sustainability lessons learned and policy implication for
TRANSCRIPT
The Fukushima Accident: Lessons Learned and Policy Implication for Nuclear
Sustainability
Satoru TanakaThe University of Tokyo,
Former President, the Atomic Energy Society of Japan
August 27, 2012The IAEA INPRO Dialogue Forum in Korea 1
1. Current Status
2. Key Lessons Learned
3. Policy Implication for Nuclear Sustainability
4. Summary
Contents
ØØØ
ØØØ
AESJ’s Report NISA’s 30 Directives to Each NPP and Stress TestsFour Investigation Committees Final Reports
Reform of Nuclear Regulatory SystemNuclear Energy Policy DiscussionContribution to Global Nuclear Energy Sustainability
2
Completion of cover construction for Unit 1 (Oct. 28, 2011)
As of Apr. 17 Step 1 (around 3 months)
Step 2 (through the end of this year)Issues
Cooling by minimum injection rate
Consideration/start offull-fledged decontamination
Installation of full-fledged water processing facilitiesStorage / management of sludge waste etc.
Mid-term issues
Accumula
ted water
reduction
3http://www.meti.go.jp/english/earthquake/nuclear/roadmap/pdf/111216_nps_03.pdf
Dec. 16, 2011 Step 2 of the Fukushima roadmap was attained.Reactors Condition equivalent to cold shutdown is maintained.Spent fuel pool Stable cooling is maintained.Accumulated water Radioactive wastewater is being processed in a continuous and stable manner in water treatment plants. Waste sludge is being stored and managed.Reactor building cover The cover for Unit 1 has been completed , and the cover for Units 3 and 4 is currently being constructed. Monitoring Environmental monitoring and decontamination are being performed.
Consideration of function /installation
CoolingM
itigation
Monitor-ing
Reactor
SFPAccum
ulated W
ater
Atmosphere
/ Soil
Circulating water cooling (cont.)
Circulat-
ingwater cooling
Fresh water
Injection Installation of Circulation cooling system
More stablecooling
Transferring & Storing water
Securestorage place
Installation of the facilities
Consideration offull-fledged processing facilities
Dispersion of inhibitor Dispersion of inhibitor(cont.)
Removal / management of debris Removal / management of debris (cont..)
Mitigate
scattering
Mitigate
scatteringDecontam
ination
Expansion, enhancement and disclosure of radiation dose monitoring in and out of the power station
December 16, 2011 It is made an extract and processed from the NISA public presentation data at the time of a road map completion report.
Dec. 16, 2011
Maintain and Continue coldshutdown condition
Start of removal work of fuels
Dispersion of inhibitor
Removal / management of debris
Continuous environmentalmonitoring
Continuous decontamination
Current status
Stable cooling
Equivalent tocold shutdow
n
Current Status of Fukushima Daiichi NPS
ØØØ
Ø
Ø
:
:
:
:
:
TEPCO removed 2 unused fuel assemblies
from No.4 spent fuel poolwithout any major trouble
18 and 19, July
No.4 pool contains1535 fuel assemblies,including 204 unused ones.
Medium -to Long-term Roadmap toward Decommissioning
4
Road to recovery, Government of Japan, March 2012http://www.kantei.go.jp/foreign/incident/pdf/road_to_recovery_1.pdf
1. Current Status
2. Key Lessons Learned
3. Policy Implication for Nuclear Sustainability
4. Summary
Contents
ØØØ
ØØØ
AESJ’s Report NISA’s 30 Directives to Each NPP and Stress TestsFour Investigation Committees Final Reports
Reform of Nuclear Regulatory SystemNuclear Energy Policy DiscussionInternational collaboration
5
u The AESJ submitted a report entitled “Lessons Learned from the Accident at the Fukushima Daiichi Nuclear Power Plant” on May 9, 2011.
The Atomic Energy Society of Japan (AESJ)’s Report
Ø
Ø
Ø
The lessons in the following 12 topics and their countermeasures categorized into short-term (immediate) and mid-term (in two or three years) measures are proposed.
12 topics:1) The seismic design2) The tsunami3) Station Blackout4) Loss of ultimate heat sink5) Accident management6) Hydrogen explosions 7) Spent fuel storage pools8) Safety research9) Safety regulations and safety design10) Organization/crisis management11) Information disclosure12) Safety management during an emergency
Important Lessons and Strongly Recommended Actions are summarized (see next pages) 6
http://www.aesj.or.jp/en/release/gbcom_kyokun_EN_20110530.pdfhttp://www.aesj.or.jp/en/release/gbcom_kyokun_gaiyo_EN_20110530R.pdf
The underlines in the following pages are Key Lessons to be universally recognized.
