structural steel shop drawing review, the past and the future
TRANSCRIPT
-
7/29/2019 Structural Steel Shop Drawing Review, The Past and the Future
1/8
Structural Steel Shop Drawing Review:The Present the FutureStructural Steel
Shop Drawing Review:
The Present the FutureBy Michael Gustafson, P.E.
August 2008
-
7/29/2019 Structural Steel Shop Drawing Review, The Past and the Future
2/82 PDH Professional Development Advertising Section TEKLA Inc.
The structural steel detailing industry has contin-
ued to expand its use of 3D modeling technology
in recent years; currently more than 50 percentof the structural steel detailing market in the
United States is using some form of 3D modeling soft-
ware (American Institute of Steel Construction, 2007). This
change has brought great efficiencies to the steel detailers
own productivity, in addition to improving upstream and
downstream processes. Structural engineers, on the other
hand, have not seen the same improvements in their own
productivity in reviewing and approving structural steel
shop drawings. In fact, some engineering firms may argue
that the average number of shop drawings to review per
project has increased over the years.
More recently, however, engineering firms are finding
new ways to increase their productivity in reviewing and
approving shop drawings using a range of emerging tech-
nologies. The transfer of shop drawing submittals electroni-
cally was the first step in using digital technology, but now
enhanced visualization methods of reviewing and approving
shop drawings are now being implemented.
Project requirements of the EORin shop drawing review
The American Institute of Steel Construction (AISC) Code
of Standard Practice (COSP) outlines what is required of
the steel fabricator and of the engineer-of-record (EOR) in
submission and approval of shop drawings. Minimal infor-mation is provided regarding the content to be reviewed by
the EOR since this is typically outlined at the project level by
the EOR and defined in the project specifications.
The COSP states that the steel fabricator expects a
14-calendar-day turn around from the day it releases draw-
ings to the day the fabricator receives the approved shop
drawings back from the EOR. If modified in the contract
documents, the actual turn around time is governed by the
EORs project specifications. With the nature of todays accel-
erated project delivery schedules, a two-week turn around
time of shop drawings is not the norm, thereby putting
more stress on the review team to be more productive andturn around approved submittals in less time.
A signed set of calculation sheets from a professional
engineer for all connection designs not covered by the
design drawing contract documents is often stated in the
project specifications when the work of connection design is
delegated. Engineering firms require this because the COSP
states that the EOR shall review and approve structural
connections and details designed by others (see COSP
Section 4.4.1). The submittal of connection calculations and
verification of the calculations does impact the efficiency of
the shop drawing review process.
Standards for shop drawing reviewThe EOR has an obligation to verify that the structural
design intent is being properly communicated by the steelfabricator on its shop and field drawings. The steps and
Continuing EducationThe Professional Development Series is a unique
opportunity to earn continuing education credit
by reading specially focused, sponsored articles in
Structural Engineer. If you read the following arti-
cle, display your understanding of the stated learning
objectives, and follow the simple instructions, you can
fulfill a portion of your continuing education require-
ments at no cost to you. This article also is available
online at www.gostructural.com/pg.asp?id=20.
InstructionsFirst, review the learning objectives below, then
read the Professional Development Series article. Next,
complete the quiz and submit your answers to the
Professional Development Series sponsor. Submittal
instructions are provided on the Reporting Form
on page 6. Your quiz answers will be graded by the
Professional Development Series sponsor. If you answer
at least 80 percent of the questions correctly, you will
receive a certificate of completion from the ProfessionalDevelopment Series sponsor within 90 days and will be
awarded 1.0 professional development hour (equiva-
lent to 0.1 continuing education unit in most states).
Note: It is the responsibility of the licensee to determine
if this method of continuing education meets his or her
governing board(s) of registrations requirements.
Learning ObjectivesThe learning objectives of this paper are the following:
Understand current contractual and industry-
expected responsibilities of the engineer-of-record in
the shop drawing review process. Identify inefficiencies or redundancies in the current
review processes.
Learn how 3D visualization tools can be used to coor-
dinate, review, and approve shop drawing submittals
while still delivering a 2D submittal of shop drawings.
