supercritical co2 turbomachinery configuration and

15
Supercritical CO 2 Turbomachinery Configuration and Controls for a Zero Emission Coal Fired Power Plant: System Off Design & Control of System Transients Chandrashekhar Sonwane, David Hanks, Tony Eastland, Ken Tran, Marinelle Peneda, Jeff Mays, and John Vega September 9-10, 2014 1

Upload: others

Post on 01-Apr-2022

22 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Supercritical CO2 Turbomachinery Configuration and

Supercritical CO2 Turbomachinery Configuration and Controls for a Zero

Emission Coal Fired Power Plant: System Off Design & Control of System Transients

Chandrashekhar Sonwane, David Hanks, Tony Eastland, Ken Tran, Marinelle Peneda, Jeff Mays, and John Vega

September 9-10, 2014

1

Page 2: Supercritical CO2 Turbomachinery Configuration and

• SCO2 Recompression Brayton cycle efficiencies have been

analytically shown to be very attractive

• Relative to an atmospheric oxy-fired supercritical steam pulverized coal

plant with carbon capture

• Previous phase defined a reference plant with a fossil heat

source and identified development needs

• Study completed for Leonardo Technologies, Incorporated (LTI)

• Objective of this effort was to analyze transient operation and

identify any additional development needs

• Start-up

• Shut-down

• Partial load operation

Introduction/Background

2

Page 3: Supercritical CO2 Turbomachinery Configuration and

• 550 MWe with Oxy-

Fired Pressurized

Fluidized Bed

Combustor (PFBC)

Reference Fossil Fueled Plant

3

• Supercritical CO2 (sCO2) power loop key components

• Separate Generator and Compressor drive turbines

• Recompression cycle with two compression and heat transfer

elements

Page 4: Supercritical CO2 Turbomachinery Configuration and

• Plant layout developed • Used to estimate piping

pressure losses and

volumes

• Assumed enhanced

shell & tube HX

technology

• System model updated

• Equipment

performance maps

updated

• System Control

Methodology assessed

for both transient and

steady state operation

Zero Emmissions Power and Steam (ZEPSTM)

Power Plant

4

Page 5: Supercritical CO2 Turbomachinery Configuration and

• Variety of start-up/shutdown

schemes evaluated – initially 14

valves, 4 bypass legs, & storage

• Detailed evaluation of two start-

up approaches • Spin start - concerns for thermally

shocking in-bed heat exchanger

• Motor assist bootstrap - Selected

• Start-up requirements to mitigate

damage to the system: • Prevent compressor stall

• Prevent heat exchanger overheat

• Do not overspeed turbines

• Avoid low Main Compressor Inlet

Temperature/Pressure

• Modified start until successful • Flow split between the recycle and

main compressors modified

• LTR initially lagged thermally

• Recirculating flow during heat up

reduced

• Final system: 6 valves, 1 bypass

leg, & CO2 storage system

System Start

5

Heat Capacity

0

100

200

300

400

500

600

700

800

900

Bed Heat-up High Temperature Recuperator Low Temperature Recuperator Turbomachinery & Piping

He

at

Req

uir

ed

fo

r H

eatu

p (

GJ)

Page 6: Supercritical CO2 Turbomachinery Configuration and

System Start-Up Transient (Conventional

Recuperator Technology)

6

0 4 8 12 16 20 24 28

5000

4000

3000

2000

1000

0

2000

1600

1200

800

400

0

3500

3000

2500

2000

1500

1000

500

0

14000

12000

10000

8000

6000

4000

2000

0

800

600

400

200

0

Hours from Start

MMBTUHDeg. FPSIAlb/sMW

Q-in MMBTUHTbed Deg. FCO2 Pressure PSIA

HTR Temp Deg. FLTR Temp Deg. FCO2 Flow lb/s

GT Power MWCT Power MWCO2 Temp Deg. F

Recuperator Heat-up

PFBC Start & SCOT Fill

Synchronization

Loaded Operation 50-100%

Full Power Operation

0 4 8 12 16 20 24 28

5000

4000

3000

2000

1000

0

2000

1600

1200

800

400

0

3500

3000

2500

2000

1500

1000

500

0

14000

12000

10000

8000

6000

4000

2000

0

800

600

400

200

0

Hours from Start

MMBTUHDeg. FPSIAlb/sMW

Q-in MMBTUHTbed Deg. FCO2 Pressure PSIA

HTR Temp Deg. FLTR Temp Deg. FCO2 Flow lb/s

GT Power MWCT Power MWCO2 Temp Deg. F

Recuperator Heat-up

PFBC Start & SCOT Fill

Synchronization

Loaded Operation 50-100%

Full Power Operation

Page 7: Supercritical CO2 Turbomachinery Configuration and

• There are three shutdown scenarios envisioned: • Planned Shutdown

• Emergency Shutdown

• Disconnect from Grid Shutdown

• Planned shutdown • Drop to 50% loaded power

• Fuel will be cut to the unload setting - bed temperature will drop

• Generator turbine isolation valve (V-1) will close

• Bypass valve (V-2) will open to maintain power to the compressor turbine

• Fuel to the PFBC will be cut and the oxygen will be switched to air

• SCOT CO2 flow will be circulated until appropriate bed temperatures are met before CO2 circulation is stopped

