Page 1: SUCCESS DAM US Army Corps of Engineers SEISMIC … · US Army Corps of Engineers Sacramento District Success Seismic Remediation Project Dam failure at early stages of MCE DISTANCE

US Army Corpsof EngineersSacramento District

SUCCESS DAMSEISMIC REMEDIATION

SUCCESS DAMSEISMIC REMEDIATION

Page 2: SUCCESS DAM US Army Corps of Engineers SEISMIC … · US Army Corps of Engineers Sacramento District Success Seismic Remediation Project Dam failure at early stages of MCE DISTANCE

US Army Corpsof EngineersSacramento District

Success Seismic Remediation ProjectIntroduction

Success Seismic Remediation ProjectIntroduction

Overview– Seismic Problem at Success Dam

– Recent Milestones

– Risk Analysis and Operating Restriction

– Alternative Selection

– Current Status

– Success Spillway Enlargement

– Challenges

Overview– Seismic Problem at Success Dam

– Recent Milestones

– Risk Analysis and Operating Restriction

– Alternative Selection

– Current Status

– Success Spillway Enlargement

– Challenges

Page 3: SUCCESS DAM US Army Corps of Engineers SEISMIC … · US Army Corps of Engineers Sacramento District Success Seismic Remediation Project Dam failure at early stages of MCE DISTANCE

US Army Corpsof EngineersSacramento District

Success Seismic Remediation Project Location Map

Success Seismic Remediation Project Location Map

Success Dam

Page 4: SUCCESS DAM US Army Corps of Engineers SEISMIC … · US Army Corps of Engineers Sacramento District Success Seismic Remediation Project Dam failure at early stages of MCE DISTANCE

US Army Corpsof EngineersSacramento District

Success Seismic Remediation Project Key Key Facts

Success Seismic Remediation Project Key Key Facts

Dual Purpose Reservoir – Flood Control & IrrigationCompleted in 1961Original Cost $14.1M185 ft high X 3,450 ft longEarth-filled damStorage capacity = 82,300 acre-ftProvides 47-year flood protection to the city of Porterville and 200,000 acres downstream

Dual Purpose Reservoir – Flood Control & IrrigationCompleted in 1961Original Cost $14.1M185 ft high X 3,450 ft longEarth-filled damStorage capacity = 82,300 acre-ftProvides 47-year flood protection to the city of Porterville and 200,000 acres downstream

Page 5: SUCCESS DAM US Army Corps of Engineers SEISMIC … · US Army Corps of Engineers Sacramento District Success Seismic Remediation Project Dam failure at early stages of MCE DISTANCE

US Army Corpsof EngineersSacramento District

Success Seismic Remediation ProjectPrimary Earthquake Sources

Success Seismic Remediation ProjectPrimary Earthquake Sources

Active Faults within 100-mile radius

– Premier Fault – 13 miles (M 6.75) MCE *– San Andreas – 72 miles (M 8.0) OBE **– Owens Valley – 52 miles (M 7.6)– White Wolf – 57 miles (M7.5)

• *Maximum Credible Earthquake – worst predicted earthquake (max ground acceleration = 0.28g)

• **Operating Basis Earthquake – expected during life of project (max ground acceleration= 0.1g)

Active Faults within 100-mile radius

– Premier Fault – 13 miles (M 6.75) MCE *– San Andreas – 72 miles (M 8.0) OBE **– Owens Valley – 52 miles (M 7.6)– White Wolf – 57 miles (M7.5)

• *Maximum Credible Earthquake – worst predicted earthquake (max ground acceleration = 0.28g)

• **Operating Basis Earthquake – expected during life of project (max ground acceleration= 0.1g)

Page 6: SUCCESS DAM US Army Corps of Engineers SEISMIC … · US Army Corps of Engineers Sacramento District Success Seismic Remediation Project Dam failure at early stages of MCE DISTANCE

US Army Corpsof EngineersSacramento District

Success Dam

San Andreas M8.0 (OBE)

