TB 11.01.07 Peter Glässel, Heidelberg 2
Outline
Last pre-commissioning items:OROC corner noise studied Optimum grounding scheme was determined
20 ground cables per sector exchanged by thicker ones
Elevated noise in corners (was 5 adc cnts typ.) completely removed!Implemented in 2 days in a heroic effort of Luciano’s teamFEE of all sectors retested in a dry run after closing covers
TPC ‘travel-ready’ before X-masPreparations in SXL2 Jan 4/5 (open clean room …) Transport to SX2 Jan 8/9Jan 10: remove ventilation duct in shaftTransport to cavern right nowTPC test drive to IP and back to parking till end Jan
TB 11.01.07 Peter Glässel, Heidelberg 6
Outlook: Installation in cavern
Detailed planning for installation sequence in UX2 existsabout 20 days needed for alignment and ‘test drive’ of TPC to IP until in ‘parking position’
Commissioning in situ after ITS installation (May 07)Starting on C-side (services available)
Temporary services for gas sys on A-side