Comprehend industry trends moving toward a 3D
model-based shop drawing review process.
Professional Development Series SponsorTEKLA Inc.
Structural Steel Shop Drawing Review:The Present the Future By Michael Gustafson, P.E.
-
7/29/2019 Structural Steel Shop Drawing Review, The Past and the Future
3/8Professional Development Advertising Section TEKLA Inc. PDH 3
Structural Steel Shop Drawing Review:The Present the Future
procedures of how this is conducted are determined by the
EOR or, more commonly, by a company standard. Typically,
structural engineers follow a checklist for reviewing and
approving the erection and assembly shop drawings.
Each engineering firm has its own standard for how much
detail needs to go into checking shop drawings. Typically,the structural assemblies comprised of primary framing
and connection parts are reviewed for compliance at
three levels: within the context of other building systems,
within the context of other structural assemblies and struc-
tural systems; and within their own structural assembly.
Furthermore, for each level of investigation, several design
parameters are typically reviewed, such as geometry, section
properties, and material properties.
Checking each of these parameters can be a tedious
process. In addition, the task of reviewing each checklist
item on the shop drawings and comparing that informa-
tion with the design drawings accumulates a fair amount of
inefficiency. The steel fabricators 3D model (also referred to
as the construction model) can help the EOR in many ways
better visualize and review the shop drawings, as well as
speed up the EORs time reviewing the shop drawings.
Workflows using the 3D construction modelFor more than 55 percent of the projects built in the
United States that detail structural steel (AISC, 2007), the
EOR may obtain access to the 3D construction model for
review of shop drawing submittals. Such a tool can be help-
ful in improving the EORs understanding of the proposed
fabricated product by the steel fabricator. Several work-
flows can be utilized to leverage different levels of the 3Dconstruction model in the review process. These workflows
range from using the 3D model as an enhanced visualiza-
tion tool which still requires 2D shop drawings as the
final, commented, and approved submittal to the fabricator
to the approval of the 3D construction model in lieu of
2D drawings.
In this paper, we refer to three workflows that use differ-
ent tools to review and approve the shop drawings: 2D
Review, 2D-3D Review, and 3D Review. Note that the first
workflow, 2D Review, basically represents the traditional
shop drawing approval process in which the structural engi-
neers paper design drawings are used along with the fabri-cators submitted paper shop drawing set. This workflows
use of the 3D model is limited to including colored markers
to make comments. The inefficiencies that exist in this typi-
cal workflow can be improved upon using either the 2D-3D
Review or the 3D Review approach, which are discussed
next.
2D-3D Review workflowThe 2D-3D Review workflow follows the traditional work-
flow of the EOR approving 2D paper drawings, but the
process incorporates the 3D model. To clarify again, this
workflow assumes that the 2D shop draw-
ings are still the final document containing the
approval comments by the EOR. In other words,
use of the 3D model makes the review process more
efficient and visual but does not replace the deliverable of
2D paper approval drawings. Key steps in the 2D-3D Reviewworkflow are discussed below.
Step 1. Coordination of building systems As a
first step, the EOR may wish to check for constructability
issues between the structural systems (such as structural
steel, cast-in-place concrete, precast, etc.) that have surfaced
during the shop drawing stage that ultimately could affect
the final design. In this context, constructability is not being
defined by means and methods (which is typically not part
of the EORs scope of work), but rather referring to the
quality of the final, in-place structure. Therefore, using the
3D construction model to aid in the review process can be
appropriate.
To coordinate interfaces of the structural steel frame with
other structural elements such as concrete foundations and
walls or roof joists, structural engineers can import their 2D
design drawings or 3D structural models, including building
information models (BIMs), into the construction model.
The overlaying reference can be used to verify the steel
structure geometry as well as clearances and tolerances (see
Figure 1).
The geometry of the model elements can be reviewed in
reports that can be created within the construction model,
or from the model elements themselves.
An obvious benefit of referencing the 2D design draw-
ings within the context of the construction model is that thecontents of both are superimposed together in one spot.
This eliminates the EORs need to go back and forth between
design plans and the fabricators erection drawings.