The Atomic Energy Society of Japan (AESJ)’s Report
Summary of Important Lessons:
7
a. Estimated tsunami was too small.b. Safety System and Components were damaged because of seawater flooding,
resulting in severe accidents.c. Long-term station blackout caused the accidents progression.d. Reactor parameter monitoring was difficult without electricity.e. Seawater cooling system was vulnerable to tsunami.f. Accident Management (AM) for long-term station blackout may have been
insufficient. g. Hydrogen explosion at outside the containment vessel (CV) was not
considered.h. Enclosure of radioactive materials at spent fuel pool was difficult after
reactor building was damaged.i. Insufficient safety design for external event.j. Japanese safety regulation system was insufficient.k. Public feels that the information disclosure was not enough.l. AM activities prevented significant deterioration of the accidents.m. It is considered Seismic Design for the earthquake was more likely to be
effective in many cases.
The Atomic Energy Society of Japan (AESJ)’s Report
Summary of Strongly Recommended Actions:
8
1. Hardware preparation to protect the safety System, Structure and Components (SSC) from tsunami.
2. Preparation for variety of power sources, such as air-cooled gas turbine system.3. Consideration and preparation for variety of cooling systems in addition to
seawater cooling system.4. Adequate consideration for severe accident management (AM), assuming severe
accidents do surely occur. Hardware preparation for the AM such as multiple wiring for power source. Training and education of AM .
5. AM for preventing hydrogen explosion. AM for spent fuel pool.6. Improvement of severe accident researches and human resources development.7. Drastic revision of the safety regulation including legal system and organizational
reconstruction.8. Establishment of quantitative risk analysis. Introduction of risk concept into the
entire safety regulation.9. Reassessment of public information disclosure and information sharing.10. Realistic disaster prevention practice based on the recognition that severe
accidents do surely occur.11. Detailed evaluation for the seismic design, coordination design, AM, plant
behaviors for the present Fukushima-Daiichi Accident. Then, improve the nuclear safety considering wide range of countermeasures.
1. NISA ( Emergency Safety Measures
2. Stress test
Nuclear and Industry Safety Agency )
NISA’s 30 Directives to Each NPP and Stress Tests
u NISA’s provisional conclusion was submitted as “Interim Report on Technical Knowledge” on March 28, 2012.30 (Lessons Learned) Directives to each NPP from NISA (see next page)Utility’s action plan in response
Ensure emergency power supply and core coolingImprove Severe Accident Management
Countermeasure against Tsunami: (Example) breakwater wall by 2013
Phase I: Plants ready for restart (assessment of safety margin)Phase II: All plants to determine continued operation or not
by comprehensive assessment (PSA)
9
ØØ
üü
ü
ØØ
Ø
Øü
Short term
Medium-to-Long term
New organization will be established in 2012 to promote safety improvement measures continuously.Continuous improvement on equipment and aspect of practical use
Power supply; Cooling; Containment (Filtered venting, etc.) ; Instrumentation
Utilities own initiatives:
Countermeasures based on Technical Knowledge Learned (NISA 30 Lessons Learned)
<Accident Sequence> <Countermeasures>Prevention of Loss of Prevention of Loss of Safety Functions by
Common Cause FailurePrevention of severe
accidentMitigation of Mitigation of
significant release of radioactivity
1. Reliable external power supply and grid2. Earthquake-resistant substation 3. Earthquake-resistant switching station 4. Quick recovery of external power supply
5. Dispersed power facilities6. Water-tightening7. Diversified and redundant emergency
power supply8. Robust emergency DC supply9. System -dedicated backup power supply
10. Facilitation of alternative power supply from outside
11. Storage of backup electrical equipments
12. Improving response capabilities to accidents14. Robust UHS at a time of accident15. Reliable and controllable isolation valves16. Alternative water injection functions17. Reliable cooling and injection system for SFP
13. Dispersed cooling water system and water-tightening
19. Prevention of damage at the top-head flange of CV caused by overheating
22. Independent venting system 23. Decreasing release of radioactivity
when venting 24. Hydrogen explosion prevention
(control gas concentration and the adequate release )
18. Diversified CV cooling system
20. Surely switching to Low pressureinjection process
22. Reliable and controllable venting system
25. Robust emergency command post26. Reliable communication tools for
accidents27. Reliable instruments for accidents28. Robust plant parameter surveillance
functions29. Robust radioactive monitoring
functions
30. Effective structure of emergency response system and training
Earthquake
Loss of External Power Supply
Tsunami
Loss of Emergency D/G
Core Damage
Hydrogen Explosion
Shut down
Start-up Emergency D/G and Core
Cooling System
Loss of Communication,
Instrumentation and Control System
On-site Power Supply
Core Cooling / Injection
External Power Supply
Loss of DC
Loss of Core Cooling System
CV Damage and Hydrogen Explosion Prevention
Communication, Instrumentation and Control
※Underlines mainly target BWR.
