statistics in cost analysis
TRANSCRIPT
-
8/8/2019 Statistics in Cost Analysis
1/22
Square Peg ConsultingCopyright 2001, all rights reserved
Quantitative Risk Analysis inBudgeting and Cost Analysis
John C. GoodpastureSquare Peg Consulting
-
8/8/2019 Statistics in Cost Analysis
2/22
Square Peg ConsultingCopyright 2001, all rights reserved
Budgets are estimates
There are no facts about thefuture, only estimates
Simple budget estimates do not
account for riskRisk is handled by estimating the
impact of uncertainties on futurecash flows (uses of funds andsources of funds)
-
8/8/2019 Statistics in Cost Analysis
3/22
Square Peg ConsultingCopyright 2001, all rights reserved
Terms in risk-managed budgeting
Discounting takes into account the risks of
receiving or paying funds in the futureExpected Value takes into account the
uncertainty of estimate
Net Present Value cash value at time zero(now)
Internal Rate of Return discount required
for NPV = 0Economic Value Add (EVA) profit-based
calculation of discounted value
-
8/8/2019 Statistics in Cost Analysis
4/22
Square Peg ConsultingCopyright 2001, all rights reserved
Capital budgeting*Present value (PV) = Value at future date * Discount factorDiscount factor = 1/(1-k)n where n is the number of accounting periods between the
present and the future and k is the cost of capital factor
Net Present Value (NPV) = PV of cash inflows - PV of cash outflows
$ Inflows
$ OutflowsTime
Economic Value Add = After-tax operating income - k (Capital invested)
where k is the cost of capital rate, %
Expected Monetary Value = $OutcomeNth * ProbabilityNthfor all possible outcomes
*The flow of cash and not expenses
-
8/8/2019 Statistics in Cost Analysis
5/22
Square Peg ConsultingCopyright 2001, all rights reserved
PM influences NPV via the project
timeline
First, the value of money decays over time. This
decay is due to the effects of inflation, the uncertaintythat future flows will continue or begin, and the
uncertainty that a better investment is available
elsewhere. In all cases, the present value is morethan the future value.
Second, the value of the project is the netof the present value of all the cash outlays forinvestment and inflows from operations and
salvage.
-
8/8/2019 Statistics in Cost Analysis
6/22
Square Peg ConsultingCopyright 2001, all rights reserved
NPV
Future benefits are discounted to thepresent to account forRISK in the future.
Time
$ Benefits, Expected Value
NPV is the benefits + investment in the present value.IRR is the discount rate that makes NPV equal to $0.
$ Investment
{present values}
-
8/8/2019 Statistics in Cost Analysis
7/22
Square Peg ConsultingCopyright 2001, all rights reserved
Two-dimensional risks
PresentTime
Future Time
Estimate Uncertainty
Discount forInflation
Risk of getting paid
Capital cost
Denied opportunity
Market uncertainty
Distribution of estimate
EV
-
8/8/2019 Statistics in Cost Analysis
8/22
Square Peg ConsultingCopyright 2001, all rights reserved
PV table
Year 0 1 2 3 4
5% 1.0 0.952 0.907 0.864 0.823
8% 1.0 0.926 0.857 0.794 0.735
12% 1.0 0.893 0.797 0.712 0.636
13% 1.0 0.885 0.783 0.693 0.613
14% 1.0 0.877 0.769 0.675 0.592
Discount
PV = Value before discount * factor at intersection of
Discount and Year
-
8/8/2019 Statistics in Cost Analysis
9/22
Square Peg ConsultingCopyright 2001, all rights reserved
NPV example$500 investment made now, that
yields a $1000 benefit 2 years fromnow, at a discount factor of 12%,has an NPV of $?.
Answer: From the table of present values, find the factor
for 12% 2 years from now; multiply the FV by the factorto get the PV; net with the investment
-$500 + 1000 * 0.797 = $297
-
8/8/2019 Statistics in Cost Analysis
10/22
Square Peg ConsultingCopyright 2001, all rights reserved
NPV example
Mathematically:$297 = -$500/(1 + 12%)0 +$1000/(1 + 12%)2
$297 = -$500 + $797
-
8/8/2019 Statistics in Cost Analysis
11/22
Square Peg ConsultingCopyright 2001, all rights reserved
NPV and EVA in project
selection
A valuable project has positive, or atworst $0, NPV
A valuable project must earn back more
than, or at worst equal, the cost of thecapital invested: EVA > $0
Discount rate used in NPV and EVA for
project approval is the hurdle rateIRR is the maximum discount rate for
EVA or NPV = $0
-
8/8/2019 Statistics in Cost Analysis
12/22
Square Peg ConsultingCopyright 2001, all rights reserved
Pauls project
$500K investment required
12.8% hurdle rate
$700K+ benefit stream estimated
over 5 yearsIs this a good deal?
