standard specifications for public works … · 413 repair of existing sewer and water facilities...
TRANSCRIPT
STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION
CITY OF WEST BEND, WISCONSIN
SECTION 400
SEWER AND WATER CONSTRUCTION
Section
Number Title
401 GENERAL
402 AMENDMENTS TO WSWS PART I - GENERAL CONDITIONS
403 AMENDMENTS TO WSWS PART II - CONSTRUCTION GENERAL
404 AMENDMENTS TO WSWS PART III - CONSTRUCTION - STORM
AND SANITARY SEWERS
405 ADDITIONAL CITY REQUIREMENTS FOR SANITARY SEWER
CONSTRUCTION
406 ADDITIONAL CITY REQUIREMENTS FOR STORM SEWER
CONSTRUCTION
407 AMENDMENTS TO WSWS PART IV - CONSTRUCTION - WATER
MAIN
408 ADDITIONAL CITY REQUIREMENTS FOR WATER MAIN
CONSTRUCTION
409 AMENDMENTS TO WSWS PART V - BUILDING SERVICES
410 AMENDMENTS TO WSWS PART VIII - MATERIAL
SPECIFICATIONS
411 AMENDMENTS TO WSWS PART IX - DETAIL DRAWINGS
412 DETAIL DRAWINGS FOR WATER AND SEWER CONSTRUCTION IN
WEST BEND
413 REPAIR OF EXISTING SEWER AND WATER FACILITIES
414 MEASUREMENT AND PAYMENT
415 UNDERDRAINS AND SUMP DRAIN CONNECTION LINES
416 AMENDMENTS TO WSWS PART VI – TRENCHLESS INSTALLATION
OF UTILITIES
440 VIDEO INSPECTION OF SANITARY SEWERS AND STORM SEWERS
DATE OF ISSUE APRIL 12, 1993 REVISION DATE December 15, 2008 _
CITY ENGINEER'S APPROVAL ___________________________________________________
SECTION 400 - SEWER AND WATER CONSTRUCTION
TABLE OF CONTENTS
401 GENERAL
401.1 Referenced Specifications
401.2 Material Certificates
402 AMENDMENTS TO WSWS PART I - GENERAL CONDITIONS
WSWS 1.2.0 Necessary Notices and Permits
WSWS 1.2.9 Notices for Local Sewerage District Connection
WSWS 1.3.0 Control of Work and Materials
WSWS 1.3.14 Final Acceptance
WSWS 1.5.0 Scope of Work and Specific Instructions
WSWS 1.5.6 Guarantee
WSWS 1.6.0 Extra Work and Credits
WSWS 1.6.3 Basis of Payment or Credit for Altered Work
WSWS 1.7.0 Protection of Work - Public and Private
WSWS 1.7.4 Flagman Required
WSWS 1.7.6 Dust Palliative
WSWS 1.7.7 Access to Properties
WSWS 1.7.12 Traffic
WSWS 1.8.0 Legal Relations
WSWS 1.8.4 Liability and Insurance
WSWS 1.8.5 Contract Bond
403 AMENDMENTS TO WSWS PART II - CONSTRUCTION - GENERAL
WSWS 2.1.0 General Work Provisions
WSWS 2.1.2 Protection of Existing Structures and
Utilities
WSWS 2.1.7 Housing for Inspectors
CITY 2.1.8 Separation of Water Mains and Storm or
Sanitary Sewers (added)
CITY 2.1.9 Separation of Water Laterals and Sewers
(added)
WSWS 2.2.0 Excavation
WSWS 2.2.13 Dewatering Sump and Pump Wells
WSWS 2.2.15 Tree Clearing and Grubbing
WSWS 2.6.0 Backfilling
WSWS 2.6.1 Excavated Material for Backfill
WSWS 2.6.2 Granular Backfill
WSWS 2.6.3 Granular Backfill Credits
WSWS 2.6.5 Support of Underground Structures
WSWS 2.6.7 Placing of Backfill
WSWS 2.6.8 Upper Level of Backfill
WSWS 2.6.9 Minimum Backfill and/or Cover
WSWS 2.6.14 Consolidation of Backfill
WSWS 2.6.16 Maintenance of Trench Surface
WSWS 2.7.0 Surface Replacement and Site Restoration
WSWS 2.7.1 Optional Replacement
WSWS 2.7.3 Replacement of Pavements
WSWS 2.9.0 Pay Measurement
WSWS 2.9.17 Pay Measurement for Clearing and Grubbing
WSWS 2.11.0 Alternate Locating Equipment
WSWS 2.11.2(b) Insulation Color
WSWS 2.11.2(e) Wire Splice
404 AMENDMENTS TO WSWS PART III - CONSTRUCTION - STORM AND SANITARY SEWER
WSWS 3.2.0 Laying of Pipe Sewers
WSWS 3.2.6 Pipe Sewer Bedding Sections
WSWS 3.2.10(b)1a (Type of Joint to Be Used On Concrete
Pipe Storm Sewers)
WSWS 3.2.24 Abandoned Sewers, Drains, and Sewer Structures
WSWS 3.2.27 Connections to Existing Manholes or Existing
Sewers
CITY 3.2.29 Connections of Pipe to Structures
WSWS 3.3.0 Monolithic Concrete Sewers and Appurtenances
WSWS 3.4.0 Reconnecting Building Sewers, Storm Water Drains and
Utility Drains
WSWS 3.4.2 Branch Fittings, Pipe, Joints
WSWS 3.5.0 Manholes
WSWS 3.5.3 Types of Manholes
WSWS 3.5.4 General Requirements
CITY 3.5.7(d) Sealing of Connection (added)
CITY 3.5.7(e) Outside and Inside Drops at Sanitary Sewer
Manholes (added)
WSWS 3.5.8 Special Types of Manholes
WSWS 3.5.8(d)1 Precast Manhole Flexible Connection
WSWS 3.6.0 Catch Basins, Storm Water Inlets and Storm Water Drains
WSWS 3.6.1 Catch Basins
WSWS 3.6.2 Trapped Sewer Catch Basin
WSWS 3.6.3 Storm Water Inlet
405 ADDITIONAL CITY REQUIREMENTS FOR SANITARY SEWER CONSTRUCTION
405.1 Television Inspection
405.2 Adjusting Manholes, Catch Basins, and Inlet Frames and Covers
405.3 Sanitary Sewer Pipe Materials
406 ADDITIONAL CITY REQUIREMENTS FOR STORM SEWER CONSTRUCTION
406.1 Television Inspection
406.2 Culverts
406.3 Rip Rap
406.4 Trash Racks at Storm Sewer Outfalls
406.4.1 General
406.4.2 Measurement and Payment
406.5 Adjusting Manholes and Catch Basins
406.6 HDPE Pipe for Cross Country Storm Sewers
407 AMENDMENTS TO WSWS PART IV - CONSTRUCTION-WATER MAIN
WSWS 4.3.0 Laying of Water Main
WSWS 4.3.13 Thrust Restraints
WSWS 4.4.0 Ductile Iron Water Main
WSWS 4.4.2 Joints
CITY 4.4.2(d) Electrical Continuity (added)
WSWS 4.4.4 Polyethylene Wrap
WSWS 4.8.5 Installing Hydrants
WSWS 4.5.0 Prestressed Concrete Water Main
WSWS 4.9.0 Strapping, Lugged Pipe and Fittings
WSWS 4.9.3 Protective Coatings
WSWS 4.10.0 Grade and Direction Changes
WSWS 4.10.2 Grade Changes for P.V.C. Main
WSWS 4.11.0 Vaults
WSWS 4.13.0 Boring and Jacking
WSWS 4.13.2 Jacking
WSWS 4.14.0 Connection, Removal and Abandonment
WSWS 4.14.3 Connection Mains
CITY 4.14.7 Operation of Existing Valves (added)
WSWS 4.15.2 Pressure Testing
WSWS 4.16.0 Disinfection of Water Mains
CITY 4.16.7 Chlorination, Sampling and Testing (added)
WSWS 4.17.0 Insulation
CITY 4.17.1 General (added)
CITY 4.17.2 Water Main Installation (added)
CITY 4.17.3 Building Water Service Insulation (added)
408 ADDITIONAL CITY REQUIREMENTS FOR WATER MAIN CONSTRUCTION
408.1 Electrical Continuity Test
408.2 Existing Sanitary Sewer, Storm Sewer, and Water Main
408.3 Re-Laying Water Mains
408.3.1 Installation Sequence
408.3.2 Service Disruption Notices
408.3.3 Water Service Reconnections
408.3.4 Abandonment of Existing Water Main
408.3.5 Opening or Closing Existing Water Mains
408.3.6 Temporary Air Release Assemblies (Blowoffs)
408.4 Abandoning and Replacing Water Service Laterals
408.5 Water Valve Installation
408.6 As-Built Valve Manufacturer List
409 AMENDMENTS TO WSWS PART V - BUILDING SERVICES
WSWS 5.1.0 General
WSWS 5.1.3 Minimum Size
CITY 5.1.5 Location Data of Non-Conductive Service
Laterals
WSWS 5.2.0 Excavation
WSWS 5.2.2 Building Combined Sewers
WSWS 5.2.4 Water Service Piping
WSWS 5.3.0 Laying of Building Sewers
WSWS 5.3.1 Connection Point to Main Sewer
WSWS 5.3.5 Alignment and Grade
WSWS 5.3.10 Type of Pipe to Be Used
WSWS 5.4.0 Acceptance Testing of Building Sewers
WSWS 5.5.0 Laying of Water Services
WSWS 5.5.5 Lead Joints
WSWS 5.5.8 Connection to Water Main
WSWS 5.5.9 Alignment and Position
WSWS 5.5.11 Laying Water Services
WSWS 5.7.0 Lawn Sprinkler Service System
410 AMENDMENTS TO WSWS PART VIII - MATERIAL SPECIFICATIONS
WSWS 8.18.0 Ductile Iron Water Pipe
WSWS 8.18.2 Description
WSWS 8.19.0 Prestressed Concrete Pressure Water Pipe, Steel Cylinder
Type, for Water Main
WSWS 8.23.0 Miscellaneous for Water Pipe
WSWS 8.23.3 Nuts and Bolts
WSWS 8.24.0 Copper Water Tubing
WSWS 8.24.3 Fittings
WSWS 8.25.0 Cast Iron Service Boxes
CITY 8.25.4 Additional Requirements (added)
WSWS 8.26.0 Fire Hydrants
CITY 8.26.4 Additional Requirements (added)
WSWS 8.27.0 Gate and Resilient Wedge Valves
CITY 8.27.6 Resilient Wedge Valves (added)
CITY 8.27.7 Cut-in Valves and Sleeves (added)
WSWS 8.28.0 Butterfly Valves
CITY 8.28.6 Additional Requirements (added)
WSWS 8.29.0 Cast Iron Valve Boxes
CITY 8.29.4 Additional Requirements (added)
WSWS 8.30.0 Corporation Stops
CITY 8.30.2 Additional Requirements (added)
WSWS 8.31.0 Curb Stops
CITY 8.31.2 Additional Requirements (added)
WSWS 8.37.0 Mortar
WSWS 8.37.1 Materials
WSWS 8.38.0 Concrete Brick and Block Masonry Units
WSWS 8.38.3 Manhole Block Dimensions and Quality
WSWS 8.43.0 Bedding, Cover, Foundation, and Backfill Materials
WSWS 8.43.1 Requirements
WSWS 8.43.3 Cover Material for Pipe
WSWS 8.48.0 Manhole and Catch Basin Castings
CITY 8.48.1 Requirements
CITY 8.48.2 Manhole Castings (added)
CITY 8.48.3 Catch Basin Castings (added)
WSWS 8.49.0 Coal Tar Epoxy
CITY 8.56.0 Substitution of Materials (added)
411 AMENDMENTS TO WSWS PART IX - DETAIL DRAWINGS
412 ADDITIONAL DETAIL DRAWINGS FOR WATER AND SEWER CONSTRUCTION
413 REPAIR OF EXISTING SEWER AND WATER FACILITIES
413.1 Scope of Work
413.2 Remove and Replace Sewer Pipe
413.2.1 General
413.2.2 Sewer Pipe Materials
413.2.3 Installation
413.2.4 Aggregate Slurry Backfill
413.2.5 Granular Backfill
413.2.6 Surface Restoration
413.2.7 Measurement and Payment
413.3 Catch Basin Repair Work
413.3.1 General
413.3.2 Remove and Replace Catch Basin Structures
413.3.3 Catch Basin Frames and Grates
413.3.4 Catch Basin Structural Repairs
413.3.5 Aggregate Slurry Backfill
413.3.6 Curb and Gutter
413.3.7 Pavement Restoration
413.3.8 Ground Restoration
413.3.9 Measurement and Payment
413.4 Manhole Repair Work
413.4.1 General
413.4.2 Measurement and Payment
413.5 Manhole and Catch Basin Adjustments
413.5.1 General
413.5.2 Pavement and Subbase Restoration
413.5.3 Chimney Seals on Sanitary Sewer Manholes
413.5.4 Measurement and Payment
413.6 Manhole Removal and Replacement
413.6.1 General
413.6.2 Manhole Structures and Pipes
413.6.3 Aggregate Slurry Backfill
413.6.4 Granular Backfill
413.6.5 Frames and Covers
413.6.6 Chimney Seals at Sanitary Sewer Manholes
413.6.7 Surface Restoration
413.6.8 Measurement and Payment
413.7 Adjusting Valve Boxes
413.7.1 General
413.7.2 Payment
413.8 Aggregate Slurry Backfill
413.8.1 General
413.8.2 Measurement and Payment
414 MEASUREMENT AND PAYMENT
414. 1 General
414. 2 Pipe Sewers
414. 3 Manholes, Catch Basins, and Inlets
414. 4 Chimney Seals for Sanitary Sewer Manholes
414. 5 Sanitary Sewer Laterals
414. 6 Water Mains and Hydrant Leads
414. 7 Water Main Valves
414. 8 Hydrant Assemblies
414. 9 Water Service Laterals
414.10 Underdrain and Sump Drain Connection Lines
415 UNDERDRAINS AND SUMP DRAIN CONNECTION LINES
415.1 General
415.2 Trenches
415.3 Pipes
415.4 Connection to Structure
415.5 Cleanouts
415.6 Tracer Wire
415.7 Staking
415.8 Discharges at Ditches
416 AMENDMENTS TO WSWS PART VI – TRENCHLESS INSTALLATION OF UTILITIES
WSWS 6.2.3 Casing Pipe
WSWS 6.2.3(a)1 Types
WSWS 6.2.3(b)Inserted Pipe
CITY 6.2.3(c)Casing Spacers (Chocks)
CITY 6.2.3(d) General
CITY 6.2.3(e)Installation
WSWS 6.4.2 Materials
440 VIDEO INSPECTION OF SANITARY AND STORM SEWERS
440.1 Scope of Work
440.2 General
440.2.1 Videotape Equipment
440.2.2 Operating Environment
440.2.3 Footage Counter
440.2.4 Push Type Camera
440.2.5 Video Recorder
440.2.6 Tape Speed
440.3 Video Inspection
440.3.1 Cleaning of the Line
440.3.2 Excess Flow
440.3.3 Communication During Video Inspection Operations
440.3.4 Calibration and Display of Footage Measurements
440.4 Documentation of Results of Video Inspection of Sewers
440.4.1 Computerized Report
440.4.1.1 Format of Data for Computerized Report
440.4.2 Inspection Logs
440.4.3 Video Inspection Report
440.4.3.1 Format of Data on Video DVD
440.4.3.2 Narrative Report
440.5 Inspection of Work by City
440.6 Possession and Rights of Video and Reports
401 - GENERAL
401.1 Referenced Specifications
All materials and construction for storm sewers, sanitary
sewers, and water mains in the City of West Bend shall be in
accordance with the "Standard Specifications for Sewer and Water
Construction in Wisconsin," latest edition, with all current
supplemental specifications and addenda, (hereinafter referred
to as the Wisconsin Sewer and Water Specifications or WSWS), and
with the following modifications.
In the event a new edition or Addendum of the Wisconsin Water
and Sewer Specifications is issued and the WSWS section numbers
become changed, the text of the City's Standard Specifications
and its references to various WSWS sections shall still apply to
the appropriate renumbered WSWS section.
Various sections of the State of Wisconsin Department of
Transportation Standard Specifications for Highway and Structure
Construction - latest edition, with all current supplemental
specifications and addenda, are made part of the City's Standard
Specifications by reference. The aforementioned standard
specification is hereinafter referenced as the "Wisconsin DOT
Specifications", the "DOT Specifications", or as "WDOT".
In addition, the sewer and water work shall conform to the
requirements of the City's Standard Specifications of which this
section is a part.
401.2 Material Certificates
Prior to the start of construction, the Contractor shall furnish
the Engineer with certificates of certification for all water
and sewer pipe, valves, hydrants, and precast concrete manholes,
catch basins, and inlets. The certificates shall conform to the
requirements of Section 205.3 of the City's Standard
Specification.
