(i) a) M 20 grade concrete

M 20 grade concrete cum 3.000 5317.00 15951.00

b) Labour

Mate day 0.040 151.44 6.06 L-12

Mazdoor day 1.000 136.69 136.69 L-13

c) Material

HYSD steel reinforcement including dowel bars tonne 0.280 45000.00 12600.00 M-082

Pre-moulded asphalt filler board sqm 0.320 425.00 136.00 M-144

d) Overhead charges @ 0.1 on (b+c) 1287.87

e) Contractor's profit @ 0.1 on (b+c+d) 1416.66

Cost for 10 metre = a+b+c+d+e 34687.71

Medium weight steel channel (ISMC series) 100 mm x 50 mm,10.8 metres length @ 9.2 kg per metre

M-179 /1000

Tubular Steel Railing on Precast RCC Posts, 1.2 m High Above Ground Level

Providing, fencing and erecting 50 mm dia painted steel pipe railing in 3 rows on precast M20 grade RCC vertical posts1.8 metres high (1.2 m above GL) with 3 holes 50 mm dia for pipe, fixed 2 metres centre to, complete as per approved drawing

i) Excavation for foundation (6 Nos)6 x 0.6 x 0.6 x 0.6

Item No. 3.13

ii) Foundation concrete M - 15 grade PCC 6 x 0.6 x 0.6 x 0.3

Item 12.8 (A)

iii) RCC M - 20 for pre cast posts 6 nos of 1.8 metres each

Item 14.1(A)

Provision of an Reinforced cement concrete crash barrier at the edges of the road, approaches to bridge structures and medians, constructed with M-20 grade concrete with HYSD reinforcement conforming to IRC:21 and dowel bars 25 mm dia, 450 mm long at expansion joints filled with pre-moulded asphalt filler board, keyed to the structure on which it is built and installed as per design given in the enclosure to MOST circular No. RW/NH - 33022/1/94-DO III dated 24 June 1994 as per dimensions in the approved drawing and at locations directed by the Engineer, all as specified

Item 14.1(A)

Page 139: Standard Data Book - Rate Analysis

Page 16 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Rate per metre = (a+b+c+d+e)/10 3468.77 say 3469.00

Note

8.23 810 Metal Beam Crash Barrier

A Type - A, "W" : Metal Beam Crash Barrier

Unit = Running metre

Taking output = 4.5 metre length

a) Labour

Mate day 0.060 151.44 9.09 L-12

Blacksmith day 0.500 264.50 132.25 L-02

Mazdoor day 1.000 136.69 136.69 L-13

b) Machinery

Tractor-trolley hour 0.100 282.50 28.25 P&M-053

c) Material

kg 41.210 45.00 1854.45

kg 88.560 45.00 3985.20

kg 16.240 45.00 730.80

Nuts and bolts kg 20.000 64.07 1281.40 M-130

1962.96

d) Overhead charges @ 0.1 on (a+b+c) 1012.11

e) Contractor's profit @ 0.1 on (a+b+c+d) 1113.32

Cost for 4.5 metre = a+b+c+d+e 12246.52

Rate per metre = (a+b+c+d+e)/4.5 2721.45 say 2721.00

8.23 B Type - B, "THRIE" : Metal Beam Crash Barrier

Unit = Running metre

Taking output = 4.5 metre length

a) Labour

Mate day 0.060 151.44 9.09 L-12

Blacksmith day 0.500 264.50 132.25 L-02

Mazdoor day 1.000 136.69 136.69 L-13

b) Machinery

Tractor-trolley hour 0.100 282.50 28.25 P&M-053

c) Material

kg 72.940 49.00 3574.06 M-088

kg 98.400 45.00 4428.00

Spacer 150 x 75 x 5 mm channel 0.546 m long,3 Nos kg 26.860 45.00 1208.70

i) Excavation and backfilling are incidental to work and not to be measured separately.

ii) Rate for RCC M 20 may be taken from chapter on super structure.

Providing and erecting a "W" metal beam crash barrier comprising of 3 mm thick corrugated sheet metal beam rail, 70 cm above road/ground level, fixed on ISMC series channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to centre, 1.8 m high, 1.1 m below ground/road level, all steel parts and fitments to be galvanised by hot dip process, all fittings to conform to IS:1367 and IS:1364, metal beam rail to be fixed on the vertical post with a spacer of channel section 150 x 75 x 5 mm, 330 mm long complete as per clause 810

Corrugated sheet,3 mm thick, "W" beam section railing,4.5 m in length

M-179 /1000

Channel post 150 x 75 x 5 mm,1.8 m long,3 Nos @ 16.4 kg per metre

M-179 /1000

Spacer 150 x 75 x 5 mm channel 0.33 m long,3 Nos @ 16.4 kg per metre

M-179 /1000

Add 25 per cent of the cost of material for fabrication, nuts, bolts and washers etc.)

Providing and erecting a "Thrie" metal beam crash barrier comprising of 3 mm thick corrugated sheet metal beam rail, 85 cm above road/ground level, fixed on ISMC series channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to centre, 2 m high with 1.15 m below ground level, all steel parts and fitments to be galvanised by hot dip process, all fittings to conform to IS:1367 and IS:1364, metal beam rail to be fixed on the vertical post with a space of channel section 150 x 75 x 5 mm, 546 mm long complete as per clause 810

Corrugated sheet,3 mm thick, "Thrie" beam section railing,4.5 m in length

Channel post 150 x 75 x 5 mm, 2 m long,3 Nos @ 16.4 kg per metre

M-179 /1000

M-179 /1000

Page 140: Standard Data Book - Rate Analysis

Page 17 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Nuts and bolts kg 30.000 64.07 1922.10 M-130

1669.93

d) Overhead charges @ 0.1 on (a+b+c) 1310.91

e) Contractor's profit @ 0.1 on (a+b+c+d) 1442.00

Cost for 4.5 metre = a+b+c+d+e 15861.97

Rate per metre= (a+b+c+d+e)/4.5 3524.88 say 3525.00

Note

8.24 811 Road Traffic Signals electrically operated

Note

8.25 Flexible Crash Barrier, Wire Rope Safety Barrier

Unit = Running metre

Taking output = 15 metre

a) Labour

Mate day 0.120 151.44 18.17 L-12

Mazdoor day 2.000 136.69 273.38 L-13

Blacksmith day 1.000 264.50 264.50 L-02

b) Material

i) RS Joist 100 x 75 mm - 16.5 m @ 11.5 kg per metre kg 190.000 45.00 8550.00

kg 46.000 45.00 2070.00

kg 188.400 45.00 8478.00

kg 65.000 61.00 3965.00 M-177

1153.15

c) Painting

Applying 2 coats of painting on exposed surface sqm 16.500 46.00 759.00 Item 8.9

d) Machinery

Tractor-trolley hour 0.250 282.50 70.63 P&M-053

e) Overhead charges @ 0.1 on (a+b+d) 2484.28

f) Contractor's profit @ 0.1 on (a+b+d+e) 2732.71

Cost for 15 m = a+b+c+d+e+f 30818.82

Rate per m = (a+b+c+d+e+f)/15 2054.59 say 2055.00

Note

8.26 Anti-Glare Devices in Median

A Plantation

Add 15 per cent of the cost of material for fabrication, nuts, bolts and washers etc.)

In the case of median crash barrier, 'W' metal beam or thrie beam section should be provided on both sides of the vertical posts fixed in the median. Extra provision for metal beam railing and spacer is required to be made when fixed in the median depending on approved design.

Since it is a ready made item commercially produced and erected by specialised firm in the electrical and electronic field, rate may be taken based on market enquiry from firms specialised in this field and ISI certified for the approved design and drawing.

Suggestive

Providing and erecting a wire rope safety barrier with vertical posts of medium weight RS Joist (ISMB series) 100 mm x 75 mm (11.50 kg/m), 1.50 m long 0.85 m above ground and 0.65 m below ground level, split at the bottom for better grip, embedded in M 15 grade cement concrete 450 x 450 x 450 mm, 1.50 m center to center and with 4 horizontal steel wire rope 40 mm dia and anchored at terminal posts 15 m apart. Terminal post to be embedded in M 15 grade cement concrete foundation 2400 x 450 x 900 mm (depth), strengthened by a strut of RS joist 100 x 75 mm, 2 m long at 450 inclination and a tie 100 x 8 mm, 1.50 m long at the bottom, all embedded in foundation concrete as per approved design and drawing, rate excluding excavation and cement concrete.

M-179 /1000

ii) Struts - 2 Nos. for terminal posts,2 m long each 2 x 2 x 11.50

M-179 /1000

iii) Tie 2 Nos. of 8 mm steel plate,1.5 sqm each for terminal posts @ 62.80 kg/sqm (2 x 1.5)

M-179 /1000

iv) Steel wire rope 40 mm, including 7.50 per cent extra for fixing at ends 15 x 4 x 1.075 @ 1 kg per m

Add 5 per cent of cost of material for drilling, gripping, fixing, fabrication and welding consumables

The items of excavations and cement concrete works will be measured and included separately as per the approved designs and drawings.

Suggestive

Page 141: Standard Data Book - Rate Analysis

Page 18 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

B

Unit = Running metre

Taking output = one metre

a) Labour

Mate day 0.004 151.44 0.61 L-12

Mazdoor day 0.100 136.69 13.67 L-13

b) Material

i) 25 mm steel pipe metre 16.000 182.00 2912.00 M-174

kg 4.320 45.00 194.40

kg 4.800 45.00 216.00

166.12

c) Painting

Applying 2 coats of painting on exposed surface sqm 1.830 46.00 84.18 Item 8.9

d) Overhead charges @ 0.1 on (a+b) 350.28

e) Contractor's profit @ 0.1 on (a+b+d) 385.31

Rate per metre = a+b+c+d+e 4322.56 say 4323.00

Note

8.26 C Anti-glare screen with rectangular vane of MS sheet

Unit = Running metre

Taking output = 1.50 metre

a) Labour

Mate day 0.004 151.44 0.61 L-12

Mazdoor day 0.100 136.69 13.67 L-13

b) Material

i) Angle iron post,50 x 50 x 6 mm, length 2.35 m kg 10.580 45.00 476.10

ii) MS sheet 3 mm thick @ 24 kg/sqm kg 9.000 45.00 405.00

44.06

c) Machinery

Tractor-trolley hour 0.100 282.50 28.25 P&M-053

d) Painting

Applying 2 coats of painting sqm 0.850 46.00 39.10 Item 8.9

e) Overhead charges @ 0.1 on (a+b+c) 96.77

f) Contractor's profit @ 0.1 on (a+b+c+e) 106.44

Cost for 1.5 m = a+b+c+d+e+f 1209.99

Plantation of shrubs and plants of approved species in the median. apart from cutting off glare from vehicle coming from opposite direction, these plants provide a pleasant envoirenment and are eco-friendly. The rate for this item is available in the chapter 11 on horticulture.

Anti-glare screen with 25 mm steel pipe framework fixed with circular and rectangular vans

Providing and erecting an anti - glare screen with 25 mm dia vertical pipes fabricated and framed in the form of panels of one metre length and 1.75 metre height fixed with circular vane 250 mm dia at top and rectangular vane 600 x 300 mm at the middle, made out of steel sheet of 3 mm thickness, end vertical pipes of the panel made larger for embedding in foundation concrete, applying 2 coats of paint on all exposed surfaces, all as per approved design and drawings.

ii) MS sheet for 600 x 300 x 3 mm rectangular vane, one number @ 24kg/sqm

M-179 /1000

iii) MS sheet for 250 mm dia circular vane 3 mm thick,4 numbers @ 24 kg/sqm

M-179 /1000

Add 5 per cent cost of material for fabrication, welding, bending, nuts, bolts etc

The items of excavation and cement concrete as per approved design to be measured and paid separately

Providing and erecting anti - glare screen with rectangular vanes of size 750 x 500 mm made from MS sheet, 3 mm thick and fixed on MS angle 50 x 50 x 6 mm at an angle of 450 to the direction of flow of traffic, 1.5 m center to center, top edge of the screen 1.75 m above ground level, vertical post firmly embedded in M-15 cement concrete foundation 0.60 m below ground level, applying 2 coats of paint on exposed faces, all complete as per approved design and drawings

M-179 /1000

M-179 /1000

Add 5 per cent of cost of material for fabrication, nuts, bolts etc

Page 142: Standard Data Book - Rate Analysis

Page 19 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Rate per metre = (a+b+c+d+e+f)/1.50 806.66 say 807.00

Note

8.27 Street Lighting

Unit = Each

Taking output = one light

a) Labour

Mate day 0.030 151.44 4.54 L-12

Mazdoor day 0.500 136.69 68.35 L-13

Electrician day 0.250 264.50 66.13 L-02

b) Material

each 1.000 1820.00 1820.00 M-171

ii) Sodium vapour lamp each 1.000 1213.00 1213.00 M-168

151.65

c) Painting

For Fixing in Median

sqm 5.750 46.00 264.50 Item 8.9

For fixing in Footpath

sqm 4.630 46.00 212.98 Item 8.9

(i) For Fixing in Median

d) Overhead charges @ 0.1 on (a+b) 332.37

e) Contractor's profit @ 0.1 on (a+b+d) 365.60

Rate per light for fixing in Median= a+b+c+d+e 4286.13 say 4286.00

(ii) For fixing in Footpath

Rate per light for Fixing in Footpath = a+b+c+d+e 4234.61 say 4235.00

Note

8.28 Lighting on Bridges

Unit = Each

Taking output = one light

a) Labour

Mate day 0.020 151.44 3.03 L-12

Mazdoor day 0.400 136.69 54.68 L-13

Electrician day 0.200 264.50 52.90 L-02

b) Material

each 1.000 1213.00 1213.00 M-170

ii) Sodium vapour lamp 70 watt each 1.000 1213.00 1213.00 M-168

24.26

c) Painting

The items of excavation and cement concrete as per approved design to be measured and paid separately. Rate of painting has been analaysed separately in this chapter.

Suggestive

Providing and erecting street light mounted on a steel circular hollow pole of standard specifications for street lighting, 9 m high spaced 40 m apart, 1.8 m overhang on both sides if fixed in the median and on one side if fixed on the footpath, fitted with sodium vapour lamp and fixed firmly in concrete foundation.

i) Steel circular hollow pole of standard specification for street lighting to mount light at 9 m height above road level

Add 5 per cent of cost of material for holder, electric cable, insulation, ladder, scaffolding etc

Providing two coats of alluminium paint over steel circular hollow pipe with overhang on both sides

Providing two coats of alluminium paint over steel circular hollow pipe with overhang on one side

The items of excavation and cement concrete foundation will be measured and included separately in the estimate as per approved design and drawing. The rate for painting has been analysed in this chapter.

Suggestive

Providing and fixing lighting on bridges, mounted on steel hollow circular poles of standard specifications, 5 m high fixed on parapets with cement concrete, 20 m apart and fitted with sodium vapour lamp

i) Steel circular hollow pole of standard specification for street lighting to mount light at 5 m above deck level

Add 1 per cent of cost of material for holder, electric cable, insulation, ladder, scaffolding etc

Page 143: Standard Data Book - Rate Analysis

Page 20 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

sqm 2.760 46.00 126.96 Item 8.9

d) Overhead charges @ 0.1 on (a+b) 256.09

e) Contractor's profit @ 0.1 on (a+b+d) 281.70

Rate per light = a+b+c+d+e 3225.61 say 3226.00

Note

8.29 Cable Duct Across the Road

(i) Single row for one utility service

Unit = Running metre

Taking output = 20metres

cum 2.360 5610.00 13239.60

b) Labour

Mate day 0.050 151.44 7.57 L-12

Mazdoor day 1.000 136.69 136.69 L-13

Mazdoor skilled day 0.250 164.69 41.17 L-15

c) Material

Reinforced Cement Concrete pipe 300 mm dia metre 20.000 1149.00 22980.00 M-151

cum 7.200 727.79 5240.09 M-009

Collar for joints 300 mm dia each 9.000 146.00 1314.00 M-083

Cement mortar 1:2 for joints cum 0.020 4152.00 83.04

d) Machinery

Tractor-trolley hour 0.500 282.50 141.25 P&M-053

e) Overhead charges @ 0.1 on (b+c+d) 2994.38

f) Contractor's profit @ 0.1 on (b+c+d+e) 3293.82

Cost for 20 metre = a+b+c+d+e+f 49471.61

Rate per metre = (a+b+c+d+e+f)/20 2473.58 say 2474.00

8.29 (ii) Double row for two utility services

Unit = Running metre

Taking output = 20metres

cum 3.370 5610.00 18905.70

b) Labour

Mate day 0.050 151.44 7.57 L-12

Mazdoor day 2.000 136.69 273.38 L-13

Mazdoor skilled day 0.250 164.69 41.17 L-15

c) Material

Reinforced Cement Concrete pipe 300 mm dia metre 40.000 1149.00 45960.00 M-151

cum 14.400 727.79 10480.18 M-009

Collar for joints 300 mm dia each 18.000 146.00 2628.00 M-083

Cement mortar 1:2 for joints cum 0.040 4152.00 166.08

d) Machinery

Tractor-trolley hour 1.000 282.50 282.50 P&M-053

e) Overhead charges @ 0.1 on (b+c+d) 5983.89

Providing two coats of alluminium paint over steel circular hollow pipe

The items of cement concrete to be measured and paid separately as per approved design. The rate for painting has already been analysed in this chapter.

Suggestive

Providing and laying of a reinforced cement concrete pipe duct, 300 mm dia, across the road (new construction), extending from drain to drain in cuts and toe of slope to toe of slope in fills, constructing head walls at both ends, providing a minimum fill of granular material over top and sides of RCC pipe as per IRC:98-1997, bedded on a 0.3 m thick layer of granular material free of rock pieces, outer to outer distance of pipe at least half dia of pipe subject to minimum 450 mm in case of double and triple row ducts, joints to be made leak proof, invert level of duct to be above higher than ground level to prevent entry of water and dirt, all as per IRC: 98 - 1997 and approved drawings.

a) Random Rubble masonry/Brick masonry in cement mortar 1:6 for head wall both side

Item 12.7 (Addl) B)

Granular soil with PI less than 6 for bedding and sides of pipe (0.6 x 0.6 x 20 m)

Item 12.6 (B)

a) Random Rubble brick/Brick masonry in cement mortar 1:6 for head wall both sides.

Item 12.7 (Addl) B)

Granular soil with PI less than 6 for bedding and sides of pipe (0.6 x 0.6 x 40 m)

Item 12.6 (B)

Page 144: Standard Data Book - Rate Analysis

Page 21 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

f) Contractor's profit @ 0.1 on (b+c+d+e) 6582.28

Cost for 20 metre = a+b+c+d+e+f 91310.75

Rate per metre = (a+b+c+d+e+f)/20 4565.54 say 4566.00

8.29 (iii) Triple rRow for three utility services

Unit = Running metre

Taking output = 20metres

cum 4.380 5610.00 24571.80

b) Labour

Mate day 0.160 151.44 24.23 L-12

Mazdoor day 3.000 136.69 410.07 L-13

Mazdoor skilled day 1.000 164.69 164.69 L-15

c) Material

Reinforced Cement Concrete pipe 300 mm dia metre 60.000 1149.00 68940.00 M-151

cum 21.600 727.79 15720.26 M-009

Collar for joints 300 mm dia each 27.000 146.00 3942.00 M-083

Cement mortar 1:2 for joints cum 0.060 4152.00 249.12

d) Machinery

Tractor-trolley hour 1.500 282.50 423.75 P&M-053

e) Overhead charges @ 0.1 on (b+c+d) 8987.41

f) Contractor's profit @ 0.1 on (b+c+d+e) 9886.15

Cost for 20 metre = a+b+c+d+e+f 133319.49

Rate per metre = (a+b+c+d+e+f)/20 6665.97 say 6666.00

Note

8.30 Highway Patrolling and Traffic Aid Post

8.31

8.32 Traffic Control System and Communication System

8.33 Gantry Mounted Variable Message Sign Board

a) Random Rubble brick/Brick masonry in cement mortar 1:6 for head wall both sides.

Item 12.7 (Addl) B)

Granular soil with PI less than 6 for bedding and sides of pipe (0.6 x 0.6 x 60 m)

Item 12.6 (B)

1.Inspection chamber at both ends is the responsibility of the agency who is laying the duct. Hence not included.

2.The rates for stone masonry / brick masonry and cement mortar to be adopted from respective clauses.

Suggestive

It is proposed to locate one Traffic Aid Post every 50-60 km of the highway.

The organisation and financial aspect are required to be finalised in consultation with administrative and traffic authorities .

Suggestive

Items Related to Underpass/ Subway/ Overhead Bridge/ Overhead Foot Bridge

The items involved for underpass/ subway/ overhead bridge/ overhead foot bridge are earthwork, plain cement concrete, plastering, painting, information sign etc. The rates for these items are available in respective chapters which can be adopted for the quantities derived from the approved designs and drawings

Suggestive

Providing a traffic control centre and communication system including telecommunication facilities and related accessories, CCTV, radar, vehicle detection camera, central computer system

These are specialised item of telecommunication system and are the commercial products. The designer is required to contact the manufacturers to ascertain market prices. In case of civil works required to be executed for these installations, pricing may be done as per rates in relevant chapters for quantities derived as per approved design and drawing.

As regards the locations where such devices are required to be installed, the traffic control authority should be consulted to finalise the location

Suggestive

Page 145: Standard Data Book - Rate Analysis

Page 22 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

(i) Gantry Support System

Unit = tonne

Taking output=1 tonne

a) Labour

Mate day 0.120 151.44 18.17 L-12

Mazdoor day 2.000 136.69 273.38 L-13

Blacksmith day 1.000 264.50 264.50 L-02

b) Material

tonne 1.050 54574.00 57302.70 M-060

8595.41

573.03

c) Machinery

Truck 10 tonne hour 1.000 315.27 315.27 P&M-057

d) Overhead charges @ 0.1 on (a+b+c) 6734.25

e) Contractor's profit @ 0.1 on (a+b+c+d) 7407.67

Rate per tonne = a+b+c+d+e 81484.37 say 81484.00

8.33 (ii) Message Display

8.34 Traffic Impact Attenuators at Abutments and Piers

A With Scrap Tyres

Unit = sqm

Taking output = 20sqm

a) Labour

Mate day 0.080 151.44 12.12 L-12

Mazdoor day 1.500 136.69 205.04 L-13

Blacksmith day 0.250 264.50 66.13 L-02

b) Material

Scrap tyres of size 900 x 20 each 80.000 364.00 29120.00 M-161

20 mm steel wire rope kg 150.000 61.00 9150.00 M-176

Add 1 per cent of cost of wire rope for clamps etc. 91.50

c) Machinery

Tractor-trolley hour 3.000 282.50 847.50 P&M-053

d) Overhead charges @ 0.1 on (a+b+c) 3949.23

e) Contractor's profit @ 0.1 on (a+b+c+d) 4344.15

Cost for 20 sqm = a+b+c+d+e 47785.65

Rate per sqm = (a+b+c+d+e)/20 2389.28 say 2389.00

8.34 B Using Plastic/Steel Barrel, Filled with Sand

Providing and erecting gantry mounted variable message sign board electronically operated capable of flashing the desired message over a designed support system of aluminium alloy or galvanised steel, erected as per approved design and drawings and with lateral clearance as per clause 802.3

Alluminium alloy/galvanised steel including 5 per cent wastage

Add 15 per cent of cost of material for fabrication and erection.

Add 1 per cent of cost of material for nuts, bolts and welding

Message display board 6 sqm electronically operated with complete electronic fitments for flashing the pre-determined messages.

This is a specilised commercial product and the lumpsum rate including erection at site is required to be as certained from the market and including in the rate analysis. The size of the board will vary depending upon specific location.

The rate for the gantry mounted variable sign would be the addition of cost of gantry support system as per approved design determined at (i) above and the cost of message display board as certained from the market at (ii) above

Suggestive

Provision and installation of traffic attenuators at abutment/pier of flyovers bridges using scrap tyres of size 100 x 20 retrieved from trucks laid in 2 rows and 4 tiers, one above the other and tied with 20 mm wire rope as per approved design and drawings.

Page 146: Standard Data Book - Rate Analysis

Page 23 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Unit = sqm

Taking output = 20sqm

a) Labour

Mate day 0.130 151.44 19.69 L-12

Mazdoor day 3.000 136.69 410.07 L-13

Blacksmith day 0.250 264.50 66.13 L-02

b) Material

Plastic barrels each 50.000

or

Steel barrels each 50.000 79.00 3950.00 M-172

Sand cum 8.000 828.00 6624.00 M-004

20 mm steel wire rope kg 15.000 61.00 915.00 M-176

Add 1 per cent of cost of wire rope for clamps etc. 9.15

c) Machinery

Tractor-trolley hour 2.000 282.50 565.00 P&M-053

d) Overhead charges @ 0.1 on (a+b+c) 1255.90

e) Contractor's profit @ 0.1 on (a+b+c+d) 1381.49

Cost for 20 sqm = a+b+c+d+e 15196.43

Rate per sqm = (a+b+c+d+e)/20 759.82 say 760.00

8.34 C With HI - DRO cell Sandwich (Patented)

Unit = sqm

Taking output = 10sqm

a) Labour

Mate day 0.100 151.44 15.14 L-12

Mazdoor day 2.500 136.69 341.73 L-13

b) Material

Plastic tubes 50 cm dia,1.2 m high each 40.000 3639.00 145560.00 M-139

Cost of water KL 12.000 10.00 120.00 M-189

20 mm steel wire rope kg 100.000 61.00 6100.00 M-176

Add 1 per cent of cost of wire rope for clamps etc. 61.00

c) Machinery

Tractor-trolley hour 2.000 282.50 565.00 P&M-053

Water tanker6 KL capacity hour 2.000 200.00 400.00 P&M-060

d) Overhead charges @ 0.1 on (a+b+c) 15316.29

e) Contractor's profit @ 0.1 on (a+b+c+d) 16847.92

Cost for 10 sqm = a+b+c+d+e 185327.07

Rate per sqm = (a+b+c+d+e)/10 18532.71 say 18533.00

8.35 Road Markers/Road Stud with Lense Reflector

Unit = Nos

Taking output = 50Nos

a) Labour

Mate day 0.040 151.44 6.06 L-12

Provision and installation of traffic impact attenuator at abutment/pier of flyovers bridges using plastic/steel barrels 0.60 m dia and 1.0 m in height, filled with sand in three rows and tied with20 mm steel wire rope as per approved design and drawings

(In this patented HI - DRO cell system, water gets discharged from plastic tubes on impact over a pre-determined time, thus absorbing the energy)

Providing and installing a patentend HI - DRO cell system as a traffic impact attenuators, using plastic tubes 50 cm dia, 1.2 m in height, 25 mm opening at the top, placed in three rows, filled with water and tied with a 20 mm steel wire rope

Suggestive

Providing and fixing of road stud 100x 100 mm, die-cast in aluminium, resistant to corrosive effect of salt and grit, fitted with lense reflectors, installed in concrete or asphaltic surface by drilling hole 30 mm upto a depth of 60 mm and bedded in a suitable bituminous grout or epoxy mortar, all as per BS 873 part 4:1973

Page 147: Standard Data Book - Rate Analysis

Page 24 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Mazdoor day 1.000 136.69 136.69 L-13

b) Material

each 50.000 546.00 27300.00 M-062

Add 10 per cent of cost of material for fixing and installation 2730.00

c) Overhead charges @ 0.1 on (a+b) 3017.27

d) Contractor's profit @ 0.1 on (a+b+c) 3319.00

Cost for 50 studs = a+b+c+d 36509.02

Rate per studs = (a+b+c+d)/50 730.18 say 730.00

8.36 Traffic Cone

Unit = Running metre

Taking output = 68 Nos.

a) Labour

Mate day 0.020 151.44 3.03 L-12

Mazdoor day 0.500 136.69 68.35 L-13

b) Material

Traffic cones with 150 mm reflective sleeve each 68.000 243.00 16524.00 M-186

c) Machinery

Tractor-trolley hour 0.100 282.50 28.25 P&M-053

d) Overhead charges @ 0.1 on (a+b+c) 1662.36

e) Contractor's profit @ 0.1 on (a+b+c+d) 1828.60

Cost for 68 Nos. = a+b+c+d+e 20114.58

Rate per metre = (a+b+c+d+e)/68 295.80 say 296.00

8.37 Roadside Amenities

A Rest areas

B

C Lawn

Providing a lawn planted with grass and its maintenance

8.38 Rumble Strips

Unit = sqm

Taking output = 100 sqm (including gaps)

Aluminium studs 100 x 100 mm fitted with lense reflectors

Suggestive

Provision of red fluorescent with white reflective sleeve traffic cone made of low density polyethylene (LDPE) material with a square base of 390 x 390 x 35 mm and a height of 770 mm, 4 kg in weight, placed at 1.5 m interval, all as per BS 873

Suggestive

Providing plainly furnished accommodation for rest rooms, dormitories, restaurants, stalls, shops, petrol pump, telephone booth, first aid room, traffic aid post, police assistance booth, including electricity, toilet and sewerage system

Pricing may be done based on current plinth area rates approved by PWD/CPWD/MES for a particular zone. Area is required to be assessed for specific location as per actual site conditions

Parking areas and bus laybyes for trucks, buses and light vehicles

Pricing of parking areas may be done for the quantities of various items based on the approved dimensions and pavement design for a particular terrain and soil. Rates for items may be from respective chapters.

Pricing of lawn may be done as per rates given in the chapter on horticulture for the quantities as per approved dimensions in the drawings

Suggestive

Provision of 15 nos rumble strips covered with premix bituminous carpet, 15-20 mm high at center, 250 mm wide placed at 1 m center to center at approved locations to control speed, marked with white strips of road marking paint.

The rate per sqm of premix carpet and road marking may be adopted from chapter 5 & 8 respectively for the quantities calculated from approved drawings

Page 148: Standard Data Book - Rate Analysis

Page 25 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

8.39 Policeman Umbrella

Unit = each

Taking output = one number

Earthwork cum

Cement Concrete cum

brick masonry or cum

stone masonry cum

Painting sqm 2.500

a) Labour

Mate day 0.090

Mazdoor day 1.000

Blacksmith day 1.000

Welder day 0.250

b) Material

Steel pipe 100 mm dia metre 3.500

Steel pipe 25 mm dia metre 10.000

CGI sheets kg 8.000

Add 25 per cent of cost of material for fabrication

c) Machinery

Tractor-trolley hour 0.500

d) Overheads @ per cent on (a+b+c)

e) Contractors Profit@ per cent on (a+b+c+d)

Rate per policeman umbrella = a+b+c+d+e

8.40 High Mast Pole Lighting at Interchanges and Flyovers

8.41 Toll Plaza

c) Toll booths with integrated roof cover

d) Barrier gates for individual lanes

Suggestive

Provision of a 2 m high (floor to roof) umbrella for traffic policeman at road crossings, where necessary, installed on a raised platform, built on a central support of a steel pipe 100 mm dia, roof made of 25 mm dia steel pipe to provide covered area of 3 sqm, roofed with CGI sheets, all steel parts to be given 2 coats of paint

Add 2 per cent of cost of material for welding consumables, J-hooks, washers etc.

suggestive

Providing and erecting a high mast pole lighting with 30 m high hot dip galvanised mast designed to withstand forces exerted with wind speeds of 180 km per hour with 3 seconds gust, as per IS:875 (Part 3) - 1978, fitted with a base flange, door at the base of mast with heavy duty internal lock, lantern carriage, suitable winching arrangement for safe working load of 750 kg and high powered electrically driven power tools for raising and lowering of lantern carriage, flexible 8 core electric cable, lightening conductor, earthing terminal, and fixing 2 nos aviation obstruction lights on top of the mast, all complete as per approved design and drawings

This is a specialised work and is generally done by firms who specialise in such jobs. The detailed designs and estimates are submitted by the firms along with their tender for checks by the Department. The cost of this work is required to be worked out based on approved design, drawings and estimate of the lowest tender. A separate contract for this work is concluded as the contractors for road and bridge works generally donot undertake such jobs.

The construction, operation and maintenance of Toll Plaza can be broken into separate items of work as under based on the approved design and drawings:-

a) Provision of toll collection service lane to separate different categories of vehicles for purpose of toll collection. This involves considerable increase in carriage way width

b) Provision of 2.5 m wide separators for different toll collection service lanes for safety

e) Provision of building to provide facility to toll plaza personnel

Quantities of these items to be calculated as per approved design and cost added as per rates of these items given in chapter 3 and 13

Page 149: Standard Data Book - Rate Analysis

Page 26 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

f) Toll plaza office equipment and furniture

i) High mast lighting

j) Pavement marking

k) Overhead signs

l) Fixed message signs (Advance)

m) Variable message signs

n) Traffic cones and pylons

o) First aid post

p) Traffic aid post and security

8.42 Safety Devices and Signs in Construction Zones

Unit = each

Taking output = one sign post

a) Diversion one km ahead

b) Traffic sign ahead

c) Road ahead closed

d) Men at work

e) Road narrow

f) Single file traffic

g) Right lane diverted

h) Left lane diverted

i) Right lane closed

j) Left lane closed

k) Median closed

l) Diversion to other carriageway

m) Traffic signal ahead

n) Two way traffic

o) Un - even road

p) Slippery road

q) Loose chippings

r) Dual carriageway ends

s) Diversion

t) Do not enter

u) Road closed

v) Stop

w) Slow

x) One way

y) Give way

z) Overtaking prohibited

aa) Speed limit

bb) Weight limit

cc) Height and length limit

dd) No stopping or standing

g) Water supply, electricity, sanitation, septic-tank system and drainage

h) Telephone, intercomes, wireless communication system

The quantities for the above mentioned items may be calculated from the approved design and drawings and their rates adopted from respective chapters of the Standard Data Book

Provision and fixing of traffic signs for limited period at suitable locations in construction zone comprising of warning zone, approach transition zone, working zone and terminal transition zone with a minimum distance of 60 cm from the edge of the kerb in case of kerbed roads and 2 to 3 m from the edge of the carriageway in case of un-kerbed roads, the bottom edge of the lowest sign plate to be not less than 2 m above the road level, fixed on 60 mm x 60 mm x 6 mm angle iron post, founded and installed as per approved design and drawings, removed and disposed of after completion of construction work, all as per IRC:SP:55-2001

Following types of signs are required to be fixed in construction zones for safety of traffic

Page 150: Standard Data Book - Rate Analysis

Page 27 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

8.43 Portable Barricade in Construction Zone

Unit = each

Taking output = one steel portable barricade

a) Labour

Mate day 0.020 151.44 3.03 L-12

Mazdoor day 0.250 136.69 34.17 L-13

Painter day 0.500 223.36 111.68 L-18

Welder day 0.250 264.50 66.13 L-02

b) Material

Angle iron 45 x 45 x 5 mm kg 25.000 45.00 1125.00

MS sheet 300 mm wide,2.5 m long and 2.6 mm thick kg 15.000 45.00 675.00

Paint litre 0.500 192.81 96.41 M-131

36.00

c) Overhead charges @ 0.1 on (a+b) 214.74

d) Contractor's profit @ 0.1 on (a+b+c) 236.22

Rate per barricade = a+b+c+d 2598.37 say 2598.00

8.44 Permanent Type Barricade in Construction Zone

A With steel components

Unit = each

Taking output = one barricade

a) Labour

Mate day 0.050 151.44 7.57 L-12

Mazdoor day 0.300 136.69 41.01 L-13

Painter day 0.600 223.36 134.02 L-18

Welder day 0.300 264.50 79.35 L-02

b) Material

Angle iron 50 x 50 x 5 mm,2 m long,2 Nos. kg 15.000 45.00 675.00

kg 50.000 45.00 2250.00

Paint litre 1.000 192.81 192.81 M-131

58.50

c) Overhead charges @ 0.1 on (a+b) 343.83

d) Contractor's profit @ 0.1 on (a+b+c) 378.21

Rate per barricade = a+b+c+d 4160.29 say 4160.00

8.44 B With wooden components

ee) Any other warning or regulatory safety sign as per site requirement and consistent with IRC:SP:55-2001 and IRC:67

The rate for traffic signs are already worked out and given elsewhere in this chapter. The same may be adopted.

suggestive

Installation of a steel portable barricade with horizontal rail 300 mm wide, 2.5 m in length fitted on a 'A' frame made with 45 x 45 x 5 mm angle iron section, 1.5 m in height, horizontal rail painted (2 coats) with yellow and white stripes, 150 mm in width at an angle of 450, 'A' frame painted with 2 coats of yellow paint, complete as per IRC:SP:55-2001

M-179 /1000

M-179 /1000

Add 2 per cent of cost of steel for welding consumables, nuts & bolts and drilling holes

suggestive

Construction of a permanent type barricade made of steel components, 1.5 m high from road level, fitted with 3 horizontal rails 200 mm wide and 4 m long on 50 x 50 x 5 mm angle iron vertical support, painted with yellow and white strips, 150 mm in width at an angle of450, complete as per IRC:SP:55-2001

M-179 /1000

MS sheet of 12 SWG,3 Nos of 200 mm width and 4 m length

M-179 /1000

Add 1 per cent of cost of steel for welding consumables, nuts & bolts and drilling holes

Page 151: Standard Data Book - Rate Analysis

Page 28 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Unit = each

Taking output = one barricade

a) Labour

Mate day 0.050 151.44 7.57 L-12

Mazdoor day 0.300 136.69 41.01 L-13

Painter day 0.600 223.36 134.02 L-18

Carpenter day 0.600 264.50 158.70 L-04

b) Material

Timber cum 0.180 24255.00 4365.90 M-185

Add 1 per cent of cost of timber for nuts & bolts, nails, etc. 43.66

c) Overhead charges @ 0.1 on (a+b) 475.09

d) Contractor's profit @ 0.1 on (a+b+c) 522.59

Rate per barricade = a+b+c+d 5748.53 say 5749.00

8.44 C With bricks

Unit = each

Taking output = one barricade

a) Labour

Mate day 0.240 151.44 36.35 L-12

Mazdoor day 3.000 136.69 410.07 L-13

Painter day 1.000 223.36 223.36 L-18

Mason day 2.000 223.36 446.72 L-11

b) Material

Brick each 1800.000 4.42 7952.72 M-079

Cement kg 22.000 5.00 110.00

Sand cum 0.090 710.46 63.94 M-005

Paint litre 1.250 192.81 241.01 M-131

c) Overhead charges @ 0.1 on (a+b) 948.42

d) Contractor's profit @ 0.1 on (a+b+c) 1043.26

Rate per barricade = a+b+c+d 11475.85 say 11476.00

8.45 Drum Delineator in Construction Zone

Unit = each

Taking output = one drum delineator

a) Labour

Mate day 0.020 151.44 3.03 L-12

Mazdoor day 0.250 136.69 34.17 L-13

Painter day 0.250 223.36 55.84 L-18

b) Material

each 1.000 79.00 79.00 M-172

Paint litre 0.500 192.81 96.41 M-131

c) Overhead charges @ 0.1 on (a+b) 26.84

d) Contractor's profit @ 0.1 on (a+b+c) 29.53

Rate per drum delineator = a+b+c+d 324.82 say 325.00

Construction of a permanent type barricade made of wooden components, 1.5 m high from road level, fitted with 3 horizontal planks 200 mm wide and 3.66 m long on 100 x 100mm wooden vertical post, painted with yellow and white strips, 150 mm in width at an angle of450, complete as per IRC:SP:55-2001

Construction of a permanent type barricade made with brick work in mud mortar, 1.5 m high, 4 m long, 600 mm thick, plastered with cement mortar 1:6, painted with yellow and white strips

M-081 /1000

suggestive

Provision of metal drum/empty bitumen drum delineator, 300 mm in diameter, 800 mm high, filled with earth for stability, painted in circumferential strips of alternate black and white 100 mm wide fitted with reflectors 3 Nos of 7.5 cm dia, all as per IRC:SP:55-2001

Steel drum 300 mm dia 1.2 m high/empty bitumen drum

Page 152: Standard Data Book - Rate Analysis

Page 29 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

8.46 Flagman

Unit = each

Taking output = one flagman

a) Labour

Mate day 0.040 151.44 6.06 L-12

Mazdoor day 1.000 136.69 136.69 L-13

b) Material

Flag of red color cloth 600 x 600 mm each 1.000 91.00 91.00 M-099

each 1.000 122.00 122.00 M-196

c) Overhead charges @ 0.1 on (a+b) 35.57

d) Contractor's profit @ 0.1 on (a+b+c) 39.13

Rate per flagman = a+b+c+d 430.45 say 430.00

suggestive

Positioning of a smart flagman with a yellow vest and a yellow cap and a red flag 600 x 600 mm securely fastened to a staff 1 m in length for guiding the traffic

Wooden staff for fastening of flag 25 mm dia, one m long

Page 153: Standard Data Book - Rate Analysis

Page 1 of 280

CHAPTER-9 PIPE CULVERTS

Sr No Description Unit Quantity Rate Rs Cost Rs

9.1 408 PCC 1:3:6 in Foundation

Unit = cumTaking output = 15 cuma) Labour

Mate day 0.640 151.44 96.92 L-12Mason day 1.000 223.36 223.36 L-11Mazdoor day 15.000 136.69 2050.35 L-13

b) Material40mm Aggregate at site cum 13.800 916.00 12640.80 M-055Sand at site cum 6.900 710.46 4902.17 M-005Cement at site tonne 3.300 5000.00 16500.00 M-081Cost of water KL 18.000 10.00 180.00 M-189

c) MachineryConcrete mixer0.4/ 0.28 cum hour 6.000 233.00 1398.00 P&M-009Generator set 33 KVA hour 6.000 406.80 2440.80 P&M-079Water tanker6 KL capacity hour 3.000 200.00 600.00 P&M-060

d) Overhead charges @ 0.1 on (a+b+c) 4103.24 e) Contractor's profit @ 0.1 on (a+b+c+d) 4513.56 Cost for 15 cum = a+b+c+d+e 49649.21 Rate per cum = (a+b+c+d+e)/15 3309.95

say 3310.00 Note

9.2 2900

Unit = metre

A 1000 mm dia

a) LabourMate day 0.180 151.44 27.26 L-12Mason day 0.500 223.36 111.68 L-11Mazdoor day 4.000 136.69 546.76 L-13

b) MaterialSand at site cum 0.070 710.46 49.73 M-005Cement at site tonne 0.050 5000.00 250.00 M-081

metre 12.500 5000.00 62500.00 M-149

Granular material passing 5.6 mm sieve for bedding cum 4.500 727.79 3275.06 M-009c) Overhead charges @ 0.1 on (a+b) 6676.05 d) Contractor's profit @ 0.1 on (a+b+c) 7343.65 Cost for 12.5 metres = a+b+c+d 80780.19 Rate per metre = (a+b+c+d)/12.5 6462.42

say 6462.42 Note

9.2 B 1200 mm diaa) Labour

Mate day 0.280 151.44 42.40 L-12Mason day 1.000 223.36 223.36 L-11

Ref. to MoRTH Spec.

Remarks/ Input ref.

Plain cement concrete 1:3:6 mix with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.

Vibrator is a part of minor T & P which is already included in overhead charges of the contractor.

Laying Reinforced Cement Concrete Pipe NP4 / Prestressed Concrete Pipe on First Class Bedding in Single Row .

Laying Reinforced cement concrete pipe NP4/prestressed concrete pipe for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls and parapets .

Taking output = 12.5 metres ( 5 pipes of 2.5 m length each )

RCC pipe NP-4 /prestressed concrete pipe including collar at site

1. In case of cement craddle bedding, quantity of PCC M15 is to be calculated as per design and priced separately and added .

2. The rate analysis does not include excavation, cement /masonry works in head walls, backfilling, protection works and parapet walls. The same are to be calculated as per approved design and drawings and priced separately on rates available under respective sections

Page 154: Standard Data Book - Rate Analysis

Page 2 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Mazdoor day 6.000 136.69 820.14 L-13 b) Material

Sand at site cum 0.090 710.46 63.94 M-005Cement at site tonne 0.070 5000.00 350.00 M-081

metre 12.500 4452.00 55650.00 M-150

cum 5.000 727.79 3638.95 M-009

c) Overhead charges @ 0.1 on (a+b) 6078.88 d) Contractor's profit @ 0.1 on (a+b+c) 6686.77 Cost for 12.5 metres = a+b+c+d 73554.44 Rate per metre= (a+b+c+d)/12.5 5884.36

say 5884.00 Note

9.3 2900

Unit = metre

A 1000 mm dia

a) Labour

Mate day 0.360 151.44 54.52 L-12

Mason day 1.000 223.36 223.36 L-11

Mazdoor day 8.000 136.69 1093.52 L-13

b) Material

Sand at site cum 0.140 710.46 99.46 M-005

Cement at site tonne 0.100 5000.00 500.00 M-081

metre 25.000 5000.00 125000.00 M-149

Granular material passing 5.6 mm sieve for bedding cum 12.500 727.79 9097.38 M-009

c) Overhead charges @ 0.1 on (a+b) 13606.82

d) Contractor's profit @ 0.1 on (a+b+c) 14967.51

Cost for 12.5 metres = a+b+c+d 164642.57

Rate per metre = (a+b+c+d)/12.5 13171.41

Note say 13171.00

9.3 B 1200 mm dia

a) Labour

Mate day 0.560 151.44 84.81 L-12

Mason day 2.000 223.36 446.72 L-11

Mazdoor day 12.000 136.69 1640.28 L-13

b) Material

Sand at site cum 0.180 710.46 127.88 M-005

Cement at site tonne 0.140 5000.00 700.00 M-081

RCC pipe NP-4/prestressed concrete pipe including collar at site

Granular material passing 5-6 mm sieve for class bedding

1. In case of cement craddle bedding, quantity of PCC M15 is to be calculated as per design and priced separately and added .

2. The rate analysis does not include excavation, cement /masonry works in head walls, backfilling, protection works and parapet walls. The same are to be calculated as per approved design and drawings and priced separately on rates available under respective sections

Laying Reinforced Cement Concrete Pipe NP4 / Prestressed Concrete Pipe on First Class Bedding in Double Row .

Laying Reinforced cement concrete pipe NP4 / prestressed concrete pipe for culverts on first class bedding of granular material in double row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls and parapets .

Taking output = 12.5 metres ( 10 pipes of 2.5 m length each in two rows.)

RCC pipe NP-4/prestressed concrete pipe including collar at site

1. In case of cement craddle bedding, quantity of PCC M15 is to be calculated as per design and priced separately and added .