• Emergency shutdown and disconnect from grid are envisioned to be the same • System does not have the luxury of gradually reducing heat load

• Fuel and oxygen supply will be stopped

• Continue bed circulation with the recycle CO2

• Generator turbine flow will be stopped by closing valve V-1

• Bypass valve V-2 will be opened to a point where flow supplied to the compressor turbine is maintained

• CO2 temperature will decay and SCOT CO2 flow will drop until the bed reaches a safe temperature

• There is risk of bed overheating during Emergency shutdown, mitigations: • Coal and oxygen feeds are stopped immediately

• Water is added to the flue gas and recycle systems to offer immediate protection of the PFBC and the solids handling equipment

System Shut Down

7

Page 8: Supercritical CO2 Turbomachinery Configuration and

• CO2 mass at rated power is

229 tons

• Turbine inlet temp maintained

at partial load

• Storage system required to

accommodate variation in

mass

• +6% to -2%

• Make-up location at the inlet

to the cooler

• Avoid impact to the main

compressor

• Drain location at the

compressor outlet

• Pressure high and temperature

low - compatible for storage

Operation at Partial Load

8

Page 9: Supercritical CO2 Turbomachinery Configuration and

• Two SCOT system start-up approaches were analyzed in detail and a

motor assist bootstrap was selected

• Motor on the compressor shaft will be used to force circulation and initiate

preheat of the SCOT system

• No turbine performance issues during transient operation

• Normal rotordynamic and structural limits apply

• Start-up and shutdown operation of the main and recycle compressors

are within the surge, choke, and speed limits

• No new technology risks identified for the turbomachinery

• Significant transient operation benefits with compact heat exchanger

designs

• Instrumentation and control challenges to maintain main compressor

inlet near the critical point

Transient Operation Analysis Conclusions

9

Page 10: Supercritical CO2 Turbomachinery Configuration and

• The information, data or work presented herein was funded in

part by Leonardo Technologies Inc, under Contract Number

S163-PWR-PPM4002

Questions ?

Tony Eastland 818 586 0345

[email protected]

Acknowledgements

10

Page 11: Supercritical CO2 Turbomachinery Configuration and

Back-Up

11

Page 12: Supercritical CO2 Turbomachinery Configuration and

• The SCOT system will

be pressurized once the

PFBC bed temperature

reaches 150°F • Opening valve V-5 on

the CO2 storage tank or

• Filling from CO2 tanker

trucks using a vaporizer

• Once the system is

filled, valve V-5 is

closed

• Generator turbine valve

(V-1) is closed

• Recycle CO2 flow is

controlled by adjusting

valve V-3

• Motor on the

compressor shaft will

be used to force

circulation and initiate

preheat

Initial Start-Up

12

LTR

HTR

-

-

Generator Turbine

1

3

5

8 9

12

13

14

16

17

Recycle

Compressor

Main

Compressor

Cooling

Water In

Cooling

Water Out

10

Compressor Turbine

2

4

11

Generator

MOTOR

CO2

STORAGE

19

20

6

7

18

15

21

22Pressurized

Fluidized

Bed

Combustor

V-1

V-2

V-5V-4

V-3

V-6

LTR

HTR

-

-

Generator Turbine

1

3

5

8 9

12

13

14

16

17

Recycle

Compressor

Main

Compressor

Cooling

Water In

Cooling

Water Out

10

Compressor Turbine

2

4

11

Generator

MOTOR

CO2

STORAGE

19

20

6

7

18

15

21

22Pressurized

Fluidized

Bed

Combustor

V-1

V-2

V-5V-4

V-3

V-6

LTR

HTR

-

-

Generator Turbine

1

3

5

8 9

12

13

14

16

17

Recycle

Compressor

Main

Compressor

Cooling

Water In

Cooling

Water Out

10

Compressor Turbine

2

4

11

Generator

MOTOR

CO2

STORAGE

19

20

6

7

18

15

21

22Pressurized

Fluidized

Bed

Combustor

V-1

V-2

V-5V-4

V-3

V-6

Page 13: Supercritical CO2 Turbomachinery Configuration and

• Compressor turbine will quickly begin offsetting motor power

• System control to a low flow during the initial heat-up • Bypass more flow

through valve V-2 than the compressor turbine

• Once the recuperators have reached their average temperatures and the bed has reached 1100°F, the PFBC is switched to coal firing

• The bypass valve admits more flow to the compressor turbine

• Bed heat duty continually rises and increases the flow to 50% of maximum flow.