REVISION DATE November 24, 1997 p. 400 - 1
402 - AMENDMENTS TO WSWS PART I - GENERAL CONDITIONS
WSWS 1.2.0 NECESSARY NOTICES AND PERMITS
WSWS 1.2.9 Notice for Local Sewerage District Connection
Delete this section in its entirety.
WSWS 1.3.0 CONTROL OF WORK AND MATERIALS
WSWS 1.3.14 Final Acceptance
Add:
"Final acceptance of sanitary and storm sewers will be
withheld until the system has been video taped, the results
have been reviewed by the City, and any defects have been
repaired."
WSWS 1.5.0 SCOPE OF WORK AND SPECIFIC INSTRUCTIONS
WSWS 1.5.6 Guarantee
Delete the first sentence and replace with the following
text:
All work shall be guaranteed for a period of one year from
the date of final acceptance as described in Section 104.16
of the City's Standard Specifications.
WSWS 1.6.0 EXTRA WORK AND CREDITS
WSWS 1.6.3 Basis of Payment or Credit for Altered Work
In subsection (a) delete the term "Schedule of Fixed Prices",
replace it with the term "Schedule of Supplemental Prices",
and add the following text:
"The Schedule of Supplemental Prices shall be as stated in
the Contract Documents."
WSWS 1.7.0 PROTECTION OF WORK - PUBLIC AND PRIVATE
WSWS 1.7.4 Flagman Required
Add:
"The Flagman shall have no duties other than directing
traffic."
WSWS 1.7.6 Dust Palliative
Remove the last sentence and insert:
"The cost of the dust palliative treatment or watering shall
be included as part of the unit cost for sewer and water
installation."
WSWS 1.7.7 Access to Properties
Add:
REVISION DATE p. 400 - 2
"The Contractor shall minimize the length of time that access
to private driveways is closed, and the property owner shall
be notified by the Contractor at least 24 hours prior to
closing the driveway to permit him to remove any vehicle from
the driveway. No private driveway shall be closed to travel
overnight or for more than one-half day without permission
from the Engineer."
WSWS 1.7.12 Traffic
Add:
"All existing streets, highways and roads will have a minimum
of one lane open to through traffic during construction at
all times. When obstructing the traffic on a roadway, the
Contractor shall have sufficient flagmen to control the flow
of traffic and the flagmen shall not be permitted to detain
traffic unnecessarily. When work is underway on
intersections, it shall be vigorously prosecuted to
completion so as to inconvenience traffic for a minimum time.
When the construction will inadvertently obstruct or in any
other way affect through vehicle traffic on State, County or
Town roads, the Contractor shall give sufficient notice to
the respective highway departments and shall furnish a copy
to the City Engineer. When the construction will
inadvertently obstruct or in any other way affect through
vehicle traffic on City streets, the Contractor shall give
sufficient notice to the City Engineer and/or Director of
Public Works. Prior to commencing work on the project, the
Contractor shall obtain any required permits, shall have such
permits available for inspection by the Engineer, and shall
furnish copies of the permits to the Engineer".
WSWS 1.8.0 LEGAL RELATIONS
WSWS 1.8.4 Liability and Insurance
Delete this section in its entirety, and replace with the
following:
"The Contractor shall obtain and maintain insurance meeting
the requirements of Section 105.7 of the City's Standard
Specifications."
WSWS 1.8.5 Contract Bond
Delete this section in its entirety, and replace with the
following:
"The Contractor shall furnish contract bonds meeting the
requirements of Section 103.4 of the City's Standard
Specifications."
REVISION DATE November 25, 2002 p. 400 – 3
403 - AMENDMENTS TO WSWS PART II - CONSTRUCTION - GENERAL
WSWS 2.1.0 GENERAL WORK PROVISIONS
WSWS 2.1.2 Protection of Existing Structures and Utilities
Add the following text:
"In the event the plans show the location of certain utilities
and/or structures both above and below ground, these locations
shall not be taken as conclusive. Verification to the
satisfaction of the Contractor of the exact location and
condition of all utilities and/or structures, whether shown on
the plans or not, shall be the responsibility of the
Contractor. The Contractor shall note that other utilities
and/or structures may exist within the project limits. No
additional costs shall be incurred by the City for utilities
which are not shown on the project plans and need to be
crossed, unless the utility substantially affects the line
and/or grades of the sewer or water piping. Prior to the
start of construction the Contractor shall contact Digger's
Hotline to have all existing utilities marked.
To avoid clogging or damaging water service laterals with
water softener materials at users not equipped with backflow
blocking check valves, the Contractor shall shut off the water
supply at the curb stop or at the water meter before
excavating across an existing water service lateral, before
disconnecting a service lateral from the existing main, and
before causing the loss of positive pressure in any water
service laterals or water mains. The Contractor shall notify
the water service user in accordance with the requirements of
Section 408.3.2 of the City's Standard Specifications. The
Contractor shall reopen the shut off valve after the water
service lateral is exposed and protected during the excavation
crossing.
If the Contractor's operations accidentally disrupt water or
sewer service to a user, the Contractor shall restore that
user's service immediately after such disruption occurs. All
service disruption restoration work associated with such
accidental disruption shall be performed by the Contractor at
no cost to the City."
WSWS 2.1.7 Housing for Inspectors
Delete this section in its entirety, and replace with the
following:
"If the Contractor maintains a temporary field office, it
shall be located and maintained at a mutually agreed upon
location. Upon completion of the work, it shall be removed
from the work site."
REVISION DATE p. 400 – 4
CITY 2.1.8 Separation of Water Mains and Storm or Sanitary Sewers
The minimum horizontal spacing of water mains with respect
to sanitary or storm sewers shall be eight (8) feet,
measured centerline to centerline. The minimum vertical
clearance between the outside diameters of water mains and
of sanitary or storm sewers shall be six (6) inches when
the water main crosses above the sewer and eighteen (18)
inches when the water main crosses under the sewer.
CITY 2.1.9 Separation of Water Laterals and Sewers
The minimum horizontal separation of water service laterals
with respect to sanitary sewers shall be:
a. Eight (8) feet if the water lateral is 2.5" diameter
or larger,
b. Eight (8) feet if the water and sewer laterals are
not installed concurrently (during the same
construction project),
c. When the water and sewer laterals are installed
concurrently and the water lateral is less than 2.5"
diameter, the minimum horizontal separation of the
centerlines shall be:
1. thirty (30) inches, or
2. less than thirty (30) inches provided that the
bottom of the water pipe is at least twelve
(12) inches above the top of the sewer pipe
The minimum horizontal separation of water service laterals
with respect to storm sewers shall be twelve (12) inches.
The minimum vertical clearance between the outside
diameters of the water service lateral and of sanitary or
storm sewers shall be twelve (12) inches when the water
lateral crosses above the sewer and at least eighteen (18)
inches when the water lateral crosses below the sewer.
REVISION DATE November 25, 2002 p. 400 - 4(A)
WSWS 2.2.0 EXCAVATION
WSWS 2.2.13 Dewatering Sumps and Pump Wells
Add the following text.
"Water from dewatering operations shall not be directly
discharged into any existing rivers, creeks, storm sewer systems,
wetlands, etc.. Silt from dewatering operations shall not be
allowed to enter any existing rivers, creeks, sewer systems,
wetlands, etc.. The Contractor’s dewatering operations shall
conform to the requirements of Section 802.7 of the City’s
Standard Specifications. Any silt that gets into existing
rivers, creeks, sewer systems, or wetlands, etc., shall be
removed by the Contractor at no expense to the City. The
Contractor shall advise the Engineer at the time of the
preconstruction meeting of how he intends to handle dewatering
and control sediments from the dewatering operations."
WSWS 2.2.15 Tree Clearing and Grubbing
Add the following text.
"Clearing and grubbing work shall conform to the requirements of
Section 303 of the City's Standard Specifications."
The sentence pertaining to pay items shall be changed to read:
"The cost of all clearing and grubbing shall be included in the
unit price bid for other items of work, provided that a unit
price specifically for clearing and grubbing is not included in
the contract."
WSWS 2.6.0 BACKFILLING
WSWS 2.6.1 Excavated Material for Backfill
Delete the entire text of this section and replace with the
following text.
"Native material excavated from a trench may be used for
backfilling in trenches when approved by the Engineer, provided
the native material meets the requirements of WSWS 8.43.5. If
used, native material shall be free of frozen materials or of
materials larger than six (6) inches in diameter. If detrimental
materials are encountered during excavation of the trench, the
Contractor shall separate suitable material from unsuitable or
rejected material. All unsuitable or rejected material shall
become the property of the Contractor and shall be properly
disposed of by the Contractor.
When the Engineer rejects native material (or a portion of the
native material) for backfilling trenches, the Contractor shall
be compensated for furnishing and placing granular backfill
material, as described below, at the unit price contained in the
Contractor's original bid proposal. The granular backfill
material shall conform to the requirements of WSWS 8.43.4.
If the deficiency of backfill materials is caused by improper
protection of the trench or by improper compaction methods (as
determined by testing procedures standard to the industry), the
material needed to make up the deficiency shall be furnished and
installed by the Contractor at no additional cost to the City.
If a bid item for "Furnish Granular Backfill Material" is
included in the Bid Proposal, it is included for the sole purpose
REVISION DATE November 26, 2007 p. 400 - 5
of determining a unit price for granular backfill should the City
Engineer determine it to be necessary as described above. The
Contractor, by way of this provision, acknowledges and agrees
that excavated material is to be utilized for backfill material
and determination for the necessity of, and payment for, granular
backfill material is at the sole discretion of the City Engineer.
The unit price for "Furnish Granular Backfill Material" shall
include all costs associated with excavating, hauling and
properly and legally disposing of the detrimental material
offsite; furnishing, hauling, placing, and compacting granular
backfill material; and all equipment, materials, tools, labor,
supervision, supplies, and other incidentals necessary to
complete the work. The Contractor shall provide the Engineer
with all load tickets for all granular backfill material placed
as backfill during construction. The Contractor shall provide
the Engineer with a Proctor and sieve analysis report on the
granular backfill material for review and approval prior to any
backfill material being placed. Measurement and payment for
"Furnish Granular Backfill Material" will be made per ton placed.
If a quantity for granular backfill material is included in the
Bid Proposal, the quantity and unit price might be used in
evaluating the bids and in recommending which Contractor should
be awarded the contract. The actual quantity used will likely
vary significantly from the quantity in the Bid Proposal.
WSWS 2.6.2 Granular Backfill
Add the following text:
"The bid price for sewer and water main construction shall
include the cost of furnishing and installing the granular
backfill in trenches. The granular backfill shall conform to the
requirements of either WDOT 209.1 to WDOT 209.3 for gradation
number 2 or of WSWS 8.43.4. The use of crushed asphaltic
concrete pavement (a.k.a. millings) for backfilling of trenches
for water and sewer pipes is prohibited."
WSWS 2.6.3 Granular Backfill Credits
Delete the entire text of this section.
WSWS 2.6.5 Support of Underground Structures
Delete the entire text of this section and replace with the
following:
"Concrete backfill or cellular concrete which conforms to the
requirements of WSWS 8.35.4 or 8.35.5, respectively, shall be
used to support sewers, building sewers, water mains, and other
utilities crossing trenches. The minimum dimensions around a
utility crossing the pipeline that shall be backfilled with
concrete backfill or cellular concrete shall be from twelve (12)
inches below the utility to half way up the utility and twelve
(12) inches on each side of the pipeline along the section of the
utility exposed.
All costs associated with supporting, protecting, and backfilling
around existing utilities located near and/or across the pipeline
as described above shall be included in the unit prices for the
pipeline. Any damage caused to any existing utilities during
work on the project shall be repaired and/or replaced by the
Contractor at no expense to the City."
REVISION DATE November 26, 2007 p. 400 – 6
WSWS 2.6.7 Placing of Backfill
Add the following text:
"If the Special Provisions or the Engineer allows the
Contractor to use pea stone, stones, or material that contains
a large percentage of voids for bedding or backfilling within
paved areas (or areas to be paved) at manholes, catch basins,
valve boxes, or trenches, the Contractor shall furnish and
install geotextile fabric over the top of the "high-voids"
material. The geotextile fabric shall conform to the
requirements of Section 645.2.2 of the Wisconsin DOT
specifications for Type SAS fabric. All costs associated with
furnishing and installing the geotextile fabric shall be
included in the cost of the item causing the need for the
bedding or backfill."
WSWS 2.6.8 Upper Level of Backfill
Delete the last sentence which reads:
"The Contractor shall backfill the remaining section of the
trench with excavated material."
WSWS 2.6.9 Minimum Backfill and/or Cover
The required cover above the outside top of all water pipe
shall be changed from a minimum five (5) feet to a minimum six
(6) feet.
The last two sentences shall be changed to read as follows:
"Excavated material meeting the requirements of WSWS 8.43.5
shall be used as a backfill only as allowed in WSWS 2.6.1 and
shall be deposited in maximum 12-inch layers. Each layer
shall be thoroughly compacted and subject to density testing
by the City."
WSWS 2.6.14 Consolidation of Backfill
Delete this entire section and refer to Section 305.0 of the
City's Standard Specifications for compaction requirements.
WSWS 2.6.16 Maintenance of Trench Surface
Add:
"This section shall apply only to those trenches made in
existing pavement."
WSWS 2.7.0 SURFACE REPLACEMENT AND SITE RESTORATION
WSWS 2.7.1 Optional Replacement
This section shall be deleted in its entirety.
WSWS 2.7.3 Replacement of Pavements
Add the following text before the existing second paragraph.
"The Contractor shall set the rim elevations of manholes,
catch basins, and valve boxes in new pavement and in
replacement pavement so that the rims are one-eighth (1/8)
inch to one-quarter (1/4) inch below the finished surface of
the pavement."
Add the following text:
"If the Contract Documents require the Contractor to
replace the pavement and crushed aggregate base course, the
work shall conform to the following additional requirements."
REVISION DATE December 15, 2008 p. 400 - 6(A)
1. Crushed Aggregate Base Course
The crushed aggregate base course shall be constructed to
the thicknessess and of the materials specified in the
Contract Documents.
2. Pavement
The pavement shall be constructed to the thicknesses and
of the materials specified in the Contract Documents.
Pavement construction shall conform to the requirements of
the City's Standard Specifications, Section 500 for
Concrete and Section 600 for Asphaltic Concrete. If the
Contract Documents require temporary pavement, it shall
conform to the requirements of Section 606.2.4 of the
City's Standard Specifications.
3. Compaction
All replacement crushed aggregate base course and
asphaltic concrete pavement shall be mechanically
compacted in accordance with Sections 305.0 and 605.5, and
to the degree of compaction specified in Sections 305.5.3
and 605.5, respectively, of the City's Standard
Specifications.
4. Saw Cutting
Prior to removal of existing pavement and/or prior to
placement of replacement gravel and pavement, the
Contractor shall saw cut existing pavement around the
excavated trench area to form straight edges."
WSWS 2.9.0 PAY MEASUREMENT
Delete the following sections. These sections are replaced by
Section 414 of the City's Standard Specifications.
WSWS 2.9.2 Pay Measurement for New Building Sewers.
WSWS 2.9.3 Pay Measurement for Relaid Building Sewers
and Drains
WSWS 2.9.6 Pay Measurement for Hydrant Branch
WSWS 2.9.7 Pay Measurement for Hydrants
WSWS 2.9.12 Pay Measurement for Manholes (Excluding Tee
Manholes)
WSWS 2.9.14 Pay Measurement for Catch Basins and Storm
Water Inlets
WSWS 2.9.15 Pay Measurement for Manhole and Catch Basin
Adjustment
REVISION DATE December 15, 2008 p. 400 - 7
WSWS 2.9.17 Pay Measurement for Clearing and Grubbing
Shall be amended to read:
"The cost of all clearing and grubbing encountered by the
Contractor shall be included in the unit price bid for other
items of work, provided that a unit price specifically for
clearing and grubbing is not included in the contract."
WSWS 2.11.0 ALTERNATE LOCATING REQUIREMENT
WSWS 2.11.2(b) Insulation Color
Delete the text of subsection 1 and replace with the following
text:
"1. The color for sanitary sewer mains and laterals and for
force mains shall be green. The color for storm sewer mains
and laterals shall be brown. "
WSWS 2.11.2(e) Wire Splice
Delete the text and replace with the following test:
"Splices in tracer wire for the initial installation of water
and sewer laterals are not allowed. For splices in repairs of
damaged existing tracer wire, use splicing assemblies
specified in Details 461, 462, and 463 of the City’s Standard
Specifications. "
REVISION DATE December 15, 2008 p. 400 - 7(A)
404 - AMENDMENTS TO WSWS PART III -
CONSTRUCTION - STORM AND SANITARY SEWER
WSWS 3.2.0 LAYING OF PIPE SEWERS
WSWS 3.2.6 Pipe Sewer Bedding Sections
1. Add to WSWS 3.2.6(a) Standard Section (Class C) the
following text:
"Class C bedding shall be required unless otherwise
specified."
