…striving for resilience in the face of adversity…
MCWD 2015 ANNUAL REPORT
1
TABLE OF CONTENTS
EXECUTIVE SUMMARY ....................................................................................................... 2
WHAT WE DO? ...................................................................................................................... 2
MANDATE ............................................................................................................................... 2
CORE PURPOSE ..................................................................................................................... 3
CORE VALUES ........................................................................................................................ 3
CORE STRATEGY .................................................................................................................... 4
CORPORATE OBJECTIVES .............................................................................................................. 4
COMPLIANCE WITH RA 10026 ................................................................................................ 4
WHAT WE HAVE DONE? ...................................................................................................... 11
OPERATIONAL HIGHLIGHTS ............................................................................................ 11
ENSURING WATER SAFETY ............................................................................................. 11
WATER TREATMENT AND WATER QUALITY TESTING ACTIVITIES .............................................. 14
REGULAR FLUSHING AND WATER PRESSURE MONITORING ...................................................... 16
REGULAR CLEANING OF THE DAM AND SETTLING BASIN ........................................................ 17
SETTLING BASIN WALL REHABILITATION ................................................................................ 18
CONSTRUCTION OF WAREHOUSE .......................................................................................... 19
DRAINAGE SYSTEM CONSTRUCTION ...................................................................................... 20
CONSTRUCTION OF PERIMETER FENCING OF BASIN COMPOUND ............................................ 21
RETAINING WALL / PIPE ENCASEMENT PROJECT ................................................................... 22
IMPROVEMENT OF WATER FACILITY ............................................................................. 23
DISTRIBUTION PIPELINE EXTENSION – JOSON DE MATA ST., BAYBAY, CARIGARA .................... 23
DISTRIBUTION PIPELINE IMPROVEMENT – BRGY. BISLIG, CARIGARA, LEYTE ................................ 24
DISTRIBUTION PIPELINE UPGRADING – BRGY. MINUHANG, BARUGO, LEYTE .............................. 24
DISTRIBUTION PIPELINE UPGRADING – BRGY. PARENA, CARIGARA, LEYTE ................................. 25
DISTRIBUTION PIPELINE UPGRADING – BRGY. CANAL-UYAWAN, CARIGARA, LEYTE .................... 26
DISTRIBUTION PIPELINE UPGRADING – BRGY. BALILIT, CARIGARA, LEYTE .................................. 27
COMPANY INFORMATION ................................................................................................... 40
MCWD 2015 ANNUAL REPORT
2
EXECUTIVE SUMMARY
The year under recovery process that has continued apace highlights the challenges two
years after Typhoon Yolanda left Eastern Visayas a badlands. This is also the time where
evaluation takes place, assessing what worked and did less so and make the efforts
required to further enhance capacity to respond and recover in the future; a time for
shared responsibility in building resilience to the affected community. Thus, the people
behind the Metro Carigara Water District (MCWD) were fueled with optimism and vibrancy
in helping rebuild lives and continue to share in the District’s struggle to a phase of
recovery and rehabilitation efforts after surmounting the challenge of providing safe water
which is every man’s most basic need.
This 2015 Annual Report allows the reader to see and understand the ceaseless efforts
of the MCWD team, spirited to move on with the guiding efforts committed to genuine
public service, highlighting the continuous implementation of various projects, programs
and strategies to ensure that the MCWD stands true to its commitment of providing safe
water supply at all times.
WHAT WE DO?
MANDATE
The Metro Carigara Water District, originally named Carigara Metropolitan Water District,
was created in January 25, 1983, by virtue of the resolutions passed by the respective
municipal councils of the municipalities of Carigara, Barugo, Tunga and Capoocan,
following the enactment of the Presidential Decree 198 (Provincial Water Utilities Act of
1973) in September 1973 by then President Ferdinand E. Marcos to ensure that Filipinos
in the countryside have access to safe and potable water.
MCWD 2015 ANNUAL REPORT
3
Pursuant to said mandate the MCWD was thus created for the following purposes laid
down by the law:
Acquiring, installing, improving, maintaining and operating water supply and
distribution systems for domestic, industrial, municipal and agricultural uses for
residents and lands within the boundaries of such districts;
Providing, maintaining and operating wastewater collection, treatment and disposal
facilities; and
Conducting such other functions and operations incidental to water resource
development, utilization and disposal within such districts, as are necessary or
incidental to said purpose. (PD 198, as amended, Chapter II, Sec. 5)
CORE PURPOSE
“QUALITY OF LIFE by way of SAFE, SUFFICIENT and AFFORDABLE WATER for the people
of Metro Carigara.”
CORE VALUES
Public service centered on love of God and country.
Excellence and integrity.
Professionalism and performance.
Stewardship of tomorrow and the environment.
MCWD 2015 ANNUAL REPORT
4
CORE STRATEGY
The MCWD aims to achieve its vision, mission and objectives through Total Quality
Management.
