substation designing- gis
TRANSCRIPT
-
7/27/2019 Substation Designing- GIS
1/11
REPORT
66/33/11 kV Substation Design Report
Northern Region, GreaterNoida(GIS Substation)
Abstract-This report outlines the need of the GIS
technology integration in the power system in areas
like GREATER NOIDA, It gives a study reportregarding an installation of distribution GIS
substation. The report includes space consideration
with other technical information of substation
erection.
I. SITE PROFILE
Greater Noida or new Okhla industrial
development area are came into being as Industrial
Township in 1976 catering to Delhis commercial
needs and addressing its concern over polluting
industries. Greater Noida is the Planning Marveland an emerging Dream Township. The Total
Notified Area: 36,000 hectares Already urbanized
in Phase I: 5,000 hectares Organisable area: 12,000
hectares (by 2011) City planned for a population
of: 0.7 million (by 2011) & 1.2 million (by 2021)
Industry led development: 3000 hectares (to be
developed by 2011) Strategic Location within NCR
* Well linked to domestic & international markets.
The year 2010-11 proved to be a bad year
for industrial development in Noida and Greater
Noida. A total of 319 units shut operations during
the last financial year, more than 50% up from the
figure of 205 a year ago. Also, in 2009-10, a totalof 1,610 new units came up. But in the last
financial year, only 1,360 units were set up. Poor
power supply and deteriorating law and order
situation remained the main issue.
Greater Noida Industrial Development
Authority falls within the National Capital Region
of Indias capital - New Delhi and is adjacent to
Noida, one of the largest industrial townships in
Asia. It conceptualizes the needs of a fast
developing city of the future. The Action Plan and
execution is at par with global standards and is
aimed at accelerating the growth of industrial, IT
and institutional sectors in the country.Ecotech is
Greater Noida's exclusive Industrial area..Industrial
investment taking place in Greater Noida is now
over Rs. 10,000 crores. It has now become one of
the favoured locations for good industrial
investment especially of multinational investment
because of its good infrastructure near Delhi and
effective single window system of speedy decision
making and clearances.
To sustain this increase in demand of
power consumption more and more challenges are
faced by the government authorities to maintain the
power quality and integration of new technologies
in the power system to make it more reliable. As a
part of this problem substation technologies have
come up with up gradation from Air Insulated
substation to the GIS (Gas Insulated Substation).
Gas insulated switchgear (GIS) is a proven
technology used throughout the world that offers
many advantages over a conventional substation. A
primary advantage is its compactness, which allows
a GIS to be placed closer to a load centre, and it ismore aesthetically attractive, resulting in quicker
installation time, reduced maintenance, higher
reliability and safety, and excellent ability to
withstand seismic events.
When all these advantages are taken into
consideration, a gas-insulated substation is a cost-
effective to a convention in an urban community
and NOIDA region also demand such new
technologies to be implemented considering the
rate of the industrialisation and urbanisation.
The problem of power quality has been a
major threat, causing interruption of supply and
voltage sags which ultimately have led to declining
production and profitability of the industries. As
the reference of this background Uttar Pradesh
Power Corporation Limited (UPPCL) has proposed
many GIS substation to be installed and one of
them is being decided to be erected at the
GREATER NOIDA which takes power from the
substation PALI located about 30km. PALI
substation draws power from the generation plant
650 km far situated at Rihand Thermal power plant
-
7/27/2019 Substation Designing- GIS
2/11
Fig 1: Single Line Diagram of Proposed GIS substation:
-
7/27/2019 Substation Designing- GIS
3/11
II.LAYOUT AND DESIGN CONEPT
The proposed substation is connected to
Pali substation and draws power at 66kV and fed
power with in all four outgoing feeders with
voltage levels 33kV and 11kV.The proposed layout
is given in Fig. 1.The specification covers scope of
design, electrical specification of the components
used, monitoring system, safety and precaution
standards considering the climatic condition of the
site. It is desirable to have the INDOOR gis
considering the scarcity of land and also the high
cost of the land. The scope also covers provision of
modular design considering future expansion in the
load demand.