2. The following sections shall be deleted unless the
deleted bedding sections are ordered as an extra by
the Engineer:
WSWS 3.2.6(b) Compacted Section (Class B)
WSWS 3.2.6(c) Concrete Cradle (Class A)
WSWS 3.2.6(d) Concrete Cap (Class A)
WSWS 3.2.6(e) Concrete Envelope
WSWS 3.2.6(f) Trench Restoration
WSWS 3.2.10(b)1a (Type of Joint to be Used on Concrete Pipe Storm Sewers)
Delete "cement mortar".
Cement mortar joints in concrete storm sewer pipe will not
be allowed. Concrete collars made of mortar and solid
concrete bricks may be used at the last pipe joint when
laying toward a manhole or other structure.
WSWS 3.2.24 Abandoned Sewers, Drains, and Sewer Structures
In the second sentence delete "15 inches and larger".
WSWS 3.2.27 Connections to Existing Manholes or Existing Sewers
Add the following text:
"Connection of sanitary laterals to sanitary mains shall be by
use of wyes or saddles rotated 45° from vertical in a cross section view and with its horizontal component of flow
direction in the same direction as flow in the main. See
Detail 430.
The cost for all sewer connections to existing manholes or
sewers shall be included as part of the unit price bid for the
sewer installation."
WSWS 3.2.28 Connections to New Sewers
Add the following text:
"The requirements of Section 3.2.27 shall also apply to the
connection of building sewers or drains to new sewers."
CITY 3.2.29 Connections of Pipe to Structures
Using concrete brick and mortar or concrete, the Contractor
shall seal the entire joint formed where the sewer pipe
connects to a manhole or catch basin/inlet structure. The
joint shall be mortared all around the pipe inside and outside
the structure to form a seal and shall be finished to provide
a smooth-contoured brushed surface. No exposed edges, bumps,
or shoulders that frost or frost heaving may push on will be
allowed at the joint.
REVISION DATE November 27 2006 p. 400 - 8
WSWS 3.3.0 MONOLITHIC CONCRETE SEWERS AND APPURTENANCES
Delete this entire chapter.
WSWS 3.4.0 RECONNECTING BUILDING SEWERS, STORM WATER DRAINS AND
UTILITY DRAINS
WSWS 3.4.2 Branch Fittings, Pipe, and Joints
Add the following text:
"The preferred method of connecting sanitary laterals to
sanitary sewer mains is by use of wyes rotated 45° from
vertical in a cross section view and with its horizontal
component of flow direction in the same direction as flow in
the main."
Add the following note to Table 4:
"Where the existing material of service or drain pipe
encountered is clay, the pipe material to be used for
reconnection shall be either PVC, as specified in WSWS 8.10.1,
or Extra Strength Vitrified Clay."
REVISION DATE December 13, 2004 p. 400 - 8(A)
WSWS 3.5.0 MANHOLES
WSWS 3.5.3 Types of Manholes
Delete this entire section and replace with the following:
"The Contractor shall backplaster the manhole chimney to a
brush finish.
Precast concrete manholes will be used at all times for
sanitary and storm manholes, unless monolithic concrete
construction or solid concrete block construction has been
authorized by the Engineer. Manholes constructed with hollow
block are not allowed and no exceptions will be allowed. The
manholes shall be constructed to conform with the requirements
of WSWS 8.39.0 and the details shown in the detail section of
the City's Standard Specifications.
The orientations of the manhole access openings and steps with
respect to the sewer pipe are different for storm and sanitary
manholes and are indicated on Details 401 and 402,
respectively.
The Contractor shall submit manufacturer's certificates for
the precast concrete manholes to the Engineer prior to using
them on the project. The certificates shall state that the
manholes conform to the requirements of ASTM C-478 and shall
be signed by an authorized representative of the manufacturer.
All sanitary and storm manholes shall be four (4') feet inside
diameter, unless otherwise specified by the Engineer."
WSWS 3.5.4 General Requirements
1. Add to WSWS 3.5.4(d) (Walls, Corbels, and Chimneys) the
following:
"Chimney seals covering the joint at the top of the
corbel, all grade ring joints, and the joint at the
bottom of the frame casting are required for all sanitary
manholes. The chimney seals shall conform to the
requirements of WSWS 8.42.0. The Chimney seals for all
new or reconstructed sanitary manholes shall be
"Internal/External Adaptor Seals" as manufactured by
Adaptor, Inc. (West Allis, WI), or equal. The Contractor
shall install the chimney seals in accordance with the
manufacturer's written instructions. The Contractor
shall not backfill the internal/external chimney seal
until the Engineer has inspected and approved its
installation.
The Contractor shall backplaster the area of the grade
rings for storm and sanitary manholes to provide a smooth
contoured brushed finish."
2. Change in WSWS 3.5.4(e) (Castings) the following:
The second sentence of the first paragraph shall be
changed to read:
REVISION DATE November 26, 2007 p. 400 - 9
"These manhole castings shall conform to the requirements
of WSWS 8.48.0 and of Detail 411 or 412 for sanitary
sewer manholes and Detail 413 for storm sewer manholes."
3. Add to WSWS 3.5.4(i)2(a) the following:
"When flexible butyl rubber gasket material is used to
seal joints in sanitary manholes, the gasket shall be
installed on both horizontal surfaces of each joint
seam."
4. Add to WSWS 3.5.4(i)3(b) the following:
"When flexible butyl rubber gasket material is used to
seal joints in storm manholes, the gasket shall be
installed on the outermost horizontal surface of each
joint seam."
CITY 3.5.7(d) Sealing of Connection
The Contractor shall seal the area around the pipe connection
with a mortar mix to prevent the accumulation of waste
materials within the area of the void between the pipe and the
manhole structure. The mortar shall be packed into the void
and troweled off.
City 3.5.7(e) Outside and Inside Drops at Sanitary Sewer Manholes
All connections of sanitary sewer pipe (including private
sanitary sewer laterals) to manholes that require a drop in
elevation greater than two (2) feet between the invert
elevation of the pipe and the bench of the manhole shall be
made utilizing outside drops only. No inside drops are
allowed, unless approved by the City Engineer. All outside
drops shall be encased in Class "D" concrete with a minimum of
4" of concrete cover around the pipe.
If the use of an inside drop at a private lateral is approved
by the City Engineer, it shall have a PVC drop bowl without
hood, 11 gauge 304 stainless steel clamping brackets and
bolting hardware, PVC schedule 40 pipe and bottom elbow. A
City-approved manufacturer of the inside drop assembly is
Reliner/Duran Inc. with telephone number 800-508-6001 and web
site of www.reliner.com. The inside drop shall be installed
in accordance with the manufacturer’s recommendations.
WSWS 3.5.8 Special Types of Manholes
Change the standard manhole diameter from 3 feet, 6 inches to
4 feet, 0 inches.
WSWS 3.5.8(d)1 Precast Manhole Flexible Connection
Delete the text of this section and replace with the
following:
"When an outside drop connection is made to a precast manhole
with a flexible connection as required in Section 3.5.7(c), it
shall be constructed as shown on Detail 406."
REVISION DATE December 17, 2012 p. 400 – 10
WSWS 3.6.0 CATCH BASINS, STORM WATER INLETS AND STORM WATER DRAINS
WSWS 3.6.1 Catch Basins
Delete this entire section and replace with the following:
"Precast concrete catch basins will be used at all times,
unless monolithic concrete construction or solid block
concrete construction has been authorized by the Engineer.
Catch basins constructed with hollow block are not allowed and
no exceptions will be allowed. The catch basins shall be
constructed to conform with the requirements and details shown
in the detail section of the City's Standard Specifications.
The Contractor shall backplaster the area of the grade rings
of catch basins and inlets to provide a smooth contoured
brushed finish."
The Contractor shall submit manufacturer's certificates for
the precast concrete catch basins to the Engineer prior to
using them on the project. The certificates shall state that
the catch basins conform to the requirements of ASTM C-478 and
shall be signed by an authorized representative of the
manufacturer."
WSWS 3.6.2 Trapped Sewer Catch Basin
Delete this entire section.
WSWS 3.6.3 Storm Water Inlet
Delete the text of this section and replace with the
following:
"Where storm water inlets are approved by the City Engineer in
lieu of catch basins, such inlets shall be of precast
concrete, unless monolithic concrete construction or solid
block concrete construction has been authorized by the
Engineer. Storm water inlets constructed with hollow block
are not allowed and no exceptions will be allowed. The inlets
shall be constructed to conform with the requirements and
details shown in the detail section of the City's Standard
Specifications.
The Contractor shall submit manufacturer's certificates for
the precast concrete inlets to the Engineer prior to using
them on the project. The certificates shall state that the
inlets conform to the requirements of ASTM C-478 and shall be
signed by an authorized representative of the manufacturer."
REVISION DATE December 1, 2003 p. 400 – 10(A)
405 - ADDITIONAL CITY REQUIREMENTS FOR SANITARY SEWER CONSTRUCTION
405.1 Television Inspection
On projects where the City is the Owner, the City will perform a
television inspection of the mainline sewer pipe upon completion
of all construction on the project and before final acceptance of
the project. The initial television inspection of the sewer will
be done by the City at no cost to the Contractor. Any recleaning
or revideotaping of the sewer required due to problems noted by
the initial videotaping, will be charged to the Contractor. The
City normally does not perform such television inspections
between the dates of November 15, and March 15, inclusively.
At no cost to the City the Contractor may have another party
perform interim videotape inspection of the sewer lines on the
project before all work on the project is completed.
When the City is not the Owner of the sewer line, the Contractor
or Owner shall have another party perform the cleaning and
television inspection at no cost to the City, and a VHS videotape
of the inspection shall be furnished to the City for keeping.
Television inspections performed by other parties shall conform
to the requirements of Section 440. All television inspections
shall be completed and videotapes made available for the City's
review prior to acceptance by the City.
All sewers shall be cleaned of all sediment and debris prior to
videotaping. The cleaning shall be performed using high pressure
jetting equipment and in such a manner as to prevent sediment and
debris from entering other sewer lines.
For new sewer lines, any of the following defects evident from
the television inspection shall be repaired by the Contractor and
shall be revideotaped for acceptance after the repair. The
following list represents some defects that will not be accepted.
The list is not all-inclusive.
a) Dips in pipe exceeding one-eighth of the internal diameter or
1.5 inches, whichever is the lesser value, when the slope of
the pipe is greater than or equal to one percent (1%).
b) Dips in pipe exceeding one (1) inch when the slope of the pipe
is less than one percent (1%).
c) Cracked, broken, or ovalled pipe.
d) Infiltration at joints or along the pipe.
e) Bulges in the pipe.
REVISION DATE November 26, 2001 p. 400 - 11
405.2 Adjusting Manhole, Catch Basin, and Inlet Frames and Covers
The Contractor shall adjust manholes, catch basins, and inlets in
accordance with WDOT 611.3.7.
Delete the third sentence of WDOT Section 611.3.7(1) and replace
with the following sentence. "
Support the fixture on precast concrete grade rings, constructed
to hold the covers firmly in place."
Delete WDOT Section 611.3.7(3) in its entirety.
Solid concrete block, concrete bricks, or metal wedges and shims
are preferred for the adjustment of frames. If wooden wedges or
shims are used they shall be removed and the area tuckpointed
prior to the acceptance of the work.
When adjusting casting are used at sanitary manholes, the
Contractor shall seal the seam between the adjusting casting and
the manhole frame with a butyl rubber caulk.
If a centering tab exists on the manhole lid of a manhole
adjustment using an adjusting casting, the Contractor shall
remove the centering tab before making the elevation adjustment.
405.3 Sanitary Sewer Pipe Materials
Unless otherwise specified in the Contract Documents, all pipe
and fittings used to repair or initially install sanitary sewer
pipe for mains, risers, and service laterals shall be as follows.
Depth (feet)
to Invert
Elevation of Pipe Pipe Description Specification
through 15 feet PVC SDR35 ASTM D3034
greater than 15 feet PVC SDR 26 or ASTM D3034
PVC DR25, DR18, or DR14 AWWA C-900
All sanitary sewer pipe and fittings shall conform to the
requirements of the specifications listed above and of WSWS
8.10.0.
REVISION DATE December 17, 2012 p. 400 - 11(A)
406 - ADDITIONAL CITY REQUIREMENTS FOR STORM SEWER CONSTRUCTION
406.1 Television Inspection
Allowable dips in storm sewers shall be as specified in WSWS 3.2.4.
All other requirements of Section 405.1 are applicable also to the
construction of storm sewers.
406.2 Culverts
The following sections of the Wisconsin DOT Specifications are by
reference made a part of the City's Standard Specifications.
WDOT 520 Pipe Culverts
WDOT 521 Corrugated Steel Pipe Culverts
WDOT 522 Reinforced Concrete Pipe Culverts
WDOT 523 Reinforced Concrete Horizontal Elliptical Pipe
Culverts
WDOT 524 Salvaged Pipe Culverts
WDOT 525 Corrugated Aluminum Pipe Culverts
Measurement and payment for culverts shall be in accordance with
the requirements of the referenced WDOT sections.
406.3 Riprap
The following sections of the Wisconsin DOT Specifications are by
reference made a part of the City's Standard Specifications.
WDOT 606 Riprap
WDOT 645 Geotextile Fabrics
Prior to using the riprap, the Contractor shall notify the Engineer
of his source for the riprap and arrange for the Engineer to
inspect the riprap at its source to verify that the weight of the
stone pieces meets the requirements of the specifications.
The Contractor shall place all riprap onto Geotextile Fabric, Type
R or Type HR as specified in the Contract Documents. The
materials, installation, measurement, and payment shall conform to
the requirements of WDOT 645.
Measurement and payment for riprap shall be in accordance with the
requirements of WDOT 606.
406.4 Trash Racks at Storm Sewer Outfalls
406.4.1 General
The Contractor shall furnish and install a trash rack at the
outfall of storm sewers where indicated in the Plans or Contract
Documents.
REVISION DATE November 20, 2000 p. 400 - 12
The bars shall be placed horizontally at the outfall end of the
pipe and shall be held in place in some manner as to prevent
removal of the rack except for maintenance purposes. The maximum
clear spacing of the horizontal tubes or bars shall be six (6)
inches, and the minimum clear spacing shall be four (4) inches.
The grate shall be hot-dipped galvanized after fabrication or
shall be constructed of corrosion resistant material approved by
the Engineer.
406.4.2 Measurement and Payment
Trash racks for storm sewer outfalls will be measured by the unit
complete in place, and the quantity to be paid for shall be the
number of units of each size incorporated in the work and
accepted in accordance with the contract.
As specified in the Contract Documents, the cost of the trash
racks shall be included in the contract unit prices for storm
sewer outfalls, or the quantity of trash racks will be paid for
at the contract unit price for each of the trash rack sizes
specified. The contract unit price shall be payment in full for
furnishing, transporting, and installing the trash racks,
including connections, and for all labor, supervision, equipment,
materials, tools, supplies, and incidentals necessary to complete
the work.
406.5 Adjusting Manholes & Catch Basins/Inlets
See Section 405.2 regarding manhole adjustments which shall also
apply to storm manholes, catch basins and inlets.
REVISION DATE December 17, 2012 p. 400 - 13
406.6 HDPE Pipe for Cross Country Storm Sewers
If specified in the Contract Documents for City contracts or if
approved by the City Engineer on private development projects,
corrugated high density polyethylene (HDPE) pipe with smooth
interior may be used for cross country storm sewers in areas where
vehicular traffic is not expected to occur.
The pipe and fittings shall conform to the retirements of AASHTO
M294 or ASTM F-667 and shall be installed in accordance with the
pipe manufacturer's written installation procedures and
recommendations.
REVISION DATE December 13, 2004 p. 400 - 13(A)
407 - AMENDMENTS TO WSWS PART IV - CONSTRUCTION - WATER MAIN
WSWS 4.3.0 LAYING OF WATER MAIN
WSWS 4.3.12 Method of Chlorination
Delete the entire text of WSWS 4.3.12 and replace with the following
wording:
"Water mains shall be disinfected in accordance with the
requirements of ANSI/AWWA C651, latest edition, Standard for
Disinfecting Water Mains. Sodium hypochlorite in liquid form and
either the continuous-feed method or the slug method shall be used
to disinfect water mains. Calcium hypochlorite tablets or granules
shall not be used for disinfecting water mains. The sodium
hypochlorite liquid will be furnished by the Water Utility at no
charge to the Contractor."
WSWS 4.3.13 Thrust Restraints
Add the following text:
"The Contractor may use solid concrete block for thrust or reaction
backing for water mains of twelve (12) inch diameter or less unless
the trench walls are unstable.
In addition to thrust restraints, the contractor shall provide one
of the following:
1. Tie rod strapping as per WSWS 4.9.1 wrapped with polyethylene.
2. Wedge action joint mechanism such as Series 1100 "Megalug" as
manufactured by EBAA Iron, Inc. or equal.