-
8/8/2019 Statistics in Cost Analysis
13/22
Square Peg ConsultingCopyright 2001, all rights reserved
Pauls project, NPVPaul's Project
$000
YearCash
InvestmentBenefits Face
ValueBenefits PresentValue @ 12.8%
PV Cash Flow
0 ($500.00) ($500.00)
1 $141.46 $125.41 ($374.59)
2 $141.46 $111.18 ($263.42)3 $141.46 $98.56 ($164.85)
4 $141.46 $87.38 ($77.48)
5 $141.46 $77.46 ($0.01)
Totals ($500.00) $707.30 $499.99 ($0.01)
NPV = $0; IRR is 12.8%
A-risk-neutral investor would take $0 or the project opportunityindifferently
Spreadsheet add-in Resolver will iteratively solve for benefits giventhe investment and hurdle rate.
-
8/8/2019 Statistics in Cost Analysis
14/22
Square Peg ConsultingCopyright 2001, all rights reserved
EVA
AlternativeCompetingfor Capital
AlternativeCompetingfor Capital
EVANet Cash
Benefits fromProject
Opportunity CostofCapital
Employed
After-TaxEarnings
$0
CE x discount rate = CCECapital Employed to Execute a Project
EVA = (Present value of after-tax earnings) (Benefits from the next bestcompeting opportunity)
-
8/8/2019 Statistics in Cost Analysis
15/22
Square Peg ConsultingCopyright 2001, all rights reserved
Pauls project EVA Depreciate $500K annually at $100K per year, discount
rate 12.8%
Depreciation Schedule for Paul's Project$000
Year 1 Year 2 Year 3 Year 4 Year 5 Total
$100.00 $100.00 $100.00 $100.00 $100.00 $500.00 Depreciation
$500.00 $400.00 $300.00 $200.00 $100.00Capital employed
(CE)
12.80% 12.80% 12.80% 12.80% 12.80%Cost of capital rate
(CCR)
$64.00 $51.20 $38.40 $25.60 $12.80 $192.00Cost of capitalemployed (CCE) =
CE x CCR
$56.74 $40.24 $26.75 $15.81 $7.01 $146.55 PV CCE
-
8/8/2019 Statistics in Cost Analysis
16/22
Square Peg ConsultingCopyright 2001, all rights reserved
Paul's Project Plan with EVA = $0$000
Outlays shown as ($000), Discount factor 12.8%
Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 TOTAL
($500.00) Investment
$56.74 $40.24 $26.75 $15.81 $7.01 $146.55 PV CCE
$29.31 $29.31 $29.31 $29.31 $29.31 $146.55 PV after-taxearnings
($27.43) ($10.93) $2.56 $13.50 $22.50 $0.00PV EVA
$33.06 $37.29 $42.07 $47.45 $53.53 $213.40 FV after-taxearnings
$100.00 $100.00 $100.00 $100.00 $100.00 $500.00 FVdepreciation
$133.06 $137.29 $142.07 $147.45 $153.53 $713.40 FV cashbenefits
($500.00) $117.96 $107.90 $98.99 $91.08 $84.07 $0.00 NPV cashbenefits
Project goal
NPV of Net Cash Flow = EVA of after-tax earnings
-
8/8/2019 Statistics in Cost Analysis
17/22
Square Peg ConsultingCopyright 2001, all rights reserved
Present value of EVA of cashearnings and NPV of cash flow areequal!
-
8/8/2019 Statistics in Cost Analysis
18/22
Square Peg ConsultingCopyright 2001, all rights reserved
Risk analysis in expense (cost)
estimating
1. Begin with WBS
2. Use decision trees to evaluate EMV ofalternatives in each WBS, asappropriate
3. For uncertain cost elements, estimatea distribution
4. Obtain PV of all EVs5. Sum EVs and deterministic costs for
project estimate
-
8/8/2019 Statistics in Cost Analysis
19/22
Square Peg ConsultingCopyright 2001, all rights reserved
Project WBS
Project NEW PRODUCT
Product Design2
PM Office
1 SoftwareDevelopment3
Integration andTest
4
Deployment6
Training and
Support5
-
8/8/2019 Statistics in Cost Analysis
20/22
Square Peg ConsultingCopyright 2001, all rights reserved
3-point estimate and the error of
Most Likely
$41Total WBS2,3,4
$23$15$114. Integration &Test
$35$20$163. SW Design
$10$6$4
2. Product
Design
PessimisticMostLikely
OptimisticWBS Element
Project Cost Estimates and Ranges
$000
All WBS cost estimates are PV
-
8/8/2019 Statistics in Cost Analysis
21/22
Square Peg ConsultingCopyright 2001, all rights reserved
EV is a better estimate
$46.67
(14% greater than Most Likely)
$41Total WBS 2,3,4
$16.33$154. Integration &Test
$23.67$203. SW Design
$6.67$62. Product Design
Expected Value*Most LikelyWBS Element
Project Cost Estimates and Ranges
$000
Triangular distribution assumed
*The EMV from a decision tree outcome for a WBS element
would go in this column
-
8/8/2019 Statistics in Cost Analysis
22/22
Square Peg ConsultingCopyright 2001, all rights reserved
Whats been learned?
Capital budgeting is about cashflow
NPV and EVA are equivalent
Good projects have positive NPVand EVA
EV math reduces risk of WBS costestimates