To coordinate the structural steel frame with non-struc-
tural elements such as exterior wall locations, floor open-
Figure 1: An example of 2D-3D Review workflow includes coordi-
nation of the 3D structural model, 2D design drawings, and the
3D steel construction model.
-
7/29/2019 Structural Steel Shop Drawing Review, The Past and the Future
4/84 PDH Professional Development Advertising Section TEKLA Inc.
Structural Steel Shop Drawing Review:The Present the Future
ings, and grade elevations, the reviewer can
overlay other 2D drawings or 3D reference
models into the steel construction model.
Step 2. Review and approval of assemblies
As described above, enhanced visualization tools exist to
help the EOR better understand how their design intent isbeing interpreted by the builders. With this in mind, there
are opportunities to improve the actual approval process
itself for the EOR, specifically with finding, commenting on,
and approving each assembly. Some structural engineering
firms have tried reviewing and approving 2D drawings in
electronic form using 2D redlining tools and have found
limited benefits. The 2D-3D Review workflow is different
because it can reduce inefficiencies of searching and coordi-
nating information between the design and shop drawings.
For example, the EOR can spend a fair amount of time
sifting through a stack of shop drawings trying to find the
assembly sheet that they wish to review. In contrast, the
3D model can be queried for a specific assembly in the
model, and then open the corresponding 2D electronic
shop drawing to view the assembly as needed. Secondly,
review of the standard materials and parts on a project is
currently achieved by checking for those standards on each
shop drawing, even though they are repeated across similar
assemblies. However, a fabricators construction model typi-
cally allows the user to view lists of such standard informa-
tion in reports, allowing the EOR to quickly review larger
quantities of data and then to compare and contrast that
data with other assemblies. For example, a report that lists
each part in the model with its corresponding material
grade. Therefore, all the material grades of structural fram-ing members can be verified as A992 in the list, while struc-
tural plate and miscellaneous steel can be verified as A36 or
A572/50 as specified for the project.
Step 3. Comment on assembly The 2D-3D work-
flow allows the user to review and make comments within
the 3D model environment that correspond to the 2D
electronic shop drawings (see Figure 2). The approval status
of each element or assembly in the model can be shown
in different colors and is also reflected on the 2D electronic
drawing as a custom stamp. This linking of the 3D model
to the 2D shop drawings in PDF format allows the EOR
to review the 3D model, the 2D shop drawings, or both;and simultaneously maintains the approval status linked
between them. With the final approved 2D shop drawings
in PDF format, the documents can be saved with restricted
privileges or simply plotted out as a record set and submit-
ted back to the fabricator as required.
Step 4. Connection design review It is recom-
mended that the fabricator and engineer agree on a pre-
approval process where the EOR pre-approves the design
calculations and associated connection parameters prior
to reviewing the shop drawings. This is already a common
practice with the current 2D Review workflow. Each type
of connection can be assigned an agreed upon connec-
tion grouping so that the connections can be easily identi-
fied in the model during the verification process and cross
referenced with the design calculations. During connection
design approval process, the EOR can also utilize the fabri-
cators model to verify the connection design within the
context of the primary structure, as well as better visualize
the load paths and constructability of the design.
During review of the shop drawings or model, the EOR
can then verify that the specified design code is valid at each
connection location, or even viewed in conjunction with theprovided submitted calculation sheets by the connection
engineer.
3D model-based shop drawing reviewThe use of integrated project delivery (IPD) methods,
in conjunction with the use of BIM, is bringing forth new
business models and workflows in reviewing and approving
structural steel shop drawings. Today, numerous projects
have been built where the review process was compressed
due to the use of a digital review of the 3D construction
model by the EOR (McGraw-Hill, 2007). These 3D model-
based review processes have been documented and arenow migrating into the mainstream work processes for
structural engineering firms, especially those leveraging BIM
technology.
Note that several entities in the building and construc-
tion industry have taken note of the benefits of model-
based review workflows used to date and are documenting
how the industry could adopt such processes. For example,
the owners group, Construction Users Roundtable (CURT),
produced a white paper in 2006 that recognized the inef-
ficiency in current business models that do not compensate
design firms for using digital design information exchanges
Figure 2: An example of an approved assembly shown in both the
3D model and on the 2D electronic drawings in PDF format.