WSWS 4.4.0 DUCTILE IRON WATER MAIN
WSWS 4.4.2 Joints
In section 4.4.2(b)4, delete the entire text of the last sentence
which starts with "After a joint...".
Delete the entire text of WSWS 4.4.2(c) (lead joints), including
Table 9, and replace with the following wording:
"The use of lead joints and of lead wedges or gasket tips is
prohibited on water distribution projects in the City of West Bend."
CITY 4.4.2(d) Electrical Continuity
The Contractor shall provide for electrical continuity
throughout the new water main using either copper cables or
copper straps. Bolts of mechanical joints and Megalugs shall
not be considered to provide electrical continuity. Wedges
or gasket tips made of either lead or brass are not allowed.
REVISION DATE December 13, 2004 p. 400 – 14
WSWS 4.4.4 Polyethylene Wrap
Add the following text after the first paragraph:
"The City reserves the right to require double wrapping of the
pipe with polyethylene in lieu of single wrapping. If double
wrapping of the pipe is required, it will be specified on the
Plans or in the Contract Documents. The Contractor shall double
wrap all valves and fittings.
When installing polyethylene wrap at hydrant assemblies, the
Contractor shall not wrap the base of the assembly in such a
manner that would interfere with the drainage of the hydrant
assembly".
WSWS 4.5.0 PRESTRESSED CONCRETE WATER MAIN
Delete this chapter in its entirety and replace with the
following:
"The use of prestressed concrete pipe is not allowed on water
distribution projects in the City of West Bend."
WSWS 4.8.5 INSTALLING HYDRANTS
Add the following text:
"The Contractor shall utilize handling techniques and
installation procedures that will protect the manufacturer’s
protective coating of the hydrant. If the coating is or becomes
damaged, the Contractor shall repair the coating in strict
conformance with the manufacturer’s written procedures."
REVISION DATE December 17, 2012 p. 400 - 14(A)
WSWS 4. 9.3 Protective Coatings
Delete this section in its entirety.
WSWS 4.10.0 GRADE AND DIRECTION CHANGES
WSWS 4.10.2 Grade Changes for PVC Main
Delete this section in its entirety.
WSWS 4.11.0 VAULTS
Delete this entire chapter.
WSWS 4.13.0 BORING AND JACKING
WSWS 4.13.2 JACKING
Add the following text:
"Unless otherwise specified in the Contract Documents, all water
main pipe to be installed in casings shall have restrained push-on
type joints such as "Snap-Lock Restrained Joint Ductile Iron Pipe"
by Griffin Pipe Products, "Super Lock Joint Pipe" by Clow Corp., or
an approved equal. Wedge action joint mechanisms such as "Megalug"
or joint restraint mechanisms such as "Uniflange" will not be
allowed within casings.
The Contractor shall furnish and install casing chocks where the
water main is installed within casings. The casing chocks shall
have a non-metallic liner to isolate the water main from the chock
and shall provide a minimum of 0.75 inches clearance between the
greatest outside diameter of the water main and the inside diameter
of the casing. The casing chocks shall be attached to the water
main at ten (10) foot spacing and shall be installed in accordance
with the manufacturer's instructions. The casing chocks shall be
Model 4810 as manufactured by Power Seal Pipeline Products Corp., or
approved equal.
After installing the water main in the casing, the Contractor shall
then seal the ends of the casing to prevent sediment from entering
the casing. No casing filler is required. Unless otherwise
specified in the Contract Documents, all casing chocks, pipe and
other materials needed for installing the water main in the casing
and for sealing the ends of the casing shall be furnished by the
Contractor and the cost of furnishing and installing the materials
shall be included in the bid price for the appropriate size of water
main pipe.
REVISION DATE November 22, 1999 p. 400 - 15
WSWS 4.14.0 CONNECTION, REMOVAL AND ABANDONMENT
WSWS 4.14.3 Connection Mains
Add the following text:
"The Contractor shall notify the City of West Bend Water Utility
by noon of the previous work day prior to the scheduled
connection of a new water main to an existing water main."
CITY 4.14.7 Operation of Existing Valves
The Contractor is not to operate any existing valves in the
water distribution system. Only Water Utility personnel are
authorized to operate the existing valves.
WSWS 4.15.2 Pressure Test
Add the following text:
"The pressure test shall be made against each valve. The test
shall be rerun if there is any drop in pressure during the
testing period specified."
WSWS 4.16.0 DISINFECTION OF WATER MAINS
CITY 4.16.7 Chlorination, Sampling and Testing
The Contractor shall be responsible for swabbing all water
main pipes, if necessary. Only liquid chlorine shall be used.
The Water Utility will supply all liquid chlorine for swabbing
pipes. Water Utility personnel will be responsible for all
chlorination of the new water main. The Contractor shall
provide all equipment and labor to flush the new water main.
The Contractor shall coordinate with the Water Utility for the
flushing of the water main. The Contractor shall NOT operate
any valves or hydrants that existed on the water distribution
system prior to the Contractor's construction operations on
the project. Only Water Utility personnel are authorized to
operate such valves and hydrants on the existing system.
Water Utility personnel will obtain all necessary water
samples and will make all decisions regarding rechlorination.
The flushing and chlorination of water mains shall be in
accordance with the requirements of WSWS 4.3.12, WSWS 4.16.0
and AWWA C-651, latest edition.
WSWS 4.17.0 INSULATION
Delete the text of this section and replace with the following:
CITY 4.17.1 General
Water mains and building water services shall be insulated
where noted on the plans and wherever the depth of cover is
less than six (6.0) feet, or wherever there is less than two
(2) feet of separation between the water pipe and any storm
sewer pipe or other open structures.
REVISION DATE December 17, 2012 p. 400 - 16
CITY 4.17.2 Water Main Insulation
The insulation for water mains shall be polystyrene boards.
Polystyrene boards conforming to WSWS 8.50.2 shall be
installed as follows (See Detail 433):
1. Prior to placing the polystyrene boards, the Contractor
shall place, level, and compact bedding material to a
height of (6") inches over the top of the pipe.
2. The insulation boards shall be placed on the cover
material with the long side parallel to the centerline of
the water main. If two (2) or more layers of insulation
board are used, each layer should be placed so as to cover
the joints of the layer immediately below. The insulation
boards shall be centered over the pipe.
3. The first lift of backfill material shall consist of six
(6") inches of bedding material which shall be end or side
dumped onto the insulation board and spread in such a
manner that construction equipment does not operate
directly on the insulation. This layer shall be compacted
to the specified density. The remaining layers of
backfill may be constructed utilizing conventional
procedures.
CITY 4.17.3 Building Water Service Insulation
The insulation for building water services shall conform to
section WSWS 4.17.2 with the addition of neoprene pipe wrap.
Neoprene pipe wrap shall be installed prior to insulating the
building water service in accordance with section WSWS 4.17.2.
(See Detail 433)
Neoprene pipe wrap shall be commercially available preformed
insulation material with a minimum wall thickness of five
eighths (5/8") inch for three quarter (3/4") inch and one (1")
inch building water services. For building water services
larger than one (1") inch in diameter, the size of the
neoprene pipe wrap shall be subject to approval by the
Engineer.
REVISION DATE DECEMBER 17, 2012 p. 400 - 16(A)
408 - ADDITIONAL CITY REQUIREMENTS FOR WATER MAIN CONSTRUCTION
408.1 Electrical Continuity Test
Following completion of installation of the water main, the Engineer
reserves the right to select a random section of the main for an
electrical continuity test. The Contractor shall notify the water
utility at least twenty-four (24) hours in advance before performing
this test. This random section shall be subjected to 300 amps AC and
DC for fifteen minutes. All equipment necessary to establish a closed
circuit, with the test section of water main providing one leg of the
circuit, shall be provided by the Contractor at no additional cost to
the City.
If the random section passes the test, the electrical continuity for
the entire water main installation will be considered acceptable.
Should the random section fail the test, it shall be repaired by and
at the expense of the Contractor and shall be retested by the
Contractor. This process shall continue until the water main passes
the test. In addition, if the random section fails the test, the
remainder of the project will be divided into test sections by the
Engineer and tested for specification compliance, by and at the
expense of the Contractor.
After the test is satisfactorily completed, the Contractor shall
remove all testing equipment and materials from the water main.
408.2 Existing Sanitary Sewer, Storm Sewer, and Water Main
The Contractor shall take appropriate action to ensure that no silt or
backfill material enters the existing sanitary sewer, storm sewer, or
water main lines or new water main. Any material that enters the
existing or new utilities as a result of the construction shall be
cleaned by the Contractor at no expense to the City.
408.3 Re-Laying Water Mains
When the Contractor is required to lay a new water main to replace an
existing, in-use, water main, the Contractor shall comply with the
following additional requirements.
408.3.1 Installation Sequence
The Contractor shall coordinate the installation, flushing, and
testing of the new water main system, reconnection of existing water
service lines, and abandonment of the existing water main so as to
cause minimum interruption of water service to each user within the
project limits. The Contractor shall prepare an installation
sequence, and submit it at the preconstruction conference for review
and approval by the Engineer. The
REVISION DATE p. 400 - 17
Contractor shall keep the existing water main system fully operational
until the new water main has been tested and satisfactory water
quality samples obtained. Only after the new water main is tested and
a satisfactory water quality sample is obtained, may the Contractor
begin reconnecting the existing water service lines to the new water
main.
408.3.2 Service Disruption Notification
When a water main needs to be shutoff during construction activities,
the Contractor shall notify the West Bend Water Utility at least
forty-eight (48) hours prior to the shutoff. The West Bend Water
Utility will notify the users in the shutoff section about the coming
service disruption.
When a water service lateral needs to be shut off or replaced during
construction activities, the Contractor shall notify the user and the
Water Utility at least four (4) hours prior to the service disruption
for residential users and at least twenty-four (24) hours prior to the
service disruption for business users.
If water service to any user is accidentally disrupted by the
Contractor's operation, the Contractor shall immediately notify the
user and the West Bend Water Utility of the disruption and the
estimated time the restoration of the service will be complete.
408.3.3 Water Service Reconnections
Unless otherwise specified, all water service pipes shall be copper
water tubing of the diameter specified in the Contract Documents.
After reconnecting the water services to the new water main, the
Contractor shall leave the corporation stops on the existing water
main in the closed position, and shall open the corporation stops on
the new water main.
408.3.4 Abandonment of Existing Water Main
When specified in the Contract Documents for re-lay projects, the
Contractor shall abandon the existing water main by pumping the pipe
full of a fly-ash concrete slurry or cellular concrete. Sand slurry
will not be allowed. The slurry or concrete shall have a 500 psi
minimum 28 day strength. The Contractor shall add sufficient water to
the mix to ensure that the mix will flow the full length of the
section of main being filled. Said concrete shall be subject to the
approval of the Engineer.
No line is to be abandoned until after all water services on that line
have been reconnected to the new water main and are operational.
408.3.5 Opening or Closing Existing Water Mains
If an existing water main must be closed or opened during the work,
the Contractor shall notify the City of West Bend Water Utility of the
need at least twenty-four (24) hours prior to the needed time. The
Contractor shall not open or close existing water mains. Only
authorized representatives of the Water Utility are allowed to open or
close existing water mains.
REVISION DATE November 20, 2000 P. 400 - 18
408.3.6 Temporary Air Release Assemblies (Blowoffs)
At the dead end of water mains and all water laterals that are three
(3) inches or larger in diameter and at locations determined in the
field by the Water Utility and/or by the Engineer, the Contractor
shall furnish and install a temporary two (2) inch air release
assembly (blowoff) to facilitate flushing of the line after the
chlorination, sampling, and testing of the line. The blowoff shall be
constructed using a two (2) inch corporation stop and two (2) inch
copper tubing. Unless otherwise instructed by the Water Utility, the
Contractor shall close the corporation stop and remove the tubing of
the blowoff after a safe sample test has been obtained. All costs
associated with furnishing, installing, and removing the blowoff shall
be considered incidental and shall be included in the cost of the pipe
causing the need for the temporary air release assembly.
408.4 Abandoning and Replacing Water Service Laterals
When a building served by an existing water service lateral is
demolished or when a new or replacement water service is required, the
existing water service lateral must be abandoned at the water main and
the corporation stop turned off in accordance with WSWS 5.6.3(c).
This requirement may be waived by the Manager of the Water Utility.
Requests for waivers must be submitted in writing to the Manager of
the West Bend Water Utility.
408.5 Water Valve Installation
For all water valves the Contractor shall tighten the bolts on the
bonnets before installing the valve.
408.6 As-built Valve Manufacturer List
For all projects that include water main construction, an as-built
list showing the City’s GIS water valve identification number, the
manufacturer’s name, and the model of the valve actually installed
shall be furnished by the Contractor on City contract projects and by
the Developer on private development projects. The valve list shall
include the valves on the main line and on hydrant leads. The City
will provide the GIS valve identification numbers.
REVISION DATE December 17, 2012 P. 400 – 18(A)
409 - AMENDMENTS TO WSWS PART V - BUILDING SERVICES
WSWS 5.1.0 GENERAL
WSWS 5.1.3 Minimum Size
Delete the text and replace with the following:
"The minimum size building sanitary sewer shall be in accord with
the Wisconsin Administrative Code, unless otherwise specified, or
four (4") inches in diameter, whichever is the larger diameter."
CITY 5.1.5 Location Data of Non-Conductive Service Laterals
The following requirements are a result of Act 425 passed by the
2005-2006 Wisconsin State Legislature. Act 425 became effective on
June 3, 2006 for all service laterals installed after December 31,
2006.
For all non-conductive water or sewer service laterals that are
installed within the City’s right-of-way or within a City easement,
the Contractor shall furnish and install tracer wire on each
lateral. In addition, the following shall be provided.
On City contracts the Contractor shall provide the City’s
Engineering Department with the location of the lateral at the
mainline, the invert elevation at the mainline and at the top
of the riser that connects the lateral to the main line, and
the location and invert elevation at the edge of the right-of-
way or easement and a sketch or map of the location of each
lateral.
On private development projects the Developer shall provide the
City’s Engineering Department with the location of the lateral
at the mainline, the invert elevation at the mainline and at
the top of the riser that connects the lateral to the mainline,
and the location and invert elevation at the edge of the right-
of-way or easement and the information shall be featured on the
required as-built plans.
A "non-conductive" service lateral is one constructed using a pipe
material that is not able to conduct an adequate electrical current
for purposes of locating the underground service lateral.
TRACER WIRE FOR EACH NON-CONDUCTIVE LATERAL SHALL BE INSTALLED IN
ACCORDANCE WITH DETAILS 461 (SANITARY), 462 (WATER), AND 463
(STORM).
The location on the main line shall be referenced to the center of
at least one manhole barrel (not the lid/cover) on the main line for
sewer laterals and to at least one valve or tee (whichever is
closest) on the main line for water laterals.
The invert elevations at the main line and at the edge of the right-
of-way or easement shall be referenced to the National Geodetic
Vertical Datum of 1929 (NGVD29).
Acceptance of improvements on private development projects or
approval for final payment on City contracts is contingent upon
receipt by the City of the service lateral information described in
the preceding paragraphs and upon satisfactory
REVISION DATE December 15, 2008 p. 400 - 19
verification by the Contractor (in the Engineer's presence) of
electrical continuity of the tracer wires installed on each non-
conductive service lateral.
Refer to the City’s additional requirements in WSWS 5.3.5 and WSWS
5.5.9 for location and painted post-marking of lateral ends.
WSWS 5.2.0 EXCAVATION
WSWS 5.2.2 Building Combined Sewers
Delete this entire section.
WSWS 5.2.4 Water Service Piping
Add the following text:
"Water service piping may be laid in the same trench as the sanitary
sewer lateral, as shown in WSWS File No. 50, Part IX. The sanitary
sewer service trench shall be backfilled up to the elevation of the
bottom of the water service line with bedding and cover material
conforming to WSWS 8.43.2 and 8.43.3 respectively, and substantially
compacted before installing the water service."
WSWS 5.3.0 LAYING OF BUILDING SEWERS
WSWS 5.3.1 Connection Point to Main Sewer
Add the following text:
"At the connection point of building sanitary sewer laterals to the
sanitary sewer main, the connection shall be made using in-line wye
connections and Fernco couplers (or approved equal) at new sanitary
sewer main under construction or at existing sanitary sewer mains
that are constructed with clay pipe. For connections to existing
sanitary sewer mains that are not constructed with clay pipe, the
connection may be made using cored, cut-in, or saddle tees. See
Detail 430. This requirement supersedes the allowable connections
mentioned in WSWS 5.3.2(a) and (b)."
WSWS 5.3.5 Alignment and Grade
Add the following text:
"All new sanitary building service laterals installed for connection
to future buildings shall be installed from the main complete to a
location at zero (0) to two (2) feet past the right of way (into the
lot) and properly plugged. The Contractor shall mark the end of the
lateral with a 2" x 4" or 4" x 4" wooden post, pressure treated with
ACQ (Alkali Copper Quat) or a 4" x 4" hardwood post with at least
four (4) feet exposed above ground and at least the top two (2) feet
painted fluorescent green."