2. The rate analysis does not include excavation, cement /masonry works in head walls, backfilling, protection works and parapet walls. The same are to be calculated as per approved design and drawings and priced separately on rates available under respective sections

Page 155: Standard Data Book - Rate Analysis

Page 3 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

metre 25.000 4452.00 111300.00 M-150

cum 13.750 727.79 10007.11 M-009

c) Overhead charges @ 0.1 on (a+b) 12430.68

d) Contractor's profit @ 0.1 on (a+b+c) 13673.75

Cost for 12.5 metres = a+b+c+d 150411.23

Rate per metre= (a+b+c+d)/12.5 12032.90

Note say 12033.00

RCC pipe NP-4 /prestressed concrete pipe including collar at site

Granular material passing 5-6 mm sieve for class bedding

1. In case of cement craddle bedding, quantity of PCC M15 is to be calculated as per design and priced separately and added .

2. The rate analysis does not include excavation, cement /masonry works in head walls, backfilling, protection works and parapet walls. The same are to be calculated as per approved design and drawings and priced separately on rates available under respective sections

Page 156: Standard Data Book - Rate Analysis

Page 1 of 280

CHAPTER-12

FOUNDATIONS

Sr No Description Unit Quantity Rate Rs Cost Rs

12.1 304 Excavation for Structures

I Ordinary soilUnit = cum

Taking output = 10 cum

A Manual Means(i) Depth upto 3 m

a) LabourMate day 0.14 151.44 21.20 L-12Mazdoor day 3.50 136.69 478.41 L-13

b) Overhead charges @ 0.2 on (a) 99.92 c) Contractor's profit @ 0.1 on (a+b) 59.95 Cost for 10 cum = a+b+c 659.49 Rate per cum = (a+b+c)/10 65.95

say 66.00 Note

12.1 (I) A (ii) Depth 3 m to 6 m a) Labour

Mate/Supervisor day 0.18 151.44 27.26 L-12 Mazdoor day 4.50 136.69 615.11 L-13

b) Overhead charges @ 0.2 on (a) 128.47 c) Contractor's profit @ 0.1 on (a+b) 77.08 Cost for 10 cum = a+b+c 847.92 Rate per cum = (a+b+c)/10 84.79

say 85.00 Note

12.1 (I) A (iii) Depth above 6 m a) Labour

Mate/Supervisor day 0.24 151.44 36.35 L-12 Mazdoor day 6.00 136.69 820.14 L-13

b) Overhead charges @ 0.2 on (a) 171.30 c) Contractor's profit @ 0.1 on (a+b) 102.78 Cost for 10 cum = a+b+c 1130.56 Rate per cum = (a+b+c)/10 113.06

say 113.00 Note

12.1 (I) B Mechanical Means(i) Depth upto 3 m

Unit = cumTaking output = 240 cuma) Labour

Mate day 0.32 151.44 48.46 L-12Mazdoor day 8.00 136.69 1093.52 L-13

b) MachineryHydraulic excavator 1.0 cum bucket capacity hour 6.00 1302.00 7812.00 P&M-026

c) Overhead charges @ 0.2 on (a+b) 1790.80 d) Contractor's profit @ 0.1 on (a+b+c) 1074.48 Cost for 240 cum = a+b+c+d 11819.25 Rate per cum = (a+b+c+d)/240 49.25

Ref. to MoRTH Spec.

Remarks/ Input ref.

Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material.

1. Cost of dewatering may be added where required upto, 10 per cent of labour cost Assessment for dewatering shall be made as per site conditions.

2.The excavated earth can be used partially for backfilling of foundation pit and partly for road work except for marshy soil. Hence cost of disposal has not been added except for marshy soil. This remark is common to all cases of item 12.1 excluding marshy soil.

3.The cost of shoring and shuttering, where needed, may be added @ 1 per cent on cost of excavation for open foundation.

Cost of dewatering may be added where required upto 15 per cent of labour cost. Assessment for dewatering shall be done as per actual ground conditions.

1. Cost of dewatering may be added where required upto 20 per cent of labour cost. Assessment for dewatering shall be made as per site conditions..

Page 157: Standard Data Book - Rate Analysis

Page 2 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

say 49.00 Note

12.1 (I) B (ii) Depth 3 m to 6 m

Unit = cumTaking output = 210 cuma) Labour

Mate day 0.32 151.44 48.46 L-12Mazdoor day 8.00 136.69 1093.52 L-13

b) Machinery

Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1302.00 7812.00 P&M-026

c) Overhead charges @ 0.2 on (a+b) 1790.80

d) Contractor's profit @ 0.1 on (a+b+c) 1074.48

Cost for 210 cum = a+b+c+d 11819.25

Rate per cum = (a+b+c+d)/210 56.28

say 56.00

Note

12.1 (I) B (iii) Depth above 6m

Unit = cum

Taking output = 180 cum

a) Labour

Mate day 0.40 151.44 60.58 L-12

Mazdoor day 10.00 136.69 1366.90 L-13

b) Machinery

Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1302.00 7812.00 P&M-026

c) Overhead charges @ 0.2 on (a+b) 1847.90

d) Contractor's profit @ 0.1 on (a+b+c) 1108.74

Cost for 180 cum = a+b+c+d 12196.11

Rate per cum = (a+b+c+d)/180 67.76

say 68.00

Note

12.1 II Ordinary Rock (not requiring blasting)

A Manual Means

(i) Depth upto 3 m

Unit = cum

Taking output = 10 cum

a) Labour

Mate day 0.20 151.44 30.29 L-12

Mazdoor day 5.00 136.69 683.45 L-13

b) Overhead charges @ 0.2 on (a) 142.75

c) Contractor's profit @ 0.1 on (a+b) 85.65

Cost for 10 cum = a+b+c 942.13

Rate per cum = (a+b+c)/10 94.21

say 94.00

Note

12.1(II) B Mechanical Means

Unit = cum

Taking output = 180 cum

a) Labour

Cost of dewatering upto 5 per cent of (a+b) may be added, where required. Assessment for dewatering shall be made as per site conditions..

Cost of dewatering upto 7.5 per cent of (a+b) may be added, where required. Assessment for dewatering shall be made as per site conditions..

1. Cost of dewatering upto 10 per cent of (a+b) may be added, where required. Assessment for dewatering shall be made as per site conditions..

2.Labour provided for excavation by mechanical means includes that required for trimming of bottom and side slopes.

Cost of dewatering upto 10 per cent of labour cost may be added, where required. Assessment for dewatering shall be made as per site conditions..

Page 158: Standard Data Book - Rate Analysis

Page 3 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Mate day 0.24 151.44 36.35 L-12

Mazdoor day 6.00 136.69 820.14 L-13

b) Machinery

Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1302.00 7812.00 P&M-026

c) Overhead charges @ 0.2 on (a+b) 1733.70

d) Contractor's profit @ 0.1 on (a+b+c) 1040.22

Cost for 180 cum = a+b+c+d 11442.40

Rate per cum = (a+b+c+d)/180 63.57

say 64.00

Note

12.1 III Hard Rock ( requiring blasting )

A Manual Means

Unit = cum

Taking output = 10 cum

a) Labour

Mate day 0.35 151.44 53.00 L-12

Driller day 0.50 264.50 132.25 L-06

Blaster day 0.25 264.50 66.13 L-03

Mazdoor day 8.00 136.69 1093.52 L-13

b) Machinery

hour 1.00 319.00 319.00 P&M-001

c) Material

Blasting Material kg 3.50 146.00 511.00 M-104

Detonator electric each 14.00 14.56 203.84 M-094/100

d) Overhead charges @ 0.2 on (a+b+c) 475.75

e) Contractor's profit @ 0.1 on (a+b+c+d) 285.45

Cost for 10 cum = a+b+c+d+e 3139.94

Rate per cum = (a+b+c+d+e)/10 313.99

say 314.00

Note

12.1 IV Hard Rock ( blasting prohibited )

Unit = cum

Taking output = 10 cum

A Mechanical Means

a) Labour

Mate day 0.20 151.44 30.29 L-12

Mazdoor day 5.00 136.69 683.45 L-13

b) Machinery

hour 6.00 319.00 1914.00 P&M-001

c) Overhead charges @ 0.2 on (a+b) 525.55

d) Contractor's profit @ 0.1 on (a+b+c) 315.33

Cost for 10 cum = a+b+c+d 3468.61

Rate per cum = (a+b+c+d)/10 346.86

say 347.00

Note

12.1 V Marshy Soil

Unit = cum

1.Cost of dewatering upto 10 per cent of (a+b), may be added, where required Assessment for dewatering shall be made as per site conditions.

2.In case of rock, foundation beyond3 m is not dug and hence not included.

Air Compressor 250 cfm with 2 jack hammer for drilling.

Cost of dewatering @ 10 per cent of (a+b) may be added, where required Assessment for dewatering shall be made as per site conditions.

Air Compressor 250 cfm with 2 leads of pneumatic breaker

1. Cost of dewatering upto10 per cent of (a+b), may be added, where required Assessment for dewatering shall be made as per site conditions.

2.In case of rock, foundation beyond3 m is not dug and hence not included.

Page 159: Standard Data Book - Rate Analysis

Page 4 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Taking output = 10 cum

Depth upto 3 m

A Manual means

a) Labour

Mate/Supervisor day 0.40 151.44 60.58 L-12

Mazdoor day 10.00 136.69 1366.90 L-13

b) Machinery

Tractor-trolley for removal. hour 2.67 282.50 754.28 P&M-053

c) Overhead charges @ 0.2 on (a+b) 436.35

d) Contractor's profit @ 0.1 on (a+b+c) 261.81

Cost for 10 cum = a+b+c+d 2879.91

Rate per cum = ( a+b+c+d)/ 10 287.99

say 288.00

Note

12.1 (V) B Mechanical Means

a) Labour

Mate day 0.08 151.44 12.12 L-12

Mazdoor for dressing sides, bottom and backfilling day 2.00 136.69 273.38 L-13

b) Machinery

hour 0.17 1302.00 221.34 P&M-026

Tipper 5.5 cum capacity, 4 trips per hour. hour 0.45 0.00 P&M-048

c) Overhead charges @ 0.2 on (a+b) 101.37

d) Contractor's profit @ 0.1 on (a+b+c) 60.82

Cost for 10 cum = a+b+c+d 669.02

Rate per cum = (a+b+c+d)/10 66.90

say 67.00

Note

VI Back Filling in Marshy Foundation Pits

Unit : Cum

Taking Output : 6 cum

a) Labour

Mate day 0.12 151.44 18.17 L-12

Mazdoor for dressing sides, bottom and backfilling day 3.00 136.69 410.07 L-13

b) Machinery

Tractor-trolley for transportation hour 2.00 282.50 565.00 P&M-053

c) Overhead charges @ 0.2 on (a+b) 198.65

d) Contractor's profit @ 0.1 on (a+b+c) 119.19

Cost for 6 cum = a+b+c+d 1311.08

Rate per cum = (a+b+c+d)/6 218.51

say 219.00

12.2 304 Filling Annular Space Around Footing in Rock

Unit = cum

Taking out put = 1 cum

1. Cost of dewatering @ 30 per cent of (a), may be added, where required Assessment for dewatering shall be made as per site conditions.

2. Shoring & strutting 15 per cent of (a), where required may be added

3. It is assumed that Marshy Soil will be available upto 3 m depth only. For deeper excavation below 3 m depth, refer analysis in item12.1 (i) to (iv) for ordinary soil

Hydraulic excavator 1.0 cum bucket capacity @ 60 cum per hour

1. Cost of dewatering @ 20 per cent of (a+b) may be added, where required

2. Shoring & strutting @ 10 per cent of (a+b), where required may be added

3. It is assumed that Marshy Soil will be available upto 3 m depth only. For deeper excavation below 3 m depth, refer analysis in item 12.1 (i) to (iv) for ordinary soil

Lean cement concrete 1:3:6 nominal mix. Rate may be taken as per item 12.4.

Page 160: Standard Data Book - Rate Analysis

Page 5 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

12.3

Unit = cum

Taking output = 1 cum

a) Labour

Mate day 0.01 151.44 1.51 L-12

Mazdoor day 0.30 136.69 41.01 L-13

b) Material

Sand (assuming 20 per cent voids) cum 1.20 476.80 572.16 M-006

c) Overhead charges @ 0.2 on (a+b) 122.94

d) Contractor's profit @ 0.1 on (a+b+c) 73.76

Rate per cum = a+b+c+d 811.38

say 811.00

12.4 2100 PCC 1:3:6 in Foundation

Unit = cum

Taking output = 15 cum 255.94

a) Labour

Mate day 0.64 151.44 96.92 L-12

Mason day 1.00 223.36 223.36 L-11

Mazdoor day 15.00 136.69 2050.35 L-13

b) Material

40 mm Aggregate cum 13.50 916.00 12366.00 M-055

coarse Sand cum 6.75 710.46 4795.61 M-005

cement tonne 3.45 5000.00 17250.00 M-081

Cost of water KL 18.00 10.00 180.00 M-189

c) Machinery

Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009

Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079

Water tanker 6 KL capacity hour 2.00 200.00 400.00 P&M-060

d) Overhead charges @ 0.2 on (a+b+c) 8240.21

e) Contractor's profit @ 0.1 on (a+b+c+d) 4944.12

Cost for 15 cum = a+b+c+d+e 54385.37

Rate per cum = (a+b+c+d+e)/15 3625.69

say 3626.00

Note

12.5 1300

Unit = cum

Taking output = 5 cum

a) Material

Bricks Ist class each 2500.00 4.42 11045.45 M-079

cum 1.20 3425.00 4110.00

b) Labour

Mate day 0.48 151.44 72.69 L-12

Mason day 4.00 223.36 893.44 L-11

Mazdoor day 8.00 136.69 1093.52 L-13

c) Overhead charges @ 0.2 on (a+b) 3443.02

d) Contractor's profit @ 0.1 on (a+b+c) 2065.81

Cost for 5 cum = a+b+c+d 22723.93

Rate per cum (a+b+c+d)/5 4544.79

say 4545.00

304

Sand Filling in Foundation Trenches as per Drawing & Technical Specification

Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.

Vibrator is a part of minor T & P which is already included in overhead charges of the contractor.

Brick Masonry Work in Cement Mortar 1:3 in Foundation complete excluding Pointing and Plastering, as per Drawing and Technical Specifications.

Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis)

Item 12.6 (A)

Page 161: Standard Data Book - Rate Analysis

Page 6 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

12.6 (A) Cement Mortar 1:3 (1 cement : 3 sand)

Unit = 1 cum

Taking output = 1 cum

a) Materials

Cement tonne 0.51 5000.00 2550.00 M-081

Sand cum 1.05 710.46 745.98 M-005

b) Labour

Mate day 0.04 151.44 6.06 L-12

Mazdoor day 0.90 136.69 123.02 L-13

Total Material and Labour = (a+b) say 3425.00

(B) Cement Mortar1:2 (1cement :2 sand)

Unit = 1 cum

Taking output = 1 cum

a) Materials

Cement tonne 0.67 5000.00 3360.00 M-081

Sand cum 0.93 710.46 660.73 M-005

b) Labour

Mate day 0.04 151.44 6.06 L-12

Mazdoor day 0.90 136.69 123.02 L-13

Total Material and Labour = (a+b) say 4150.00

(C) Cement Mortar1:4 (1cement :4 sand)

Unit = 1 cum

Taking output = 1 cum

a) Materials

Cement tonne 0.40 5000.00 2016.00 M-081

Sand cum 1.12 710.46 795.72 M-005

b) Labour

Mate day 0.04 151.44 6.06 L-12

Mazdoor day 0.90 136.69 123.02 L-13

Total Material and Labour = (a+b) say 2941.00

(D) Cement Mortar1:6 (1cement :6 sand)

Unit = 1 cum

Taking output = 1 cum

a) Materials

Cement tonne 0.29 5000.00 1440.00 M-081

Sand cum 1.34 710.46 949.99 M-005

b) Labour

Mate day 0.04 151.44 6.06 L-12

Mazdoor day 0.90 136.69 123.02 L-13

Total Material and Labour = (a+b) say 2519.00

12.7 1400

Unit = cum

Taking output = 5 cum

1405.4 (A) Square Rubble Coursed Rubble Masonry (first sort)

a) Material

Stone cum 5.50 2705.04 14877.72 M-169

Sub-analysis

Sub-analysis (Addl.)

Sub-analysis (Addl.)

Sub-analysis (Addl.)

Stone Masonry Work in Cement Mortar 1:3 in Foundation complete as per Drawing and Technical Specifications.

Page 162: Standard Data Book - Rate Analysis

Page 7 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Through and bond stone each 35.00 14.45 505.85 M-182

(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)

cum 1.50 3425.00 5137.50

b) Labour

Mate day 0.66 151.44 99.95 L-12

Mason day 7.50 223.36 1675.20 L-11

Mazdoor day 9.00 136.69 1230.21 L-13

c) Overhead charges @ 0.2 on (a+b) 4705.29

d) Contractor's profit @ 0.1 on (a+b+c) 2823.17

Cost for 5 cum = a+b+c+d 31054.89

Rate per cum (a+b+c+d)/5 6210.98

say 6211.00

1405.3 (B) Random Rubble Masonry

( coursed/uncoursed )

Unit = cum

Taking output = 5 cum

a) Material

Stone cum 5.50 2604.51 14324.81 M-148

Through and bond stone each 35.00 14.45 505.85 M-182

(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)

cum 1.55 3425.00 5308.75

b) Labour

Mate day 0.62 151.44 93.89 L-12

Mason day 6.00 223.36 1340.16 L-11

Mazdoor day 9.00 136.69 1230.21 L-13

c) Overhead charges @ 0.2 on (a+b) 4560.73

d) Contractor's profit @ 0.1 on (a+b+c) 2736.44

Cost for 5 cum = a+b+c+d 30100.85

Rate per cum (a+b+c+d)/5 6020.17

say 6020.00

Note

12.8

A PCC Grade M15

Unit = cum

Taking output = 15 cum

a) Material

Cement tonne 4.13 5000.00 20650.00 M-081

Coarse sand cum 6.75 710.46 4795.61 M-005

40 mm Aggregate cum 8.10 916.00 7419.60 M-055

20 mm Aggregate cum 4.05 1028.00 4163.40 M-053

10 mm Aggregate cum 1.35 1005.00 1356.75 M-051

b) Labour

Mate day 0.86 151.44 130.24 L-12

Mason day 1.50 223.36 335.04 L-11

Mazdoor day 20.00 136.69 2733.80 L-13

c) Machinery

Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009

Generator 63 KVA hour 6.00 535.00 3210.00 P&M-019

3080.00

1847.70

Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis)

Item 12.6 (A)

Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis)

Item 12.6 (A)

The labour already considered in cement mortar has been taken into account while proposing labour for masonry works.

1500, 1700 & 2100

Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications.

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) Formwork @ 4 per cent on cost of concrete i.e. cost of material, labour and machinery

Page 163: Standard Data Book - Rate Analysis

Page 8 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

e) Overhead charges @ 0.2 on (a+b+c+d) 9608.03

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 5764.82

Cost for 15 cum = a+b+c+d+e+f 63412.97

Rate per cum = (a+b+c+d+e+f)/15 4227.53

say 4228.00

Note

12.8 B PCC Grade M20

Unit : cum

Taking output = 15 cum

a) Material

Cement tonne 5.16 5000.00 25800.00 M-081

Coarse sand cum 6.75 710.46 4795.61 M-005

40 mm Aggregate cum 5.40 916.00 4946.40 M-055

20 mm Aggregate cum 5.40 1028.00 5551.20 M-053

10 mm Aggregate cum 2.70 1005.00 2713.50 M-051

b) Labour

Mate day 0.86 151.44 130.24 L-12

Mason day 1.50 223.36 335.04 L-11

Mazdoor day 20.00 136.69 2733.80 L-13

c) Machinery

Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009

Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079

3390.00

2033.78

e) Overhead charges @ 0.2 on (a+b+c+d) 10575.67

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 6345.40

Cost for 15 cum = a+b+c+d+e+f 69799.44

Rate per cum = (a+b+c+d+e+f)/15 4653.30

say 4653.00

12.8 C RCC Grade M20

Case I Using Concrete Mixer

Unit = cum

Taking output = 15 cum

a) Material

Cement tonne 5.21 5000.00 26050.00 M-081

Coarse sand cum 6.75 710.46 4795.61 M-005

20 mm Aggregate cum 8.10 1028.00 8326.80 M-053

10 mm Aggregate cum 5.40 1005.00 5427.00 M-051

b) Labour

Mate day 0.86 151.44 130.24 L-12

Mason day 1.50 223.36 335.04 L-11

Mazdoor day 20.00 136.69 2733.80 L-13

c) Machinery

Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009

Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079

3443.00

2065.49

e) Overhead charges @ 0.2 on (a+b+c+d) 10740.55

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 6444.33

Cost for 15 cum = a+b+c+d+e+f 70887.66

Rate per cum = ( a+b+c+d+e+f )/15 4725.84

say 4726.00

Needle Vibrator is an item of minor T & P which is already included in overhead charges. Hence not added in rate analysis of cement concrete works.

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) Formwork @ 4 per cent on cost of concrete i.e. cost of material, labour and machinery

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) Formwork @ 4 per cent on (a+b+c)

Page 164: Standard Data Book - Rate Analysis

Page 9 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

12.8 C Case II With Batching Plant, Transit Mixer and Concrete Pump

Unit : cum

Taking Output = 120 cum

a) Material

Cement tonne 41.66 5000.00 208300.00 M-081

Coarse Sand cum 54.00 828.00 44712.00 M-004

20 mm Aggregate cum 64.80 1028.00 66614.40 M-053

10 mm Aggregate cum 43.20 1005.00 43416.00 M-051

b) Labour

Mate day 0.84 151.44 127.21 L-12

Mason day 3.00 223.36 670.08 L-11

Mazdoor day 18.00 136.69 2460.42 L-13

c) Machinery

Batching Plant @ 20 cum/hour hour 6.00 2232.00 13392.00 P&M-002

Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080

Loader 1 cum capacity hour 6.00 806.00 4836.00 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1017.00 15255.00 P&M-049

Lead beyond 1 km, L-lead in km tonne.km 300L 2.03 610.20

Concrete Pump hour 6 256.00 1536.00 P&M-007

3388.00

16260.23

e) Overhead charges @ 0.2 on (a+b+c+d) 84553.21

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 50731.93

Cost for 120 cum = a+b+c+d+e+f 558051.18

Rate per cum = ( a+b+c+d+e+f )/120 4650.43

say 4650.00

12.8 D PCC Grade M25

Case I Using Concrete Mixer

Unit = cum

Taking output = 15 cum

a) Material

Cement tonne 5.99 5000.00 29950.00 M-081

Coarse sand cum 6.75 710.46 4795.61 M-005

40 mm Aggregate cum 5.40 916.00 4946.40 M-055

20 mm Aggregate cum 5.40 1028.00 5551.20 M-053

10 mm Aggregate cum 2.70 1005.00 2713.50 M-051

b) Labour

Mate day 0.86 151.44 130.24 L-12

Mason day 1.50 223.36 335.04 L-11

Mazdoor day 20.00 136.69 2733.80 L-13

c) Machinery

Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009

Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079

3667.00

2062.30

e) Overhead charges @ 0.2 on (a+b+c+d) 11411.38

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 6846.83

Cost for 15 cum = a+b+c+d+e+f 75315.08

Rate per cum = ( a+b+c+d+e+f )/15 5021.01

say 5021.00

12.8 D Case II With Batching Plant, Transit Mixer and Concrete Pump

Unit : cum

P&M-050 Lead= 1

km

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) Formwork @ 4 per cent on cost of concrete i.e. cost of material, labour and machinery

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) Formwork @ 3.75 per cent of (a+b+c)

Page 165: Standard Data Book - Rate Analysis

Page 10 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Taking Output = 120 cum

a) Material

Cement tonne 47.95 5000.00 239750.00 M-081

Coarse sand cum 54.00 828.00 44712.00 M-004

40 mm Aggregate cum 43.20 916.00 39571.20 M-055

20 mm Aggregate cum 43.20 1028.00 44409.60 M-053

10 mm Aggregate cum 21.60 1005.00 21708.00 M-051

b) Labour

Mate day 0.84 151.44 127.21 L-12

Mason day 3.00 223.36 670.08 L-11

Mazdoor day 18.00 136.69 2460.42 L-13

c) Machinery

Batching Plant @ 20 cum/hour hour 6.00 2232.00 13392.00 P&M-002

Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080

Loader 1 cum capacity hour 6.00 806.00 4836.00 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1017.00 15255.00 P&M-049

tonne.km 300L 2.03 610.20

Concrete Pump hour 6 256.00 1536.00 P&M-007

3614.00

16260.53

e) Overhead charges @ 0.2 on (a+b+c+d) 89974.95

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 53984.97

cost of 120 cum = a+b+c+d+e+f 593834.66

Rate per cum = (a+b+c+d+e+f)/120 4948.62

say 4949.00

12.8 E RCC Grade M25

Case I Using Concrete Mixer

Unit = cum

Taking output = 15 cum

a) Material

Cement tonne 6.05 5000.00 30250.00 M-081

Coarse sand cum 6.75 710.46 4795.61 M-005

20 mm Aggregate cum 8.10 1028.00 8326.80 M-053

10 mm Aggregate cum 5.40 1005.00 5427.00 M-051

b) Labour

Mate day 0.86 151.44 130.24 L-12

Mason day 1.50 223.36 335.04 L-11

Mazdoor day 20.00 136.69 2733.80 L-13

c) Machinery

Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009

Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079

3723.00

2093.90

e) Overhead charges @ 0.2 on (a+b+c+d) 11586.24

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 6951.74

cost of 15 cum = a+b+c+d+e+f 76469.16

Rate per cum (a+b+c+d+e+f )/15 5097.94

say 5098.00

12.8 E Case II With Batching Plant, Transit Mixer and Concrete Pump

Unit: cum

Taking Output = 120 cum

a) Material

Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead in Kilometer

P&M-050 Lead= 1

km

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) Formwork @ 3.75 per cent of cost of concrete i.e. cost of material, labour and machinery

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) Formwork @ 3.75 per cent of a+b+c.

Page 166: Standard Data Book - Rate Analysis

Page 11 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Cement tonne 48.38 5000.00 241900.00 M-081

Coarse sand cum 54.00 828.00 44712.00 M-004

20 mm Aggregate cum 64.80 1028.00 66614.40 M-053

10 mm Aggregate cum 43.20 1005.00 43416.00 M-051

b) Labour

Mate day 0.84 151.44 127.21 L-12

Mason day 3.00 223.36 670.08 L-11

Mazdoor day 18.00 136.69 2460.42 L-13

c) Machinery

Batching Plant @ 20 cum/hour hour 6.00 2232.00 13392.00 P&M-002

Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080

Loader 1 cum capacity 1 cum hour 6.00 806.00 4836.00 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1017.00 15255.00 P&M-049

tonne.km 300L 2.03 610.20

Concrete Pump hour 6.00 256.00 1536.00 P&M-007

3668.00

16503.97

e) Overhead charges @ 0.2 on (a+b+c+d) 91321.96

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 54793.17

cost of 120 cum = a+b+c+d+e+f 602724.91

Rate per cum (a+b+c+d+e+f )/120 5022.71

say 5023.00

12.8 F PCC Grade M30

Case I Using Concrete Mixer

Unit = cum

Taking output = 15 cum

a) Material

Cement tonne 6.08 5000.00 30400.00 M-081

Coarse sand cum 6.75 710.46 4795.61 M-005

40 mm Aggregate cum 5.40 916.00 4946.40 M-055

20 mm Aggregate cum 5.40 1028.00 5551.20 M-053

10 mm Aggregate cum 2.70 1005.00 2713.50 M-051

b) Labour

Mate day 0.86 151.44 130.24 L-12

Mason day 1.50 223.36 335.04 L-11

Mazdoor day 20.00 136.69 2733.80 L-13

c) Machinery

Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009

Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079

3697.00

1940.56

e) Overhead charges @ 0.2 on (a+b+c+d) 11477.03

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 6886.22

cost of 15 cum = a+b+c+d+e+f 75748.39

Rate per cum (a+b+c+d+e+f )/15 5049.89

say 5050.00

12.8 F Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit : cum

Taking Output = 120 cum

a) Material

Cement tonne 48.60 5000.00 243000.00 M-081

Coarse sand cum 54.00 828.00 44712.00 M-004

Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead in Kilometer

P&M-050 Lead= 1

km

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) Formwork @ 3.75 per cent on cost of concrete i.e. cost of material, labour and machinery

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) Formwork @ 3.50 per cent of cost of concrete i.e. cost of material, labour and machinery

Page 167: Standard Data Book - Rate Analysis

Page 12 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

40 mm Aggregate cum 43.20 916.00 39571.20 M-055

20 mm Aggregate cum 43.20 1028.00 44409.60 M-053

10 mm Aggregate cum 21.60 1005.00 21708.00 M-051

b) Labour

Mate day 0.84 151.44 127.21 L-12

Mason day 3.00 223.36 670.08 L-11

Mazdoor day 18.00 136.69 2460.42 L-13

c) Machinery

Batching Plant @ 20 cum/hour hour 6.00 2232.00 13392.00 P&M-002

Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080

Loader 1 cum capacity hour 6.00 806.00 4836.00 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1017.00 15255.00 P&M-049

tonne.km 300L 2.03 610.20

Concrete Pump hour 6.00 256.00 1536.00 P&M-007

3641.00

15290.25

e) Overhead charges @ 0.2 on (a+b+c+d) 90430.89

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 54258.53

cost of 120 cum = a+b+c+d+e+f 596843.88

Rate per cum (a+b+c+d+e+f )/120 4973.70

say 4974.00

12.8 G RCC Grade M30

Case I Using Concrete Mixer

Unit = cum

Taking output = 15 cum

a) Material

Cement tonne 6.10 5000.00 30500.00 M-081

Coarse sand cum 6.75 710.46 4795.61 M-005

20 mm Aggregate cum 8.10 1028.00 8326.80 M-053

10 mm Aggregate cum 5.40 1005.00 5427.00 M-051

b) Labour

Mate day 0.86 151.44 130.24 L-12

Mason day 1.50 223.36 335.04 L-11

Mazdoor day 20.00 136.69 2733.80 L-13

c) Machinery

Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009

Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079

3740.00

1963.05

e) Overhead charges @ 0.2 on (a+b+c+d) 11610.07

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 6966.04

cost of 15 cum = a+b+c+d+e+f 76626.45

Rate per cum = (a+b+c+d+e+f)/15 5108.43

say 5108.00

12.8 G Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum

Taking output = 120 cum

a) Material

Cement tonne 48.80 5000.00 244000.00 M-081

Coarse sand cum 54.00 828.00 44712.00 M-004

20 mm Aggregate cum 64.80 1028.00 66614.40 M-053

10 mm Aggregate cum 43.20 1005.00 43416.00 M-051

Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead in Kilometer

P&M-050 Lead= 1

km

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) Formwork @ 3.50 per cent of cost of concrete i.e. cost of material, labour and machinery

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) Formwork @ 3.5 per cent on cost of concrete i.e. cost of material, labour and machinery

Page 168: Standard Data Book - Rate Analysis

Page 13 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

b) Labour

Mate day 0.84 151.44 127.21 L-12

Mason day 3.00 223.36 670.08 L-11

Mazdoor day 18.00 136.69 2460.42 L-13

c) Machinery

Batching Plant @ 20 cum/hour hour 6.00 2232.00 13392.00 P&M-002

Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080

Loader 1 cum capacity hour 6.00 806.00 4836.00 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1017.00 15255.00 P&M-049

tonne.km 300L 2.03 610.20

Concrete Pump hour 6.00 256.00 1536.00 P&M-007

3686.00

15477.20

e) Overhead charges @ 0.2 on (a+b+c+d) 91536.60

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 54921.96

cost of 120 cum = a+b+c+d+e+f 604141.58

Rate per cum (a+b+c+d+e+f )/120 5034.51

say 5035.00

12.8 H RCC Grade M35

Case I Using Concrete Mixer

Unit = cum

Taking output = 15 cum

a) Material

Cement tonne 6.33 5000.00 31650.00 M-081

Coarse sand cum 6.75 710.46 4795.61 M-005

20 mm Aggregate cum 8.10 1028.00 8326.80 M-053

10 mm Aggregate cum 5.40 1005.00 5427.00 M-051

b) Labour

Mate day 0.86 151.44 130.24 L-12

Mason day 1.50 223.36 335.04 L-11

Mazdoor day 20.00 136.69 2733.80 L-13

c) Machinery

Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009

Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079

3816.00

1717.12

e) Overhead charges @ 0.2 on (a+b+c+d) 11790.88

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 7074.53

cost of 15 cum = a+b+c+d+e+f 77819.81

Rate per cum = (a+b+c+d+e+f)/15 5187.99

say 5188.00

12.8 H Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit ; cum

Taking Output = 120 cum

a) Material

Cement tonne 50.64 5000.00 253200.00 M-081

Coarse sand cum 54.00 828.00 44712.00 M-004

20 mm Aggregate cum 64.80 1028.00 66614.40 M-053

10 mm Aggregate cum 43.20 1005.00 43416.00 M-051

b) Labour

Mate day 0.84 151.44 127.21 L-12

Mason day 3.00 223.36 670.08 L-11

Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead in Kilometer

P&M-050 Lead= 1

km

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) Formwork @ 3.5 per cent of cost of concrete i.e. cost of material, labour and machinery

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) Formwork @ 3 per cent on a+b+c

Page 169: Standard Data Book - Rate Analysis

Page 14 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Mazdoor day 18.00 136.69 2460.42 L-13

c) Machinery

Batching Plant @ 20 cum/hour hour 6.00 2232.00 13392.00 P&M-002

Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080

Loader1 cum capacity hour 6.00 806.00 4836.00 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1017.00 15255.00 P&M-049

tonne.km 300L 2.03 610.20

Concrete Pump hour 6.00 256.00 1536.00 P&M-007

3762.00

13542.17

e) Overhead charges @ 0.2 on (a+b+c+d) 92989.60

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 55793.76

cost of 120 cum = a+b+c+d+e+f 613731.34

Rate per cum = (a+b+c+d+e+f)/120 5114.43

say 5114.00

Note:

WELL FOUNDATION

12.9 1200

A

Unit = 1 No

Taking output = 1 No.

a) Material

Earth (compacted) cum 251.20 28.0 7033.60 M-092

Sand bags each 750.00 7.00 5250.00 M-159

b) Labour

Mate day 0.40 151.44 60.58 L-12

Mazdoor for filling sand bags, stitching and placing day 15.00 136.69 2050.35 L-13

c) Machinery

Crane with grab 1 cum capacity hour 20.00 853.00 17060.00 P&M-012

Consumables @ 2.5 per cent of (c) above 426.50

d) Overhead charges @ 0.2 on (a+b+c) 6376.21

e) Contractor's profit @ 0.1 on (a+b+c+d) 3825.72

Rate per No. (a+b+c+d+e) 42082.95

say 42083.00

Note

12.9 B

Unit = 1No

Taking output = 1 No

a) Material

Earth (compacted) cum 904.32 28.00 25320.96 M-092

Sand bags each 6000.00 7.00 42000.00 M-159

Wooden ballies 8" Dia and 9 m long each 95.00 91.00 8645.00 M-194

Wooden ballies 2" Dia for bracing metre 190.00 61.00 11590.00 M-193

b) Labour

Mate day 5.60 151.44 848.06 L-12

Mazdoor for piling 8" dia ballies for piling 8" dia ballies day 18.00 136.69 2460.42 L-13

Mazdoor for bracing with 2" dia ballies day 12.00 136.69 1640.28 L-13

Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead in Kilometer

P&M-050 Lead= 1

km

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) Formwork @ 3 per cent on cost of concrete i.e. cost of material, labour and machinery

Where ever concrete is carried out using batching plant, transit mixer, concrete pump, Admixtures @ 0.4 per cent of weight of cement may be added for achieving desired slump of concrete.

Providing and Constructing Temporary Island 16 m diameter for Construction of Well Foundation for 8m dia. Well.

Assuming depth of water 1.0 m and height of island to be 1.25 m.

It is assumed that earth will be available within the working space of crane with grab bucket.

Assuming depth of water 4.0 m and height of island 4.5 m.

Page 170: Standard Data Book - Rate Analysis

Page 15 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Mazdoor for filling sand bags, stitching and placing day 110.00 136.69 15035.90 L-13

c) Machinery

Crane with grab 1 cum capacity hour 50.00 853.00 42650.00 P&M-012

3754.77

d) Overhead charges @ 0.2 on (a+b+c) 30789.08

e) Contractor's profit @ 0.1 on (a+b+c+d) 18473.45

Rate per No. (a+b+c+d+e) 203207.91

say 203208.00

Note

12.9 C

Unit = 1 meter

Taking output = 30 metre

a) Material

Earth cum 450.00 28.00 12600.00 M-092

Sand bags each 300.00 7.00 2100.00 M-159

b) Labour

Mate day 0.24 151.44 36.35 L-12

Mazdoor for filling sand bags, stitching and placing day 6.00 136.69 820.14 L-13

c) Machinery

Front end Loader 1 cum capacity hour 27.00 806.00 21762.00 P&M-017

Tipper 5.5 cum capacity hour 28.00 339.00 9492.00 P&M-048

d) Overhead charges @ 0.2 on (a+b+c) 9362.10

e) Contractor's profit @ 0.1 on (a+b+c+d) 5617.26

Cost for 30 m (a+b+c+d+e) 61789.84

Rate per m (a+b+c+d+e)/30 2059.66

say 2060.00

12.10

Unit = 1 MT

Taking output = 1 MT

a) Material

tonne 1.05 45000.00 47250.00 M-179

Nuts & bolts Kg 20.00 64.07 1281.40 M-130

b) Labour

Mate day 1.32 151.44 199.90 L-12

Fitter day 5.50 230.00 1265.00 L-08

Blacksmith day 5.50 264.50 1454.75 L-02

Welder day 5.50 264.50 1454.75 L-02

Mazdoor day 16.50 136.69 2255.38 L-13

4853.14

c) Overhead charges @ 0.2 on (a+b) 12002.87

d) Contractor's profit @ 0.1 on (a+b+c) 7201.72

Rate per MT (a+b+c+d) 79218.91

say 79219.00

12.11

Consumables and other arrangements for piling ballies @ 2.5 per cent of (a+b+c).

For other well diameters rate can be worked out on the basis of cross-sectional area of well. The diameter of the island shall be in the conformity with clause 1203.2 of MoRTH specifications.

Providing and constructing one span service road to reach island location from one pier location to another pier location

Assuming span length 30 m, width of service road 10m and depth of water 1m

1200 & 1900

Providing and Laying Cutting Edge of Mild Steel weighing 40 kg per metre for Well Foundation complete as per Drawing and Technical Specification.

Structural steel in plates, angles, etc including 5 per cent wastage

(for cutting, bending, making holes, joining, welding and erecting in position)

Electrodes, cutting gas and other consumables @ 10 per cent of cost of (a) above

1200, 1500 & 1700

Plain/Reinforced Cement Concrete, in Well Foundation complete as per Drawing and Technical Specification.

Page 171: Standard Data Book - Rate Analysis

Page 16 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Unit = 1 cum

Taking output = 1 cum

A Well curb

(i) RCC M20 Grade

Case I Using Concrete Mixer

3443.00

688.60

e) Overhead charges @ 0.2 on (a+b+c+d) 826.32

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 495.79

Rate perm (a+b+c+d+e+f) 5453.71

say 5454.00

Case II With Batching Plant, Transit Mixer and Concrete Pump

3388.00

677.60

e) Overhead charges @ 0.2 on (a+b+c+d) 813.12

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 487.87

Rate perm (a+b+c+d+e+f) 5366.59

say 5367.00

12.11 A (ii) RCC M25 Grade

Case I Using Concrete Mixer

3723.00

744.60

e) Overhead charges @ 0.2 on (a+b+c+d) 893.52

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 536.11

Rate perm (a+b+c+d+e+f) 5897.23

say 5897.00

Case II With Batching Plant, Transit Mixer and Concrete Pump

3740.00

748.00

e) Overhead charges @ 0.2 on (a+b+c+d) 897.60

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 538.56

Rate perm (a+b+c+d+e+f) 5924.16

say 5924.00

12.11 A (iii) RCC M35 Grade

Case I Using Concrete Mixer

3816.00

763.20

e) Overhead charges @ 0.2 on (a+b+c+d) 915.84

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 549.50

Rate perm (a+b+c+d+e+f) 6044.54

say 6045.00

Case II With Batching Plant, Transit Mixer and Concrete Pump

3838.00

Same as for 12.8 (C) except for formwork which shall be@ 20 per cent of the cost of concrete instead of 4 per cent.

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) formwork @ 20 per cent of the cost of concrete

12.11 A (i)

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) formwork @ 20 per cent of the cost of concrete

Same as for 12.8 (E) except for formwork which shall be@ 20 per cent of the cost of concrete instead of 3.75 per cent.

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) formwork @ 20 per cent of the cost of concrete

12.11 A (ii)

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) formwork @ 20 per cent of the cost of concrete

Same as for 12.8 (H) except for formwork which shall be@ 20 per cent of the cost of concrete instead of 3.0 per cent.

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) formwork @ 20 per cent of the cost of concrete

12.11 A (iii)

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

Page 172: Standard Data Book - Rate Analysis

Page 17 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

767.60

e) Overhead charges @ 0.2 on (a+b+c+d) 921.12

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 552.67

Rate perm (a+b+c+d+e+f) 6079.39

say 6079.00

Note.

12.11 B Well steining

(I) PCC M15 Grade

Case I Using Concrete Mixer

3080.00

308.00

e) Overhead charges @ 0.2 on (a+b+c+d) 677.60

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 406.56

Rate perm (a+b+c+d+e+f) 4472.16

say 4472.00

12.11 B (ii) PCC M20 Grade

Case I Using Concrete Mixer

3390.00

339.00

e) Overhead charges @ 0.2 on (a+b+c+d) 745.80

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 447.48

Rate perm (a+b+c+d+e+f) 4922.28

say 4922.00

12.11 B (iii) RCC M20 Grade

Case I Using Concrete Mixer

3443.00

344.30

e) Overhead charges @ 0.2 on (a+b+c+d) 757.46

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 454.48

Rate perm (a+b+c+d+e+f) 4999.24

say 4999.00

Case II With Batching Plant, Transit Mixer and Concrete Pump

3388.00

338.80

e) Overhead charges @ 0.2 on (a+b+c+d) 745.36

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 447.22

Rate perm (a+b+c+d+e+f) 4919.38

say 4919.00

12.11 B (iv) PCC M25 Grade

Case I Using Concrete Mixer

3667.00

d) formwork @ 20 per cent of the cost of concrete

If curb concrete is carried out within steel liner, cost of formwork shall be excluded.

Same as for 12.8 (A) except for formwork which shall be @ 10 per cent of the cost of concrete instead of 4 per cent.

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) formwork @ 10 per cent of the cost of concrete

Same as for 12.8 (B) except for formwork which shall be @ 10 per cent of the cost of concrete instead of 4 per cent.

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) formwork @ 10 per cent of the cost of concrete

Same as for 12.8 (C) except for formwork which shall be @ 10 per cent of the cost of concrete instead of 4 per cent.

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) formwork @ 10 per cent of the cost of concrete

12.11 B (iii)

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) formwork @ 10 per cent of the cost of concrete

Same as for 12.8 (D) except for formwork which shall be @ 10 per cent of the cost of concrete instead of 4 per cent.

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

Page 173: Standard Data Book - Rate Analysis

Page 18 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

366.70

e) Overhead charges @ 0.2 on (a+b+c+d) 806.74

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 484.04

Rate perm (a+b+c+d+e+f) 5324.48

say 5324.00

Case II With Batching Plant, Transit Mixer and Concrete Pump

3614.00

361.40

e) Overhead charges @ 0.2 on (a+b+c+d) 795.08

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 477.05

Rate perm (a+b+c+d+e+f) 5247.53

say 5248.00

'12.11 B (v) RCC M25 Grade

Case I Using Concrete Mixer

3723.00

372.30

e) Overhead charges @ 0.2 on (a+b+c+d) 819.06

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 491.44

Rate perm (a+b+c+d+e+f) 5405.80

say 5406.00

Case II With Batching Plant, Transit Mixer and Concrete Pump

3740.00

374.00

e) Overhead charges @ 0.2 on (a+b+c+d) 822.80

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 493.68

Rate perm (a+b+c+d+e+f) 5430.48

say 5430.00

'12.11 B (vi) PCC M30 Grade

Case I Using Concrete Mixer

3697.00

369.70

e) Overhead charges @ 0.2 on (a+b+c+d) 813.34

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 488.00

Rate perm (a+b+c+d+e+f) 5368.04

say 5368.00

Case II With Batching Plant, Transit Mixer and Concrete Pump

3641.00

364.10

e) Overhead charges @ 0.2 on (a+b+c+d) 801.02

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 480.61

Rate perm (a+b+c+d+e+f) 5286.73

say 5287.00

'12.11 B (vii) RCC M30 Grade

Case I Using Concrete Mixer

d) formwork @ 10 per cent of the cost of concrete

12.11 B (iv)

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) formwork @ 10 per cent of the cost of concrete

Same as for 12.8 (E) except for formwork which shall be @ 10 per cent of the cost of concrete instead of 3.5 per cent.

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) formwork @ 10 per cent of the cost of concrete

12.11 B (v)

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) formwork @ 10 per cent of the cost of concrete

Same as for 12.8 (F) except for formwork which shall be @ 10 per cent of the cost of concrete instead of 3.5 per cent.

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) formwork @ 10 per cent of the cost of concrete

12.11 B (vi)

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) formwork @ 10 per cent of the cost of concrete

Same as for 12.8 (G) except for formwork which shall be @ 10 per cent of the cost of concrete instead of 3.5 per cent.

Page 174: Standard Data Book - Rate Analysis

Page 19 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

3740.00

374.00

e) Overhead charges @ 0.2 on (a+b+c+d) 822.80

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 493.68

Rate perm (a+b+c+d+e+f) 5430.48

say 5430.00

Case II With Batching Plant, Transit Mixer and Concrete Pump

3686.00

368.60

e) Overhead charges @ 0.2 on (a+b+c+d) 810.92

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 486.55

Rate perm (a+b+c+d+e+f) 5352.07

say 5352.00

'12.11 B (viii) RCC M35 Grade

Case I Using Concrete Mixer

3816.00

381.60

e) Overhead charges @ 0.2 on (a+b+c+d) 839.52

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 503.71

Rate perm (a+b+c+d+e+f) 5540.83

say 5541.00

Case II With Batching Plant, Transit Mixer and Concrete Pump

3838.00

383.80

e) Overhead charges @ 0.2 on (a+b+c+d) 844.36

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 506.62

Rate perm (a+b+c+d+e+f) 5572.78

say 5573.00

'12.11 B (ix) RCC M40 Grade

Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum

Taking output = 120 cum

a) Material

Cement tonne 51.60 5000.00 258000.00 M-081

Coarse Sand cum 54.00 828.00 44712.00 M-004

20 mm Aggregate cum 64.80 1028.00 66614.40 M-053

10 mm Aggregate cum 43.20 1005.00 43416.00 M-051

Admixture kg 206.00 44.70 9208.20 M-180

b) Labour

Mate day 0.84 151.44 127.21 L-12

Meson day 3.00 223.36 670.08 L-11

Mazdoor day 18.00 136.69 2460.42 L-13

c) Machinery

Batching Plant hour 6.00 2232.00 13392.00 P&M-002

Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080

Loader 1 cum capacity hour 6.00 806.00 4836.00 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1017.00 15255.00 P&M-049

Transit Mixer 4 cum capacity for lead beyond 1 km. tonne.km 300xL 2.03 610.20

Concrete Pump hour 6.00 256.00 1536.00 P&M-007

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) formwork @ 10 per cent of the cost of concrete

12.11 B (vii)

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) formwork @ 10 per cent of the cost of concrete

Same as for 12.8 (H) except for formwork which shall be @ 10 per cent of the cost of concrete instead of 3 per cent.