CORPORATE OBJECTIVES
Water Security
Water Resiliency
Service Congeniality
Efficient and Effective Resources Management
COMPLIANCE WITH RA 10026
Republic Act No. 10026, also known as, “An Act Granting Income Tax Exemption to Local
Water Districts By Amending Section 27(C) of the National Internal Revenue Code (NIRC)
of 1997, As Amended, and Adding Section 289-A to the Code, for the Purpose,” provides
for exempting local water districts from the payment of corporate income tax as a way
of giving support to their mandate to provide clean and safe water to the provinces. As
such, water districts are expected to comply with the requirements of the law for such
tax exemption by using the amount that would have been paid as income tax for capital
expenditures that are aimed at expanding and improving the quality of water services and
adopting internal control reforms, among others.
After last year’s compliance, the MCWD once again dutifully complies with the mandate
of RA 10026. The year was focused on various projects and programs in the areas of a)
water service improvement, b) NRW Management, c) fiscal discipline and sustainability
MCWD 2015 ANNUAL REPORT
5
measures, and d) capacity building. The weakest economic growth brought about by the
enormous destruction due to the super typhoon further did not hinder the district’s
outlook for expansion, which was able to realize the following:
2015 PROGRAM OF INTENAL REFORMS
% of
Accomplishment
I. Water Service Improvement
Projects/Programs Implemented
1. Air Release Valve and Hydrants Installation 100%
2. Joson de Mata Pipeline Expansion 80%
3. Water Meters and Service Connections Clustering 30%
4. Brgy. Bislig Distribution Pipeline Improvement 100%
5. Brgy. Minuhang Distribution Line Upgrading (11/2” GI
Pipe to 3ӯ uPVC Pipes)
100%
6. Brgy. Parena Distribution Line Upgrading 100%
7. Brgy. Canal – Uyawan Distribution Line Upgrading 100%
8. Brgy. Balilit Distribution Line Upgrading 30%
9. Perimeter Fencing (Phase IV) 100%
10. Shed House Improvement 100%
11. Warehouse Construction (Phase II) 100%
12. Drainage Construction (Phase I & II) 100%
II. Non-Revenue Water Management
Projects/Programs Implemented
1. Non-Revenue Reduction Program 10%
MCWD 2015 ANNUAL REPORT
6
III. Fiscal Discipline and Sustainability Measures
Projects/Programs Implemented
1. Settling Basin Wall Rehabilitation (Phase 1 & 2) 100%
2. Transmission Intake Pipe Realignment 100%
3. Dam Wall Rehabilitation 100%
4. Pipelaying from Dam - Basin 3%
IV. Capacity Building
Projects/Programs Implemented
1. Training of employees
1st Congress on Fortifying Graft and Corruption 100%
Orientation on Sexual Harassment Law 100%
Seminar on Strategic Human Resource Management 100%
Water Philippine 2015 Expo 100%
Seminar on Gender Sensitivity and Development (GAD) 100%
Re-Orientation Seminar on GSIS Rules 100%
Orientation on Disaster Risk Reduction Management Plan 100%
Public Sector HR Symposium and PSTD National
Convention “Transformation Through Leadership
Development”
100%
Basic Policy Makers Seminar 100%
Basic Orientation on Climate Change 100%
Seminar on Gender Sensitivity and Responsive Planning
and Budgeting
100%
5th CSC Visayas HRMP Congress on Talent and
Character Champions
100%
Prime Human Resource Assessment 100%
MCWD 2015 ANNUAL REPORT
7
Orientation on Causes and Symptoms of Hypertension 100%
Gender and Development Plan Orientation 100%
23rd PWWA Internal Conference and Exhibition 100%
WASH (Water Sanitation and Hygiene) Training 100%
Orientation on Causes and Symptoms of Diabetes 100%
3rd Quarterly EVAWD Meeting and Continuation 100%
Gender Sensitivity Seminar for the Human Resource
Practitioners and GAD Focal Person
100%
Updates on Bureau of Internal Revenue (BIR) Rules and
Regulations
100%
Government Service Insurance System (GSIS) –
Stakeholders Dialogue
100%
Corporate Planning 100%
Further, internal control measures were observed in an effort to ostensibly achieve
management’s objectives of ensuring economic and financial viability. As a whole, the
2015 operations can be viewed as follows:
Annual Report of LWDs Pursuant to R.A. No. 10026
METRO CARIGARA WATER DISTRICT
2015
1. SERVICE CONNECTION
1.1 Total Services 8,113
1.2 Total Active 6,828
1.3 Total Metered 6,828
1.4 Total Billed 6,682
1.5 Population Served 48,678
MCWD 2015 ANNUAL REPORT
8
1.6 Number of Connections
Domestic/Government 6,267
Commercial/Industrial 229
Semi-Commercial A 98
Semi-Commercial B 69
Semi-Commercial C 16
Bulk/Wholesale 3
Total 6,682
2. WATER PRODUCTION (cu.m.)
2.1 Pumped (e.g. wells) _
2.2 Gravity (e.g. springs) 1,646,385
2.3 Purchased _
Total 1,646,385
2.4 Total Rated Capacity 202,000
2.5 Non-revenue Water 19.31%
2.6 Pumping Expense/cu.m. Produced _
2.7 Treatment Expense/cu.m. Produced 0.76
2.8 Fuel for Pumping Expense/cu.m. Produced _
2.9 Total Production Expense/Connections/Month 33.96
2.10 Total Production Expense/Operating Expense 11.75%
3. PERSONNEL COMPLEMENT
3.1 Number of Regular Employees 41
3.2 Number of Casual Employees 4
3.3 Number of Connections per Employee 151:1
3.4 Average Monthly Salary/Employee 17,558.33
MCWD 2015 ANNUAL REPORT
9
3.5 Average Payroll/Operating Expense 43.53%
4. FINANCIAL DATA
4.1 Revenues 35,032,199.88
Operating 34,683,287.64
Non-operating 348,912.24
4.2 Expenses 24,858,427.13
Pumping Costs (fuel, oil, electric) _
Chemicals for Treatment 478,373.06
Purchased Water _
Other O and M Expenses 9,362,725.17
Depreciation Expenses 2,157,583.50
Interest Expenses 1,157,074.56
Salaries and Wages 10,313,004.04
Travel 429,636.80
Transportation and Representation 564,000.00
Honoraria and Allowances 396,030.00
Net Income Before Income Tax 10,173,772.75
4.3 Capital Expenditure 6,292,758.45
Expansion Projects 96,193.11
Rehabilitation Projects (including structures,
improvements & facilities)
3,797,612.64
Electromechanical Facilities _
Purchase of Vehicles, Water Meters, Water Treatment
Equipment, Tools and Other Office Equipment
2,398,952.70
5. TAX SAVINGS APPLICATION
5.1 Purchase of Lot _
MCWD 2015 ANNUAL REPORT
10
5.2 Construction of Structures (dam, pumping station,
etc.)
1,300,716.84
5.3 Rehabilitation of Pipelines, Wells, Pumping Stations,
etc.
1,607,020.72
5.4 Expansion (pipelines, well drilling) 96,193.11
5.5 Expansion of Service Area _
5.6 Development of New Water Resources _
5.7 Purchase of Electromechanical Facilities _
5.8 Purchase of Motor Vehicles, Water Treatment
Equipment
268,730.00
5.9 NRW Reduction Program _
5.10 Others _
MCWD 2015 ANNUAL REPORT
11
WHAT WE HAVE DONE?
Operational Highlights
ENSURING WATER SAFETY
Water safety is the primary concern of MCWD. To ensure the delivery of safe
drinking water to our concessionaires, regular water quality monitoring is
conducted throughout the year. In 2015, all of the water samples collected around
the service area of the water district have passed the Philippine National Standards
for Drinking Water (PNSDW).
The following tables show the summary of the different water quality tests
conducted for the year 2015.
Table 1. SUMMARY OF BACTERIOLOGICAL TEST RESULT
MONTH No. of
Samples Taken
No. of Negative
Results
No. of Positive
Results
No. of Results
Submitted to LWUA
January 8 8 0 8
February 9 9 0 9
March 9 9 0 9
April 9 9 0 9
May 10 10 0 10
June 10 10 0 10
July 10 10 0 10
August 10 10 0 10
September 10 10 0 10
October 10 10 0 10
MCWD 2015 ANNUAL REPORT
12
November 10 10 0 10
December 10 10 0 10
Total 115 115 0 115
Table 2. SUMMARY CHLORINE RESIDUAL MONITORING
MONTH No. of Samples
Taken
No. of Samples
Meeting PNSDW
No. of Days with
Full Chlorination
January 63 63 31
February 67 67 28
March 81 81 31
April 72 72 30
May 79 79 31
June 83 83 30
July 59 59 31
August 63 63 31
September 92 92 30
October 43 43 31
November 69 69 30
December 36 36 31
Total 807 807 365
MCWD 2015 ANNUAL REPORT
13
Table 3. SUMMARY OF BACTERIOLOGICAL TEST USING PHC MEDIA
Month No. of Samples
Taken
No. of Negative
Results
No. of Positive
Results
January 10 10 0
February 10 10 0
March 15 15 0
April 10 10 0
May 15 15 0
June 15 15 0
July 9 9 0
August 14 14 0
September 20 20 0
October 5 5 0
November 10 10 0
December 5 5 0
Total 138 138 0
MCWD 2015 ANNUAL REPORT
14
Water Treatment and Water Quality Testing Activities
Metro Carigara Water District
employs a simple water
treatment process which
involves sedimentation and
chlorination. Raw water from
Maula-og River is drawn from
the impounding dam. Water
is transported from the
impounding dam to the
treatment plant by gravity.