(“Interim Report on Technical Knowledge”, NISA, 28 Mar 2012)
10
Safety Improvements of Commercial Reactors
From the presentation material of FEPC’s chairman used at Apr. 19, 2012 Nuclear Industry Convention 11http://www.jaif.or.jp/ja/annual/45th/45-s2_makoto-yagi_e.pdf
12 12http://www.jaif.or.jp/ja/annual/45th/45-s2_makoto-yagi_e.pdf
Safety Improvements of Commercial Reactors
From the presentation material of FEPC’s chairman used at Apr. 19, 2012 Nuclear Industry Convention
:
:
:
:
:
:
In operation Outage for the periodic inspection and others
Shutdown due to tsunami and the government request
46.16 GWe in total : Abolished
In operation Outage for the periodic inspection and others
Shutdown due to tsunami and the government request
46.16 GWe in total : Abolished
Status of nuclear power plants (NPPs) in JAPAN(Ohi-3, Ohi-4, 2 units, 2.36GWe)
(35 units, 30.61GWe)
(13 units, 13.18 GWe)
(4 units, 2.79 GWe)
(Ohi-3, Ohi-4, 2 units, 2.36GWe)
(35 units, 30.61GWe)
(13 units, 13.18 GWe)
(4 units, 2.79 GWe)
13
As of August 27, 2012
Plant name Submitted by utilities Reviewed by NISA Confirmed by NSC Restarted
Ohi-3, Kansai
Ohi-4, Kansai
Stress test and restart status of NPPs in Japan
Before the Emergency Safety Measures
After the Emergency Safety Measures
Oct. 28, 2011 Feb. 13, 2012 Mar. 23, 2012 July 9, 2012 full power
Ikata-3, Shikoku Nov. 14, 2011 Mar. 26, 2012 Being reviewed
Nov. 17, 2011 Feb. 13, 2012 Mar. 23, 2012 July 25, 2012 full power
Tomari -1, Hokkaido Dec. 7, 2011 Being reviewed
Genkai-2, Kyushu Dec. 14, 2011 Being reviewed
Sendai-1, Kyushu Dec. 14, 2011 Being reviewed
Sendai-2, Kyushu Dec. 14, 2011 Being reviewed
Mihama-3, Kansai Dec. 21, 2011 Being reviewed
Tsuruga-2, JAPC Dec. 27, 2011 Being reviewed
Tomari -2, Hokkaido Dec. 27, 2011 Being reviewed
Higashidori-1, Tohoku Dec. 27, 2011 Being reviewed
Takahama-1, Kansai Jan. 13, 2012 Being reviewed
Kashiwazaki-1, Tokyo Jan. 16, 2012 Being reviewed
Kashiwazaki-7, Tokyo Jan. 16, 2012 Being reviewed
Ohi-1, Kansai Jan. 27, 2012 Being reviewed
Shika-2, Hokuriku Feb. 1, 2012 Being reviewed
Shika-1, Hokuriku Mar. 26, 2012 Being reviewed
Takahama-4, Kansai Apr. 6, 2012 Being reviewed
Takahama-3, Kansai Apr. 27, 2012 Being reviewed
Genkai-4, Kyushu May 10, 2012 Being reviewed
Ikata-1, Shikoku May 25, 2012 Being reviewed
Genkai-3, Kyushu May 25, 2012 Being reviewed
Earthquake 1.75 times(equivalent to 1,225 gal)
1.8 times(equivalent to1,260 gal)
Tsunami Approx. 1.6 times(4.65m)
Approx. 4.0 times(11.4m)
Total loss of AC power
Approx. 5 hoursafter the event
Approx. 16 daysafter the event
Loss of ultimate heat sink
Approx.6 daysafter the event
Approx.16 daysafter the event
3% improvement
145% improvement
76-fold improvement
2.6-fold improvement
Primary evaluation results summary, Ohi-3 and 4 of KEPCO
14
Investigation Committees final reports
Date Investigation Committee
Key focus Report management
Private Sector
TEPCO (Internal report)
Diet
Government
15
Feb. 27,2012 Koichi KITAZAWA
(Advisor of Japan Science and Technology Agency)
The report hopes to be helpful to extract lessons to the future of children in Japan and World identifying the truth of the unfortunate situation of the accident as a complex severe accident.