WSWS 5.3.10 Type of Pipe to be Used
Delete the first paragraph and replace with the following text:
"PVC pipe shall be used for building service sewers, unless
otherwise authorized by the Engineer. The minimum size building
sewer shall be four (4) inches in diameter, unless otherwise
specified. In a remove and replace project, the minimum pipe size
shall be equal to the size of pipe that was removed, but not
smaller than four (4) inches. The class of pipe required for PVC
REVISION DATE November 27, 2006 P. 400 – 20
or other materials which may be allowed, shall be as listed in Table
11 of WSWS 5.3.10."
WSWS 5.4.0 ACCEPTANCE TESTING OF BUILDING SEWERS
Delete all text in this chapter and replace with the following:
"All building sanitary sewers shall be tested simultaneously with
the main sewer, as specified in WSWS Part III."
WSWS 5.5.0 LAYING OF WATER SERVICES
WSWS 5.5.5 Lead Joints
Delete this entire section
WSWS 5.5.8 Connection to Water Main
Delete the entire first paragraph of WSWS 5.5.8(a) (General) and
replace with the following text:
"The connection to the water main for the corporation stop of the
tap service or the tapping valve of the branch service shall be made
by the Contractor only in the presence of the Engineer. The
connection shall not be backfilled until the connection is approved
by the Engineer. Any defects in workmanship or materials and any
failures due to said defects shall be the responsibility of the
Contractor during the guarantee period."
WSWS 5.5.9 Alignment and Position
Add the following text:
"All new building service water laterals installed for connection to
future buildings shall be installed complete with curb stop. The
curb stop shall be placed at a location at zero (0) to two (2) feet
past the right-of-way (into the lot). The curb stop consists of the
shut off valve and the valve service box. The Contractor shall
paint the top of the valve box blue in color. The Contractor shall
mark the end of the water lateral with a 2"x4" or 4"x4" wooden post,
pressure treated with ACQ (Alkali Copper Quat) or 4"x4" hardwood
post and with at least four (4) feet exposed above ground and at
least the top two (2) feet painted fluorescent blue."
WSWS 5.5.11 Laying Water Services
Add the following text:
"In lieu of bending the horizontal offsets at the corporation stops
when using 1 1/4", 1 1/2", and 2" copper water service piping, the
Contractor may install the pipe in a curved path in such a manner as
to allow for movement of the in-place pipe.
The water service lateral shall be installed at such an invert
elevation at the water service box (curb box) so that valve stem
extensions (risers) are not needed for operation of the valve with a
standard seven (7) foot long valve-opening key and so that the six
(6) foot minimum cover of the lateral is maintained. "
WSWS 5.5.20 Insulation
Delete the text in this section and replace with the following text:
"See Section 407 of the City's Standard Specifications concerning
WSWS 4.17.2."
WSWS 5.7.0 LAWN SPRINKLER SERVICE SYSTEM
Delete this entire chapter.
REVISION DATE November 27, 2006 P. 400 – 21
410 - AMENDMENTS TO WSWS PART VIII - MATERIAL SPECIFICATIONS
WSWS 8.10.0 POLYVINYL CHLORIDE SEWER PIPE AND FITTINGS
WSWS 8.10.1 Requirements
Add the following text:
"Polyvinyl chloride pipe to be used in sanitary sewers shall be
green or blue in color. White colored PVC shall not be used for
sanitary sewers."
WSWS 8.18.0 DUCTILE IRON WATER PIPE
WSWS 8.18.2 Description
Delete the last sentence and replace with the following text:
"Unless otherwise specified in the Contract Documents, the
minimum pipe thickness or class shall be ANSI Class 52. The pipe
size and length shall be as specified in the Contract Documents."
WSWS 8.19.0 PRESTRESSED CONCRETE PRESSURE WATER PIPE, STEEL CYLINDER
TYPE, FOR WATER MAIN
Delete this entire chapter and replace with the following text:
"The use of prestressed concrete pipe is not allowed on water
distribution projects in the City of West Bend."
WSWS 8.23.3 Nuts and Bolts
Delete all text in this section and replace with the following:
"All nuts and bolts used in flanges for live tap valve sleeves
and for valve-to-hydrant connection joints shall be made from
ASTM 304 stainless steel. All T-bolts used for all other water
main fittings shall be made from corrosion-resistant high-
strength low-alloy steel and shall be coated with "Fluorocote #1"
fluoropolymer coating, or equal. All nuts and bolts shall
conform to all other requirements of AWWA C-111."
WSWS 8.24.0 COPPER WATER TUBING
WSWS 8.24.1 Requirements
Add the following text:
"Unless otherwise specified in the Contract Documents or approved
by the City Engineer, all water service laterals to single family
and duplex residences shall be one and one-fourth (1¼") diameter
from the water main to the stop box (water service shutoff
valve). Water service laterals to commercial and industrial
properties and to multi-family residences shall be as specified
in the Plans or Contract Documents."
REVISION DATE December 17, 2012 p. 400 – 22
WSWS 8.25.0 CAST IRON SERVICE BOXES
(Curb Boxes for Curb Stop Water Service Shutoff Valves)
Add the following section:
CITY 8.25.4 Additional Requirements
All curb boxes used on the water distribution system of the
City of West Bend shall be Mueller H-10300 or H-10304 or
approved equal meeting the following additional
requirements.
1. The upper barrel and the lower section of curb boxes
shall be Class B gray iron pipe.
2. All curb boxes shall be designed to telescope downward
to protect against truck loading or similar type weight
applied to the top section of the box.
3. There shall be a heavy phosphorus bronze spring meeting
ASTM B-159 requirements, positioned between the upper and
lower section to assure proper telescoping of the upper
barrel and to provide reasonable rigidity during
installation. The upper section shall be retained in the
lower barrel by at least two lugs flared at the bottom of
the upper section.
WSWS 8.26.0 FIRE HYDRANTS
Add the following section:
CITY 8.26.4 Additional Requirements
All hydrants used on the water distribution system of the
City of West Bend shall be Waterous (American Flow Control)
"Pacer" - model WB-67, Clow "Medallion" with bronze lower
valve plate, Mueller "Centurions", or approved equal
meeting the following additional requirements. The term
"hydrant" includes the nozzle, standpipe, and base bend
sections complete with all parts making it a functioning
complete assembly.
1. Hydrants shall be "traffic type" with break-off coupling
on the standpipe and on the stem.
2. Hydrants shall be equipped with a 6" diameter inlet and
5¼" minimum diameter valve opening.
3. Hydrants shall be equipped with one 5" diameter pump
nozzle and two 2½" diameter hose nozzles. All nozzles are
to be equipped with National Standard threads.
4. Hydrants shall have a 1½" pentagonal operating nut
opening counter clockwise.
5. Hydrants shall be equipped with O-ring packing.
6. Hydrants shall be provided with a flanged joint at the
base bend for connection to the adjacent shut off valve.
REVISION DATE December 15, 2008 P. 400 – 23
7. The bronze lower valve plate shall be installed on the
hydrant prior to delivery to the project site.
8. The hydrants are to be provided in lengths required for specific hydrant locations shown on the Plans. The
hydrant lead is to have a minimum of six (6) feet of
cover and the center of the "traffic breakoff" flanged
connection (between the nozzle section and standpipe
section) is to be vertically positioned between 1" and
4" above the surrounding finished ground elevation.
9. The hydrant section located above the center of the "traffic breakoff" flanged connection shall be painted
yellow by the manufacturer before shipping to the
Contractor. If the paint is or becomes damaged, the
Contractor shall repair the protective coating in
strict conformance with the manufacturer’s written
procedures.
WSWS 8.27.0 GATE AND RESILIENT WEDGE VALVES
Add the following sections:
CITY 8.27.6 Resilient Wedge Valves
For 3" through 12" valves on water distribution piping in
the City of West Bend, resilient wedge valves are
required. Resilient wedge valves shall be Clow, Mueller,
Waterous, or equal meeting the following additional
requirements. Gate valves are not allowed on water mains
in the City of West Bend.
1. The valve body and bonnet shall be made of cast iron
meeting ASTM A-126 Class B, whereas bronze parts
shall meet either of the following ASTM, B-61, B-62,
B-98 as prescribed by AWWA C-509 for water with a
specific conductance of more than 350 UMHO/CM.
2. Valves shall be non-rising stem type and shall have a
2" square operating nut opening to the left (counter-
clockwise).
3. Valves attaching to hydrants shall have a flanged
joint towards the hydrant and a mechanical joint away
from the hydrant. All other valves shall be equipped
with mechanical joints at each end.
4. Resilient wedge valves shall be epoxy lined in
accordance with AWWA C-550.
5. The working pressure of the valves shall be 200 psi.
6. Prior to shipping from the factory, all valves shall
be hydrostatically shell tested at 400 psi and shut
off tested at 200 psi, with no leakage allowed at the
200 psi shut off pressure.
REVISION DATE December 17, 2012 p. 400 – 24
7. All valves shall be of the design that permits
repacking under pressure in the fully open position.
At least one (1) o-ring is to be located above and
one (1) o-ring below the stem thrust collar, thus
permitting automatic lubrication of the thrust collar
during the operation of the valve. A bronze stem
collar bushing or bonnet bushing will be acceptable
in lieu of the lubricant to assure ease of valve
operation after extended periods of not being used.
8. The basis of the structural design of the valve shall
be such that should a valve stem failure ever occur
during the closing of the valve, the failure shall
not be subjected to the pressure retaining parts such
as the valve body bonnet. This gives assurance that
if excessive torques are applied, resulting in
failure of the stem, the failure will be external and
can be safely handled in a workmanlike manner and
permit the repair of the stem to be completed under
adverse conditions.
CITY 8.27.7 Cut-In Valves and Sleeves
(Tapping Valves and Sleeves)
All cut-in (tapping) valves shall be resilient wedge
valves with mechanical joints. Where cut-in valves are
used, a mechanical joint cut-in sleeve shall be furnished
by the Contractor to facilitate ease of installation of
the valve and sleeve onto all classes of cast iron or
ductile iron pipe. Cut-in sleeve and cut-in valve glands
are to be such that all classes of cast iron and ductile
iron pipe will serve the one gland by changing only the
gasket.
WSWS 8.28.0 BUTTERFLY VALVES
Add the following section:
CITY 8.28.6 Additional Requirements
For valves larger than 12" diameter on water distribution
piping in the City of West Bend, butterfly valves are
required. All butterfly valves shall be Henry Pratt
Company, or approved equal, meeting the following
additional requirements.
1. All butterfly valves are to be provided with worm gear
operators and extension stems.
2. All valves and actuators are to be compatible with
buried or submerged service.
REVISION DATE December 17, 2012 p. 400 - 25
3. Seals on shafts and gaskets on valve and actuator covers
shall be provided to prevent entry of groundwater and
dirt. Mounting brackets shall be provided with gasket
seals.
4. All butterfly valves are to have mechanical joints.
5. The working pressure of butterfly valves shall be 150
PSI for valves larger than 12". Prior to shipping from
the factory, all valves are to be hydrostatically shell
tested at twice the working pressure and shut off
tested at the working pressure with no leakage allowed
at the shut off test pressure.
WSWS 8.29.0 CAST IRON VALVE BOXES
Add the following section:
CITY 8.29.4 Additional Requirements
All valve boxes used on the water distribution system of
the City of West Bend shall be Tyler Type DD for depths of
5.5 feet or less and Tyler Type F for depth greater than
5.5 feet, or approved equal meeting the following
additional requirements.
1. The valve box length shall be sufficient to provide for
the depths of cover shown on the drawings.
2. The valve box shall be furnished with a no-tilt drop
cover marked "water".
3. The valve box shall be a three (3) piece screw type and
shall have threads for the top and middle sections that
are compatible with Clow or Tyler brand valve boxes.
4. All valve boxes shall be installed upon the valve with
the use of a valve adaptor to center the valve box over
the valve nut. The valve adaptor shall be made of
epoxy-coated 0.25" steel, as manufactured by Adaptor,
Inc. (tel. 414-764-6733), or approved equal. When used
for gate valves the adaptor shall be installed with a
0.5" rubber gasket.
WSWS 8.30.0 CORPORATION STOPS
(Service-to-Main Tie-in Valve)
Add the following section:
CITY 8.30.2 Additional Requirements
All corporation stops used on the water distribution system
of the City of West Bend shall be Mueller type H-15000 for
flared connections or Mueller type H-15008 for compression
connections, Ford equivalent, or other approved equal,
meeting the following additional requirements.
REVISION DATE December 17, 2012 p. 400 – 26
1. All components of the corporation stops shall be
manufactured of brass cast in accordance with AWWA C-
800 Section 1, Paragraph 1.2 (ASTM B62). All brass
castings shall conform to ASTM B62, and shall consist
of 85-5-5-5 copper, tin, lead, zinc, as checked and
verified in the finished (completed) product. A
notarized certificate shall be signed by an officer of
the manufacturing company stating compliance of the
finished product (completed) with AWWA C-800 and ASTM
B62 and of their latest revisions. All component
parts, body, key, washer, nut, and tube nut shall have
the same metal analysis complying with ASTM B62.
2. Inlet and outlet threads shall fully conform to AWWA C-
800 with the key and body seating surfaces being
accurately machined and fit to the taper of 1¾" per
foot, (.1458 inch per inch) plus or minus .007 inches
per inch. The key shall have a "D" shaped boss
provided at the small end and the retaining washer
shall have a matched flat surface so machined as to
provide an interference fit across the diameter of the
boss perpendicular to this surface. There shall be no
evidence of staking or chisel marks in this assembly.
3. The stem and retaining nut shall be so designed that
failure from over tightening the retaining nut shall
result in the stripping of threads rather than the stem
fracture.
4. Corporation stops of the 1" size shall weigh no less
than 3.7 pounds, and the 1¼" size no less than 5.7
pounds.
WSWS 8.31.0 CURB STOPS
(Water Service Shut Off Valves)
Add the following section:
CITY 8.31.2 Additional Requirements
All curb stops used on the water distribution system of the
City of West Bend shall be Mueller type H-15150 or H-15154
for flared connections or Mueller type H-15155 for
compression fittings, Ford equivalent, or other approved
equal, meeting the following additional requirements.
REVISION DATE December 13, 2004 p. 400 - 27
1. All components of the curb stops shall be manufactured
in accordance with AWWA C-800. All brass components
shall conform to ASTM B62 and shall consist of 85-5-5-5
copper, tin, lead, zinc as checked and verified in the
finished or completed product. A notarized certificate
shall be signed by an officer of the manufacturing
company, stating that the completed or finished product
fully complies with AWWA C-800 and ASTM B62 and of
their latest revisions.
2. Curb stops shall be of the inverted key design with the
Minneapolis pattern top to accommodate thread size
having 11-1/2 threads per inch with a pitch diameter of
.262 inch and with an O. D. diameter of 2.316 inches.
The inverted key design shall have a copper by copper
connection.
3. All curb stops shall be of the quarter turned design and
shall incorporate a check design to facilitate their
quartered turning in such way that the valve key or
stem shall be capable of withstanding an excess of
1,200 inch pounds of torque applied in both the fully
opened and fully closed position.
4. All curb stops that are one and one-quarter inch and
larger, shall be the ball or o-ring type. If o-ring
designed curb stops are required, they shall be of the
closed bottom design and sealed against external
leakage at the top by means of a non-adjustable
resilient pressure actuated seal and shall have a
secondary resilient seal disposed above the pressure
seal for added protection of the bearing surfaces
against ground water infiltration. Further, this
design shall be of the cylinder plug style having
suitable o-ring seals and placed in such manner as to
provide a balanced pressure across the plug.
5. The curb stop design shall be such that shut off of the
curb stop shall be accomplished by a resilient pressure
actuated seal so disposed in the key or plug to
completely close the inlet body port flow in the closed
position.
6. The curb stops shall not weigh less than 3.9 pounds for
3/4" size or 6.1 pounds for 1" size.
REVISION DATE November 25, 1996 p. 400 - 28
WSWS 8.37.0 MORTAR
WSWS 8.37.1 Materials
Add the following text:
"Type "S" mortar conforming to ASTM Designation C-270 may be used
in lieu of Type "M" mortar."
WSWS 8.38.0 CONCRETE BRICK AND BLOCK MASONRY UNITS
WSWS 8.38.3 Manhole Block Dimensions and Quality
Add the following text:
"Concrete block, when specified by the Engineer for manhole or
inlet construction, shall be structured as a half course or solid
block. No hollow core building block will be allowed, unless
specifically ordered by the Engineer."
WSWS 8.43.0 BEDDING, COVER, FOUNDATION, AND BACKFILL MATERIALS
WSWS 8.43.1 Requirements
Add the following text:
"When crushed stone chips or crushed stone screenings are used
for bedding material, the bedding material shall be placed no
higher than the spring line of the pipe."
WSWS 8.43.3 Cover Material for Pipe
Add the following text:
"In areas susceptible to ground water flow, as determined by the
Engineer, and where the bedding material is crushed stone, the
Contractor may be required to flood the cover material as
specified in WSWS 2.6.14 to move cover material into the void
spaces of the bedding stone."
