technical, engineering and maintenance - hidlor's · technical, engineering and maintenance...
TRANSCRIPT
[email protected]&12/29/2009
Introducing……………. T E A M
Technical, Engineering And Maintenance
Bengaluru International Airport Limited
Maintenance Divisions -
Airfield Civil
Airfield Electrical
Wildlife Control
Power System
Landside Building & Electrical
Horticulture and Landscaping
Services ( C & WD)
Water Supply System
Vehicle & Equipments
Mechanical Maintenance
Material Management
/ Copy
/ Circ
ulatio
n
Technic
al, Engin
eering &
Main
tenance D
epartment
CONT
ROLL
ED COP
Y
BENGALU
RU INTE
RNATIONAL
AIR P
ORT LIM
ITED
1
2
3
4
5
6
7
8
Team - Airport Maintenance Department
To achieve SQL of 4.2 out of 5 by committing 100% serviceability of airport systems & passenger facilities
and by enhancing the airport ambiance through continuous improvement on maintenance practices.
To ensure Zero Downtime of all critical airport systems by ensuring proper redundancy, implementing the
PM tool and reducing the response time to attend maintenance calls.
To work towards achieving zero accidents and zero incidents by improving the working conditions,
conducting awareness programs and pledging against any compromise on safety regulations.
To improve the work process by bench marking practices in task scheduling, documentation, training,
communication and internal audits.
To adopt Reliability centered maintenance practices by embracing modern techniques and strategies.
To win the trust and confidence of all internal and external customers through proactive, systematic and
customer oriented approach in problem solving.
To ensure 100% compliances to all statutory obligations.
To improve the discipline and Organizational Culture of TEAM for better recognition by external members.
To develop a dazzling team spirit through open communication, personnel development programs and
team building internal workshops.
To strengthen the trust and confidence level among team members through periodical performance
review, frequent counseling to improve the areas of weakness, delegating responsibilities and defining role
clarity.
To adopt collective responsibility for success and failures by developing leadership skills at all levels,
participative management, encouraging free expression of ideas and discouraging internal politics.
To adopt sympathetic approach to personal problems, not to deny the employee’s rights or natural justice,
allowing free expression of employee problems and practicing freedom to escalate unresolved issues.
To spread TEAM logo and slogans, publishing internal journal, organizing get together and recreation
activities.
Page 2
1
2
3
4
5
6
7
8
Page 4
Team - Introduction and Significant Activities
Team - Airport Maintenance
Technical, Engineering and Maintenance Department is responsible
for maintenance upkeep as well as for the post AOD (Air port operation day)
construction activities, with updated design, as per suggested amendments to increase
the service level in the air port. They also perform critical daily operations involved with
utility services in which experienced technical engineering staff is engaged to handle
highly advanced systems & machineries installed at the airport. Team is a care taker of
Bengaluru International air port. Their maintenance activity covers complete 4000
acres of land area as required to be maintained as per international regulations, It
includes air side as well as land side responsibilities. The activities for upkeep has
special focus on runway, taxiway, aircraft stands at apron, runway lighting system,
High Voltage power network, air side nav-aid buildings and operation/ serviceability of
the equipments installed in it, land side roads, parking, centralized HVAC for almost all
buildings. The area of activity not only covers operation/providing of utility services
( like water supply, rain water storm water drains, sewage collection and treatment,
power supply to buildings, fire water pumping ) but also keeping the service level high.
The departmental activities are not limited to Infrastructural engineering installations
but main elements of great concern in daily air port operation like nature conservation
& greenery, prevention of bird strike & cleaning, wild life conservation also.
Team has taken up initiatives in making group of expert engineers working on
Making of specifications, Team LEED Certification, Team ISO, Team SAP PM
implementation, Team - social activity and many more. Team Engineering has
prepared specifications focusing on generalized project requirements. The stand alone
document gives detailed technical information of the requirements of BIAL. It not only
gives work description but also will be referred in future for confirming the quality
checks also.
Runway maintenance, is one of the main weekly maintenance activity
performed on the airport covers almost all critical area.
1
2
3
4
5
6
7
8
[email protected]&12/29/2009
Page 5
System Upkeep as per Maintenance
Manuals, SOP’ s & EOP’ s
- Leading ahead the success story
Runway Maintenance
Team - Airport Maintenance
1
2
3
4
5
6
7
8
Weekly maintenance activities like runway
maintenance are performed as per described
protocols, guidelines as mentioned in Annexure of
Aerodrome maintenance manual. Aerodrome
Maintenance Manual is a guiding documented
protocol for the Maintenance Department
personnel of Bangalore International Airport in
ensuring effective maintenance of various airport facilities in a condition which does not
impair the safety, regularity or efficiency of air navigation. Preventive maintenance
programs and procedures have been worked out in line with the recommendations of
Annexure 14- Chapter – 10, DGCA Civil Aviation Requirement, Series ‘B’ Part I- capter
-10 and ICAO Airport Service Manual Part9 -
Airport Maintenance Practices. Various
recommendations of ICAO design Manuals,
Various FAA Series 150 Advisory Circulars,
Indian Electricity Rules, Various IS Publications,
Industry standards, Local regulations etc have
also been adhered to while deriving various
preventive maintenance schedules.