White Wolf M7.5

Owens Valley M7.5

Premier Fault M 6.8 (MCE)

Success Seismic Remediation ProjectPrimary Seismic Sources

Success Seismic Remediation ProjectPrimary Seismic Sources

Page 7: SUCCESS DAM US Army Corps of Engineers SEISMIC … · US Army Corps of Engineers Sacramento District Success Seismic Remediation Project Dam failure at early stages of MCE DISTANCE

US Army Corpsof EngineersSacramento District

Success Seismic Remediation ProjectHistoric Earthquakes

Large deformations begin

0

0.05

0.1

0.15

0.2

0.25

0.3

0.35

0.4

1850 1860 1870 1880 1890 1900 1910 1920 1930 1940 1950 1960 1970 1980 1990 2000

YEAR

Peak

Gro

und

Acce

lera

tion

(PG

A)

worst casebest casemean

“0.07g failure

threshold”

CoalingaSan Simeon

Kern County/White WolfOwens ValleySan Andreas

Page 8: SUCCESS DAM US Army Corps of Engineers SEISMIC … · US Army Corps of Engineers Sacramento District Success Seismic Remediation Project Dam failure at early stages of MCE DISTANCE

US Army Corpsof EngineersSacramento District

Success Seismic Remediation ProjectCross –Section of Dam

Success Seismic Remediation ProjectCross –Section of Dam

Most of the problem materials are the stream deposits known as “Recent Alluvium”

Page 9: SUCCESS DAM US Army Corps of Engineers SEISMIC … · US Army Corps of Engineers Sacramento District Success Seismic Remediation Project Dam failure at early stages of MCE DISTANCE

US Army Corpsof EngineersSacramento District

Success Seismic Remediation ProjectRecent Alluvium

Success Seismic Remediation ProjectRecent Alluvium

Qog

Qog

Qtg,ch

Qtg,ch

Alluvial Fan

Recent Alluvium

Saprolite

Older Alluvium

Recent Alluvium

Terrace Deposit

Bedrock Terrace Deposit

Bedrock

Terrace

SlopeWash

Deposit

Recent Alluvium

Downstream

1,500 ft

Page 10: SUCCESS DAM US Army Corps of Engineers SEISMIC … · US Army Corps of Engineers Sacramento District Success Seismic Remediation Project Dam failure at early stages of MCE DISTANCE

US Army Corpsof EngineersSacramento District

Success Seismic Remediation ProjectDam failure at early stages of MCE

Success Seismic Remediation ProjectDam failure at early stages of MCE

DISTANCE FROM CENTER LINE, Ft

700 -600 -500 -400 -300 -200 -100 0 100 200 300 400 500

Maximum Credible Earthquake

Upstream slumping

Page 11: SUCCESS DAM US Army Corps of Engineers SEISMIC … · US Army Corps of Engineers Sacramento District Success Seismic Remediation Project Dam failure at early stages of MCE DISTANCE

US Army Corpsof EngineersSacramento District

Success Seismic Remediation ProjectMilestones

Success Seismic Remediation ProjectMilestones

– 1999 – Corps completes DSAP Evaluation Report

– 2000 – Construction General Funds appropriated

– 2000-2003 - Further studies and modeling indicate Recent Alluvium will liquefy.

– 2003-2004 - Risk assessment performed

– Sep 2004 – Selection of Roller Compacted Concrete as preferred remediation alternative

– Nov 2004 – CE-SPK Dam Safety Committee recommends temporary operating elevation restriction of 620’ or approximately 1/3 capacity

– Nov 2004 – RCC analysis and studies begin

– 1999 – Corps completes DSAP Evaluation Report

– 2000 – Construction General Funds appropriated

– 2000-2003 - Further studies and modeling indicate Recent Alluvium will liquefy.