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) formwork @ 10 per cent of the cost of concrete

12.11 B (viii)

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) formwork @ 10 per cent of the cost of concrete

Lead= 1 , P&M-050

Page 175: Standard Data Book - Rate Analysis

Page 20 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

31028.00

46541.40

e) Overhead charges @ 0.2 on (a+b+c+d) 102391.08

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 61434.65

cost of 120 cum = a+b+c+d+e+f 675781.14

Rate per cum = (a+b+c+d+e+f)/120 5631.51

say 5632.00

12.11 C C Bottom Plug

Concrete to be placed using tremie pipe

(i) PCC Grade M20

Case I Using Concrete Mixer

Unit = cum

Taking output = 15 cum

a) Material

Cement tonne 5.55 5000.00 27750.00 M-081

Coarse sand cum 6.75 710.46 4795.61 M-005

40 mm Aggregate cum 5.40 916.00 4946.40 M-055

20 mm Aggregate cum 5.40 1028.00 5551.20 M-053

10 mm Aggregate cum 2.70 1005.00 2713.50 M-051

Admixture Kg 18.60 44.70 831.42 M-180

b) Labour

Mate day 0.90 151.44 136.30 L-12

Mason day 1.50 223.36 335.04 L-11

Mazdoor day 20.00 136.69 2733.80 L-13

c) Machinery

Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009

Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079

Light Crane 3 tonnes capacity for handling tremie pipe hour 6.00 357.00 2142.00 P&M-013

3719.00

2489.66

d) Overhead charges @ 0.2 on (a+b+c) 11652.74

e) Contractor's profit @ 0.1 on (a+b+c+d) 6991.65

cost of 15 cum = a+b+c+d+e 76908.12

Rate per cum = (a+b+c+d+e)/15 5127.21

say 5127.00

Case II

Unit ; cum

Taking Output = 120 cum

a) Material

Cement tonne 44.40 5000.00 222000.00 M-081

Coarse sand cum 54.00 828.00 44712.00 M-004

20 mm Aggregate cum 64.80 1028.00 66614.40 M-053

10 mm Aggregate cum 43.20 1005.00 43416.00 M-051

Admixture Kg 148.80 44.70 6651.36 M-180

b) Labour

Mate day 0.88 151.44 133.27 L-12

Mason day 3.00 223.36 670.08 L-11

Mazdoor day 18.00 136.69 2460.42 L-13

c) Machinery

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) Formwork @ 10 per cent on cost of concrete i.e. cost of material, labour and machinery

Note: 10% extra cement to be added where under water concreting is involved

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

Add 5 per cent of cost of material and labour towards cost of forming sump, protective bunds, chiselling and making arrangements for under water concreting with tremie pipe..

12.11 C (i)

Using Batching Plant, Transit Mixer and Crane/concrete pump

Page 176: Standard Data Book - Rate Analysis

Page 21 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Batching Plant @ 20 cum/hour hour 6.00 2232.00 13392.00 P&M-002

Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080

Loader 1 cum capacity hour 6.00 806.00 4836.00 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1017.00 15255.00 P&M-049

tonne.km 300L 2.03 610.20

Concrete Pump hour 6.00 256.00 1536.00 P&M-007

3558.00

19332.88

d) Overhead charges @ 0.2 on (a+b+c) 89239.22

e) Contractor's profit @ 0.1 on (a+b+c+d) 53543.53

cost of 120 cum = a+b+c+d+e 588978.86

Rate per cum = (a+b+c+d+e)/120 4908.16

say 4908.00

'12.11 C (ii) PCC Grade M25

Case I Using Concrete Mixer

Unit = cum

Taking output = 15 cum

a) Material

Cement tonne 5.99 5000.00 29950.00 M-081

Coarse sand cum 6.75 710.46 4795.61 M-005

40 mm Aggregate cum 5.40 916.00 4946.40 M-055

20 mm Aggregate cum 5.40 1028.00 5551.20 M-053

10 mm Aggregate cum 2.70 1005.00 2713.50 M-051

Admixture Kg 21.60 44.70 965.52 M-180

b) Labour

Mate day 0.90 151.44 136.30 L-12

Mason day 1.50 223.36 335.04 L-11

Mazdoor day 20.00 136.69 2733.80 L-13

c) Machinery

Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009

Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079

hour 6.00 357.00 2142.00 P&M-013

3874.00

2606.37

d) Overhead charges @ 0.2 on (a+b+c) 12142.91

e) Contractor's profit @ 0.1 on (a+b+c+d) 7285.74

cost of 15 cum = a+b+c+d+e 80143.18

Rate per cum = (a+b+c+d+e)/15 5342.88

say 5343.00

Case II

Unit = cum

Taking output = 120 cum

a) Material

Cement tonne 47.88 5000.00 239400.00 M-081

Coarse sand cum 54.00 828.00 44712.00 M-004

20 mm Aggregate cum 64.80 1028.00 66614.40 M-053

10 mm Aggregate cum 43.20 1005.00 43416.00 M-051

Admixture Kg 172.80 44.70 7724.16 M-180

Transit Mixer 4 cum capacity, lead beyond 1 Km, L - lead in Kilometer

P&M-050 Lead= 1

km

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

Add 5 per cent of cost of material and labour towards cost of forming sump, protective bunds, chiselling and making arrangements for under water concreting with tremie pipe..

Light Crane of 3 tonnes capacity for handling tremie pipe

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

Add 5 per cent of cost of material and labour towards cost of forming sump, protective bunds, chiselling and making arrangements for under water concreting with tremie pipe..

12.11 C (ii)

Using Batching Plant, Transit Mixer and Crane/concrete pump

Page 177: Standard Data Book - Rate Analysis

Page 22 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

b) Labour

Mate day 0.88 151.44 133.27 L-12

Mason day 3.00 223.36 670.08 L-11

Mazdoor day 18.00 136.69 2460.42 L-13

c) Machinery

Batching Plant @ 20 cum/hour hour 6.00 2232.00 13392.00 P&M-002

Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080

Loader 1 cum capacity hour 6.00 806.00 4836.00 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1017.00 15255.00 P&M-049

tonne.km 300L 2.03 610.20

Concrete Pump hour 6.00 256.00 1536.00 P&M-007

3712.00

20256.52

d) Overhead charges @ 0.2 on (a+b+c) 93118.51

e) Contractor's profit @ 0.1 on (a+b+c+d) 55871.11

cost of 120 cum = a+b+c+d+e 614582.16

Rate per cum = (a+b+c+d+e)/120 5121.52

say 5122.00

'12.11 C (iii) PCC Grade M30

Case I Using Concrete Mixer

Unit = 1 cum

Taking output = 15 cum

a) Material

Cement tonne 6.08 5000.00 30400.00 M-081

Coarse sand cum 6.75 710.46 4795.61 M-005

40 mm Aggregate cum 5.40 916.00 4946.40 M-055

20 mm Aggregate cum 5.40 1028.00 5551.20 M-053

10 mm Aggregate cum 2.70 1005.00 2713.50 M-051

Admixture Kg 21.60 44.70 965.52 M-180

b) Labour

Mate day 0.90 151.44 136.30 L-12

Mason day 1.50 223.36 335.04 L-11

Mazdoor day 20.00 136.69 2733.80 L-13

c) Machinery

Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009

Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079

hour 6.00 357.00 2142.00 P&M-013

3904.00

2628.87

d) Overhead charges @ 0.2 on (a+b+c) 12237.41

e) Contractor's profit @ 0.1 on (a+b+c+d) 7342.44

cost of 15 cum = a+b+c+d+e 80766.88

Rate per cum = (a+b+c+d+e)/15 5384.46

say 5384.00

Case II

Unit = cum

Taking output = 120 cum

a) Material

Transit Mixer 4 cum capacity, lead beyond 1 Km, L - lead in Kilometer

P&M-050 Lead= 1

km

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

Add 5 per cent of cost of material and labour towards cost of forming sump, protective bunds, chiselling and making arrangements for under water concreting with tremie pipe..

Light Crane of 3 tonnes capacity for handling tremie pipe

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

Add 5 per cent of cost of material and labour towards cost of forming sump, protective bunds, chiselling and making arrangements for under water concreting with tremie pipe..

12.11 C (iii)

Using Batching Plant, Transit Mixer and Crane/concrete pump

Page 178: Standard Data Book - Rate Analysis

Page 23 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Cement tonne 48.64 5000.00 243200.00 M-081

Coarse sand cum 54.00 828.00 44712.00 M-004

20 mm Aggregate cum 64.80 1028.00 66614.40 M-053

10 mm Aggregate cum 43.20 1005.00 43416.00 M-051

Admixture Kg 172.80 44.70 7724.16 M-180

b) Labour

Mate day 0.88 151.44 133.27 L-12

Mason day 3.00 223.36 670.08 L-11

Mazdoor day 18.00 136.69 2460.42 L-13

c) Machinery

Batching Plant @ 20 cum/hour hour 6.00 2232.00 13392.00 P&M-002

Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080

Loader 1 cum capacity hour 6.00 806.00 4836.00 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1017.00 15255.00 P&M-049

tonne.km 300L 2.03 610.20

Concrete Pump hour 6.00 256.00 1536.00 P&M-007

3743.00

20446.52

d) Overhead charges @ 0.2 on (a+b+c) 93916.51

e) Contractor's profit @ 0.1 on (a+b+c+d) 56349.91

cost of 120 cum = a+b+c+d+e 619848.96

Rate per cum = (a+b+c+d+e)/120 5165.41

say 5165.00

'12.11 C (iv) PCC Grade M35

Case I Using Concrete Mixer

Unit = 1 cum

Taking output = 15 cum

a) Material

Cement tonne 6.29 5000.00 31450.00 M-081

Coarse sand cum 6.75 710.46 4795.61 M-005

40 mm Aggregate cum 5.40 916.00 4946.40 M-055

20 mm Aggregate cum 5.40 1028.00 5551.20 M-053

10 mm Aggregate cum 2.70 1005.00 2713.50 M-051

Admixture Kg 21.60 44.70 965.52 M-180

b) Labour

Mate day 0.90 151.44 136.30 L-12

Mason day 1.50 223.36 335.04 L-11

Mazdoor day 20.00 136.69 2733.80 L-13

c) Machinery

Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009

Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079

hour 6.00 357.00 2142.00 P&M-013

3974.00

2681.37

d) Overhead charges @ 0.2 on (a+b+c) 12457.91

e) Contractor's profit @ 0.1 on (a+b+c+d) 7474.74

cost of 15 cum = a+b+c+d+e 82222.18

Rate per cum = (a+b+c+d+e)/15 5481.48

Transit Mixer 4 cum capacity, lead beyond 1 Km, L - lead in Kilometer

P&M-050 Lead= 1

km

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

Add 5 per cent of cost of material and labour towards cost of forming sump, protective bunds, chiselling and making arrangements for under water concreting with tremie pipe..

Light Crane of 3 tonnes capacity for handling tremie pipe

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

Add 5 per cent of cost of material and labour towards cost of forming sump, protective bunds, chiselling and making arrangements for under water concreting with tremie pipe..

Page 179: Standard Data Book - Rate Analysis

Page 24 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

say 5481.00

Case II

Unit = cum

Taking output = 120 cum

a) Material

Cement tonne 50.28 5000.00 251400.00 M-081

Coarse sand cum 54.00 828.00 44712.00 M-004

20 mm Aggregate cum 64.80 1028.00 66614.40 M-053

10 mm Aggregate cum 43.20 1005.00 43416.00 M-051

Admixture Kg 172.80 44.70 7724.16 M-180

b) Labour

Mate day 0.88 151.44 133.27 L-12

Mason day 3.00 223.36 670.08 L-11

Mazdoor day 18.00 136.69 2460.42 L-13

c) Machinery

Batching Plant @ 20 cum/hour hour 6.00 2232.00 13392.00 P&M-002

Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080

Loader 1 cum capacity hour 6.00 806.00 4836.00 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1017.00 15255.00 P&M-049

tonne.km 300L 2.03 610.20

Concrete Pump hour 6.00 256.00 1536.00 P&M-007

3812.00

20856.52

d) Overhead charges @ 0.2 on (a+b+c) 95638.51

e) Contractor's profit @ 0.1 on (a+b+c+d) 57383.11

cost of 120 cum = a+b+c+d+e 631214.16

Rate per cum = (a+b+c+d+e)/120 5260.12

say 5260.00

12.11 D Intermediate plug

(i) Grade M20 PCC

Case I Using Concrete Mixer

3719.00

d) Overhead charges @ 0.2 on (a+b+c) 743.80

e) Contractor's profit @ 0.1 on (a+b+c+d) 446.28

Rate per cum = (a+b+c+d+e) 4909.08

say 4909.00

Case II

3558.00

d) Overhead charges @ 0.2 on (a+b+c) 711.60

e) Contractor's profit @ 0.1 on (a+b+c+d) 426.96

Rate per cum = (a+b+c+d+e) 4696.56

say 4697.00

'12.11 D (ii) Grade M25 PCC

Case I Using Concrete Mixer

3874.00

d) Overhead charges @ 0.2 on (a+b+c) 774.80

12.11 C (iv)

Using Batching Plant, Transit Mixer and Crane/concrete pump

Transit Mixer 4 cum capacity, lead beyond 1 Km, L - lead in Kilometer

P&M-050 Lead= 1

km

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

Add 5 per cent of cost of material and labour towards cost of forming sump, protective bunds, chiselling and making arrangements for under water concreting with tremie pipe..

Same as in bottom plug concrete, excluding cost of forming sump, protective bunds, chiseling etc.

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

12.11 D (i)

Using Batching Plant, Transit Mixer and Crane/concrete pump

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

Same as in bottom plug concrete, excluding cost of forming sump, protective bunds, chiseling etc.

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

Page 180: Standard Data Book - Rate Analysis

Page 25 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

e) Contractor's profit @ 0.1 on (a+b+c+d) 464.88

Rate per cum = (a+b+c+d+e) 5113.68

say 5114.00

Case II

3712.00

d) Overhead charges @ 0.2 on (a+b+c) 742.40

e) Contractor's profit @ 0.1 on (a+b+c+d) 445.44

Rate per cum = (a+b+c+d+e) 4899.84

say 4900.00

'12.11 D (iii) Grade M30 PCC

Case I Using Concrete Mixer

3904.00

d) Overhead charges @ 0.2 on (a+b+c) 780.80

e) Contractor's profit @ 0.1 on (a+b+c+d) 468.48

Rate per cum = (a+b+c+d+e) 5153.28

say 5153.00

Case II

3743.00

d) Overhead charges @ 0.2 on (a+b+c) 748.60

e) Contractor's profit @ 0.1 on (a+b+c+d) 449.16

Rate per cum = (a+b+c+d+e) 4940.76

say 4941.00

12.11 E Top plug

(i) Grade M15 PCC

Same as Item 12.8(a) excluding formwork

Case I Using Concrete Mixer

3080.00

d) Overhead charges @ 0.2 on (a+b+c) 616.00

e) Contractor's profit @ 0.1 on (a+b+c+d) 369.60

Rate per cum = (a+b+c+d+e) 4065.60

say 4066.00

'12.11 E (ii) Grade M20 PCC

Same as Item 12.8(b) excluding formwork

Case I Using Concrete Mixer

3390.00

d) Overhead charges @ 0.2 on (a+b+c) 678.00

e) Contractor's profit @ 0.1 on (a+b+c+d) 406.80

Rate per cum = (a+b+c+d+e) 4474.80

say 4475.00

'12.11 E (iii) Grade M25 PCC

Same as Item 12.8 (d) excluding formwork

Case I Using Concrete Mixer

3667.00

d) Overhead charges @ 0.2 on (a+b+c) 733.40

e) Contractor's profit @ 0.1 on (a+b+c+d) 440.04

Rate per cum = (a+b+c+d+e) 4840.44

say 4840.00

Case II

12.11 D (ii)

Using Batching Plant, Transit Mixer and Crane/concrete pump

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

Same as in bottom plug concrete, excluding cost of forming sump, protective bunds, chiseling etc.

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

12.11 D (iii)

Using Batching Plant, Transit Mixer and Crane/concrete pump

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

12.11 E (iii)

Using Batching Plant, Transit Mixer and Crane/concrete pump

Page 181: Standard Data Book - Rate Analysis

Page 26 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

3614.00

d) Overhead charges @ 0.2 on (a+b+c) 722.80

e) Contractor's profit @ 0.1 on (a+b+c+d) 433.68

Rate per cum = (a+b+c+d+e) 4770.48

say 4770.00

'12.11 E (iv) Grade M30 PCC

Same as Item 12.8(f) excluding formwork

Case I Using Concrete Mixer

3697.00

d) Overhead charges @ 0.2 on (a+b+c) 739.40

e) Contractor's profit @ 0.1 on (a+b+c+d) 443.64

Rate per cum = (a+b+c+d+e) 4880.04

say 4880.00

Case II

3641.00

d) Overhead charges @ 0.2 on (a+b+c) 728.20

e) Contractor's profit @ 0.1 on (a+b+c+d) 436.92

Rate per cum = (a+b+c+d+e) 4806.12

say 4806.00

12.11 F Well cap

(i) RCC Grade M20

Case I Using Concrete Mixer

Unit = cum

Taking output = 15 cum

a) Material

Cement tonne 5.12 5000.00 25600.00 M-081

Coarse sand cum 6.75 710.46 4795.61 M-005

20 mm Aggregate cum 8.10 1028.00 8326.80 M-053

10 mm Aggregate cum 5.40 1005.00 5427.00 M-051

b) Labour

Mate day 0.86 151.44 130.24 L-12

Mason day 1.50 223.36 335.04 L-11

Mazdoor day 20.00 136.69 2733.80 L-13

c) Machinery

Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009

Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079

2047.49

d) Overhead charges @ 0.2 on (a+b+c) 10646.95

e) Contractor's profit @ 0.1 on (a+b+c+d) 6388.17

cost of 15 cum = a+b+c+d+e 70269.90

Rate per cum = (a+b+c+d+e)/15 4684.66

say 4685.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum

Taking output = 120 cum

a) Material

Cement tonne 40.92 5000.00 204600.00 M-081

Coarse sand cum 54.00 828.00 44712.00 M-004

20 mm Aggregate cum 64.80 1028.00 66614.40 M-053

10 mm Aggregate cum 43.20 1005.00 43416.00 M-051

b) Labour

Mate day 0.84 151.44 127.21 L-12

Mason day 3.00 223.36 670.08 L-11

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

12.11 E (iv)

Using Batching Plant, Transit Mixer and Crane/concrete pump

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

Form Work @ 4 per cent of a+b+c

12.11 F (i)

Page 182: Standard Data Book - Rate Analysis

Page 27 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Mazdoor day 18.00 136.69 2460.42 L-13

c) Machinery

Batching Plant @ 20 cum/hour hour 6.00 2232.00 13392.00 P&M-002

Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080

Loader (capacity 1 cum) hour 6.00 806.00 4836.00 P&M-017

Transit Mixer ( capacity 4.0 cu.m )

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1017.00 15255.00 P&M-049

Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 2.03 610.20

Concrete Pump hour 6.00 256.00 1536.00 P&M-007

Formwork @ 4 per cent of (a+b+c) 16112.23

d) Overhead charges @ 0.2 on (a+b+c) 83783.61

e) Contractor's profit @ 0.1 on (a+b+c+d) 50270.17

cost of 120 cum = a+b+c+d+e 552971.82

Rate per cum = (a+b+c+d+e)/120 4608.10

say 4608.00

12.11 F (ii) RCC Grade M25

Case I Using Concrete Mixer

Unit = cum

Taking output = 15 cum

a) Material

Cement tonne 6.05 5000.00 30250.00 M-081

Coarse sand cum 6.75 710.46 4795.61 M-005

20 mm Aggregate cum 8.10 1028.00 8326.80 M-053

10 mm Aggregate cum 5.40 1005.00 5427.00 M-051

b) Labour

Mate day 0.86 151.44 130.24 L-12

Mason day 1.50 223.36 335.04 L-11

Mazdoor day 20.00 136.69 2733.80 L-13

c) Machinery

Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009

Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079

Form Work @ 3.75 per cent of a+b+c 2093.90

d) Overhead charges @ 0.2 on (a+b+c) 11586.24

e) Contractor's profit @ 0.1 on (a+b+c+d) 6951.74

cost of 15 cum = a+b+c+d+e 76469.16

Rate per cum = (a+b+c+d+e)/15 5097.94

say 5098.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum

Taking output = 120 cum

a) Material

Cement tonne 48.40 5000.00 242000.00 M-081

Coarse sand cum 54.00 828.00 44712.00 M-004

20 mm Aggregate cum 64.80 1028.00 66614.40 M-053

10 mm Aggregate cum 43.20 1005.00 43416.00 M-051

b) Labour

Mate day 0.84 151.44 127.21 L-12

Mason day 3.00 223.36 670.08 L-11

Mazdoor day 18.00 136.69 2460.42 L-13

c) Machinery

Batching Plant @ 20 cum/hour hour 6.00 2232.00 13392.00 P&M-002

Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080

Loader (capacity 1 cum) hour 6.00 806.00 4836.00 P&M-017

Transit Mixer ( capacity 4.0 cu.m )

P&M-050 Lead= 1

km

12.11 F (ii)

Page 183: Standard Data Book - Rate Analysis

Page 28 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1017.00 15255.00 P&M-049

Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 2.03 610.20

Concrete Pump hour 6.00 256.00 1536.00 P&M-007

Formwork @ 3.75 per cent of ( a+b+c) 16507.72

d) Overhead charges @ 0.2 on (a+b+c) 91342.71

e) Contractor's profit @ 0.1 on (a+b+c+d) 54805.62

cost of 120 cum = a+b+c+d+e 602861.86

Rate per cum = (a+b+c+d+e)/120 5023.85

say 5024.00

12.11 F (iii) RCC Grade M30

Case I Using Concrete Mixer

Unit = cum

Taking output = 15 cum

a) Material

Cement tonne 6.10 5000.00 30500.00 M-081

Coarse sand cum 6.75 710.46 4795.61 M-005

20 mm Aggregate cum 8.10 1028.00 8326.80 M-053

10 mm Aggregate cum 5.40 1005.00 5427.00 M-051

b) Labour

Mate day 0.86 151.44 130.24 L-12

Mason day 1.50 223.36 335.04 L-11

Mazdoor day 20.00 136.69 2733.80 L-13

c) Machinery

Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009

Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079

Formwork @ 3.5 per cent of (a+b+c) 1963.05

d) Overhead charges @ 0.2 on (a+b+c) 11610.07

e) Contractor's profit @ 0.1 on (a+b+c+d) 6966.04

cost of 15 cum = a+b+c+d+e 76626.45

Rate per cum = (a+b+c+d+e)/15 5108.43

say 5108.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum

Taking output = 120 cum

a) Material

Cement tonne 48.79 5000.00 243950.00 M-081

Coarse sand cum 54.00 828.00 44712.00 M-004

20 mm Aggregate cum 64.80 1028.00 66614.40 M-053

10 mm Aggregate cum 43.20 1005.00 43416.00 M-051

b) Labour

Mate day 0.84 151.44 127.21 L-12

Mason day 3.00 223.36 670.08 L-11

Mazdoor day 18.00 136.69 2460.42 L-13

c) Machinery

Batching Plant @ 20 cum/hour hour 6.00 2232.00 13392.00 P&M-002

Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080

Loader (capacity 1 cum) hour 6.00 806.00 4836.00 P&M-017

Transit Mixer ( capacity 4.0 cu.m )

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1017.00 15255.00 P&M-049

Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 2.03 610.20

Concrete Pump hour 6.00 256.00 1536.00 P&M-007

Formwork @ 3.5 per cent of (a+b+c) 15475.45

d) Overhead charges @ 0.2 on (a+b+c) 91526.25

P&M-050 Lead= 1

km

12.11 F (iii)

P&M-050 Lead= 1

km

Page 184: Standard Data Book - Rate Analysis

Page 29 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

e) Contractor's profit @ 0.1 on (a+b+c+d) 54915.75

cost of 120 cum = a+b+c+d+e 604073.27

Rate per cum = (a+b+c+d+e)/120 5033.94

say 5034.00

12.11 F (iv) RCC Grade M35

Case I Using Concrete Mixer

Unit = cum

Taking output = 15 cum

a) Material

Cement tonne 6.33 5000.00 31650.00 M-081

Coarse sand cum 6.75 710.46 4795.61 M-005

20 mm Aggregate cum 8.10 1028.00 8326.80 M-053

10 mm Aggregate cum 5.40 1005.00 5427.00 M-051

b) Labour

Mate day 0.86 151.44 130.24 L-12

Mason day 1.50 223.36 335.04 L-11

Mazdoor day 20.00 136.69 2733.80 L-13

c) Machinery

Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009

Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079

Formwork @ 3 per cent of (a+b+c) 1717.12

d) Overhead charges @ 0.2 on (a+b+c) 11790.88

e) Contractor's profit @ 0.1 on (a+b+c+d) 7074.53

cost of 15 cum = a+b+c+d+e 77819.81

Rate per cum = (a+b+c+d+e)/15 5187.99

say 5188.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum

Taking output = 120 cum

a) Material

Cement tonne 50.64 5000.00 253200.00 M-081

Coarse sand cum 54.00 828.00 44712.00 M-004

20 mm Aggregate cum 64.80 1028.00 66614.40 M-053

10 mm Aggregate cum 43.20 1005.00 43416.00 M-051

b) Labour

Mate day 0.84 151.44 127.21 L-12

Mason day 3.00 223.36 670.08 L-11

Mazdoor day 18.00 136.69 2460.42 L-13

c) Machinery

Batching Plant @ 20 cum/hour hour 6.00 2232.00 13392.00 P&M-002

Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080

Loader (capacity 1 cum) hour 6.00 806.00 4836.00 P&M-017

Transit Mixer ( capacity 4.0 cu.m )

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1017.00 15255.00 P&M-049

Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 2.03 610.20

Concrete Pump hour 6.00 256.00 1536.00 P&M-007

Formwork @ 3 per cent of (a+b+c) 13542.17

d) Overhead charges @ 0.2 on (a+b+c) 92989.60

e) Contractor's profit @ 0.1 on (a+b+c+d) 55793.76

cost of 120 cum = a+b+c+d+e 613731.34

Rate per cum = (a+b+c+d+e)/120 5114.43

say 5114.00

12.11 F (iv)

P&M-050 Lead= 1

km

Page 185: Standard Data Book - Rate Analysis

Page 30 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Note

'12.11 F (v) RCC M40 Grade

Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum

Taking output = 120 cum

a) Material

Cement tonne 52.20 5000.00 261000.00 M-081

Coarse Sand cum 54.00 828.00 44712.00 M-004

20 mm Aggregate cum 64.80 1028.00 66614.40 M-053

10 mm Aggregate cum 43.20 1005.00 43416.00 M-051

Admixture kg 206.00 44.70 9208.20 M-180

b) Labour

Mate day 0.84 151.44 127.21 L-12

Mason day 3.00 223.36 670.08 L-11

Mazdoor day 18.00 136.69 2460.42 L-13

c) Machinery

Batching Plant hour 6.00 2232.00 13392.00 P&M-002

Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080

Loader 1 cum capacity hour 6.00 806.00 4836.00 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1017.00 15255.00 P&M-049

Transit Mixer 4 cum capacity for lead beyond 1 km. tonne.km 300.L 2.03 610.20

Concrete Pump hour 6.00 256.00 1536.00 P&M-007

14052.42

d) Overhead charges @ 0.2 on (a+b+c) 96493.29

e) Contractor's profit @ 0.1 on (a+b+c+d) 57895.97

cost of 120 cum = a+b+c+d+e 636855.69

Rate per cum = (a+b+c+d+e)/120 5307.13

say 5307.00

12.12

Unit = Running Meter.

Taking output = 1 m

Diameter of well - 6 m.

A Sandy Soil

(i) Depth below bed level upto 3.0 M

Rate of sinking = 0.50 m per hour.

a) Labour

Mate day 0.12 151.44 18.17 L-12

Sinker ( skilled ) day 1.00 164.69 164.69 L-15

Sinking helper ( semi-skilled ) day 2.00 230.00 460.00 L-14

b) Machinery

hour 2.00 1073.50 2147.00 P&M-075

Consumables in sinking @10 per cent of (b) 214.70

c) Overhead charges @ 0.2 on (a+b) 600.91

d) Contractor's profit @ 0.1 on (a+b+c) 360.55

Rate per metre = (a+b+c+d) 3966.02

say 3966.00

12.12 A (ii) Beyond 3m upto 10m depth

Where ever concrete is carried out using batching plant, transit mixer, concrete pump, Admixtures @ 0.4 per cent of weight of cement may be added for achieving desired slump of concrete.

P&M-050 Lead= 1

km

Formwork @ 3 per cent on cost of concrete i.e. cost of material, labour and machinery

Section 1200

Sinking of 6 m external diameter well (other than pneumatic method of sinking) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is reckoned from bed level.

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Page 186: Standard Data Book - Rate Analysis

Page 31 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Rate of sinking = 0.33 m per hour.

a) Labour

Mate day 0.15 151.44 22.72 L-12

Sinker day 1.25 164.69 205.86 L-15

Sinking helper ( semi-skilled ) day 2.50 230.00 575.00 L-14

b) Machinery

hour 3.00 1073.50 3220.50 P&M-075

Consumables in sinking @10 per cent of (b) 322.05

c) Overhead charges @ 0.2 on (a+b) 869.23

d) Contractor's profit @ 0.1 on (a+b+c) 521.54

Rate per metre = (a+b+c+d) 5736.89

say 5737.00

12.12 A (iii) Beyond 10m upto 20m

a

11th m 5% 6024.00

12th m 5% 6325.00

13th m 5% 6641.00

14th m 5% 6973.00

15th m 5% 7322.00

16th m 5% 7688.00

17th m 5% 8072.00

18th m 5% 8476.00

19th m 5% 8900.00

20th m 5% 9345.00

Total Cost from 10m upto 20m 75766.00

Avg Rate per metre 7577.00

12.12 A (iv) Beyond 20m upto 30 m

a

b

21st m 7.5% 10046.00 12055.00

22nd m 7.5% 10799.00 12959.00

23rd m 7.5% 11609.00 13931.00

24th m 7.5% 12480.00 14976.00

25th m 7.5% 13416.00 16099.00

26th m 7.5% 14422.00 17306.00

27th m 7.5% 15504.00 18605.00

28th m 7.5% 16667.00 20000.00

29th m 7.5% 17917.00 21500.00

30th m 7.5% 19261.00 23113.00

Total Cost from 20m upto 30m 142121.00 170544.00

Avg Rate per metre 14212.00 17054.00

12.12 A (v) Beyond 30m upto 40 m

a

b

31st m 10% 21187.00 25424.00

32nd 10% 23306.00 27967.00

33rd m 10% 25637.00 30764.00

34th m 10% 28201.00 33841.00

35th m 10% 31021.00 37225.00

36th m 10% 34123.00 40948.00

37th m 10% 37535.00 45042.00

38th m 10% 41289.00 49547.00

39th m 10% 45418.00 54502.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories

Add 5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports, loading arrangement and Labour.

Including 20% for Kentledge

Add 10 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports, loading arrangement and Labour.

Including 20% for Kentledge

Page 187: Standard Data Book - Rate Analysis

Page 32 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

40th m 10% 49960.00 59952.00

Total Cost from 30m upto 40m 337677.00 405212.00

Avg Rate per metre 33768.00 40521.00

12.12 B Clayey Soil ( 6m dia. Well )

Unit = Running Meter.

Taking output = 1 meter

(i) Depth below bed level upto 3.0 M

Rate of sinking = 0.33 m per hour.

a) Labour

Mate day 0.15 151.44 22.72 L-12

Sinker ( skilled ) day 1.50 164.69 247.04 L-15

Sinking helper ( semi-skilled ) day 2.25 230.00 517.50 L-14

b) Machinery

hour 3.00 1073.50 3220.50 P&M-075

Consumables in sinking @ 10 per cent of (b) 322.05

c) Overhead charges @ 0.2 on (a+b) 865.96

d) Contractor's profit @ 0.1 on (a+b+c) 519.58

Rate per metre = (a+b+c+d) 5715.34

say 5715.00

12.12 B (ii) Beyond 3m upto 10m depth

Rate of sinking = 0.17 m per hour.

a) Labour

Mate day 0.30 151.44 45.43 L-12

Sinker day 3.00 164.69 494.07 L-15

Sinking helper ( semi-skilled ) day 4.50 230.00 1035.00 L-14

b) Machinery

hour 6.00 1073.50 6441.00 P&M-075

hour 2.00 740.15 1480.30 P&M-063

Consumables in sinking @ 10 per cent of (b) 792.13

c) Overhead charges @ 0.2 on (a+b) 2057.59

d) Contractor's profit @ 0.1 on (a+b+c) 1234.55

Rate per metre = (a+b+c+d) 13580.07

say 13580.00

12.12 B (iii) Beyond 10 m upto 20 m

a

b Add for dewatering @ 5 per cent of cost, if required.

11th m 5% 14259.00 14972.00

12th m 5% 14972.00 15721.00

13th m 5% 15721.00 16507.00

14th m 5% 16507.00 17332.00

15th m 5% 17332.00 18199.00

16th m 5% 18199.00 19109.00

17th m 5% 19109.00 20064.00

18th m 5% 20064.00 21067.00

19th m 5% 21067.00 22120.00

20th m 5% 22120.00 23226.00

Total Cost from 10m upto 20m 179350.00 188317.00

Avg Rate per metre 17935.00 18832.00

12.12 B (iv) Beyond 20m upto 30 m

a

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Air compressor with pneumatic chisel attachment for cutting hard clay.

Add 5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Including for dewatering @ 5% of cost, if

required

Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Page 188: Standard Data Book - Rate Analysis

Page 33 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

b Add 5 per cent of cost for dewatering of the cost, if required

c

21st m 7.5% 23779.00 29724.00 31210.00

22nd m 7.5% 25562.00 31953.00 33551.00

23rd m 7.5% 27479.00 34349.00 36066.00

24th m 7.5% 29540.00 36925.00 38771.00

25th m 7.5% 31756.00 39695.00 41680.00

26th m 7.5% 34138.00 42673.00 44807.00

27th m 7.5% 36698.00 45873.00 48167.00

28th m 7.5% 39450.00 49313.00 51779.00

29th m 7.5% 42409.00 53011.00 55662.00

30th m 7.5% 45590.00 56988.00 59837.00

Total Cost from 20m upto 30m 336401.00 420504.00 441530.00

Avg Rate per metre 33640.00 42050.00 44153.00

12.12 B (v) Beyond 30m upto 40 m

a

b Add 5 per cent of cost for dewatering, if required

c

31st m 10% 50149.00 60179.00 63188.00

32nd 10% 55164.00 66197.00 69507.00

33rd m 10% 60680.00 72816.00 76457.00

34th m 10% 66748.00 80098.00 84103.00

35th m 10% 73423.00 88108.00 92513.00

36th m 10% 80765.00 96918.00 101764.00

37th m 10% 88842.00 106610.00 111941.00

38th m 10% 97726.00 117271.00 123135.00

39th m 10% 107499.00 128999.00 135449.00

40th m 10% 118249.00 141899.00 148994.00

Total Cost from 30m upto 40m 799245.00 959095.00 1007051.00

Avg Rate per metre 79925.00 95910.00 100705.00

12.12 C Soft Rock (6m dia well )

Unit = Running Meter.

Taking output = 1 m

Depth in Soft rock strata up to 3m

Rate of sinking = 0.25 m per hour.

a) Labour

Mate day 0.92 151.44 139.32 L-12

Sinker ( skilled ) day 3.00 164.69 494.07 L-15

Sinking helper ( semi-skilled ) day 20.00 230.00 4600.00 L-14

Diver day 0.50 264.50 132.25 L-07

b) Machinery

hour 4.00 1073.50 4294.00 P&M-075

Air compressor with pneumatic breakers hour 3.50 740.15 2590.53 P&M-063

Consumables in sinking @ 10 per cent of (b) 688.45

646.93

c) Overhead charges @ 0.2 on (a+b) 2717.11

d) Contractor's profit @ 0.1 on (a+b+c) 1630.27

Rate per metre = (a+b+c+d) 17932.93

say 17933.00

Add 25 per cent of cost for Kentledge including supports, loading arrangement and Labour ).

Including 25% for Kentledge

Including 5% for

dewatering, if required

Add 10 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports, loading arrangement and Labour).

Including 20% for Kentledge

Including 5% for

dewatering, if required

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Add for dewatering @ of 5 per cent of (a+b), if required

Page 189: Standard Data Book - Rate Analysis

Page 34 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

12.12 D Hard Rock (6m dia well )

Unit = Running Meter

Taking output = 1 m

Depth in hard rock strata upto 3 m

Rate of sinking = 0.17 m per hour.

a) Material

Gelatine 80 per cent Kg 4.00 146.00 584.00 M-104

Electric Detonators each 18.00 14.56 262.08 M-094/100

b) Labour

Mate day 1.56 151.44 236.25 L-12

Driller day 2.00 264.50 529.00 L-06

Blaster day 0.25 264.50 66.13 L-03

Mazdoor day 12.00 136.69 1640.28 L-13

Mazdoor (Skilled) day 4.00 164.69 658.76 L-15

c) Machinery

hour 6.00 1073.50 6441.00 P&M-075

hour 2.00 740.15 1480.30 P&M-063

Dewatering @ 5 per cent of cost of (b+c), if required. 552.59

Consumables in sinking @ 10 per cent of cost of (b). 792.13

d) Overhead charges @ 0.2 on (a+b+c) 2648.50

e) Contractor's profit @ 0.1 on (a+b+c+d) 1589.10

Rate per metre = (a+b+c+d+e) 17480.11

say 17480.00

12.13

Unit = Running Meter.

Taking output = 1 m

Diameter of well - 7 m.

A Sandy Soil

(i) Depth below bed level upto 3.0 M

Rate of sinking = 0.30 m per hour.

a) Labour

Mate day 0.15 151.44 22.72 L-12

Sinker ( skilled ) day 1.25 164.69 205.86 L-15

Sinking helper ( semi-skilled ) day 2.50 230.00 575.00 L-14

b) Machinery

hour 3.25 1073.50 3488.88 P&M-075

Consumables in sinking @10 per cent of (b) 348.89

c) Overhead charges @ 0.2 on (a+b) 928.27

d) Contractor's profit @ 0.1 on (a+b+c) 464.13

Rate per metre = (a+b+c+d) 6033.74

12.13 A (ii) Beyond 3m upto 10m depth 12067.49

Rate of sinking = 0.22 m per hour. say 12067.00

a) Labour

Mate day 0.18 151.44 27.26 L-12

Sinker day 1.50 164.69 247.04 L-15

Sinking helper ( semi-skilled ) day 3.00 230.00 690.00 L-14

b) Machinery

hour 4.50 1073.50 4830.75 P&M-075

Consumables in sinking @10 per cent of (b) 483.08

c) Overhead charges @ 0.2 on (a+b) 1255.62

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Hire & running charges of compressor with pneumatic breaker/Jack hammer for drilling.

Section 1200

Sinking of 7 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is reckoned from bed level.

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Page 190: Standard Data Book - Rate Analysis

Page 35 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

d) Contractor's profit @ 0.1 on (a+b+c) 753.37

Rate per metre = (a+b+c+d) 8287.12

say 8287.00

12.13 A (iii) Beyond 10m upto 20m

a

11th m 5% 8701.00

12th m 5% 9136.00

13th m 5% 9593.00

14th m 5% 10073.00

0.165 15th m 5% 10577.00

16th m 5% 11106.00

17th m 5% 11661.00

18th m 5% 12244.00

19th m 5% 12856.00

20th m 5% 13499.00

Total Cost from 10m upto 20m 109446.00

Avg Rate per metre 10945.00

12.13 A (iv) Beyond 20m upto 30 m

a

b

21st m 7.5% 14511.00 17413.00

22nd m 7.5% 15599.00 18719.00

23rd m 7.5% 16769.00 20123.00

24th m 7.5% 18027.00 21632.00

25th m 7.5% 19379.00 23255.00

26th m 7.5% 20832.00 24998.00

27th m 7.5% 22394.00 26873.00

28th m 7.5% 24074.00 28889.00

29th m 7.5% 25880.00 31056.00

30th m 7.5% 27821.00 33385.00

Total Cost from 20m upto 30m 205286.00 246343.00

Avg Rate per metre 20529.00 24634.00

12.13 A (v) Beyond 30m upto 40 m

a

b

31st m 10% 30603.00 36724.00

32nd 10% 33663.00 40396.00

33rd m 10% 37029.00 44435.00

34th m 10% 40732.00 48878.00

35th m 10% 44805.00 53766.00

36th m 10% 49286.00 59143.00

37th m 10% 54215.00 65058.00

38th m 10% 59637.00 71564.00

39th m 10% 65601.00 78721.00

40th m 10% 72161.00 86593.00

Total Cost from 30m upto 40m 487732.00 585278.00

Avg Rate per metre 48773.00 58528.00

12.13 B Clayey Soil ( 7m dia. Well )

Unit = Running Meter.

Taking output = 1 cum

(I) Depth below bed level upto 3.0 M

Rate of sinking = 0.22 m per hour.

a) Labour

Add 5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports, loading arrangement and Labour).

Including 20% for Kentledge

Add 10 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports, loading arrangement, and Labour etc.

Including 20% for Kentledge

Page 191: Standard Data Book - Rate Analysis

Page 36 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Mate day 0.18 151.44 27.26 L-12

Sinker ( skilled ) day 1.50 164.69 247.04 L-15

Sinking helper ( semi-skilled ) day 3.00 230.00 690.00 L-14

b) Machinery

hour 4.50 1073.50 4830.75 P&M-075

Consumables in sinking @ 10 per cent of (b) 483.08

d) Overhead charges @ 0.2 on (a+b) 1255.62

e) Contractor's profit @ 0.1 on (a+b+c) 753.37

Rate per metre = (a+b+c+d) 8287.12

say 8287.00

12.13 B (ii) Beyond 3m upto 10m depth

Rate of sinking = 0.17 m per hour.

a) Labour

Mate day 0.26 151.44 39.37 L-12

Sinker day 2.00 164.69 329.38 L-15

Sinking helper ( semi-skilled ) day 4.00 230.00 920.00 L-14

b) Machinery

hour 6.00 1073.50 6441.00 P&M-075

hour 3.25 740.15 644.10 P&M-063

Consumables in sinking @ 10 per cent of (b) 708.51

c) Overhead charges @ 0.2 on (a+b) 1816.47

d) Contractor's profit @ 0.1 on (a+b+c) 1089.88

Rate per metre = (a+b+c+d) 11988.72

say 11989.00

12.13 B (iii) Beyond 10 m upto 20 m

a

b Add for dewatering @ 5 per cent of cost, if required.

11th m 5% 12588.00 13217.00

12th m 5% 13217.00 13878.00

13th m 5% 13878.00 14572.00

14th m 5% 14572.00 15301.00

15th m 5% 15301.00 16066.00

16th m 5% 16066.00 16869.00

17th m 5% 16869.00 17712.00

18th m 5% 17712.00 18598.00

19th m 5% 18598.00 19528.00

20th m 5% 19528.00 20504.00

Total Cost from 10m upto 20m 158329.00 166245.00

Avg Rate per metre 15833.00 16625.00

12.13 B (iv) Beyond 20m upto 30 m

a

b Add 5 per cent of cost for dewatering on the cost, if required

c

31st m 7.5% 20993.00 26241.00 27553.00

32nd 7.5% 22567.00 28209.00 29619.00

33rd m 7.5% 24260.00 30325.00 31841.00

34th m 7.5% 26080.00 32600.00 34230.00

35th m 7.5% 28036.00 35045.00 36797.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Air compressor with pneumatic chisel attachment for cutting hard clay.

Add 5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Including for dewatering @ 5% of cost, if

required

Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 25 per cent of cost for Kentledge including supports, loading arrangement and Labour ).

Including 25% for Kentledge

Including 5% for

dewatering, if required

Page 192: Standard Data Book - Rate Analysis

Page 37 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

36th m 7.5% 30139.00 37674.00 39558.00

37th m 7.5% 32399.00 40499.00 42524.00

38th m 7.5% 34829.00 43536.00 45713.00

39th m 7.5% 37441.00 46801.00 49141.00

40th m 7.5% 40249.00 50311.00 52827.00

Total Cost from 30m upto 40m 296993.00 371241.00 389803.00

Avg Rate per metre 29699.00 37124.00 38980.00

12.13 B (v) Beyond 30m upto 40 m

a

b Add 5 per cent of cost for dewatering, if required

c

31st m 10% 44274.00 53129.00 55785.00

32nd 10% 48701.00 58441.00 61363.00

33rd m 10% 53571.00 64285.00 67499.00

34th m 10% 58928.00 70714.00 74250.00

35th m 10% 64821.00 77785.00 81674.00

36th m 10% 71303.00 85564.00 89842.00

37th m 10% 78433.00 94120.00 98826.00

38th m 10% 86276.00 103531.00 108708.00

39th m 10% 94904.00 113885.00 119579.00

40th m 10% 104394.00 125273.00 131537.00

Total Cost from 30m upto 40m 705605.00 846727.00 889063.00

Avg Rate per metre 70561.00 84673.00 88906.00

12.13 C Soft Rock ( 7m dia well )

Unit = Running Meter.