The treatment begins in a small water maze where the initial reduction of silt and
turbidity takes place. Initial disinfection also takes place through a pre-chlorination
treatment which is done at the inlet of the small water maze using dissolved
chlorine granules. The pre-treated water is then sent to the sedimentation basin
where reduction of turbidity takes place as sediments settle at the bottom of the
basin. Lastly, water is
disinfected by injecting
chlorine gas before it
is sent to the
consumers. Chlorine
gas is fed at rates
ranging from 28 to 30
pounds per day and is
strictly monitored
hourly. The chlorine
dosage is regulated to
maintain a chlorine residue concentration of not lesser than 0.3 nor greater than
Chlorine Gas (1 Ton)
Mixing Containers of Chlorine Granules
MCWD 2015 ANNUAL REPORT
15
1.5 parts per million (ppm) in any point of the distribution system as required of
the Philippine National Standards for Drinking Water (PNSDW).
Another water source is a spring located in Brgy. Daraupay, Capoocan, Leyte. This
water source is enclosed in a spring box and can supply water to the said
barangay. The spring water is disinfected using chlorine granules. Chlorine granules
are dissolved and is introduced to the spring water drop wise. The spring box is
visited and chlorine solution is supplied weekly. The chlorine residue is measured
and the dosage is regulated to meet the PNSDW for chlorine residue.
To monitor the water quality in
the distribution system, the
Production and Water Quality
Division conducts regular water
sampling and testing. Chlorine
residue monitoring is
conducted twice a week. This
is done in selected sampling
points around the four municipalities covered by the MCWD service area. The
permissible limits imposed is 0.3 to 1.5 ppm following the PNSDW requirement.
The results obtained are recorded in a Water Sampling Monitoring Sheet along
with the concessionaire information and details of the test conducted.
On-site Chlorine Residual Test at Santarin Elementary School
MCWD 2015 ANNUAL REPORT
16
To monitor the
microbiological quality of
the water, bacteriological
tests are conducted
regularly. Water samples
from different sampling
points in the service area
are collected monthly
and sent to the Leyte
Metropolitan Water
District (LMWD)
Laboratory for
bacteriological test. The number of samples collected and sent for analysis is
based on the number of population served by the water district following the
PNSDW.
Another bacteriological test is conducted by the Production and Water Quality
Division. The presence or absence of the indicator bacteria E. coli in the water is
determined using Primary Health Care Media. This test is conducted weekly and
is properly documented with pictures of the water sampling and results.
Aside from the treated water, the quality of the raw water is also monitored.
Samples from the water source are collected and are sent to LMWD Laboratory
for Physical-Chemical Analysis. This is done twice a year. The sterilized sampling
bottles used for the said tests are obtained from LMWD laboratory.
Regular Flushing and Water Pressure Monitoring
Regular flushing of distribution and transmission pipelines are conducted regularly
to eliminate the sediments present in the pipes that may cause turbidity of the
Samples collected for Primary Health Care Media Test
MCWD 2015 ANNUAL REPORT
17
water. Flushing is conducted at least once a month in each of the municipality
served by the water district. The activity is scheduled to be done at 10 o’clock
in the evening as the consumption is lesser during this time.
Another function of the Production and Water Quality Control Division is the
regular monitoring of the water pressure. This regular activity of the Production
Division is assigned to a Water Utilities Maintenance Man. He is responsible in
the regular controlling of the main gate valve at settling basin. This main valve
controlling has two purposes namely (1) to raise the water level and (2) to control
the water pressure on the main distribution lines that may burst at night. Reducing
main gate valve is usually done in the evening because consumers of the water
district reduces to almost 90%. The main gate valve that is located at our settling
basin compound, is being reduced to a given or specified turns depending on the
water level at exactly 9pm and start opening at 2am until it reaches its full
opening to 24 turns.
TIME WATER LEVEL NO. OF TURNS REDUCED
9 PM 2.79 METERS – BELOW 21 TURNS
9 PM 2.80 METERS – ABOVE 20 TURNS
Regular Cleaning of the Dam and Settling Basin
Cleaning of the dam at Maulaug
River and at settling basin has
been a regular activity of the
water district to ensure safe
drinking water supply. These are
conducted in order to remove the
settled sludge at the bottom of
Scraping sludge at Settling Basin
MCWD 2015 ANNUAL REPORT
18
the basin for the past six months’ period.
Cleaning of the settling basin is done twice a year. For 2015, the cleaning of settling
basin was conducted last April 13 to 16 and December 1 to 4. The scheduled cleaning
of the settling basin took a bit longer than in the previous years because the rehabilitation
of the settling basin wall was done simultaneously with the basin cleaning. Retrofitting of
the said settling basin wall was planned in 2014 and implemented in 2015.