A. Material and design
Aluminium or aluminium alloys shall be
used preferably for the enclosures. The material
and thickness of the enclosure shall be selected to
withstand an internal arc and to prevent a burn-
through or puncturing of the housing within thefirst stage of protection, referred to a short-circuit
current of 40 kA.
For supervision of the gas within the
enclosures, density monitors with electrical
contacts for at least two pressure levels shall be
installed. The circuit-breakers, however, might be
monitored by density gauges fitted in circuit-
breaker control units.
The manufacturer assures that the pressure
loss within each individual gas compartment and
not referred to the total switchgear installation only
will be not more than 1% per year per gascompartment.Each gas-filled compartment shall be
equipped with static filters of a capacity to absorb
any water vapour penetrating into the switchgear
installation over a period of at least 25 years.
B. SF6
Sulphur hexafluoride is an inert, nontoxic,
colourless, odourless, tasteless, and non-flammable
gas consisting of a sulphur atom surrounded by and
tightly bonded to six fluorine atoms. It is about five
times as dense as air. SF6 is about 100 times better
than air for interrupting arcs.
SF6 is a strong greenhouse gas that couldcontribute to global warming. At an international
treaty conference in Kyoto in 1997, SF6 was listed
as one of the six greenhouse gases whose emissions
should be reduced. Field checks of GIS in service
for many years indicate that the leak rate objective
can be as low as 0.1% per year when GIS standards
are revised.
Fig. 2 GIS assembly
C. Circuit Breaker
GIS uses dead tank SF6 puffer circuit
breakers. The nozzles on the circuit breaker
enclosure are directly connected to the adjacent
GIS module. Enclosure material will be aluminium
alloy.Circuit breakers are equipped with self-blast
interrupters. require minimum maintenance and
only a low amount of switching energy.
Table No.1
(High voltage Alternating current circuit breakers: IEC
62271-100)
1 Rated voltage 72.5 kV
2 Rated current 1600A
3 Rated frequency 50Hz
4 Rated short-circuit breaking current 25 kA rms,3 sec
5 Rated break-time 3 cycle
6 Rated short-circuit making current 62.5 kA peak
D. Disconnector (Isolator)
Disconnect switches have a moving
contact that opens or closes a gap between
stationary contacts when activated by an insulating
operating rod that is itself moved by a sealed shaft
coming through the enclosure wall. The moving
contact velocity is relatively low and the disconnect
switch can interrupt only low levels of capacitive
current or small inductive currents.
-
7/27/2019 Substation Designing- GIS
4/11
Table No.2
(Alternating current Disconnector (isolators) and earthingSwitch IEC 62271-102)
1 Rated voltage 72.5 kV
2 Rated current 1600 A
3 Rated short-time current 25 kA rms, 3 sec
4 Rated control and operatingvoltage 110/220 V DC
5 Type of operating mechanism Motor operated
Mechanically gangedOperated
6 Rated insulation level
a Power frequency withstand
voltage- phase to phase, between phases
rms
- Across the isolating distance
140 kV160 kV rms
b Lightning impulse withstandvoltage
- phase to phase, between phases
350 kV peak
E. High Speed Earthing Switch
(IEC 62271102 class B) as mentioned above.
Fast acting grounding switches shall be of
three phase, encapsulated, three phase linkage
group operated by a maintenance-free self-
contained electrical motor. They shall also have
facilities for emergency manual operation and the
necessary operating handles or hand cranks shall be
supplied.DC motor operation (220 V) completely
suitable for remoteoperation and a manual
emergency drivemechanism is required.
F. Maintenance Earthing Switch
(IEC 62271102 class B) as mentioned above.
G. Current Transformers
CTs are inductive ring types installed
inside the GIS enclosure. The GIS conductor is the
single turn primary for the CT. CTs inside the
enclosure are shielded from the electric field
produced by the high voltage conductor or high
transient voltages can appear on the secondary
through capacitive coupling.
Table No.3
H. Voltage Transformers
VTs are inductive types with an iron core.