Taking output = 1 m

Depth in soft rock strata upto 3m

Rate of sinking = 0.22 m per hour.

a) Labour

Mate day 0.58 151.44 87.84 L-12

Sinker ( skilled ) day 4.00 164.69 658.76 L-15

Sinking helper ( semi-skilled ) day 10.00 230.00 2300.00 L-14

Diver day 0.75 264.50 198.38 L-07

b) Machinery

hour 4.50 1073.50 4830.75 P&M-075

Air compressor with pneumatic breakers hour 3.75 740.15 2775.56 P&M-063

Consumables in sinking @ 10 per cent of (b) 760.63

542.56

c) Overhead charges @ 0.2 on (a+b) 2430.90

d) Contractor's profit @ 0.1 on (a+b+c) 1458.54

Rate per metre = (a+b+c+d) 16043.91

say 16044.00

12.13 D Hard Rock ( 7m dia well )

Unit = Running Meter

Taking output = 1 m

Depth in Hard rock strata up to 3 m

Rate of sinking = 0.17 m per hour.

a) Material

Gelatine 80 per cent Kg 7.00 146.00 1022.00 M-104

Electric Detonators each 30.00 14.56 436.80 M-094/100

b) Labour

Mate day 1.60 151.44 242.30 L-12

Add 10 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports, loading arrangement and Labour).

Including 20% for Kentledge

Including 5% for

dewatering, if required

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Add for dewatering @ of 5 per cent of (a+b), if required

Page 193: Standard Data Book - Rate Analysis

Page 38 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Driller day 2.00 264.50 529.00 L-06

Blaster day 0.25 264.50 66.13 L-03

Mazdoor day 18.00 136.69 2460.42 L-13

Mazdoor (Skilled) day 4.00 164.69 658.76 L-15

Diver day 0.50 264.50 132.25 L-07

c) Machinery

hour 6.00 1073.50 6441.00 P&M-075

hour 2.00 740.15 1480.30 P&M-063

Dewatering @ 5 per cent of cost of (b+c), if required. 600.51

Consumables in sinking @ 10 per cent of cost of (b). 852.18

d) Overhead charges @ 0.2 on (a+b+c) 2984.33

e) Contractor's profit @ 0.1 on (a+b+c+d) 1790.60

Rate per metre = (a+b+c+d+e) 19696.58

say 19697.00

12.14

Unit = Running Meter.

Taking output = 1 m

Diameter of well - 8 m.

A Sandy Soil

(i) Depth below bed level upto 3.0 M

Rate of sinking @ 0.25 m/hour

a) Labour

Mate day 0.18 151.44 27.26 L-12

Sinker ( skilled ) day 1.50 164.69 247.04 L-15

Sinking helper ( semi-skilled ) day 3.00 230.00 690.00 L-14

b) Machinery

hour 4.00 1073.50 4294.00 P&M-075

Consumables in sinking @10 per cent of (b) 429.40

c) Overhead charges @ 0.2 on (a+b) 1137.54

d) Contractor's profit @ 0.1 on (a+b+c) 682.52

Rate per metre = (a+b+c+d) 7507.76

say 7508.00

12.14 A (ii) Beyond 3m upto 10m depth

Rate of sinking @ 0.20 m/hour

a) Labour

Mate day 0.25 151.44 37.86 L-12

Sinker day 1.75 164.69 288.21 L-15

Sinking helper ( semi-skilled ) day 3.50 230.00 805.00 L-14

b) Machinery

hour 5.00 1073.50 5367.50 P&M-075

Consumables in sinking @10 per cent of (b) 536.75

c) Overhead charges @ 0.2 on (a+b) 1407.06

d) Contractor's profit @ 0.1 on (a+b+c) 844.24

Rate per metre = (a+b+c+d) 9286.62

say 9287.00

12.14 A (iii) Beyond 10m upto 20m

a

11th m 5% 9751.00

12th m 5% 10239.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Hire & running charges of compressor with pneumatic breaker/Jack hammer for drilling.

Section 1200

Sinking of 8 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is reckoned from bed level.

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Add 5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Page 194: Standard Data Book - Rate Analysis

Page 39 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

13th m 5% 10751.00

14th m 5% 11289.00

15th m 5% 11853.00

16th m 5% 12446.00

17th m 5% 13068.00

18th m 5% 13721.00

19th m 5% 14407.00

20th m 5% 15127.00

Total Cost from 10m upto 20m 122652.00

Avg Rate per metre 12265.00

12.14 A (iv) Beyond 20m upto 30 m

a

b

21st m 7.5% 16262.00 19514.00

22nd m 7.5% 17482.00 20978.00

23rd m 7.5% 18793.00 22552.00

24th m 7.5% 20202.00 24242.00

25th m 7.5% 21717.00 26060.00

26th m 7.5% 23346.00 28015.00

27th m 7.5% 25097.00 30116.00

28th m 7.5% 26979.00 32375.00

29th m 7.5% 29002.00 34802.00

30th m 7.5% 31177.00 37412.00

Total Cost from 20m upto 30m 230057.00 276066.00

Avg Rate per metre 23006.00 27607.00

12.14 A (v) Beyond 30m upto 40 m

a

b

31st m 10% 34295.00 41154.00

32nd 10% 37725.00 45270.00

33rd m 10% 41498.00 49798.00

34th m 10% 45648.00 54778.00

35th m 10% 50213.00 60256.00

36th m 10% 55234.00 66281.00

37th m 10% 60757.00 72908.00

38th m 10% 66833.00 80200.00

39th m 10% 73516.00 88219.00

40th m 10% 80868.00 97042.00

Total Cost from 30m upto 40m 80868.00 97042.00

Avg Rate per metre 8087.00 9704.00

12.14 B Clayey Soil ( 8m dia. Well )

Unit = Running Meter.

Taking output = 1 meter

(i) Depth from bed level upto 3.0 M

Rate of sinking @ 0.18 m/hour

a) Labour

Mate day 0.22 151.44 33.32 L-12

Sinker ( skilled ) day 2.00 164.69 329.38 L-15

Sinking helper ( semi-skilled ) hour 3.50 230.00 805.00 L-14

b) Machinery

5.50 1073.50 5904.25 P&M-075

Consumables in sinking @ 10 per cent of (b) 590.43

c) Overhead charges @ 0.2 on (a+b) 1532.47

Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports, loading arrangement and Labour.

Including 20% for Kentledge

Add 10 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports, loading arrangement, and Labour etc.

Including 20% for Kentledge

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Page 195: Standard Data Book - Rate Analysis

Page 40 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

d) Contractor's profit @ 0.1 on (a+b+c) 919.48

Rate per metre = (a+b+c+d) 10114.33

say 10114.00

12.14 B (ii) Beyond 3m upto 10m depth

Rate of sinking @ 0.17 m/hour

a) Labour

Mate day 0.32 151.44 48.46 L-12

Sinker day 2.50 164.69 411.73 L-15

Sinking helper ( semi-skilled ) day 4.50 230.00 1035.00 L-14

b) Machinery

hour 6.00 1073.50 6441.00 P&M-075

hour 3.50 740.15 2590.53 P&M-063

Consumables in sinking @ 10 per cent of (b) 903.15

c) Overhead charges @ 0.2 on (a+b) 2285.97

d) Contractor's profit @ 0.1 on (a+b+c) 1371.58

Rate per metre = (a+b+c+d) 15087.42

say 15087.00

12.14 B (iii) Beyond 10 m upto 20 m

a

b Add for dewatering @ 5 per cent of cost, if required.

11th m 5% 15842.00 16634.00

12th m 5% 16634.00 17466.00

13th m 5% 17466.00 18339.00

14th m 5% 18339.00 19256.00

15th m 5% 19256.00 20219.00

16th m 5% 20219.00 21230.00

17th m 5% 21230.00 22292.00

18th m 5% 22292.00 23407.00

19th m 5% 23407.00 24577.00

20th m 5% 24577.00 25806.00

Total Cost from 10m upto 20m 199262.00 209226.00

Avg Rate per metre 19926.00 20923.00

12.14 B (iv) Beyond 20m upto 30 m

a

b Add 5 per cent of cost for dewatering on the cost, if required

c

31st m 7.5% 26420.00 33025.00 34676.00

32nd 7.5% 28402.00 35503.00 37278.00

33rd m 7.5% 30532.00 38165.00 40073.00

34th m 7.5% 32822.00 41028.00 43079.00

35th m 7.5% 35284.00 44105.00 46310.00

36th m 7.5% 37930.00 47413.00 49784.00

37th m 7.5% 40775.00 50969.00 53517.00

38th m 7.5% 43833.00 54791.00 57531.00

39th m 7.5% 47120.00 58900.00 61845.00

40th m 7.5% 50654.00 63318.00 66484.00

Total Cost from 30m upto 40m 373772.00 467217.00 490577.00

Avg Rate per metre 37377.00 46722.00 49058.00

12.14 B (v) Beyond 30m upto 40 m

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Air compressor with pneumatic chisel attachment for cutting hard clay.

Add 5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Including for dewatering @ 5% of cost, if

required

Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 25 per cent of cost for Kentledge including supports, loading arrangement and Labour ).

Including 25% for Kentledge

Including 5% for

dewatering, if required

Page 196: Standard Data Book - Rate Analysis

Page 41 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

a

b Add 5 per cent of cost for dewatering, if required

c

31st m 10% 55719.00 66863.00 70206.00

32nd 10% 61291.00 73549.00 77226.00

33rd m 10% 67420.00 80904.00 84949.00

34th m 10% 74162.00 88994.00 93444.00

35th m 10% 81578.00 97894.00 102789.00

36th m 10% 89736.00 107683.00 113067.00

37th m 10% 98710.00 118452.00 124375.00

38th m 10% 108581.00 130297.00 136812.00

39th m 10% 119439.00 143327.00 150493.00

40th m 10% 131383.00 157660.00 165543.00

Total Cost from 30m upto 40m 888019.00 1065623.00 1118904.00

Avg Rate per metre 88802.00 106562.00 111890.00

12.14 C Soft Rock ( 8m dia well )

Unit = Running Meter.

Taking output = 1 m

Depth in soft rock strata upto 3m

Rate of sinking @ 0.20 m/hour

a) Labour

Mate day 0.68 151.44 102.98 L-12

Sinker ( skilled ) day 4.00 164.69 658.76 L-15

Sinking helper ( semi-skilled ) day 12.00 230.00 2760.00 L-14

Diver day 1.00 264.50 264.50 L-07

b) Machinery

hour 5.00 1073.50 5367.50 P&M-075

Air compressor with pneumatic breakers hour 3.75 740.15 2775.56 P&M-063

Consumables in sinking @ 10 per cent of (b) 814.31

637.18

c) Overhead charges @ 0.2 on (a+b) 2676.16

d) Contractor's profit @ 0.1 on (a+b+c) 1605.69

Rate per metre = (a+b+c+d) 17662.64

say 17663.00

12.14 D Hard Rock ( 8m dia well )

Unit = Running Meter

Taking output = 1 m

Depth in hard rock strata upto 3 m

Rate of sinking @ 0.17 m/hour

a) Material

Gelatine 80 per cent Kg 8.00 146.00 1168.00 M-104

Electric Detonators each 32.00 14.56 465.92 M-094/100

b) Labour

Mate day 1.09 151.44 165.07 L-12

Driller day 2.00 264.50 529.00 L-06

Blaster day 0.25 264.50 66.13 L-03

Mazdoor day 20.00 136.69 2733.80 L-13

Mazdoor (Skilled) day 4.00 164.69 658.76 L-15

c) Machinery

hour 6.00 1073.50 6441.00 P&M-075

hour 2.00 740.15 1480.30 P&M-063

Add 10 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports, loading arrangement and Labour).

Including 20% for Kentledge

Including 5% for

dewatering, if required

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Add for dewatering @ of 5 per cent of (a+b), if required

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Hire & running charges of compressor with pneumatic breaker/Jack hammer for drilling.

Page 197: Standard Data Book - Rate Analysis

Page 42 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Dewatering @ 5 per cent of cost of (b+c), if required. 603.70

Consumables in sinking @ 10 per cent of cost of (b). 415.28

d) Overhead charges @ 0.2 on (a+b+c) 2945.39

e) Contractor's profit @ 0.1 on (a+b+c+d) 1767.23

Rate per metre = (a+b+c+d+e) 19439.58

say 19440.00

12.15

Unit = Running Meter.

Taking output = 1 m

Diameter of well - 9 m.

A Sandy Soil

(i) Depth below bed level upto 3.0 M

Rate of sinking @ 0.25 m/hour

a) Labour

Mate day 0.19 151.44 28.77 L-12

Sinker ( skilled ) day 1.50 164.69 247.04 L-15

Sinking helper ( semi-skilled ) day 3.25 230.00 747.50 L-14

b) Machinery

hour 4.00 1073.50 4294.00 P&M-075

Consumables in sinking @10 per cent of (b) 429.40

c) Overhead charges @ 0.2 on (a+b) 1149.34

d) Contractor's profit @ 0.1 on (a+b+c) 689.61

Rate per metre = (a+b+c+d) 7585.66

say 7586.00

12.15 A (ii) Beyond 3m upto 10m depth

Rate of sinking @ 0.18 m/hour

a) Labour

Mate day 0.27 151.44 40.89 L-12

Sinker day 1.75 164.69 288.21 L-15

Sinking helper ( semi-skilled ) day 4.00 230.00 920.00 L-14

b) Machinery

hour 5.50 1073.50 5904.25 P&M-075

Consumables in sinking @10 per cent of (b) 590.43

c) Overhead charges @ 0.2 on (a+b) 1548.75

d) Contractor's profit @ 0.1 on (a+b+c) 929.25

Rate per metre = (a+b+c+d) 10221.78

say 10222.00

12.15 A (iii) Beyond 10m upto 20m

a

11th m 5% 10733.00

12th m 5% 11270.00

13th m 5% 11834.00

14th m 5% 12426.00

15th m 5% 13047.00

16th m 5% 13699.00

17th m 5% 14384.00

18th m 5% 15103.00

19th m 5% 15858.00

20th m 5% 16651.00

Total Cost from 10m upto 20m 135005.00

Avg Rate per metre 13501.00

Section 1200

Sinking of 9 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is reckoned from bed level.

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Add 5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Page 198: Standard Data Book - Rate Analysis

Page 43 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

12.15 A (iv) Beyond 20m upto 30 m

a

b

21st m 7.5% 17899.83 21480.00

22nd m 7.5% 19242.00 23090.00

23rd m 7.5% 20685.00 24822.00

24th m 7.5% 22236.00 26683.00

25th m 7.5% 23904.00 28685.00

26th m 7.5% 25697.00 30836.00

27th m 7.5% 27624.00 33149.00

28th m 7.5% 29696.00 35635.00

29th m 7.5% 31923.00 38308.00

30th m 7.5% 34317.00 41180.00

Total Cost from 20m upto 30m 253223.83 303868.00

Avg Rate per metre 25322.00 30387.00

12.15 A (v) Beyond 30m upto 40 m

a

b

31st m 10% 37748.70 45298.00

32nd 10% 41524.00 49829.00

33rd m 10% 45676.00 54811.00

34th m 10% 50244.00 60293.00

35th m 10% 55268.00 66322.00

36th m 10% 60795.00 72954.00

37th m 10% 66875.00 80250.00

38th m 10% 73563.00 88276.00

39th m 10% 80919.00 97103.00

40th m 10% 89011.00 106813.00

Total Cost from 30m upto 40m 601623.70 721949.00

Avg Rate per metre 60162.00 72195.00

12.15 B Clayey Soil ( 9m dia. Well )

Unit = Running Meter.

Taking output = 1 cum

(i) Depth below bed level upto 3.0 M

Rate of sinking 0.17 m / hour

a) Labour

Mate day 0.24 151.44 36.35 L-12

Sinker ( skilled ) day 2.25 164.69 370.55 L-15

Sinking helper ( semi-skilled ) day 3.75 230.00 862.50 L-14

b) Machinery

hour 5.75 1073.50 6172.63 P&M-075

Consumables in sinking @ 10 per cent of (b) 617.26

c) Overhead charges @ 0.2 on (a+b) 1611.86

d) Contractor's profit @ 0.1 on (a+b+c) 967.11

Rate per metre = (a+b+c+d) 10638.26

say 10638.00

12.15 B (ii) Beyond 3m upto 10m depth

Rate of sinking 0.15 m / hour

a) Labour

Mate day 0.34 151.44 51.49 L-12

Sinker day 2.50 164.69 411.73 L-15

Sinking helper ( semi-skilled ) day 5.00 230.00 1150.00 L-14

b) Machinery

Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports, loading arrangement and Labour.

Including 20% for Kentledge

Add 10 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports, loading arrangement, and Labour etc.

Including 20% for Kentledge

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Page 199: Standard Data Book - Rate Analysis

Page 44 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

hour 6.50 1073.50 6977.75 P&M-075

hour 3.75 740.15 2775.56 P&M-063

Consumables in sinking @ 10 per cent of (b) 975.33

c) Overhead charges @ 0.2 on (a+b) 2468.37

d) Contractor's profit @ 0.1 on (a+b+c) 1481.02

Rate per metre = (a+b+c+d) 16291.25

say 16291.00

12.15 B (iii) Beyond 10 m upto 20 m

a

b Add for dewatering @ 5 per cent of cost, if required.

11th m 5% 17106.00 17961.00

12th m 5% 17961.00 18859.00

13th m 5% 18859.00 19802.00

14th m 5% 19802.00 20792.00

15th m 5% 20792.00 21832.00

16th m 5% 21832.00 22924.00

17th m 5% 22924.00 24070.00

18th m 5% 24070.00 25274.00

19th m 5% 25274.00 26538.00

20th m 5% 26538.00 27865.00

Total Cost from 10m upto 20m 215158.00 225917.00

Avg Rate per metre 21516.00 22592.00

12.15 B (iv) Beyond 20m upto 30 m

a

b Add 5 per cent of cost for dewatering on the cost, if required

c

31st m 7.5% 28528.00 35660.00 37443.00

32nd 7.5% 30668.00 38335.00 40252.00

33rd m 7.5% 32968.00 41210.00 43271.00

34th m 7.5% 35441.00 44301.00 46516.00

35th m 7.5% 38099.00 47624.00 50005.00

36th m 7.5% 40956.00 51195.00 53755.00

37th m 7.5% 44028.00 55035.00 57787.00

38th m 7.5% 47330.00 59163.00 62121.00

39th m 7.5% 50880.00 63600.00 66780.00

40th m 7.5% 54696.00 68370.00 71789.00

Total Cost from 30m upto 40m 403594.00 504493.00 529719.00

Avg Rate per metre 40359.00 50449.00 52972.00

12.15 B (v) Beyond 30m upto 40 m

a

b Add 5 per cent of cost for dewatering, if required

c

31st m 10% 60166.00 72199.00 75809.00

32nd 10% 66183.00 79420.00 83391.00

33rd m 10% 72801.00 87361.00 91729.00

34th m 10% 80081.00 96097.00 100902.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Air compressor with pneumatic chisel attachment for cutting hard clay.

Add 5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Including for dewatering @ 5% of cost, if

required

Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 25 per cent of cost for Kentledge including supports, loading arrangement and Labour ).

Including 25% for Kentledge

Including 5% for

dewatering, if required

Add 10 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports, loading arrangement and Labour).

Including 20% for Kentledge

Including 5% for

dewatering, if required

Page 200: Standard Data Book - Rate Analysis

Page 45 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

35th m 10% 88089.00 105707.00 110992.00

36th m 10% 96898.00 116278.00 122092.00

37th m 10% 106588.00 127906.00 134301.00

38th m 10% 117247.00 140696.00 147731.00

39th m 10% 128972.00 154766.00 162504.00

40th m 10% 141869.00 170243.00 178755.00

Total Cost from 30m upto 40m 958894.00 1150673.00 1208206.00

Avg Rate per metre 95889.00 115067.00 120821.00

12.15 C Soft Rock ( 9m dia well )

Unit = Running Meter.

Taking output = 1 m

Depth in soft rock strata up to 3m

Rate of sinking 0.15 m / hour

a) Labour

Mate day 0.76 151.44 115.09 L-12

Sinker ( skilled ) day 4.00 164.69 658.76 L-15

Sinking helper ( semi-skilled ) day 14.00 230.00 3220.00 L-14

Diver day 1.20 264.50 317.40 L-07

b) Machinery

hour 6.50 1073.50 6977.75 P&M-075

Air compressor with pneumatic breakers hour 4.00 740.15 2960.60 P&M-063

Consumables in sinking @ 10 per cent of (b) 993.84

1524.34

c) Overhead charges @ 0.2 on (a+b) 3353.56

d) Contractor's profit @ 0.1 on (a+b+c) 2012.13

Rate per metre = (a+b+c+d) 22133.47

say 22133.00

12.15 D Hard Rock ( 9m dia well )

Unit = Running Meter

Taking output = 1 m

Depth in hard rock strata upto 3 m

Rate of sinking 0.15 m / hour

a) Material

Gelatine 80 per cent Kg 10.00 146.00 1460.00 M-104

Electric Detonators each 40.00 14.56 582.40 M-094/100

b) Labour

Mate day 1.17 151.44 177.18 L-12

Driller day 2.00 264.50 529.00 L-06

Blaster day 0.25 264.50 66.13 L-03

Mazdoor day 22.00 136.69 3007.18 L-13

Mazdoor (Skilled) day 4.00 164.69 658.76 L-15

Diver day 1.00 264.50 264.50 L-07

c) Machinery

hour 7.00 1073.50 7514.50 P&M-075

hour 2.50 740.15 1850.38 P&M-063

Dewatering @ 5 per cent of cost of (b+c), if required. 703.38

Consumables in sinking @ 10 per cent of cost of (b). 470.27

d) Overhead charges @ 0.2 on (a+b+c) 3456.74

e) Contractor's profit @ 0.1 on (a+b+c+d) 2074.04

Rate per metre = (a+b+c+d+e) 22814.46

say 22814.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Add for dewatering @ of 5 per cent of (a+b), if required

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Hire & running charges of compressor with pneumatic breaker/Jack hammer for drilling.

Page 201: Standard Data Book - Rate Analysis

Page 46 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

12.16 1200

Unit = Running Meter

Taking output = 1 m

Diameter of well - 10 m.

A Sandy Soil

(i) Depth below bed level upto 3.0 M

Rate of sinking 0.20 m / hour

a) Labour

Mate day 0.20 151.44 30.29 L-12

Sinker ( skilled ) day 1.50 164.69 247.04 L-15

Sinking helper ( semi-skilled ) day 3.50 230.00 805.00 L-14

b) Machinery

hour 5.00 1073.50 5367.50 P&M-075

Consumables in sinking @10 per cent of (b) 536.75

c) Overhead charges @ 0.2 on (a+b) 1397.31

d) Contractor's profit @ 0.1 on (a+b+c) 838.39

Rate per metre = (a+b+c+d) 9222.28

say 9222.00

12.16 A (ii) Beyond 3m upto 10m depth

Rate of sinking 0.17 m / hour

a) Labour

Mate day 0.31 151.44 46.95 L-12

Sinker day 2.00 164.69 329.38 L-15

Sinking helper ( semi-skilled ) day 4.25 230.00 977.50 L-14

b) Machinery

hour 5.75 1073.50 6172.63 P&M-075

Consumables in sinking @10 per cent of (b) 617.26

c) Overhead charges @ 0.2 on (a+b) 1628.74

d) Contractor's profit @ 0.1 on (a+b+c) 977.25

Rate per metre = (a+b+c+d) 10749.70

say 10750.00

12.16 A (iii) Beyond 10m upto 20m

a

11th m 5% 11287.00

12th m 5% 11851.00

13th m 5% 12444.00

14th m 5% 13066.00

15th m 5% 13719.00

16th m 5% 14405.00

17th m 5% 15125.00

18th m 5% 15881.00

19th m 5% 16675.00

20th m 5% 17509.00

Total Cost from 10m upto 20m 141962.00

Avg Rate per metre 14196.00

12.16 A (iv) Beyond 20m upto 30 m

a

b

21st m 7.5% 18822.00 22586.00

Sinking of 10 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is reckoned from bed level.

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Add 5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports, loading arrangement and Labour.

Including 20% for Kentledge

Page 202: Standard Data Book - Rate Analysis

Page 47 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

22nd m 7.5% 20234.00 24281.00

23rd m 7.5% 21752.00 26102.00

24th m 7.5% 23383.00 28060.00

25th m 7.5% 25137.00 30164.00

26th m 7.5% 27022.00 32426.00

27th m 7.5% 29049.00 34859.00

28th m 7.5% 31228.00 37474.00

29th m 7.5% 33570.00 40284.00

30th m 7.5% 36088.00 43306.00

Total Cost from 20m upto 30m 266285.00 319542.00

Avg Rate per metre 26629.00 31954.00

12.16 A (v) Beyond 30m upto 40 m

a

b

31st m 10% 39697.00 47636.00

32nd 10% 43667.00 52400.00

33rd m 10% 48034.00 57641.00

34th m 10% 52837.00 63404.00

35th m 10% 58121.00 69745.00

36th m 10% 63933.00 76720.00

37th m 10% 70326.00 84391.00

38th m 10% 77359.00 92831.00

39th m 10% 85095.00 102114.00

40th m 10% 93605.00 112326.00

Total Cost from 30m upto 40m 632674.00 759208.00

Avg Rate per metre 63267.00 75921.00

12.16 B Clayey Soil (10m dia. Well )

Unit = Running Meter

Taking output = 1 cum

(i) Depth below bed level upto 3.0 M

Rate of sinking 0.18m/hour.

a) Labour

Mate day 0.25 151.44 37.86 L-12

Sinker ( skilled ) day 2.50 164.69 411.73 L-15

Sinking helper ( semi-skilled ) day 5.50 230.00 1265.00 L-14

b) Machinery

hour 6.00 1073.50 6441.00 P&M-075

Consumables in sinking @ 10 per cent of (b) 644.10

c) Overhead charges @ 0.2 on (a+b) 1759.94

d) Contractor's profit @ 0.1 on (a+b+c) 1055.96

Rate per metre = (a+b+c+d) 11615.58

say 11616.00

12.16 B (ii) Beyond 3m upto 10m depth

Rate of sinking 0.15m/hour.

a) Labour

Mate day 0.40 151.44 60.58 L-12

Sinker day 3.00 164.69 494.07 L-15

Sinking helper ( semi-skilled ) day 5.50 230.00 1265.00 L-14

b) Machinery

hour 6.00 1073.50 6441.00 P&M-075

hour 4.00 740.15 2960.60 P&M-063

Consumables in sinking @ 10 per cent of (b) 940.16

c) Overhead charges @ 0.2 on (a+b) 2432.28

Add 10 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports, loading arrangement, and Labour etc.

Including 20% for Kentledge

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Air compressor with pneumatic chisel attachment for cutting hard clay

Page 203: Standard Data Book - Rate Analysis

Page 48 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

d) Contractor's profit @ 0.1 on (a+b+c) 1459.37

Rate per metre = (a+b+c+d) 16053.06

say 16053.00

12.16 B (iii) Beyond 10 m upto 20 m

a

b Add for dewatering @ 5 per cent of cost, if required.

11th m 5% 16856.00 17699.00

12th m 5% 17699.00 18584.00

13th m 5% 18584.00 19513.00

14th m 5% 19513.00 20489.00

15th m 5% 20489.00 21513.00

16th m 5% 21513.00 22589.00

17th m 5% 22589.00 23718.00

18th m 5% 23718.00 24904.00

19th m 5% 24904.00 26149.00

20th m 5% 26149.00 27456.00

Total Cost from 10m upto 20m 212014.00 222614.00

Avg Rate per metre 21201.00 22261.00

12.16 B (iv) Beyond 20m upto 30 m

a

b Add 5 per cent of cost for dewatering on the cost, if required

c

31st m 7.5% 28110.00 35138.00 36895.00

32nd 7.5% 30218.00 37773.00 39662.00

33rd m 7.5% 32484.00 40605.00 42635.00

34th m 7.5% 34920.00 43650.00 45833.00

35th m 7.5% 37539.00 46924.00 49270.00

36th m 7.5% 40354.00 50443.00 52965.00

37th m 7.5% 43381.00 54226.00 56937.00

38th m 7.5% 46635.00 58294.00 61209.00

39th m 7.5% 50133.00 62666.00 65799.00

40th m 7.5% 53893.00 67366.00 70734.00

Total Cost from 30m upto 40m 397667.00 497085.00 521939.00

Avg Rate per metre 39767.00 49709.00 52194.00

12.16 B (v) Beyond 30m upto 40 m

a

b Add 5 per cent of cost for dewatering, if required

c

31st m 10% 59282.00 71138.00 74695.00

32nd 10% 65210.00 78252.00 82165.00

33rd m 10% 71731.00 86077.00 90380.85

34th m 10% 78904.00 94685.00 99419.25

35th m 10% 86794.00 104153.00 109360.65

36th m 10% 95473.00 114568.00 120296.40

37th m 10% 105020.00 126024.00 132325.20

38th m 10% 115522.00 138626.00 145557.30

39th m 10% 127074.00 152489.00 160113.45

Add 5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Including for dewatering @ 5% of cost, if

required

Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 25 per cent of cost for Kentledge including supports, loading arrangement and Labour ).

Including 25% for Kentledge

Including 5% for

dewatering, if required

Add 10 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports, loading arrangement and Labour).

Including 20% for Kentledge

Including 5% for

dewatering, if required

Page 204: Standard Data Book - Rate Analysis

Page 49 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

40th m 10% 139781.00 167737.00 176123.85

Total Cost from 30m upto 40m 944791.00 1133749.00 1190436.95

Avg Rate per metre 94479.00 113375.00 119044.00

12.16 C Soft Rock (10m dia well )

Unit = Running Meter.

Taking output = 1 m

Depth in soft rock strata upto 3m

Rate of sinking 0.14m/hour.

a) Labour

Mate day 0.86 151.44 130.24 L-12

Sinker ( skilled ) day 4.00 164.69 658.76 L-15

Sinking helper ( semi-skilled ) day 16.00 230.00 3680.00 L-14

Diver day 1.40 264.50 370.30 L-07

b) Machinery

hour 7.00 1073.50 7514.50 P&M-075

Air compressor with pneumatic breakers hour 4.25 740.15 3145.64 P&M-063

Consumables in sinking @ 10 per cent of (b) 1066.01

Add for dewatering @ 5 per cent of cost, if required 586.31

c) Overhead charges @ 0.2 on (a+b) 3430.35

d) Contractor's profit @ 0.1 on (a+b+c) 2058.21

Rate per metre = (a+b+c+d) 22640.32

say 22640.00

12.16 D Hard Rock (10m dia well )

Unit = Running Meter.

Taking output = 1 m

Depth in hard rock strata upto 3 m

Rate of sinking 0.12 m/ hour.

a) Material

Gelatine 80 per cent Kg 11.00 146.00 1606.00 M-104

Electric Detonators each. 44.00 14.56 640.64 M-094/100

b) Labour

Mate day 1.27 151.44 192.33 L-12

Driller day 2.00 264.50 529.00 L-06

Blaster day 0.25 264.50 66.13 L-03

Mazdoor day 24.00 136.69 3280.56 L-13

Mazdoor (Skilled) day 4.00 164.69 658.76 L-15

c) Machinery

hour 8.50 1073.50 9124.75 P&M-075

hour 3.00 740.15 2220.45 P&M-063

Dewatering @ 5 per cent of cost (c), if required. 567.26

1663.92

d) Overhead charges @ 0.2 on (a+b+c) 4109.96

e) Contractor's profit @ 0.1 on (a+b+c+d) 2465.98

Rate per metre = (a+b+c+d+e) 27125.73

say 27126.00

12.17 1200

Unit = Running Meter

Taking output = 0.50 m

Diameter of well - 11 m.

A Sandy Soil

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Hire & running charges of compressor with pneumatic breaker/Jack hammer or drill

Consumables in sinking @ 10 per cent of cost of (b+c).

Sinking of 11 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is reckoned from bed level.

Page 205: Standard Data Book - Rate Analysis

Page 50 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

(i) Depth from bed level upto 3.0 M

Rate of sinking @ 0.15 m/hour

a) Labour

Mate day 0.21 151.44 31.80 L-12

Sinker ( skilled ) day 1.50 164.69 247.04 L-15

Sinking helper (semi-skilled) day 3.30 230.00 759.00 L-14

b) Machinery

hour 6.00 1073.50 6441.00 P&M-075

Consumables in sinking @10 per cent of (b) 644.10

d) Overhead charges @ 0.2 on (a+b+c) 1624.59

e) Contractor's profit @ 0.1 on (a+b+c+d) 974.75

Cost for 0.5m = a+b+c+d 10722.28

Rate per metre = (a+b+c+d)/0.50 21444.55

say 21445.00

12.17 A (ii) Beyond 3m upto 10m depth

Rate of sinking @ 0.13 m/hour

a) Labour

Mate day 0.32 151.44 48.46 L-12

Sinker day 2.00 164.69 329.38 L-15

Sinking helper (semi-skilled) day 4.50 230.00 1035.00 L-14

b) Machinery

hour 4.00 1073.50 4294.00 P&M-075

Consumables in sinking @10 per cent of (b) 429.40

c) Overhead charges @ 0.2 on (a+b+c) 1227.25

d) Contractor's profit @ 0.1 on (a+b+c+d) 736.35

Cost for 0.5m = a+b+c+d 8099.84

Rate per metre = (a+b+c+d)/0.50 16199.68

say 16200.00

12.17 A (iii) Beyond 10m upto 20m

a

11th m 5% 17010.00

12th m 5% 17861.00

13th m 5% 18754.00

14th m 5% 19692.00

15th m 5% 20677.00

16th m 5% 21711.00

17th m 5% 22797.00

18th m 5% 23937.00

19th m 5% 25134.00

20th m 5% 26391.00

Total Cost from 10m upto 20m 213964.00

Avg Rate per metre 21396.00

12.17 A (iv) Beyond 20m upto 30 m

a

b

21st m 7.5% 28370.00 34044.00

22nd m 7.5% 30498.00 36598.00

23rd m 7.5% 32785.00 39342.00

24th m 7.5% 35244.00 42293.00

25th m 7.5% 37887.00 45464.00

26th m 7.5% 40729.00 48875.00

27th m 7.5% 43784.00 52541.00

28th m 7.5% 47068.00 56482.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Add 5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports, loading arrangement and Labour.

Including 20% for Kentledge

Page 206: Standard Data Book - Rate Analysis

Page 51 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

29th m 7.5% 50598.00 60718.00

30th m 7.5% 54393.00 65272.00

Total Cost from 20m upto 30m 401356.00 481629.00

Avg Rate per metre 40136.00 48163.00

12.17 A (v) Beyond 30m upto 40 m

a

b

31st m 10% 59832.00 71798.00

32nd 10% 65815.00 78978.00

33rd m 10% 72397.00 86876.00

34th m 10% 79637.00 95564.00

35th m 10% 87601.00 105121.00

36th m 10% 96361.00 115633.00

37th m 10% 105997.00 127196.00

38th m 10% 116597.00 139916.00

39th m 10% 128257.00 153908.00

40th m 10% 141083.00 169300.00

Total Cost from 30m upto 40m 953577.00 1144290.00

Avg Rate per metre 95358.00 114429.00

12.17 B Clayey Soil (11 m dia. Well )

Unit = Running Meter

Taking output = 0.50 meter

(i) Depth from bed level upto 3.0 M

Rate of sinking @ 0.10 m/hour

a) Labour

Mate day 0.26 151.44 39.37 L-12

Sinker ( skilled ) day 2.50 164.69 411.73 L-15

Sinking helper (semi-skilled) day 4.00 230.00 920.00 L-14

b) Machinery

hour 5.00 1073.50 5367.50 P&M-075

Consumables in sinking @ 10 per cent of (b) 536.75

c) Overhead charges @ 0.2 on (a+b) 1455.07

d) Contractor's profit @ 0.1 on (a+b+c) 873.04

Cost for 0.5m = a+b+c+d 9603.46

Rate per metre = (a+b+c+d)/0.50 19206.92

say 19207.00

12.17 B (ii) Beyond 3m upto 10m depth

Rate of sinking @ 0.08 m/hour

a) Labour

Mate day 0.43 151.44 65.12 L-12

Sinker day 3.50 164.69 576.42 L-15

Sinking helper (semi-skilled) day 5.75 230.00 1322.50 L-14

b) Machinery

hour 6.00 1073.50 6441.00 P&M-075

hour 4.25 740.15 3145.64 P&M-063

Consumables in sinking @ 10 per cent of (b) 958.66

c) Overhead charges @ 0.2 on (a+b) 2501.87

d) Contractor's profit @ 0.1 on (a+b+c) 1501.12

Cost for 0.5m = a+b+c+d 16512.32

Rate per metre = (a+b+c+d)/0.50 33024.65

say 33025.00

12.17 B (iii) Beyond 10 m upto 20 m

a

Add 10 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports, loading arrangement, and Labour etc.

Including 20% for Kentledge

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Air compressor with pneumatic chisel attachment for cutting hard clay

Add 5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Page 207: Standard Data Book - Rate Analysis

Page 52 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

b Add for dewatering @ 5 per cent of cost, if required.

11th m 5% 34676.00 36410.00

12th m 5% 36410.00 38231.00

13th m 5% 38231.00 40143.00

14th m 5% 40143.00 42150.00

15th m 5% 42150.00 44258.00

16th m 5% 44258.00 46471.00

17th m 5% 46471.00 48795.00

18th m 5% 48795.00 51235.00

19th m 5% 51235.00 53797.00

20th m 5% 53797.00 56487.00

Total Cost from 10m upto 20m 436166.00 457974.00

Avg Rate per metre 43617.00 45797.00

12.17 B (iv) Beyond 20m upto 30 m

a

b Add 5 per cent of cost for dewatering on the cost, if required

c

31st m 7.5% 57832.00 72290.00 75905.00

32nd 7.5% 62169.00 77711.00 81597.00

33rd m 7.5% 66832.00 83540.00 87717.00

34th m 7.5% 71844.00 89805.00 94295.00

35th m 7.5% 77232.00 96540.00 101367.00

36th m 7.5% 83024.00 103780.00 108969.00

37th m 7.5% 89251.00 111564.00 117142.00

38th m 7.5% 95945.00 119931.00 125928.00

39th m 7.5% 103141.00 128926.00 135372.00

40th m 7.5% 110877.00 138596.00 145526.00

Total Cost from 30m upto 40m 818147.00 1022683.00 1073817.00

Avg Rate per metre 81815.00 102268.00 107382.00

12.17 B (v) Beyond 30m upto 40 m

a

b Add 5 per cent of cost for dewatering, if required

c

31st m 10% 121965.00 146358.00 153676.00

32nd 10% 134162.00 160994.00 169044.00

33rd m 10% 147578.00 177094.00 185949.00

34th m 10% 162336.00 194803.00 204543.00

35th m 10% 178570.00 214284.00 224998.00

36th m 10% 196427.00 235712.00 247498.00

37th m 10% 216070.00 259284.00 272248.00

38th m 10% 237677.00 285212.00 299473.00

39th m 10% 261445.00 313734.00 329421.00

40th m 10% 287590.00 345108.00 362363.00

Total Cost from 30m upto 40m 1943820 2332583 2449213

Avg Rate per metre 194382.00 233258.00 244921.00

12.17 C Soft Rock (11m dia well )

Unit = Running Meter.

Taking output = 0.50 m

Including for dewatering @ 5% of cost, if

required

Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 25 per cent of cost for Kentledge including supports, loading arrangement and Labour ).

Including 25% for Kentledge

Including 5% for

dewatering, if required

Add 10 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports, loading arrangement and Labour).

Including 20% for Kentledge

Including 5% for

dewatering, if required

Page 208: Standard Data Book - Rate Analysis

Page 53 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Depth in soft rock strata upto 3m

Rate of sinking @ 0.06 m/hour

a) Labour

Mate day 0.95 151.44 143.87 L-12

Sinker ( skilled ) day 4.25 164.69 699.93 L-15

Sinking helper (semi-skilled) day 18.00 230.00 4140.00 L-14

Diver day 1.50 264.50 396.75 L-07

b) Machinery

hour 8.00 1073.50 8588.00 P&M-075

Air compressor with pneumatic breakers hour 4.50 740.15 3330.67 P&M-063

Consumables in sinking @ 10 per cent of (b) 1191.87

Add for dewatering @ 5 per cent of cost, if required 655.53

c) Overhead charges @ 0.2 on (a+b) 3829.32

d) Contractor's profit @ 0.1 on (a+b+c) 2297.59

Cost for 0.5m = a+b+c+d 25273.54

Rate per metre = (a+b+c+d)/0.50 50547.08

say 50547.00

12.17 D Hard Rock (11m dia well )

Unit = Running Meter.

Taking output = 0.50 m

Depth in hard rock upto 3 m

Rate of sinking @ 0.05 m/hour

a) Material

Gelatine 80 per cent Kg 12.00 146.00 1752.00 M-104

Electric Detonators each. 48.00 14.56 698.88 M-094/100

b) Labour

Mate day 1.35 151.44 204.44 L-12

Driller day 2.00 264.50 529.00 L-06

Blaster day 0.25 264.50 66.13 L-03

Mazdoor day 26.00 136.69 3553.94 L-13

Mazdoor (Skilled) day 4.00 164.69 658.76 L-15

c) Machinery

hour 10.00 1073.50 10735.00 P&M-075

hour 3.50 740.15 2590.53 P&M-063

Dewatering @ 5 per cent of cost (c), if required. 666.28

1833.78

d) Overhead charges @ 0.2 on (a+b+c) 4657.75

e) Contractor's profit @ 0.1 on (a+b+c+d) 2794.65

Cost for 0.5m = a+b+c+d 30741.12

Rate per metre = (a+b+c+d)/0.50 61482.25

say 61482.00

12.18 1200

Unit = Running Meter

Taking output = 0.25 m

Diameter of well - 12 m.

A Sandy Soil

(i) I) Depth below bed level upto 3.0 M

Rate of sinking @ 0.05 m/hour

a) Labour

Mate day 0.22 151.44 33.32 L-12

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Hire & running charges of compressor with pneumatic breaker/Jack hammer or drill

Consumables in sinking @ 10 per cent of cost of (b+c).

Sinking of 12 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is reckoned from bed level.

Page 209: Standard Data Book - Rate Analysis

Page 54 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Sinker ( skilled ) day 1.75 164.69 288.21 L-15

Sinking helper (semi-skilled) day 4.00 230.00 920.00 L-14

b) Machinery

hour 6.00 1073.50 6441.00 P&M-075

Consumables in sinking @10 per cent of (b) 644.10

c) Overhead charges @ 0.2 on (a+b) 1665.32

d) Contractor's profit @ 0.1 on (a+b+c) 999.19

Cost for 0.25m = a+b+c+d 10991.14

Rate per metre = (a+b+c+d)/0.25 43964.58

say 43965.00

12.18 A (ii) Beyond 3m upto 10m depth

Rate of sinking @ 0.038 m/hour

a) Labour

Mate day 0.37 151.44 56.03 L-12

Sinker day 2.50 164.69 411.73 L-15

Sinking helper (semi-skilled) day 4.75 230.00 1092.50 L-14

b) Machinery

hour 6.50 1073.50 6977.75 P&M-075

Consumables in sinking @10 per cent of (b) 697.78

c) Overhead charges @ 0.2 on (a+b) 1847.16

d) Contractor's profit @ 0.1 on (a+b+c) 1108.29

Cost for 0.25m = a+b+c+d 12191.23

Rate per metre = (a+b+c+d)/0.25 48764.93

say 48765.00

12.18 A (iii) Beyond 10m upto 20m

a

11th m 5% 51203.00

12th m 5% 53763.00

13th m 5% 56451.15

14th m 5% 59273.71

15th m 5% 62237.39

16th m 5% 65349.26

17th m 5% 68616.73

18th m 5% 72047.56

19th m 5% 75649.94

20th m 5% 79432.44

Total Cost from 10m upto 20m 644024.18

Avg Rate per metre 64402.00

12.18 A (iv) Beyond 20m upto 30 m

a

b

21st m 7.5% 85390.00 102468.00

22nd m 7.5% 91794.00 110153.00

23rd m 7.5% 98679.00 118415.00

24th m 7.5% 106080.00 127296.00

25th m 7.5% 114036.00 136843.00

26th m 7.5% 122589.00 147107.00

27th m 7.5% 131783.00 158140.00

28th m 7.5% 141667.00 170000.00

29th m 7.5% 152292.00 182750.00

30th m 7.5% 163714.00 196457.00

Total Cost from 20m upto 30m 1208024.00 1449629.00

Avg Rate per metre 120802.00 144963.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Add 5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports, loading arrangement and Labour.

Including 20% for Kentledge

Page 210: Standard Data Book - Rate Analysis

Page 55 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

12.18 A (v) Beyond 30m upto 40 m

a

b

31st m 10% 180085.00 216102.00

32nd 10% 198094.00 237713.00

33rd m 10% 217903.00 261484.00

34th m 10% 239693.00 287632.00

35th m 10% 263662.00 316394.00

36th m 10% 290028.00 348034.00

37th m 10% 319031.00 382837.00

38th m 10% 350934.00 421121.00

39th m 10% 386027.00 463232.00

40th m 10% 424630.00 509556.00

Total Cost from 30m upto 40m 2870087 3444105

Avg Rate per metre 287009.00 344411.00

12.18 B Clayey Soil (12 m dia. Well )

Unit = Running Meter.

Taking output = 0.25 meter.

(i) Depth below bed level upto 3.0 M

Rate of sinking @ 0.04 m/hour

a) Labour

Mate day 0.30 151.44 45.43 L-12

Sinker ( skilled ) day 3.00 164.69 494.07 L-15

Sinking helper (semi-skilled) day 4.50 230.00 1035.00 L-14

b) Machinery

hour 6.25 1073.50 6709.38 P&M-075

Consumables in sinking @ 10 per cent of (b) 670.94

c) Overhead charges @ 0.2 on (a+b) 1790.96

d) Contractor's profit @ 0.1 on (a+b+c) 1074.58

Cost for 0.25m = a+b+c+d 11820.36

Rate per metre = (a+b+c+d)/0.25 47281.42

say 47281.00

12.18 B (ii) Beyond 3m upto 10m depth

Rate of sinking @ 0.03 m/hour

a) Labour

Mate day 0.48 151.44 72.69 L-12

Sinker day 3.75 164.69 617.59 L-15

Sinking helper (semi-skilled) day 6.00 230.00 1380.00 L-14

b) Machinery

hour 8.33 1073.50 8942.26 P&M-075

hour 4.50 740.15 3330.67 P&M-063

Consumables in sinking @ 10 per cent of (b) 1227.29

c) Overhead charges @ 0.2 on (a+b) 3114.10

d) Contractor's profit @ 0.1 on (a+b+c) 1868.46

Cost for 0.25m = a+b+c+d 20553.06

Rate per metre = (a+b+c+d)/0.25 82212.25

say 82212.00

12.18 B (iii) Beyond 10 m upto 20 m

a

b Add for dewatering @ 5 per cent of cost, if required.

Add 10 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports, loading arrangement, and Labour etc.

Including 20% for Kentledge

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Air compressor with pneumatic chisel attachment for cutting hard clay.