Lessons learned are extracted to achieve safer Japan identifying the back ground of the accident.
June 20,2012 Masao YAMAZAKI
(Vice President of TEPCO)
To clarify causes of the accident by investigating and verifying facts by ourselves as the central player of the accident, and to incorporate the lessons learned into future business operations.
Lessons learned and regrets are reflected to future management of the TEPCO and are helpful for improving the safety of the all NPPs .
July 5,2012 Kiyoshi KUROKAWA
(Former Chairman of Science Council of Japan)
The committee was created under the diet, which has the one of three powers, to recover the trust of Japan and its government from national and world by investigating independently from TEPCO and government administrative body as the party concerned.
For the contents of the report, the investigation committee watches the implementing situation by government.
July 23,2012 Yotaro HATAMURA
(Professor Emeritus at the Univ. Tokyo)
The committee was established with the aim of making policy recommendations on measures to prevent further spread of the damage caused by the accident and a recurrence of similar accidents in the future. This was being done by conducting a multifaceted investigation in an open and neutral manner, accountable to the Japanese public, to determine the causes of the accident.
Government will propose recurrence prevention measures.
NAIIC
ICANPS
Report published, July 5, 2012
“Manmade” disasterThis was a disaster “Made in Japan.”
Its fundamental causes are to be found in the ingrained conventions of Japanese culture (our reflexive obedience; our reluctance to question authority; our devotion to ‘sticking with the program’; our groupism; and our insularityHighlighted
1) Organizational issues: Regulatory capture (lack of oversight of safety by regulatory body due to industry lobbying), organizational issue of TEPCO (lack of concern over public health etc.), organizational issue of NISA, and
2) Deficiency in crisis management system16
NAIIC: The National Diet of Japan Fukushima Nuclear Accident Independent Investigation Committee
[source] http://naiic.go.jp/wp-content/uploads/2012/08/NAIIC_report_lo_res5.pdf]
Conclusions:
Key issues raised byDiet Investigation Committee [NAIIC]
ØØ
Ø
A
)
Recommendations
Key issues raised byDiet Investigation Committee [NAIIC]
1) Monitoring of the nuclear regulatory body by the National Diet2) Reform the crisis management system3) Government responsibility for public health and welfare4) Monitoring the operators including corporate reform of TEPCO
(governance and risk management and information disclosure—with safety as the sole priority)
5) Criteria for the new regulatory body (Independent (from organizations promoted by the government, operator, politics), Transparent, Professional, Consolidated (especially emergency communications, decision-making and control), Proactive)
6) Reforming laws related to nuclear energy7) Develop a system of independent investigation commissions
17
[source] http://naiic.go.jp/wp-content/uploads/2012/08/NAIIC_report_lo_res5.pdf
Key issues raised byGovernment Investigation Committee [ICANPS]
Report published on July 23, 2012
TEPCO & Government trapped by “safety myth” by thinking“severe accident will not happen here”Preparedness to complex disaster by natural hazard andconsequential nuclear accidentParadigm shift (expressed as “changing attitude”) in riskmanagement to avoid nuclear disaster
[Comprehensive] mitigation, regardless of its probability of occurrenceNot setting aside residual risk
18
ICANPS: Investigation Committee on the Accident at the Fukushima Nuclear Power Stations
[source] http://icanps.go.jp/eng/ExecutiveSummaryOfTheFinalReport.pdf
Major Issues:Ø
Ø
Ø
ü
ü
[source] http://icanps.go.jp/eng/SaishyuRecommendation.pdf
Recommendations:
Key issues raised byGovernment Investigation Committee [ICANPS]
1) A basic stance for safety measures and disaster preparednessPreparedness in light of complex disasters in mindChanging an attitude to see risks (Different approach for risk reduction, regardless of its probability of occurrence; Institutional framework to ensure in-depth examination of residual risk)Need to identify all risk potentials from “disaster victims’ standpoint” Incorporating the latest knowledge in the disaster prevention planCentral Disaster Management Council to consider nuclear disaster
2) Safety measures regarding nuclear power generationComprehensive risk analysis Building disaster prevention measures and severe accident management
3) Nuclear disaster response systemsReforming the crisis management system for a nuclear disasterRole of Nuclear emergency response headquarters, Off-site centers, Prefecture
19
üü
üüü
üü
üü
[source] http://icanps.go.jp/eng/SaishyuRecommendation.pdf
Recommendations:
Key issues raised byGovernment Investigation Committee [ICANPS]
4) Damage prevention and mitigationProvision of information and risk communication to build mutual trust between the public and the governmentUse of the SPEEDI systemEvacuation procedures of residentsDeepen public understanding for radiation effects, Information sharing with, and receiving support from, overseas, etc.