-
7/29/2019 Structural Steel Shop Drawing Review, The Past and the Future
5/8Professional Development Advertising Section TEKLA Inc. PDH 5
Structural Steel Shop Drawing Review:The Present the Future
to expedite the shop drawing and fabrication processes.
Also, the American General Contractors Associations Guide
to BIM (2006) states, Shop drawings could be developed
simultaneously as the design unfoldseliminating the need
for approvals and submittal turn arounds, as that process
will already have been accomplished during the designperiod. Such statements imply the use of an IPD process.
Furthermore, the structural steel industrys AISC has modi-
fied its COSP by adding Appendix A to accommodate the
use of digital design and/or fabrication models to be used
instead of design and/or shop drawings given the project
requirements (see COSP, Appendix A, 16.3-65).
Using a 3D Review approach, the EOR coordinates and
reviews the model using procedures similar to that of the
2D-3D Review approach; however, howthe EOR approves
and communicates their approval is different than using 2D
drawing submittals. Instead of using paper drawings, the
EOR provides the steel fabricator, depending upon the tech-
nology being used, the submittal comments and approval
status in electronic form as a file exported from the model.
This file is then submitted to the steel fabricators detailer who
imports and views the EORs approval status and comments
into his or her own construction model. Note that the EOR
does not have to submit an actual model, but only submits
comments to the fabricators detailer. That way there is
no concern with the EOR changing the fabricators model
during the review process. What can be used as a record-set
of the approved submittal is the approval file of each assem-
bly reviewed, as well as the construction model archived in
a neutral file format (such as CIS2, XML, etc.) that maintains
all the construction information per submittal, and whichcan be retrieved easily and with accuracy at a later date.
The benefits of the 3D Review approach are that it does
not require 2D shop drawings to be produced. The EOR
can still recognize the same benefits outlined in the 2D-3D
Review process above, with the exception of needing to
stamp 2D electronic drawings as the submitted deliverable,
which is eliminated in this process.
A new approach to shop drawing reviewIf you are interested in incorporating either the 2D-3D
Review or 3D Review workflows on your next structural
steel project, the first step is communicating early in theproject with the project team, including the steel specialty
contractor. One way of facilitating this dialog is by host-
ing a pre-coordination meeting held between the owners
representative, steel contractor (detailer and/or fabricator),
structural engineer, and general contractor involved in the
shop drawing submittal process to determine what type of
model-based review process can be realistically achieved.
Depending upon which workflow is utilized, the project
team members may have to adjust certain aspects of their
workflow to accommodate a different process. Suggested
items to discuss include the following:
Deliverable of submittals The type
of documentation required for submittal
process whether paper, 2D electronic, or
3D model-based must be established first since it
can affect other aspects of the review workflow.
Defining project roles and responsibilities Thetype of information that the EOR wishes to review should
be defined up front so that rights and privileges can be set
up properly in the technologies being utilized. This may
relate to both modeling software as well as PDF redlining
software.
Pre-work by steel fabricator Any set up by the steel
fabricators detailer, such as plotting shop drawings in PDF
format, shall be coordinated up front. Also, the scope of
content included in the 3D model to be approved shall be
agreed upon.
Pre-approved connections Having the EOR pre-
approve as many connection designs and connection
groups as possible will make checking the model much
easier. Establishing how the pre-approval process will work
and what the EORs expectations are for design calcula-
tions can be discussed.
Stamping and approvals The fabricators detailer
can be asked to set up the electronic stamp template
for the EOR so that when the shop drawings are sent to
the engineer, stamping the drawing does not require the
EORs stamp and signature. Electronic stamps could also
be set up in advance so that during the redlining process,
the approval can be performed on the 2D electronic draw-
ings within the file format agreed upon, such as a PDF, and
saved.Review of approved shop drawings by the steel
fabricator Depending on the workflow used, the
fabricators detailer may wish to receive the approval status
information in a specific file format, not just in PDF format,
to improve his or her management of received submittals.