The primary winding is supported on an insulating
plastic film immersed in SF6. The VT has an
electric field shield between the primary and
secondary windings to prevent capacitive coupling
of transient voltages.
(IEC 60044)
Table No.4
1 Rated voltage 66kV
2 Highest system voltage 72.5kV
3 Rated frequency 50Hz
4 P F(dry) withstand voltage 140kV
5 Voltage factor 1.2 continuous
6 1.2/50 micro sec. lightningimpulse withstand voltage
350kVp
7 Grounding Effective
I.Bus
To connect GIS modules that are not
directly connected to each other, an SF6 busconsisting of an inner conductor and outer
enclosure is used. Support insulators, sliding
electrical contacts, and flanged enclosure joints are
usually the same as for the GIS modules.
J. Bushings
Outdoor bushings shall be provided for
connection of conventional external conductors to
SF6 GIS. Suitable clamp & connectors shall be
supplied with bushing. The dimensional and
clearance requirements for the metal clad enclosure
shall be maintained as per requirement of relevant
standards.Only SF6 insulated composite silicon
bushings will be provided. The terminals on the
outdoor bushings shall be a solid stem with
dimensions specified.
K. GIS Connection
x Gis to transformerTransformers will be connected to the GIS by
termination of 66 kV XLPE power cable. The
connection between GIS and high voltage cable at
GIS end will be done through cable termination /
cable sealing end. For transformer end connection
the cable termination on structure shall be provided
outdoor. The plug in cable sealing ends for XLPEcables will consist of gas tight plug in sockets and
prefabricated plugs with grading elements of
silicone rubber.
x Gis to lineThe 66 kV line will be terminated to GIS by XLPE
power cable.
x 66 kV Power Cable connection
-
7/27/2019 Substation Designing- GIS
5/11
The connection between GIS and high voltage
cable at GIS end is done through cable termination
/ cable sealing end. Plug in cable sealing ends for
XLPE cables will consist of gas tight plug in
sockets, and prefabricated plugs with grading
elements of silicone rubber. A separate cable
basement is provided for cable entry, its
distribution and installation. All end cable moduleswill be suitable for connecting single core, XLPE
specified cable.
L. Metal-Enclosed Surge Arresters
The 60 kV, hermetically sealed, Gapless,
ZnO, Surge arrestor, suitable for use with GIS. for
each phase, at the 66 kV line underground cable
entry terminals of GIS shall be provided, if
indicated in Schedule of requirements. Each Surge
Arrester shall be provided with self-leakage current
monitoring device at convenient elevation.
M.Power Transformer
Type and Ratings:
x Max. Continuous capacity:ONAF 20 MVA
x Number of phases 3x Frequency 50 Hz(5%)x Rated Voltage :HV side 66kV
LV side 33kV
x Connections :HV side StarLV side Star
x ON load taps on HV side+5% to -15% in steps of 1.25% each
Table No. 5
Insulation Level 66kV 33kV
i)Lightning
withstand
325kV 170kV
ii)Power frequencywithstand voltage
140kV(rms)
70kV(rms)
Insulation level of
Bushing
i)Lightningimpulse voltage 325 kV 170 kV
ii)Power frequency
voltage
140kV
(rms)
70kV
(rms)
III. MONITERING
A. Gas monitoring unit
Gas density or pressure monitoring
devices shall be provided for each gas
compartment. The devices shall provide continuous
and automatic monitoring of the state of the gas.
The SF6 gas monitoring device shall have two
supervision and alarm settings.After an urgent
alarm, operative measures can be taken to
immediately isolate the particular compartment
electrically by tripping circuit breakers and opening
Disconnector.
The gas monitoring device shall monitor at least the
following, locally and on remote.
i) "Gas Refill" Level- This will be used to
annunciate the need for gas refilling.
ii) "Breaker Block" Level- This is the minimum gas
density at which the manufacturer will guarantee
the rated fault interrupting capability of the breaker.