5) Harmonization with international practices such as the IAEA safety standards6) Relevant organizations
Functional separation for safety-first decision by regulationRebuilding safety culture, etc.
7) Continued investigation of accident causes and damage
20
ü
üüüü
üü
21
Nuclear Regulation SystemIndependent, Transparent, Professional, Consolidated, Proactive also in Severe Accident (SA) conditionsHarmonization with international good practices such as the IAEA safety standards
Preparedness against Low -Probability High-Consequence (LPHC) risks:Complex hazards of extreme external events such as earthquake and Tsunami and consequent Loss of ultimate heat sink and SBO.Comprehensive mitigation for LPHC events considering Level 4 and Level 5 in Defense-in -Depth. (Level 4:Prevention and mitigation of Severe Accidents, Level 5: Emergency Plan and Crisis Management)
Robust Design:Reduced system interactions; Enhanced reliability by ‘passive’, ‘diversity’ and ‘Redundancy’ in safety system; Elimination of common mode failure
Robustness of Nuclear emergency response headquarters, Off-site centersStrengthen of SA measures in multiple units installationInterface with society:
Provision of information and Risk communicationInformation sharing with, and receiving support from, overseas, etc.
Universal Key Lessons Learned (personal view)Ø
ü
ü
Øü
ü
Øü
ØØØ
üü
1. Current Status
2. Key Lessons Learned
3. Policy Implication for Nuclear Sustainability
4. Summary
Contents
ØØØ
ØØØ
AESJ’s Report NISA’s 30 Directives to Each NPP and Stress TestsFour Investigation Committees Final Reports
Reform of Nuclear Regulatory SystemNuclear Energy Policy DiscussionInternational collaboration
22
New Act (June 27, 2012) Independence
Integration
Amendment to the Nuclear Regulation Act
Reform of nuclear regulatory systemwithin 3 months
Ø
Ø
ØØ
Ø
ØØ
: Separate nuclear regulation function and nuclear promotion function and establish the “Nuclear Regulatory Agency (NRA),” as an independent commission body affiliated to the Ministry of Environment (MOE). A Chair and 4 Commissioners are appointed by the Prime Minister after the approval of the National Diet.
: Integrate nuclear regulation functions, namely, nuclear safety, security, safeguards, radiation monitoring and radioisotopes regulation, into the NRA
Legally requested Severe Accident Measures to the licensees Regulation system based on the latest scientific/technical knowledge (Introduction of back-fit rule )Operational limit of 40 years in principle
Establish “Nuclear Emergency Preparedness Commission (NEPC)” in a CabinetAmendment to the Nuclear Emergency Act
23
Crisis Management:
Reform of Nuclear Safety Regulation System
【 】
【 】
Current Organizations
Nuclear Regulatory
Agency
Nuclear Regulatory
Commission
Chair +4 commissioners
Regulation
New Organizations
CabinetOffice
Atomic Energy
Commission(AEC)
Nuclear Safety
Commission(NSC)
Nuclear Security
METI
Agency for Natural
Resources and Energy
(ANRE)
Nuclear and Industrial
Safety Agency (NISA)
Regulations concerning
commercial power reactors etc.
Double -Check
MEXT
research reactors etc.
Ministry of the
Environment(MOE)
※
24
○
○
【 】
・
・
・
・
・
+
+ +
+ +
【
】
【 】
・
【 】
【 】
In light of the two oil crises, Japan has been steadily promoting efforts to ensure a stable supply of imported resources while reducing the rate of dependency on external resources (through diversification of the generation mix and energy conservation)The energy policy of Japan, a country with limited natural resources, is based on the best mix of the 3 Es: “energy security,” “economic efficiency” and “environmental preservation.”
