tamil nadu electricity ombudsman - tneo ap no 37 of 2014.pdf · tamil nadu electricity ombudsman...
TRANSCRIPT
1
TAMIL NADU ELECTRICITY OMBUDSMAN 19- A, Rukmini Lakshmipathy Salai, (Marshal Road),
Egmore, Chennai – 600 008. Phone : ++91-044-2841 1376 / 2841 1378/ 2841 1379 Fax : ++91-044-2841 1377
Email : [email protected] Web site : www.tnerc.gov.in
BEFORE THE TAMIL NADU ELECTRICITY OMBUDSMAN, CHENNAI
Present : Thiru. A. Dharmaraj, Electricity Ombudsman
Appeal Petition No.37 of 2014 Thiru K.Kathirvelu, B.E., No.54, Kamaraj Nagar, Sholingur & Post, Vellore District, Pincode 631 102 :. . . . . . Appellant
(Party in person) Vs
The Assistant Engineer / O & M, Erumbi Village & Post, Kancheepuram Electricity Distribution Circle Pallipat Taluk, Thiruvallur District, Pincode – 631 302. :. . . . . Respondent (Party in person)
Date of hearing : 7.8.2014 & 11.11.2014
Date of order : 07.01.2015 The Appeal petition dt. 19-6-2014 received from Thiru K. Kathirvelu, Kamaraj
Nagar, was registered as AP 37 of 2014. The Appeal petition came up for hearing
before the Electricity Ombudsman on 7.8.2014 & 11.11.2014. Upon perusing the
Appeal Petition, counter affidavit and after hearing both sides, the Electricity
Ombudsman passes the following order.
Order
1. Prayer of the Appellant:
i) To pass orders for refund of both the amounts of Rs.47,300/- and 32,200/- for which
the copy of the original receipts are enclosed and also to pass orders for submission
2
of detailed original estimates and deviated estimates for the amounts of Rs.47,300/-
and Rs.32,200/-.
ii) To pass orders for restoring the conveniences and facilities which were available to
the Complainant as was existing before the execution of DCW on 15.04.2014.
iii) To pass orders granting the Complainant the same concessions which were
rendered to his immediate neighbours in removing the entire 3 phase 4 lined
transmission system over their houses and plots without any payment.
iv) To pass orders for submission of orders from Mr. Sathish the AE/O&M/Erumbi under
which the 4 lined 3 phase transmission system was modified into 2 lined single
phase transmission system to a length of about 300 feet.
v) To pass orders for submission of orders from Mr. Sathish, the AE/O&M/Erumbi
under which the 4 line 3 phase transmission system was fully removed over the
houses and plots of the neighbours of the complainant before executing the DCW in
the premises of the Complainant on 16.4.2014.
vi) To pass an order for the compensation to the Complainant atleast to an amount of
Rs.5.00 lakhs from Mr. Sathish, the Assistant Engineer, Erumbi EB Section for his
adamancy, to comply with the request of the Complainant already made in direct and
through the CGRF, KEDC, Kancheepuram and such other orders that may deem fit
and to be considered by the Electricity Ombudsman.
vii) To pass orders for advising and warning to the executive staff concerned in the level
of AE / JE in EB Section, Erumbi Village involved to create such a Consumer
Grievance Application, appeal etc. resulting waste of time, money on both sides.
2. Brief history of the case:
2.1 The Appellant applied for 3 Nos service connection for his premises situated
at Erumbi village .
(a) 1 No. LT 3 phase service connection under tariff I A in Survey No. 235/57 of
Erumbi Village.
(b) 2 Nos of LT 3 phase service connection one under tariff IA and another under
Tariff V in survey No. 949/2AI.
2.2 The Appellant was informed that on payment of the damage cost and DCW
shifting cost of the line that are passing over his building the service connection
requested will be considered.
2.3 The Appellant filed a petition before the CGRF of Kancheepuram Electricity
Distribution Circle and the Forum has issued its order on 28.3.2014. The Forum
3
ordered that the service connection application will be admitted only after the
payment of damage and shifting cost by the petitioner.
The Appellant paid a sum of Rs.47,300/- towards the damage and shifting
charges and the services were effected.
3. Orders of CGRF
3.1 The CGRF of Kancheepuram Electricity Distribution Circle issued its order on
28.3.2014. The relevant para of the Forum order is extracted below:-
“ Conclusion: Based on the substantiated reasons as placed by the Petitioner and the
Respondents (1 & 2) at the various hearing before the Forum and after thorough
verification on the issue, the Forum directs as follows:
1. The request made by the Petitioner for the electrification of 3 Nos of Service
connections at his owned premises (in Survey No. 235/57 – 1 No & 2 Nos in SF
No.949/2A1 would be admitted only after the payment of Damage & Shifting cost by
the petitioner to the Licensee at any cause.
2. Hence, abiding the Regulations 27 (6) & (7) a DCW estimate may be evolved
for the damages and shifting of the LT 3 phase 4 wire line and the payment charges
may be intimated to the petitioner by the EE / O & M/Tiruttani within 3 days on
receipt of this order and the Petitioner may also be intimated to pay the amount on or
before 10.04.14 (failing which this the order gets cancelled).
3. On payment of the DCW cost the Licensee shall entrust the shifting work and
complete within the shortest time period (Within 3 days).
4. On completion of the shifting work, the request towards the electrification of
service connections as requested by the petitioner in Forum shall be admitted and
electrified within a period of 15 days on receipt of the service connection charges.