At this level the device contact shall trip the
breaker and block the closing circuits.
iii) Over pressure alarm level- This alarm level
shall be provided to indicate abnormal pressure rise
in the gas compartment. It shall be possible to testall gas monitoring relays without de-energizing the
primary equipment and without reducing pressure
in the main section. Each gas zone shall be
furnished with a gas monitoring system consisting
of a gas density continuous monitoring device
provided with two electrically independent contacts
which operate in two stages as follows:
a) First alarm: At a gas density normally 5 to 10%
below the nominal fill density.
b) Second alarm: Minimum gas density to achieve
equipment ratings.
In special cases determined by the supplier, a third
stage with a set of contacts may be necessary in
certain areas. It shall be ensured that there is no
chance of the gas liquefying at the lowest ambient
temperature
B. Local monitoring unit
a) The operator must be forced in to the only safe
and logical sequence to actuate the circuit breakers,
Disconnector&earthing switches.
b) The actual, completely closed or completely
opened position of all switching devices must be
checked before and after each move.
c) Implementation of logic checks and issuing the
resultant signals
The bursting pressure of relief device should be
effectively coordinated with the rated gas pressure
and the pressure rise due to arcing.
x Dew point measurement meterx SF6 gas leakage detector
-
7/27/2019 Substation Designing- GIS
6/11
x Precision pressure gaugex Gas-service cartsx Any other special tool/tackle required.
C.Indicating Devices
Position indicators shall be provided to clearly
indicate whether a circuit-breaker is open or closed.Each circuit-breaker shall be provided with an
operation counter to record the number of tripping
operations performed.
D. Timing Test
Timing tests are to be carried out after the switch
gear has been completely charged with SF6 gas.
Testing instruments
x Air / gas humidity tester,x Gas purity detector for SO2, H2O, CF4,
AIR etc.,
x Gas leakage tester,x Breaker timing measurement kit,x Set of equipment for pressure
measurement and gas density meter.
Timing test facility shall be provided with
switchgear such that it is not necessary to
open up any gas section to make test
connections to the circuit breaker
terminals.
E.SCADA
The technologies developed are ranging from the
actual building and integrated SCADA based
monitoring system, through the compact gas-insulated Switchgear and transformers with
integrated control and protection equipment to the
SF6 Gas Management Plan (GMP) built around the
world. With all incoming and outgoing feeders
taking the form of cables, the building has no high
voltage-carrying elements on its outer walls.
IV. MODERN TECHNIQUES
1.Innovative and safe circuit breaker technology
requiring minimum space. The circuit breaker can
therefore be designed quite simple and reliable.
Interrupting unit based on the self blast principle
and hydromechanical spring operating mechanism
for a reactionless, reliable switching with soft
extinction behavior.
2.Integrated technology
Two different types of enclosures are available to
integrate the combined disconnector and earthing
switch into the building block system.
3.Busbardisconnector and earthing switch module
The busbar module of the combined disconnector
and earthing switch contains the busbar conductors
and in addition thereto a transversal arranged three
position switch..
4.Digital control and protection
. In case of digital control technology, the single
line diagram with position indicators and control
buttons is replaced by a digital human-machine
interface. Digital control devices provide the same
functions as conventional control technology.
Furthermore a lot of versatile, additional control
and protection functions can be implemented:
Synchro-check,Auto re-closing Operating
frequency supervision, Fault recorder, Backup
protection
5.Connection to station control
Communication between bay devices and the
device on
station level uses solely the new standardized
communication protocol
6.Digital monitoring systems
Either the conventional or the digital control
technology is completed by digital monitoring
systems. These systems operate as an add-on to the
existing control technology and do not interact with
the switchgear protection.
Monitoring systems improve the overall
availability by continuous supervision of all vital
functions of the switchgear. This ensures an earlydetection of critical situations and scheduling of
countermeasures into non-critical times.
