study on economic partnership projects in developing ... · study on economic partnership projects...
TRANSCRIPT
Study on Economic Partnership Projects
in Developing Countries in FY2010
Study on the Second My Thuan Bridge Construction Project
SUMMARY
March 2011
第1章 第2章 The Ministry of Economy, Trade and Industry
Prepared by:
Ernst & Young ShinNihon LLC Japan External Trade Organization (JETRO) NIPPON KOEI CO., LTD. IHI Infrastructure Systems Co.,Ltd.
1. Background and Necessity of the Project
The Ministry of Transport of the Socialist Republic of Vietnam (MOT) established the
Master Plan for Expressway Development in November 2007. The plan includes a total
expressway length of approximately 6,000 km as stated in letter No. 7056/TTg-BGTVT, approved
by the Prime Minister in December 2008 through Decision No.1734/QD-TTg. The Trung
Luong–Can Tho Expressway including the Second My Thuan Bridge is a part of the North-South
Expressway. Also included is a main arterial road connecting between Ho Chi Minh City (HCMC)
and the area of the Mekong Delta, which is planned to be completed till the year of 2020.
In February 2008, Bank for Investment and Development of Vietnam (BIDV) obtained
the right to development of the Trung Luong-Can Tho Expressway which had been planned as a
Build-Operate-Transfer scheme (BOT) project with BIDV Expressway Development Company
(BEDC) as the owner by MOT’s Decision No. 343/QD-BGTVT. Although the construction of the
Trung Luong–My Thuan Expressway has been conducted, the development of the remaining
section including the Second My Thuan Bridge and the My Thuan-Can Tho Expressway has been
transferred to PMU My Thuan due to lack of investment fund, through MOT’s Decision No.
1318/QD-BTTVT dated 18th of May 2009, following the Government of Vietnam (GOV) Notice
No. 137/TB-VPCP of 24th of April 2009.
Due to lack of investment funds, MOT planned to postpone the construction of the
Second My Thuan Bridge and temporarily utilize the National Highway No. 1 (NH1) including
the existing My Thuan Bridge and National Highway No. 80 (NH 80). Figure S-1 shows the
detailed plan for the North-South Expressway made 6803/TTr-BGTVT on the 30th of September
2009, approved by the Prime Minster through Decision 140/QD-TTg on 21th January 2010.
However, it is concerned that the section of the four-lane My Thuan Bridge and two-lane NH80
will experience traffic bottleneck and the level of service of the expressway will be downgraded
due to traffic congestion, which will also induce air pollution.
The traffic volume between HCMC and Can Tho has been increased in the wake of
opening of HCMC-Trung Luong Expressway in February 2010. Further increase in traffic volume
is expected upon the opening of the Trung Luong–Can Tho Expressway. Therefore, MOT places
high priority on the Second My Thuan Bridge Construction Project (the Project) in order to
reinforce the traffic capacity for crossing Tieng River and hopes for prompt project
materialization by Japanese ODA.
Under such circumstance, the Ministry of Economy, Trade and Industry of Japan (METI)
decided to carry out a study on the Project under the scheme of “Study on Economic Partnership
Projects in Developing Countries in FY2010”.
NH No.1
Trung Luong - My Thuan Expressway
My Thuan - Can Tho Expressway
My Thuan Bridge
Tien Giang River
NH No.30
NH No.80
HCMC
Can Tho
NH No.1
Temporary Usage
of NH No.1
2nd My Thuan Bridge and
Approach Road
Source: Study Team
Figure S-1 Location of the Second My Thuan Bridge and Temporary Plan to Utilize NH1
2. Policies for Determination of Contents of the Project
The contents of the project are number of lanes, geometric structure, route, span length,
bridge type, connection to the adjacent expressways and highways, which are to be defined based
on Vietnamese standards as described below. During this process, the opinions of the
implementing agency, PMU My Thuan, are to be confirmed.
