SAFE WORK PROCEDURE
3. After completion of work
a. Perform housekeeping at the work area.b. Clean up all spillages.c. Remove all warning signages / barriers in a
sequential and safe manner.
4. Emergency preparedness
a. In the event of any emergency situation, ceasedall work activity, notify Main Contractor andproceed to assembly area.
b. In the event of any incident, seek for immediatemedical treatment and report incident to MainContractor.
c. In the event of any machinery breakdown, ensureonly qualified and competent person to carriedout the repair work.
d. Ensure proper equipment is being used in the aidof any repair work.
e. Ensure emergency response equipments are
made available at the work area.
Emergency ResponseEquipment to be madeavailable at the workarea
RE AL IGNMENT A ND CL EANING O F TBM CUTTER
H E A D
Rev 0 Page 3 of 3
Proceed to assemblyarea in case of
emergency
ER 296