7.A new way of Testing Gas Insulated Switchgear:
A voltage withstand test is necessary during the
commissioning of gas insulated high-voltage
switchgear (GIS). To date, the test was performed
by connecting a high-voltage test transformer and a
heavy control unit to the GIS. New technology
combines the multi-functional primary test system
CPC 100 with the newly developed CP RC
package, Together, they form a resonantcircuit..The package is connected to a voltage
transformer, which is specially designed for this
purpose .
8.Digital Relay:
Modern digital relays can be used for control as
well as for protection and other secondary
functions. Because of this, it is possible to group
-
7/27/2019 Substation Designing- GIS
7/11
and combine different functions using just software
tools. Increased availability through self
supervision and selfchecking of the electronics for
the remaining hardwired connections
V. GROUNDING
GIS are subjected to the same magnitude of
ground fault current and require the same low-
impedance grounding as conventional substation. a
strong grounding system is necessary.
Material used:
Copper-clad steel
Copper is a common material used for grounding.
Copper conductors, in addition to their high
conductivity.
Size of conductor-6AWG
Area of grounding earth mat-40ft x 60ft
Equipments used:
1. grounding connectors Connecting all GIS
equipment, Bus duct, enclosures, control cabinets
supporting structures etc. To the ground bus of GIS
2.Connecting ground bus of GIS to the ground mat
riser.-GIS is housed on GIS floor. There will be
under-ground mat below the substation. There will
be adequate number of Galvanized steel risers to be
connected to grounding mat.
Enclosures and circulating currents:
the continuous-type enclosures provide a return
path for induced currents so that the conductor and
enclosure form a concentric pair with effective
external shielding of the field internal to the
enclosure
To limit the undesirable effects caused by
circulating currents, The possible solutions to
reduce the earth electrode resistance are taken as:
1. Use of High density grid:
2.Connection to the reinforced concrete mat:.
3.Use of deep driven ground rods
The following points will be considered:
The grounding arrangement of GIS will ensure
that touch and step voltages are limited to safe
values. Theenclosures of the GIS will be grounded
at several points such that there will be a grounded
cage around all live parts.
The inductive voltage against ground in each part
of the enclosure will not be more than 65 Volts.
Where operating mechanism cabinets are
mounted on the switchgear, the grounding will be
made by separate conductor. Bay control cabinets
will be grounded through a separate conductor.
All conduits and control cable sheaths will be
connected to the control cabinet grounding bus. All
steel structures will be grounded.
Each removable section of catwalk will be bolted
to the support structure for ground continuity.
The enclosure grounding system will be
designed to minimize circulating currents and to
ensure that the potential rise during an external or
internal fault is kept to an acceptable level.
. connectors will be of sufficient mechanical
strength to withstand electromagnetic forces as well
as capable of carrying the anticipated maximumfault current without overheating by at least from
two paths to ground from the main ground bus.
The guidelines of IEEE Std. 80-2000 on GIS
grounding, will be taken into consideration while
designing the grounding system for GIS
Grounding of GIS foundations
A simple monolithic concrete steel reinforced
slab is advantageous both as an auxiliary grounding
device and for seismic reasons. If a continuous
floor slab is used, a good adjunct measure is to tie
its reinforcing steel mesh to the common ground
bus (main ground bus) so that both the GIS
enclosures and the structural steel in and above the
foundation will be approximately the same
potential level
VI. Testing
Three types of testing has to be performed:
1.Type Tests:
1. Tests to verify the insulation level (Lightning
impulse, Switching impulse and ac withstand test
with PD) test on each GIS device (CB,
Disconnector, bus, etc):
2. Dielectric tests on auxiliary circuits.
3. Tests to prove the radio interference voltage
(RIV) level.
4. Tests to prove the temperature rise of any part of
the equipmentand measurement of the resistance of
the main circuit.
-
7/27/2019 Substation Designing- GIS
8/11
5. Tests to prove the ability of the main and
earthing circuits to carrythe rated peak and the
rated short time withstand current.
6. Tests to verify the making and breaking capacity
of the includedswitching devices.
7. Tests to prove the satisfactory operation of the
included switchingdevices.
8. Tests to prove the strength of enclosures.
9. Verification of the degree of protection of the
enclosure.