WSWS 8.48.0 MANHOLE AND CATCH BASIN CASTINGS
Delete the text of this entire chapter and replace with the
following:
CITY 8.48.1 Requirements
All manhole and inlet castings shall conform to the
requirements of A.S.T.M. A-48, Class No. 30-B. Castings
shall be free from cracks, holes, swells, and cold shuts.
CITY 8.48.2 Manhole Castings
Manhole casting frames and covers shall be:
1. For sanitary sewer manholes: Neenah R-1733 M.H.D. with
non-vented lid having two pick holes (no orientation
notch or tab), or approved equal.
2. For storm sewer manholes: Neenah R-1733 M.H.D. with
vented lid having two pick holes (no orientation
notch or tab), or approved equal.
3. For sanitary sewer manholes at subaqueous or buried
locations: Neenah R-1916-C water tight frame and lid
assembly with bolted lid having two pick holes or
approved equal.
REVISION DATE November 26, 2007 p. 400 - 29
Manhole covers shall be non-rocking type, to prevent
cover noise under traffic. Machined bearing surfaces
shall fulfill the non-rocking requirement.
CITY 8.48.3 Catch Basin Castings
Storm sewer catch basin frames and grates shall be:
1. For curb catch basins: Neenah R-3067 frame with Type V
(Vane) grate. When specifically indicated on the
drawings or in the Contract Documents, Type DL
(Diagonal Slot) or Type L (Heavy Vane) grates shall be
used.
2. For driveway catch basins: Neenah R-3290-A frame with
grid type grate.
3. For field catch basins:
Neenah circular beehive frame and grate:
- R-2561 for Type A of Detail 425
- R-2563 for Type B of Detail 426
WSWS 8.49.0 COAL-TAR EPOXY
Delete this entire chapter.
CITY 8.56.0 SUBSTITUTION OF MATERIALS
Add this new chapter and text:
"Neither the Owner, (when the Owner is not the City of West
Bend) nor the Contractor shall substitute for materials
specified without prior written permission of the City
Engineer. Prior to such permission being granted, the City
may require the Contractor or Owner to supply a typical
unit, at the location chosen by the City, to be checked for
interchangeability with the City's standard unit."
REVISION DATE December 17, 2012 p. 400 – 30
411 - AMENDMENTS TO WSWS PART IX - DETAIL DRAWINGS
Delete the following file drawings:
File No. Title
8 Standard Filled Section
9 Standard Tunnel Section
14A Standard Manhole Frame & Storm Manhole Cover
14B Standard Sanitary Manhole Cover
19 Outside Drop-Precast Manhole-Flexible Pipe to Manhole
Seal
23 Details of Sampling and Gauging Manholes for Sewer Sizes
from 8" to 24" Diameter
25 Standard Catch Basin (Masonry or Precast)
26 Catch Basin
27 Trapped Catch Basin
28 Standard Storm Water Inlet (Masonry or Precast)
29 Field Inlet or Catch Basin (Masonry or Precast)
32 Anchored Manhole Frame and Cover
33 Standard Square Catch Basin Casting - Curb Type
35 Field Grate Casting - 4 Flange
38 Standard Hydrant Setting
39 Butterfly Valve and Box (16" and smaller)
40 Standard Vault for Grate Valves
40A Standard Vault for Butterfly Valves
41 Air Release Vault
43 Concrete Buttress for Plug with Air Vent for 20" and
Smaller
50 (Figure 1 only) Standard Section for Building Sewer and
Water Services
53 Drain and Riser Assembly
54 Building Sanitary Sewer Test
55 Standard Catch Basin Casting Mountable Curb Type
REVISION DATE December 13, 2004 p. 400 - 31
412 - ADDITIONAL DETAIL DRAWINGS FOR WATER AND SEWER CONSTRUCTION
The following detail drawings are incorporated into this water and sewer
construction section of the City's Standard Specifications.
Detail
Number Title
401 Type "A" Manhole - Standard Precast Manhole for Storm Sewers
402 Type "B" Manhole - Standard Precast Manhole for Sanitary Sewers
403 Type "T" Storm Manhole
404 Type "C" Combination Storm Manhole and Catch Basin
405 Flat Top Detail For Sanitary and Storm Manholes
406 Outside Drop for Precast Manhole with Flexible Pipe-To-Manhole Seal
408 Connection Detail for Watertight Manhole Frame and Cover
411 Standard Frame & Cover for Sanitary Manholes
412 Standard Frame & Cover for Sanitary Manholes in Subaqueous or Buried
Conditions
413 Standard Frame & Cover for Storm Manholes
421 Standard Precast Catch Basin
422 Standard Precast Inlet
423 Standard Frame & Grate for Catch Basins
424 Standard Frame & Grate for Driveway Catch Basins
425 Field Catch Basin/Inlet Type "A"
426 Field Catch Basin/Inlet Type "B"
427 Hinged Grate for Storm Sewer Outfalls
428 Joint Ties at Storm Sewer Outfalls and Culverts Using Concrete Pipe
429 Riprap Apron at Storm Water Pipe Outfalls
430 Connection of Sanitary Lateral to Main
431 Standard Hydrant Setting
432 Standard Hydrant Setting at Ditch Sections
433 Water Main/Building Water Service Insulation
REVISION DATE December 15, 2008 p. 400 – 32
Detail
Number Title
434 Valves at Connection of Private Looped Water Lines to Public Water
Mains
441 Standard Trench Section
451 Underdrains
452 Sump Drain Connection Line
453 Combination Underdrain and Sump Drain Connection Line
461 Tracer Wire for Non-Conductive Sanitary Sewer Laterals
462 Tracer Wire for Non-Conductive Water Laterals and Hydrant Leads
463 Tracer Wire for Non-Conductive Storm Sewer Laterals
REVISION DATE December 15, 2008 p. 400 – 32(A)
413 - REPAIR OF EXISTING SEWER AND WATER FACILITIES
413.1 Scope Of Work
The work under this section shall include the repair of existing
sanitary and storm sewer facilities as shown on the plans, or as
specified in the Contract Documents. All repair work shall conform
to the requirements of Section 400 of the City's Standard
Specifications except as modified within this subsection 413 or as
specified otherwise in the Special Provisions.
The Contractor shall furnish all labor, supervision, equipment,
materials, supplies, tools, and incidentals necessary to complete
the work.
413.2 Remove And Replace Sewer Pipe
413.2.1 General
The repair work consists of removing and replacing sections of
existing sewers at various locations.
The locations of proposed sewer pipe repairs are normally
determined by the use of the City of West Bend Sewer Utility
televising equipment and are not to be taken as exact locations,
but rather close approximations of the locations. The Engineer
will mark all sewer pipe repair locations prior to any sewer pipe
repair work beginning. There shall be no adjustments to the unit
prices for additional trench excavations to determine the exact
location of the defective sections unless the defective section is
ten (10) feet or more away from the location specified or marked by
the Engineer.
413.2.2 Sewer Pipe Materials
Unless otherwise specified in the Contract Documents, all pipe used
to repair sanitary sewer pipe shall be SDR35 PVC sewer pipe
conforming to ASTM D3034 and meeting the requirements of WSWS
8.10.0.
Unless otherwise specified in the Contract Documents, all pipe used
to repair storm sewer pipe shall be reinforced concrete pipe, Class
III, conforming to ASTM C-76 and meeting the requirements of WSWS
8.6.0.
413.2.3 Installation
When removing a section or sections of existing sewer pipe, the
Contractor shall take extreme care not to damage any adjacent
sections of pipe. Any damage that may occur to adjacent sections
shall be repaired by the Contractor at no expense to the City.
REVISION DATE December 13, 2004_ p. 400 - 33
The Contractor shall prepare the new pipe to "fit" as tight as
possible in the space left by removing the old pipe. "Fernco"
couplers or equal shall then be used to joint the pipes together.
At no expense to the City, the Contractor shall repair any damage
that may occur to existing catch basins, manholes, curb and gutter,
sidewalk sections, or other City facilities due to the Contractor's
sewer pipe repair operations.
413.2.4 Aggregate Slurry Backfill
When required by the Contract Documents, the Contractor shall use
aggregate slurry backfill material for backfill around the sewer
pipe repairs when pavement or curb and gutter exists above the
repair location. The aggregate slurry backfill shall conform to
the requirements specified in Section 413.8 of the City's Standard
Specifications.
413.2.5 Granular Backfill
When allowed by the Contract Documents, or by the Engineer,
granular backfill may be used at repair locations that are not to
be paved, provided the granular backfill meets the requirements of
WSWS 8.43.4.
413.2.6 Surface Restoration
If pavement exists above a repair location, the Contractor shall
restore and compact the subbase and the pavement at that location
to meet the requirements of Section 606.2 of the City's Standard
Specifications for asphalt pavement and Section 512.0 for concrete
pavement. The requirements of Section 606.2.4 for temporary
pavement are applicable to this work. If no pavement exists above
the repair location, the Contractor shall restore the surface to
its original condition in accordance with the requirements of
Section 700 of the City's Standard Specifications.
413.2.7 Measurement and Payment
Measurement for removal and replacement of sewer pipe shall be made
in lineal feet of pipe actually installed.
The contract unit prices for removal and replacement of sewer pipe
of various specified types and sizes shall include all costs
associated with removing and properly disposing of the existing
damaged pipe sections and replacing them with the specified size
and type of pipe; furnishing the pipe, couplers, and manufacturer's
certificates for the pipe; hauling and properly disposing of
excavated detrimental objects and materials; furnishing,
installing, and compacting granular backfill (when allowed) and
temporary pavement; and for all labor, supervision, equipment,
materials, supplies, tools, and incidentals necessary to complete
the work.
Unless otherwise specified in the Contract Documents, the costs
associated with the aggregate slurry backfill, pavements
sawcutting, and restoration of the roadway pavement and ground
surface at the pipe repair locations are not to be included in
REVISION DATE December 15, 2008 p. 400 - 34
the contract unit prices for removal and replacement of sewer pipe.
These items are normally either separate bid items or are included
in separate bid items.
The maximum quantity for payment of pavement restoration at sewer
pipe repairs shall be based upon a maximum pavement patch width of
ten (10) feet and a maximum pavement patch length equal to the
length of the pipe replaced plus ten (10) feet for pipes with an
inert depth of ten (10) feet or less. For pipes with invert depths
in excess of ten (10) feet, the maximum pavement patch width shall
be fifteen (15) feet and the maximum pavement patch length shall be
equal to the length of pipe replaced plus fifteen (15) feet.
413.3 Catch Basin Repair Work
413.3.1 General
The work under this section includes repairing existing catch
basins or inlets and removing and replacing existing catch basin or
inlet structures, frames, and/or grates. The location and a brief
description of the work to be done at each catch basin or inlet
shall be as specified in the Contract Documents.
Unless specifically indicated in the Contract Documents, all
structures for collecting storm water from streets shall be catch
basins with twenty-four (24") inch sumps below the inlet pipes.
Under certain situations, inlet structures may be specified,
subject to the approval of the Engineer. Within this Section 413.3
the term "catch basin" shall be understood to include both catch
basins and inlets.
413.3.2 Remove and Replace Catch Basin Structures
Where catch basin structures are to be removed and replaced, the
Contractor shall furnish and install precast reinforced concrete
catch basins as specified on Detail 421 of the City's Standard
Specifications. Inlet structures shall be as specified on Detail
422. The removed structures shall be properly disposed of off site
by the Contractor. The Contractor shall be responsible for
determining the depth of the replacement structures and the number,
size and location of the replacement pipes which will be needed.
Any existing pipe inverted into the remove and replace structures
shall also be removed and replaced as necessary. The replacement
pipe shall be SDR35 PVC Pipe or Reinforced Concrete Pipe which
matches the inner diameter size of the existing pipe. All
connections between the replacement pipe and existing pipe shall be
made with "Fernco" couplers (or equal). Concrete collars made of
mortar and solid concrete bricks may be used only when approved by
the Engineer.
413.3.3 Catch Basin Frames and Grates
Where catch basin frames and grates are to be removed and replaced,
the Contractor shall furnish and install Neenah R-3067 frames with
Type V (vane) grates or Type DL or DR (diagonal). The type of
grate shall be as specified in the Contract Documents. The
existing frames and grates on the removed catch basins shall remain
the property of the City, and the Contractor shall deliver and
offload the used frames and grates at the City’s municipal yard
located at 251 Municipal Drive.
REVISION DATE November 26, 2007 p. 400 – 35
Frames and grates removed and intended for reinstallation which are
rendered unfit for use by the Contractor through the Contractor's
operations shall be replaced by the Contractor at no additional cost
to the City.
413.3.4 Catch Basin Structural Repairs
Where catch basins are to receive structural repairs, the
Contractor shall make the repairs as specified in the Contract
Documents. The various types of repair work to be performed by the
Contractor are described in the following general terms:
1. Tuckpoint - Fill gaps and joints between existing blocks
or below frame casting by tuckpointing mortar into the
gaps. The gaps shall be cleaned of all soil before being
filled with mortar.
2. Brick and Mortar - Fill gaps between existing blocks, at
pipe connections, at lift holes, below the frame casting,
and at broken inner faces of block with solid concrete
brick and mortar. The gaps shall be cleaned of all soil
before being filled with brick and mortar.
3. Backplaster - Backplaster the existing concrete block and
brick on the inside of the catch basin with mortar.
Prior to backplastering, the surface to be backplastered
shall be thoroughly cleaned. The surface must be free of
dust, oil, rust, loose materials, and other contaminants.
4. Remove and replace grade rings - Remove the existing
frame and grate. Remove the existing block or brick
grade rings and replace with new reinforced concrete
grade rings. Replace the existing frame and grate or
reinstall the existing frame and grate (as specified in
the description of the repair). If there is a difference
in the depth of the existing frame and the replacement
frame, the difference shall be made up with the
reinforced concrete adjusting rings. The new adjusting
rings (grade rings) shall be mortared together with
mortar between each ring, and the frame shall be mortared
to the top adjusting ring.
413.3.5 Aggregate Slurry Backfill
When required by the Contract Documents, the Contractor shall use
aggregate slurry material for backfill around the replacement catch
basins. The aggregate slurry backfill shall conform to the
requirements of Section 413.8 of the City's Standard
Specifications.
413.3.6 Curb and Gutter
At each location where a catch basin structure or frame is to be
removed and replaced, curb and gutter will have to be removed and
replaced. The curb and gutter removal and replacement work shall
REVISION DATE December 15, 2008 p. 400 – 36
be in accordance with the requirements of Section 508 of the
City's Standard Specifications.
At locations where catch basins are to be removed and replaced,
the minimum length of curb and gutter to be removed and replaced
shall be four (4) feet to each side of the catch basin or as
otherwise marked by the Engineer. Any curb and gutter removed and
replaced outside of the removal and replacement limits without
prior approval from the Engineer will be at no cost to the City.
413.3.7 Pavement Restoration
The Contractor shall remove and replace any existing pavement
disturbed during catch basin repair or removal and replacement
work. Pavement restoration shall be in accordance with the
requirements for full depth patching, as specified in Section
606.2 of the City's Standard Specifications for asphaltic concrete
pavements or Section 512.2 for concrete pavements. The
requirements of Section 606.2.4 for temporary pavement are
applicable to this work. Pavement restoration shall include
removing the existing asphaltic concrete pavement and replacing it
with pavement of thickness and type equal to the surrounding
pavement. The pavement shall be sawcut to form a minimum width of
two (2) feet for the pavement patch.
413.3.8 Ground Restoration
All areas behind the back of curb disturbed by the catch basin
repair or replacement work shall be backfilled, regraded,
topsoiled, seeded, fertilized, mulched, and watered by the
Contractor in accordance with the requirements of Section 700 of
the City's Standard Specifications.
413.3.9 Measurement and Payment
The measurement and payment of catch basin replacements and
repairs shall be by the unit. The quantity measured for payment
shall be the number of catch basin units actually removed and
replaced or repaired.
All costs associated with the following work shall be included in
the bid prices for the catch basin work:
- temporary pavement at the catch basin
- removal and proper disposal of the specified structures, grade
rings, frames, grates, and backs
- removal and proper disposal of detrimental and native
materials
- furnishment and placement of structures, grade rings, frames,
grates, and backs
- removal, replacement, and connection of all existing pipes
joined to the catch basin, including couplings
- when specified, reinstallation of existing frames, grates, and
backs
- repair of existing catch basins by tuck pointing, bricking,
back plastering, and/or mortaring.
REVISION DATE December 17, 2012 p. 400 – 37
All costs associated with the following work at the catch basin
repairs are to be included in separate bid prices for such work
and are not to be included in the bid prices for the catch basin
work.
- removal, disposal, and replacement of adjacent curb and gutter
- removal, disposal, and replacement of adjacent pavement
- furnishment and placement of slurry aggregate backfill
- ground restoration.