Note: The last hearing was arranged on 28.03.14 (as per the request of the
petitioner) and during the discussions as expressed by Quorum, the petitioner had
also accepted the aforementioned conclusion and complied to pay the DCW
estimate cost to the Licensee to proceed further.”
4. Contentions of the Appellant:
The Appellant has contended the following in the appeal petition.
4
(i) The CGRF at KEDC, Kancheepuram clubbed all the three complaints of the
Complainant and registered as Case 1/2014 and passed its orders on 28.3.2014.
(ii) The Complainant have clearly explained in detail in letter dt.29.3.2014 and 4.4.2014
regarding his critical position to follow the orders of the CGRF, Kancheepuram and
explained every possibility and feasibility to modify the orders as insisted by the
complainant from the beginning.
(iii) The CGRF, Kancheepuram never considered the documentary evidences produced
by the Complainant and also his explanations with his personal witness. The
CGRF’s actions were favourable to the Respondents from the beginning of the date
of receipt of the complaints from the Complainant. The irregularities of the CGRF,
Kancheepuram have also been intimated to the Electricity Ombudsman.
(iv) On receiving the order from the CGRF, Kancheepuram and under the compulsions,
circumstances and forces as explained by the Complainant in the leter dt.4.4.2014
addressed to CGRF & Electricity Ombudsman, the Complainant sent his letter dated
04-04-2014 with a DD for Rs.47,300/- to the AE O & M, Erumbi Village, KEDC,
Kancheepuram as instructed by the Forum and the same was acknowledged by the
Assistant Engineer, on 07.04.2014.
(v) The necessity of sending the DD for the entire amount of Rs.47,300/- ordered by the
Forum forcibly as detailed below was committed by the Complainant under protest
as expressed by the Complainant in the letters dated 4.4.2014 written to the CGRF
Kancheepuram and Mr. Sathish Assistant Engineer, O & M, Erumbi respectively.
The forcible and compulsory orders are
i) The request made by the Petitioner for the electrification of 3 Nos of
service connections at his owned premises (in Survey No. 235/57 – 1 and 2 Nos in
S.No. 949/2A1) would be admitted only after the payment of Damage & Shifting cost
by the Petitioner to the Licensee at any cause.
ii) Hence, abiding the Regulation 27 (6) & (7), a DCW estimate may be
evolved for the damages & shifting of the LT 3 phase 4 wire line and the payment
charges may be intimated to the petitioner by the Executive Engineer/O&M/Tiruttani
within 3 days on receipt of this orders and the Petitioner may also be intimated to
pay the amount on or before 10.04.14 (failing which this the order gets
cancelled).
Further in the above orders of the Forum under the footnote it is give as :-
5
Note: The last hearing was arranged on 28.03.14 (as per the request of the
Petitioner) and during the discussions, as expressed by Quorum, the Petitioner had
also accepted the aforementioned conclusion and complied to pay the DCW
estimate cost to the Licensee to proceed further.
(vi) Both of the above orders and also the note as said above are contrary to the
discussions and decisions made during the enquiry on 28.3.14 at CGRF,
Kancheepuram.
(vii) The orders of the Forum were passed only on the views of the above said
person to safe guard his interest and to make him free from the three complaints of
the complainant.
(viii) The Forum allowed sufficient time to both of them to create false replies to
suit the three complaints with the help of Mr. Karthikeyan, the then JE, of Erumbi
Section who is now working at Athimanjerypet, Tiruttani Division, KEDC,
Kancheepuram.
(ix) This may be due to the reason that the Licensee, the Chairman of CGRF and
the Superintending Engineer are all one and the same person. The other two
members of the Forum have not been facilitated with separate staff and Office to
analyse the complaints for taking the decisions and revealing their own views. Both
of them did not put any question to the Respondents. They have been only as
observers. The Chairman was the only person to deal the proceedings of the
enquiry. Hence his decisions were final and contrary to the actuals. Both the
Respondents have been freed and the Complainant was not given any relief and the
orders were on the line of the view of the Respondents.
(x) The Complainant quoted in several occasions in his documents and by
personal witness during the enquiry the previleges granted by the “G.O. Ms. No. 7
Energy (C3) Department dated 23.02.2005 to the Chairman, TNEB, Chennai – 2
and the Secretary, TNEB, Chennai – 2 and also copy marked to the Municipal
Administration and Water Supply Department Chennai – 9” in shifting the
Electric poles and wires in the premises of the Complainant that comes in Village
Panchayat. The privileges and concessions in the above G.O. is “The cost of
shifting work in Village Panchayats and Panchayat unions is to be borne by the
TNEB itself since these institutions are weaker”. The Forum has failed to record
its views about this G.O. in its orders. Mr. Sathish the AE, O & M received the
6
DD for Rs.47,300/- for the DCW estimate that was prepared on this own accord
without any consent or application or agreement from the Complainant.
(xi) Three phase 4 lined wires were existing in premises of the Complainant before
the execution of the DCW. The same convenience might have been replaced while
shifting also. But the AE has replaced the 3 Phase 4 lined transmission power
system which was a convenience to the Complainant, as single phase 2 lined
transmission power system. This acts of Mr.s Sathish, the AE, O & M were against
the Natural Justice and against the welfare of the Complainant.
(xii) The new pole erected is still without strut or supporting pole. It stands in a
slanting position. The new pole erected may fall down at any time due to the
unexpected storms and wind pressure and one wire is now going in touch with a
coconut tree very closely and this wire may be damaged at any time due to friction
with the coconut tree and may cause hazards to the livings. Two poles rigidly fixed
were also forcibly removed.