Energy demand and energy supply mix of Japan
10%
3%
3%
19%
23%
42%
Stable supply
Stable supply Economic efficiency
Stable supply EnvironmentEconomic efficiency
Stable supply EnvironmentEconomic efficiency
Ensuring stable supply by reducing the dependency on oil and introducing alternative energy to oil
Further promotion of the introduction of alternative energy to oil and energy conservation
Ensuring economic efficiency through electricity/gas service reform
Expanded introduction of non-fossil energy (renewables, nuclear)Strengthening of resource diplomacy
1970’s
1990’s
2000’s
1980’s
Promotion of energy conservation
Reinforcement of the efforts to ensure
resources
Energy demand increased with economic growth (1.4-times increase from 1973 to 2008)
Improved efficiency through energy conservation
(By 40% from 1973 to 2008)
Renewable energy, etc.
Water power
Coal
Oil
The 1st oil shock
Nuclear
Natural gas
CoalEnforcement of the Kyoto Protocol (‘05),increased competition for resources
Oil crisis (‘73 and ‘79)
Demand for economic structural reform
Adoption of the Kyoto Protocol (’97)
25Current Basic Energy Plan (June 2010)
Dependence on oil
History of the Energy Policy Based on the 3 Es (Before 3.11)
○
年度実績 年推計年度実績 年推計
()
%
【 】
:
【 】
The current Basic Energy Plan anticipates the increase of the energy self-sufficiency rate (18% 40%) and the zero-emission power source ratio (renewable energy: about 10% 20%, nuclear power: about 30% 50%) by 2030
Total: 10,305Total: 10,200
Oil39% Oil
27%
LPG3%
LPG3%
Natural gas:19%
Natural gas:16%
Coal23%
Coal17%
0
100
200
300
400
500
600
700
2007 2030
Mill
ion
kL c
rude
oil
equi
vale
nt
Current energy self-sufficiency ratio: 18
Energy self-sufficiency ratio in 2030: about 40%
Total: 592
Total: 517
(100 million kW h)
Generated output
Zero-emission power source: 34%
Zero-emission power source: about 70%
Nuclear 10%
Nuclear: 24%
Primary energy supply
Renewables, etc.6%
Renewables, etc:13%
Renewables, etc: 9%
Renewables, etc:21%
àà
à
Oil13%
Oil2%
LNG28%
LNG 13%
Coal25%
Coal11%
Nuclear26%
Nuclear53%
0
2000
4000
6000
8000
10000
12000
2007 20302007 record 2030 estimate 2007 record 2030 estimate26
Supply Forecast in the Basic Energy Plan (Before 3.11.2011) Cabinet Decision in June 2010)(
Ø
Ø
Øüü
Ø
üü
Statements
Medium- and long-term onsite activities (decommissioning) in Fukushima Daiichi NPS
Revision of “Framework for Nuclear Energy Policy”
Evaluation and report to “Energy and Environment Committee” (Cabinet)
JAEC activities after 3.11.2011
Dec. 11, 2011
Start in November 2010 and suspended after March 11, 2011Resumed (August 2011) and suspended again (June 2012)
on June 21, 2012Accident costFuel cycle options- Three options (Complete recycle, Direct disposal, Hybrid)- Evaluation from 7 viewpoints (Economics, SF and waste, International
aspect….) - Report emphasized, besides evaluation, four points (SF storage,
comprehensive assessment of the nuclear fuel cycle business, FBR R&D, International aspect)
27
(See next page)
Seven Evaluation Viewpoints in Evaluating Scenarios(JAEC; ) http://www.aec.go.jp/jicst/NC/iinkai/teirei/siryo2012/siryo22/siryo1-1.pdf
Important issues in the short term
Important issues in the medium - and long-term
June 5, 2012
Management and storage of spent fuelsVolume of spent fuel to be stored and the storage capacity
International perspectives over the nuclear fuel cycleUse of Pu (in stock) and International contributionImplications for non-proliferation and for nuclear security riskImpacts on Japan-United States Atomic Agreement
Challenges involved in the policy change or for realization of the policy (incl. difficulty in siting)
Implications for spent fuels storage, trust relationships with local governments, employments, technical capabilities (human resources, technical basis and infrastructure), waste to be returned from abroad and the burden of costs associated with the policy change
EconomicsTotal cost of the nuclear fuel cycle based on the scenarios
Energy security and security of uranium supply Resource conservation and resistance to fuel crisis
Amount of radioactive waste generatedSecuring options (flexibility)
Flexibility of development and flexibility to the policy change 28
u
u
Øü
Øüüü
Ø
ü
Øü
Øü
ØØ
ü
l
l
l
l
Preparations for future uncertainty are vital, regardless of the chosen option.The government should be responsible for policy changes, and take appropriate measures to maintain reliable relationships with municipalities nationwide, especially those which have cooperated in the national nuclear fuel cycle policies for a long period and accepted the related facilities.Various arrangements and related costs are required to change the present policies and promote other policies.The following issues should be discussed :
1. Expansion of the storage capacity of spent fuel on-site and off-site of nuclear power plants, including dry storage, finding final disposal site for high-level radioactive waste, the discussing the development of technology enabling direct disposal and the required measures and regulations.