(1) Number of Lanes
The necessary number of lanes is to be decided in accordance with the traffic demand
forecast, basically 20 years later from the inauguration of the Project, and based on the
Vietnamese standard TCVN 4054-2005. The consistency with the adjacent Trung Luon-My Thuan
and My Thuan-Can Tho expressways is also to be confirmed.
(2) Geometric Structure of Road
The geometric structure of the road is to be decided in accordance with Vietnamese
standard TCVN 5729-97. The consistency with the adjacent Trung Luon-My Thuan and My
Thuan-Can Tho expressways is to be confirmed.
(3) Route Selection
The route is to be selected in accordance with the comparison study considering
following items:
a) Geometric alignment
b) River width
c) Control points to be avoided, such as transmission line towers and important cultural
assets
d) Numbers of affected households
e) Distance from power lines
(4) Span Length
The span length is determined considering the following aspects:
a) River width
b) Depth of river bed
c) Scouring of river bed
(5) Bridge Type Selection
The bridge type is selected considering the following aspects:
a) Applicability to required span Length
b) Construction cost
c) Workability in construction method
d) Aesthetic preference
e) Facility in maintenance
(6) Connections to Adjacent Expressways and Highways
The connections to adjacent expressways and highways are defined considering the
following items:
a) Progress of construction of the adjacent expressways, and
b) Results of traffic demand forecast.
3. Outline of the Project
(1) Route and Bridge Site
The Project starts at the beginning of the approach road to existing My Thuan Bridge,
where the planned Trung Luong-Can Tho Expressway will be connected. On the right bank of the
river, or the southern side, there are no specific objects to be avoided and thus, the routes are
selected to minimize the total cost.
In planning the bridge routes, existing parallel power lines and houses clustered around
the old ferry terminal must be avoided.
The route alternative selected by TEDI’s FS on Second My Thuan Bridge, Alternative 1,
passes through the old ferry terminal area and many houses (309 houses) need to be relocated.
Alternative 2, which can be obtained by shifting Alternative 1 slightly to the power line side, does
not pass through the old ferry terminal area hence, the number of affected houses can be reduced
to 159. Alternative 3, which is at the east side beyond the two parallel power lines, has the shortest
span over the river, or about 500 m, passing over 180 houses. Advantages and disadvantages of
these three alternatives are compared.
It becomes clear that in Alternative 3, the northern approach road from the starting point
needs to pass through the power line towers. Therefore, a curved section must be introduced to the
approach road and the side span of the main bridge. This, however, is unfavorable for planning the
main bridge with a very long span length. The side span needs to be exactly behind the center
span and on the straight line from the center span, to work as a counter weight of the center span.
Alternative 2 has enough clearance of about 100 m from the power line and there should
be no problems in constructing the tower for a cable-stayed bridge. Moreover, the construction
cost of Alternative 2 is close to that of Alternative 1, while the latter will affect more houses. From
these considerations, Alternative 2 is selected as the most favorable route for the construction of
the bridge.
Figure S-2 shows the plan for the three alternative routes for the Second My Thuan
Bridge.
Source: Study Team
Figure S-2 Alternative Routes for the Second My Thuan Bridge (Upstream is on Left Side)
(2) Selection of Bridge Types
Considering the depth of the river bed, underwater foundations are not favorable. Thus,
introducing a center span of 550 m in Alternative 2 is recommended.
Five bridge types, namely an arch bridge, a suspension bridge, and three cable-stayed
bridges, which can all be considered to achieve a span length of 550 m, were compared. The
cable-stayed bridge alternatives for comparison consist of an A-shaped tower 2-edge girder type
(or the Nhat Tan Bridge type), a single column tower 4-edge girder type, and a steel two box
girder type.
Because the construction of arch and suspension bridges are more costly than
cable-stayed bridges, only the three types of cable-stayed bridge were compared further.
Construction of the A-shaped tower 2-edge girder type and single column tower 4-edge
girder type are realized to be less costly than the steel two box girder type. Furthermore, single
column tower 4-edge girder type gives an impression of a new appearance.
Consequently, the two types of edge girder cable-stayed bridge are selected, as shown in Figure
S-3 and Figure S-4. Out of these two bridge types, the single column tower 4-edge girder type is
most favorable because of its new impression.