Managing resubmittals Resubmittals or successive
submittals must be clearly marked as to what information
is to be reviewed or re-reviewed by the EOR. Traditional
methods use clouding of drawings to communicate such
changes. However, a 3D model with status information
could be used so that the project team can better visualize
what his or her responsibility is to review.
ConclusionBuilding and construction industry experts anticipate
significant changes to their industry because of the conver-
gence of three industry trends: BIM, IPD methods (such as
design-build), and sustainability (Cross, 2008). The impact
of the convergence could offer big benefits toward project
productivity and also for how projects are managed and
delivered. The 3D model-based review workflows discussed
above find synergies with these three trends.
First, BIM can help engineers better visualize not only their
-
7/29/2019 Structural Steel Shop Drawing Review, The Past and the Future
6/86 PDH Professional Development Advertising Section TEKLA Inc.
Structural Steel Shop Drawing Review:The Present the Future
design intent, but the construction teams
interpretation of the design intent during the
shop drawing review stage.
Secondly, project delivery methods that capitalize
on the expertise of structural steel specialty contractors, as
well as that of the structural engineer, will further enable
the use of 3D model-based review workflows during the
shop drawing review stage. For example, a recent domes-
tic project demonstrated a reduction of 25 percent in the
overall project schedule when implementing a 3D model-based review of the structural steel shop drawing submit-
tals using an integrated project delivery process (Ghafari &
Associates 2007).
Third, the growing trend of sustainable design is giving
structural engineers an opportunity to better promote their
capabilities in producing sustainable designs for clients.
Using less paper during the structural steel shop drawing
review process could in effect help create a more sustain-
able project delivery method. Rough estimates show that
more than 65 million sheets of paper shop drawings were
used to procure the structural steel shop drawing review
process for projects in the United States in 2007 (Survey
of 100,000 tons of projects delivered in the United States
in 2007).
With such benefits being recognized, the structural
engineering industry will move ahead with more effective
Professional Development Series Sponsor:114 Town Park Dr., Suite 500, Kennesaw, GA 30144
Phone: 770-426-5105 Fax: 770-919-0574 Email: [email protected]
Web: www.tekla.com
Structural EngineerProfessional Development Series Reporting Form
Article Title: Structural Steel Shop Drawing Review: The Present the FuturePublication Date:August 2008
Sponsor: TEKLA Inc. Valid for credit until: August 2010
Instructions: Select one answer for each quiz question and clearly circle the appropriate letter. Provide all of the requested contact infor-mation. Fax this Reporting Form to 770-919-0574. (You do not need to send the Quiz; only this Reporting Form is necessary to be
submitted.)
1) a b c d 6) a b c d
2) a b c d 7) a b c d
3) a b c d 8) a b c d
4) a b c d 9) a b c d
5) a b c d 10) a b c d
Required contact informationLast Name: First Name: Middle Initial:
Title: Firm Name:
Address:
City: State: Zip:
Telephone: Fax: E-mail:
Certification of ethical completion: I certify that I read the article, understood the learning objectives, and completed the quizquestions to the best of my ability. Additionally, the contact information provided above is true and accurate.
Signature: Date:
References American Council of Engineering Companies, 2007,
Design & Construction Industry Trends Survey
American Institute of Steel Construction, Feb. 2007,
2007 Structural Steel Detailer Listing,
Modern Steel Construction
Construction Users Roundtable, 2006,
White Paper 1202, p.7
Cross, John, April 2008, Hat Trick,
Design-Build Dateline, Vol. 15/No. 4
Ghafari & Associates, 2007, Breakthrough Results
on General Motors Project Series
McGraw-Hill, 2007, Interoperability in the Construc-
tion Industry, Smart Market Report, p. 24-25
-
7/29/2019 Structural Steel Shop Drawing Review, The Past and the Future
7/8Professional Development Advertising Section TEKLA Inc. PDH 7
collaboration methods with the construction team, while
the structural engineer can use a more productive, accu-
rate, and even more enjoyable process in approving struc-
tural steel shop drawings.
