successfully manage cost and schedule with primavera unifier and primavera p6
TRANSCRIPT
Copyright © 2014 Oracle and/or its affiliates. All rights reserved. |
Oracle Primavera Successfully Manage Cost and Schedule with Primavera Unifier and Primavera P6
Ray McEnteeDirector, Product Strategy
Copyright © 2014 Oracle and/or its affiliates. All rights reserved. |
Safe Harbor StatementThe following is intended to outline our general product direction. It is intended for information purposes only, and may not be incorporated into any contract. It is not a commitment to deliver any material, code, or functionality, and should not be relied upon in making purchasing decisions. The development, release, and timing of any features or functionality described for Oracle’s products remains at the sole discretion of Oracle.
Copyright © 2014 Oracle and/or its affiliates. All rights reserved. |
Why• Integrate cost and schedule across Unifier and P6.• Need to be able to compare forecasted schedule and costs from baselines to the current project in terms of cash flow and summarized by CBS.• Be able to cost a resource-‐loaded P6 Project.
Copyright © 2014 Oracle and/or its affiliates. All rights reserved. |
Benefits• Ability to compare top down estimates/budgets within Unifier with bottom-‐up developed costs from P6.• Ability to cost, resource loaded schedules within Unifier.• Compare Forecasts from Unifier Business Processes and P6 Baselines and Current Project with the Unifier Cost Sheet and Cash Flow.• Use P6 data as sources of input to EV.
Copyright © 2014 Oracle and/or its affiliates. All rights reserved. |
Supported Use Cases• Duration Based Schedule–Only Dates sent to Unifier
• Resource-‐Based Schedule– Dates and Resource Unit Spreads sent to Unifier. Costs can be calculated in Unifier
• Cost-‐Loaded Schedules– Dates, Resource Unit and Cost Spreads sent to Unifier
Copyright © 2014 Oracle and/or its affiliates. All rights reserved. |
Summarization Level• Data summarized by CBS to predefined WBS levels– Complete – all WBS Codes– Levels – to a user defined level of WBS– Partial – user selects which WBS level on any branch in the hierarchy
Copyright © 2014 Oracle and/or its affiliates. All rights reserved. |
CBS Codes now at Assignments/Expenses
Copyright © 2014 Oracle and/or its affiliates. All rights reserved. |
Send WBS Hierarchy to Unifier Cost Sheet
Copyright © 2014 Oracle and/or its affiliates. All rights reserved. |
Unifier Cost Codes created in the Cost Sheet
Copyright © 2014 Oracle and/or its affiliates. All rights reserved. |
Can send the current Project and include Baselines
Copyright © 2014 Oracle and/or its affiliates. All rights reserved. |
• Planned – Start & Finish Dates– Resource Unit Spreads (Only
Resource & Cost Type projects)
– Cost Spreads (Only Cost Type projects)• Actual – Start & Finish Dates– Resource Unit Spreads (Only
Resource & Cost Type projects)
– Cost Spreads (Only Cost Type projects)
• Remaining – Start & Finish Dates– Resource Unit Spreads (Only Resource
& Cost Type projects)– Cost Spreads (Only Cost Type projects)
• At Completion – Start & Finish Dates– Resource Unit Spreads (Only
Resource & Cost Type projects)
– Cost Spreads (Only Cost Type projects)
Data being sent to Unifier, summarized by CBS Code at the defined WBS Level
Copyright © 2014 Oracle and/or its affiliates. All rights reserved. |
Resource & Cost Loaded Schedules• P6 Resource assigned to the Project are automatically created as Roles in Unifier. (Roles in Unifier provide the rates and assigned currency)• P6 Resource Based projects will be costed within Unifier as they are integrated. If a rates do not exist for a role then they can be added and the P6 Summary Sheet can be re-‐costed.
Copyright © 2014 Oracle and/or its affiliates. All rights reserved. |
Project Detail Form updated with Schedule Type from P6
Copyright © 2014 Oracle and/or its affiliates. All rights reserved. |
Role currency and rates
The currency for the role can be defined and Unifier will convert the rate to the project currency. Escalating Rates can be defined.
Copyright © 2014 Oracle and/or its affiliates. All rights reserved. |
P6 Summary Sheet – Overall Summary
Sheet shows summary by Unifier WBS and Role. All Dates and available Costs and Units are displayed. Clicking on the links will display the detail.
Copyright © 2014 Oracle and/or its affiliates. All rights reserved. |
P6 Summary Sheet – By Month
Drill down to the detail by Week, Month, Quarter or Year. Clicking on the links will display more detail.
Copyright © 2014 Oracle and/or its affiliates. All rights reserved. |
P6 Summary Sheet – By Month
Drill down to the detail by Week, Month, Quarter or Year. Clicking on the links will display more detail.
Copyright © 2014 Oracle and/or its affiliates. All rights reserved. |
P6 Summary Sheet – By Day
The lowest level of detail will shows costs and units
by day.
Copyright © 2014 Oracle and/or its affiliates. All rights reserved. |
Define the Cost Sheet Columns -‐ BaselineThe P6 Summary Sheets become
Datasources for the Cost Sheet
Copyright © 2014 Oracle and/or its affiliates. All rights reserved. |
Define the Cost Sheet Columns -‐ Actuals
Copyright © 2014 Oracle and/or its affiliates. All rights reserved. |
Cost Sheet
Values from the Project Baseline
Values from the Current Project
Copyright © 2014 Oracle and/or its affiliates. All rights reserved. |
Create a new Earned Value Sheet
Copyright © 2014 Oracle and/or its affiliates. All rights reserved. |
Planned Value
PV is based on our Project
Baseline Planned Cost
Copyright © 2014 Oracle and/or its affiliates. All rights reserved. |
EV is based on the Progress that
has been captured in P6
Copyright © 2014 Oracle and/or its affiliates. All rights reserved. |
EAC is based on the AT
Completion Costs of the
Current Project
Copyright © 2014 Oracle and/or its affiliates. All rights reserved. |
Capturing Progress in P6 and sending to Unifier
Copyright © 2014 Oracle and/or its affiliates. All rights reserved. |
P6 Summary Sheets show ActualsWe can drill down into the details as we saw earlier.
Copyright © 2014 Oracle and/or its affiliates. All rights reserved. |
P6 Summary Sheets show At Completion
Copyright © 2014 Oracle and/or its affiliates. All rights reserved. |
This data then updates the Cash Flow
Copyright © 2014 Oracle and/or its affiliates. All rights reserved. |
And finally the EV can be updated
Copyright © 2014 Oracle and/or its affiliates. All rights reserved. |
In Summary• This new integration provides a means of comparing top-‐down budgets with bottom-‐up costs defined within the schedule.• It also allows us to compare the various baselines to review the performance of the project.
Copyright © 2014 Oracle and/or its affiliates. All rights reserved. |
Safe Harbor StatementThe preceding is intended to outline our general product direction. It is intended for information purposes only, and may not be incorporated into any contract. It is not a commitment to deliver any material, code, or functionality, and should not be relied upon in making purchasing decisions. The development, release, and timing of any features or functionality described for Oracle’s products remains at the sole discretion of Oracle.