Figure S-3 Side view of the Edge Girder Cable-Stayed Bridge
A-shaped tower 2-edge girder
cable-stayed bridge
Single column tower 4-edge girder
Cable-stayed bridge Source: Study Team
Figure S-4 Selected Two Types of Cable-Stayed Bridge
(3) Outline of Expressway Facilities
Outline of the expressway facilities is summarized in the table below.
Table S-1 Outline of Expressway Facilities
1 Project Length 4.05 km (Beginning Point at Km. 103+700 in Tien Giang Province, Ending Point at Km. 107+750 in Vinh Long Province)
2 Road Classification Expressway Class A 3 Design Speed 120 km/hr for approach road, 100 km/hr for main bridge
4 Road Width 33 m (Carriageway: [email protected] m, Emergency Stopping Lane: [email protected] m, Inner Safety Strip: [email protected] m, Shoulder: [email protected] m, Median: 1.0 m)
5 Navigation Clearance 110 m x 37.5 m, 300 m x 30 m 6 Span Length of Main Bridge Center Span: 550 m, Side Span: 240 m 7 Foundation of Main Bridge Bored Pile (Diameter=2.5 m, Length=90 m) 8 Approach Bridge Span Length: 40 m, super-tee girder 9 Foundation of Approach Bridge Bored Pile (Diameter=1.2 m, Length=60 m)
10 Interchange 1 interchange at end point connect to NH 80 with toll gate 11 Bridge 1 bridge with a length of 38 m, 1 overpass bridge at interchange with length of 3@40 m 12 Cross Structures 1 box culvert [email protected] m x 3.2 m, 1 box culvert 2@2 m x 4 m 13 Softground Soil Section Approximately 1.7 km 14 Toll Gate 1 Toll Gate at interchange, 1 toll management office
Source: Study Team
Figure S-5 shows the project alignment plan, while Figure S-6 shows the typical road
cross section.
My Thuan BridgeNH1
HCMC Can Tho
Main Bridge
240+550+240=
1,030m
Approach Bridge
18@40=
720m
Approach Bridge
18@40
= 720m
Approach Road
1,260m
Approach Road
320m
Project Length
4,050m
Box Culvert
[email protected] x 3.2m
Bridge
L=38m
Box Culvert
2@2 x 4m
Interchange with
Toll Gate
My Thuan BridgeNH1
HCMC Can Tho
Main Bridge
240+550+240=
1,030m
Approach Bridge
18@40=
720m
Approach Bridge
18@40
= 720m
Approach Road
1,260m
Approach Road
320m
Project Length
4,050m
Box Culvert
[email protected] x 3.2m
Bridge
L=38m
Box Culvert
2@2 x 4m
Interchange with
Toll Gate
Source: Study Team
Figure S-5 Plan of the Project
Source: Study Team
Figure S-6 Typical Cross Section
The main road consists of 3x3.75 m lanes carriageways, 3.0 m emergency lanes, 1.0 m
median, 0.75 m inner safety strip, and 1.0 m shoulder lane per direction, consequently requiring a
total width of 33 m. Meanwhile, frontage road, which will be constructed to maintain local
people’s traffic, consists of a one lane 3.5 m carriageway and two shoulder 1 m wide shoulders,
necessitating a total width of 5.5 m.
Demarcation line is set at the toe of embankment of the frontage road, or 10 m from the
toe of embankment of the main road. The right of way is set 50 m from the toe of embankment of
main road in accordance with Decree No. 11/2010/ND-CP dated 24th of February 2010.
Figure S-7 shows the proposed arrangement of the toll gate for closed toll collection
system.
Toll Gate at Rampway
Toll Gate at Main Route
NH80NH30
Source: Study Team
Figure S-7 Plan of Toll Gate
(4) Evaluation of Environmental and Social Impacts
Anticipated Impact resulting from the Project: The impacts resulting from the project
were studied based on the secondary information acquired from relevant authorities and
field surveys. With these findings, the JBIC Environmental Check List was filled out
in order to identify the type and degree of impacts. As a result, the main potential
environmental impacts of the project are summarized as follows:
- The most significant negative impacts will associate with the pre-construction phase
resulting from land acquisition, such as resettlement of people, relocation of fixed assets,
and compensation for loss.