Subsequently, 18 Aerodrome Maintenance Manual containing detailed equipment
descriptions, maintenance procedures for various facilities, equipment, system,
buildings etc. were also in practice since February 08.
Maintenance manuals contain thorough details of the respective area of
operation of the respective division. They also cover the need of co-ordination/ co-
operation among various divisions required for performing an activity. The clear cut
picture of activity execution in the form of standard operating procedure, Emergency
Team - Airport Maintenance
Page 6
Over & above
Special points Under
Execution :-
Weekly Runway Mainte. between 12.30Hrs to 15Hrs on every Saturday.
Cleaning and painting
A i r f i e l d t u r f maintenance
Pavement repairs/ layer replacement
Shoulder and basic strip maintenance
Surface dist ress m a p p i n g , c o r e cutting, evaluation, testing .
A i r f ie l d l i gh t ing system maintenance
De-briefing session: Observations, status review and planning for next week.
operating procedure not only completes the desired work in limited time but also
gives the rated quality level as per international standards of air port operation.
More than 500 Standard Operating Procedures (SOPs) and Emergency
Operating Procedure (EOPs) have been published and implemented so far. All
SOPs and EOPs are part of Maintenance Manual- Annexure as Appendices.
Runway maintenance is one of them. The closure of runway maintenance is not
an innovative work but it combines close inspection of all parts of runway civil
works, painting and markings, air field lightings with the suggestions. The activity
incorporate - successful reform produced from the time tested solutions, - The
corrective feeling of enthusiastic engineers given ideas and to familiarizes
contractual work force with the critical nature and type of work available. It also
strengthen the installations as some times observed weakening due to balance
works of installation contractor left un-attended because of minor in nature, non
priority item, lack of supervision.
In the run way maintenance activity a complete fleet equipped with modern
equipments, preplanned/ perfect co-ordination among various divisions execute
Runway Maintenance…...
In spite of the regular
maintenance activity
“The TEAM
divisions are currently
working on prestigious
projects like LEED
CERTIFICATION,
ISO CERTIFICATION,
SAP PM
IMPLEMENTATION
also"
Cleaning Activity
Turf maintenance
1
2
3
4
5
6
7
8
it, in the targeted time span. It is a type of activity
performed weekly on runway in which
Pavement repairs/ layer replacement
Surface distress mapping, core cutting, evaluation,
testing
Cleaning and painting
Airfield turf maintenance
Shoulder and basic strip maintenance
Airfield lighting system maintenance are performed
mainly.
Turf is maintained at
Airs ide unpaved
areas to have
reduction in Air
contaminates & toxic particulates resulting the air craft movement in dust free
atmosphere. Mowing & trimming are the key activities performed weekly during
runway maintenance slot. Mechanized Cleaning is the primary requirement
fulfilled under close supervision not only peeks up foreign objects from runway &
taxiway but also gives dust free atmosphere during cleaning. The runway
[email protected]&12/29/2009
Team - Airport Maintenance
Runway Maintenance…...Debriefing & Return
Pavement Repair
Shoulder & Basic strip
Maintenance
Surface distress mapping
Airfield lighting maintenance
De– briefing Session
Page 7
Layer Replacement
1
2
3
4
5
6
7
8 maintenance team is equipped with Ultra high
pressure water jetting system (Track jet) for
rubber removal. The optimum friction characters
for safe operations is the deciding
factor of rubber removal /cleaning
of runway. Pavement repairs/
layer replacement work is an activity performed under supervision of airside civil division. The smooth
surface finish and friction values are the denominators. High level co-ordination between expertise and
machinery operators have been established to made available all the equipments / raw material at site on
time during the runway maintenance slot. Execution as well as supervision of multiple work in a pre
decided time is a common phenomenon among teams participating in runway maintenance. Shoulder and
basic strip maintenance is also a need of
time after the rainy season. It requires heavy
earthwork with proper spreading, leveling and
compaction in predefined span of time. Close
supervision for surface distress
mapping, core cutting (if required),
evaluation and testing are the parallel
activities to improve the sustainability. It
will be a key factor for deciding the
implementation strategy and direction of resource mobilization. The weekly runway maintenance work also
has Airfield lighting maintenance as one of the regular activity performed. A team equipped with testing
equipment is deployed to check healthiness of runway lighting system. A team of technicians & engineer
works here on runway to maintain the
serviceability as 100%. A 2.5 hour runway
maintenance session ends with
a De-briefing session to share
the observations, status review and planning for the next week. The details about the teams are as
enclosed next page onwards -