(xiii) The AE has removed 3 phase 4 lined wiring that were passing over the houses
and plots of the very adjacent neighbours living at the north of the premises of the
Complainant and also he made 3 phase 4 lined wiring into single phase 2 lined
wiring to a length of about 300 feet beyond the houses and plots before executing
the remaining DCW Work in the premises of the Complainant on 16.04.2014.
(xiv) The Complainant is of the opinion that no rules and regulations have been
followed in executing the DCW work beyond the premises of the Complainant. Only
with the aim of completing his desire in executing the DCW in the premises of the
complainant he violated all the rules and regulation and took them all in his hand.
5. Contentions of the Respondent:
The Respondent have furnished a detailed counter. But the contentions that
are relevant to the prayers of the Appellant alone are furnished below:-
(i) The sum of Rs.47,300/- and Rs.32,200/- paid by the Appellant are as per the
sanctioned DCW estimates. As the works are completed as per the estimate
seeking refund of the said amounts are against Boards rules.
(ii) As per the orders of the CGRF of Kancheepuram Electricity Distribution Circle the
DCW works was completed. The poles and the lines passing through the premises
were removed to safe guard the interest of the Petitioner.
7
(iii) As stated by the Appellant, no electric lines was removed in the nearby house of the
Appellant. The works were executed as per the sanctioned estimate only.
(iv) A 3 phase, 4 wire was passing through the Appellant premises. The above line was
removed and a single phase line was erected to continue the supply to the other
consumers who are fed by the above line. As there was no three phase supply
availing consumer the line was erected as a single phase line. But the estimate was
prepared without any loss to Board and the Appellant.
(v) The electric poles and lines were removed only based on the estimate approved by
the Assistant Executive Engineer / R.K. Pettai and not as per his desire as stated by
the petitioner.
(vi) In letter dated 17.3.2006, the petitioner has requested for removal of lines passing
over his house plots wherein he has agreed to have the shifted line to pass over his
land. The above work was done based on a proper sanction as DCW estimate.
(vii) The petitioner has thanked the Executive Engineer / Thiruthani & Assistant Engineer
/ Erumbi for completing the DCW works. The copies of the letters are furnished for
reference.
(viii) He also filed a petition to shift the electric line passing through the premises and the
poles erected in the premises at boards cost. In response to the above request,
necessary reply was sent on 29-12-2007.
(ix) On 4-1-2009, Thiru A. Ravi wireman informed the Junior Engineer / Erumbi that the
electric line passing over the premises of the petitioner was damaged and a pole has
also broken due to falling of the broken concrete and rods on the electric line.
(x) Accordingly, the petitioner was informed to stop the work and arrange to shift the line
in an alternate route by paying the DCW estimate cost as per the rates in force vide
letter dt.5.1.2009. A complaint was also made with R.K. Pettai Police Station in this
regard (Crime No.07/2009 sec 337 & 338).
(xi) As per the requests of the other consumers, supply was restored to them through an
alternate route.
(xii) The petitioner filed a petition dt.12.1.2009 to remove the dead LT lines which are still
existing on the premises of the petitioner which was also replied by the Junior
Engineer / Erumbi on 21.1.2009.
6. Rejoinder of the Appellant :-
6.1 The contentions that are relevant to the case alone are furnished below :
8
6.2 It is also one of the efforts taken by Thiru. Satish, AE to create record against
the complainant to face the complaints. The S.I of R.K. Pet Police Station found no
evidence at all at the premises of the complainant to take action against the
appellant.
6.3 Against the discussions made in the meeting held on 28.3.2014 at CGRF,
Kancheepuram, the cost of Rs.47,300/- towards DCW estimate was collected from
the appellant under protest. The appellant has not given consent to the DCW work
and against his information, request etc. the cost of Rs.47,300/- have been collected
from the appellant forcibly and Thiru. Sathish, AE has executed the DCW work as
per his will and wish against the code rules. In these aspects the communications
sent to TNEO may please be referred to.
6.4 Against all the objections, informations, request etc., Thiru. Sathish, AE,
removed the existing pole at Loc.2 and 4 lined wiring between Loc. 1 and Loc.2
which were in good condition and no one wanted its removal except Thiru. Sathish,
AE. The poles and wires were in a separate condition from the buildings and they
were serving its purpose to the appellant and also to others away from the premises
of the appellant. From the year 2006 they were in the present position and no EB
officials was under the necessity to remove them from their position. To cope up his
false activities in non granting new supply to the appellant , he took all the steps and
created causes to disturb the appellant. It is to be informed to the TNEO that, from
the year 2006 the appellant as well as other adjacent to the appellant’s premises
were getting supply only from the pole at Loc. 2 and no one gave applications to
remove it. If at all given, it is only at the cost of EB.
6.5 It is false to state that Thiru. Raja, JE and Thiru. Sathish, AE have acted
properly as per the code rules. If all their actions were as per the code rules, there is
no necessity at all to the appellant to bear such a sorrowful mental agonying state of
affairs. During the service of Mr. Karthikeyan the JE, the appellant gave application
for new connection from the same pole at Loc2. But he did not grant new supply.
This message have already been proved with the relevant records and the same
may please be referred to.
6.6 It is true that a case was filed at R.K. Pet Police Station on 5.4.2009 against
the appellant for a small accidental incident under section 337 & 338. These
sections are meant for incidence of negligence on the part of persons while doing
9
works in general. This case was closed later as there was no necessity to keep it
pending.
6.7 It is the actual fact that the most sufferer is the appellant and he is facing a
lot of problems, loses, worries, mental tiredness etc., because of the reason that
Thiru. Sathis, AE, instead of solving problems peacefully, is going on creating
problem more than his capacity and made the appellant to come to this stage. he
proposed DCW estimate got the order as per his wish and executed the same as per
his wish and all his activities were against the code rules.