– 2003-2004 - Risk assessment performed

– Sep 2004 – Selection of Roller Compacted Concrete as preferred remediation alternative

– Nov 2004 – CE-SPK Dam Safety Committee recommends temporary operating elevation restriction of 620’ or approximately 1/3 capacity

– Nov 2004 – RCC analysis and studies begin

Page 12: SUCCESS DAM US Army Corps of Engineers SEISMIC … · US Army Corps of Engineers Sacramento District Success Seismic Remediation Project Dam failure at early stages of MCE DISTANCE

US Army Corpsof EngineersSacramento District

Success Seismic Remediation ProjectRisk Analysis and Operating Restriction

Success Seismic Remediation ProjectRisk Analysis and Operating Restriction

Risk Analysis Results

– Risk of uncontrolled release of the reservoir: 1/285 per year. Required 1/10,000

– Short-term risk reduction: Elevation 620’Eliminates overtopping Reduces seepage failure risk to 1/950Reduces loss of life to within acceptable guidelinesMay only be in effect for 7 years.

– Long-term risk reduction requires remediation of dam

Risk Analysis Results

– Risk of uncontrolled release of the reservoir: 1/285 per year. Required 1/10,000

– Short-term risk reduction: Elevation 620’Eliminates overtopping Reduces seepage failure risk to 1/950Reduces loss of life to within acceptable guidelinesMay only be in effect for 7 years.

– Long-term risk reduction requires remediation of dam

Page 13: SUCCESS DAM US Army Corps of Engineers SEISMIC … · US Army Corps of Engineers Sacramento District Success Seismic Remediation Project Dam failure at early stages of MCE DISTANCE

US Army Corpsof EngineersSacramento District

Success Seismic Remediation ProjectRisk Analysis and Operating Restriction

Success Seismic Remediation ProjectRisk Analysis and Operating Restriction

Effects of reservoir restriction

– Loss of Recreation -$2.8M/year (average)

– Flooding in Tulare Lakebed (wet years = 20%) -$.06M/year (average) - Range $0 - $3.2M

– Loss of Storage (Agricultural water users) -$1.4M/year (average) - Range $0 - $3.0M

Effects of reservoir restriction

– Loss of Recreation -$2.8M/year (average)

– Flooding in Tulare Lakebed (wet years = 20%) -$.06M/year (average) - Range $0 - $3.2M

– Loss of Storage (Agricultural water users) -$1.4M/year (average) - Range $0 - $3.0M

Page 14: SUCCESS DAM US Army Corps of Engineers SEISMIC … · US Army Corps of Engineers Sacramento District Success Seismic Remediation Project Dam failure at early stages of MCE DISTANCE

US Army Corpsof EngineersSacramento District

Success Seismic Remediation ProjectAlternative Selection

Success Seismic Remediation ProjectAlternative Selection

Page 15: SUCCESS DAM US Army Corps of Engineers SEISMIC … · US Army Corps of Engineers Sacramento District Success Seismic Remediation Project Dam failure at early stages of MCE DISTANCE

US Army Corpsof EngineersSacramento District

Success Seismic Remediation ProjectCurrent Status

Success Seismic Remediation ProjectCurrent Status

RCC Design and Engineering– Foundation exploration -75% complete– Structural Analysis - 30% complete– Environmental Impact Study (EIS) started– Quarry Sites – initial testing begun– Tower and Conduit analysis started– Real Estate Plan started

RCC Design and Engineering– Foundation exploration -75% complete– Structural Analysis - 30% complete– Environmental Impact Study (EIS) started– Quarry Sites – initial testing begun– Tower and Conduit analysis started– Real Estate Plan started

Page 16: SUCCESS DAM US Army Corps of Engineers SEISMIC … · US Army Corps of Engineers Sacramento District Success Seismic Remediation Project Dam failure at early stages of MCE DISTANCE

US Army Corpsof EngineersSacramento District

Success Seismic Remediation ProjectOngoing and Future Contracts

Success Seismic Remediation ProjectOngoing and Future Contracts

Sonic drilling for continuous core sample100’ Shaft design and constructionConcrete coring of inlet tower for seismic analysisInitial excavation of quarry site – 200 ton Geophysics testing to profile foundationShear wave testingPanel of consultants review of RCC decisionRock screening and crushing Sample existing embankment for materials