On the other hand, cleaning
of the impounding dam is
another main activity of the
Production and Water Quality
Control Division to improve
the intake of water which is
transported through the
transmission pipelines down to
the settling basin. Cleaning of
the dam was conducted by
the MCWD personnel once a
month, to remove fallen tree branches and
other debris. They also remove boulders and aggregates and washed sand that traps the
continuous heavy flow through the intake pipe.
Settling Basin Wall Rehabilitation
Settling Basin Wall Rehabilitation was
initiated simultaneously with the
cleaning of the settling basin. This
Basin Wall Retrofitting is expected to
be finished in 9 years. That’s why, the
district started the first and second
phase of the said project in the year
2015 and two additional phases in
every year to come.
Clearing of Boulders at Maula-og River Dam
MCWD 2015 ANNUAL REPORT
19
The estimated approved amount for the
settling basin wall rehabilitation for the two
phases is Six Hundred Sixty Thousand
Pesos (₱660,000.00).
Construction of Warehouse
The multiphase construction project of warehouse was initiated by MCWD in the year
2014. The second 2nd phase of the said project was initiated in 2015 that covers 84.5
square meters (m²) floor area prioritizing the concrete works and roofing system
installation. Concrete works includes 7 columns, beams, rafter, gutter and slab.
The approved total estimated cost for the warehouse project phase 2 in 2015 is Seven
Hundred Thousand Pesos (₱700,000.00). Almost nine percent (9%) of the total estimated
budget was exceeded to initiate the construction to a physical work progress of 100% by
the end of December 2015.
Pouring of concrete mixture for
basin wall retrofitting
First Layer (1.2m high) Retrofitted Basin Wall
MCWD 2015 ANNUAL REPORT
20
Drainage System Construction
During heavy rainfall, surface runoffs enter the sedimentation basin causing high turbidity.
As a precautionary measure for future similar events, the office had to construct a
drainage system to prevent the over flows of rain water coming from the upper part of
the settling basin
compound to enter the
sedimentation basin.
These drainage system
project is also a multi-
phase project and is
expected to its full
completion by the end
of 2017.
The first phase of the
drainage system project
covers one hundred eighteen linear meters (118 m), while the second phase of the
drainage system covers one hundred linear meters (100 m).
ACCOMPLISHMENT
Drainage system project Phase 1 and 2 was initiated in FY 2015. The estimated total
cost of the said project is One Million and Three Hundred Thousand Pesos
MCWD 2015 ANNUAL REPORT
21
(₱1,300,000.00) almost eighty-three percent (83%) of the estimated cost was spent by
the district to initiate the physical work progress of 100% by the end of December 2015.
Construction of Perimeter Fencing of Basin Compound
To maintain the security and safety of the settling basin compound, the Water District
come up to a decision to continue the multiphase perimeter fencing project of the settling
basin. In FY 2015, Phase 4 of the Perimeter fencing project commenced and covers 50
linear meters (50 m).
ACCOMPLISHMENT
Construction of the Perimeter Fence of Settling Basin Compound has a total approved
budget of Two Hundred Thousand Pesos (₱200,000.00). The total expenses incurred for
this project is One Hundred Forty-
Seven Thousand Three Hundred
Ninety Pesos (₱147,390.00). Almost
74% of this total approved budget
MCWD 2015 ANNUAL REPORT
22
Construction of the Perimeter Fence of Basin Compound Phase 4 has an approved budget
of Two Hundred Thousand Pesos (₽200,000.00) for the year 2015. Almost seventy-four
percent (74%) of the budget was incurred in order for the project to be realized to 100%
by the end of October 2015.
Retaining Wall / Pipe Encasement Project
One of the major projects of
Metro Carigara Water District
for the CY 2015 is the
encasement of the major
transmission pipelines from
dam to basin. Construction of
Retaining Wall for these
pipelines will protect from
further damages in case of
land slide due to heavy rains
and earthquakes. Last 2014,
Metro Carigara Water District signed a
Memorandum of Understanding (MOU)
together with the United States Agency
International Development (USAID) to
rehabilitate the typhoon damaged
retaining walls at our Maulaug River Dam.
The said encasement project for the
retaining wall of these transmission
pipelines funded by the USAID started its construction in January 19, 2015 and was
completed last March 18, 2015.
Basin Perimeter Fence
MCWD 2015 ANNUAL REPORT
23
IMPROVEMENT OF WATER FACILITY
Distribution Pipeline Extension – Joson De Mata St., Baybay, Carigara
In continuity to the distribution line laid along Joson
de Mata St. [from Aguja to San Roque Sts.] in 2014,
the water district replaced the 1ӯ G.I. Pipeline
[from Esperanza to San Quintin Sts.] with 3ӯ uPVC,
further extending the line [traversing Joson de
Mata St. Ext.] down to the main line in Real St. this
year.