Add 5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Including for dewatering @ 5% of cost, if

required

Page 211: Standard Data Book - Rate Analysis

Page 56 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

11th m 5% 86323.00 90639.00

12th m 5% 90639.00 95171.00

13th m 5% 95171.00 99930.00

14th m 5% 99930.00 104927.00

15th m 5% 104927.00 110173.00

16th m 5% 110173.00 115682.00

17th m 5% 115682.00 121466.00

18th m 5% 121466.00 127539.00

19th m 5% 127539.00 133916.00

20th m 5% 133916.00 140612.00

Total Cost from 10m upto 20m 1085766.00 1140055.00

Avg Rate per metre 108577.00 114006.00

12.18 B (iv) Beyond 20m upto 30 m

a

b Add 5 per cent of cost for dewatering on the cost, if required

c

31st m 7.5% 143960.00 179950.00 188948.00

32nd 7.5% 154757.00 193446.00 203118.00

33rd m 7.5% 166364.00 207955.00 218353.00

34th m 7.5% 178841.00 223551.00 234729.00

35th m 7.5% 192254.00 240318.00 252334.00

36th m 7.5% 206673.00 258341.00 271258.00

37th m 7.5% 222173.00 277716.00 291602.00

38th m 7.5% 238836.00 298545.00 313472.00

39th m 7.5% 256749.00 320936.00 336983.00

40th m 7.5% 276005.00 345006.00 362256.00

Total Cost from 30m upto 40m 2036612 2545764 2673053

Avg Rate per metre 203661.00 254576.00 267305.00

12.18 B (v) Beyond 30m upto 40 m

a

b Add 5 per cent of cost for dewatering, if required

c

31st m 10% 303606.00 364327.00 382543.00

32nd 10% 333967.00 400760.00 420798.00

33rd m 10% 367364.00 440837.00 462879.00

34th m 10% 404100.00 484920.00 509166.00

35th m 10% 444510.00 533412.00 560083.00

36th m 10% 488961.00 586753.00 616091.00

37th m 10% 537857.00 645428.00 677699.00

38th m 10% 591643.00 709972.00 745471.00

39th m 10% 650807.00 780968.00 820016.00

40th m 10% 715888.00 859066.00 902019.00

Total Cost from 30m upto 40m 4838703 5806443 6096765

Avg Rate per metre 483870.00 580644.00 609677.00

12.18 C Soft Rock (12m dia well )

Unit = Running Meter

Taking output = 0.25 m

Depth in soft rock strata upto 3m

Rate of sinking @ 0.025 m/hour

a) Labour

Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 25 per cent of cost for Kentledge including supports, loading arrangement and Labour ).

Including 25% for Kentledge

Including 5% for

dewatering, if required

Add 10 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports, loading arrangement and Labour).

Including 20% for Kentledge

Including 5% for

dewatering, if required

Page 212: Standard Data Book - Rate Analysis

Page 57 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Mate day 1.06 151.44 160.53 L-12

Sinker ( skilled ) day 4.50 164.69 741.11 L-15

Sinking helper (semi-skilled) day 20.00 230.00 4600.00 L-14

Diver day 1.75 264.50 462.88 L-07

b) Machinery

hour 10.00 1073.50 10735.00 P&M-075

hour 4.75 740.15 3515.71 P&M-063

Consumables in sinking @ 10 per cent of (b) 1425.07

Add for dewatering @ 5 per cent, if required 783.79

c) Overhead charges @ 0.2 on (a+b) 4484.82

d) Contractor's profit @ 0.1 on (a+b+c) 2690.89

Cost for 0.25m = a+b+c+d 29599.78

Rate per metre = (a+b+c+d)/0.25 118399.14

say 118399.00

12.18 D Hard Rock (12m dia well )

Unit = Running Meter

Taking output = 0.25 m

(i) Depth in hard rock strata upto 3 m

Rate of sinking @ 0.020 m/hour

a) Material

Gelatine80 per cent Kg 14.00 146.00 2044.00 M-104

Electric detonator each. 56.00 14.56 815.36 M-094/100

b) Labour

Mate day 1.44 151.44 218.07 L-12

Driller day 2.00 264.50 529.00 L-06

Blaster day 0.25 264.50 66.13 L-03

Mazdoor day 28.00 136.69 3827.32 L-13

Mazdoor (Skilled) day 4.50 164.69 741.11 L-15

c) Machinery

hour 12.50 1073.50 13418.75 P&M-075

hour 4.00 740.15 2960.60 P&M-063

Dewatering @ 5 per cent, if required. 818.97

Consumables in sinking @ 10 per cent of (c). 1719.83

d) Overhead charges @ 0.2 on (a+b+c) 5431.83

e) Contractor's profit @ 0.1 on (a+b+c+d) 3259.10

Cost for 0.25m = a+b+c+d+e 35850.06

Rate per metre = (a+b+c+d+e)/0.25 143400.22

say 143400.00

12.19 1200

Unit = Running Meter

Taking output = 1 m

Dimensions of well.

Overall length = 12 m

Overall width = 6 m

A Sandy Soil

(i) Depth from bed level upto 3.0 M

Rate of sinking @ 0.18 m/hour

a) Labour

Mate day 0.20 151.44 30.29 L-12

Sinker ( skilled ) day 1.25 164.69 205.86 L-15

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Air compressor with pneumatic chisel attachment for cutting hard clay.

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Hire & running charges of compressor with pneumatic breaker/Jack hammer or drill

Sinking of Twin D Type well (other than pneumatic method of sinking) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is reckoned from bed level.

Page 213: Standard Data Book - Rate Analysis

Page 58 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Sinking helper (semi-skilled) day 3.75 230.00 862.50 L-14

b) Machinery

hour 5.50 1073.50 5904.25 P&M-075

Consumables in sinking @10 per cent of (b) 590.43

c) Overhead charges @ 0.2 on (a+b) 1518.67

d) Contractor's profit @ 0.1 on (a+b+c) 911.20

Rate per metre = (a+b+c+d) 10023.19

say 10023.00

12.19 A (ii) Beyond 3m upto 10m depth

Rate of sinking @ 0.17 m/hour

a) Labour

Mate day 0.30 151.44 45.43 L-12

Sinker day 1.50 164.69 247.04 L-15

Sinking helper (semi-skilled) day 4.00 230.00 920.00 L-14

b) Machinery

hour 5.88 1073.50 6312.18 P&M-075

Consumables in sinking @10 per cent of (b) 631.22

c) Overhead charges @ 0.2 on (a+b) 1631.17

d) Contractor's profit @ 0.1 on (a+b+c) 978.70

Rate per metre = (a+b+c+d) 10765.74

say 10766.00

12.19 A (iii) Beyond 10m upto 20m

a

11th m 5% 11304.00

12th m 5% 11869.00

13th m 5% 12462.00

14th m 5% 13085.00

15th m 5% 13739.00

16th m 5% 14426.00

17th m 5% 15147.00

18th m 5% 15904.00

19th m 5% 16699.00

20th m 5% 17534.00

Total Cost from 10m upto 20m 142169.00

Avg Rate per metre 14217.00

12.19 A (iv) Beyond 20m upto 30 m

a

b

21st m 7.5% 18849.00 22619.00

22nd m 7.5% 20263.00 24316.00

23rd m 7.5% 21783.00 26140.00

24th m 7.5% 23417.00 28100.00

25th m 7.5% 25173.00 30208.00

26th m 7.5% 27061.00 32473.00

27th m 7.5% 29091.00 34909.00

28th m 7.5% 31273.00 37528.00

29th m 7.5% 33618.00 40342.00

30th m 7.5% 36139.00 43367.00

Total Cost from 20m upto 30m 266667.00 320002.00

Avg Rate per metre 26667.00 32000.00

12.19 A (v) Beyond 30m upto 40 m

a

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Add 5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports, loading arrangement and Labour.

Including 20% for Kentledge

Add 10 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Page 214: Standard Data Book - Rate Analysis

Page 59 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

b

31st m 10% 39753.00 47704.00

32nd 10% 43728.00 52474.00

33rd m 10% 48101.00 57721.00

34th m 10% 52911.00 63493.00

35th m 10% 58202.00 69842.00

36th m 10% 64022.00 76826.00

37th m 10% 70424.00 84509.00

38th m 10% 77466.00 92959.00

39th m 10% 85213.00 102256.00

40th m 10% 93734.00 112481.00

Total Cost from 30m upto 40m 633554.00 760265.00

Avg Rate per metre 63355.00 76027.00

12.19 B Clayey Soil (Twin D Type Well )

Unit = Running Meter

Taking output = 1 meter

(i) Depth below bed level upto 3.0 M

Rate of sinking @ 0.16 m/hour

a) Labour

Mate day 0.26 151.44 39.37 L-12

Sinker ( skilled ) day 2.50 164.69 411.73 L-15

Sinking helper (semi-skilled) day 4.00 230.00 920.00 L-14

b) Machinery

hour 6.25 1073.50 6709.38 P&M-075

Consumables in sinking @ 10 per cent of (b) 670.94

c) Overhead charges @ 0.2 on (a+b) 1750.28

d) Contractor's profit @ 0.1 on (a+b+c) 1050.17

Rate per metre = (a+b+c+d) 11551.86

say 11552.00

12.19 B (ii) Beyond 3m upto 10m depth

Rate of sinking @ 0.15 m/hour

a) Labour

Mate day 0.45 151.44 68.15 L-12

Sinker day 3.25 164.69 535.24 L-15

Sinking helper (semi-skilled) day 6.00 230.00 1380.00 L-14

b) Machinery

hour 6.67 1073.50 7160.25 P&M-075

hour 4.50 740.15 3330.67 P&M-063

Consumables in sinking @ 10 per cent of (b) 1049.09

c) Overhead charges @ 0.2 on (a+b) 2704.68

d) Contractor's profit @ 0.1 on (a+b+c) 1622.81

Rate per metre = (a+b+c+d) 17850.89

say 17851.00

12.19 B (iii) Beyond 10 m upto 20 m

a

b Add for dewatering @ 5 per cent of cost, if required.

11th m 5% 18743.00 19680.00

12th m 5% 19680.00 20664.00

13th m 5% 20664.00 21697.00

14th m 5% 21697.00 22782.00

15th m 5% 22782.00 23921.00

Add 20 per cent of cost for Kentledge including supports, loading arrangement, and Labour etc.

Including 20% for Kentledge

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Air compressor with pneumatic chisel attachment for cutting hard clay.

Add 5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Including for dewatering @ 5% of cost, if

required

Page 215: Standard Data Book - Rate Analysis

Page 60 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

16th m 5% 23921.00 25117.00

17th m 5% 25117.00 26373.00

18th m 5% 26373.00 27692.00

19th m 5% 27692.00 29077.00

20th m 5% 29077.00 30531.00

Total Cost from 10m upto 20m 235746.00 247534.00

Avg Rate per metre 23575.00 24753.00

12.19 B (iv) Beyond 20m upto 30 m

a

b Add 5 per cent of cost for dewatering on the cost, if required

c

31st m 7.5% 31258.00 39073.00 41027.00

32nd 7.5% 33602.00 42003.00 44103.00

33rd m 7.5% 36122.00 45153.00 47411.00

34th m 7.5% 38831.00 48539.00 50966.00

35th m 7.5% 41743.00 52179.00 54788.00

36th m 7.5% 44874.00 56093.00 58898.00

37th m 7.5% 48240.00 60300.00 63315.00

38th m 7.5% 51858.00 64823.00 68064.00

39th m 7.5% 55747.00 69684.00 73168.00

40th m 7.5% 59928.00 74910.00 78656.00

Total Cost from 30m upto 40m 442203.00 552757.00 580396.00

Avg Rate per metre 44220.00 55276.00 58040.00

12.19 B (v) Beyond 30m upto 40 m

a

b Add 5 per cent of cost for dewatering, if required

c

31st m 10% 65921.00 79105.00 83060.00

32nd 10% 72513.00 87016.00 91367.00

33rd m 10% 79764.00 95717.00 100503.00

34th m 10% 87740.00 105288.00 110552.00

35th m 10% 96514.00 115817.00 121608.00

36th m 10% 106165.00 127398.00 133768.00

37th m 10% 116782.00 140138.00 147145.00

38th m 10% 128460.00 154152.00 161860.00

39th m 10% 141306.00 169567.00 178045.00

40th m 10% 155437.00 186524.00 195850.00

Total Cost from 30m upto 40m 1050602.00 1260722.00 1323758.00

Avg Rate per metre 105060.00 126072.00 132376.00

12.19 C Soft Rock (Twin D Type Well )

Unit = Running Meter

Taking output = 1 m

Depth in soft rock strata upto 3m

Rate of sinking @ 0.12 m/hour

a) Labour

Mate day 0.86 151.44 130.24 L-12

Sinker ( skilled ) day 4.50 164.69 741.11 L-15

Sinking helper (semi-skilled) day 15.00 230.00 3450.00 L-14

Diver day 1.50 264.50 396.75 L-07

b) Machinery

Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 25 per cent of cost for Kentledge including supports, loading arrangement and Labour ).

Including 25% for Kentledge

Including 5% for

dewatering, if required

Add 10 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports, loading arrangement and Labour).

Including 20% for Kentledge

Including 5% for

dewatering, if required

Page 216: Standard Data Book - Rate Analysis

Page 61 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

hour 8.33 1073.50 8942.26 P&M-075

Air compressor with pneumatic breakers hour 6.00 740.15 4440.90 P&M-063

Consumables in sinking @ 10 per cent of (b) 1338.32

Add for dewatering @ 5 per cent, if required 736.07

c) Overhead charges @ 0.2 on (a+b) 4035.13

d) Contractor's profit @ 0.1 on (a+b+c) 2421.08

Rate per metre = (a+b+c+d) 26631.84

say 26632.00

12.19 D Hard Rock (Twin D Type Well )

Unit = Running Meter

Taking output = 1 m

Depth in hard rock strata upto 3 m

Rate of sinking @ 0.10 m/hour

a) Material

Geletine80 per cent Kg 10.00 146.00 1460.00 M-104

Electric detonators each. 40.00 14.56 582.40 M-094/100

b) Labour

Mate day 1.34 151.44 202.93 L-12

Driller day 2.00 264.50 529.00 L-06

Blaster day 0.25 264.50 66.13 L-03

Mazdoor day 25.00 136.69 3417.25 L-13

Mazdoor (Skilled) day 4.25 164.69 699.93 L-15

c) Machinery

hour 10.00 1073.50 10735.00 P&M-075

hour 3.00 740.15 2220.45 P&M-063

Dewatering @ 5 per cent of cost of (b+c), if required. 893.53

Consumables in sinking @ 10 per cent of (b). 1384.90

d) Overhead charges @ 0.2 on (a+b+c) 4438.30

e) Contractor's profit @ 0.1 on (a+b+c+d) 2662.98

Rate per metre = (a+b+c+d+e) 29292.81

say 29293.00

12.20 1200

Unit - 1 cum

Taking output = 5 cum

a) Material

Cum 8.00 5217.00 41736.00

HYSD bar reinforcement in corbel tonne 0.48 45000.00 21600.00 M-082

Blasting material

Gelatine 80 per cent Kg 1.50 146.00 219.00 M-104

Electric detonators each 6.00 14.56 87.36 M-094/100

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Hire & running charges of compressor with pneumatic breaker/Jack hammer or drill

Pneumatic sinking of wells with equipment of approved design, drawing and specifications worked by competent and trained personnel and comprising of compression and decompression chambers, reducers, two air locks separately for men and plant & materials, arrangement for supply of fresh air to working chambers, check valves, exhaust valves, shafts made from steel plates of riveted construction not less than 6 mm thick to withstand an air pressure of 0.50 MPa, controlled blasting of hard rock where required, staircases and 1 m wide landing plateforms with railing, arrangement for compression and decompression, electric lighting of 50 V maximum, proper rooms for rest and medical examinations and compliance with safety precautions as per IS:4138, all as per clause1207.6 of MoRTH Specifications.

M35 grade RCC corbel provided for supporting of equipment (Dimensions as per ground conditions). Rate may be adopted vide Item 12.8 (H)

Item 12.8 (H)

Page 217: Standard Data Book - Rate Analysis

Page 62 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

b) Labour

Medical Officer day 0.50 304.20 152.10 L-16

Para medical personnel day 1.00 264.50 264.50 L-19

Mate day 1.86 151.44 281.68 L-12

Driller day 1.00 264.50 264.50 L-06

Blaster day 0.50 264.50 132.25 L-03

day 30.00 136.69 4100.70 L-13

day 10.00 164.69 1646.90 L-15

Diver day 4.00 264.50 1058.00 L-07

c) Machinery

hour 6.00 1000.00 6000.00 P&M-082

Induction and deinduction L.S 100000.00

Erection at site and commissioning L.S 150000.00

hour 6.00 4170.00 25020.00 P&M-038

Air compressor 250 cfm, 2 nos. hour 2 x 6 319.00 3828.00 P&M-001

hour 6.00 349.59 2097.56 P&M-072

Motorised barge of 20 tonne capacity hour 6.00 100.00 600.00 P&M-066

Boat to carry atleast 20 persons hour 6.00 100.00 600.00 P&M-066

Electric generating set 33 KVA hour 6.00 406.80 2440.80 P&M-079

Tipper 10 tonne capacity hour 6.00 339.00 2034.00 P&M-048

d) Overhead charges @ 0.2 on (a+b+c) 64485.47

e) Contractor's profit @ 0.1 on (a+b+c+d) 38691.28

Cost for 5 cum = a+b+c+d+e (see notes below)

Rate per cum = (a+b+c+d+e)/5

Note

7.Depth of sinking shall be restricted to 30 m.

12.21 1207

Unit = 1 cum

Taking output = 1 cum

a) Material

Sand (assuming 20 per cent voids ) cum 1.20 476.80 572.16 M-006

b) Labour

Mate day 0.01 151.44 1.51 L-12

Mazdoor day 0.30 136.69 41.01 L-13

c) Overhead charges @ 0.2 on (a+b) 122.94

Mazdoor (for cutting, blasting, cleaning, removal of Material etc.)

Mazdoor (Skilled) (for fixation and removal of adopter for air lock, carrying out mechanical and electrical operations and repairs and other skilled jobs.)

(i) Induction, deinduction and erection of plant and equipment including all components and accessories for pneumatic method of well sinking.

Usage of plant and equipment for pneumatic method of well sinking

Hire and running charges of crane of 15 tonne capacity

1.The cost of induction, deinduction and erection of equipment shall be divided by the total quantity of pneumatic sinking for all the wells of a particular bridge to arrive at the per cum rate on account of this item.

2.Cost of pneumatic sinking per cum of individual wells will be added to the cost indicated at (1) above to arrive at the final rate of pneumatic sinking per cum.

3.The cost of induction and deinduction will depend upon the distance involved for shifting of equipment which may be assessed in individual cases as per actual ground conditions at the time of making of cost estimates.

4.In case pneumatic sinking is involved on a dry bed, the provision of barge and boat may be omitted.

5.The necessity and dimensions of the corbel will be as per actual ground conditions.

6.Small equipments like welding sets, pumps, vibrators, pneumatic tools, portable lamps, fire extinguishers, hose pipes etc., have not been included as the same are covered as items of minor T&P under overhead charges.

Sand Filling in Wells complete as per Drawing and Technical Specifications.

Page 218: Standard Data Book - Rate Analysis

Page 63 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

d) Contractor's profit @ 0.1 on (a+b+c) 73.76

Rate per cum (a+b+c+d) 811.38

say 811.00

12.22

Unit = 1 MT

Taking output = 1 MT

a) Material

i) Structural steel including 5 per cent wastage tonne 1.05 45000.00 47250.00 M-179

b) Labour

Mate day 1.24 151.44 187.79 L-12

Fitter day 6.00 230.00 1380.00 L-08

Blacksmith day 5.00 230.00 1150.00 L-01

Welder day 5.00 264.50 1322.50 L-02

Mazdoor day 10.00 136.69 1366.90 L-13

2362.50

c) Overhead charges @ 0.2 on (a+b) 11003.94

d) Contractor's profit @ 0.1 on (a+b+c) 6602.36

Rate for per MT (a+b+c+d) 72625.98

say 72626.00

12.23

Pile diameter-750 mm

Unit = meter

Taking output = 15 m

a) Materials

PCC Grade M35 cum 6.62 5260.00 34821.20

Concrete to be cast with a tremie pipe 200mm dia.

b) Machinery( for boring and construction )

hour 6.00 5464.00 32784.00 P&M-036

hour 0.50 357.00 178.50 P&M-013

Hire and running charges of Bentonite pump hour 6.00

Loader I cum bucket capacity. hour 0.30 806.00 241.80 P&M-017

hour 0.30 339.00 101.70 P&M-048

Bentonite kg 300.00 4.10 1230.00 M-071

c) Labour

Mate/Supervisor day 0.14 151.44 21.20 L-12

Mazdoor day 3.50 136.69 478.41 L-13

d) Overhead charges @ 0.2 on (b+c) 7007.12

e) Contractor's profit @ 0.1 on (b+c+d) 4204.27

Cost for 15 m = a+b+c+d+d+e 81068.21

Rate per metre (a+b+c+d+e)/15 5404.55

say 5405.00

12.24

Pile diameter-1000 mm

1200 & 1900

Providing Steel Liner 10 mm thick for Curbs and 6 mm thick for Steining of Wells including Fabricating and Setting out as per Detailed Drawing.

Electrodes, cutting gas and other consumables @ 5 per cent on cost a (a) above.

1100 & 1700

Bored cast-in-situ M35 grade R.C.C. Pile excluding Reinforcement complete as per Drawing and Technical Specifications and removal of excavated earth with all lifts and lead upto 1000 m.

Item 12.11 (C) iv

Rate for concrete may be adopted same as for bottom plug vide item no. 12.11( C ) (IV)

Hire and running charges of hydraulic piling rig with power unit and complete accessories including shifting from one bore location to another.

Hire and running charges of light crane for lowering reinforcement cage

Rate included in piling rig

Tipper 5.5 cum capacity for disposal of muck from pile bore hole

1100,16

00 & 1700

Bored cast-in-situ M35 grade R.C.C. Pile excluding Reinforcement complete as per Drawing and Technical Specifications and removal of excavated earth with all lifts and lead upto 1000 m.

Page 219: Standard Data Book - Rate Analysis

Page 64 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Unit = meter

Taking output = 10 m

a) Materials

PCC Grade M35 cum 7.85 5260.00 41291.00

Concrete to be cast with a tremie pipe 200mm dia.

b) Machinery( for boring and construction )

hour 6.00 5464.00 32784.00 P&M-036

hour 0.50 357.00 178.50 P&M-013

Hire and running charges of Bentonite pump hour 6.00

Loader I cum bucket capacity. hour 0.40 806.00 322.40 P&M-017

hour 0.40 339.00 135.60 P&M-048

Bentonite kg 350.00 4.10 1435.00 M-071

c) Labour

Mate/Supervisor day 0.16 151.44 24.23 L-12

Mazdoor day 4.00 136.69 546.76 L-13

d) Overhead charges @ 0.2 on (b+c) 7085.30

e) Contractor's profit @ 0.1 on (b+c+d) 4251.18

Cost for 10 m = a+b+c+d+d+e 88053.97

Rate per metre (a+b+c+d+e)/10 8805.40

say 8805.00

12.25

Pile diameter-1200 mm

Unit = meter

Taking output = 9 m

a) Materials

PCC Grade M35 cum 10.17 5260.00 53494.20

Concrete to be cast with a tremie pipe 200mm dia.

b) Machinery( for boring and construction )

hour 6.00 5464.00 32784.00 P&M-036

hour 0.50 357.00 178.50 P&M-013

Hire and running charges of Bentonite pump hour 6.00

Loader I cum bucket capacity. hour 0.50 806.00 403.00 P&M-017

hour 0.50 339.00 169.50 P&M-048

Bentonite kg 385.00 4.10 1578.50 M-071

c) Labour

Mate/Supervisor day 0.18 151.44 27.26 L-12

Mazdoor day 4.50 136.69 615.11 L-13

d) Overhead charges @ 0.2 on (b+c) 7151.17

e) Contractor's profit @ 0.1 on (b+c+d) 4290.70

Cost for 9 m = a+b+c+d+d+e 100691.94

Rate per metre (a+b+c+d+e)/9 11187.99

say 11188.00

Item 12.11 (C) iv

Rate for concrete may be adopted same as for bottom plug vide item no. 12.11( C ) (IV)

Hire and running charges of hydraulic piling rig with power unit and complete accessories including shifting from one bore location to another.

Hire and running charges of light crane for lowering reinforcement cage

Rate included in piling rig

Tipper 5.5 cum capacity for disposal of muck from pile bore hole

1100 & 1700

Bored cast-in-situ M35 grade R.C.C. Pile excluding Reinforcement complete as per Drawing and Technical Specifications and removal of excavated earth with all lifts and lead upto 1000 m.

Item 12.11 (C) iv

Rate for concrete may be adopted same as for bottom plug vide item no. 12.11( C ) (IV)

Hire and running charges of hydraulic piling rig with power unit and complete accessories including shifting from one bore location to another.

Hire and running charges of light crane for lowering reinforcement cage

Rate included in piling rig

Tipper 5.5 cum capacity for disposal of muck from pile bore hole

Page 220: Standard Data Book - Rate Analysis

Page 65 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

12.26

Pile diameter - 750 mm

Unit = Running meter

Taking output = 40 metre

a) Materials

PCC Grade M35 cum 17.66 5260.00 92891.60

b) Materials Pile shoes

i) C.I. shoes for the pile Kg 160.00 59.60 9536.00 M-080

ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 52.15 3650.50 M-124

Kg 50.00 61.00 3050.00 M-173

c) Machinery

hour 6.00 5974.88 35849.25 P&M-085

hour 0.50 825.00 412.50 P&M-070

d) Labour

Mate/Supervisor day 0.12 151.44 18.17 L-12

Mazdoor day 3.00 136.69 410.07 L-13

e) Overhead charges @ 0.2 on (b+c+d) 10585.30

f) Contractor's profit @ 0.1 on (b+c+d+e) 6351.18

Cost for 40 m = a+b+c+d+e 162754.57

Rate per metre (a+b+c+d+e)/40 4068.86

say 4069.00

Note

12.27

Pile diameter - 1000 mm

Unit = Running meter

Taking output = 30 metre

a) Materials

PCC Grade M35 cum 23.55 5260.00 123873.00

b) Materials Pile shoes

i) C.I. shoes for the pile Kg 160.00 59.60 9536.00 M-080

ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 52.15 3650.50 M-124

Kg 50.00 61.00 3050.00 M-173

c) Machinery

hour 6.00 5974.88 35849.25 P&M-085

hour 0.50 116.53 58.27 P&M-070

1100 & 1700

Driven cast-in-place vertical M35 grade R.C.C. Pile excluding Reinforcement complete as per Drawing and & Technical Specification

Item 12.11 (C) iv

Rate for concrete may be adopted same as for bottom plug vide item no. 12.11( C ) (IV)

iii) Steel helmet and cushion block on top of casing head during driving

Hire and running charges of piling rig Including double acting pile driving hammer complete with power unit and accessories..

Hiring and running charges for light crane 5 tonnes lifting capacity for lowering reinforcement and handling steel casing.

1.The quantity of concrete required to be removed above the designed top level of concrete, if any, will be provided for in the rate analysis.

2.In case steel lining is included in the design for driven cast-in-situ pile and is planned to be retained, the same may be included in the rate analysis. In case the temporary steel casing used during casting is planned to be removed, an additional cost @ 0.50 per cent of cost of concrete may be provided to cover its usage.

1100 & 1700

Driven cast-in-place vertical M35 grade R.C.C. Pile excluding Reinforcement complete as per Drawing and & Technical Specification

Item 12.11 (C) iv

Rate for concrete may be adopted same as for bottom plug vide item no. 12.11( C ) (IV)

iii) Steel helmet and cushion block on top of casing head during driving

Hire and running charges of piling rig Including double acting pile driving hammer complete with power unit and accessories.

Hiring and running charges for light crane 5 tonnes lifting capacity for lowering reinforcement and handling steel casing.

Page 221: Standard Data Book - Rate Analysis

Page 66 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

hour 0.50 357.00 178.50 P&M-013

d) Labour

Mate/Supervisor day 0.16 151.44 24.23 L-12

Mazdoor day 4.00 136.69 546.76 L-13

e) Overhead charges @ 0.2 on (b+c+d) 10578.70

f) Contractor's profit @ 0.1 on (b+c+d+e) 6347.22

Cost for 30 m = a+b+c+d+e 193692.43

Rate per metre (a+b+c+d+e)/30 6456.41

say 6456.00

Note

12.28

Pile diameter - 1200 mm

Unit = Running meter

Taking output = 20 metre

a) Materials

PCC Grade M35 cum 22.61 5260.00 118928.60

b) Materials Pile shoes

i) C.I. shoes for the pile Kg 160.00 59.60 9536.00 M-080

ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 52.15 3650.50 M-124

iii) Steel helmet on top of casing head during driving Kg 50.00 61.00 3050.00 M-173

c) Machinery

hour 6.00 5974.88 35849.25 P&M-085

hour 0.50 116.53 58.27 P&M-070

d) Labour

Mate/Supervisor day 0.18 151.44 27.26 L-12

Mazdoor day 4.50 136.69 615.11 L-13

e) Overhead charges @ 0.2 on (b+c+d) 10557.28

f) Contractor's profit @ 0.1 on (b+c+d+e) 6334.37

Cost for 20 m = a+b+c+d+e 188606.62

Rate per metre (a+b+c+d+e)/20 9430.33

say 9430.00

Note

12.29

Pile Diameter = 500 mm

Unit = Running Meter

Hire and running charges for light crane for lowering reinforcement cage.

1.The quantity of concrete required to be removed above the designed top level of concrete, if any, will be provided for in the rate analysis.

2.In case steel lining is included in the design for driven cast-in-situ pile and is planned to be retained, the same may be included in the rate analysis. In case the temporary steel casing used during casting is planned to be removed, an additional cost @ 0.50 per cent of cost of concrete may be provided to cover its usage.

1100 & 1700

Driven cast-in-place vertical M35 grade R.C.C. Pile excluding Reinforcement complete as per Drawing and & Technical Specification

Item 12.11 (C) iv

Rate for concrete may be adopted same as for bottom plug vide item no. 12.11( C ) (IV)

Hire and running charges of piling rig Including double acting pile driving hammer complete with power unit and accessories.

Hiring and running charges for light crane 5 tonnes lifting capacity for lowering reinforcement and handling steel casing.

1.The quantity of concrete required to be removed above the designed top level of concrete, if any, will be provided for in the rate analysis.

2.In case steel lining is included in the design for driven cast-in-situ pile and is planned to be retained, the same may be included in the rate analysis. In case the temporary steel casing used during casting is planned to be removed, an additional cost @ 0.50 per cent of cost of concrete may be provided to cover its usage.

1100 & 1700

Driven precast vertical M35 grade R.C.C. Piles excluding Reinforcement complete as per Drawing and & Technical Specification

Page 222: Standard Data Book - Rate Analysis

Page 67 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Taking output = 60 m

a) Materials

RCC Grade M35 cum 11.78 5114.00 60242.92

b ) Material Pile shoes

a) C.I Shoes Kg 240.00 59.60 14304.00 M-080

b) M.S. shoes Kg 105.00 37.00 3885.00 M-125

Kg 30.00 61.00 1830.00 M-173

c) Machinery

Crane20 t capacity hour 6.00 466.13 2796.75 P&M-073

hour 6.00 1000.00 6000.00 P&M-092

d) Labour

Mate/Supervisor day 0.12 151.44 18.17 L-12

Mazdoor day 3.00 136.69 410.07 L-13

894.87

e) Overhead charges @ 0.2 on (b+c+d) 6027.77

f) Contractor's profit @ 0.1 on (b+c+d+e) 3616.66

Cost for 60 m = a+b+c+d+e+f 100026.22

Rate per metre (a+b+c+d+e+f)/60 1667.10

say 1667.00

Note

12.30

Pile Diameter = 750 mm

Unit = Running Meter

Taking output = 50 m

a) Materials

RCC Grade M35 cum 22.08 5114.00 112917.12

b ) Material Pile shoes

a) C.I. shoes Kg 160.00 59.60 9536.00 M-080

b) M.S. shoes Kg 70.00 37.00 2590.00 M-125

Kg 40.00 61.00 2440.00 M-173

c) Machinery

Crane 40 T capacity hour 6.00 932.25 5593.50 P&M-074

hour 6.00 1000.00 6000.00 P&M-092

d) Labour

Mate/Supervisor day 0.16 151.44 24.23 L-12

Mazdoor day 4.00 136.69 546.76 L-13

1396.48

e) Overhead charges @ 0.2 on (b+c+d) 5625.39

f) Contractor's profit @ 0.1 on (b+c+d+e) 3375.24

Cost for 50 m = a+b+c+d+e+f 150044.72

Rate per metre (a+b+c+d+e+f)/50 3000.89

say 3001.00

Item 12.11 (F) iv

Rate for concrete may be adopted same as for bottom plug vide item no. 12.11( F ) (IV)

c) Steel helmet and cushion block on top of pile head during driving.

Vibrating Pile driving hammer complete with power unit and accessories.

Add 1 per cent of (a+b+c) for carriage of piles from casting yard to work site and stacking, and other imponderables during installation.

The quantity of concrete required to be removed above the designed top level of concrete, if any, will be provided for in the rate analysis.

1100 & 1700

Driven precast vertical M35 grade R.C.C. Piles excluding Reinforcement complete as per Drawing and & Technical Specification

Item 12.11 (F) iv

Rate for concrete may be adopted same as for bottom plug vide item no. 12.11( F ) (IV)

c) Steel helmet and cushion block on top of pile head during driving.

Vibrating Pile driving hammer complete with power unit and accessories.

Add 1 per cent of (a+b+c) for carriage of piles from casting yard to work site and stacking, and other imponderables during installation.

Page 223: Standard Data Book - Rate Analysis

Page 68 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Note

12.31

Pile Diameter = 1000 mm

Unit = Running Meter

Taking output = 40 m

a) Materials

RCC Grade M35 cum 31.40 5114.00 160579.60

b ) Material Pile shoes

a) C.I. shoes for the pile Kg 160.00 59.60 9536.00 M-080

b) M.S. shoes @ 35 Kg per pile of 15 m Kg 70.00 37.00 2590.00 M-125

Kg 50.00 61.00 3050.00 M-173

c) Machinery

Crane 50 t capacity. hour 6.00 1279.00 7674.00 P&M-011

hour 6.00 1000.00 6000.00 P&M-092

d) Labour

Mate/Supervisor day 0.20 151.44 30.29 L-12

Mazdoor day 5.00 136.69 683.45 L-13

1901.43

e) Overhead charges @ 0.2 on (b+c+d) 6293.03

f) Contractor's profit @ 0.1 on (b+c+d+e) 3775.82

Cost for 40 m = a+b+c+d+e+f 202113.63

Rate per metre (a+b+c+d+e+f)/40 5052.84

say 5053.00

Note

12.32

Size of pile - 300 mm x 300 mm

Unit = Running Meter

Taking output = 60 m

a) Materials

RCC Grade M-35

cum 5.40 5114.00 27615.60

b ) Material Pile shoes

a) C I shoes kg 240.00 59.60 14304.00 M-080

b) M. S shoes kg 105.00 37.00 3885.00 M-125

Kg 30.00 61.00 1830.00 M-173

c) Machinery

Crane 10 tonne capacity hour 6.00 1237.50 7425.00 P&M-071

hour 6.00 1000.00 6000.00 P&M-092

d ) Labour

Mate/Supervisor day 0.12 151.44 18.17 L-12

Mazdoor day 3.00 136.69 410.07 L-13

614.88

The quantity of concrete required to be removed above the designed top level of concrete, if any, will be provided for in the rate analysis.

1100 & 1700

Driven precast vertical M35 grade R.C.C. Piles excluding Reinforcement complete as per Drawing and & Technical Specification

Item 12.11 (F) iv

Rate for concrete may be adopted same as for bottom plug vide item no. 12.11( F ) (IV)

c) Steel helmet and cushion block on top of pile head during driving.

Vibrating Pile driving hammer complete with power unit and accessories.

Add 1 per cent of (a+b+c) for carriage of piles from casting yard to work site and stacking, and other imponderables during installation.

The quantity of concrete required to be removed above the designed top level of concrete, if any, will be provided for in the rate analysis.

1100&1700

Driven precast vertical M35 grade R.C.C. Piles excluding Reinforcement complete as per Drawing and & Technical Specification

Rate for concrete may be adopted same as for bottom plug vide item no. 12.11( F ) (IV)

Item 12.11 (F) iv

c) Steel helmet and cushion block on top of pile head during driving.

Vibrating Pile driving hammer complete with power unit and accessories.

Add 1 per cent of (a+b+c) for carriage of piles from casting yard to work site and stacking, and other imponderables during installation.

Page 224: Standard Data Book - Rate Analysis

Page 69 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

e) Overhead charges @ 0.2 on (b+c+d) 6897.42

f) Contractor's profit @ 0.1 on (b+c+d+e) 4138.45

Cost for 60 m = a+b+c+d+e+f 73138.60

Rate per metre (a+b+c+d+e+f)/60 1218.98

say 1219.00

Note

12.33

Size of pile - 500 mm x 500 mm

Unit = Running Meter

Taking output = 50 m

a) Materials

RCC Grade M-35

cum 12.50 5114.00 63925.00

b ) Material Pile shoes

a) C I shoes kg 160.00 59.60 9536.00 M-080

b) M. S shoes kg 70.00 37.00 2590.00 M-125

Kg 30.00 61.00 1830.00 M-173

c) Machinery

Crane 20 tonne capacity hour 6.00 466.13 2796.75 P&M-073

hour 6.00 1000.00 6000.00 P&M-092

d ) Labour

Mate/Supervisor day 0.16 151.44 24.23 L-12

Mazdoor day 4.00 136.69 546.76 L-13

872.49

e) Overhead charges @ 0.2 on (b+c+d) 4839.25

f) Contractor's profit @ 0.1 on (b+c+d+e) 2903.55

Cost for 50 m = a+b+c+d+e+f 95864.02

Rate per metre (a+b+c+d+e+f)/50 1917.28

say 1917.00

Note

12.34

Size of pile - 750 mm x 750 mm

Unit = Running Meter

Taking output = 40 m

a) Materials

RCC Grade M-35

cum 22.50 5114.00 115065.00

b ) Material

Pile shoes

a) C I shoes kg 160.00 59.60 9536.00 M-080

b) M. S shoes kg 70.00 37.00 2590.00 M-125

Kg 30.00 61.00 1830.00 M-173

c) Machinery

Crane 20 tonne capacity hour 6.00 466.13 2796.75 P&M-073

hour 6.00 1000.00 6000.00 P&M-092

The quantity of concrete required to be removed above the designed top level of concrete, if any, will be provided for in the rate analysis.

1100 &1700

Driven precast vertical M35 grade R.C.C. Piles excluding Reinforcement complete as per Drawing and & Technical Specification

Rate for concrete may be adopted same as for bottom plug vide item no. 12.11( F ) (IV)

Item 12.11 (F) iv

c) Steel helmet and cushion block on top of pile head during driving.

Vibrating Pile driving hammer complete with power unit and accessories.

Add 1 per cent of (a+b+c) for carriage of piles from casting yard to work site and stacking, and other imponderables during installation.

The quantity of concrete required to be removed above the designed top level of concrete, if any, will be provided for in the rate analysis.

1100 &1700

Driven precast vertical M35 grade R.C.C. Piles excluding Reinforcement complete as per Drawing and & Technical Specification

Rate for concrete may be adopted same as for bottom plug vide item no. 13.11( F ) (IV)

Item 12.11 (F) iv

c) Steel helmet and cushion block on top of pile head during driving.

Vibrating Pile driving hammer complete with power unit and accessories.

Page 225: Standard Data Book - Rate Analysis

Page 70 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

d ) Labour

Mate/Supervisor day 0.18 151.44 27.26 L-12

Mazdoor day 4.50 136.69 615.11 L-13

1384.60

e) Overhead charges @ 0.2 on (b+c+d) 4955.94

f) Contractor's profit @ 0.1 on (b+c+d+e) 2973.57

Cost for 40 m = a+b+c+d+e+f 147774.22

Rate per metre (a+b+c+d+e+f)/40 3694.36

say 3694.00

Note

12.35

Unit = Running Meter

Taking output = 70 m

a) Materials

tonnes 6.04 45000.00 271800.00 M-179

b) Machinery

Crane 10 T capacity hour 6.00 233.06 1398.38 P&M-071

hour 6.00 1000.00 6000.00 P&M-092

c) Labour

Mate/Supervisor day 0.12 151.44 18.17 L-12

Mazdoor day 3.00 136.69 410.07 L-13

1398.13

d) Overhead charges @ 0.2 on (a+b+c) 56204.95

e) Contractor's profit @ 0.1 on (a+b+c+d) 33722.97

Cost for 70 m = a+b+c+d+e 370952.67

Rate per metre (a+b+c+d+e)/70 5299.32

say 5299.00

12.36

Unit = Running Meter

Taking output = 60 m

a) Materials

tonnes 5.83 45000.00 262350.00 M-179

b) Machinery

Crane 10 T capacity hour 6.00 233.06 1398.38 P&M-071

hour 6.00 1000.00 6000.00 P&M-092

c) Labour

Mate/Supervisor day 0.14 151.44 21.20 L-12

Mazdoor day 3.50 136.69 478.41 L-13

1351.24

d) Overhead charges @ 0.2 on (a+b+c) 54319.85

e) Contractor's profit @ 0.1 on (a+b+c+d) 32591.91

Add 1 per cent of (a+b+c) for carriage of piles from casting yard to work site and stacking, and other imponderables during installation.

The quantity of concrete required to be removed above the designed top level of concrete, if any, will be provided for in the rate analysis.

1100, 1900

Driven Vertical Steel Piles complete as per Drawing and & Technical Specification

Section of the pile - H Section steel column 400 x 250 mm (ISHB Series)

Structural steel including 5 per cent wastage @ 82.20 kg/m

Vibrating Pile driving hammer complete with power unit and other accessories.

Add 0.5 per cent of (a+b+c) for providing steel helmet on top of pile head during driving, stacking of piles at site, providing anti-corrosion treatment and other imponderables during installation.

1100 &1900

Driven Vertical Steel Piles complete as per Drawing and & Technical Specification

Section of the pile - H Section steel column 450 x 250 mm (ISHB Series)

Structural steel including 5 per cent wastage @92.50 kg/m

Vibrating Pile driving hammer complete with power unit and accessories.

Add 0.5 per cent of (a+b+c) for providing steel helmet and cushion block on top of pile head during driving, stacking of piles at site, providing anti-corrosive treatment and other imponderables during installation.

Page 226: Standard Data Book - Rate Analysis

Page 71 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Cost for 60 m = a+b+c+d+e 358510.99

Rate per metre (a+b+c+d+e)/60 5975.18

say 5975.00

12.37 1100

Unit = 1 MT

Taking output = 1 MT

a) Initial and routine load test tonne 1.00 300.00

b) Lateral load test tonne 1.00 5000.00

Note

12.38

A RCC Grade M20

Unit = cum

Taking output = 15 cum

(i) Using Concrete Mixer

a) Material

Cement tonne 5.12 5000.00 25600.00 M-081

Coarse sand cum 6.75 710.46 4795.61 M-005

20 mm Aggregate cum 8.10 1028.00 8326.80 M-053

10 mm Aggregate cum 5.40 1005.00 5427.00 M-051

b) Labour

Mate day 0.90 151.44 136.30 L-12

Mason day 1.50 230.00 345.00 L-10

Mazdoor for concreting day 20.00 136.69 2733.80 L-13

day 1.00 136.69 136.69 L-13

c) Machinery

Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009

Generator (capacity 33 KVA) hour 6.00 406.80 2440.80 P&M-079

2053.60

d) Overhead charges @ 0.2 on (a+b+c) 10678.72

e) Contractor's profit @ 0.1 on (a+b+c+d) 6407.23

Cost for 15 cum = a+b+c+d+e 70479.54

Rate per metre (a+b+c+d+e)/15 4698.64

say 4699.00

12.38A (ii) Using Batching Plant, Transit Mixer and Concrete Pump

a) Material

Cement tonne 5.12 5000.00 25600.00 M-081

Coarse sand cum 6.75 828.00 5589.00 M-004

20 mm Aggregate cum 8.10 1028.00 8326.80 M-053

10 mm Aggregate cum 5.40 1005.00 5427.00 M-051

b) Labour

Mate day 0.16 151.44 24.23 L-12

Mason day 0.38 230.00 87.40 L-10

Mazdoor for concreting day 2.50 136.69 341.73 L-13

day 1.00 136.69 136.69 L-13

c) Machinery

Batching Plant @ 20 cum/hour hour 0.75 2232.00 1674.00 P&M-002

Generator 100 KVA hour 0.75 762.75 572.06 P&M-080

Loader (capacity 1 cum) hour 0.75 806.00 604.50 P&M-017

Transit Mixer ( capacity 4.0 cu.m )

Lead upto 1 Km hour 2.00 1017.00 2034.00 P&M-049

Pile Load Test on single Vertical Pile in accordance with IS:2911(Part-IV)

Although, this item is incidental to work and is not required to be included in BOQ of contract, the same is required to be added in the estimate to assess cost of work.

1100, 1500

&1700

Cement Concrete for Reinforced Concrete in Pile Cap complete as per Drawing and Technical Specification

Mazdoor for breaking pile head, bending bars, cleaning etc.

Formwork @ 4 per cent on cost of concrete i.e. cost of a) Material, b) Labour and c) Machinery

Mazdoor for breaking pile head, bending bars, cleaning etc.