6.8 Both the DCW were executed under protest and against the information and
request made by the appellant. The DCW for Rs.32200/- was carried out against the
safety rules (vide safety aspects under code rules already enclosed. Section 53 of
Electricity Act 2003, section 63 under TNEDC 2004 and section 13 of CEA
Regulations 2010 already enclosed). The DCW executed under protest as said in
the above para in the same have been removed from the premises of the Appellant
by getting an amount of Rs.47,300/- from the appellant forcibly. Further, on the
resolution passed by the village panchayat, Erumbi village based on the G.O the
DCW work in the premises of the appellant might have been executed at the cost of
TNEB Ltd., (vide resolution No.39, dated 27.12.2006 of Erumbi village panchayat,
pallipat taluk, Tiruvallur Dist. and G.O. Ms No.7, EnergyC3 Department dated
23.2.2005 to the Chairman, TNEB, Chennai2).
6.9 The appellant never requested for the removal of the existing poles and wires
which were erected while executing DCW in the year 2006. They were forcibly
removed by getting compulsory demand of Rs.47,300/-
6.10 In the appeal petition itself it has been clearly proved with photos that he has
removed wires over the houses and house sites very adjacent to the premises of the
appellant without any payment by the concerned to the TNEB without any cost. The
same procedure is applicable to the appellant also and the appellant need not pay
any cost to do a similar type of work in appellant premises.
6.11 The appellant and others were having the convenience of getting 3 phases 4
lined transmission system which were existing before executing unnecessary DCW
by the AE. It is the natural justice and it is also duty of the public servant to keep the
convenience as it is when the system is changed and put in another place. The AE
so far not given the copy of the estimate under which he removed the transmission
system in premises of the appellant and also over the house sites of the others.
10
6.12 Without any consent from the appellant , the DCW was executed and
amount collected. This is against the code rules. The wires over the houses and
house sites of the neighbours were also removed without any estimate or amount
collected from the concerned.
6.13 It is true that the appellant submitted application but later on before executing
DCW the appellant made protest and requested not to execute DCW because of
the reason that the DCW would created more dangers to the persons in his
premises. But only for the reason that amount collected from him, the EB executed
DCW .
6.14 The AE has comfortably taken two lines from the letter dated 26.12.2007 and
he has hidden all the important grievances revealed by the appellant. It is very
clear , he is creating false reply to suit the complaints.
6.15 It is true that the appellant requested the EB to remove all the wires and the
poles from his premises at the cost of the EB on the resolution passed by the Erumbi
village panchayat based on the G.O.Ms No.7 dated 23.2.2005 energy (C3)
department addressed to the Chairman, TNEB, Chennai 2. But, it is fully false that
the JE, Karthikeyan has given his reply letter dated 29.12.2007 to the appellant. The
letter which is said to be as written by the Karthikeyan JE is a created one. There is
no proof that it has been served to and acknowledged by the appellant.
6.16 The letter from A Ravi is created one on the lines of the instruction from the
AE to issue reply to the complaints. A. Ravi is the son-in-law of D.Munivel and
relative to Raja and velu who are the defendants/respondents in 3 suits in which he
was the Plaintiff and the suits are pending before DMC Pallipat, Tiruvallur Dist.
6.17 The JE Karthikeyan did not give any such letter dt.5.1.2009 to the appellant to
stop the work and issue application to change the transmission supplies. There is no
proof at all for having served the same to the appellant. This letter is also created
one to reply complaints.
6.18 Thiru. Karthikeyan, JE, had never given complaint to RK Pet Police Station.
This letter also a created one. No evidence and proof enclosed. No CSR received .
In case of accidents, he might have reported the fact, as per the code rules to all
the higher officials( vide TNERC 2005 section 12 cognizance of the offence and the
intimation of the accidents (from time of service of notice) Rules 2005).
11
6.19 No disturbance happened for the supply to the neighbours as well as to the
appellant’s house. The service connection for the appellant’s house is 331. copy of
the meter reading card already enclosed and the same may please be referred to.
6.20 It is true that the appellant has submitted letter to the JE karthikeyan for
removal of the deadlines. But, Karthikeyan never gave any letter to the appellant .
No evidence and no proof for having delivered such a letter to the appellant . This is
also a created one for giving reply to the complaints.
6.21 Thiru. Karthikeyan has served in EB section for about seven years
continuously and he went on leave at the beginning of the year 2013. From the year
2006 he has been incharge of Erumbi EB section. There is no single
correspondences at all from him to the appellant. The appellant only sent many
correspondences to the JE Karthikeyan and no single reply got from the JE.
7. Hearing held by the Electricity Ombudsman :
7.1 In order to enable the Appellant and the Respondent to put forth their
arguments in person, a hearing was held before the Electricity Ombudsman ON 7-8-
2014. Appellant informed that the counter was served to him only on 6-8-2014 and
hence prayed for an adjournment to study the counter. Accordingly the hearing was
adjourned to 20-8-2014 and further hearing was conducted on 11.11.2014.
On both the days of hearing, the Appellant himself attended the hearing.
Thiru B. Sathish, Assistant Engineer / O & M, Erumbi & Thiru K. Raja, Junior
Engineer / O & M, K.K. Kandigai have attended the hearing on behalf of the
Respondent.
8. Argument of the Appellant:-
8.1 Thiru K. Kathirvelu, the Appellant herein has attended the hearing and
presented the case.