2. A comprehensive assessment of nuclear fuel cycle business operations focused on the performance of plant operation at the Rokkasho Reprocessing Plant, progress of plutonium utilization and international perspective (in several years).
(1/2)
29
http://www.aec.go.jp/jicst/NC/about/kettei/kettei120718_e.pdf
Key issues for promoting Nuclear fuel cycle policy options(JAEC; June 21, 2012)
3. Construction of an effective check-and-review system for R&D of FBRs, an R&D system to produce innovative and competitive advanced reactors, and effective and efficient R&D utilizing international cooperation without insisting on finalizing the domestic R&D. Despite opting for a direct disposal policy, continuation of basic R&D into advanced reprocessing and FR technology, etc. is important.
4. Establishment of nuclear fuel cycle policy which takes sufficient account of the increased safety of nuclear power generation worldwide, reducing nuclear nonproliferation and the nuclear security risk.
5. The government is responsible for deciding nuclear policies, with the more explicit assignment of responsibilities to government and private utilities, and enhanced trust via sincere communications with people, and ensuring transparency.
(2/2)
30
://www.aec.go.jp/jicst/NC/about/kettei/kettei120718_e.pdf
Key issues for promoting Nuclear fuel cycle policy options(JAEC; June 21, 2012)http
n
n
n
n
Three options for power generation capability in 2030
Based on discussions by;(considering green growth)
’s discussion on “Framework for Nuclear Energy Policy”on countermeasures against Global
Warming
Mindful* of;Risk management of nuclear powerReduce dependence on nuclear powerShift to low carbon economy fully utilizing energy saving, renewableEconomics, energy security, green growth
To be decided by the end of August
31
* Interim Compilation of Discussion Points for the Formulation of “Innovative Strategy for Energy and the Environment,” July 29, 2011, The Energy and Environment Council
üüüü
üüüü
Energy & Environment Committee Advisory Committee on Energy and Natural ResourcesAECCentral Environment Council
Options raised for public consultation
http://www.npu.go.jp/policy/policy09/pdf/20110908/20110908_02_en.pdf
Three options were presented for nationwide discussions on the basis of reducing the dependence upon nuclear power generation;
Viewpoint: Stick with the principle of zero nuclear power with no new construction or expansion.
Viewpoint: Lower the dependency on nuclear power generation. Make the most strenuous efforts to promote green innovation and nuclear safety improvements.
Viewpoint: Within the direction of lowering the dependency on nuclear power generation, utilize nuclear power to a certain degree including new construction.
32
Option 1: Reduce the nuclear power generation ratio to 0% as soon as possible (0% at 2030)
Option 2: Gradually reduce the nuclear power generation ratio to 15% by 2030
Option 3: Lower the rate of nuclear power generation to below that before the Earthquake but maintain a certain portion. Make the rate 20 -25% at 2030
Three Options for Energy Mix
Fuel Cycle Options Depending on Nuclear Power Generation capacity in 2030
Commercialization of fast breeder reactors (FBR) or fast reactors (FR) is prerequisite.
FBRs/FRs is an option to prepare for future uncertainty.
FBRs/FRs is not an option.
Option 1 Full reprocessing of all nuclear spent fuelsFull reprocessing of spent nuclear fuel, which entails reprocessing all spent
fuel and reusing the recovered uranium and plutonium .
Option 2 Dual policy of reprocessing and direct disposalBoth reprocessing and direct disposal of nuclear spent fuel are kept as
options.
Option 3 Full direct disposal of all nuclear spent fuelsFull direct disposal of all spent nuclear fuel, which entails direct disposal of
spent nuclear fuel after a period of storage.
