status of our x-band klystrons

28
Status of our X-band klystrons SLAC XL5 (a short history) CPI VKX-8311A Toshiba E37113

Upload: aneko

Post on 24-Feb-2016

108 views

Category:

Documents


2 download

DESCRIPTION

Status of our X-band klystrons . SLAC XL5 (a short history) CPI VKX-8311A Toshiba E37113. XL5 First ‘optimistic’ planning presented at CLIC workshop October 2007. JPD considered it to be too pessimistic !!!. XL5 performance at SLAC (Feb 2010). - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Status of our X-band klystrons

Status of our X-band klystrons

SLAC XL5 (a short history)CPI VKX-8311AToshiba E37113

Page 2: Status of our X-band klystrons

XL5First ‘optimistic’ planning presented at CLIC workshop October 2007

2007 2008 200911 12123456789 10 11 121234567

Klystron feasibility and costing enquiry

Finance Committee Approval (for klystron collaboration and project approval)

Order Klystron

Klystron Manufacture and Delivery

Modulator Price Enquiry

Modulator Manufacture and Delivery

Preparation of Modulator area

Procurement and preparation of auxiliaries

Preparation of test area

Procurement and manufacture of test area equipment

Low level RF

START TEST STAND COMISSIONING (single klystron)

JPD considered it to be too pessimistic !!!

Page 3: Status of our X-band klystrons

XL5 performance at SLAC (Feb 2010)

Voltage, Current and rf waveforms at 57MW 1.25usDespite admin delays (1 year to agree to WFO text) SLAC had klystron ready ahead of schedule

Unfortunately during preparation for shipment the klystron was damaged

Best efforts agreement meant CERN had to pay for repair Klystron eventually delivered to CERN end of October 2010

Page 4: Status of our X-band klystrons

Klystron Delivered to CERN October 2010

Although there was some cosmetic damage the tube vacuum was ok and there didn't seem to be anything visually wrong with the tube

Page 5: Status of our X-band klystrons

Klystron installation in modulator with help from our SLAC collaborators

Many teething problems with modulator calibration, interlocking etc. But we got first pulse on klystron before end of the year, stopped to do some modifications to modulator

Page 6: Status of our X-band klystrons

First signs of trouble

• When klystron was reinstalled we turned Ion Pump supplies on and they indicated that the klystron was up to near air pressure ... Disaster as klystron is sealed unit with pinch off

• Contacted SLAC and we decided a leak test may be possible, SLAC sent engineer to participate

• While waiting for SLAC engineer, we removed the tube and contacted our vacuum group to see what was the best way to proceed

Page 7: Status of our X-band klystrons

Leak test showedceramic feed throughon ion pump was leaking

New ion pump and valve installedtube pumped down vacuum ok

Page 8: Status of our X-band klystrons

Tube was baked out at 200 degrees for 4 daysActivated cathode during the bake out periodSuccess tube ready for reinstallation

Page 9: Status of our X-band klystrons

Reinstallation of klystron in modulator

• Several issues with believing current and voltage calibration of the modulator

• But tube was pulsing !!!

• If we believe the figures from the voltage and current waveforms the perveance (I/V3/2) on the tube is lower than what was seen at SLAC

• Varying heater filament current while pulsing eliminated the idea of cathode pollution (poor electron emission). One other option left, was the cathode misaligned in the gun?

• Unfortunately the calorimetric measurement confirmed the low perveance and allowed us to believe that the voltage and current measurements were correct

• Temperature probes were installed at input and output of collector water cooling and also a precision flow meter in order to do a calorimetric check.

Page 10: Status of our X-band klystrons
Page 11: Status of our X-band klystrons
Page 12: Status of our X-band klystrons
Page 13: Status of our X-band klystrons

Conclusive that there is a misalignmentalthough we don't really know how it happened

what do we do ?

• First option• We send the tube back to SLAC for repair• As its a best effort collaboration will cost us 200k$

and at least 6 months delay• Second option

• Long shot, try and realign gun at CERN• Risky but if it doesn't work the tube will have to be

sent back anyway• Extra 4 week delay but worth the risk?

Page 14: Status of our X-band klystrons

After consultation with SLAC we prepared a clamping system to squeeze the gun on the “low side”

The process seemed to have worked and the misalignment was removed and tube vacuum still ok

Tube reinstalled in modulator

Page 15: Status of our X-band klystrons

Many measurements were performed to see if the klystron behaves as it did in SLAC

0 200 400 600 800 1000 120000.5

11.5

22.5

33.5

4f(x) = 0.00000329708 x² + 0.0000434317 x + 0.0174008R² = 0.999856734068473

Vchg vs collector dt

primary Vchg [V]

colle

ctor

dT

[dT]

0 50 100 150 200 250 300 350 400 4500.000.200.400.600.801.001.20

Vchg vs uK

Vchg [kV]uK

[A/

V^1.