8.2 He reiterated the contents of the petition.
8.3 He argued that he paid Rs.47,300/- under protest.
8.4 The Appellant citing G.O.Ms. No. 7 Energy (C3) Department dated 23-2-2005,
argued that the shifting works would have been done at the expenses of
TANGEDCO as the Erumbi Village Panchayat has passed a resolution to the effect.
12
8.5 He also argued that the DCW estimate was prepared without consulting him.
Further, he argued that he has not given any consent for shifting the lines under
DCW.
8.6 He also argued that the 3 Ø, 4 wire Electric line passing over the adjacent
house of his premises was now removed without collecting any cost from the
adjacent house owner. Hence, argued the same benefit shall be given to him also.
8.7 He also argued that the existing 3 Ø wire was changed to single phase
electric line while shifting the line. Hence argued due to shifting of line, the existing
facility of 3 Ø, 4 wire was taken back and only a single phase line was provided.
8.8 The Appellant informed that he has not raised the issue of refund of
Rs.32,200/-paid during 2006 in the CGRF. Hence, agreed to drop the above prayer
as the prayer which was not raised in the lower forum cannot be raised in appeal.
8.9 On 11.11.2014 he informed that the shifted line was changed as 3 Ø, 4 wire
line while effecting 3 phase supply to his application submitted on 9.9.2014 Hence,
the facility which was given before shifting was restored now. Hence, he say that he
is dropping the prayer on the above issue also.
8.10 Regarding the estimate for Rs.47,300/- he pointed out the following defects
stating that his arguments on the defects in estimate are without prejudice to his
argument that he need not pay the shifting charges as has not requested for the
shifting on DCW basis.
(i) The shifting of lines between Loc 1 & 2 is not warranted as the same was
available in the vacant place of his premises and the above line was also erected
during 2006 under DCW after collecting Rs.32,200/- from him. As any new
construction was not done on the above area, the horizantal clearance issue now
raised by the respondent is only to justify the estimate. If the horizontal clearance is
really less than the requirement then the respondent have erected the line wrongly
while executing the work during 2006. Hence, he cannot be held responsible for
licensee mistake. He also furnished the copy of the plan sanction in support of the
above argument.
(ii) As per the DCW estimate sanctioned at location 1 provision has been given
for two RCC poles but only one pole was erected. Hence, the cost charged from
him is wrong. He also informed that the erected pole is leaning for want of support.
(iii) The charges of contingences at 3 %, storage at 3 % Transport & labour at
30% estimate and supervision charges at 22% are wrongly adopted.
13
(iv) Dismantling cost of Rs.27,919/- claimed is false. There was no dismantling
between Loc 2 to 3, 3 to 4 and 4 to 5. The lines were already dismantled by the EB
officials during 2009 itself.
(v) He also pointed the difference in span length adopted in between the
DCW estimate sanctioned during 2006 & the DCW estimate sanctioned now.
9. Argument of the Respondent:-
9.1 Thiru Sathish, Assistant Engineer / Erumbi attended the hearing and putforth his
arguments.
9.2 He reiterated the contents of his counter.
9.3 He argued that the Electric line which was passing over the premises was
damaged while the Appellant was doing his construction works. Hence, the
appellant has to pay the damage cost. Further, as the line damaged by the
Appellant was feeding other consumers also alternate feeding arrangement was
made to feed the other consumers as requested by them pending payment of the
damage cost by the Appellant.
9.4 The Assistant Engineer argued that the shifting of line done during 2006 was
based on the request of the appellant only and he has also thanked the concerned
officers for completing the work. Hence, claiming to refund the above amount is not
justifiable.
9.5 The Assistant Engineer also informed that the existing three phase line was
changed to single phase as it is feeding the consumer, who are availing single phase
supply only. He however informed that it will be converted as 3 Ø, 4 wire line
whenever, an application was made to avail a three phase service by any consumer
in that area.
9.6 He also argued that while shifting the lines passing through the premises of the
Appellant, the lines between location 5 to 7 has also to be removed as there is no
possibility to erect stay or strut pole at location no.6. Hence, he argued that the
dismantling of the lines from 5 to 7 is only due to technical reasons and not for
favouring any other consumers.
9.7 On 11-11-2014, the Assistant Engineer / Erumbi informed that as there was
objection to erect a strut pole a stay was erected in location no.1 and the same will
be taken into account while closing the work order. The respondent also argued
14
that the distance between location 5 to 9 will also be checked and the correct span
length will be adopted in the work order closure. He also argued that the estimate
as per actuals will be worked out while closing the work order.
9.8 Regarding the materials that are available at location 2 to 5, the Assistant
Engineer argued as no material was available at present, the cost of such materials
were included in the estimate. He also argued that the charges towords
contingencies, storage transport and labour included in the estimate are as per the
procedure in vogue only.
9.9 The Assistant Engineer / Erumbi also informed that as per the direction of
CGRF only the estimate for shifting of line available in the Appellant’s premises was
prepared and as the Appellant has paid the amount the works were executed and
the services were effected.
10. Findings of the Electricity Ombudsman:
10.1 In the appeal petition the Appellant has made seven prayers out of the seven
prayers the following prayer have already been met by the licensee.
(i) Restoring the conveniences and facilities which were available to the
complainant as was existing before the execution of DCW on 15-4-2014.
(ii) Copy of DCW estimates pertaining to the shifting done under DCW during
2006 and the shifting done during 2014.
10.2 The Appellant in his letter dt. 6.10.2014 has also stated that the following are
the balance prayers. Hence, I am taking the above prayer only for issue of orders.
