Supply Diversion DamProject Status Open House

Presented by Molly Davidson, PE – Morrison-Maierle, Inc.

Page 2: Supply Diversion Dam Project Status Open Housebitterrootconservationdistrict.net/pdf/morrison-maierle-presentation_20160222.pdfFeb 22, 2016  · Project Status Open House Presented

2

Page 3: Supply Diversion Dam Project Status Open Housebitterrootconservationdistrict.net/pdf/morrison-maierle-presentation_20160222.pdfFeb 22, 2016  · Project Status Open House Presented

3

• Hydraulic roller (“killer dam”)• At least 8 documented incidents since

2011 including one fatality• 8th most visited reach of river in MT• River closures between Woodside and

Tucker

Presentation Title Goes Here

Page 4: Supply Diversion Dam Project Status Open Housebitterrootconservationdistrict.net/pdf/morrison-maierle-presentation_20160222.pdfFeb 22, 2016  · Project Status Open House Presented

4

Hydraulic Roller

Page 5: Supply Diversion Dam Project Status Open Housebitterrootconservationdistrict.net/pdf/morrison-maierle-presentation_20160222.pdfFeb 22, 2016  · Project Status Open House Presented

5

• View looking downstream– Strong current on right, portage left– Horizon line is subtle

Page 6: Supply Diversion Dam Project Status Open Housebitterrootconservationdistrict.net/pdf/morrison-maierle-presentation_20160222.pdfFeb 22, 2016  · Project Status Open House Presented

6

• View looking upstream

Page 7: Supply Diversion Dam Project Status Open Housebitterrootconservationdistrict.net/pdf/morrison-maierle-presentation_20160222.pdfFeb 22, 2016  · Project Status Open House Presented

7

Page 8: Supply Diversion Dam Project Status Open Housebitterrootconservationdistrict.net/pdf/morrison-maierle-presentation_20160222.pdfFeb 22, 2016  · Project Status Open House Presented

8

Page 9: Supply Diversion Dam Project Status Open Housebitterrootconservationdistrict.net/pdf/morrison-maierle-presentation_20160222.pdfFeb 22, 2016  · Project Status Open House Presented

9

Project Objectives

• Delivery of irrigation water• Public safety• Aquatic benefit

Page 10: Supply Diversion Dam Project Status Open Housebitterrootconservationdistrict.net/pdf/morrison-maierle-presentation_20160222.pdfFeb 22, 2016  · Project Status Open House Presented

10

Project History

• 2011 to current - Incidents at diversion dam• May 2014 – Preparation of Preliminary Engineer Report

and grant application• July 2015 – State DNRC funded grant through Renewable

Resource Grant Program• October 2015 – Engineer selected• November 2015 – Survey completed• February 2016 – Notification of USASE grant award

Page 11: Supply Diversion Dam Project Status Open Housebitterrootconservationdistrict.net/pdf/morrison-maierle-presentation_20160222.pdfFeb 22, 2016  · Project Status Open House Presented

11

Project Funding

• Montana DNRC - $125,000• US Army Corps of Engineers - $300,000• Bitterroot Conservation District - $10,000• Montana FWP - $47,500• Irrigators - $50,000

Page 12: Supply Diversion Dam Project Status Open Housebitterrootconservationdistrict.net/pdf/morrison-maierle-presentation_20160222.pdfFeb 22, 2016  · Project Status Open House Presented

12

Project Schedule

• December 2015 – today – Preliminary design• Today – Meet with interested persons• March 2016 – Permitting• April 2016 – Final design• June 2016 – Bidding • October 2016 - Construction

Page 13: Supply Diversion Dam Project Status Open Housebitterrootconservationdistrict.net/pdf/morrison-maierle-presentation_20160222.pdfFeb 22, 2016  · Project Status Open House Presented

13

Page 14: Supply Diversion Dam Project Status Open Housebitterrootconservationdistrict.net/pdf/morrison-maierle-presentation_20160222.pdfFeb 22, 2016  · Project Status Open House Presented

14

Page 15: Supply Diversion Dam Project Status Open Housebitterrootconservationdistrict.net/pdf/morrison-maierle-presentation_20160222.pdfFeb 22, 2016  · Project Status Open House Presented

15

Proposed design

• Eliminates hydraulic roller• Recreators can cross dam at any point • Varying slopes over dam• Historic crossing location is less steep

– Lowest point over diversion• Varying flow conditions for aquatic life

Page 16: Supply Diversion Dam Project Status Open Housebitterrootconservationdistrict.net/pdf/morrison-maierle-presentation_20160222.pdfFeb 22, 2016  · Project Status Open House Presented

16

Page 17: Supply Diversion Dam Project Status Open Housebitterrootconservationdistrict.net/pdf/morrison-maierle-presentation_20160222.pdfFeb 22, 2016  · Project Status Open House Presented

17Presentation Title Goes Here

Page 18: Supply Diversion Dam Project Status Open Housebitterrootconservationdistrict.net/pdf/morrison-maierle-presentation_20160222.pdfFeb 22, 2016  · Project Status Open House Presented

18

• 4:1 vs 20:1

Page 19: Supply Diversion Dam Project Status Open Housebitterrootconservationdistrict.net/pdf/morrison-maierle-presentation_20160222.pdfFeb 22, 2016  · Project Status Open House Presented

19

• 4:1 vs 20:1

Page 20: Supply Diversion Dam Project Status Open Housebitterrootconservationdistrict.net/pdf/morrison-maierle-presentation_20160222.pdfFeb 22, 2016  · Project Status Open House Presented

20

Next Steps

• Consider input from stakeholders• Proceed with permitting• Finalize design