This 258m pipe extension project is almost 91% in
progress. All pipes are already in place, however, considering the time length of water
interruptions, the interconnection
activity to the main distribution
line and transfer of service taps
will be done on the first periodic
(2016) cleaning of the
Old 1ӯ G.I. Distribution Line replaced with 3ӯ
uPVC as seen on the photos.
MCWD 2015 ANNUAL REPORT
24
sedimentation basin. The district ensures adequate and increased pressure of water will
soon be experienced by more than fifty (50) consumers close to the new line.
Distribution Pipeline Improvement – Brgy. Bislig, Carigara, Leyte
Consequent to the increasing number of water service users in Brgy. Bislig, Carigara,
Leyte, the increasing number of complaints for the insufficient supply of water opted the
district to separate the distribution line supplying water to some water service
concessionaires of Brgy. Tangnan along the barangay road going to Bislig. A 3ӯ uPVC
distribution line [390m] parallel to the existing was laid from the main distribution line
[National Highway] down to the boundary of the two barangays allowing the new to
supply water to Brgy. Bislig exclusively.
Distribution Pipeline Upgrading – Brgy. Minuhang, Barugo, Leyte
Water users of Brgy. Minuhang, Barugo, Leyte have experienced intermittent to no water
supply at all on the last few months of 2014. Aside from the fact that the barangay is
located at the tail-end,
the existing galvanized
iron of 1½” diameter
distribution pipe could
no longer adequately
supply the growing
number of
concessionaires in the
area.
To address this difficulty
in supplying sufficient
water, MCWD upgraded
MCWD 2015 ANNUAL REPORT
25
the line into a 3-inch diameter
uPVC. This is approximately half a
kilometer [500m] pipeline that will
deliver the water needs of the
barangay. The project started on
June and completed [100%] before
the end of October 2015.
Distribution Pipeline Upgrading – Brgy. Parena, Carigara, Leyte
Similar to Brgy. Bislig, another barangay
[Brgy. Parena] near Carigara poblacion is
also experiencing water shortage during
peak hours. One of the main reasons is
that some of the water users
of Brgy. Barugohay Norte are
connected to the fore line of
the distribution pipe going to
Brgy. Parena.
New parallel 3ӯ uPVC pipeline [220m] has been laid from the main distribution line [along
Real St.] down to the junction of the two adjoining barangays to separately supply water
Interconnection of pipes at the junction of
Barugohay Norte and Parena
Pipe Laying at Brgy. Minuhang,
Barugo, Leyte
MCWD 2015 ANNUAL REPORT
26
to Brgy. Parena. A total amount of ₱83,061.30 is incurred to completely accomplish [100%]
the project by the end of October 2015.
Distribution Pipeline Upgrading – Brgy. Canal-Uyawan, Carigara, Leyte
In year 2015, another one (1) kilometer length of 4ӯ uPVC distribution line was laid in
barangay road joining Brgy. Binongtoan [formerly Brgy. Canal] and Brgy. Uyawan. These
two named barangays undergo similar problems encountered by the barangays situated
at tail-ends. Since the existing 2 ½”Ø G.I. pipeline insufficiently supply water to all service
users in Brgy. Uyawan, the district tapped from the main line [National Highway] another
larger diameter distribution pipe to transport more water to the said barangays.
The upgrading line project amounted to ₱365,920.50 and completed [100%] last December
2015.
Pipe laying in Brgy. Binongtoan (Canal), Carigara, Leyte
MCWD 2015 ANNUAL REPORT
27
Distribution Pipeline Upgrading – Brgy. Balilit, Carigara, Leyte
In view of the increasing complaints of water unavailability and excessive leakages in
numerous points at Brgy. Balilit, Carigara, Leyte, MCWD implemented the upgrading of its
distribution line by replacing the existing 2ӯ with 3ӯ uPVC pipeline.
The project is still in progress [60%] because not all pipes are delivered. Some of the
fittings are subject for replacement for they do not meet the specifications required by
the district.
3ӯ uPVC laid beside the 2ӯ uPVC which it replaced)
MCWD 2015 ANNUAL REPORT
28
Team Accomplishments
FINANCE AND COMMERCIAL DIVISION
The key accomplishments for the year are as follows:
2015 2014 Increase
(Decrease)
% Increase
(Decrease)
Service
Connections
8,113 7,640 473 6.19%
Water Sales 30,982,428.38 29,872,338.64 1,110,089.74 3.72%
Collection from
Water Sales
32,407,384.53 31,830,493.79 576,890.74 1.81%
Connection Data:
NWSC Reconnected Disconnected Ave. Consumption
(cu.m.)
Ave. Billing
January 28 11 26 18.45 429.80
February 20 16 16 15.08 362.63
March 28 18 24 15.38 366.09
April 39 12 13 18.59 428.84
May 40 26 17 15.87 366.90
June 37 11 6 17.88 411.28
July 82 8 11 18.11 422.83
August 67 13 3 19.11 446.22
September 56 11 3 16.84 391.53
October 36 22 23 17.74 415.02
November 32 12 33 18.23 425.60
December 19 10 19 15.34 364.60
The district is keen in observing the following:
Service connections are 100% metered.