(1) Refund of Rs.47,300/-
(2) Granting the same concession which were rendered to his immediate
neighbours in removing the entire 3 phase 4 line transmission system over their
house and plots without any payment.
(3) Granting the same concession which were rendered to his immediate
neighbours in removing and modifying the 4 line 3 phase transmission line into 2
line single phase system over the house and plots of his neighbours.
(4) The defendant will furnish the authority under which two operations were
executed by him.
(5) Granting maximum compensation within the powers of Tamil Nadu Electricity
Ombudsman.
15
(6) Advising and warning the executive staff concerned in the level of Assistant
Engineer / Junior Engineer in EB section Erumbi village involved to create such a
Consumer Grievance appeal etc.
The findings are discussed below in prayer wise.
11. Prayer 1 to 3:
11.1 All the three prayers are essentially one prayer only (i.e) refund of Rs.47,300/-
paid by the Appellant towards shifting of line. The prayer 2 & 3 are only arguments
in support of the first prayer.
11.2 The Appellant argued that he has not given any oral or written request for
shifting of the lines under DCW. The licensee only prepared estimate under DCW
and collected the amount which was also paid by him under protest.
11.3 He argued that there is no need to shift the line between location 1 to 2. He
further argued that the above line was erected during 2006 under DCW and there is
no change in the structure. If shifting is necessary due to inadequate Horizontal
clearance then the first erection itself is wrong. He also furnished the approved
plan in support of his argument that there is no change in the structure.
11.4 He also argued that no transmission line was existing between location 2 to
location 5. These transmission lines were dismantled and removed by the EB
officials in the year 2009 itself. The EB officials have agreed that they have
transmitted power from location 2 to other consumers through alternate route.
Hence, the line from location 2 to location 5 is not a live line and already removed by
EB staff by themselves. Hence, no charge shall be made for that work which was
not executed now.
11.5 The Respondents argued that the Appellant has damaged the line passing
through his premises during his construction works and has not paid the damage
cost to the licensee.
11.6 As the Appellant has not co-operated in restoring the damaged line, the other
consumers were given supply through the alternate route. The transmission line
from location 2 to 5 were not removed by the licensee. As the line was passing over
the building of Appellant, the line cannot be removed without the permission of the
Appellant. As the lines are available within his premises, the Appellant is
responsible for safe custody of the above lines. As they are not available now, the
cost of such materials were added to estimate.
16
11.7 The Respondent also argued that on 4-1-09 while construction works were
carried out in the above premises, the LT line and a pole were damaged due to fall of
the rod and the concrete wooden plank on the line.
11.8 The Appellant was informed to pay the damage cost and also to seek
diversion of line on DCW basis. But the Appellant has not paid the damage cost,
hence a complaint was made against him in R.K. Pet police station on 6-1-2009.
Further, in order to restore supply to the other consumers the Jumper at location 2
and 5 have been cut and supply restored to the consumers in an alternate route.
11.9 The respondent also argued that the Appellant has requested for shifting of
line that are passing through his premises at Boards cost by citing the G.O. (Ms) No.
7 energy C3 dt. 23-2-2005. But, as the above G.O. is for village panchayat which
are financially weak, the Appellant was requested to obtain a letter from the Collector
in this regard. But, the appellant has not produced any such letter from Collector.
11.10 On a careful analysis of the arguments putforth by rival parties, it is observed
that a 3 ph 4 wire line was crossing the premises of the Appellant and it was in
service upto 4.1.2009. Only on 4.1.2009, due to falling of the rod and concrete
wooden plank, the above line has been damaged and a pole was also damaged. It
is also observed that the Appellant was requested to pay the damage cost and
shifting of line under DCW on 21.1.2009. But it is seen that due to interruption of
supply to other consumer, the line damaged and passing through the Appellant’s
premises was left as such and supply to other consumers were made through an
alternate route after cutting the jumper at location 2 & 5 on 6.1.2009. The cutting of
jumpers at location 2 & 5 made the line passing through the Appellants premises as
dead lines. The Appellant has written a letter to the JE / Erumbi to remove those line
also at Boards cost citing Government GO on shifting of lines in village panchayat
area.
11.11 But the JE / Erumbi has intimated the shifting of line will be done if the
consumer is willing to pay the estimate cost (or) if a letter is obtained from the
Collector that the Panchayat is a financially weak to bear the cost of shifting.
11.12 From the above letters, it is construed that there was a 3 ph 4 wire line
passing over the building of the Appellant and it was cut due to the construction
works carried out by the Appellant and the Appellant has not paid the damage cost
to restore the damaged line and the licensee has made alternate arrangement to
17
supply the other consumers who have suffered due to the above line cut. Due to the
act of non payment of the damage cost, the line passing through the premises of the
Appellant was allowed to be without supply. The licensee’s local JE at the time has
not taken action to intimate the estimate amount and to collect the cost and to
restore the line.
11.13 As keeping the line in dead condition is advantageous to the Appellant he has
not paid the damage cost. But the silence of the concerned section officer to take
appropriate action to recover the cost and to restore the damaged line is not
explained and it is only negligence of duty. But the licensee has taken the issue on
hand only when the Appellant sought service connection for his premises.