Page 227: Standard Data Book - Rate Analysis

Page 72 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Lead beyond 1 Km, L - lead in Kilometer tonne.km 37.5L 2.03 76.27

Concrete Pump hour 0.75 256.00 192.00 P&M-007

2027.43

d) Overhead charges @ 0.2 on (a+b+c) 10542.62

e) Contractor's profit @ 0.1 on (a+b+c+d) 6325.57

Cost for 15 cum = a+b+c+d+e 69581.31

Rate per metre (a+b+c+d+e)/15 4638.75

say 4639.00

Note

12.38 B RCC Grade M25

Unit = cum

Taking output = 15 cum

(i) Using Concrete Mixer

a) Material

Cement tonne 5.99 5000.00 29950.00 M-081

Coarse sand cum 6.75 710.46 4795.61 M-005

20 mm Aggregate cum 8.10 1028.00 8326.80 M-053

10 mm Aggregate cum 5.40 1005.00 5427.00 M-051

b) Labour

Mate day 0.90 151.44 136.30 L-12

Mason day 1.50 230.00 345.00 L-10

Mazdoor for concreting day 20.00 136.69 2733.80 L-13

day 1.00 136.69 136.69 L-13

c) Machinery

Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009

Generator (capacity 33 KVA) hour 6.00 406.80 2440.80 P&M-079

2227.60

d) Overhead charges @ 0.2 on (a+b+c) 11583.52

e) Contractor's profit @ 0.1 on (a+b+c+d) 6950.11

Cost for 15 cum = a+b+c+d+e 76451.22

Rate per metre (a+b+c+d+e)/15 5096.75

say 5097.00

12.38B (ii) Using Batching Plant, Transit Mixer and Concrete Pump

a) Material

Cement tonne 5.99 5000.00 29950.00 M-081

Coarse sand cum 6.75 828.00 5589.00 M-004

20 mm Aggregate cum 8.10 1028.00 8326.80 M-053

10 mm Aggregate cum 5.40 1005.00 5427.00 M-051

b) Labour

Mate day 0.16 151.44 24.23 L-12

Mason day 0.38 230.00 87.40 L-10

Mazdoor for concreting day 2.50 136.69 341.73 L-13

day 1.00 136.69 136.69 L-13

c) Machinery

Batching Plant @ 20 cum/hour hour 0.75 2232.00 1674.00 P&M-002

Generator 125 KVA hour 0.75 652.00 489.00 P&M-018

Loader (capacity 1 cum) hour 0.75 806.00 604.50 P&M-017

Transit Mixer ( capacity 4.0 cu.m )

Lead upto 1 Km hour 2.00 1017.00 2034.00 P&M-049

Lead beyond 1 Km, L - lead in Kilometer tonne.km 37.5L 2.03 76.27

Lead =1 km & P&M-

050

Formwork @ 4 per cent on cost of concrete i.e. cost of a) Material, b) Labour and c) Machinery

The value of a, b and c may be taken as applicable i.e. either using concrete mixer or batching plant.

Mazdoor for breaking pile head, bending bars, cleaning etc.

Formwork @ 4 per cent on cost of concrete i.e. cost of a) Material, b) Labour and c) Machinery

Mazdoor for breaking pile head, bending bars, cleaning etc.

Lead =1 km & P&M-

050

Page 228: Standard Data Book - Rate Analysis

Page 73 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Concrete Pump hour 0.75 256.00 192.00 P&M-007

2198.10

d) Overhead charges @ 0.2 on (a+b+c) 11430.15

e) Contractor's profit @ 0.1 on (a+b+c+d) 6858.09

Cost for 15 cum = a+b+c+d+e 75438.96

Rate per metre (a+b+c+d+e)/15 5029.26

say 5029.00

Note

12.38 C RCC Grade M30

Unit = cum

Taking output = 15 cum

(i) Using Concrete Mixer

a) Material

Cement tonne 6.10 5000.00 30500.00 M-081

Coarse sand cum 6.75 710.46 4795.61 M-005

20 mm Aggregate cum 8.10 1028.00 8326.80 M-053

10 mm Aggregate cum 5.40 1005.00 5427.00 M-051

b) Labour

Mate day 0.90 151.44 136.30 L-12

Mason day 1.50 230.00 345.00 L-10

Mazdoor for concreting day 20.00 136.69 2733.80 L-13

day 1.00 136.69 136.69 L-13

c) Machinery

Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009

Generator (capacity 33 KVA) hour 6.00 406.80 2440.80 P&M-079

2249.60

d) Overhead charges @ 0.2 on (a+b+c) 11697.92

e) Contractor's profit @ 0.1 on (a+b+c+d) 7018.75

Cost for 15 cum = a+b+c+d+e 77206.26

Rate per metre (a+b+c+d+e)/15 5147.08

say 5147.00

'12.38C (ii) Using Batching Plant, Transit Mixer and Concrete Pump

a) Material

Cement tonne 6.10 5000.00 30500.00 M-081

Coarse sand cum 6.75 828.00 5589.00 M-004

20 mm Aggregate cum 8.10 1028.00 8326.80 M-053

10 mm Aggregate cum 5.40 1005.00 5427.00 M-051

b) Labour

Mate day 0.16 151.44 24.23 L-12

Mason day 0.38 230.00 87.40 L-10

Mazdoor for concreting day 2.50 136.69 341.73 L-13

day 1.00 136.69 136.69 L-13

c) Machinery

Batching Plant @ 20 cum/hour hour 0.75 2232.00 1674.00 P&M-002

Generator 100 KVA hour 0.75 762.75 572.06 P&M-080

Loader (capacity 1 cum) hour 0.75 806.00 604.50 P&M-017

Transit Mixer ( capacity 4.0 cu.m )

Lead upto 1 Km hour 2.00 1017.00 2034.00 P&M-049

Lead beyond 1 Km, L - lead in Kilometer tonne.km 37.5L 2.03 76.27

Concrete Pump hour 0.75 256.00 192.00 P&M-007

Formwork @ 4 per cent on cost of concrete i.e. cost of a) Material, b) Labour and c) Machinery

The value of a, b and c may be taken as applicable i.e. either using concrete mixer or batching plant.

Mazdoor for breaking pile head, bending bars, cleaning etc.

Formwork @ 4 per cent on cost of concrete i.e. cost of a) Material, b) Labour and c) Machinery

Mazdoor for breaking pile head, bending bars, cleaning etc.

Lead =1 km & P&M-

050

Page 229: Standard Data Book - Rate Analysis

Page 74 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

2223.43

d) Overhead charges @ 0.2 on (a+b+c) 11561.82

e) Contractor's profit @ 0.1 on (a+b+c+d) 6937.09

Cost for 15 cum = a+b+c+d+e 76308.03

Rate per metre (a+b+c+d+e)/15 5087.20

say 5087.00

Note

12.38 D RCC Grade M35

Unit = cum

Taking output = 15 cum

(i) Using Concrete Mixer

a) Material

Cement tonne 6.33 5000.00 31650.00 M-081

Coarse sand cum 6.75 710.46 4795.61 M-005

20 mm Aggregate cum 8.10 1028.00 8326.80 M-053

10 mm Aggregate cum 5.40 1005.00 5427.00 M-051

b) Labour

Mate day 0.90 151.44 136.30 L-12

Mason day 1.50 230.00 345.00 L-10

Mazdoor day 20.00 136.69 2733.80 L-13

day 1.00 136.69 136.69 L-13

c) Machinery

Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009

Generator (capacity 33 KVA) hour 6.00 406.80 2440.80 P&M-079

2295.60

d) Overhead charges @ 0.2 on (a+b+c) 11937.12

e) Contractor's profit @ 0.1 on (a+b+c+d) 7162.27

Cost for 15 cum = a+b+c+d+e 78784.98

Rate per metre (a+b+c+d+e)/15 5252.33

say 5252.00

'12.38D (ii) Using Batching Plant, Transit Mixer and Concrete Pump

a) Material

Cement tonne 6.33 5000.00 31650.00 M-081

Coarse sand cum 6.75 828.00 5589.00 M-004

20 mm Aggregate cum 8.10 1028.00 8326.80 M-053

10 mm Aggregate cum 5.40 1005.00 5427.00 M-051

b) Labour

Mate day 0.16 151.44 24.23 L-12

Mason day 0.38 230.00 87.40 L-10

Mazdoor for concreting day 2.50 136.69 341.73 L-13

day 1.00 136.69 136.69 L-13

c) Machinery

Batching Plant @ 20 cum/hour hour 0.75 2232.00 1674.00 P&M-002

Generator 125 KVA hour 0.75 652.00 489.00 P&M-018

Loader (capacity 1 cum) hour 0.75 806.00 604.50 P&M-017

Transit Mixer ( capacity 4.0 cu.m )

Lead upto 1 Km hour 2.00 1017.00 2034.00 P&M-049

Lead beyond 1 Km, L - lead in Kilometer tonne.km 37.5L 2.03 76.27

Concrete Pump hour 0.75 256.00 192.00 P&M-007

2266.10

Formwork @ 4 per cent on cost of concrete i.e. cost of a) Material, b) Labour and c) Machinery

The value of a, b and c may be taken as applicable i.e. either using concrete mixer or batching plant.

Mazdoor for breaking pile head, bending bars, cleaning etc.

Formwork @ 4 per cent on cost of concrete i.e. cost of a) Material, b) Labour and c) Machinery

Mazdoor for breaking pile head, bending bars, cleaning etc.

Lead =1 km & P&M-

050

Formwork @ 4 per cent on cost of concrete i.e. cost of a) Material, b) Labour and c) Machinery

Page 230: Standard Data Book - Rate Analysis

Page 75 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

d) Overhead charges @ 0.2 on (a+b+c) 11783.75

e) Contractor's profit @ 0.1 on (a+b+c+d) 7070.25

Cost for 15 cum = a+b+c+d+e 77772.72

Rate per metre (a+b+c+d+e)/15 5184.85

say 5185.00

12.39 Levelling Course for Pile cap

Unit = cum

Taking output = 15 cum

a) Material

Cement tonne 4.13 5000.00 20650.00 M-081

Coarse sand cum 6.75 710.46 4795.61 M-005

40 mm aggregate cum 8.10 916.00 7419.60 M-055

20 mm Aggregate cum 4.05 1028.00 4163.40 M-053

10 mm Aggregate cum 1.35 1005.00 1356.75 M-051

b) Labour

Mate day 0.86 151.44 130.24 L-12

Mason day 1.50 230.00 345.00 L-10

Mazdoor day 20.00 136.69 2733.80 L-13

c) Machinery

Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009

Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079

d) Overhead charges @ 0.2 on (a+b+c) 9086.64

e) Contractor's profit @ 0.1 on (a+b+c+d) 5451.98

Cost for 15 cum = a+b+c+d+e 59971.82

Rate per metre (a+b+c+d+e)/15 3998.12

say 3998.00

12.40 1600

Unit = 1 MT

Taking output = 1 MT

a) Material

HYSD bars including5 per cent overlaps and wastage tonne 1.05 45000.00 47250.00 M-082

Binding wire Kg 6.00 100.00 600.00 M-072

Mate day 0.40 151.44 60.58 L-12

Blacksmith day 2.00 264.50 529.00 L-02

Mazdoor day 6.00 136.69 820.14 L-13

9851.94

5911.17

65022.83

say 65023.00

12.41 1600

Unit = 1 MT

Taking output = 1 MT

a) Material

MS bars including 5 per cent overlaps and wastage tonne 1.05 47307.50 49672.88 M-126

Binding wire Kg 6.00 100.00 600.00 M-072

Mate day 0.43 151.44 65.12 L-12

Blacksmith day 2.25 264.50 595.13 L-02

1100&1700

Providing and laying of PCC M15 levelling course 100mm thick below the pile cap.

Supplying, Fitting and Placing un-coated HYSD bar Reinforcement in Foundation complete as per Drawing and Technical Specifications.

b) Labour for cutting, bending, shifting to site, tying and placing in position

Supplying, fitting and placing un-coated Mild steel reinforcement complete in foundation as per drawing and technical specification

b) Labour for straightening, cutting, bending, shifting to site, tying and placing in position

Page 231: Standard Data Book - Rate Analysis

Page 76 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Mazdoor day 6.50 136.69 888.49 L-13

c) Overhead charges @ 0.2 on (a+b) 10364.32

d) Contractor's profit @ 0.1 on (a+b+c) 6218.59

Rate for per MT (a+b+c+d) 68404.52

say 68405.00

Page 232: Standard Data Book - Rate Analysis

Page 1 of 280

CHAPTER-13SUB-STRUCTURE

Sr No Description Unit Quantity Rate Rs Cost Rs

13.1

Unit = cumTaking output = 1 cuma) Material

Bricks Ist class each 500.00 4.42 2209.09 M-079cum 0.24 3425.00 822.00

b) Labour Mate day 0.06 151.44 9.09 L-12Mason day 0.80 0.00 L-11Mazdoor day 0.80 136.69 109.35 L-13

157.48

c) Overhead charges @ 0.2 on (a+b) 661.40 d) Contractor's profit @ 0.1 on (a+b+c) 396.84 Rate per cum (a+b+c+d) 4365.25

say 4365.00 13.2

Unit = 10 sqmTaking output = 10 sqma) Material

Cement mortar 1:3 (Rate as in Item 12.6 ) cum 0.03 3425.00 102.75

b) LabourMate day 0.04 151.44 6.06 L-12Mason day 0.50 223.36 111.68 L-11Mazdoor day 0.50 136.69 68.35 L-13

c) Overhead charges @ 0.2 on (a+b) 57.77 d) Contractor's profit @ 0.1 on (a+b+c) 34.66 Rate per 10 sqm (a+b+c+d) 381.26

say 381.00 Note Scaffolding is already included in item 13.1

13.3

Unit = 10 sqmTaking output = 10 sqma) Material

Cement mortar 1:3 (Rate as in Item 12.6) cum 0.144 3425.00 493.20

b) LabourMate day 0.04 151.44 6.06 L-12Mason day 0.50 223.36 111.68 L-11Mazdoor day 0.50 136.69 68.35 L-13

c) Overhead charges @ 0.2 on (a+b) 135.86 d) Contractor's profit @ 0.1 on (a+b+c) 81.51 Rate per 10 sqm (a+b+c+d) 896.65

say 897.00 Note 1.Scaffolding is already included in item no. 13.1

13.4

A Random Rubble Masonry( coursed/uncoursed )Unit = cumTaking output = 1 cuma) Material

Stone cum 1.00 2604.51 2604.51 M-148Through and bond stone No 7.00 14.45 101.17 M-182

(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)Cement mortar 1:3 (Rate as in Item 12.6) cum 0.33 3425.00 1130.25

Ref. to MoRTH Spec.

Remarks/ Input ref.

1300 & 2200

Brick masonry work in 1:3 in sub-structure complete excluding pointing and plastering, as per drawing and Technical Specifications

Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis)

Item 12.6 (A)

Add for scaffolding @ 5 per cent of cost of material and labour

1300 & 2200

Pointing with cement mortar (1:3 ) on brick work in substructure as per Technical Specifications

Item 12.6 (A)

1300 & 2200

Plastering with cement mortar (1:3 ) on brick work in sub-structure as per Technical Specifications

Item 12.6 (A)

2.The number of masons and Mazdoors already catered in the cement mortar have been taken into account while providing these categories in brick masonry, pointing and plastering.

1400 & 2200

Stone masonry work in cement mortar 1:3 for substructure complete as per drawing and Technical Specifications

Item 12.6 (A)

Page 233: Standard Data Book - Rate Analysis

Page 2 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

b) LabourMate day 0.10 151.44 15.14 L-12Mason day 1.20 223.36 268.03 L-11Mazdoor day 1.20 136.69 164.03 L-13

214.16

c) Overhead charges @ 0.2 on (a+b) 899.46

d) Contractor's profit @ 0.1 on (a+b+c) 539.68

Rate per cum (a+b+c+d) 5936.43

say 5936.00

13.4 B Coursed rubble masonry (first sort )

Unit = cum

Taking output = 1 cum

a) Material

Stone cum 1.10 2604.51 2864.96 M-148

Through and bond stone each 7.00 14.45 101.17 M-182

(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)

Cement mortar 1:3 (Rate as in Item 12.6) cum 0.30 3425.00 1027.50

b) Labour

Mate day 0.12 151.44 18.17 L-12

Mason day 1.50 223.36 335.04 L-11

Mazdoor day 1.50 136.69 205.04 L-13

227.59

c) Overhead charges @ 0.2 on (a+b) 955.89

d) Contractor's profit @ 0.1 on (a+b+c) 573.54

Rate per cum (a+b+c+d) 6308.91

say 6309.00

13.4 C Ashlar masonry ( first sort )

Plain ashlar

Unit = cum

Taking output = 1 cum

a) Material

Stone cum 1.11 2705.04 3002.59 M-169

Through and bond stone each 7.00 14.45 101.17 M-182

(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)

Cement mortar 1:3 (Rate as in Item 12.6) cum 0.33 3425.00 1130.25

b) Labour for masonry work

Mate day 0.20 151.44 30.29 L-12

Mason day 2.50 223.36 558.40 L-11

Mazdoor day 2.50 136.69 341.73 L-13

258.22

c) Overhead charges @ 0.2 on (a+b) 1084.53

d) Contractor's profit @ 0.1 on (a+b+c) 650.72

Rate per cum (a+b+c+d) 7157.90

say 7158.00

Note

13.5

Unit = cum

Taking output = 1 cum

A PCC Grade M15

(p) Height upto 5m

Add for scaffolding @ 5 per cent of cost of a) Material and b) Labour

Item 12.6 (A)

Add for scaffolding @ 5 per cent of cost of material and labour

Item 12.6 (A)

Add for scaffolding @ 5 per cent of cost of a) Material and b) Labour

The labour already considered in the cement mortar have been taken into account while providing these categories in the stone masonry works.

1500, 1700 & 2200

Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical Specifications

Page 234: Standard Data Book - Rate Analysis

Page 3 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

3080.00 Item 12.8 (A)

d) formwork

10.00 308.00

e) Overhead charges @ 0.2 on (a+b+c+d) 677.60

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 406.56

Rate perm (a+b+c+d+e+f) 4472.16

say 4472.00

13.5 B PCC Grade M20

(p) Height upto 5m

3390.00 Item 12.8 (B) PCC

d) formwork

10.00 339.00

e) Overhead charges @ 0.2 on (a+b+c+d) 745.80

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 447.48

Rate perm (a+b+c+d+e+f) 4922.28

say 4922.00

13.5 C PCC Grade M25

(p) Height upto 5m

Using concrete Mixer

3667.00 Item 12.8 (D)

d) formwork

10.00 366.70

e) Overhead charges @ 0.2 on (a+b+c+d) 806.74

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 484.04

Rate perm (a+b+c+d+e+f) 5324.48

say 5324.00

With Batching Plant, Transit Mixer and Concrete Pump

3614.00 Item 12.8 (D)

d) formwork

10.00 361.40

e) Overhead charges @ 0.2 on (a+b+c+d) 795.08

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 477.05

Rate perm (a+b+c+d+e+f) 5247.53

say 5248.00

13.5 C (q) Height 5m to 10m

Using concrete Mixer

3667.00 Item 12.8 (D)

Same as Item 12.8 (A) upto 5 m height, except for formwork which shall be 10 per cent instead of 4 per cent of cost of material, labour and machinery.

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (A)

Add 10 per cent of cost of material, labour and machinery (a+b+c) for Formwork

Same as Item 12.8 (B) upto 5 m height, except for formwork which shall be 10 per cent instead of 4 per cent of cost of material, labour and machinery.

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (B)

Add 10 per cent of cost of material, labour and machinery (a+b+c) for Formwork

Same as Item 12.8 (D) upto 5 m height with the only change that the provision of form work shall be 10 per cent instead of 3.75 per cent of cost of material, labour and machinery.

Case I

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (D) Case I

Add 10 per cent of cost of material, labour and machinery (a+b+c) for Formwork

13.5 C (p)

Case II

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (D) Case II

Add 10 per cent of cost of material, labour and machinery (a+b+c) for Formwork

Same as Item 12.8 (D) with the following changes: (i) Add 2 per cent of cost of material, Labour and machinery excluding form work to cater for extra lift. (ii) The provision of form work shall be 12 per cent instead of 3.75 per cent of cost of material, labour and machinery

Case I

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (D) Case I

Page 235: Standard Data Book - Rate Analysis

Page 4 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

d) formwork

12.00 440.04

2.00 73.34

e) Overhead charges @ 0.2 on (a+b+c+d) 836.08

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 501.65

Rate perm (a+b+c+d+e+f) 5518.10

say 5518.00

With Batching Plant, Transit Mixer and Concrete Pump

3614.00

d) formwork

12.00 433.68

2.00 72.28

e) Overhead charges @ 0.2 on (a+b+c+d) 823.99

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 494.40

Rate perm (a+b+c+d+e+f) 5438.35

say 5438.00

13.5 C (r) Height above 10m

Using concrete Mixer

3667.00 Item 12.8 (D)

d) formwork

15.00 550.05

4.00 146.68

e) Overhead charges @ 0.2 on (a+b+c+d) 872.75

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 523.65

Rate perm (a+b+c+d+e+f) 5760.12

say 5760.00

With Batching Plant, Transit Mixer and Concrete Pump

3614.00 Item 12.8 (D)

d) formwork

15.00 542.10

4.00 144.56

e) Overhead charges @ 0.2 on (a+b+c+d) 860.13

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 516.08

Rate perm (a+b+c+d+e+f) 5676.87

say 5677.00

13.5 D PCC Grade M30

(p) Height upto 5m

Using concrete Mixer

3697.00

Add 12 per cent of cost of material, labour and machinery (a+b+c) for Formwork

Add 2 per cent of cost of material, Labour and machinery excluding formwork to cater for extra lift

13.5 C (q)

Case II

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (D) Case II

Add 12 per cent of cost of material, labour and machinery (a+b+c) for Formwork

Add 2 per cent of cost of material, Labour and machinery excluding formwork to cater for extra lift

Same as Item 12.8 (D) with the following changes: (i) Add 4 per cent of cost of material, labour and machinery excluding form work to cater for extra lift. (ii) The provision of form work shall be 15 per cent instead of 3.75 per cent of cost of material, labour and machinery.

Case I

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (D) Case I

Add 15 per cent of cost of material, labour and machinery (a+b+c) for Formwork

Add 4 per cent of cost of material, Labour and machinery excluding formwork to cater for extra lift

13.5 C (r)

Case II

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (D) Case II

Add 15 per cent of cost of material, labour and machinery (a+b+c) for Formwork

Add 4 per cent of cost of material, Labour and machinery excluding formwork to cater for extra lift

Same as Item 12.8 (F) upto 5 m height with the only change that the provision of form work shall be 10 per cent instead of 3.50 per cent of cost of material, labour and machinery.

Case I

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (F) Case I

Page 236: Standard Data Book - Rate Analysis

Page 5 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

d) formwork

10.00 369.70

e) Overhead charges @ 0.2 on (a+b+c+d) 813.34

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 488.00

Rate perm (a+b+c+d+e+f) 5368.04

say 5368.00

With Batching Plant, Transit Mixer and Concrete Pump

3641.00

d) formwork

10.00 364.10

e) Overhead charges @ 0.2 on (a+b+c+d) 801.02

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 480.61

Rate perm (a+b+c+d+e+f) 5286.73

say 5287.00

13.5 D (q) Height 5m to 10m

Using concrete Mixer

3697.00

d) formwork

12.00 443.64

2.00 73.94

e) Overhead charges @ 0.2 on (a+b+c+d) 842.92

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 505.75

Rate perm (a+b+c+d+e+f) 5563.25

say 5563.00

With Batching Plant, Transit Mixer and Concrete Pump

3641.00

d) formwork

12.00 436.92

2.00 72.82

e) Overhead charges @ 0.2 on (a+b+c+d) 830.15

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 498.09

Rate perm (a+b+c+d+e+f) 5478.98

say 5479.00

13.5 D (r) Height above 10m

Using concrete Mixer

3697.00

d) formwork

15.00 554.55

Add 10 per cent of cost of material, labour and machinery (a+b+c) for Formwork

13.5 D (p)

Case II

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (F) Case II

Add 10 per cent of cost of material, labour and machinery (a+b+c) for Formwork

Same as Item 12.8 (F) with the following changes: (i) Add 2 per cent of cost of material, Labour and machinery excluding form work to cater for extra lift. (ii) The provision of form work shall be 12 per cent instead of 3.50 per cent of cost of material, labour and machinery.

Case I

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (F) Case I

Add 12 per cent of cost of material, labour and machinery (a+b+c) for Formwork

Add 2 per cent of cost of material, Labour and machinery excluding formwork to cater for extra lift

13.5 D (q)

Case II

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (F) Case II

Add 12 per cent of cost of material, labour and machinery (a+b+c) for Formwork

Add 2 per cent of cost of material, Labour and machinery excluding formwork to cater for extra lift

Same as Item 12.8 (F) with the following changes: (i) Add 4 per cent of cost of material, labour and machinery excluding form work to cater for extra lift. (ii) The provision of form work shall be 15 per cent instead of 3.50 per cent of cost of material, labour and machinery

Case I

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (F) Case I

Add 15 per cent of cost of material, labour and machinery (a+b+c) for Formwork

Page 237: Standard Data Book - Rate Analysis

Page 6 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

4.00 147.88

e) Overhead charges @ 0.2 on (a+b+c+d) 879.89

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 527.93

Rate perm (a+b+c+d+e+f) 5807.25

say 5807.00

With Batching Plant, Transit Mixer and Concrete Pump

3641.00

d) formwork

15.00 546.15

4.00 145.64

e) Overhead charges @ 0.2 on (a+b+c+d) 866.56

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 519.93

Rate perm (a+b+c+d+e+f) 5719.28

say 5719.00

13.5 E RCC Grade M20

(p) Height upto 5m

Using concrete Mixer

3443.00

d) formwork

10.00 344.30

e) Overhead charges @ 0.2 on (a+b+c+d) 757.46

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 454.48

Rate perm (a+b+c+d+e+f) 4999.24

say 4999.00

With Batching Plant, Transit Mixer and Concrete Pump

3388.00

d) formwork

10.00 338.80

e) Overhead charges @ 0.2 on (a+b+c+d) 745.36

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 447.22

Rate perm (a+b+c+d+e+f) 4919.38

say 4919.00

13.5 E (q) Height 5m to 10m

Using concrete Mixer

3443.00

d) formwork

12.00 413.16

2.00 68.86

e) Overhead charges @ 0.2 on (a+b+c+d) 785.00

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 471.00

Rate perm (a+b+c+d+e+f) 5181.03

Add 4 per cent of cost of material, Labour and machinery excluding formwork to cater for extra lift

13.5 D (r)

Case II

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (F) Case II

Add 15 per cent of cost of material, labour and machinery (a+b+c) for Formwork

Add 4 per cent of cost of material, Labour and machinery excluding formwork to cater for extra lift

Same as Item 12.8 (C) upto 5 m height, except for formwork which shall be 10 per cent instead of 4 per cent of cost of material, labour and machinery.

Case I

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (C) Case I

Add 10 per cent of cost of material, labour and machinery (a+b+c) for Formwork

13.5 E (p)

Case II

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (C) Case II

Add 10 per cent of cost of material, labour and machinery (a+b+c) for Formwork

For height, upto 10m, add 2 per cent of cost as above excluding formwork. For cost of formwork add 12 per cent of cost of material, labour and machinery instead of 4 per cent .

Case I

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (C) Case I

Add 12 per cent of cost of material, labour and machinery (a+b+c) for Formwork

Add 2 per cent of cost of material, Labour and machinery excluding formwork to cater for extra lift

Page 238: Standard Data Book - Rate Analysis

Page 7 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

say 5181.00

With Batching Plant, Transit Mixer and Concrete Pump

3388.00

d) formwork

12.00 406.56

2.00 67.76

e) Overhead charges @ 0.2 on (a+b+c+d) 772.46

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 463.48

Rate perm (a+b+c+d+e+f) 5098.26

say 5098.00

13.5 E (r) Height above 10m

Using concrete Mixer

3443.00

d) formwork

15.00 516.45

4.00 137.72

e) Overhead charges @ 0.2 on (a+b+c+d) 819.43

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 491.66

Rate perm (a+b+c+d+e+f) 5408.26

say 5408.00

With Batching Plant, Transit Mixer and Concrete Pump

3388.00

d) formwork

15.00 508.20

4.00 135.52

e) Overhead charges @ 0.2 on (a+b+c+d) 806.34

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 483.81

Rate perm (a+b+c+d+e+f) 5321.87

say 5322.00

13.5 F RCC Grade M25

(p) Height upto 5m

Using concrete Mixer

3723.00

d) formwork

10.00 372.30

e) Overhead charges @ 0.2 on (a+b+c+d) 819.06

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 491.44

Rate perm (a+b+c+d+e+f) 5405.80

say 5406.00

With Batching Plant, Transit Mixer and Concrete Pump

13.5 E (q)

Case II

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (C) Case II

Add 12 per cent of cost of material, labour and machinery (a+b+c) for Formwork

Add 2 per cent of cost of material, Labour and machinery excluding formwork to cater for extra lift

Same as Item 12.8 (C) with the following changes: (i) Add 4 per cent of cost of material, labour and machinery excluding form work to cater for extra lift. (ii) The provision of form work shall be 15 per cent instead of 4 per cent of cost of material, labour and machinery.

Case I

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (C) Case I

Add 15 per cent of cost of material, labour and machinery (a+b+c) for Formwork

Add 4 per cent of cost of material, Labour and machinery excluding formwork to cater for extra lift

13.5 E (r)

Case II

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (C) Case II

Add 15 per cent of cost of material, labour and machinery (a+b+c) for Formwork

Add 4 per cent of cost of material, Labour and machinery excluding formwork to cater for extra lift

Same as Item 12.8 (E) upto 5m height, excluding formwork. For cost of formwork, add 10 per cent of cost of material, labour and machinery instead of 3.75 per cent .

Case I

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (E) Case I

Add 10 per cent of cost of material, labour and machinery (a+b+c) for Formwork

13.5 F (p)

Case II

Page 239: Standard Data Book - Rate Analysis

Page 8 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

3740.00

d) formwork

10.00 374.00

e) Overhead charges @ 0.2 on (a+b+c+d) 822.80

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 493.68

Rate perm (a+b+c+d+e+f) 5430.48

say 5430.00

13.5 F (q) Height 5m to 10m

Using concrete Mixer

3723.00

d) formwork

11.80 439.31

1.80 67.01

e) Overhead charges @ 0.2 on (a+b+c+d) 845.87

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 507.52

Rate perm (a+b+c+d+e+f) 5582.71

say 5583.00

With Batching Plant, Transit Mixer and Concrete Pump

3740.00

d) formwork

11.80 441.32

1.80 67.32

e) Overhead charges @ 0.2 on (a+b+c+d) 849.73

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 509.84

Rate perm (a+b+c+d+e+f) 5608.20

say 5608.00

13.5 F (r) Height above 10m

Using concrete Mixer

3723.00

d) formwork

15.00 558.45

4.00 148.92

e) Overhead charges @ 0.2 on (a+b+c+d) 886.07

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 531.64

Rate perm (a+b+c+d+e+f) 5848.09

say 5848.00

With Batching Plant, Transit Mixer and Concrete Pump

3740.00

d) formwork

15.00 561.00

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (E) Case II

Add 10 per cent of cost of material, labour and machinery (a+b+c) for Formwork

For height, upto 10m, add 1.8 per cent of cost as above excluding formwork. For cost of formwork add 11.8 per cent of cost of material, labour and machinery

Case I

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (E) Case I

Add 11.8 per cent of cost of material, labour and machinery (a+b+c) for Formwork

Add 1.8 per cent of cost of material, Labour and machinery excluding formwork to cater for extra lift

13.5 F (q)

Case II

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (E) Case II

Add 11.8 per cent of cost of material, labour and machinery (a+b+c) for Formwork

Add 1.8 per cent of cost of material, Labour and machinery excluding formwork to cater for extra lift

For height, above 10m, add 4 per cent of cost as above excluding formwork. For cost of formwork add 15 per cent of cost of material, labour and machinery

Case I

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (E) Case I

Add 15 per cent of cost of material, labour and machinery (a+b+c) for Formwork

Add 4 per cent of cost of material, Labour and machinery excluding formwork to cater for extra lift

13.5 F (r)

Case II

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (E) Case II

Add 15 per cent of cost of material, labour and machinery (a+b+c) for Formwork

Page 240: Standard Data Book - Rate Analysis

Page 9 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

4.00 149.60

e) Overhead charges @ 0.2 on (a+b+c+d) 890.12

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 534.07

Rate perm (a+b+c+d+e+f) 5874.79

say 5875.00

13.5 G RCC Grade M30

(p) Height upto 5m

Using concrete Mixer

3740.00

d) formwork

10.00 374.00

e) Overhead charges @ 0.2 on (a+b+c+d) 822.80

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 493.68

Rate perm (a+b+c+d+e+f) 5430.48

say 5430.00

With Batching Plant, Transit Mixer and Concrete Pump

3686.00

d) formwork

10.00 368.60

e) Overhead charges @ 0.2 on (a+b+c+d) 810.92

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 486.55

Rate perm (a+b+c+d+e+f) 5352.07

say 5352.00

13.5 G (q) Height 5m to 10m

Using concrete Mixer

3740.00

d) formwork

11.50 430.10

1.60 59.84

e) Overhead charges @ 0.2 on (a+b+c+d) 845.99

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 507.59

Rate perm (a+b+c+d+e+f) 5583.52

say 5584.00

With Batching Plant, Transit Mixer and Concrete Pump

3686.00

d) formwork

11.50 423.89

1.60 58.98

e) Overhead charges @ 0.2 on (a+b+c+d) 833.77

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 500.26

Rate perm (a+b+c+d+e+f) 5502.90

say 5503.00

Add 4 per cent of cost of material, Labour and machinery excluding formwork to cater for extra lift

Same as Item 12.8 (G) upto 5m height, excluding formwork. For cost of formwork, add 10 per cent of cost of material, labour and machinery instead of 3.5 per cent .

Case I

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (G) Case I

Add 10 per cent of cost of material, labour and machinery (a+b+c) for Formwork

13.5 G (p)

Case II

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (G) Case II

Add 10 per cent of cost of material, labour and machinery (a+b+c) for Formwork

For height, upto 10m, add 1.6 per cent of cost as above excluding formwork. For cost of formwork add 11.5 per cent of cost of material, labour and machinery

Case I

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (G) Case I

Add 11.5 per cent of cost of material, labour and machinery (a+b+c) for Formwork

Add 1.6 per cent of cost of material, Labour and machinery excluding formwork to cater for extra lift

13.5 G (q)

Case II

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (G) Case II

Add 11.5 per cent of cost of material, labour and machinery (a+b+c) for Formwork

Add 1.6 per cent of cost of material, Labour and machinery excluding formwork to cater for extra lift

Page 241: Standard Data Book - Rate Analysis

Page 10 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

13.5 G (r) Height above 10m

Using concrete Mixer

3740.00

d) formwork

14.00 523.60

3.50 130.90

e) Overhead charges @ 0.2 on (a+b+c+d) 878.90

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 527.34

Rate perm (a+b+c+d+e+f) 5800.74

say 5801.00

With Batching Plant, Transit Mixer and Concrete Pump

3686.00

d) formwork

14.00 516.04

3.50 129.01

e) Overhead charges @ 0.2 on (a+b+c+d) 866.21

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 519.73

Rate perm (a+b+c+d+e+f) 5716.99

say 5717.00

13.5 H RCC Grade M35

(p) Height upto 5m

Using concrete Mixer

3816.00

d) formwork

10.00 381.60

e) Overhead charges @ 0.2 on (a+b+c+d) 839.52

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 503.71

Rate perm (a+b+c+d+e+f) 5540.83

say 5541.00

With Batching Plant, Transit Mixer and Concrete Pump

3838.00

d) formwork

10.00 383.80

e) Overhead charges @ 0.2 on (a+b+c+d) 844.36

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 506.62

Rate perm (a+b+c+d+e+f) 5572.78

say 5573.00

13.5 H (q) Height 5m to 10m

Using concrete Mixer

For height, above 10m, add 3.5 per cent of cost as above excluding formwork. For cost of formwork add 14 per cent of cost of material, labour and machinery

Case I

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (G) Case I

Add 14 per cent of cost of material, labour and machinery (a+b+c) for Formwork

Add 3.5 per cent of cost of material, Labour and machinery excluding formwork to cater for extra lift

13.5 G (r)

Case II

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (G) Case II

Add 14 per cent of cost of material, labour and machinery (a+b+c) for Formwork

Add 3.5 per cent of cost of material, Labour and machinery excluding formwork to cater for extra lift

Same as Item 12.8 (H) upto 5m height, excluding formwork. For cost of formwork, add 10 per cent of cost of material, labour and machinery instead of 3 per cent .

Case I

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (H) Case I

Add 10 per cent of cost of material, labour and machinery (a+b+c) for Formwork

13.5 H (p)

Case II

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (H) Case II

Add 10 per cent of cost of material, labour and machinery (a+b+c) for Formwork

For height, upto 10m, add 1.4 per cent of cost as above excluding formwork. For cost of formwork add 11 per cent of cost of material, labour and machinery .

Case I

Page 242: Standard Data Book - Rate Analysis

Page 11 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

3816.00

d) formwork

11.00 419.76

1.40 53.42

e) Overhead charges @ 0.2 on (a+b+c+d) 857.84

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 514.70

Rate perm (a+b+c+d+e+f) 5661.72

say 5662.00

With Batching Plant, Transit Mixer and Concrete Pump

3838.00

d) formwork

11.00 422.18

1.40 53.73

e) Overhead charges @ 0.2 on (a+b+c+d) 862.78

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 517.67

Rate perm (a+b+c+d+e+f) 5694.36

say 5694.00

13.5 H (r) Height above 10m

Using concrete Mixer

3816.00

d) formwork

13.00 496.08

3.00 114.48

e) Overhead charges @ 0.2 on (a+b+c+d) 885.31

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 531.19

Rate perm (a+b+c+d+e+f) 5843.06

say 5843.00

With Batching Plant, Transit Mixer and Concrete Pump

3838.00

d) formwork

13.00 498.94

3.00 115.14

e) Overhead charges @ 0.2 on (a+b+c+d) 890.42

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 534.25

Rate perm (a+b+c+d+e+f) 5876.75

say 5877.00

Note

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (H) Case I

Add 11 per cent of cost of material, labour and machinery (a+b+c) for Formwork

Add 1.4 per cent of cost of material, Labour and machinery excluding formwork to cater for extra lift

13.5 H (q)

Case II

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (H) Case II

Add 11 per cent of cost of material, labour and machinery (a+b+c) for Formwork

Add 1.4 per cent of cost of material, Labour and machinery excluding formwork to cater for extra lift

For height, above 10m, add 3 per cent of cost as above excluding formwork. For cost of formwork add 13 per cent of cost of material, labour and machinery

Case I

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (H) Case I

Add 13 per cent of cost of material, labour and machinery (a+b+c) for Formwork

Add 3 per cent of cost of material, Labour and machinery excluding formwork to cater for extra lift

13.5 H (r)

Case II

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (H) Case II

Add 13 per cent of cost of material, labour and machinery (a+b+c) for Formwork

Add 3 per cent of cost of material, Labour and machinery excluding formwork to cater for extra lift

The basic components of this analysis are the same as those of items 13.8 (A to H). The only changes are as under:

a) Ramps/Stairs: Extra expenditure on structures which are more than 5 m high @ 2 per cent of cost for height upto 10 m and 4 per cent for heights above 10 m will be involved for approaching the work spot by providing higher ramp/stair case for use by the working parties.

Page 243: Standard Data Book - Rate Analysis

Page 12 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

13.6

Output: MT

Taking output = 1 MT

a) Material

HYSD bars including 5 per cent overlaps and wastage tonne 1.05 45000.00 47250.00 M-082

Binding wire kg 6.00 100.00 600.00 M-072

Mate day 0.34 151.44 51.49 L-12

Blacksmith day 2.00 264.50 529.00 L-02

Mazdoor day 6.50 136.69 888.49 L-13

c) Overhead charges @ 0.2 on (a+b) 9863.79

d) Contractor's profit @ 0.1 on (a+b+c) 5918.28

Rate for per MT (a+b+c+d) 65101.05

say 65101.00

13.7

Unit = MT

Taking output = 1 MT

a) Material

MS bars including 5 per cent overlaps and wastage tonne 1.05 47307.50 49672.88 M-126

Binding wire kg 6.00 100.00 600.00 M-072

Mate day 0.28 151.44 42.40 L-12

Blacksmith day 1.50 264.50 396.75 L-02

Mazdoor day 5.50 136.69 751.80 L-13

c) Overhead charges @ 0.2 on (a+b) 10292.76

d) Contractor's profit @ 0.1 on (a+b+c) 6175.66

Rate for per MT (a+b+c+d) 67932.25

say 67932.00

13.8

Unit = Nos.

Taking output = 30 Nos.

a) Material

metre 31.50 65.00 2047.50 M-056

MS clamp each. 30.00 13.00 390.00 M-123

each. 10.00 6.50 65.00 M-056/10

Cement mortar 1:3 (Rate as in Item 12.6) cum 0.05 3425.00 171.25

b) Labour

Mate day 0.03 151.44 4.54 L-12

Mason day 0.50 223.36 111.68 L-11

b) The above mentioned percentages have been suitably modified for different categories as cost for various categories varies, whereas effort for access for same height will be similar. As the cost of richer concrete is comparatively more, the percentage to be added has been reduced to maintain the same cost for extra efforts.

Section 1600 & 2200

Supplying, fitting and placing HYSD bar reinforcement in sub-structure complete as per drawing and Technical Specifications

b) Labour for cutting, bending, shifting to site, tying and placing in position

1600 & 2200

Supplying, fitting and placing Mild steel reinforcement complete in sub-structure as per drawing and Technical Specification

b) Labour for straightening, cutting, bending, shifting to site, tying and placing in position

2706 & 2200

Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/ return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. Complete as per drawing and Technical Specifications

AC pipe 100 mm dia. (including wastage @ 5 per cent )

Average length of weep hole is taken as one metre for the purpose of estimating.

collar for AC pipe (average) taking 10% of above pipe rate

Item 12.6 (A)

Page 244: Standard Data Book - Rate Analysis

Page 13 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Mazdoor day 0.25 136.69 34.17 L-13

c) Overhead charges @ 0.2 on (a+b) 564.83

d) Contractor's profit @ 0.1 on (a+b+c) 338.90

Cost for 30 m = a+b+c+d 3727.87

Rate per m (a+b+c+d)/30 124.26

say 124.00

Note

13.9

Unit = cum

Taking output = 10 cum

A Granular material

a) Labour

Mate day 0.28 151.44 42.40 L-12

Mazdoor day 7.00 136.69 956.83 L-13

b) Material

Granular material cum 12.00 727.79 8733.48 M-009

c) Machinery

Plate compactor/power rammer hour 2.50 101.70 254.25 P&M-086

Water Tanker hour 0.05 200.00 10.00 P&M-060

d) Overhead charges @ 0.2 on (a+b+c) 1999.39

e) Contractor's profit @ 0.1 on (a+b+c+d) 1199.64

Cost for 10 cum of granular backfill = a+b+c+d+e 13195.99

Rate per cum = (a+b+c+d+e)/10 1319.60

say 1320.00

13.9 B Sandy material

a) Labour

Mate day 0.28 151.44 42.40 L-12

Mazdoor for filling, watering, ramming etc. day 7.00 136.69 956.83 L-13

b) Material

Sand cum 12.00 476.80 5721.60 M-006

c) Machinery

Plate compactor/power rammer hour 2.50 101.70 254.25 P&M-086

Water Tanker hour 0.06 200.00 12.00 P&M-060

d) Overhead charges @ 0.2 on (a+b+c) 1397.42

e) Contractor's profit @ 0.1 on (a+b+c+d) 838.45

Cost for 10 cum of sandy backfill = a+b+c+d+e 9222.95

Rate per cum = (a+b+c+d+e)/10 922.29

say 922.00

13.10

Unit = cum

Taking output = 10 cum.

a) Labour

Mate day 0.32 151.44 48.46 L-12

1. In case of stone masonry, the size of the weep hole shall be 150 mm x 80 mm or circular with 150 mm diameter.

2. For structure in stone masonry, the weep holes shall be deemed to be included in the item of stone masonry work and shall not be paid separately.

710.1.4.of

IRC:78 & 2200

Back filling behind abutment, wing wall and return wall complete as per drawing and Technical Specification

710.1.4.of

IRC:78 and 2200

Providing and laying of Filter media with granular materials/stone crushed aggregates satisfying the requirements laid down in clause 2504.2.2. of MoRTH specifications to a thickness of not less than 600 mm with smaller size towards the soil and bigger size towards the wall and provided over the entire surface behind abutment, wing wall and return wall to the full height compacted to a firm condition complete as per drawing and Technical Specification.

Page 245: Standard Data Book - Rate Analysis

Page 14 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Mazdoor for filling, watering, ramming etc. day 7.00 136.69 956.83 L-13

Mazdoor (Skilled) day 1.00 164.69 164.69 L-15

b) Material

cum 12.00 894.00 10728.00 M-012

c) Machinery

Water Tanker of 6 KL capacity hour 0.06 200.00 12.00 P&M-060

d) Overhead charges @ 0.2 on (a+b+c) 2382.00

e) Contractor's profit @ 0.1 on (a+b+c+d) 1429.20

cost for 10 cum of Fiter Media = a+b+c+d+e 15721.17

Rate per cum = (a+b+c+d+e)/10 1572.12

say 1572.00

13.11

Unit: one tonne capacity

Considering a 250 tonne capacity bearing for this analysis

a) Labour

Mate day 0.06 151.44 9.09 L-12

Mazdoor (Skilled) day 0.50 164.69 82.35 L-15

Mazdoor day 1.00 136.69 136.69 L-13

b) Material

each. 1.00 50000.00 50000.00 M-065

500.00

c) Overhead charges @ 0.2 on (a+b) 10145.62

d) Contractor's profit @ 0.1 on (a+b+c) 6087.37

cost for 250 tonnes capacity bearing = a+b+c+d 66961.12

Rate per tonne capacity = (a+b+c+d)/250 267.84

say 268.00

13.12

Unit: one tonne capacity

Considering a 250 tonne capacity bearing for this analysis

a) Labour

Mate day 0.06 151.44 9.09 L-12

Mazdoor day 1.00 136.69 136.69 L-13

Mazdoor (Skilled) day 0.50 164.69 82.35 L-15

b) Material

each. 1.00 41309.00 41309.00 M-067

413.09

c) Overhead charges @ 0.2 on (a+b) 8390.04

d) Contractor's profit @ 0.1 on (a+b+c) 5034.03

cost for 250 tonnes capacity bearing = a+b+c+d 55374.28

Rate per tonne capacity = (a+b+c+d)/250 221.50

say 221.00

Filter media of stone aggregate conforming to clause 2504.2.2. of MoRTH specifications.

2000, 1000 & 2200

Supplying, fitting and fixing in position true to line and level cast steel rocker bearing conforming to IRC: 83(Pt.-1) section IX and clause 2003 of MoRTH specifications complete including all accessories as per drawing and Technical Specifications.

Cast steel rocker bearing assembly of 250 tonne design load capacity duly painted complete with all its components as per drawing and specifications

Add 1 per cent of cost of bearing assembly for foundation anchorage bolts, lifting arrangements, grease and other consumables.

2000 , 1000 & 2200

Supplying, fitting and fixing in position true to line and level forged steel roller bearing conforming to IRC: 83(Pt.-1) section IX and clause 2003 of MoRTH specifications complete including all accessories as per drawing and Technical Specifications.