413.4 Manhole Repair Work
413.4.1 General
The work under this section includes repairing existing sanitary,
storm, or water manholes. The location and description of the
work to be done at each manhole shall be as specified in the
Contract Documents.
The various type of work (tuckpoint, brick, backplaster, and
mortar) are the same as described in Section 413.3.4 for
structural repairs of catch basins.
413.4.2 Measurement and Payment
The measurement of manhole repairs shall be by the unit and the
quantity measured for payment shall be the number of manholes
actually repaired.
The contract unit price for manhole repairs shall include all
costs associated with the specified repairs to be made and all
costs of labor, supervision, equipment, materials, supplies,
tools, and incidentals necessary to complete the work in
accordance with the specifications and Contract Documents.
REVISION DATE November 25, 2002 p. 400 - 38
413.5 Manhole and Catch Basin Adjustments
413.5.1 General
The work under this section includes making adjustments to the
elevation of existing manholes, catch basins, and inlets so that
they are one-eighth (1/8) inch to one-quarter (1/4) inch below
the finished pavement. All adjustments shall be made by using
reinforced concrete adjustment rings (grade rings) or by the use
of approved adjusting castings designed for such purpose. When
adjusting castings are used at sanitary manholes, the Contractor
shall seal the seam between the adjusting casting and the manhole
frame with a butyl rubber caulk.
If a centering tab exists on the manhole lid of a manhole
adjustment using an adjusting casting, the Contractor shall
remove the centering tab before making the elevation adjustment.
Metal wedges and shims are preferred for the adjustment of catch
basin and manhole frames. If wooden wedges or shims are used they
shall be removed and the area tuckpointed prior to the acceptance
of the work.
The location and description of the adjustment work to be done by
the Contractor at each unit shall be as specified in the Contract
Documents.
413.5.2 Pavement and Subbase Restoration
All pavement required to be removed and replaced for the
adjustments shall be a minimum width of two (2) feet measured
perpendicular to the perimeter of the unit, and the pavement
patching work shall conform to the requirements for asphaltic
concrete pavement patching of Section 606.2 of the City's
Standard Specifications or to Section 512.2 for concrete
pavement. The requirements of Section 606.2.4 for temporary
pavement are applicable to this work.. All subbase required to
be removed for adjustments shall be replaced with crushed
aggregate materials equivalent to or better than the surrounding
roadway subbase materials.
413.5.3 Chimney Seals on Sanitary Sewer Manholes
If sanitary manholes are to be adjusted, they may contain
internal chimney seals. Extreme care shall be taken not to hit
existing manhole frames and damage existing chimney seals. Any
chimney seal damaged during the work shall be replaced by the
Contractor at no expense to the City. The Contractor shall
remove the existing chimney seal prior to adjusting the manhole.
The Contractor shall be responsible for the safe storage and
condition of the chimney seals and for re-installing the chimney
seals in the manholes immediately after work is completed.
413.5.4 Measurement and Payment
The measurement and payment of manhole, catch basin, and inlet
adjustments will be in accordance with the provisions of WSWS
2.9.15 for the number of units actually adjusted. The contract
unit price for the adjustments shall include all costs associated
with removing and reinstalling the frame and cover; removal and
reinstallation of chimney seals; removal and proper disposal of
REVISION DATE December 17, 2012 p. 400 - 39
pavement and subbase materials; furnishing and installing
adjusting grade rings or castings; removing centering tabs on
manhole lids, subbase restoration and compaction; temporary
pavement and pavement restoration; and all labor, supervision,
materials, tools, equipment, supplies, and incidentals necessary
to complete the adjustment work.
413.6 Manhole Removal and Replacement
413.6.1 General
The work under this section shall include the removal and
replacement of all or part of existing sanitary, storm, or water
manholes. The location and description of the work to be done at
each manhole shall be as specified in the Contract Documents.
413.6.2 Manhole Structures and Pipes
Where manhole structures are to be removed and replaced, the
Contractor shall furnish and install precast reinforced concrete
manholes as specified on Detail 401 of the City's Standard
Specifications. The removed structures shall be properly
disposed of off site by the Contractor. The Contractor shall be
responsible for determining the depth of the replacement
structures and the number, size and location of the replacement
pipes which will be needed.
Any existing pipe connected to structures that are to be removed
and replaced shall also be removed and replaced as necessary.
The replacement pipe shall be SDR35 PVC Pipe conforming to ASTM
D-3034 for sanitary sewer pipe and either SDR35 PVC Pipe or Class
III Reinforced Concrete Pipe for storm sewer pipe. The pipe
shall match the inner diameter size of the existing pipe. All
connections between the replacement pipe and existing pipe shall
be made with "Fernco" couplers (or equal). Concrete collars made
of mortar and solid concrete brick may be used only when approved
by the Engineer.
413.6.3 Aggregate Slurry Backfill
When required by the Contract Documents, the Contractor shall use
aggregate slurry backfill material for backfill around the
replaced manholes where pavement exists around the manhole. The
aggregate slurry backfill shall conform to the requirements
specified in Section 413.8 of the City's Standard Specifications.
413.6.4 Granular Backfill
Granular backfill may be used when specified by the Engineer at
repair locations that are not to be paved, provided the granular
backfill meets the requirements of WSWS 8.43.4.
413.6.5 Frames and Covers
The Contract Documents specify whether the Contractor is to
remove and reinstall the existing frame and cover or to furnish
and install a new frame and grate. Unless otherwise specified in
the Contract Documents, the frames and covers shall conform to
the requirements of Detail 411 for sanitary manholes and Detail
413 for storm manholes shown in the City's Standard
Specifications.
REVISION DATE December 17, 2012 p. 400 - 40
413.6.6 Chimney Seals at Sanitary Sewer Manholes
The requirements of Section 413.5.3 for chimney seals shall also
apply to the manhole replacement work.
413.6.7 Surface Restoration
If pavement exists at the manhole replacement location, the
Contractor shall restore and compact the subbase and the pavement
of that location to meet the requirements of Section 606.2 of the
City's Standard Specifications for asphalt pavement and Section
512.2 for concrete pavement. The requirements of Section 606.2.4
for temporary pavement are applicable to this work. If no
pavement exists at the manhole location, the Contractor shall
restore the surface to its original condition in accordance with
the requirements of Section 700 of the City's Standard
Specifications.
413.6.8 Measurement and Payment
The measurement and payment of manholes removed and replaced
shall be by the unit, and the quantity measured for payment shall
be the number of manhole units actually removed and replaced.
Unless specified otherwise in the Contract Documents, the
following rules shall apply to the pricing and payment for the
specified work of removing and replacing manholes:
1. All costs associated with curb and gutter removal and
replacement at manholes are to be included in the separate
contract unit prices for such work and are not to be
included in the contract unit prices for the manhole
removal and replacement work.
2. All costs associated with ground restoration at the
manhole replacement work shall be included in the contract
unit prices for the manhole removal and replacement work.
3. All costs associated with furnishing and placing aggregate
slurry backfill at manholes are to be included in the
separate contract unit price for aggregate slurry backfill
and are not to be included in the contract unit prices for
the manhole removal and replacement work.
4. All costs associated with temporary pavement at manholes
shall be included in the contract unit prices for the
manhole removal and replacement work.
5. All costs associated with the permanent pavement
restoration are to be included in the separate bid prices
for pavement patches and are not to be included in the bid
prices for the manhole removal and replacement work.
6. All costs associated with the removal and replacement
REVISION DATE March 20, 1995 p. 400 - 41
of manholes shall be included in the contract unit prices for
such work. The costs included in the contract unit prices shall
include the removal and proper disposal of specified structures,
grade rings, frames, covers, and detrimental and native
materials; the furnishing and placement of structures, grade
rings, frames, and covers; removing and replacing existing
inverted pipe, including couplings; placing concrete
channelization of the manhole benches; reinstallation of existing
frames; and all costs of labor, supervision, equipment,
materials, supplies, tools, and incidentals necessary to complete
the manhole removal and replacement work in accordance with the
specifications and Contract Documents.
413.7 Adjusting Valve Boxes
413.7.1 General
The work under this section includes making adjustments to the
elevation of existing valve boxes of water main valves so that
they are one-eighth (1/8) inch to one-quarter (1/4) inch below
the finished pavement. All valve box adjustments shall be made
preferably by turning the existing valve box. If the valve box
cannot be adjusted by turning without disturbing the existing
pavement, the Contractor may use Tyler valve box insert pieces,
or approved equal, to make the adjustment.
413.7.2 Payment
The adjustment of any valve boxes, when so designated in the
plans or in the contract, and when not covered by a contract bid
item, shall be considered as work incidental to the other
contract bid items causing the need for the adjustments, and no
separate or extra compensation will be allowed for the
adjustments.
413.8 Aggregate Slurry Backfill
413.8.1 General
When required by the Contract Documents, the Contractor shall use
aggregate slurry material for backfilling where any excavations
are made through existing pavements for replacements of sewer
pipe, manholes, and catch basins. The aggregate slurry backfill
shall conform to the requirements specified in WSWS 8.43.8.
413.8.2 Measurement and Payment
The measurement and payment for aggregate slurry backfill will be
by the cubic yard of material used to backfill. The maximum
payment quantity shall be based upon the following limiting
trench dimensions. No adjustments will be made for sloping of
trench walls. Any additional volume of excavation created due to
excavation beyond the limits described below, without prior
approval from the Engineer, shall be backfilled with aggregate
slurry material by the Contractor at no expense to the City.
For volume calculations using the following limiting trench
dimensions, the maximum trench depth shall be from the underside
of the road base (when crushed stone road base is used) or from
the underside of the pavement (when the aggregate slurry backfill
is used as the road base) to the top of the bedding material.
REVISION DATE December 15, 2008 p. 400 - 42
a. For sewer pipe repairs:
Maximum trench width equal to the outside diameter of
the pipe plus three (3) feet and a maximum trench length
equal to the length of the pipe plus six (6) feet.
b. For catch basin structure removals:
Maximum trench width equal to the catch basin’s interior
width plus four (4) feet and a maximum trench length
equal to the catch basin’s interior length plus five (5)
feet.
c. For manhole removals:
For a cylindrical manhole a maximum trench width and
length equal to the manhole’s inside diameter plus eight
(8) feet.
For a rectangular manhole a maximum trench width equal to
the manhole’s interior width plus eight (8) feet and a
maximum trench length equal to the manhole’s interior
length plus eight (8) feet.
The contract unit price for aggregate slurry backfill shall
include all costs associated with furnishing and placing the
aggregate slurry backfill where excavations are made at
replacements of sewer pipe, manholes, and catch basins.
REVISION DATE December 15, 2008 p. 400 – 43
414 - MEASUREMENT AND PAYMENT
414.1 General
Unless otherwise specified in the Contract Documents, the
measurement and basis of payment for sanitary sewers, storm
sewers and water distribution systems shall be in accordance
with the methods specified within this section.
The methods for measurement and payment for repairs to existing
sanitary and storm sewers and structures are specified in
Section 413 of the City's Standard Specifications.
If granular backfill is needed, it will be measured and paid for
as specified in WSWS 2.6.1.
414.2 Pipe Sewers
Pipe sewers will be measured by the linear foot in place, and
the quantity measured for payment shall be the number of linear
feet of each of the various sizes, classes, and types completed
and accepted in accordance with the contract. The measurement
shall be made along the centerline of the pipe, center to center
of junctions and fittings. The footage to be paid for shall be
measured in accordance with the requirements of WSWS 2.9.1.
The quantity of pipe sewers, measured as provided above, will be
paid for at the contract unit prices per linear foot for the
various sizes, classes, and types of pipe specified. This price
shall be payment in full for furnishing all materials, including
special Y's, mitered sections, elbows and connections required;
for all excavation, all pipe, dewatering, sheeting and shoring,
forming foundation, laying pipe, sealing joints and making
connections to new or existing fixtures; for furnishing backfill
material, including bedding and cover material; for backfilling,
compacting, removing sheeting and shoring, cleaning out and
restoring the site of the work; for performing the required
tests; for furnishing manufacturer's certificates; and for
furnishing all labor, supervision, tools, equipment, supplies,
and incidentals necessary to complete the work in accordance
with the contract.
414.3 Manholes, Catch Basins, and Inlets
The construction of manholes shall be measured by the vertical
foot in place and the quantity measured for payment shall be the
number of vertical feet of each of the various sizes and types
completed and accepted in accordance with the contract. The
measurements for manholes shall be from the lowest invert to the
top of the frame (rim).
The construction of catch basins, and inlets shall be measured
by the number of units constructed.
REVISION DATE November 26, 2001 p. 400 - 44
The work under the bid items of Manholes, Catch Basins, and
Inlets, measured as provided above, will be paid for at the
respective contract unit price. Said price shall be full
compensation for furnishing all materials, including all masonry,
conduit and sewer connections, frames, grates, covers, steps, and
other fittings; for all excavation, backfilling, proper disposal
of surplus material, cleaning out and restoring the site of the
work; and for all labor, supervision, tools, equipment, supplies,
and incidentals necessary for each structure complete, except
that chimney seals on sanitary manholes will be paid for
separately.
414.4 Chimney Seals for Sanitary Sewer Manholes
If the Contract Documents have a separate bid item for Furnish
and Install Chimney Seals, all costs associated with furnishing
and installing the chimney seals in accordance with the plans and
Contract Documents shall be included in the contract unit price
for this item. If the Contract Documents do not have a separate
bid item for chimney seals, all costs associated with furnishing
and installing the chimney seals shall be included in the unit
price for the construction, repair, or replacement work at the
sanitary sewer manhole.
414.5 Sanitary Sewer Laterals
The construction of sanitary sewer laterals will be measured by
the linear foot in place, and the quantity measured for payment
shall be the number of linear feet of each of the various sizes
completed and accepted in accordance with the contract. The
measurement shall be made along the centerline of the pipe,
center to center of junctions and fittings.
The quantity of sanitary sewer laterals, measured as provided
above, will be paid for at the contract unit prices per linear
foot for the various sizes of pipe specified. This price shall
be payment in full for furnishing all materials, including
special Y's, mitered sections, elbows and connections required;
for all excavation, all pipe, dewatering, sheeting and shoring,
forming foundation, laying pipe, sealing joints and making
connections to new or existing fixtures; for furnishing backfill
material, including bedding and cover material; for backfilling,
compacting, removing sheeting and shoring, for cleaning up and
restoring the site of the work; for performing the required
tests; for furnishing manufacturer's certificates; and for
furnishing all labor, supervision, tools, equipment, supplies,
and incidentals necessary to complete the work in accordance with
the contract.
REVISION DATE November 26, 2001 p. 400 - 45
414.6 Water Mains and Hydrant Leads
Water mains and hydrant leads shall be measured by the linear
foot in place, and the quantity measured for payment shall be the
number of linear feet of each of the various sizes, classes, and
types completed and accepted in accordance with the contract.
The measurement shall be made along the centerline of the pipe,
center to center of junctions and fittings. The footage of water
mains to be paid for shall include the footage through valves and
fittings. The footage of hydrant leads to be paid for shall be
measured from the centerline of the water main to the center of
the flange on the water main side of the hydrant auxiliary valve.
The quantity of water mains and hydrant leads, measured as
provided above, will be paid for at the contract unit prices per
linear foot for the various sizes, classes, and types of pipe
specified. This price shall be payment in full for furnishing
all materials, including all pipe, fittings, polyethylene wrap,
protective coating, insulation, thrust restraints, and
connections required; for all excavation, dewatering, sheeting,
and shoring, forming foundation, laying and wrapping the pipe,
and making connections to new or existing facilities; for
providing electrical continuity; for installing thermal
insulation; for applying protective coating; for furnishing
backfill material, including bedding and cover material; for
construction of thrust restraints; for furnishing and installing
air relief assemblies; for backfilling, compacting, and removal
of sheeting and shoring; for furnishing material certificates;
for testing the water main as specified; for cleaning up and
restoring the Project Site; and for furnishing all labor,
supervision, equipment, tools, supplies, and incidentals
necessary to complete the work in accordance with the contract.
414.7 Water Main Valves
Water main valves shall be measured and paid for on a unit basis
for the various sizes and types of valves installed and accepted
in accordance with the contract.
The contract unit prices for the various sizes and types of water
main valves shall include all costs associated with furnishing
and installing the valves, valve adaptors, and valve boxes with
bases; furnishing manufacturer's certificates; furnishing and
installing polyethylene wrap around the valves; and for all
labor, supervision, equipment, tools, supplies, and incidentals
necessary to complete the valve installation in accordance with
the requirements of the contract.
414.8 Hydrant Assemblies
Hydrant assemblies shall be measured and paid for on a unit basis
for those assemblies installed and accepted in accordance with
the contract. The hydrant assembly referred to includes the
nozzle section, standpipe (barrel) section, and bottom section
(shoe or base bend) of the hydrant; the polyethylene wrap; and
the auxiliary valve with valve adaptor, valve box, and base;
REVISION DATE November 26, 2001 p. 400 – 46
and accepted in accordance with the contract. The hydrant
assembly referred to includes the nozzle section, standpipe
(barrel) section, and bottom section (shoe or base bend) of the
hydrant; the polyethylene wrap; and the auxiliary valve with valve
box and base.