Water rates approved and implemented since February 2006.
Regular orientation/seminar for all water service applicants every other
Friday, Special orientation is also attended upon request of the applicant.
Individually we are one drop.
Together we are an ocean.
- Ryunosuke Satoro
MCWD 2015 ANNUAL REPORT
29
Observance of “No-Noon Break Policy.”
Special lane for senior citizen, pregnant women and person with disability.
ADMINISTRATIVE AND GENERAL SERVICES DIVISION
Staff Productivity
Metro Carigara Water District has been categorized by the Local Water Utilities
Administration (LWUA) as Category “C” in March 2012 pursuant to the guidelines provided
for in the DBM approved Revised Local Water District (LWD) Manual on Categorization,
Re-Categorization and Other Related Matters. In line with the Staffing Pattern of this
MaCRO, the district, being under the Medium Category observes the Staff Productivity
Index with One Hundred Twenty (120) water service connections for every one (1) position
title or a ratio of 120:1.
Below is the data on staff productivity index as of December 31, 2015:
Total Number of Active WSC Total Number of Personnel
6,828 45
As shown above, the MCWD is still capable of employing eleven (11) more regular or
casual positions.
HR Capacity Building
One of the major accomplishments of the AGS Division is a two-day seminar on: (1)
Gender Sensitivity and Development
and (2) Gender and Sensitivity and
Responsive Planning and Budgeting
given to all MCWD employees. The
division manager facilitated the
negotiation with the CSC regional
officers for the conduct of said
seminar.
MCWD 2015 ANNUAL REPORT
30
Furthermore, the AGS recommended a total of seventy-five (75) employees to attend
training/workshop as follows:
1st Congress on Fortifying Graft and Corruption
January 8, 2015
Caballes, Regidor V.
Rocha, Ma. Cynthia B.
Ong, Cherry Lyn F.
Orientation on Sexual Harassment Law
February 13,2015
All Employees
Seminar on Strategic Human Resource Management
March 3, 2015
Ong, Cherry Lyn F.
Water Philippine 2015 Expo
March 25-27, 2015
Caballes, Regidor V.
Seminar on Gender Sensitivity and Development (GAD)
March 26, 2015
Arintok, Anna Marie
Cano, Virginia
Martus, Orlando Jr.
Ong, Cherry Lyn
Rocha, Ma. Cynthia
MCWD 2015 ANNUAL REPORT
31
Re-Orientation Seminar on GSIS Rules
April 23, 2015
Rocha, Ma. Cynthia
Piangco, Jennifer
Orientation on Disaster Risk Reduction Management Plan
May 8, 2016
All employees
Public Sector HR Symposium & PSTD National Convention "Transformation Through
Leadership Development
May 27-29, 2015
Caballes, Regidor V.
Ong, Cherry Lyn
Rocha, Ma. Cynthia
Basic Orientation on Climate Change
July 6-8, 2015
Caballes, Regidor V.
Jacobe, Yvonne Jane
5th CSC Visayas HRMP Congress on Talent & Character Champions
August 12-13, 2015
Caballes, Regidor V.
Ong, Cherry Lyn
Rocha, Ma. Cynthia
Prime Human Resource Assessment
August 19, 2015
MCWD 2015 ANNUAL REPORT
32
Rocha, Ma. Cynthia
Gender and Development Plan Orientation
September 18, 2015
Rocha, Ma. Cynthia
Ong, Cherry Lyn
23rd PWWA Internal Conference & Exhibition
October 21-24, 2015
Caballes, Regidor V.
WASH (Water Sanitation & Hygiene) Training
October 7 & 14, 2015
Caballes, Regidor V.
Jacobe, Yvonne Jane
3rd Quarterly EVAWD Meeting & Continuation on GAD Focal Persons
October 15, 2015
Rocha, Ma. Cynthia
Ong, Cherry Lyn
Gender Sensitivity Seminar for the Human Resource Practitioners
and GAD Focal Person
October 29-30, 2015
Rocha, Ma. Cynthia
Ong, Cherry Lyn
Jacobe, Yvonne Jane
Machete, Shirlee Alicor
MCWD 2015 ANNUAL REPORT
33
Updates on Bureau of Internal Revenue (BIR) Rules and Regulations
October 26, 2015
Balindo, Daryl T.