- Although the impact is limited during the construction phase, air, water, vibration, and
noise pollution resulting from construction activities will cause adverse effects on
natural environment and society within the proposed project area.
Project Area
- During operation, the impacts associated with increased transport density are the
concerns. These impacts would worsen the air quality, noise and vibration pollution
and accidents.
Based on the satellite image, the total area for land acquisition was estimated to be
71.2 ha, and the number of affected fixed assets, such as houses and huts, was
confirmed to be 159. The type of fixed assets shall be identified and the number of
affected households shall be finalized for further study. The land use type of the final
route is shown in Table S-2.
Table S-2 Land Use
Residential Land (m²)
Agricultural Land (m²)
Rice Field (m²)
River (m²)
Road (m²)
Others (m²)
Total (m²)
Final Route 28,969 635,584 0 41,862 3,345 2,354 712,114 Source: Study Team
Actions Taken by Project Proponent for Further Study: An environmental impact
assessment (EIA) shall be conducted to fulfill the requirement of the GOV and
JETRO/JICA guidelines. The following are the actions that should be taken by the
project proponent:
EIA Related Agenda:
- Conduct an EIA and prepare reports in compliance with the requirements of the
GOV and JETRO/JICA guidelines on environmental and social considerations.
- Hold public consultation meetings with project-affected people (PAP) and reflect in
EIA reports the comments obtained from the meetings.
- Submit the EIA reports to the Ministry of Natural Resources and Environment
(MONRE) for certification.
- Submit the certified EIA report together with other F/S related documents to the
GOV for project approval.
RAP Related Agenda:
- Prepare a preliminary resettlement action plan (RAP) in compliance with the
requirement of the GOV and JETRO/JICA guidelines on environmental and social
considerations.
- Submit the preliminary RAP together with other F/S related documents to the GOV
for project approval.
- Update the information on PAP in the RAP in conducting detailed measurement
survey.
- Hold public consultation meetings with PAPs and finalize the RAP.
- Submit the finalized RAP to the District People’s Committee for approval
- Deliver the compensation and support according to the RAP and acquire the land
for the project.
4. Implementation Program (I/P)
The I/P in this Study is proposed based on following assumptions:
• Special Terms for Economic Partnership (STEP) Scheme of Japanese ODA Loan is
applied.
• Consulting services for the detailed design and tender assistance are supported by
Japanese grant.
• Construction period is 36 months.
Table S-3 shows the implementation program, assuming that common practice and
standard time of procurement procedures under Japanese ODA Loan with STEP scheme are
applied.
Table S-3 Proposed Implementation Schedule
Months 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q
Procurement of D/D Consultant 2
Detailed Design (D/D) 12
Procurement of T/A Consultant 2
P/Q of Contractors 3
Preparation of Tender Document 3
Tender Period 2
Tender Evaluation 3
Concurrence of Tender Evaluation 1
Negotiation of Contract 2
Concurrence of Contract 1
Procurement of C/S consultant 9
Land Acquisition 24
Resettlement 24
Resettlement Monitoring 36
Construction 36 Inauguration
Defect Liability Period 24
5th Year 7th Year6th Year1st Year 2nd Year 3rd Year 4th YearMajor Items
Source: Study Team
5. Feasibility of Japanese ODA
(1) Traffic Demand Forecast
Table S-4 summarizes the results of traffic demand forecast up to the target year 2040.
Table S-4 Result of Traffic Assignment (PCU/Day)
Target
Year
Future Traffic Volume
Second My Thuan Bridge IC Direction to NH80
NH1(Existing My Thuan
Bridge) NH80
2020 55,308 9,782 21,489 13,472
2030 79,799 22,113 35,357 26,354
2040 84,521 19,179 41,606 28,621
Source: Study Team
Traffic volumes for the years 2020 and 2030 is expected to be 55,000 PCU/day and
80,000 PCU/day, respectively. In 2040, traffic volume of Second My Thuan Bridge is expected to
reach 85,000 PCU/day, with only 5,000 PCU/day difference from that of 2030. This results to the
construction of new bridges at that time.