10. Gas tightness tests
11.additional tests on auxiliary and control circuits.
12. Tests on partitions.
13. Tests to prove the satisfactory operation at limit
temperatures.
14. Tests to prove performance under thermal
cycling and gastightness tests on insulators.
15. Tests to assess the effects of arcing due to an
internal fault.
16. Seismic test
17. Test on Auxiliary switches (Electrical &
Mechanical Endurance,Heat run, IR & HVtest)
2.Routine / Acceptance Testing:
During manufacture and on completion, all
equipment will be subjected to the Routine tests as
laid down in IEC Standard IEC 62271-203.
Tests will include the following:
1.Dielectric test on the main circuit.
The dielectric routine test consists of a power
frequency voltage test on the main circuit including
PD measurement according The PD level needs to
be lower than 5 pC.
2.PD test:
No measurable partial discharge is allowed at 1.1
line-to-line voltage (approx. twice the phase-to-
ground voltage). This test ensures maximum safety
against insulator failure, good long-term
performance and thus a very high degree of
reliability.
3. Tests on auxiliary and control circuits.
4. Measurement of the resistance of the main
circuit.
5. Tightness test.
6. Design and visual checks.
7. Pressure tests of enclosures.
Each cast aluminium enclosure of the switchgear
shall be pressure-tested to at least double the
service pressure
8. Functional tests
9. Tests on auxiliary circuits, equipment and
interlocks in the controlmechanism.
10. Pressure test on partitions.
3.Tests after installation of complete GIS atSite:
After installation and before being put into service,
the GIS will betested in order to check the correct
operation and dielectric integrity ofthe equipment
as laid down in IEC 62271-203.
Tests will include the following:
1. Dielectric tests on the main circuits.
2. Dielectric tests on auxiliary circuits.
3. Measurement of the resistance of the main
circuit.
4. Gas tightness tests.
5. Checks and verifications.
6. Gas quality verifications.
7. On site power frequency voltage withstand test
with PD test.
8. Functional & interlock tests for all items
9. Demonstration of operational compatibility with
SCADA
10. Visual inspection, checks & verifications.
11. Mechanical operation tests of circuit breakers,
Disconnectors and earthingswitches and high-speed
earthing switches
12. Insulation resistance measurement
13. Tests on CTs and PTs
14. Tests on Surge Arresters
-
7/27/2019 Substation Designing- GIS
9/11
VII. FAULTS AND PROTECTION
Faults Status of GIS:
1. mis-operation : grease hardening , corrosion of
switchgear, broken shaft
2.insulating materials : contact badness ofelectrodes, tran sient over voltage, tracking
phenomena of the polymeric insulation material.
3. damage of bushing : defect in voltage screen
4. breakdown of elbow connector : surface damage,
loose contact of connector
5. others : moisture absorption, trouble of control
circuits.
Protection :
Arc detection systems Arc detection systems are
protection systems that use sensors to detect thepresence of an internal arc and then isolate the
faulted section by opening of the incoming or
feeder circuit breaker. In general three types of
systems exist,
1. Light detection systems
2. Pressure rise detection systems
3. Micro switches situated on pressure relief
devices - A high speed fault diverter switch used in
response to arcing anywhere within the substation
to connect the gas-insulated high-voltage conductor
to ground for each phase of the system at highspeed to divert the fault current to ground
Protection of Power Transformer:
Table No.6
Incipient faults below oil level
resulting in decomposition of
oil
Buchholz relay
Sudden pressure relay
Pressure relief relay
Large internal faults (phase-to-
phase, phase-to-ground) below
oil level.Faults in tap-changer.
Buchholz relay
Percentage differentialprotection.
High speed high-set
overcurrent relay.
Saturation of magnetic circuit Over fluxing protectionOver voltage protection
Earth Faults Earth fault relay
Differential protection
Overload Thermal overload relay
Temperature relay sound
alarm
High voltage surges due tolightning, switching etc.