5]

0 50000 100000 150000020000400006000080000

100000120000

f(x) = 1.084980799531 x − 934.2821709306R² = 0.999742854138294

peak power cap vs chg

P cap[kW]

P ch

g[kW

]0 50 100 150 200 250 300 350 400 450

050

100150200250300350400

f(x) = − 0.000362963 x² + 1.0803788 x − 5.6450614R² = 0.99992408812278

f(x) = 0.910959758828326 x + 9.08960033678321R² = 0.998447967992157

Vchg vs Vcap

Vchg [kV]

Vcap

[kV

]

0 50 100 150 200 250 300 350 4000.000.200.400.600.801.001.201.40

Vcap vs uK

Vcap [kV]

uK [

A/V^

1.5]

0 50 10015020025030035040045000.5

11.5

22.5

33.5

4

f(x) = 0.0000228339 x² − 0.000130577 x + 0.0265783R² = 0.999845480772457

Vchg vs dT

Vchg [kV]

dT [

K]Electrically it works

Page 16: Status of our X-band klystrons

First RF from klystron on 6th September 2011Snippet from logbook

No vacuum activity in klystron only loads

Page 17: Status of our X-band klystrons

For almost 2 years, ~13000 operational hours no problemsGun arcs started occurring in November last year

Decided to remove klystron to see if ion pump reading was klystron or modulator problem

With klystron removed the modulator circuit for ion pump supply was ok

Page 18: Status of our X-band klystrons

5kV

Klystron moved to assembly area

Ion pump at high voltage cathode potential on gun

Page 19: Status of our X-band klystrons

5kV

Page 20: Status of our X-band klystrons

5kV

Shell Diala B oil reacted with rubber insulationcausing it to “dissolve”

We are now reasonably confident that the tube may still be ok to operate

Page 21: Status of our X-band klystrons

CPI VKX-8311A

• Call for tender for industrialized XL5 equivalent September 2010• Contract signed with CPI 25th June 2011 for two tubes with

option of a spare– Under DOE rules SLAC collaborated with CPI for the industrial design

• Delivery of first tube expected March 2013• After bake out of tube there was a vacuum problem due to

some contamination in the gun area – tube refurbishment• Tube shipped to SLAC for testing July 2013, took 5 months to

condition to nominal 50 MW (not just klystron problem but RF network conditioning and no 24/7 running at SLAC)

• Tube final factory acceptance tests January 2014

Page 22: Status of our X-band klystrons

CPI VKX-8311A

Page 23: Status of our X-band klystrons

CPI VKX-8311A

Page 24: Status of our X-band klystrons

CPI VKX-8311A

• 2nd tube has been assembled and baked out– After consultation with SLAC the bake out temperature was

increased by 90 degrees compared to first tube• Unfortunately there are 2 leaks on the output gaskets on

the waveguide components– New gaskets being manufactured– New bake out in 2 to 3 weeks– Testing at SLAC probably beginning of April

• Acceptance tests estimated for June/July 2014 (if testing goes well)

• Option for 3rd tube, not ordered yet

Page 25: Status of our X-band klystrons

Toshiba E37113• 6 MW, 400 Hz, 5µs• Turnkey solution for 4 klystron modulators• Tender March 2013• Contract August 2013• Delivery of fist pre series klystron modulator

planned for October 2014– Klystron design and manufacture ahead of schedule– Modulator on schedule

• 3 series production units no later than July 2015

Page 26: Status of our X-band klystrons

Toshiba E37113

Compact Scandinova Modulator

Klystron outline

Page 27: Status of our X-band klystrons

Toshiba E37113in XBOX 3

Page 28: Status of our X-band klystrons

Summary• XL5 removed from XBOX 1, will be installed in XBOX 2 next week

– Commission modulator with this tube – Test if tube is ok– Condition crab cavity

• CPI tube S.No. 1– Arrives next week– Install in XBOX 1 (happy with modulator, easier to commission new tube)– Test into load tree to full power (50 MW, 1.5µs)– Put load tree in CTF2 and condition RF network with compressed pulse– Connect to cavity in dogleg and condition

• CPI tube S.No. 2– Upon arrival install in XBOX2 to do acceptance tests on tube

• Keep XL5 as hot spare if still considered operational until CPI tube number 3 arrives, otherwise send back to SLAC for repair