Corporate Planning (Part I)
November 5-6, 2015
Regidor V. Caballes
Francisco Y. Parena
Rogelio A. Alvarado
Virginia A. Cano
Ma. Cynthia B. Rocha
Cherry Lyn F. Ong
Shirlee Alicor L. Machete
Anthony A. Alcober
Anna Marie O. Arintok
Dahlia E. Javines
Jane Yvonne J. Jacobe
Orlando S. Martus
Nicanor D. Obo
Lea P. Quebec
Dolores T. Bodo
Jennifer A. Piangco
Rose Ann O. Llames
Ahlera M. Samutya
Julian Eduardo S. Gunabe
Eleazar S. Ducalang
Continuation of Corporate Planning (Part II)
December 7-9, 2016
Regidor V. Caballes
Francisco Y. Parena
MCWD 2015 ANNUAL REPORT
34
Rogelio A. Alvarado
Virginia A. Cano
Ma. Cynthia B. Rocha
Cherry Lyn F. Ong
Shirlee Alicor L. Machete
Anthony A. Alcober
Anna Marie O. Arintok
Dahlia E. Javines
Jane Yvonne J. Jacobe
Orlando S. Martus
Nicanor D. Obo
Lea P. Quebec
Dolores T. Bodo
Jennifer A. Piangco
Rose Ann O. Llames
Ahlera M. Samutya
Julian Eduardo S. Gunabe
Eleazar S. Ducalang
MCWD 2015 ANNUAL REPORT
35
Orientation on Sexual Harassment Law
MCWD 2015 ANNUAL REPORT
36
HR Health and Wellness Program
In 2015, the AGS Division initiated the conduct of the orientation on (1) Causes and
Symptoms of Hypertension on September 9-10 and (2) Causes and Symptoms of Diabetes
on October 15-16 for all employees which are directly related to health and wellness
program. The employees also undergo an anti-tetanus and diphtheria vaccination last
November 18, 2015 and giving out of Vitamin D capsules for intake last November 20,
2015. In addition to, a “zumba” dance exercise is being done every Friday to allow the
employees of any fitness level enjoy a fantastic workout and support their fitness goals
even at work.
MCWD 2015 ANNUAL REPORT
37
Property Management
The property section updated the recording of the stocks at the stock cards, prepares
weekly report on materials and supplies issued and monthly stock status report and
ensured that all equipment and other items issued to all employees were supported with
sixty-eight (68) property acknowledgment receipts and properties were assigned with
property cards.
General Services
The AGS also continue to commit to an improved cleanliness and orderliness of the office
and parking area. Additionally, security services of the MCWD office and other properties
are guaranteed 24/7.
UNDERTAKING CORPORATE SOCIAL RESPONSIBILITIES
The MCWD with its
continuing commitment to
contribute to community
and society at large
participated in activities
involving the public and
other organizations and
government offices. It
spearheaded one of the
major events during the
town fiesta celebration
which was the “Kalsada ni
Gara” Street Decoration
and Festivity Contest with
entries from different
barangays in Carigara.
MCWD 2015 ANNUAL REPORT
38
Aside from the town fiesta activities, the district also took part in the anniversary
celebration of Carigara on January 25, 2015 by participating in the civic parade. Similarly,
the MCWD responded to the invitation from the local government unit, it actively joined
the celebration of Carigara’s 419th Town Fiesta in honor of the Holy Cross on July 16,
2015. Among the activities participated in were: Grand Fiesta Parade, LGU and NGA Night
and Search for King and Queen 2015.
The district, in its utmost concern to the consuming public especially on occasions when
water is of great demand provided a free drinking water stationed in different cemeteries
within its coverage areas of Carigara, Barugo and Tunga during the All Soul’s Day. The
Capoocan cemetery is somehow located at a far flung area such that it has no direct
access to the district’s distribution system.
MCWD 2015 ANNUAL REPORT
39
Environmental protection is also one of the main pillars of MCWD’s corporate philosophy
especially with water, being its main product has assumed principal responsibility to
protect the environment and conserve natural resources. Among its activities were the
tree planting and awareness drive to
the students from different schools
within the four service coverage
areas. Through these efforts the
district can truly share the precious
gift of nature it can save to the next
generations.
Tree Planting held during the WWD 2015, together with guests
from Medicos del Mundo, Bigonia Ruiz & Marco Velasco, and
students from secondary schools within Metro Carigara.
WWD Motorcade and Visit at LGUs of Carigara,
Barugo, Capoocan and Tunga.
MCWD 2015 ANNUAL REPORT
40
COMPANY INFORMATION
METRO CARIGARA WATER DISTRICT
Old Municipal Hall, Carigara, Leyte
Tel +639176741610
The Board of Directors
BALTAZAR C. ESQUIBEL, Chairman
ROQUE U. AGUILAR, JR., Vice-Chairman
LUCILA A. BENUSA, Member
CHARITA E. MACAPUS, Member
DAMIANA C. MAKABENTA, Member
The Key Officers
ENGR. REGIDOR V. CABALLES, General Manager
FRANCISCO Y. PARENA, OIC – Engineering & Construction Division
ENGR. NICANOR D. OBO, Supervisor – Production & Water Quality Division
VIRGINIA A. CANO, Division Manager – Finance & Commercial Division
MA. CYNTHIA B. ROCHA, Division Manager – Administrative & General Services Division