11.14 Regarding shifting of line, I would like to refer regulation 5(6) of the Supply
Code, which is extracted below : This regulation was amended subsequently in
notification No.TNERC/SC/7-36, dt.1.7.2014. However, as the shifting was done
prior to 1.7.2014, the regulation in force at that time was extracted below :
“5. Miscellaneous charges xxx xxx xxx xxxx xxx xxxx (6) Service / line, structure and equipments shifting charge. (1) The cost of shifting service / line, Structure and equipments] shall be borne by the consumer. The consumer shall pay the estimated cost of shifting in advance in full. The shifting work will be taken up only after the payment is made. The estimate will cover the following: i. Charges for dismantling at the old site. ii. Charges for transport from the old site to the new site. iii. Charges for erection at the new site. iv. Depreciation on retrievable old materials, if any, not re-used at the site. v. Cost of new materials, if required including transport. vi. Cost of irretrievable materials. vii. Overhead charges. (2) Temporary dismantling and re-erection or shifting of a service connection within the same premises necessitated due to remodeling of premises will be carried out on payment of the required charges for the same. (3) Shifting of an existing service connection involving change in door number or sub-door number or survey field number, shall be considered as a new service connection only. No shifting of an existing service connection is permissible unless all arrears in the service connection are paid, if so demanded by the Licensee.” 11.15 On a careful reading of regulation 5(6) of the Supply Code, it is noted that the
cost of shifting service/line structure equipments shall be borne by the consumer.
The consumer has to pay the estimated cost of shifting in advance in full. The
shifting work will be taken up only after the payment is made. The costs that are to
18
be included in the estimate was also given in the regulation. But, there is no
provision to exempt the shifting cost if the village panchayat is seeking the shifting in
the above regulation.
11.16 As there was a line passing through the premises, and the line was damaged
by the consumer, it is the duty of the consumer to pay the damage and rectification
cost. Had it been paid, the line would have been restored and the line would be a
live line from location 2 to 5. Further, as the lines are passing over the building, they
are to be removed on safety grounds. As the construction was done after laying of
the lines, the consumer has to be bear the cost for shifting. Hence, I am of the view
that the cost of line shifting has to be borne by the Appellant only. Had the line been
dead due to the act of the licensee in changing the route of the line, then, the
licensee would have removed the line also at its cost. But in the case on hand, the
line was damaged by the Appellant while carrying out the construction works and his
failure to pay the damage and rectification cost only resulted in keeping the line as
dead. Hence, the Appellant cannot claim that for removing the dead line he need not
pay the charges.
11.17 The Appellant’s contention is that the village panchayat has given resolution
to the effect of shifting the above line and as per G.O.M.S. No.7, Energy Dept,
dt.23.2.2005, the Board has to be bear the cost.
11.18 The respondent argued that the Appellant was informed to produce a letter
from the collector to the effect that the above panchayat is financially weak.
11.19 As the Appellant has cited G.O.No.7, dt.23.2.2005, the relevant para of the
G.O. is extracted below :
“ xxx xxx xxx xxx xxx xxxx In regard to cost of shifting works required by the Corporation, Municipalities and Town Panchayats, those expenditures should be borne by them provided the Tamil Nadu Electricity Board while preparing estimates for works should fix over heads charges only at 7.5% covering all items such as centage, storage, etc., The concession of fixing this charges of 7.5% is applicable only for the above mentioned local bodies. In regard to Panchayats, Panchayat Unions, shifting expenditure should be brone by Tamil Nadu Electricity Board itself as these institutions are financially weaker. xxx xxx xxx xxx xxx xxxx”
19
11.20 On a careful reading of para IV, of the G.O., it is noted that in respect of
Panchayat & Panchayat Unions shifting expenditure should be borne by the Tamil
Nadu Electricity Board itself as these institutions are financially weaker.
11.21 Here, the line to be shifted is passing through a individuals (Appellant’s) land
and not through a premises owned by panchayat, and as per regulation 5(6) of the
Supply Code, the cost of shifting service/line structure equipments shall be borne by
the consumer and there is no provision to exempt local body from payment of
shifting charges. As there is no provision in the regulation to exempt anybody from
payment of shifting charges, I am, unable to accept the argument of the Appellant
that , Board has to be meet the expenditure of the shifting charges.
11.122 Another argument putforth by the Appellants is no shifting charges was
collected from another consumer for removal of lines passing over his house and
plot by the respondent and hence he argued that he shall also be given the same
concession (ie) shifting of line is to be done without collecting any charges from him.
11.23 In this aspect, the respondent argued that due to technical reasons (ie)
unable to provide either strut pole or stay at location 6, the lines passing over the
adjouring premises were removed. As the removal of lines passing over the other
consumers premises was not due to the concerned consumer/individuals request
but due to technical reasons, the charges was not claimed from them. He also
argued that the clearance between the line and the premises in the said case are
as per electricity rules and there is no safety constrains also.
11.24 As the lines passing over the other consumer’s premises was removed
without any request from the concerned individuals and the existing lines are also
said to be safe, I am in agreement with the respondent that, if the shifting of line is
attributable to licensee, then the consumer need not pay the shifting cost. But, in
this case, the shifting is not done by the licensee on its own accord but due to
shifting of line passing over the Appellant’s premises. Hence, any work which was
carried out to fulfil the shifting of lines passing thro the Appellant’s premises has to
be borne by the Appellant only. But, at the same it has to be confirmed whether the
reasons explained by the respondent to remove the lines passing over the adjacent
premises is for bonafide reasons.
11.25 In view of the discussion, in the previous para, the Superintending
Engineer/Kancheepuram EDC is directed to depute an officer from other Division to
check whether the removal of lines between location 6 to 7 and 7 to 8 is for
20
bonafide technical reasons warranted due to site condition as argued by the
respondent and to take appropriate action based on the inspection report.