System Start-Up

13

LTR

HTR

-

-

Generator Turbine

1

3

5

8 9

12

13

14

16

17

Recycle

Compressor

Main

Compressor

Cooling

Water In

Cooling

Water Out

10

Compressor Turbine

2

4

11

Generator

MOTOR

CO2

STORAGE

19

20

6

7

18

15

21

22Pressurized

Fluidized

Bed

Combustor

V-1

V-2

V-5V-4

V-3

V-6

LTR

HTR

-

-

Generator Turbine

1

3

5

8 9

12

13

14

16

17

Recycle

Compressor

Main

Compressor

Cooling

Water In

Cooling

Water Out

10

Compressor Turbine

2

4

11

Generator

MOTOR

CO2

STORAGE

19

20

6

7

18

15

21

22Pressurized

Fluidized

Bed

Combustor

V-1

V-2

V-5V-4

V-3

V-6

LTR

HTR

-

-

Generator Turbine

1

3

5

8 9

12

13

14

16

17

Recycle

Compressor

Main

Compressor

Cooling

Water In

Cooling

Water Out

10

Compressor Turbine

2

4

11

Generator

MOTOR

CO2

STORAGE

19

20

6

7

18

15

21

22Pressurized

Fluidized

Bed

Combustor

V-1

V-2

V-5V-4

V-3

V-6

Page 14: Supercritical CO2 Turbomachinery Configuration and

• During ramp, the

generator turbine will

be preheated by

slightly opening valve

V-1

• Once 50% flow is

reached, the

generator turbine flow

will be increased by

further opening valve

V-1

• Synchronize with the

grid

System Start-Up (Continued)

14

LTR

HTR

-

-

Generator Turbine

1

3

5

8 9

12

13

14

16

17

Recycle

Compressor

Main

Compressor

Cooling

Water In

Cooling

Water Out

10

Compressor Turbine

2

4

11

Generator

MOTOR

CO2

STORAGE

19

20

6

7

18

15

21

22Pressurized

Fluidized

Bed

Combustor

V-1

V-2

V-5V-4

V-3

V-6

LTR

HTR

-

-

Generator Turbine

1

3

5

8 9

12

13

14

16

17

Recycle

Compressor

Main

Compressor

Cooling

Water In

Cooling

Water Out

10

Compressor Turbine

2

4

11

Generator

MOTOR

CO2

STORAGE

19

20

6

7

18

15

21

22Pressurized

Fluidized

Bed

Combustor

V-1

V-2

V-5V-4

V-3

V-6

LTR

HTR

-

-

Generator Turbine

1

3

5

8 9

12

13

14

16

17

Recycle

Compressor

Main

Compressor

Cooling

Water In

Cooling

Water Out

10

Compressor Turbine

2

4

11

Generator

MOTOR

CO2

STORAGE

19

20

6

7

18

15

21

22Pressurized

Fluidized

Bed

Combustor

V-1

V-2

V-5V-4

V-3

V-6

Page 15: Supercritical CO2 Turbomachinery Configuration and

• Once connected to the

grid, the system will

increase heat duty to

the desired load

• System control will be

transitioned to the

turbine compressor by

closing valve V-2 and

throttling valve V-6

• Completing the startup

Completion of System Start-Up

15

LTR

HTR

-

-

Generator Turbine

1

3

5

8 9

12

13

14

16

17

Recycle

Compressor

Main

Compressor

Cooling

Water In

Cooling

Water Out

10

Compressor Turbine

2

4

11

Generator

MOTOR

CO2

STORAGE

19

20

6

7

18

15

21

22Pressurized

Fluidized

Bed

Combustor

V-1

V-2

V-5V-4

V-3

V-6

LTR

HTR

-

-

Generator Turbine

1

3

5

8 9

12

13

14

16

17

Recycle

Compressor

Main

Compressor

Cooling

Water In

Cooling

Water Out

10

Compressor Turbine

2

4

11

Generator

MOTOR

CO2

STORAGE

19

20

6

7

18

15

21

22Pressurized

Fluidized

Bed

Combustor

V-1

V-2

V-5V-4

V-3

V-6

LTR

HTR

-

-

Generator Turbine

1

3

5

8 9

12

13

14

16

17

Recycle

Compressor

Main

Compressor

Cooling

Water In

Cooling

Water Out

10

Compressor Turbine

2

4

11

Generator

MOTOR

CO2

STORAGE

19

20

6

7

18

15

21

22Pressurized

Fluidized

Bed

Combustor

V-1

V-2

V-5V-4

V-3

V-6