Forged steel roller bearing of 250 tonne design load capacity duly painted complete with all its components as per drawing and specifications

Add 1 per cent of cost of bearing assembly for foundation anchorage bolts, lifting arrangements, grease and other consumables.

Page 246: Standard Data Book - Rate Analysis

Page 15 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

13.13

Unit: one tonne capacity

Considering a 80 tonne capacity bearing for this analysis

a) Labour

Mate day 0.06 151.44 9.09 L-12

Mazdoor day 1.00 136.69 136.69 L-13

Mazdoor (Skilled) day 0.50 164.69 82.35 L-15

b) Material

each. 1.00 16378.00 16378.00 M-069

163.78

c) Overhead charges @ 0.2 on (a+b) 3353.98

d) Contractor's profit @ 0.1 on (a+b+c) 2012.39

cost for 80 tonnes capacity bearing = a+b+c+d 22136.27

Rate per tonne capacity = (a+b+c+d)/80 276.70

say 277.00

13.14

Unit: one cubic centimetre

Overall volume - 19200 cu.cm

Hence volume of elastometer = 14655 cu.cm.

a) Labour

Mate day 0.06 151.44 9.09 L-12

Mazdoor day 1.00 136.69 136.69 L-13

Mazdoor (Skilled) day 0.50 164.69 82.35 L-15

b) Material

each. 1.00 15000.00 15000.00 M-066

150.00

c) Overhead charges @ 0.2 on (a+b) 3075.62

d) Contractor's profit @ 0.1 on (a+b+c) 1845.37

cost for 19200cc of elastomeric bearing = a+b+c+d 20299.12

Rate per cc of elastomeric bearing = (a+b+c+d)/19200 1.06

say 1.00

13.15

Unit: one tonne capacity

a) Labour

2000 & 2200

Supplying, fitting and fixing in position true to line and level sliding plate bearing with PTFE surface sliding on stainless steel complete including all accessories as per drawing and Technical Specifications and BS: 5400, section 9.1 & 9.2 (for PTFE) and clause 2004 of MoRTH Specifications.

PTFE sliding plate bearing assembly of 80 tonnes design load capacity duly painted complete with all its components as per drawing and Technical Specifications

Add 1 per cent for foundation anchorage bolts and consumables.

2000 & 2200

Supplying, fitting and fixing in position true to line and level elastomeric bearing conforming to IRC: 83 (Part-II) section IX and clause 2005 of MoRTH specifications complete including all accessories as per drawing and Technical Specifications.

Considering an elastomeric bearing of size 500 x 400 x 96 mm for this analysis.

Volume of 6 nos. 488 x 388 x 4 mm size reinforcing steel plates = 4545 cu.cm.

Elastomeric bearing assembly consisting of 7 layers of elastomer bonded to 6 nos. internal reinforcing steel laminates by the process of vulcanisation, complete with all components as per drawing and Technical Specifications.

Add 1 per cent of cost of bearing assembly for foundation anchorage bolts and consumables.

2000 & 2200

Supplying, fitting and fixing in position true to line and level sliding plate bearing with stainless steel plate sliding on stainless steel plate with mild steel matrix complete including all accessories as per drawing and Technical Specifications.

Considering the sliding bearing of 80 tonnes design capacity for this analysis.

Page 247: Standard Data Book - Rate Analysis

Page 16 of 280

Sr No Description Unit Quantity Rate Rs Cost RsRef. to MoRTH Spec.

Remarks/ Input ref.

Mate day 0.04 151.44 6.06 L-12

Mazdoor day 0.75 136.69 102.52 L-13

Mazdoor (Skilled) day 0.35 164.69 57.64 L-15

b) Material

each. 1.00 16378.00 16378.00 M-070

163.78

c) Overhead charges @ 0.2 on (a+b) 3341.60

d) Contractor's profit @ 0.1 on (a+b+c) 2004.96

cost for 80 tonnes of capacity bearing = a+b+c+d 22054.56

275.68

say 276.00

13.16

Unit: one tonne capacity 387.20

a) Labour

Mate day 0.08 151.44 12.12 L-12

Mazdoor day 1.50 136.69 205.04 L-13

Mazdoor (Skilled) day 0.50 164.69 82.35 L-15

b) Material

each. 1.00 41309.00 41309.00 M-068

413.09

c) Overhead charges @ 0.2 on (a+b) 8404.32

d) Contractor's profit @ 0.1 on (a+b+c) 5042.59

cost for 250 tonnes capacity bearing = a+b+c+d 55468.49

Rate per tonne capacity = (a+b+c+d)/250 221.87

say 222.00

Supply of sliding plate bearing of 80 tonne design capacity complete as per drawings and Technical Specifications.

Add 1 per cent of cost of bearing assembly for foundation anchorage bolts and consumables.

2000 & 2200

Supplying, fitting and fixing in position true to line and level POT-PTFE bearing consisting of a metal piston supported by a disc or unreinforced elastomer confined within a metal cylinder, sealing rings, dust seals, PTFE surface sliding against stainless steel mating surface, complete assembly to be of cast steel/fabricated structural steel, metal and elastomer elements to be as per IRC: 83 part-I & II respectively and other parts conforming to BS: 5400, section 9.1 & 9.2 and clause 2006 of MoRTH Specifications complete as per drawing and approved Technical Specifications.

Considering a Pot bearing assembly of 250 tonne capacity for this analysis.

Pot type bearing assembly consisting of a metal piston supported by a disc, PTFE pads providing sliding surfaces against stainless steel mating together with cast steel assemblies/fabricated structural steel assemblies duly painted with all components as per clause 2006 and complete as per drawings and Technical Specifications.

Add 1 per cent of cost of bearing assembly for foundation anchorage bolts and consumables.

Page 248: Standard Data Book - Rate Analysis

Page 1 of 280

CHAPTER-14SUPER-STRUCTURE

Sr No Description Unit Quantity Rate Rs Cost Rs

14.1

A RCC Grade M20

Case I Using Concrete Mixer

Unit = 1 cum

Taking output = 15 cum

a) Material

Cement tonne 5.12 5000.00 25600.00 M-081

Coarse sand cum 6.75 710.46 4795.61 M-005

20 mm Aggregate cum 8.10 1028.00 8326.80 M-053

10 mm Aggregate cum 5.40 1005.00 5427.00 M-051

b) Labour

Mate day 0.86 151.44 130.24 L-12

Mason day 1.50 223.36 335.04 L-11

Mazdoor day 20.00 136.69 2733.80 L-13

c) Machinery

Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009

Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079

51188.00

For formwork and staging add the following:

(i)

(p) Height upto 5m

51188.00

d) Formwork and staging 20 per cent of (a+b+c) 20.00 10237.60

e) Overhead charges @ 0.2 on (a+b+c+d) 12285.12

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 7371.07

Cost for 15 cum = a+b+c+d+e+f 81081.79

Rate per cum = (a+b+c+d+e+f)/15 5405.45

say 5405.00

(q) Height 5m to 10m

51188.00

d) Formwork and staging 25 per cent of (a+b+c) 25.00 12797.00

e) Overhead charges @ 0.2 on (a+b+c+d) 12797.00

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 7678.20

Cost for 15 cum = a+b+c+d+e+f 84460.20

Rate per cum = (a+b+c+d+e+f)/15 5630.68

say 5631.00

(r) Height above 10m

51188.00

d) Formwork and staging 30 per cent of (a+b+c) 30.00 15356.40

e) Overhead charges @ 0.2 on (a+b+c+d) 13308.88

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 7985.33

Cost for 15 cum = a+b+c+d+e+f 87838.61

Rate per cum = (a+b+c+d+e+f)/15 5855.91

say 5856.00

(ii) For T-beam & slab, 25-35 per cent of (a+b+c)

(p) Height upto 5m

Ref. to MoRTH Spec.

Remarks/ Input ref.

1500 &1600 1700

Furnishing and Placing Reinforced/ Prestressed cement concrete in super-structure as per drawing and Technical Specification

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

14.1A Case I

For solid slab super-structure, 20-30 per cent of (a+b+c)

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

14.1A Case I (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

14.1A Case I (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

14.1A Case I

Page 249: Standard Data Book - Rate Analysis

Page 2 of 280

51188.00

d) Formwork and staging 25 per cent of (a+b+c) 25.00 12797.00

e) Overhead charges @ 0.2 on (a+b+c+d) 12797.00

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 7678.20

Cost for 15 cum = a+b+c+d+e+f 84460.20

Rate per cum = (a+b+c+d+e+f)/15 5630.68

say 5631.00

(q) Height 5m to 10m

51188.00

d) Formwork and staging 30 per cent of (a+b+c) 30.00 15356.40

e) Overhead charges @ 0.2 on (a+b+c+d) 13308.88

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 7985.33

Cost for 15 cum = a+b+c+d+e+f 87838.61

Rate per cum = (a+b+c+d+e+f)/15 5855.91

say 5856.00

(r) Height above 10m

51188.00

d) Formwork and staging 35 per cent of (a+b+c) 35.00 17915.80

e) Overhead charges @ 0.2 on (a+b+c+d) 13820.76

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 8292.46

Cost for 15 cum = a+b+c+d+e+f 91217.02

Rate per cum = (a+b+c+d+e+f)/15 6081.13

say 6081.00

14.1A Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum

Taking output = 120 cum

a) Material

Cement tonne 40.92 5000.00 204600.00 M-081

Coarse sand cum 54.00 828.00 44712.00 M-004

20 mm Aggregate cum 64.80 1028.00 66614.40 M-053

10 mm Aggregate cum 43.20 1005.00 43416.00 M-051

b) Labour

Mate day 0.84 151.44 127.21 L-12

Mason day 3.00 223.36 670.08 L-11

Mazdoor day 18.00 136.69 2460.42 L-13

c) Machinery

Batching Plant @ 20 cum/hour hour 6.00 2232.00 13392.00 P&M-002

Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080

Loader hour 6.00 806.00 4836.00 P&M-017

Transit Mixer ( capacity 4.0 cu.m )

Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 1017.00 15255.00 P&M-049

Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 2.03 610.20

Concrete Pump hour 6.00 256.00 1536.00 P&M-007

402806.00

For formwork and staging add the following:

(i)

(p) Height upto 5m

402806.00

d) Formwork and staging 20 per cent of (a+b+c) 20.00 80561.20

e) Overhead charges @ 0.2 on (a+b+c+d) 96673.44

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

14.1A Case I

(ii)

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

14.1A Case I

(ii)

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

Lead =1 km & P&M-

050

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1A Case II

For solid slab super-structure, 20-30 per cent of (a+b+c)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

Page 250: Standard Data Book - Rate Analysis

Page 3 of 280

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 58004.06

Cost for 120 cum = a+b+c+d+e+f 638044.70

Rate per cum = (a+b+c+d+e+f)/120 5317.04

say 5317.00

(q) Height 5m to 10m

402806.00

d) Formwork and staging 25 per cent of (a+b+c) 25.00 100701.50

e) Overhead charges @ 0.2 on (a+b+c+d) 100701.50

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 60420.90

Cost for 120 cum = a+b+c+d+e+f 664629.90

Rate per cum = (a+b+c+d+e+f)/120 5538.58

say 5539.00

(r) Height above 10m

402806.00

d) Formwork and staging 30 per cent of (a+b+c) 30.00 120841.80

e) Overhead charges @ 0.2 on (a+b+c+d) 104729.56

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 62837.74

Cost for 120 cum = a+b+c+d+e+f 691215.10

Rate per cum = (a+b+c+d+e+f)/120 5760.13

say 5760.00

(ii) For T-beam & slab, 25-35 per cent of (a+b+c)

(p) Height upto 5m

402806.00

d) Formwork and staging 25 per cent of (a+b+c) 25.00 100701.50

e) Overhead charges @ 0.2 on (a+b+c+d) 100701.50

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 60420.90

Cost for 120 cum = a+b+c+d+e+f 664629.90

Rate per cum = (a+b+c+d+e+f)/120 5538.58

say 5539.00

(q) Height 5m to 10m

402806.00

d) Formwork and staging 30 per cent of (a+b+c) 30.00 120841.80

e) Overhead charges @ 0.2 on (a+b+c+d) 104729.56

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 62837.74

Cost for 120 cum = a+b+c+d+e+f 691215.10

Rate per cum = (a+b+c+d+e+f)/120 5760.13

say 5760.00

(r)

Height above 10m 402806.00

35.00 140982.10

d) Formwork and staging 35 per cent of (a+b+c) 108757.62

e) Overhead charges @ 0.2 on (a+b+c+d) 65254.57

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 717800.29

Cost for 120 cum = a+b+c+d+e+f 5981.67

Rate per cum = (a+b+c+d+e+f)/120 say 5982.00

14.1 B

Case I RCC Grade M25

Using Concrete Mixer

Unit = 1 cum

14.1A Case II

(i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1A Case II

(i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1A Case II

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1A Case II

(ii)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1A Case II

(ii)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

Page 251: Standard Data Book - Rate Analysis

Page 4 of 280

Taking output = 15 cum

a) Material tonne 5.99 5000.00 29950.00 M-081

Cement cum 6.75 710.46 4795.61 M-005

Coarse sand cum 8.10 1028.00 8326.80 M-053

20 mm Aggregate cum 5.40 1005.00 5427.00 M-051

10 mm Aggregate

b) Labour day 0.86 151.44 130.24 L-12

Mate day 1.50 223.36 335.04 L-11

Mason day 20.00 136.69 2733.80 L-13

Mazdoor

c) Machinery hour 6.00 233.00 1398.00 P&M-009

Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 406.80 2440.80 P&M-079

Generator 33 KVA 55538.00

(i) For formwork and staging add the following:

(p)

Height upto 5m 55538.00

20.00 11107.60

d) Formwork and staging 20 per cent of (a+b+c) 13329.12

e) Overhead charges @ 0.2 on (a+b+c+d) 7997.47

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 87972.19

Cost for 15 cum = a+b+c+d+e+f 5864.81

Rate per cum = (a+b+c+d+e+f)/15 say 5865.00

(q)

Height 5m to 10m 55538.00

25.00 13884.50

d) Formwork and staging 25 per cent of (a+b+c) 13884.50

e) Overhead charges @ 0.2 on (a+b+c+d) 8330.70

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 91637.70

Cost for 15 cum = a+b+c+d+e+f 6109.18

Rate per cum = (a+b+c+d+e+f)/15 say 6109.00

(r)

Height above 10m 55538.00

30.00 16661.40

d) Formwork and staging 30 per cent of (a+b+c) 14439.88

e) Overhead charges @ 0.2 on (a+b+c+d) 8663.93

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 95303.21

Cost for 15 cum = a+b+c+d+e+f 6353.55

Rate per cum = (a+b+c+d+e+f)/15 say 6354.00

(ii)

(p) For T-beam & slab, 25-35 per cent of (a+b+c)

Height upto 5m 55538.00

25.00 13884.50

d) Formwork and staging 25 per cent of (a+b+c) 13884.50

e) Overhead charges @ 0.2 on (a+b+c+d) 8330.70

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 91637.70

Cost for 15 cum = a+b+c+d+e+f 6109.18

Rate per cum = (a+b+c+d+e+f)/15 say 6109.00

(q)

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

14.1B Case I

For solid slab super-structure, 20-30 per cent of (a+b+c)

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

14.1B Case I (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

14.1B Case I (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

14.1B Case I

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

14.1B Case I

(ii)

Page 252: Standard Data Book - Rate Analysis

Page 5 of 280

Height 5m to 10m 55538.00

30.00 16661.40

d) Formwork and staging 30 per cent of (a+b+c) 14439.88

e) Overhead charges @ 0.2 on (a+b+c+d) 8663.93

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 95303.21

Cost for 15 cum = a+b+c+d+e+f 6353.55

Rate per cum = (a+b+c+d+e+f)/15 say 6354.00

(r)

Height above 10m 55538.00

35.00 19438.30

d) Formwork and staging 35 per cent of (a+b+c) 14995.26

e) Overhead charges @ 0.2 on (a+b+c+d) 8997.16

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 98968.72

Cost for 15 cum = a+b+c+d+e+f 6597.91

Rate per cum = (a+b+c+d+e+f)/15 say 6598.00

14.1B Case II

Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum

Taking output = 120 cum

a) Material tonne 47.95 5000.00 239750.00 M-081

Cement cum 54.20 828.00 44877.60 M-004

Coarse sand cum 64.80 1028.00 66614.40 M-053

20 mm Aggregate cum 43.20 1005.00 43416.00 M-051

10 mm Aggregate

b) Labour day 0.84 151.44 127.21 L-12

Mate day 3.00 223.36 670.08 L-11

Mason day 18.00 136.69 2460.42 L-13

Mazdoor

c) Machinery hour 6.00 2232.00 13392.00 P&M-002

Batching Plant @ 20 cum/hour hour 6.00 762.75 4576.50 P&M-080

Generator 100 KVA hour 6.00 806.00 4836.00 P&M-017

Loader

Transit Mixer ( capacity 4.0 cu.m ) hour 15.00 1017.00 15255.00 P&M-049

Transit Mixer 4 cum capacity lead upto1 Km tonne.km 300L 2.03 610.20

Lead beyond 1 Km, L - lead in Kilometer hour 6.00 256.00 1536.00 P&M-007

Concrete Pump 438122.00

(i) For formwork and staging add the following:

(p)

Height upto 5m 438122.00

20.00 87624.40

d) Formwork and staging 20 per cent of (a+b+c) 105149.28

e) Overhead charges @ 0.2 on (a+b+c+d) 63089.57

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 693985.25

Cost for 120 cum = a+b+c+d+e+f 5783.21

Rate per cum = (a+b+c+d+e+f)/120 say 5783.00

(q)

Height 5m to 10m 438122.00

25.00 109530.50

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

14.1B Case I

(ii)

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

Lead =1 km & P&M-

050

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1B Case II

For solid slab super-structure, 20-30 per cent of (a+b+c)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1B Case II

(i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

Page 253: Standard Data Book - Rate Analysis

Page 6 of 280

d) Formwork and staging 25 per cent of (a+b+c) 109530.50

e) Overhead charges @ 0.2 on (a+b+c+d) 65718.30

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 722901.30

Cost for 120 cum = a+b+c+d+e+f 6024.18

Rate per cum = (a+b+c+d+e+f)/120 say 6024.00

(r)

Height above 10m 438122.00

30.00 131436.60

d) Formwork and staging 30 per cent of (a+b+c) 113911.72

e) Overhead charges @ 0.2 on (a+b+c+d) 68347.03

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 751817.35

Cost for 120 cum = a+b+c+d+e+f 6265.14

Rate per cum = (a+b+c+d+e+f)/120 say 6265.00

(ii)

(p) For T-beam & slab, 25-35 per cent of (a+b+c)

Height upto 5m 438122.00

25.00 109530.50

d) Formwork and staging 25 per cent of (a+b+c) 109530.50

e) Overhead charges @ 0.2 on (a+b+c+d) 65718.30

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 722901.30

Cost for 120 cum = a+b+c+d+e+f 6024.18

Rate per cum = (a+b+c+d+e+f)/120 say 6024.00

(q)

Height 5m to 10m 438122.00

30.00 131436.60

d) Formwork and staging 30 per cent of (a+b+c) 113911.72

e) Overhead charges @ 0.2 on (a+b+c+d) 68347.03

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 751817.35

Cost for 120 cum = a+b+c+d+e+f 6265.14

Rate per cum = (a+b+c+d+e+f)/120 say 6265.00

(r)

Height above 10m 438122.00

35.00 153342.70

d) Formwork and staging 35 per cent of (a+b+c) 118292.94

e) Overhead charges @ 0.2 on (a+b+c+d) 70975.76

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 780733.40

Cost for 120 cum = a+b+c+d+e+f 6506.11

Rate per cum = (a+b+c+d+e+f)/120 say 6506.00

14.1 C

Case I RCC Grade M 30

Using Concrete Mixer

Unit = 1 cum

Taking output = 15 cum

a) Material tonne 6.10 5000.00 30500.00 M-081

Cement cum 6.75 710.46 4795.61 M-005

Coarse sand cum 8.10 1028.00 8326.80 M-053

20 mm Aggregate cum 5.40 1005.00 5427.00 M-051

10 mm Aggregate

b) Labour day 0.90 151.44 136.30 L-12

Mate day 1.50 223.36 335.04 L-11

Mason day 21.00 136.69 2870.49 L-13

14.1B Case II

(i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1B Case II

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1B Case II

(ii)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1B Case II

(ii)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

Page 254: Standard Data Book - Rate Analysis

Page 7 of 280

Mazdoor

c) Machinery hour 6.00 233.00 1398.00 P&M-009

Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 406.80 2440.80 P&M-079

Generator 33 KVA 56231.00

(i) For formwork and staging add the following:

(p)

Height upto 5m 56231.00

20.00 11246.20

d) Formwork and staging 20 per cent of (a+b+c) 13495.44

e) Overhead charges @ 0.2 on (a+b+c+d) 8097.26

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 89069.90

Cost for 15 cum = a+b+c+d+e+f 5937.99

Rate per cum = (a+b+c+d+e+f)/15 say 5938.00

(q)

Height 5m to 10m 56231.00

25.00 14057.75

d) Formwork and staging 25 per cent of (a+b+c) 14057.75

e) Overhead charges @ 0.2 on (a+b+c+d) 8434.65

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 92781.15

Cost for 15 cum = a+b+c+d+e+f 6185.41

Rate per cum = (a+b+c+d+e+f)/15 say 6185.00

(r)

Height above 10m 56231.00

30.00 16869.30

d) Formwork and staging 30 per cent of (a+b+c) 14620.06

e) Overhead charges @ 0.2 on (a+b+c+d) 8772.04

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 96492.40

Cost for 15 cum = a+b+c+d+e+f 6432.83

Rate per cum = (a+b+c+d+e+f)/15 say 6433.00

(ii)

(p) For T-beam & slab, 25-35 per cent of (a+b+c)

Height upto 5m 56231.00

25.00 14057.75

d) Formwork and staging 25 per cent of (a+b+c) 14057.75

e) Overhead charges @ 0.2 on (a+b+c+d) 8434.65

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 92781.15

Cost for 15 cum = a+b+c+d+e+f 6185.41

Rate per cum = (a+b+c+d+e+f)/15 say 6185.00

(q)

Height 5m to 10m 56231.00

30.00 16869.30

d) Formwork and staging 30 per cent of (a+b+c) 14620.06

e) Overhead charges @ 0.2 on (a+b+c+d) 8772.04

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 96492.40

Cost for 15 cum = a+b+c+d+e+f 6432.83

Rate per cum = (a+b+c+d+e+f)/15 say 6433.00

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

14.1C Case I

For solid slab super-structure, 20-30 per cent of (a+b+c)

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

14.1C Case I (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

14.1C Case I (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

14.1C Case I

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

14.1C Case I

(ii)

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

Page 255: Standard Data Book - Rate Analysis

Page 8 of 280

(r)

Height above 10m 56231.00

35.00 19680.85

d) Formwork and staging 35 per cent of (a+b+c) 15182.37

e) Overhead charges @ 0.2 on (a+b+c+d) 9109.42

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 100203.64

Cost for 15 cum = a+b+c+d+e+f 6680.24

Rate per cum = (a+b+c+d+e+f)/15 say 6680.00

14.1C Case II

Using Batching Plant, Transit Mixer and Concrete Pump.

Unit = cum

Taking output = 120 cum

a) Material tonne 48.79 5000.00 243950.00 M-081

Cement cum 54.60 828.00 45208.80 M-004

Coarse sand cum 64.80 1028.00 66614.40 M-053

20 mm Aggregate cum 43.20 1005.00 43416.00 M-051

10 mm Aggregate

b) Labour day 0.88 151.44 133.27 L-12

Mate day 3.00 223.36 670.08 L-11

Mason day 19.00 136.69 2597.11 L-13

Mazdoor

c) Machinery hour 6.00 2232.00 13392.00 P&M-002

Batching Plant @ 20 cum/hour hour 6.00 762.75 4576.50 P&M-080

Generator 100 KVA hour 6.00 806.00 4836.00 P&M-017

Loader

Transit Mixer ( capacity 4.0 cu.m ) hour 15.00 1017.00 15255.00 P&M-049

Transit Mixer 4 cum capacity lead upto1 Km tonne.km 300L 2.03 610.20

Lead beyond 1 Km, L - lead in Kilometer hour 6.00 256.00 1536.00 P&M-007

Concrete Pump 442796.00

(i) For formwork and staging add the following:

(p)

Height upto 5m 442796.00

20.00 88559.20

d) Formwork and staging 20 per cent of (a+b+c) 106271.04

e) Overhead charges @ 0.2 on (a+b+c+d) 63762.62

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 701388.86

Cost for 120 cum = a+b+c+d+e+f 5844.91

Rate per cum = (a+b+c+d+e+f)/120 say 5845.00

(q)

Height 5m to 10m 442796.00

25.00 110699.00

d) Formwork and staging 25 per cent of (a+b+c) 110699.00

e) Overhead charges @ 0.2 on (a+b+c+d) 66419.40

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 730613.40

Cost for 120 cum = a+b+c+d+e+f 6088.45

Rate per cum = (a+b+c+d+e+f)/120 say 6088.00

(r)

Height above 10m 442796.00

14.1C Case I

(ii)

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

Lead =1 km & P&M-

050

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1C Case II

For solid slab super-structure, 20-30 per cent of (a+b+c)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1C Case II

(i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1C Case II

(i)

Page 256: Standard Data Book - Rate Analysis

Page 9 of 280

30.00 132838.80

d) Formwork and staging 30 per cent of (a+b+c) 115126.96

e) Overhead charges @ 0.2 on (a+b+c+d) 69076.18

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 759837.94

Cost for 120 cum = a+b+c+d+e+f 6331.98

Rate per cum = (a+b+c+d+e+f)/120 say 6332.00

(ii)

(p) For T-beam & slab, 25-35 per cent of (a+b+c)

Height upto 5m 442796.00

25.00 110699.00

d) Formwork and staging 25 per cent of (a+b+c) 110699.00

e) Overhead charges @ 0.2 on (a+b+c+d) 66419.40

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 730613.40

Cost for 120 cum = a+b+c+d+e+f 6088.45

Rate per cum = (a+b+c+d+e+f)/120 say 6088.00

(q)

Height 5m to 10m 442796.00

30.00 132838.80

d) Formwork and staging 30 per cent of (a+b+c) 115126.96

e) Overhead charges @ 0.2 on (a+b+c+d) 69076.18

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 759837.94

Cost for 120 cum = a+b+c+d+e+f 6331.98

Rate per cum = (a+b+c+d+e+f)/120 say 6332.00

(r)

Height above 10m 442796.00

35.00 154978.60

d) Formwork and staging 35 per cent of (a+b+c) 119554.92

e) Overhead charges @ 0.2 on (a+b+c+d) 71732.95

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 789062.47

Cost for 120 cum = a+b+c+d+e+f 6575.52

Rate per cum = (a+b+c+d+e+f)/120 say 6576.00

14.1 D

Case I RCC/PSC Grade M35

Using Concrete Mixer.

Unit = 1 cum

Taking output = 15 cum

a) Material tonne 6.33 5000.00 31650.00 M-081

Cement cum 6.75 710.46 4795.61 M-005

Coarse sand cum 8.10 1028.00 8326.80 M-053

20 mm Aggregate cum 5.40 1005.00 5427.00 M-051

10 mm Aggregate

b) Labour day 0.90 151.44 136.30 L-12

Mate day 1.50 223.36 335.04 L-11

Mason day 21.00 136.69 2870.49 L-13

Mazdoor

c) Machinery hour 6.00 233.00 1398.00 P&M-009

Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 406.80 2440.80 P&M-079

Generator 33 KVA 57381.00

(i) For formwork and staging add the following:

(p)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1C Case II

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1C Case II

(ii)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1C Case II

(ii)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

14.1D Case I

For solid slab super-structure, 18-28 per cent of (a+b+c)

Page 257: Standard Data Book - Rate Analysis

Page 10 of 280

Height upto 5m 57381.00

18.00 10328.58

d) Formwork and staging 18 per cent of (a+b+c) 13541.92

e) Overhead charges @ 0.2 on (a+b+c+d) 8125.15

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 89376.65

Cost for 15 cum = a+b+c+d+e+f 5958.44

Rate per cum = (a+b+c+d+e+f)/15 say 5958.00

(q)

Height 5m to 10m 57381.00

23.00 13197.63

d) Formwork and staging 23 per cent of (a+b+c) 14115.73

e) Overhead charges @ 0.2 on (a+b+c+d) 8469.44

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 93163.79

Cost for 15 cum = a+b+c+d+e+f 6210.92

Rate per cum = (a+b+c+d+e+f)/15 say 6211.00

(r)

Height above 10m 57381.00

28.00 16066.68

d) Formwork and staging 28 per cent of (a+b+c) 14689.54

e) Overhead charges @ 0.2 on (a+b+c+d) 8813.72

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 96950.94

Cost for 15 cum = a+b+c+d+e+f 6463.40

Rate per cum = (a+b+c+d+e+f)/15 say 6463.00

(ii)

(p) For T-beam & slab, 23-33 per cent of (a+b+c)

Height upto 5m 57381.00

23.00 13197.63

d) Formwork and staging 23 per cent of (a+b+c) 14115.73

e) Overhead charges @ 0.2 on (a+b+c+d) 8469.44

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 93163.79

Cost for 15 cum = a+b+c+d+e+f 6210.92

Rate per cum = (a+b+c+d+e+f)/15 say 6211.00

(q)

Height 5m to 10m 57381.00

28.00 16066.68

d) Formwork and staging 28 per cent of (a+b+c) 14689.54

e) Overhead charges @ 0.2 on (a+b+c+d) 8813.72

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 96950.94

Cost for 15 cum = a+b+c+d+e+f 6463.40

Rate per cum = (a+b+c+d+e+f)/15 say 6463.00

(r)

Height above 10m 57381.00

33.00 18935.73

d) Formwork and staging 33 per cent of (a+b+c) 15263.35

e) Overhead charges @ 0.2 on (a+b+c+d) 9158.01

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 100738.08

Cost for 15 cum = a+b+c+d+e+f 6715.87

Rate per cum = (a+b+c+d+e+f)/15 say 6716.00

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

14.1D Case I (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

14.1D Case I (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

14.1D Case I

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

14.1D Case I

(ii)

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

14.1D Case I

(ii)

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

Page 258: Standard Data Book - Rate Analysis

Page 11 of 280

(iii)

(p)

Height upto 5m 57381.00

38.00 21804.78

d) Formwork and staging 38 per cent of (a+b+c) 15837.16

e) Overhead charges @ 0.2 on (a+b+c+d) 9502.29

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 104525.23

Cost for 15 cum = a+b+c+d+e+f 6968.35

Rate per cum = (a+b+c+d+e+f)/15 say 6968.00

(q)

Height 5m to 10m 57381.00

48.00 27542.88

d) Formwork and staging 48 per cent of (a+b+c) 16984.78

e) Overhead charges @ 0.2 on (a+b+c+d) 10190.87

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 112099.52

Cost for 15 cum = a+b+c+d+e+f 7473.30

Rate per cum = (a+b+c+d+e+f)/15 say 7473.00

(r)

Height above 10m 57381.00

58.00 33280.98

d) Formwork and staging 58 per cent of (a+b+c) 18132.40

e) Overhead charges @ 0.2 on (a+b+c+d) 10879.44

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 119673.81

Cost for 15 cum = a+b+c+d+e+f 7978.25

Rate per cum = (a+b+c+d+e+f)/15 say 7978.00

Case II

Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum

Taking output = 120 cum

a) Material tonne 50.64 5000.00 253200.00 M-081

Cement cum 54.00 828.00 44712.00 M-004

Coarse sand cum 64.80 1028.00 66614.40 M-053

20 mm Aggregate cum 43.20 1005.00 43416.00 M-051

10 mm Aggregate

b) Labour day 0.88 151.44 133.27 L-12

Mate day 3.00 223.36 670.08 L-11

Mason day 19.00 136.69 2597.11 L-13

Mazdoor

c) Machinery hour 6.00 2232.00 13392.00 P&M-002

Batching Plant @ 20 cum/hour hour 6.00 762.75 4576.50 P&M-080

Generator 100 KVA hour 6.00 806.00 4836.00 P&M-017

Loader

Transit Mixer ( capacity 4.0 cu.m ) hour 15.00 1017.00 15255.00 P&M-049

Transit Mixer 4 cum capacity lead upto1 Km tonne.km 300L 2.03 610.20

Lead beyond 1 Km, L - lead in Kilometer hour 6.00 256.00 1536.00 P&M-007

Concrete Pump 451549.00

(i) For formwork and staging add the following:

(p)

14.1D Case I

For box girder and balanced cantilever, 38-58 per cent of cost of concrete.

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

14.1D Case I

(iii)

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

14.1D Case I

(iii)

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

Lead =1 km & P&M-

050

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1D Case II

For solid slab super-structure, 18-28 per cent of (a+b+c)

Page 259: Standard Data Book - Rate Analysis

Page 12 of 280

Height upto 5m 451549.00

18.00 81278.82

d) Formwork and staging 18 per cent of (a+b+c) 106565.56

e) Overhead charges @ 0.2 on (a+b+c+d) 63939.34

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 703332.72

Cost for 120 cum = a+b+c+d+e+f 5861.11

Rate per cum = (a+b+c+d+e+f)/120 say 5861.00

(q)

Height 5m to 10m 451549.00

23.00 103856.27

d) Formwork and staging 23 per cent of (a+b+c) 111081.05

e) Overhead charges @ 0.2 on (a+b+c+d) 66648.63

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 733134.96

Cost for 120 cum = a+b+c+d+e+f 6109.46

Rate per cum = (a+b+c+d+e+f)/120 say 6109.00

(r)

Height above 10m 451549.00

28.00 126433.72

d) Formwork and staging 28 per cent of (a+b+c) 115596.54

e) Overhead charges @ 0.2 on (a+b+c+d) 69357.93

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 762937.19

Cost for 120 cum = a+b+c+d+e+f 6357.81

Rate per cum = (a+b+c+d+e+f)/120 say 6358.00

(ii)

(p) For T-beam & slab, 23-33 per cent of (a+b+c)

Height upto 5m 451549.00

23.00 103856.27

d) Formwork and staging 23 per cent of (a+b+c) 111081.05

e) Overhead charges @ 0.2 on (a+b+c+d) 66648.63

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 733134.96

Cost for 120 cum = a+b+c+d+e+f 6109.46

Rate per cum = (a+b+c+d+e+f)/120 say 6109.00

(q)

Height 5m to 10m 451549.00

28.00 126433.72

d) Formwork and staging 28 per cent of (a+b+c) 115596.54

e) Overhead charges @ 0.2 on (a+b+c+d) 69357.93

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 762937.19

Cost for 120 cum = a+b+c+d+e+f 6357.81

Rate per cum = (a+b+c+d+e+f)/120 say 6358.00

(r)

Height above 10m 451549.00

33.00 149011.17

d) Formwork and staging 33 per cent of (a+b+c) 120112.03

e) Overhead charges @ 0.2 on (a+b+c+d) 72067.22

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 792739.42

Cost for 120 cum = a+b+c+d+e+f 6606.16

Rate per cum = (a+b+c+d+e+f)/120 say 6606.00

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1D Case II

(i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1D Case II

(i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1D Case II

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1D Case II

(ii)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1D Case II

(ii)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

Page 260: Standard Data Book - Rate Analysis

Page 13 of 280

(iii)

(p)

Height upto 5m 451549.00

38.00 171588.62

d) Formwork and staging 38 per cent of (a+b+c) 124627.52

e) Overhead charges @ 0.2 on (a+b+c+d) 74776.51

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 822541.66

Cost for 120 cum = a+b+c+d+e+f 6854.51

Rate per cum = (a+b+c+d+e+f)/120 say 6855.00

(q)

Height 5m to 10m 451549.00

48.00 216743.52

d) Formwork and staging 48 per cent of (a+b+c) 133658.50

e) Overhead charges @ 0.2 on (a+b+c+d) 80195.10

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 882146.13

Cost for 120 cum = a+b+c+d+e+f 7351.22

Rate per cum = (a+b+c+d+e+f)/120 say 7351.00

(r)

Height above 10m 451549.00

58.00 261898.42

d) Formwork and staging 58 per cent of (a+b+c) 142689.48

e) Overhead charges @ 0.2 on (a+b+c+d) 85613.69

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 941750.59

Cost for 120 cum = a+b+c+d+e+f 7847.92

Rate per cum = (a+b+c+d+e+f)/120 say 7848.00

14.1 E

Case 1 PSC Grade M-40

Using concrete mixer.

Unit = 1 cum

Taking output = 15 cum

a) Material tonne 6.45 5000.00 32250.00 M-081

Cement cum 6.75 710.46 4795.61 M-005

Coarse sand cum 8.10 1028.00 8326.80 M-053

20 mm Aggregate cum 5.40 1005.00 5427.00 M-051

10 mm Aggregate kg 25.80 44.70 1153.26 M-180

Admixture @ 0.4 per cent of cement

b) Labour day 0.96 151.44 145.38 L-12

Mate day 2.00 223.36 446.72 L-11

Mason day 22.00 136.69 3007.18 L-13

Mazdoor

c) Machinery hour 6.00 233.00 1398.00 P&M-009

Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 406.80 2440.80 P&M-079

Generator 33 KVA 59391.00

(i) For formwork and staging add the following:

(p)

Height upto 5m 59391.00

20.00 11878.20

d) Formwork and staging 20 per cent of (a+b+c) 14253.84

e) Overhead charges @ 0.2 on (a+b+c+d) 8552.30

14.1D Case II

For box girder and balanced cantilever, 38-58 per cent of cost of concrete.

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1D Case II

(iii)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1D Case II

(iii)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

14.1E Case I

For solid slab super-structure, 20-30 per cent of (a+b+c)

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

Page 261: Standard Data Book - Rate Analysis

Page 14 of 280

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 94075.34

Cost for 15 cum = a+b+c+d+e+f 6271.69

Rate per cum = (a+b+c+d+e+f)/15 say 6272.00

(q)

Height 5m to 10m 59391.00

25.00 14847.75

d) Formwork and staging 25 per cent of (a+b+c) 14847.75

e) Overhead charges @ 0.2 on (a+b+c+d) 8908.65

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 97995.15

Cost for 15 cum = a+b+c+d+e+f 6533.01

Rate per cum = (a+b+c+d+e+f)/15 say 6533.00

(r)

Height above 10m 59391.00

30.00 17817.30

d) Formwork and staging 30 per cent of (a+b+c) 15441.66

e) Overhead charges @ 0.2 on (a+b+c+d) 9265.00

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 101914.96

Cost for 15 cum = a+b+c+d+e+f 6794.33

Rate per cum = (a+b+c+d+e+f)/15 say 6794.00

(ii)

(p) For T-beam & slab, 25-35 per cent of (a+b+c)

Height upto 5m 59391.00

25.00 14847.75

d) Formwork and staging 25 per cent of (a+b+c) 14847.75

e) Overhead charges @ 0.2 on (a+b+c+d) 8908.65

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 97995.15

Cost for 15 cum = a+b+c+d+e+f 6533.01

Rate per cum = (a+b+c+d+e+f)/15 say 6533.00

(q)

Height 5m to 10m 59391.00

30.00 17817.30

d) Formwork and staging 30 per cent of (a+b+c) 15441.66

e) Overhead charges @ 0.2 on (a+b+c+d) 9265.00

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 101914.96

Cost for 15 cum = a+b+c+d+e+f 6794.33

Rate per cum = (a+b+c+d+e+f)/15 say 6794.00

(r)

Height above 10m 59391.00

35.00 20786.85

d) Formwork and staging 35 per cent of (a+b+c) 16035.57

e) Overhead charges @ 0.2 on (a+b+c+d) 9621.34

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 105834.76

Cost for 15 cum = a+b+c+d+e+f 7055.65

Rate per cum = (a+b+c+d+e+f)/15 say 7056.00

14.1E Case II

Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum

Taking output = 120 cum

a) Material tonne 51.60 5000.00 258000.00 M-081

14.1E Case I (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

14.1E Case I (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

14.1E Case I

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

14.1E Case I

(ii)

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

14.1E Case I

(ii)

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum

Page 262: Standard Data Book - Rate Analysis

Page 15 of 280

Cement cum 54.00 828.00 44712.00 M-004

Coarse sand cum 64.80 1028.00 66614.40 M-053

20 mm Aggregate cum 43.20 1005.00 43416.00 M-051

10 mm Aggregate kg 206.40 44.70 9226.08 M-180

Admixture @ 0.4 per cent of cement

b) Labour day 0.94 151.44 142.35 L-12

Mate day 3.50 223.36 781.76 L-11

Mason day 20.00 136.69 2733.80 L-13

Mazdoor

c) Machinery hour 6.00 2232.00 13392.00 P&M-002

Batching Plant @ 20 cum/hour hour 6.00 762.75 4576.50 P&M-080

Generator 100 KVA hour 6.00 806.00 4836.00 P&M-017

Loader

Transit Mixer ( capacity 4.0 cu.m ) hour 15.00 1017.00 15255.00 P&M-049

Transit Mixer 4 cum capacity lead upto1 Km tonne.km 300L 2.03 610.20

Lead beyond 1 Km, L - lead in Kilometer hour 6.00 256.00 1536.00 P&M-007

Concrete Pump 465833.00

(i) For formwork and staging add the following:

(p)

Height upto 5m 465833.00

18.00 83849.94

d) Formwork and staging 18 per cent of (a+b+c) 109936.59

e) Overhead charges @ 0.2 on (a+b+c+d) 65961.95

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 725581.48

Cost for 15 cum = a+b+c+d+e+f 6046.51

Rate per cum = (a+b+c+d+e+f)/120 say 6047.00

(q)

Height 5m to 10m 465833.00

23.00 107141.59

d) Formwork and staging 23 per cent of (a+b+c) 114594.92

e) Overhead charges @ 0.2 on (a+b+c+d) 68756.95

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 756326.46

Cost for 120 cum = a+b+c+d+e+f 6302.72

Rate per cum = (a+b+c+d+e+f)/120 say 6303.00

(r)

Height above 10m 465833.00

28.00 130433.24

d) Formwork and staging 28 per cent of (a+b+c) 119253.25

e) Overhead charges @ 0.2 on (a+b+c+d) 71551.95

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 787071.44

Cost for 120 cum = a+b+c+d+e+f 6558.93

Rate per cum = (a+b+c+d+e+f)/120 say 6559.00

(ii)

(p) For T-beam & slab, 23-33 per cent of (a+b+c)

Height upto 5m 465833.00

23.00 107141.59

d) Formwork and staging 23 per cent of (a+b+c) 114594.92

e) Overhead charges @ 0.2 on (a+b+c+d) 68756.95

Lead =1 km & P&M-

050

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1E Case II

For solid/voided slab super-structure, 18-28 per cent of (a+b+c)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1E Case II

(i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1E Case II

(i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1E Case II

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

Page 263: Standard Data Book - Rate Analysis

Page 16 of 280

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 756326.46

Cost for 120 cum = a+b+c+d+e+f 6302.72

Rate per cum = (a+b+c+d+e+f)/120 say 6303.00

(q)

Height 5m to 10m 465833.00

28.00 130433.24

d) Formwork and staging 28 per cent of (a+b+c) 119253.25

e) Overhead charges @ 0.2 on (a+b+c+d) 71551.95

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 787071.44

Cost for 120 cum = a+b+c+d+e+f 6558.93

Rate per cum = (a+b+c+d+e+f)/120 say 6559.00

(r)

Height above 10m 465833.00

33.00 153724.89

d) Formwork and staging 33 per cent of (a+b+c) 123911.58

e) Overhead charges @ 0.2 on (a+b+c+d) 74346.95

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 817816.41

Cost for 120 cum = a+b+c+d+e+f 6815.14

Rate per cum = (a+b+c+d+e+f)/120 say 6815.00

(iii)

(p)

Height upto 5m 465833.00

38.00 177016.54

d) Formwork and staging 38 per cent of (a+b+c) 128569.91

e) Overhead charges @ 0.2 on (a+b+c+d) 77141.94

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 848561.39

Cost for 120 cum = a+b+c+d+e+f 7071.34

Rate per cum = (a+b+c+d+e+f)/120 say 7071.00

(q)

Height 5m to 10m 465833.00

48.00 223599.84

d) Formwork and staging 48 per cent of (a+b+c) 137886.57

e) Overhead charges @ 0.2 on (a+b+c+d) 82731.94

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 910051.35

Cost for 120 cum = a+b+c+d+e+f 7583.76

Rate per cum = (a+b+c+d+e+f)/120 say 7584.00

(r)

Height above 10m 465833.00

58.00 270183.14

d) Formwork and staging 58 per cent of (a+b+c) 147203.23

e) Overhead charges @ 0.2 on (a+b+c+d) 88321.94

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 971541.30

Cost for 120 cum = a+b+c+d+e+f 8096.18

Rate per cum = (a+b+c+d+e+f)/120 say 8096.00

14.1F F

PSC Grade M-45

Unit = 1 cum

Taking output = 120 cum

14.1E Case II

(ii)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1E Case II

(ii)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1E Case II

For cast-in-situ box girder, segment construction and balanced cantilever, 38-58 per cent of cost of concrete.

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1E Case II

(iii)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1E Case II

(iii)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

Page 264: Standard Data Book - Rate Analysis

Page 17 of 280

a) Material tonne 55.80 5000.00 279000.00 M-081

Cement cum 54.00 828.00 44712.00 M-004

Coarse sand cum 64.80 1028.00 66614.40 M-053

20 mm Aggregate cum 43.20 1005.00 43416.00 M-051

10 mm Aggregate kg 223.20 44.70 9977.04 M-180

Admixture @ 0.4 per cent of cement

b) Labour day 0.94 151.44 142.35 L-12

Mate day 3.50 223.36 781.76 L-11

Mason day 20.00 136.69 2733.80 L-13

Mazdoor

c) Machinery hour 6.00 2232.00 13392.00 P&M-002

Batching Plant @ 20 cum/hour hour 6.00 762.75 4576.50 P&M-080

Generator 100 KVA hour 6.00 806.00 4836.00 P&M-017

Loader

Transit Mixer ( capacity 4.0 cu.m ) hour 15.00 1017.00 15255.00 P&M-049

Transit Mixer 4 cum capacity lead upto1 Km tonne.km 300L 2.03 610.20

Lead beyond 1 Km, L - lead in Kilometer hour 6.00 256.00 1536.00 P&M-007

Concrete Pump 487584.00

14.1F (i) For formwork and staging add the following:

(p)

Height upto 5m 487584.00

16.00 78013.44

d) Formwork and staging 16 per cent of (a+b+c) 113119.49

e) Overhead charges @ 0.2 on (a+b+c+d) 67871.69

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 746588.62

Cost for 120 cum = a+b+c+d+e+f 6221.57

Rate per cum = (a+b+c+d+e+f)/120 say 6222.00

(q)

Height 5m to 10m 487584.00

21.00 102392.64

d) Formwork and staging 21 per cent of (a+b+c) 117995.33

e) Overhead charges @ 0.2 on (a+b+c+d) 70797.20

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 778769.16

Cost for 120 cum = a+b+c+d+e+f 6489.74

Rate per cum = (a+b+c+d+e+f)/120 say 6490.00

(r)

Height above 10m 487584.00

26.00 126771.84

d) Formwork and staging 26 per cent of (a+b+c) 122871.17

e) Overhead charges @ 0.2 on (a+b+c+d) 73722.70

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 810949.71

Cost for 120 cum = a+b+c+d+e+f 6757.91

Rate per cum = (a+b+c+d+e+f)/120 say 6758.00

14.1F (ii)

(p)

Height upto 5m 487584.00

21.00 102392.64

d) Formwork and staging 21 per cent of (a+b+c) 117995.33

e) Overhead charges @ 0.2 on (a+b+c+d) 70797.20

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 778769.16

Lead =1 km & P&M-

050

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

For solid slab/voided slab super-structure, 16-26 per cent of cost of concrete (a+b+c)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1F (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1F (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

For T-beam & slab including launching of precast girders by launching truss upto 40 m span, 21-31 per cent of cost of concrete.