(2) Economic and Financial Analysis
(a) Economic Analysis
For the purpose of the economic evaluation, the following preconditions were
established:
Price Level: Constant 2010 prices
Evaluation Period: 30 years after the first opening to traffic
Disbursement Schedule: Assumed in accordance with the construction plan
Residual Value: No residual values were counted
Opportunity Cost of Capital (Discount Rate): 12%
The cost and benefit streams are presented in the table in the next page. The following
indicators for evaluation were calculated based on the traditional discount cash flow method
(DCF):
Economic Internal Rate of Return (EIRR)
Net Present Value (NPV)
Benefit Cost Ratio (B/C)
The results of evaluation are summarized in Table S-5
Table S-5 Results of Economic Evaluation
Evaluation Indicators Values EIRR NPV(*) B/C(*)
18.07% USD791.87 Million
2.92 (*): Discount Rate = 12%
Source: Study Team
(b) Financial Analysis
Toll revenues were calculated using the following formula:
(Constant Basic Toll Rate) x (Traffic Demand of Base Case)
Toll rate is determined in accordance with Circular No.90/2004/TT-BTC and toll rate of
each vehicle type is calculated from ratio of PCU.
FIRR was calculated as 3.45%.
It is noted that FIRR of 3.45% is not enough to attract private sectors to invest in this
project for both BOT and PPP schemes. However, although financial return is not so high, this
project is determined to be economically feasible and is expected to generate positive economic
impacts. Therefore, it should be implemented under the scheme of public investment.
6. Technical Advantage of Japanese Companies
Japanese companies have experience in construction of many large scale steel
cable-stayed bridges, steel concrete composite cable-stayed bridges and steel suspension bridges
not only in Japan but also around the world. They have also earned extensive experience in
construction of longer span bridges. To assure the wind resistance of the long span bridges not
only at the completion stage but also during the construction stage, the wind tunnel tests are
indispensable. Japanese companies have many experiences for this kind of tests, too.
In the construction of long span bridges, cable-related technology is the most important.
Parallel wire strand (PWS) cables, which are often used as materials for cable-stayed bridges,
were developed by Japanese companies. This type of cable has a very high sectional efficiency
and its cross-section area is smaller than that of the conventional cables developed in Europe,
while it possess the same tensile strength. For long span cable-stayed bridges, the static wind load
on the cables becomes considerably large. PWS cables can reduce induced wind loads, which can
be great merit over the conventional cables.
This bridge is planned to be constructed over the very soft ground area and the large
diameter in-situ bored piles will be employed. For the construction of these piles, large
construction machines which utilize Japanese technology are indispensable.
From these facts, it can be said that the Japanese companies have an advantage compared
to those of other countries.
7. Schedule for Project Formation and its Risks
(1) Schedule for Project Formation
The actions needed for project formation are as follows:
1) EIA should be conducted for approval by the MONRE.
2) MOT should propose to Ministry of Planning and Investment (MPI) to include the
project in priority list for investment.
3) MPI should recommend the project to be included in the priority list for approval
from the Prime Minster.
4) GOV should request the Government of Japan (GOJ) for ODA Loan for the
project after the F/S draft final report is submitted.
5) Following GOV’s request, GOJ will send JICA’s fact finding mission to Vietnam
to sign the Memorandum of Understanding (MOU) for JICA’s Preparatory Study
for ODA Loan.
6) At the end of JICA’s Preparatory Study, GOJ will send JICA’s follow-up study
mission to discuss the conditions for ODA Loan.
7) GOJ then decides and pledges the application of ODA Loan for the Project,
followed by the signing of exchange of notes (E/N).
8) JICA and GOV will finally negotiate for Japanese ODA Loan, followed by the
signing of loan agreement (L/A).