:
:
:
33
From the presentation material of in the JAEC’ Regular meeting (June 12, 2012) http://www.aec.go.jp/jicst/NC/iinkai/teirei/siryo2012/siryo23/siryo1.pdf (Japanese)
http://www.jaea.go.jp/04/turuga/internationalworkshop/presentationPDF/201206121030_Hiroshi%20Ikukawa_Japan.pdf
MEXT
Options raised for public consultation
Year 2010 2030
**)
34
Option Current Option 1 Option 2 Option 3
Shares(%)
Nuclear 26 %* 0 % 15 % 20-25 %
Renewable(including Hydro)
10 % 35 % 30 % 25-30 %
Fossil 63 % 65 % 55 % 50 %
Electricity output saving Base(1.1 Trillion kWh)
-10 % -10 % -10 %
Electricity cost (JPY/kWh) 8.6 15.1 14.1 14.1
Final energy consumption saving Base (3.9 Billion kl) -22 % -18 % -18 %
GHG emission (compared to 1990) -0.4 % -23 % -23 % -25 %
GDP change in Trillion JPY (compared to business as usual
Base(511)
-8 - 45 -2 -30 -2 -28
Nuclear fuel cycle Reprocessing Direct disposal
Reprocessing/Direct disposal
Reprocessing/Direct disposal
* 26% shows the electricity output (kWh) fraction of nuclear power generation in total power generation in 2010** economic growth rate: 1.1% in 2010s; 0.8% in 2020s (609-636 Trillion JPY in 2030)
[SOURCE] Cabinet’s Energy & Environment Committee (29 June 2012)http://www.npu.go.jp/policy/policy09/pdf/20120629/20120629_1.pdf
~ ~ ~
Government opinion poll on Japan’s future energy policy
Opinions of the three major economic organizations
Japan Business Federation).
Japan Chambers of Commerce and Industry)
Japan Committee for Economic Development)
Deliberative polling, Public hearing and Public comments
0%scenario
15% scenario
20-25% scenario
Other
Deliberative poll
47 15 13 25 285 randomlyselected people
Public hearing 68 11 16 5 1,400 participants
Publiccomments
90* 1* 3* 6* *preliminary resultsin 7,000 out of 89,124
comments
Ø
Ø
Ø
All three options have numerous problems in terms of feasibility and impact on the economy (All of the three options are unfeasible and the scenarios are lack of consistency with the government’s growth strategy* (
.
The nuclear power ratio should be considered flexible in accordance with technological innovations after establishing new safety standards ( .
(between Jul. 2 and Aug. 12, 2012)
* Based on the economic growth rare 2% in 2010s
35
Contribution to Global Nuclear Energy Sustainability (1/2)
36
Japan, as its responsibility, should share severe experience and lessons learned by tackling the accident at TEPCO's Fukushima NPS with all other countries and contribute to enhancing nuclear safety worldwide.
Develop safety design criteria and specification standards which clearly define severe accident measures on the basis of the IAEA’s Safety Standards taking in the lessons from the accident and contribute to harmonizing international standards.
Develop nuclear plants and components with higher levels of safety and make a contribution to the worldwide introduction and expansion of nuclear energy.
l
l
l
Contribution to Global Nuclear Energy Sustainability (2/2)
37
Share knowledge/lessons accumulated in the world regarding spent fuel management (storage technology, etc.), radioactive waste management, disposal technology, site selection, social acceptability and so on.
Contribute to fostering of human resources in the fields of nuclear safety/security/safeguards, nuclear engineering, emergency preparedness and response, radiation medicine, and so on.
In order to respond to the interest of countries seeking to use nuclear power generation for energy security and for responses to global warming, Japan should provide with its nuclear technologies of the world-class safety.
l
l
l
Summary (1/2)
38
Nuclear energy is essential as an energy source with sustainability on a global scale.
We, however, never let an accident like the one at Fukushima Daiichi NPS which affects people and the environment happen again.
It is necessary to 1) thoroughly investigate the cause of the accident2)continue to examine and understand the accident progression3)develop and review the measures for preventing the
recurrence of accident of a severe accident4)build effective AM measures.
l
l
l
Summary (2/2)
39
Given the investigation reports submitted by various accident investigation committees, it is important to share internationally the results and reflect the results in improving the safety of nuclear energy in future.
Cooperating with the IAEA, Japan will promptly develop and update the safety design criteria, specifications standards and nuclear emergency preparedness and response which clearly define severe accident measures, based on the knowledge and lessons learned.
Japanese industry strongly supports nuclear power although the current public opinion on nuclear energy is negative.
l
l
l