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

Page 265: Standard Data Book - Rate Analysis

Page 18 of 280

Cost for 120 cum = a+b+c+d+e+f 6489.74

Rate per cum = (a+b+c+d+e+f)/120 say 6490.00

(q)

Height 5m to 10m 487584.00

26.00 126771.84

d) Formwork and staging 26 per cent of (a+b+c) 122871.17

e) Overhead charges @ 0.2 on (a+b+c+d) 73722.70

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 810949.71

Cost for 120 cum = a+b+c+d+e+f 6757.91

Rate per cum = (a+b+c+d+e+f)/120 say 6758.00

(r)

Height above 10m 487584.00

31.00 151151.04

d) Formwork and staging 31 per cent of (a+b+c) 127747.01

e) Overhead charges @ 0.2 on (a+b+c+d) 76648.20

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 843130.25

Cost for 120 cum = a+b+c+d+e+f 7026.09

Rate per cum = (a+b+c+d+e+f)/120 say 7026.00

14.1F (iii)

(p)

Height upto 5m 487584.00

36.00 175530.24

d) Formwork and staging 36 per cent of (a+b+c) 132622.85

e) Overhead charges @ 0.2 on (a+b+c+d) 79573.71

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 875310.80

Cost for 120 cum = a+b+c+d+e+f 7294.26

Rate per cum = (a+b+c+d+e+f)/120 say 7294.00

(q)

Height 5m to 10m 487584.00

46.00 224288.64

d) Formwork and staging 46 per cent of (a+b+c) 142374.53

e) Overhead charges @ 0.2 on (a+b+c+d) 85424.72

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 939671.88

Cost for 120 cum = a+b+c+d+e+f 7830.60

Rate per cum = (a+b+c+d+e+f)/120 say 7831.00

(r)

Height above 10m 487584.00

56.00 273047.04

d) Formwork and staging 56 per cent of (a+b+c) 152126.21

e) Overhead charges @ 0.2 on (a+b+c+d) 91275.72

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 1004032.97

Cost for 120 cum = a+b+c+d+e+f 8366.94

Rate per cum = (a+b+c+d+e+f)/120 say 8367.00

14.1 G

PSC Grade M-50

Unit = 1 cum

Taking output = 120 cum

a) Material tonne 58.80 5000.00 294000.00 M-081

Cement cum 54.00 828.00 44712.00 M-004

Coarse sand cum 64.80 1028.00 66614.40 M-053

20 mm Aggregate cum 43.20 1005.00 43416.00 M-051

10 mm Aggregate kg 235.20 44.70 10513.44 M-180

14.1F (ii)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1F (ii)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

For cast-in-situ box girder, segmental construction and balanced cantilever, 36-56 per cent of cost of concrete.

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1F (iii)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1F (iii)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

Page 266: Standard Data Book - Rate Analysis

Page 19 of 280

Admixture @ 0.4 per cent of cement

b) Labour day 0.94 151.44 142.35 L-12

Mate day 3.50 223.36 781.76 L-11

Mason day 20.00 136.69 2733.80 L-13

Mazdoor

c) Machinery hour 6.00 2232.00 13392.00 P&M-002

Batching Plant @ 20 cum/hour hour 6.00 762.75 4576.50 P&M-080

Generator 100 KVA hour 6.00 806.00 4836.00 P&M-017

Loader

Transit Mixer ( capacity 4.0 cu.m ) hour 15.00 1017.00 15255.00 P&M-049

Transit Mixer 4 cum capacity lead upto1 Km tonne.km 300L 2.03 610.20

Lead beyond 1 Km, L - lead in Kilometer hour 6.00 256.00 1536.00 P&M-007

Concrete Pump 503120.00

14.1G (i) For formwork and staging add the following:

(p)

Height upto 5m 503120.00

35.00 176092.00

d) Formwork and staging 35 per cent of (a+b+c) 135842.40

e) Overhead charges @ 0.2 on (a+b+c+d) 81505.44

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 896559.84

Cost for 120 cum = a+b+c+d+e+f 7471.33

Rate per cum = (a+b+c+d+e+f)/120 say 7471.00

(q)

Height 5m to 10m 503120.00

45.00 226404.00

d) Formwork and staging 45 per cent of (a+b+c) 145904.80

e) Overhead charges @ 0.2 on (a+b+c+d) 87542.88

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 962971.68

Cost for 120 cum = a+b+c+d+e+f 8024.76

Rate per cum = (a+b+c+d+e+f)/120 say 8025.00

(r)

Height above 10m 503120.00

55.00 276716.00

d) Formwork and staging 55 per cent of (a+b+c) 155967.20

e) Overhead charges @ 0.2 on (a+b+c+d) 93580.32

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 1029383.52

Cost for 120 cum = a+b+c+d+e+f 8578.20

Rate per cum = (a+b+c+d+e+f)/120 say 8578.00

14.1 H

PSC Grade M- 55

Unit = 1 cum

Taking output = 120 cum

a) Material tonne 63.50 5000.00 317500.00 M-081

Cement cum 54.00 828.00 44712.00 M-004

Coarse sand cum 64.80 1028.00 66614.40 M-053

20 mm Aggregate cum 43.20 1005.00 43416.00 M-051

10 mm Aggregate kg 254.00 44.70 11353.80 M-180

Admixture @ 0.4 per cent of cement

b) Labour day 0.94 151.44 142.35 L-12

Mate day 3.50 223.36 781.76 L-11

Mason day 20.00 136.69 2733.80 L-13

Lead =1 km & P&M-

050

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

For cast-in-situ box girder, segmental construction and balanced cantilever, 35-55 per cent of cost of concrete

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1G (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1G (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

Page 267: Standard Data Book - Rate Analysis

Page 20 of 280

Mazdoor

c) Machinery hour 6.00 2232.00 13392.00 P&M-002

Batching Plant @ 20 cum/hour hour 6.00 762.75 4576.50 P&M-080

Generator 100 KVA hour 6.00 806.00 4836.00 P&M-017

Loader

Transit Mixer ( capacity 4.0 cu.m ) hour 15.00 1017.00 15255.00 P&M-049

Transit Mixer 4 cum capacity lead upto1 Km tonne.km 300L 2.03 610.20

Lead beyond 1 Km, L - lead in Kilometer hour 6.00 256.00 1536.00 P&M-007

Concrete Pump 527460.00

14.1H (i) For formwork and staging add the following:

(p)

Height upto 5m 527460.00

35.00 184611.00

d) Formwork and staging 35 per cent of (a+b+c) 142414.20

e) Overhead charges @ 0.2 on (a+b+c+d) 85448.52

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 939933.72

Cost for 120 cum = a+b+c+d+e+f 7832.78

Rate per cum = (a+b+c+d+e+f)/120 say 7833.00

(q)

Height 5m to 10m 527460.00

45.00 237357.00

d) Formwork and staging 45 per cent of (a+b+c) 152963.40

e) Overhead charges @ 0.2 on (a+b+c+d) 91778.04

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 1009558.44

Cost for 120 cum = a+b+c+d+e+f 8412.99

Rate per cum = (a+b+c+d+e+f)/120 say 8413.00

(r)

Height above 10m 527460.00

55.00 290103.00

d) Formwork and staging 55 per cent of (a+b+c) 163512.60

e) Overhead charges @ 0.2 on (a+b+c+d) 98107.56

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 1079183.16

Cost for 120 cum = a+b+c+d+e+f 8993.19

Rate per cum = (a+b+c+d+e+f)/120 say 8993.00

Note

14.2 1600

Unit = 1 MT

Taking output = 1 MT

Lead =1 km & P&M-

050

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

For cast-in-situ box girder, segmental construction and balanced cantilever, 35-55 per cent of cost of concrete

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1H (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1H (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

1.Where ever concrete is carried out using batching plant, transit mixer, concrete pump, admixers conforming IS: 9103 @ 0.4 per cent of weight of cement may be added for achieving desired slump of concrete.

2. Cement provided for various components of the super structure is for estimating purpose only. Actual quantity of cement will be as per approved mix design. Similarly, the provision for coarse and fine aggregates is for estimating purpose and the exact quantity shall be as per the mix design.

3. The items like needle and surface vibrators are part of minor T & P which is already covered under the overhead charges. As such these items have not been added separately in the rate analysis.

Supplying, fitting and placing HYSD bar reinforcement in super-structure complete as per drawing and technical specifications

Page 268: Standard Data Book - Rate Analysis

Page 21 of 280

a) Material tonne 1.05 45000.00 47250.00 M-082

HYSD bars including 5 per cent for laps and wastage Kg 8.00 100.00 800.00 M-072

Binding wire

day 0.44 151.44 66.63 L-12

Mate day 3.00 264.50 793.50 L-02

Blacksmith day 8.00 136.69 1093.52 L-13

Mazdoor 50004.00

Basic Cost of Labour & Material (a+b) 10000.73

c) Overhead charges @ 0.2 on (a+b) 6000.44

d) Contractor's profit @ 0.1 on (a+b+c) 66004.82

Rate per MT = a+b+c+d say 66005.00

14.3 1800

Unit = 1 MT

Taking output = 0.377 MT

a) Material tonne 0.39 57453.00 22119.41 M-119

metre 42.00 304.00 12768.00 M-165

each 2.00 6064.00 12128.00 M-187

tonne 0.125 5000.00 625.00 M-081

2382.02

b) Labour

i) For making and fixing cables, anchorages day 0.16 151.44 24.23 L-12

Mate day 1.00 264.50 264.50 L-02

Blacksmith day 3.00 136.69 410.07 L-13

Mazdoor

ii) For prestressing day 0.05 151.44 7.57 L-12

Mate/Supervisor day 0.25 230.00 57.50 L-08

Prestressing operator / Fitter day 1.00 136.69 136.69 L-13

Mazdoor

iii) For grouting day 0.05 151.44 7.57 L-12

Mate/Supervisor day 0.25 223.36 55.84 L-11

Mason day 1.00 136.69 136.69 L-13

Mazdoor

c) Machinery hour 2.50 129.00 322.50 P&M-040

Stressing jack with pump hour 1.00 304.00 304.00 M-111

Grouting pump with agitator hour 3.50 406.80 1423.80 P&M-079

Generator 33 KVA. 630.19

d) Overhead charges @ 0.2 on (a+b+c) 378.12

e) Contractor's profit @ 0.1 on (a+b+c+d) 54181.70

Cost for 0.377 MT (a+b+c+d+e) 143718.03

Rate per MT = (a+b+c+d+e)/0.377 say 143718.00

Note

14.4 2702

Unit = 1 cum

Taking output = 1 cum

b) Labour for cutting, bending, tying and placing in position

High tensile steel wires/strands including all accessories for stressing, stressing operations and grouting complete as per drawing and Technical Specifications

Details of cost for 12T13 strand 40 m long cable (weight = 0.377 MT)

H.T. Strand @ 9.42 kg/m including 2 per cent for wastage and extra length for jacking

Sheathing duct ID 66 mm along with 5 per cent extra length 40 x 1.05 = 42 m.

Tube anchorage set complete with bearing plate, permanent wedges etc

Cement for grouting including 3 per cent wastage @ 3.00 kg/m = 3 x 1.03 x 40 = 123.60 kg (say, = 125 kg)

Add 0.50 per cent cost of material for Spacers, Insulation tape and miscellaneous items

Cost of HT steel has been taken for delivery at site. Hence carriage has not been considered.

Providing and laying Cement concrete wearing coat M-30 grade including reinforcement complete as per drawing and Technical Specifications

Page 269: Standard Data Book - Rate Analysis

Page 22 of 280

a) Material cum 1.00 3690.00 3690.00

tonne 0.075 50004.00 3750.30

b) Labour day 0.15 136.69 20.50 L-13

Mazdoor for cleaning deck slab concrete surface. 1492.16

c) Overhead charges @ 0.2 on (a+b) 895.30

d) Contractor's profit @ 0.1 on (a+b+c) 9848.26

Rate per cum (a+b+c+d) say 9848.00

14.5

Mastic Asphalt

Unit = sqm

a) Labour day 0.49 151.44 74.21 L-12

Mate day 11.00 136.69 1503.59 L-13

Mazdoor day 1.25 164.69 205.86 L-15

Mazdoor (Skilled)

b) Machinery hour 0.06 357.00 21.42 P&M-031

Mechanical broom @ 1250 sqm per hour hour 0.06 319.00 19.14 P&M-001

Air compressor 250 cfm hour 6.00 62.00 372.00 P&M-030

Mastic cooker 1 tonne capacity hour 6.00 198.00 1188.00 P&M-005

Bitumen boiler 1500 litres capacity hour 1.00 282.50 282.50 P&M-053

c) Material

Base mastic (without coarse aggregates) = 60 per cent

Coarse aggregate(3.35mm to 9.5 mm size) = 40 per cent .

tonne 0.204 55132.00 11246.93 M-074

cum 0.39 476.80 185.95 M-021

tonne 0.36 4500.00 1620.00 M-188

cum 0.55 1005.00 552.75 M-051

cum 0.036 1213.00 43.67 M-142

kg 1.05 55.13 57.89

3474.78

d) Overhead charges @ 0.2 on (a+b+c) 2084.87

e) Contractor's profit @ 0.1 on (a+b+c+d) 22933.55

Cost for 72.46 sqm = a+b+c+d+e 316.50

Item 14.1(C)

Cement concrete M30 Grade Refer relevant item of concrete in Item 14.1 excluding formwork

Item 14.2 A

HYSD bar reinforcement Rate as per item No 14.2(Excluding OH & CP)

515 & 2702

Providing and laying 12 mm thick mastic asphalt wearing course on top of deck slab excluding prime coat with paving grade bitumen meeting the requirements given in table 500-29, prepared by using mastic cooker and laid to required level and slope after cleaning the surface, including providing antiskid surface with bitumen precoated fine grained hard stone chipping of 9.5 mm nominal size at the rate of 0.005cum per 10 sqm and at an approximate spacing of 10 cm center to center in both directions, pressed into surface when the temperature of surfaces not less than 100 deg. C, protruding 1 mm to 4 mm over mastic surface, all complete as per clause 515.

Taking output = 72.46 sqm (2 tonnes)(0.869 cum) assuming a density of 2.3 tonnes/cum.

Tractor for towing and positioning of mastic cooker and bitumen boiler

Proportion of material required for mastic asphalt with coarse aggregates (based on mix design done by CRRI for a specific case)

i) Bitumen 80/100 or 60/70 or 30/40 @ 10.2 per cent by weight of mix. 2 x 10.2/100 = 0.204

ii) Crusher stone dust @ 31.9 per cent by weight of mix = 2 x 31.9/100 = 0.638 tonnes = 0.638/1.625 = 0.39

iii) Lime stone dust filler with calcium carbonate content not less than 80 per cent by weight @ 17.92 per cent by weight of mix = 2 x 17.92/100 = 0.36

iv) Coarse aggregates 9.5 mm to 3.35 mm size @ 40 per cent by weight of mix = 2 x 40/100 = 0.8 MT = 0.8/1.456 = 0.55

v) Pre-coated stone chips of 9.5 mm nominal size for skid resistance = 72.46x0.005/10 = 0.036

M-074/1000

vi) Bitumen for coating of chips @ 2 per cent by weight = 0.036 x 1.456 x 2/100 = 0.001048MT = 1.05kg

Page 270: Standard Data Book - Rate Analysis

Page 23 of 280

Rate per sqm = (a+b+c+d+e)/72.46 say 316.00

Note

14.6

Unit = 1 RM

Taking output = 2 x 24 m span = 48 m

a) Material cum 4.09 3690.00 15099.48

754.97

tonne 0.87 50004.00 43253.46

Refer MoRTH SD / 202. 2955.40

12412.66

b) Overhead charges @ 0.2 on (a) 7447.60

c) Contractor's profit @ 0.1 on (a+b) 81923.57

Rate for 48 m (a+b+c) 1706.74

Rate per metre (a+b+c)/48 say 1707.00

Note

14.7

Unit = 1 RM

Taking output = 2 x 24 m span = 48 m.

a) Material cum 4.092 3690.00 15099.48

1.The rates for 6 mm or any other thickness may be worked out on pro-rata basis.

2. Where tack coat is required to be provided before laying mastic asphalt, the same is required to be measured and paid separately.

3.The quantities of binder, filler and aggregates are for estimating purpose. Exact quantities shall be as per mix design.

4.This rate analysis is based on design made by CRRI for a specific case and is meant for estimating purposes only. Actual design is required to be done for each case.

2703, 1500, 1600 & 1700

5.The quantity of bitumen works out 17 per cent of the mastic asphalt blocks without aggregates and falls within the standards laid down by MoRTH Specifications.

Construction of precast RCC railing of M30 Grade, aggregate size not exceeding 12 mm, true to line and grade, tolerance of vertical RCC post not to exceed 1 in 500, centre to centre spacing between vertical post not to exceed 2000 mm, leaving adequate space between vertical post for expansion, complete as per approved drawings and technical specifications.

Item 14.1(C)

Cement concreteM30 Grade Refer relevant item of concrete in Item 14.1(C) by using batching plant, excluding formwork i.e. per cum basic cost (a+b+c)

No. of vertical posts = (12 + 2)2 = 28 Nos., External area of vertical post 0.25x0.275 = 0.069sqm, Concrete in Vertical posts = 0.069 x 28 = 1.932 cum, Hand rail in 3 tiers = 3 x 24 = 72 m, External area = 0.170 x 0.175 = 0.03 sqm, Concrete in hand rails = 0.03 x 72 = 2.16 cum, Total Concrete = 1.932 + 2.16 = 4.092 cum. (Refer MoRTH SD / 202).

Add 5 per cent of above cost for form work for casting in casting yard.

Item 14.2 A

HYSD bar reinforcement Rate as per item No 14.2(Excluding OH & CP)

Add 5 per cent of (a) for handling and fixing of precast panels in position

1.Quantities of material have been adopted from standard plans of MoRTH vide drawing no. SD/202.

2703, 1500, 1600 & 1700

2.48 m length is the total linear length adding both sides of 24 m span.

Construction of RCC railing of M30 Grade in-situ with 20 mm nominal size aggregate, true to line and grade, tolerance of vertical RCC post not to exceed 1 in 500, centre to centre spacing between vertical post not to exceed 2000 mm, leaving adequate space between vertical post for expansion, complete as per approved drawings and technical specifications.

Item 14.1(C)

Page 271: Standard Data Book - Rate Analysis

Page 24 of 280

1811.94

Add 12 per cent of above cost for form work. tonne 0.87 50004.00 43253.46

refer MoRTH SD / 202. 12032.98

b) Overhead charges @ 0.2 on (a) 7219.79

c) Contractor's profit @ 0.1 on (a+b) 79417.64

Rate for 48 m (a+b+c) 1654.53

Rate per metre (a+b+c)/48 say 1655.00

Note

14.8

Unit = 1 RM

Taking output = 2 x 50 m span = 100 m

a) Material: tonne 2.95 45000.00 132570.00 M-179

1) ISMC 100 = 2.806 x 1.05 = 2.946 MT tonne 1.01 45000.00 45540.00 M-179

2) MS Flat = 0.964 x 1.05 = 1.012 MT tonne 0.18 45000.00 8100.00 M-179

3) MS bars = 0.17 x 1.05 = 0.180 MT tonne 0.15 64070.00 9610.50

4) MS bolts, nuts and washers 9791.03

1958.21

1958.21

b) Labour day 2.80 151.44 424.03 L-12

Mate day 30.00 164.69 4940.70 L-15

Mazdoor (Skilled) day 40.00 136.69 5467.60 L-13

Mazdoor 44072.05

c) Overhead charges @ 0.2 on (a+b) 26443.23

d) Contractor's profit @ 0.1 on (a+b+c) 290875.55

Cost for 100 m steel railing = a+b+c+d 2908.76

Rate per metre (a+b+c+d)/100 say 2909.00

14.9 2705

Unit = 1 No.

Taking output = 1 No.

a) Material Kg 4.00 46.53 186.10

metre 6.00 65.00 390.00 M-056

GI pipe 100mm dia each 6.00 13.00 78.00 M-110

GI bolt 10 mm Dia each 2.00 25.00 50.00 M-101

Galvanised MS flat clamp

b) Labour

For fabrication day 0.02 151.44 3.03 L-12

Cement concreteM30 Grade Refer relevant item of concrete in Item 14.1(C) by using batching plant, excluding formwork i.e. per cum basic cost (a+b+c)

No. of vertical posts = (12 + 2)2 = 28 Nos., External area of vertical post 0.25x0.275 = 0.069sqm, Concrete in vehicle posts = 0.069 x 28 = 1.932 cum, Hand rail in 3 tiers = 3 x 24 = 72 m, External area = 0.170 x 0.175 = 0.03 sqm, Concrete in hand rails = 0.03 x 72 = 2.16 cum, Total Concrete = 1.932 + 2.16 = 4.092 cum. (Refer MoRTH SD / 202).

Item 14.2 A

HYSD bar reinforcement Rate as per item No 14.2(Excluding OH & CP)

1. Quantities of material have been adopted from standard plans of MoRTH vide drawing no. SD/202.

2703.2 & 1900

2. 48 m length is the total linear length adding both sides of 24 m span.

Providing, fitting and fixing mild steel railing complete as per drawing and Technical Specification

M-130*1000

Add @ 5 per cent of cost of material for painting one shop coat with red oxide primer and three coats of synthetic enamel paint and consumables to safeguard against weathering and corrosion.

Add for cost of concrete for fixing vertical posts in the performed recess @ 1 per cent of cost of material.

Add for electricity charges, welding and drilling equipment, electrodes and other consumables @ 1 per cent of cost of material.

Drainage Spouts complete as per drawing and Technical specification

M-087/1000

Corrosion resistant Structural steel including 5 per cent wastage

Page 272: Standard Data Book - Rate Analysis

Page 25 of 280

Mate day 0.02 264.50 5.29 L-02

Skilled (Blacksmith, welder etc.) day 0.02 136.69 2.73 L-13

Mazdoor

For fixing in position day 0.01 151.44 1.51 L-12

Mate day 0.01 223.36 2.23 L-11

Mason day 0.20 136.69 27.34 L-13

Mazdoor 37.31

156.71

c) Overhead charges @ 0.2 on (a+b) 94.03

d) Contractor's profit @ 0.1 on (a+b+c) 1034.29

Rate per metre (a+b+c+d) say 1034.00

Note

14.10 2700

Unit = 1 cum

Taking output = 1 cum

Material cum 1.00 4066.00 4066.00

say 4066.00

14.11 Rate per cum

Unit = 1 cum

Taking output = 1 cum

a) Material cum 1.00 3686.00 3686.00

73.72

tonne 0.05 50004.00 2500.20

1251.98

b) Overhead charges @ 0.2 on (a) 751.19

c) Contractor's profit @ 0.1 on(a+b) 8263.09

Rate per cum (a+b+c) say 8263.00

Note

14.12 1600

Unit = 1 MT

Taking output = 1 MT

Note To be taken as per the prevailing market rates.

Add @ 5 per cent of cost of material and labour for electrodes, cutting gas, sealant, anti-corrosive bituminous paint, mild steel grating etc.

1. In case of viaducts in urban areas, the drainage spouts should be connected with suitably located pipelines to discharge the surface run-off to drains provided at ground level.

2. In case of bridges, sufficient length of G.I Pipe shall be provided to ensure that there is no splashing of water from the drainage spout on the structure.

PCC M15 Grade leveling course below approach slab complete as per drawing and Technical specification

Item 12.8 (A)

Concrete, Rate as per item No. 12.8 (A) excluding formworks

1500,1600,1700 & 2704

Reinforced cement concrete approach slab including reinforcement and formwork complete as per drawing and Technical specification

Item 12.8 (G)

Cement concreteM30 Grade Refer relevant item of concrete in item 12.8(G)by using batching plant, excluding formwork i.e. per cum basic cost (a+b+c) (Excluding OH & CP)

( Refer relevant item of concrete in item No. 13.8 (G) except that form work may be added at the rate of 2 per cent of cost against 3.5 per cent provided in the foundation concrete.

Item 14.2 A

HYSD bar reinforcement Rate as per item No 14.2(Excluding OH & CP)

The grade of reinforced cement concrete may be adopted as M30 for severe conditions and M25 for moderate conditions.

Providing anti-corrosive treatment to HYSD reinforcement with Fusion Bonded Epoxy Coating (FBEC)

Page 273: Standard Data Book - Rate Analysis

Page 26 of 280

14.13

Precast - pretensioned Girders

Unit = 1 cum

Taking output = 1 cum

Grade of concrete - M40

a) Material tonne 0.47 5000.00 2350.00 M-081

Cement cum 0.45 828.00 372.60 M-004

Coarse sand cum 0.54 1028.00 555.12 M-053

20 mm Aggregate cum 0.36 1005.00 361.80 M-051

10 mm Aggregate Kg 1.88 44.70 84.04 M-180

Admixture @ 0.4 per cent of cement tonne 0.10 45000.00 4500.00 M-082

HYSD steel . tonne 0.06 57453.00 3447.18 M-119

Litre 37.00 43.00 1591.00 M-122

LDO for steam curing 132.62

b) Labour

day 0.06 151.44 9.09 L-12

Mate day 0.35 164.69 57.64 L-15

Mazdoor (Skilled) day 1.40 136.69 191.37 L-13

Mazdoor

Taking quantity of HT strand 60 Kg/cum day 0.02 151.44 3.03 L-12

Mate day 0.14 164.69 23.06 L-15

Mazdoor (Skilled) day 0.50 136.69 68.35 L-13

Mazdoor

(iii) Erection and dismantling of shuttering

Taking shuttering area 10 sqm/cum of concrete day 0.12 151.44 18.17 L-12

Mate day 1.00 164.69 164.69 L-15

Mazdoor (Skilled) day 2.00 136.69 273.38 L-13

Mazdoor

day 0.03 151.44 4.54 L-12

Mate day 0.05 164.69 8.23 L-15

Mazdoor (Skilled) day 0.60 136.69 82.01 L-13

Mazdoor

(v) Steam curing and manual curing day 0.01 151.44 1.51 L-12

Mate day 0.35 136.69 47.84 L-13

Mazdoor

day 0.01 151.44 1.51 L-12

Mate day 0.25 136.69 34.17 L-13

Mazdoor

day 0.01 151.44 1.51 L-12

1800 & 2300

Contractors generally do not have expertise for this item . The job is therefore, got done from specialised firms who have the expertise in the field of construction chemicals. The prevailing rate in the market is required to be ascertained from the market and added in the cost estimate. Detailed guidelines in this regard have been issued by MoRTH vide their circular no. RW/NH-34041/44/91-S&R dated 21.3.2000.

Providing, precasting, transportation and placing in position precast pretensioned concrete girders as per drawing and technical specifications

HT strand with 5 per cent as wastage and extra length for anchoring

Add consumables such as binding wire, foam, packing tape, shuttering oil, HDPE pipe for unbonding of strand, bolt & nuts etc @ 1 per cent of material cost

(i) Cutting, bending, making reinforcement cage, placing in position, binding etc. complete

Taking quantity of steel 100 Kg/cum of concrete including laps and wastage

(ii) Cable cutting and threading in position including binding by insulation tape with HDPE pipes etc., prestessing and cutting of extra length of HT strand after de-stressing.

(iv) Concreting by Batching plant and stationary concrete pump

(vi) Handling of precast girder, stacking in stockyard and again loading in trailor

(vii) Placement of girders in position over pier caps including placement of sand jacks, channel, levelling etc.

Page 274: Standard Data Book - Rate Analysis

Page 27 of 280

Mate day 0.06 164.69 9.88 L-15

Mazdoor (Skilled) day 0.24 136.69 32.81 L-13

Mazdoor

c) Machinery

i) At casting yard hour 0.05 762.75 38.14 P&M-080

Generator 100 KVA hour 0.05 2232.00 111.60 P&M-002

Batching Plant @ 20 cum/hour hour 0.10 1017.00 101.70 P&M-049

Transit Mixer 4 cum capacity hour 0.05 256.00 12.80 P&M-007

Concrete Pump stationary hour 0.10 853.00 85.30 P&M-012

Crane 35 tonne capacity hour 0.10 847.50 84.75 P&M-089

Trailor 30 tonne capacity hour 0.05 806.00 40.30 P&M-017

Loader

ii) For transportation and placement at site hour 0.15 853.00 127.95 P&M-012

Crane 35 tonne capacity tonne.km 2.5xL 0.68 1.69

Trailer 30 tonne capacity for transporting to site.

(L - Lead in Kilometer) hour 0.15 847.50 127.13 P&M-089

Trailor 30 tonne capacity during placement. 745.09

3180.72

d) Overhead charges @ 0.2 on (a+b+c) 1908.43

e) Contractor's profit @ 0.1 on (a+b+c+d) 20992.75

Rate per cum = (a+b+c+d+e) say 20993.00

14.14

Unit = 1 RM

Taking output = 1 RM

a) Material metre 1.00 2426.00 2426.00 M-117

Helical pipes 600mm diameter each 1.00 49.00 49.00 M-183

Tie rods 20mm diameter 123.75

b) Labour day 0.01 151.44 1.51 L-12

Mate day 0.05 230.00 11.50 L-08

Fitter day 0.20 136.69 27.34 L-13

Mazdoor 527.82

c) Overhead charges @ 0.2 on (a+b) 316.69

d) Contractor's profit @ 0.1 on (a+b+c) 3483.62

Rate per cum (a+b+c+d) say 3484.00

14.15 800

Crash Barriers

14.16 800

Painting on concrete surface

Unit = sqm

Taking output = 10 sqm

a) Labour day 0.01 151.44 1.51 L-12

Mate day 0.25 223.36 55.84 L-18

Painter day 0.25 164.69 41.17 L-15

Mazdoor (Skilled)

b) Material Litres 5.00 31.00 155.00 M-190

Lead =1 km & P&M-

090

Cost of formwork, steam curing arrangement, pretensioning arrangement etc @ 5 per cent of cost material, labour and machinery

1700 & 1800

Providing and fixing Helical pipes in voided concrete slabs

Consumables for sealing joints etc.@ 5 per cent of cost of material

The rate analysis for rigid crash barrier in reinforced cement concrete, semi-rigid crash barrier with metal beam and flexible crash barrier with wire ropes have been made and included in chapter-8 on Traffic and Transportation.

Providing and applying 2 coats of water based cement paint to unplastered concrete surface after cleaning the surface of dirt, dust, oil, grease, efflorescence and applying paint @ of 1 litre for 2 sqm.

Page 275: Standard Data Book - Rate Analysis

Page 28 of 280

50.71

c) Overhead charges @ 0.2 on (a+b) 30.42

d) Contractor's profit @ 0.1 on (a+b+c) 334.66

Cost for 10 sqm (a+b+c+d) 33.47

Rate per sqm (a+b+c+d)/10 say 33.00

14.17 2604

Burried Joint

Unit = Running meter

Taking output = 12 m

a) Labour day 0.02 151.44 3.03 L-12

Mate day 0.40 136.69 54.68 L-13

Mazdoor day 0.20 164.69 32.94 L-15

Mazdoor (Skilled)

b) Material kg 237.50 54.57 12961.32

129.61

2636.32

c) Overhead charges @ 0.2 on (a+b) 1581.79

d) Contractor's profit @ 0.1 on (a+b+c) 17399.69

Cost for 12 m = (a+b+c+d) 1449.97

Rate per m = (a+b+c+d)/12 say 1450.00

Note

14.18 2605

(i) Filler joint

Unit = Running meter

Taking output = 12 m

a) Labour

Cutting, bending, carrying & fixing etc. day 0.04 151.44 6.06 L-12

Mate day 0.50 136.69 68.35 L-13

Mazdoor day 0.50 164.69 82.35 L-15

Mazdoor (Skilled)

b) Material kg 55.00 290.55 15980.25 M-086

Copper plate - 12m long x 250 mm wide

Area = 12 x 0.25 = 3 sqm

Weight = 3 x 0.002 x 8900 = 53.4 kg

Wastage @ 2.5 per cent = 1.33 kg/54.73 kg say = 55 kg. 3227.40

c) Overhead charges @ 0.2 on (a+b) 1936.44

d) Contractor's profit @ 0.1 on (a+b+c) 21300.84

Cost for 12 m = (a+b+c+d) 1775.07

Rate per m = (a+b+c+d)/12 say 1775.00

14.18 (ii)

Unit = Running meter

Taking output = 12 m

Water based paint of approved quality for cement concrete surface

Providing and laying a burried expansion joint, expansion gap being 20 mm, covered with 12 mm thick, 200 mm wide galvanised weldable structural steel plate as per IS: 2062, placed symmetrical to centre line of the joint, resting freely over the top surface of the deck concrete, welding of 8 mm dia. 100 mm long galvanised nails spaced 300 mm c/c along the centre line of the plate, all as specified in clause 2604.

M-060/1000

Galvanised M.S plate 200 mm wide,12 mm thick @ 94.20 kg/sqm including 5 per cent wastage

Add 1 per cent of cost of steel plate cutting, welding consumables and galvanised nails.

Guidelines laid down vide the MoRTH circular No. RW/NH-34059/1/96-S&R dated 30.11.2000 and subsequent corrigendum dated 25.01.2001 may be reffered for expansion joints.

Providing & fixing 2 mm thick corrugated copper plate in expansion joint complete as per drawing & Technical Specification.

Providing & fixing 20 mm thick compressible fibre board in expansion joint complete as per drawing & Technical Specification.

Page 276: Standard Data Book - Rate Analysis

Page 29 of 280

a) Labour

For carrying, placing & fixing. day 0.008 151.44 1.21 L-12

Mate day 0.10 136.69 13.67 L-13

Mazdoor day 0.10 164.69 16.47 L-15

Mazdoor (Skilled)

b) Material sqm 3.00 486.00 1458.00 M-084

Area = 12 x 0.25 = 3 sqm 297.87

c) Overhead charges @ 0.2 on (a+b) 178.72

d) Contractor's profit @ 0.1 on (a+b+c) 1965.94

Cost for 12 m = (a+b+c+d) 163.83

Rate per m = (a+b+c+d)/12 say 164.00

14.18 (iii)

Unit = Running meter

Taking output = 12 m

a) Labour day 0.01 151.44 1.51 L-12

Mate day 0.20 136.69 27.34 L-13

Mazdoor day 0.10 164.69 16.47 L-15

Mazdoor (Skilled)

b) Material sqm 3.60 965.00 3474.00 M-141

703.86

c) Overhead charges @ 0.2 on (a+b) 422.32

d) Contractor's profit @ 0.1 on (a+b+c) 4645.50

Cost for 12 m = (a+b+c+d) 387.13

Rate per m = (a+b+c+d)/12 say 387.00

14.18 (iv)

Unit = Running meter

Taking output = 12 m

12m long x 100 mm wide x 10mm deep recess

a) Labour day 0.02 151.44 3.03 L-12

Mate day 0.50 136.69 68.35 L-13

Mazdoor day 0.10 164.69 16.47 L-15

Mazdoor (Skilled)

b) Material cum 0.012 710.46 8.53 M-005

Sand

Volume 12 x 0.1 x 0.01 = 0.012 cum

Weight 0.012 x 1400 = 16.8kg cum 0.001 55132.00 55.13 M-074

Bitumen

16.8 x 0.06 = 1 kg 30.30

c) Overhead charges @ 0.2 on (a+b) 18.18

d) Contractor's profit @ 0.1 on (a+b+c) 199.98

Cost for 12 m = (a+b+c+d) 16.67

Rate per m = (a+b+c+d)/12 say 17.00

Note

For arriving at the final rate of filler joints per m

length and per cm depth of joint filling compound,

14.19 2600 the rates at Sl. No. i), ii), iii) & iv) shall be added

Asphaltic Plug joint

20 mm thick compressible fibre board 12 m long x 25 cm deep.

Providing and fixing in position 20 mm thick premoulded joint filler in expansion joint for fixed ends of simply supported spans not exceeding 10 m to cater for a horizontal movement upto 20 mm, covered with sealant complete as per drawing and technical specifications.

Premoulded joint filler 12 m long,20 mm thick and 300 mm deep.

Providing and filling joint sealing compound as per drawings and technical specifications with coarse sand and 6 per cent bitumen by weight

Page 277: Standard Data Book - Rate Analysis

Page 30 of 280

Unit = Running meter

Taking output = 12 m

a) Labour day 0.052 151.44 7.87 L-12

Mate day 1.00 136.69 136.69 L-13

Mazdoor day 0.30 164.69 49.41 L-15

Mazdoor (Skilled)

b) Material cum 0.75 1028.00 771.00 M-052

Crushed stone aggregate 12.5 mm nominal size kg 77.50 38.74 3002.35

2.4 Polymer modified bitumen kg 113.00 61.00 6893.00 M-103

108.60

c) Machinery hour 1.00 62.00 62.00 P&M-030

Mastic cooker 1 tonne capacity hour 0.50 460.00 230.00 P&M-044

Smooth 3-wheeled steel roller 8-10 capacity 2252.19

d) Overhead charges @ 0.2 on (a+b+c) 1351.31

e) Contractor's profit @ 0.1 on (a+b+c+d) 14864.42

Cost for 12 m asphalt plug joint = (a+b+c+d+e) 1238.70

Rate per m = (a+b+c+d+e)/12 say 1239.00

Note

14.20 2606

Elastomeric Slab Steel Expansion Joint

Unit = Running meter

Taking output = 12 m

a) Labour day 0.06 151.44 9.09 L-12

Mate day 1.00 136.69 136.69 L-13

Mazdoor day 0.50 164.69 82.35 L-15

Mazdoor (Skilled)

b) Material metre 12.00 6064.00 72768.00 M-093

3638.40

15326.90

c) Overhead charges @ 0.2 on (a+b) 9196.14

d) Contractor's profit @ 0.1 on (a+b+c) 101157.57

Providing and laying of asphaltic plug joint to provide for horizontal movement of 25 mm and vertical movement of 2 mm, depth of joint varying from 75 mm to 100 mm, width varying from 500 mm to 750 mm (in traffic direction), covered with a closure plate of 200mm x 6mm of weldable structural steel conforming to IS: 2062, asphaltic plug to consist of polymer modified bitumen binder, carefully selected single size aggregate of 12.5 mm nominal size and a heat resistant foam caulking/backer rod, all as per approved drawings and specifications.

M-078/ 1000

Galvanised structural steel plate 200 mm wide,6 mm thick, 12 m long (2.4 sqm) @ 47.10 kg/sqm including 5 per cent wastage

Add 1 per cent for welding and foam caulking/backer rod and other incidentals.

The nominal size of aggregates shall be 12.5 mm for depth of joint upto 75 mm and 20 mm for joints of depth more than 75 mm.

Providing and laying of an elastomeric slab steel expansion joint, catering to right or skew (less than 20 deg., moderately curved with maximum horizontal movement upto 50 mm, complete as per approved drawings and standard specifications to be installed by the manufacturer/supplier or their authorised representative ensuring compliance to the manufacturer's instructions for installation and clause 2606 of MoRTH specifications for road & bridge works.

Supply of elastomeric slab seal expansion joint assembly manufactured by using chloroprene, elastomer for elastomeric slab unit conforming to clause 915.1 of IRC: 83 (part II), complete as per approved drawings and standard specification conforming to clause 2606 of MoRT&H Specification

Add 5 per cent of cost of material for anchorage reinforcement, welding and other incidentals.

Page 278: Standard Data Book - Rate Analysis

Page 31 of 280

Cost for 12 m = (a+b+c+d) 8429.80

Rate per m = (a+b+c+d)/12 say 8430.00

14.21 2600

Compression Seal Joint

Unit = Running meter

Taking output = 12 m

a) Labour day 0.036 151.44 5.45 L-12

Mate day 0.60 136.69 82.01 L-13

Mazdoor day 0.30 164.69 49.41 L-15

Mazdoor (Skilled)

b) Material kg 446.00 61.00 27206.00 M-103

1367.14

metre 12.00 668.00 8016.00 M-143

80.16

7361.24

c) Overhead charges @ 0.2 on (a+b) 4416.74

d) Contractor's profit @ 0.1 on (a+b+c) 48584.15

Cost for 12 m = (a+b+c+d) 4048.68

Rate per m = (a+b+c+d)/12 say 4049.00

Note

14.22 2607

Strip Seal Expansion Joint

Unit = Running meter

Taking output = 12 m

a) Labour day 0.05 151.44 7.57 L-12

Mate day 1.00 136.69 136.69 L-13

Mazdoor day 0.25 164.69 41.17 L-15

Mazdoor (Skilled)

b) Material metre 12.00 7500.00 90000.00 M-178

4509.27

18938.94

c) Overhead charges @ 0.2 on (a+b) 11363.36

Providing and laying of compression seal joint consisting of steel armoured nosing at two edges of the joint gap suitably anchored to the deck concrete and a preformed chloroprene elastomer or closed cell foam joint sealer compressed and fixed into the joint gap with special adhesive binder to cater for a horizontal movement upto 40 mm and vertical movement of 3 mm.

1. Galvanised angle sections 100mm x 100mm of 12mm thickness weldable structural steel as per IS: 2062, 2 nos. of 12 m length each @ 17.7 kg/m and 5 per cent wastage.

Add 5 per cent of cost of above for structural steel for anchorage, welding and other incidentals.

Preformed continuous chloroprene elastomer or closed cell foam sealing element with high tear strength, vulcanised in a single operation for the full length of a joint to ensure water tightness.

Add 1 per cent of cost of sealing element for lubricant-cum-adhesive and other consumables.

1. The installation shall be done by the manufacturer or his authorised representative to the satisfaction of the Engineer.

2. The concreting for joining the expansion joint assembly with the deck has not been included in this analysis as the same is catered in the quantities of RCC deck.

3. The anchoring bars of the expansion joint assembly shall be welded to the main reinforcement of the deck.

Providing and laying of a strip seal expansion joint catering to maximum horizontal movement upto 70 mm, complete as per approved drawings and standard specifications to be installed by the manufacturer/supplier or their authorised representative ensuring compliance to the manufacturer's instructions for installation.

Supply of complete assembly of strip seal expansion joint comprising of edge beams, anchorage, strip seal element and complete accessories as per approved specifications and drawings.

Add 5 per cent of cost of material for anchorage reinforcement, welding and other incidentals.

Page 279: Standard Data Book - Rate Analysis

Page 32 of 280

d) Contractor's profit @ 0.1 on (a+b+c) 124997.01

Cost for 12 m = (a+b+c+d) 10416.42

Rate per m = (a+b+c+d)/12 say 10416.00

Note

14.23 2600

Modular Strip / Box Seal Joint

Unit = Running meter

Taking output = 12 m

a) Labour day 0.056 151.44 8.48 L-12

Mate day 1.00 136.69 136.69 L-13

Mazdoor day 0.40 164.69 65.88 L-15

Mazdoor (Skilled)

b) Material metre 12.00 1820.00 21840.00 M-127

4410.21

c) Overhead charges @ 0.2 on (a+b) 2646.13

d) Contractor's profit @ 0.1 on (a+b+c) 29107.38

Cost for 12 m Modular strip/box seal joint = (a+b+c+d) 2425.62

Rate per m = (a+b+c+d)/12 say 2426.00

Note

14.24 2600

Modular Strip / Box Seal Joint

Unit = Running meter

Taking output = 12 m

a) Labour day 0.07 151.44 10.60 L-12

Mate day 1.25 136.69 170.86 L-13

Mazdoor day 0.50 164.69 82.35 L-15

Mazdoor (Skilled)

b) Material metre 12.00 1820.00 21840.00 M-128

4420.76

1. The installation shall be done by the manufacturer or his authorised representative to the satisfaction of the Engineer.

2. The concreting for joining the expansion joint assembly with the deck has not been included in this analysis as the same is catered in the quantities of RCC deck.

Providing and laying of a modular strip Box seal expansion joint including anchorage catering to a horizontal movement beyond 70 mm and upto 140mm, complete as per approved drawings and standard specifications to be installed by the manufacturer/supplier or their authorised representative ensuring compliance to the manufacturer's instructions for installation.

Supply of a modular strip/box seal joint assembly comprising of edge beams, central beam,2 modules chloroprene seal, anchorage elements, support and control system, all steel sections protected against corrosion and installed by the manufacturer or his authorised representative.

1. The installation shall be done by the manufacturer or his authorised representative to the satisfaction of the Engineer.

2. The concreting for joining the expansion joint assembly with the deck has not been included in this analysis as the same is catered in the quantities of RCC deck.

3. The anchoring bars of the expansion joint assembly shall be welded to the main reinforcement of the deck.

Providing and laying of a modular strip box seal expansion joint catering to a horizontal movement beyond 140mm and upto 210mm, complete as per approved drawings and standard specifications to be installed by the manufacturer/supplier or their authorised representative ensuring compliance to the manufacturer's instructions for installation.

Supply of a modular box/box seal joint assembly containing 3 modules/cells and comprising of edge beams, two central beams, chloroprene seal, anchorage elements, support and control system, all steel sections protected against corrosion and installed by the manufacturer or his authorised representative.

Page 280: Standard Data Book - Rate Analysis

Page 33 of 280

c) Overhead charges @ 0.2 on (a+b) 2652.46

d) Contractor's profit @ 0.1 on (a+b+c) 29177.03

Cost for 12 m Modular strip/box seal joint = (a+b+c+d) 2431.42

Rate per m = (a+b+c+d)/12 say 2431.00

Note

1. The installation shall be done by the manufacturer or his authorised representative to the satisfaction of the Engineer.

2. The concreting for joining the expansion joint assembly with the deck has not been included in this analysis as the same is catered in the quantities of RCC deck.