Sonic drilling for continuous core sample100’ Shaft design and constructionConcrete coring of inlet tower for seismic analysisInitial excavation of quarry site – 200 ton Geophysics testing to profile foundationShear wave testingPanel of consultants review of RCC decisionRock screening and crushing Sample existing embankment for materials

Page 17: SUCCESS DAM US Army Corps of Engineers SEISMIC … · US Army Corps of Engineers Sacramento District Success Seismic Remediation Project Dam failure at early stages of MCE DISTANCE

US Army Corpsof EngineersSacramento District

Success Seismic Remediation ProjectSpillway Enlargement Project

Success Seismic Remediation ProjectSpillway Enlargement Project

10 ft curve ogee in spillway

Page 18: SUCCESS DAM US Army Corps of Engineers SEISMIC … · US Army Corps of Engineers Sacramento District Success Seismic Remediation Project Dam failure at early stages of MCE DISTANCE

US Army Corpsof EngineersSacramento District

Success Seismic Remediation ProjectSpillway Enlargement Project

Success Seismic Remediation ProjectSpillway Enlargement Project

PCA signed June 2003Non-Federal Sponsors– Lower Tule River Irrigation District– The Reclamation Board, State of CA

Estimated cost $28M

Dual Purpose Project– Increase Flood Control from 1:47 to 1:100– Increase storage capacity by 29,000 ac-ft

Work stopped pending further progress on seismic remediation of Success Dam

PCA signed June 2003Non-Federal Sponsors– Lower Tule River Irrigation District– The Reclamation Board, State of CA

Estimated cost $28M

Dual Purpose Project– Increase Flood Control from 1:47 to 1:100– Increase storage capacity by 29,000 ac-ft

Work stopped pending further progress on seismic remediation of Success Dam

Page 19: SUCCESS DAM US Army Corps of Engineers SEISMIC … · US Army Corps of Engineers Sacramento District Success Seismic Remediation Project Dam failure at early stages of MCE DISTANCE

US Army Corpsof EngineersSacramento District

Success Seismic Remediation ProjectChallenges

Success Seismic Remediation ProjectChallenges

Roller Compacted Concrete Dam – Foundation materials inconsistent– Cement availability and price stability

Real Estate Acquisition– Real Estate Plan dependent upon EIS– Costs of mobile home park relocations– Purchase 40-acre parcel before EIS

Funding– Large FY07 and FY08 funding requirements

Roller Compacted Concrete Dam – Foundation materials inconsistent– Cement availability and price stability

Real Estate Acquisition– Real Estate Plan dependent upon EIS– Costs of mobile home park relocations– Purchase 40-acre parcel before EIS

Funding– Large FY07 and FY08 funding requirements

Page 20: SUCCESS DAM US Army Corps of Engineers SEISMIC … · US Army Corps of Engineers Sacramento District Success Seismic Remediation Project Dam failure at early stages of MCE DISTANCE

US Army Corpsof EngineersSacramento District

Success Seismic Remediation ProjectAccelerated Schedule for RCC

Success Seismic Remediation ProjectAccelerated Schedule for RCC

Accelerated Schedule 2004 2005 2006 2007 2008 2009 2010 2011Select AlternativeDrilling/Exploration ProgramEnvironmental Impact StudyAggregateTesting ProgramSeismic Analysis of DamTower and Conduit AnalysisPlans and SpecificationsReal Estate AcquisitionConstruction of RCC DamMitigation

Funding Requirements ($170M)* $4M $8M $50M $85M $18M $5* (does not include new tower or conduit)

Potential risks due to foundation, tower, conduit

Page 21: SUCCESS DAM US Army Corps of Engineers SEISMIC … · US Army Corps of Engineers Sacramento District Success Seismic Remediation Project Dam failure at early stages of MCE DISTANCE

US Army Corpsof EngineersSacramento District

SUCCESS DAMQuestions

SUCCESS DAMQuestions