Table S-6 shows the implementation program, assuming that common practice and
standard time of procurement procedures under Japanese ODA Loan with STEP scheme are
applied.
Table S-6 Proposed Implementation Schedule including Project Formation Period
Months 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q
1 SAPROF Study 3
2 Pledge
3 Exchange Note & Loan Agreement (E/N, L/A)
4 Procurement of D/D Consultant 2
5 Detailed Design (D/D) 8
6 Procurement of T/A Consultant 2
7 P/Q of Contractors 3
8 Preparation of Tender Document 3
9 Tender Period 2
10 Tender Evaluation 3
11 Concurrence of Tender Evaluation 1
12 Negotiation of Contract 2
13 Concurrence of Contract 1
14 Procurement of C/S consultant 9
15 Land Acquisition 24
16 Resettlement 24
17 Construction 30 Inauguration
18 Defect Liability Period 24
2015 2016 2017Major Items
2011 2012 2013 2014
Source: Study Team
(2) Risks against the Project Formation
The risks against the project formation are as follows:
1) Comparative Priority with Other Construction Projects
In Vietnam, there are many projects under the priority list. There are four other major
bridge construction projects in Mekong River Region planned for implementation by PMU My
Thuan. These include Cao Lanh Bridge along HCMC Highway (Tien River, 6 km upstream of My
Thuan Bridge); Vam Cong Bridge along HCMC Highway (Hau River, upstream of Can Tho
Bridge); Co Chien Bridge along NH 60 (Tien River, downstream of My Thuan Bridge); and Dai
Ngai Bridge (Hau River, downstream of Can Tho Bridge) along NH 60. Compared to these bridge
construction projects, the Project does not stand out because of the existing of My Thuan Bridge
along NH1. Therefore, there is a need to emphasize the necessity and significance of the Project in
order to be included in the priority list for investment.
2) Limited or Shortage of Budget
Amount for Japanese ODA Loan is limited each year while many projects are queueing
for Japanese ODA Loan application. In addition, the estimated project cost for this project is
nearly USD 600 million, which is quite big compared to other projects. Therefore, there is a risk
of delays due to limited budget.
3) Progress of Implementation of Adjacent Expressways
In case that the project implementation of the Trung Luong–My Thuan and My
Thuan–Can Tho expressways delays or stops, the priority of the Project will be lessened. This will
also result in the delay of project formation. Therefore, the progress monitoring on the
implementation of the adjacent expressways is needed.
4) Delay in Study and Assessment
Delays are possible in conducting and approving F/S, EIA, and Preparatory Study.
Therefore, there is a need to select competent consultants for smooth coordination and
cooperation with stakeholders.
5) Other Risks
In addition to above risks, several risks in the country such as change of law, cancellation
of approval, and political violence are to be considered.
8. Location of the Project
Location of the project is shown in Figure S-8 and S-9.
Can Tho
Dau Giay
Ca Mau
Da Lat
Vietnam
Laos
Cambodia
Thailand
Hanoi
Ho Chi Minh
Ho Chi Minh City
China
Study Area
An Phu
Trung Luong
An Lac
R.R.2
Expressway (North-South Expressway)
HCMC - LT-DG (under construction)
Ben Luc - Long Than (F/S)
An Lac - Trung Luong (completed)
Trung Luong - My Thuan (under construction)
My Thuan - Can Tho (F/S)
Other Classified Road
Saigon East West Highway (partial completion)
An Phu - R.R.2 Urban Road (D/D)
National Highway No.1
SCALE
0 10 20 30 km
Vung Tau
Bien Hoa
My Thuan
LEGEND
Long Thanh
Ben Luc
Figure S-8 Project Location Map (1)
My Thuan Bridge
Sa Dec
Trung Luong - My Thuan
Expressway
SCALE
0 500 1000 1500m
Key Map
HCMC
Vinh Long
NH80
NH1
NH30
Vinh Long
Tien River
HCMC
Cao Lanh
Can Tho
Study Area
4.05km
My Thuan - Can Tho
Expressway
Figure S-9 Project Location Map (2)