11.26 On the review of the estimate sanctioned for Rs.47,300/- it is noted the
estimate is not prepared as per regulation 5(6) of the supply code. Hence, the
Respondent is directed to prepare the estimate as detailed in regulation 5(6) of the
supply code. Further while preparing the estimate, the non provision of strut pole
and provision of stay set and the actual works executed, at ground reality may be
taken into consideration. After revising the estimate as per regulation 5(6) of the
Supply Code, as per actuals, the balance amount if any shall be refunded to the
appellant if the amount collected is more than the estimate prepared as per actuals.
Similarly, if the amount already collected is less, the balance amount may be
collected from the appellant.
12. Prayer -4 :
12.1 With regard to removal of line passing through other persons land, the
respondent argued that after removing the line at location 5 which is in the premises
of the Appellant, the pole at location no.6 needs support (i.e) either a stay or strut
pole has to be erected. But the land is private and the land owner has objected for
either erecting a strut pole or stay in the above place. Hence, due to site condition,
(i.e) on technical ground, the line passing over the adjacent premises was removed.
12.2 As the respondent has intimated that due to technical reasons, they are
forced to remove the line, I am of the opinion that, the Appellant can not seek such
facility for him also.
12.3 As the shifting estimate was sanctioned by Assistant Executive Engineer,
which cover the dismantling of the line passing over the adjacent owner’s premises, I
am of the view that the shifting is approved by Assistant Executive Engineer / O & M.
13. Prayer-5:
13.1 The Appellant prayed maximum compensation within the powers of Tamil
Nadu Electricity Ombudsman even though he has requested a compensation of Rs.5
lakhs in the original prayer.
13.2 In this connection, I would like to refer regulation 7(11) of the regulation for
CGRF & Electricity Ombudsman which is extracted below:-
“7(11) In respect of grievances on non implementation of standards of performance
of licensee on consumer service specified by the Commission under section 57(1) of
21
the Electricity Act 2003, if the forum finds that there was default of the licensee, it
shall only hold that the consumer is entitled to the compensation and shall state that,
the consumer if agreed, can accept the compensation prescribed by the Commission
in the relevant Regulations”.
13.3 On a careful reading of the said regulation 7(11) of CGRF & Electricity
Ombudsman it is noted that in respect of Grievances on non implementation of
standards of performance of licensee on consumer services specified by the
Commission under Section 57(1) of the Electricity Act 2003 alone, the CGRF &
Electricity Ombudsman can hold that the consumer is entitled for compensation.
13.4 As there is no provision to order compensation other than the one discussed
in para above, I am not issuing any order on the above issue.
14. Prayer 6:
14.1 The duty of the Electricity Ombudsman is to receive the appeal petition
against the order of CGRF and settle the issue through conciliation and mediation
between a licensee and the aggrieved parties or by passing an award in accordance
with Act and rules or regulations made thereunder.
14.2 Hence, I am of the view the Electricity Ombudsman can only settle the issue
between the licensee and an aggrieved consumer and it is the duty of the licensee to
take action if any needed on his employees based on the order of the Forum or
Electricity Ombudsman.
15. Observation:
15.1 It is noted that there was a damage of line and pole done by the Appellant on
4.1.2009. But the licensees officer has not taken any action to collect the damage
cost and restore the damaged line. The alternate route was kept in service without
taking any action to restore the power supply on the original route and no approval
was obtained to supply the other consumer through alternate route. Though supply
was restored to other consumers through alternate route, no action was taken either
to rectify the damage and restore supply on the route already available or get
approval to maintain the supply on the alternate route. The officer on duty has not
taken any action to recover the damage cost from the consumer but raise the issue
22
when he applies for a new service after a lapse of 3 years. Because of the above
act only this dispute has arisen. The Superintending Engineer/Kancheepuram EDC
may take suitable action to avoid such occurrences in future.
16. Conclusion :
16.1 (i) In view of my finding is para 11, the respondent is directed to prepare
the DCW estimate for shifting as per regulation 5(6) of the Supply Code. Further,
while preparing the estimate as per actuals the non provision of one pole at location
no.1, and provision of stay set etc as per the execution alone has to be taken into
account. If the estimated amount is less than the amount already paid by the
Appellant the balance amount has to be refunded to him. In case, the estimate cost
is more than the amount already paid by the Appellant, then the balance amount has
to be collected from him. The above exercise has to be completed within a month
from the date of this order and a compliance report shall be sent within 45 days
from the date of receipt of this order.
(ii) With the above findings, the A.P.No. 37 of 2014 is finally disposed of
by the Electricity Ombudsman. No Costs.
(A. Dharmaraj) Electricity Ombudsman To 1) Thiru K.Kathirvelu, B.E., No.54, Kamaraj Nagar, Sholingur & Post, Vellore District, Pincode 631 102 2) The Assistant Engineer / O & M, Erumbi Village & Post, Kancheepuram Electricity Distribution Circle Pallipat Taluk, Thiruvallur District, Pincode – 631 302. 3) The Chairman, (Superintending Engineer) Consumer Grievance Redressal Forum, Kanchipuram EDC, TANGEDCO (formerly TNEB), Olimohamedpet, Kanchipuram-631 502
23
4) The Chairman & Managing Director, TANGEDCO, NPKR Malaigai, 144, Anna Salai, Chennai – 600 002. 5) The Secretary Tamil Nadu Electricity Regulatory Commission No.19A, Rukmini Lakshmipathy Salai Egmore, Chennai – 600 008. 6) The Assistant Director (Computer) - FOR HOSTING IN THE TNEO WEBSITE PLEASE Tamil Nadu Electricity Regulatory Commission, No.19-A, Rukmini Lakshmipathy Salai, Egmore, Chennai – 600 008.