Surge arresterR-C Surge suppressors
Feederand Bus Coupler Protection:
Table No.7
Line Protection
Adapted
Type of relay
66 kV
Directional O/C &
E/FProtection
Numerical Relay
with IEC 61850Protocol
Local Breaker
Backup
Integrated in Dir.
O/C & E/FProtection
33/11 kV
Non-Directional
O/C & E/F
Protection
Integrated in Dir.
O/C & E/F
Protection
Local BreakerBackup
Integrated in Dir.O/C & E/F
Protection
VIII. LOAD SPECIFICATIONS
As GIS compactness allowed erecting the
substation in the vicinity of the load, the proposed
GIS can sustain the power demand of the fast
growing NOIDA region at industrial level. The
substation will have 20+20=40 MVA of installed
capacity. There will be in all four outgoing feeders,two with voltage rating of 33kV and two with
11kV.The substation mainly aim to supply the
industrial load with stipulated quality regulations.
We are also expecting general residential load. The
two 11 kV feeders will take care of the load in the
close region. For the load which are expected in
near future 33 kV feeders are provided that can fed
power to the another substation and then to
consumer. At present 47 large and small scale
industries are working with their full capacity. As
the growth of NOIDA in the recent past many more
industries are expected in this region, some of themare listed below.
Table No.8
Type Present Upcoming
Engineering 12 17
Material Science 2 4
Automobile 5 5
Paint 2 -
Automobile Parts 5 6
Consumer Electronics 9 11
Manufacturing 4 7
Software/IT services 8 20
Research andDevelopment
1 -
Industries mainly demand loads like inductionmotors, water pumps, small furnaces and other.
Beside the different industries nominal load of
residential area must be handled by the substation.
The substation will be designed to run 24 hour to
ensure continuous power supply to the industries
that are running in three shifts.
-
7/27/2019 Substation Designing- GIS
10/11
IX. SPACE REQUIREMENT
The proposed 66/33/11 kV substation is of
INDOOR type and will be planned in a building.
The Fig shows the vertical section of the building
and placement of the various components. For
design purposes indoor temperaturesof 5 C to
+40 C and outdoor temperaturesof25 C to +40C shall be considered.The floor area of 20 ft x 8 ft complies with the ISO
668 standard for the switch gears.
The power transformer demands floor area of 30
ft. x 20 ft. Such two transformers will be installed
and hence the overall floor area required for
flooring is 40 ft. x 60 ft.
X. SYSTEM DATA AND CLIMATIC
CONDITIONS
Table No.9
Sr.No
.
Particulars
Value
1 General
I Installation
Indoor GIS
ii No. of
phases
3
iii
Standardsapplicabl
e
IEC and IS
2 Configuration
I Numberof Feeder
Bay
3 doublebay
Ii Numberoftransform
er Bay
2
Iii Number
of Bus
coupler
1
Iv GIS to
Transformer
Connectio
n
XLPE
powercables
V GIS to
Feeder
connection
XLPE
power
cables
Vi Number
of VT
3
Vii Numberof SA
2
Viii Future
extensionpossibility
One spare
FeederBay
Two spare
capacitorbanks
3 Service conditions
I Condensation Occasional
Ii Max Temp. in
Deg. C
50
Iii Min Temp. in
Deg. C
-5
Iv Daily average
Temp. in Deg. C
38
V Pollution Class III/25mm/
kVvi Average no of
rainy days/annum
50
7 Enclosure
I Material Aluminiu
m alloy
ii Painting shades
and thickness
Shade 631
(IS:5)
8 Auxiliary Supply
I For operation,
control and
signalling
220 Volts
(+10%&-
20%)
ii Other load 440/230
-
7/27/2019 Substation Designing- GIS
11/11
Volts, AC
50 Hz
9 System Parameters
i Rated system
voltage
66/72.5 kV
ii One min. power
frequencywithstand voltage
140kv
(rms)
iii Rated frequency 50Hz
iv Rated continuousat 40 deg Cambient temp.
bus bar
2500A
v Feeder and
transformer bay
1600 A
vi Rated short
circuit withstand
current for 3seconds
25 kA