The contract unit price for hydrant assemblies shall include all
costs associated with furnishing and installing the complete
hydrant assembly and polyethylene wrap; for testing; and for all
labor, supervision, equipment, tools, supplies, and incidentals
necessary to complete the installation of the hydrant assembly in
accordance with the requirements of the contract.
414.9 Water Service Laterals
Water service laterals shall be measured horizontally along the
centerline from the centerline of the main to the end of the
lateral and shall be paid for on a linear foot basis or paid for
on a unit basis for the various sizes of laterals installed and
accepted in accordance with the contract.
The contract unit price for water service laterals shall include
all costs associated with furnishing and installing the
corporation stops (service-to-main tie-in valve), service piping,
curb stops (water service shut off valves), and curb boxes (for
curb stop water service shut off valves); for furnishing
manufacturer's certificates; for all excavating, dewatering,
sheeting and shoring, forming foundation, laying pipe, sealing
joints, and making connections to new or existing fixtures; for
furnishing backfill material, including bedding and cover; for
backfilling, compacting, removing sheeting and shoring; for
cleaning up and restoring the site of the work; for testing; and
for all labor, supervision, equipment, tools, supplies, and
incidentals to complete the installation of the water service
laterals in accordance with the requirements of the contract.
414.10 Underdrain and Sump Drain Connection Lines
Measurement and payment shall be per the linear foot in place for
underdrains, sump drain connection lines, and combination
underdrain and sump drain connection lines. The measurement shall
be made along the center of the pipe.
The contract unit price for such underdrains, sump drain
connection lines, and combination underdrain and sump drain
connection lines shall include all costs associated with
furnishing and installing all pipe, fittings, cleanouts, tracer
wire, geotextile fabric, and backfill material; connecting the
pipe to the storm sewer structure; (if applicable) constructing
the outfall, complete with precast concrete endwall and removable
rodent barrier; backfilling; and (if not specified to be included
in a separate bid item) ground restoration of any lawns or grass
areas disturbed by the pipe installation work.
REVISION DATE December 1, 2003 p. 400 – 47
415 - UNDERDRAINS AND SUMP DRAIN CONNECTION LINES
415.1 General
When underdrains, sump drain connection lines, or combination
underdrain and sump drain connection lines (hereinafter
collectively called “collection pipes”) are specified in the
Contract Documents, the Contractor shall construct them in
accordance with the project plans; details 451, 452, and 453,
respectively; this section; and WDOT Section 612.
The collection pipes shall have a minimum 0.5% slope toward the
point of discharge.
All collection pipes shall commence at cleanout risers and
terminate at storm sewer structures or storm water management
facilities. The Contractor shall be solely responsible for
setting termination points, line, and grade of the collection
pipes shown on the plans.
The collection pipes shall be installed prior to construction of
the curb and gutter (except when the curb and gutter is existing
and is not being replaced).
The Contractor shall install fabric around the stone and pipe as
indicated in details 451 and 453 for underdrains and for combination
underdrain and sump drain collection lines, respectively.
The Contractor shall furnish and install removable rodent barriers
at all open ends of the collection pipes.
415.2 Trenches The trench for the collection pipes shall not exceed eighteen
inches (18") in width, and the centerline of the pipe shall not be
located less than six inches (6") or more than twenty-one inches
(21") behind the back of curb, unless otherwise shown on the plans.
The top of the underdrain package (clear stone and fabric wrap of
details 451 and 453) shall be a minimum of 19.5 inches below the
top of curb.
The depth of the trench for the collection pipes shall not exceed
30 inches from the top of the curb.
415.3 Pipe Pipe shall be as per the following table.
Type of Use Pipe
Type A Underdrain 6” perforated PVC or corrugated HDPE
with fabric sock
Type B Underdrain 6” perforated PVC with fabric sock
Type C Underdrain 6” perforated PVC or corrugated HDPE
with fabric sock
Type D Underdrain 6” perforated PVC or corrugated HDPE
with fabric sock
Sump Drain Connection Line 6” non-perforated PVC with NO fabric sock
Combination Underdrain & 6” perforated PVC with fabric sock
Sump Drain Connection Line
REVISION DATE December 17, 2012 p. 400 – 47(A)
Perforations for PVC pipe shall be four (4) rows of 1/4” to 3/8”
diameter holes, at 3” longitudinal spacing, with approximately 45
and 80 degree orientation on both sides of the vertical centerline
of the pipe, and shall be located at the top one-half (1/2) of the
pipe. Perforations for HDPE pipe shall be one-eight inch (1/8")
and shall be spaced around the entire perimeter of the pipe.
A fabric sock shall be installed around the pipe used for
underdrains or for combination underdrain and sump drain connection
lines. Pipe used for sump drain connection lines shall be
installed without a fabric sock.
415.4 Connection to Structure
The collection pipes shall be connected into the back or the side
of the existing catch basins or inlets, by utilizing a 45-degree
wye or a series of 45-degree PVC fittings. Coring and rebuilding
of existing catch basins or inlets may be required. All
connections to existing catch basins or inlets shall be done in
accordance with Section 3.2.27 of the Standard Specifications for
Sewer and Water Construction in Wisconsin.
The Contractor shall mortar the joint where the pipe connects to
the catch basin or inlet and shall trim the end of the pipe to a
one (1") inch maximum overhang of the pipe at the interior wall
face of the structure.
415.5 Cleanouts
The Contractor shall install cleanout risers at the upstream ends
of the collection pipes and at three hundred foot (300') maximum
intervals along the collection pipes using 45-degree PVC fittings,
unless otherwise shown on the plans. This is to provide means to
clean, flush and locate the collection pipes. Cleanout risers
shall be installed so that the top of the cleanout riser is two
(2”) inches above the finished topsoil grade. The Contractor
shall provide a screw-in plug at the cleanout.
415.6 Tracer Wire
Tracer wire shall be installed along the collection pipes. The
wire shall be taped to the top half of the pipe at ten foot (10')
intervals and not allowed to "float freely" within the backfill.
Tracer wire shall be a minimum 10-gauge, copper single-conductor
wire with type UF (Underground Feed) insulation and shall be
continuous along the pipe and laterals. The wire shall be attached
by means of a screw at the top of the cleanout riser, to insure
that locators can be hooked onto it.
415.7 Staking
On projects where the City provides staking, City survey crews will
place stakes behind the back of curb for line (location) reference
only. Staking will be done at 50 foot intervals, except within
horizontal curves where 25 foot intervals will be used. A radius
point will be placed at intersections.
415.8 Discharges at Ditches or Ponds
If the pipe discharges into a ditch or pond, the Contractor shall
furnish and install a precast concrete headwall with removable
rodent barrier. The headwall shall be approximately three (3’)
feet long with the top sloped to conform to the finished grade of
the side of the ditch.
REVISION DATE December 17, 2012 p. 400 – 47(B)
416 – AMENDMENTS TO WSWS PART VI – TRENCHLESS INSTALLATION OF UTILITIES
WSWS 6.2.3 Casing Pipe
WSWS 6.2.3(a)1 Types
Add the following text:
"Steel casing pipe shall be used for the casing of water main
and sanitary sewer main pipe. The Contractor shall determine
the required diameter, wall thickness, and yield strength of the
casing pipe based upon the anticipated stresses that will occur
during and after installation of the casing and inserted pipes.
The diameter of the casing pipe shall be suitable to accommodate
the size of the pipe and casing spacers (chocks) to be inserted
within the casing pipe. The casing pipe shall also conform to
any other requirements applicable to the project (for example,
specific permits or rules applicable to the project or
additional requirements from outside agencies such as railroad
companies, WisDNR, WisDOT, etc.)."
WSWS 6.2.3(b) Inserted Pipe
Delete this section and replace with the following text:
"Unless specified otherwise in the Contract Documents, all pipes
(other than concrete pipe) inserted into casings shall have
restrained push-on type joints and shall extend at least two (2)
feet beyond both ends of the casing pipe. Wedge action joint
mechanisms such as "Megalug" will not be allowed within the
casing pipe.
When ductile iron pipe is used as the inserted pipe, the ductile
iron pipe shall be installed with polyethylene wrap.
If high-density polyethylene pipe (HDPE), polyvinylchloride
(PVS), or other type of plastic pipe is specified in the
Contract Documents as the inserted pipe, the inserted pipe shall
be installed with twelve (12) gauge tracer wire as specified in
WSWS 4.3.14. "
Add the following sections:
CITY 6.2.3(c) Casing Spacers (chocks)
The Contractor shall furnish and install casing spacers
(chocks) where the inserted pipe is installed within the
casing pipe. The casing spacers (chocks) shall have a
non-metallic liner to isolate the inserted pipe from the
spacer and shall provide a minimum of 0.75 inches of
clearance between the greatest outside diameter of the
inserted pipe and the inside of the casing pipe. The
casing spacers (chocks) shall be attached and spaced in
accordance with the manufacturer’s recommendations.
CITY 6.2.3(d) General
At least one week prior to beginning work on the casing
installation, the Contractor shall submit all
manufacturers’ specifications, including recommended chock
spacing and details and end seals, to the Engineer, in
writing, for review and approval.
REVISION DATE November 27, 2006 p. 400 – 47(C)
CITY 6.2.3(e) Installation
The casing pipe shall be installed at the slope and
elevations shown on the plans.
The pipe shall be supported and braced to prevent shifting
or flotation.
Unless otherwise required, all pipe installed in casing
pipe shall have a flexible joint located not less than two
(2) feet outside the ends of the casing pipe.
The casing pipe shall not be filled once the inserted pipe
has been installed. After the inserted pipe has been
installed within the casing pipe, the Contractor shall
install casing end seals to provide a barrier to backfill
debris and seepage.
WSWS 6.4.2 Materials
Add the following text:
"All HDPE pipe for horizontal directionally drilled pipe shall
be installed with twelve (12) gauge tracer wire as specified in
WSWS 4.3.14."
REVISION DATE November 27, 2006 p. 400 – 47(D)
440 – VIDEO INSPECTION OF SANITARY SEWERS AND STORM SEWERS
440.1 Scope Of Work
The work under this section shall consist of video inspection of
sanitary sewers and storm sewers and preparing a report of the
video inspection.
The Contractor shall furnish all labor, equipment, materials, and
supplies required to do the work.
440.2 General
440.2.1 Video Equipment
Video equipment shall include video camera, television monitor,
cables, power source, lights, and other equipment. The video
camera shall be specifically designed and constructed for sewer
inspections.
The camera, television monitor, and other components of the video
system shall be capable of producing a minimum 350 line
resolution color video picture. The camera shall be mounted on
skids suitably sized for each pipe diameter to be investigated,
or on a self-propelled transporter specifically sized for each
pipe diameter.
440.2.2 Operating Environment
The camera shall be operative in 100 percent humidity. Lighting
for the camera shall minimize reflective glare. Lighting and
camera quality shall be suitable to provide a clear, in-focus
picture of the entire inside perimeter of the sewer pipe for a
minimum length of seven (7) feet, for all conditions encountered
during the work. Focal distance shall be adjustable through a
range of from six (6) inches to infinity.
440.2.3 Footage Counter
The remote reading footage counter shall be accurate to one
percent (1%) over the length of the particular section being
inspected and shall be synchronized with the television monitor.
440.2.4 Push Type Camera
At the Contractor's option, a push-type camera may be used for
video inspection of storm sewer laterals from manholes to the
catch basins/inlets, as well as short dead end pipe (stub)
sections.
440.2.5 Video Recorder
A DVD video recording shall be made during the televising
operation. A high grade DVD format compact disk shall be used.
440.2.6 Video Speed
The DVD shall be recorded at the standard play (SP) setting.
REVISION DATE December 15, 2008 p. 400 – 48
440.3 Video Inspection
The camera shall be moved through the line in either direction at
a uniform rate which allows for maximum clarity of the image,
stopping when necessary to ensure proper documentation of the
sewer's condition, but in no case shall the video camera be
pulled at a speed greater than thirty (30) feet per minute.
Manual winches, power winches, video cable, powered crawlers, or
powered rewinds or other devices that do not obstruct the camera
view or interfere with proper documentation of the sewer
conditions shall be used to move the camera through the sewer.
If, during the inspection operation, the video camera will not
pass through the entire pipe section, the Contractor shall reset
his equipment in a manner so that the inspection can be performed
from the manhole on the opposite end of the line.
440.3.1 Cleaning of the Line
The line to be video inspected shall be cleaned and a dye shall
be flushed down the line to help identify any dips or offsets in
the line. The dye shall be of a color that will contrast with
the color of the inside of the pipe when the video recording is
viewed.
440.3.2 Excess Flow
In the event the section being inspected has substantial flow
entering the sewer between manholes, such that inspection of the
sewer is impaired, then the Contractor shall reroute or pump the
flow past the line being inspected.
440.3.3 Communication During Video Inspection Operations
Whenever non-remote powered and controlled winches are used to
pull the video camera through the line, radios, telephones, or
other suitable means of communication shall be set up between the
two manholes of the section being inspected to ensure that
adequate communications exist between members of the crew.
440.3.4 Calibration and Display of Footage Measurements
Accuracy of the footage counter shall be checked daily by use of
a walking meter, roll-a-tape, or other suitable device. Footage
measurements shall begin at the sewer line point of penetration
of the upstream manhole, unless specific permission is given to
do otherwise. Footage shall be shown on the video monitor at all
times.
440.4 Documentation Of Results Of Video Inspection Of Sewers
440.4.1 Computerized Report
Video inspections shall be documented through the use of a
computer system. This system must be PC compatible with a DVD
drive. The report shall be written in Word 6.0 (or later
version) format or in PDF format (created using Adobe Acrobat
software). All defects and general information on the pipe being
viewed along with an index for retrieving the information must be
supplied to the City as part of the report.
REVISION DATE December 15, 2008 p. 400 – 49
440.4.1.1 Format of Data for Computerized Report
The computerized report shall include, but is not limited to, the
following information:
1. Location of each point of leakage.
2. Location of each service connection measured in feet from the
designated manhole and by point on the pipe axis.
3. Location of any damaged sections, nature of damage, and
location with respect to pipe axis.
4. Deflection in alignment or grade of pipe.
5. Record of repairs and quantity of sealing material used (if
applicable).
6. Day, date, time, city, street and limits, basin, manhole
section, reference manhole number, name of operator, and
weather conditions.
7. Pipe diameter, pipe material, section length, and
corresponding identification of the video.
8. Type of improvement - sanitary or storm sewer.
9. Subdivision name or City construction contract number and
street name.
440.4.2 Inspection Logs
Video inspection logs shall be typed, or computer printed, and
shall be in a form acceptable to the City. Printed location
reports shall clearly show the location, in relation to adjacent
manholes, of each source of infiltration discovered. In
addition, other data of significance include the location of
building and house service connections, joints, unusual
conditions, roots, storm sewer connections, collapsed sections,
presence of scale and corrosion, and other discernible features
shall be recorded. A sketch of the line being inspected and the
direction of the video inspection shall be on the back of the log
sheet.
The measurement of distance to laterals and defects is critical
in confirming the location of areas to be repaired by excavating.
The computerized report may be substituted for the standard
inspection logs only if the computerized report contains the same
information in a format approved by the City prior to the start
of the work.
440.4.3 Video Inspection Report
Color video recordings of the data on the monitor shall be made
by the Contractor. Copies of each video shall be provided to the
City.
Video recording playback shall be the same speed that it was
recorded. Slow motion or stop motion playback features may be
supplied at the option of the Contractor. The Contractor shall
have all videos and necessary playback equipment readily
accessible for review by the City during the project. Video
speed shall be noted on the recorded video. Standard play (SP)
mode shall be used.
REVISION DATE December 15, 2008 p. 400 – 50
440.4.3.1 Format of Data on Video DVD
Video DVDs shall include the following information:
Data view:
1. Report number.
2. Date of TV inspection.
3. Upstream and downstream manhole numbers.
4. Current distance along reach (tape counter footage).
5. Printed labels on DVD disk container and on the DVD disk
cartridge with location information, date, format information,
and other descriptive information.
440.5 Inspection Of Work By City
The City representatives shall be given full access to the site,
including vehicles used to monitor the video inspection, during
the course of the work to view the video inspection operations.
440.6 Possession And Rights Of Video And Reports
Upon completion of the video inspection of the utilities, the
video DVDs and all reports including the video log forms, CD
computerized report, and other records required in this section
as part of the video inspection report shall become the property
of the City of West Bend, who shall have the sole control of all
rights associated with the documents.
- END OF SECTION 400 -
REVISION DATE December 15, 2008 p. 400 – 51
SECTION 400 - SEWER AND WATER CONSTRUCTION
DETAILS
(SEE LIST OF DETAILS IN SECTION 412 OF THESE STANDARD SPECIFICATIONS)
City of
West Bend
City of
West Bend
City of
West Bend
City of
West Bend