Professional Development Series Quiz
1. Per AISC COSP Section 4.4.1, a signed set of calculation
sheets from a Professional Engineer is required by the
project specifications when what scope of the struc-
tural steel design is delegated:
a) Foundation elements
b) Mechanical ductwork
c) All connection designs not covered by the Design Drawing
contract documents
d) Architectural concrete-masonry
2. The COSP states a turn-around time the steel fabricator
expects from when it releases to when the fabricator
receives the approved shop drawings from the EOR.
What is that time frame?
a) 7 calendar days
b) 14 calendar days
c) 21 calendar days
d) none of the above
3. The EOR will typically check the following design
parameters on a shop drawing EXCEPT:
a) Temporary shoring requirements of the steel erectorb) Geometry of assembly
c) Section properties of assembly
d) Material properties of assembly
4. The estimated percentage of structural steel projects in
the United States that use 3D modeling for structural
steel detailing is:
a) More than 90 percent
b) More than 50 percent
c) Less than 40 percent
d) Less than 30 percent
5. When using the 2D-3D Review workflow, what are the
benefits of referencing structural design drawings
and other 3D design models into the structural steel
construction model?
a) To coordinate the structural steel frame with other structural
elements
b) By reviewing the architectural model, the EOR relieves the
architect of all responsibility in coordinating the accuracy of
their design
c) To view assembly information and design drawing informa-
tion at the same time during the approval process
d) a and c
6. When using the 2D-3D Review workflow, how can the
EOR utilize a 3D construction model during the review
and approval of assemblies?
a) Search for assemblies in the model
b) View reports of standard material lists of the assemblies
c) Comment and stamp 2D PDF shop drawings through the
3D model
d) All of the above
7. Which topics are suggested to be discussed during a
shop drawing review pre-coordination meeting with
the project team?
a) Deliverable type of submittals
b) Pre-approved connections
c) Managing resubmittals
d) All of the above
8. Which structural steel industry document states that
the use of digital design and/or fabrication models can
be used instead of design and/or structural steel shop
drawings?
a) AISC Code of Standard Practice Appendix A
b) CURT AGC AIA 3XPT document
c) BIM Addendum to the Consensus Docs
d) PCI Handbook
9. A 3D Review method differs from a 2D-3D Review
process in what following way(s)?
a) It uses paper drawings as the deliverable of submittals
b) It uses electronic 2D drawings as the deliverable of submittals
c) It uses a digital 3D construction model, in conjunction with
EOR approval comments to the model, as a deliverable of
submittals
d) Both a and b
10. What is the estimated number of drawing sheets
used to create structural steel shop drawings for all
U.S. projects in 2007?
a) 2.5 million
b) 10 million
c) 65 million
d) 500 million
Michael Gustafson, P.E., is the engineering
product manager for North America at Tekla Inc.
He can be reached at [email protected].
-
7/29/2019 Structural Steel Shop Drawing Review, The Past and the Future
8/8
Tekla Welcomes you to
Atlanta
Tekla welcomes you to Atlanta for the 2008 Structural Engineers Building Conference. We also welcome you to earn yourprofessional development hours with our free course designed to maintain, improve and expand your skills and knowledgeof the structural steel shop drawing review process. To learn more about how you can earn professional developmenthours through Tekla visit www.tekla.com/pdh
Tekla Structures is Building Information Modeling (BIM) software that streamlines the delivery process of design, detailing,fabrication, and construction organizations. The software easily integrates with other systems such as architectural, MEPprocess layouts as well as analysis and design solutions. Use the same model to save time and ensure quality projects. Notonly have Tekla Structures Users delivered BIM-based projects in Atlanta, but also thousands of users have successfullydelivered BIM-based projects in more than 80 countries around the world.
Proud Sponsor of the 2008 Structural EngineersBuilding Conference and Expo,October 2-3, Hyatt Regency Atlanta, GA
Gwinnett Arena
Georgia
AquariumCobb Energy
Centre
The above structures fabricated
by SteelFab, Inc. and detailed
by Hutchins & Associates, Inc.
Gwinnett picture courtesy of Rosser International, Inc.
www.tekla.com/pdh1.877.TEKLA.OK
Enter #154 at gostructural.com/infodirect