  • Technical Seminar

    Experience Sharing for

    Implementation of Multi-Function

    Heat Pump in Hotel

    Joinly organized with AMC, CAD & EVD, HKIE

  • Dr. Wong Kaixuan

    Be engaged in heat energy and cooling study from 1990 to 1994,

    University Stuttgart.

    Dissertation on heat pump study for the Doctor Cours

    Professor, NEU, 1994 to 1997.

    Chief engineer, Guangdong 吉荣空调公司,1997-1999.

    General manager of Central A/C Dep., Zhuhai Gree (格力空调), 1999-

    2001.

    To found Zhuhai Boka Cool Source Equipment Co., Ltd., 2001 – Now.

  • Mr. Roger Lee

    Hong Kong Polytechnic graduate in BSE, 1989

    More than 10 years hotel operation experience

    More than 20 years working experience

    Member of CIBSE

    Project Director of ECO Green Energy Saving Company

  • Hotel Energy AnalysisCooling

    Others

    Hot Water Lighting

    60%

    15%15%

    10%

  • Typical Design(most of the Hong Kong hotel design)

    Chiller BoilerTo provide air conditioning

    To provide hot water year round

  • Average around 5%-10% increase per year(http://www.mongabay.com/images/commodities/charts/crude_oil.html)

  • Lastest Design in the past 10 years

    Chiller Heat Pump

    - To provide air conditioning

    - To provide 40 degree hot water

    - To provide 7 degree chilled water supply for air conditioningin summer only

    Boiler

    - To re-heat hot water to 50 – 60 degree for hot water use in Summer

    - To provide 50 – 60 degree hot water supply in Winter

  • Obviously this system cuts the energy cost.

    BUT

  • Complicated system

    Heat pump always operated in fully heat recovery mode

    On non-peak hours hot water consumption, heat pump will be easily hunting

    On/Off heat pump will disturb the central A/C system

    Large invesment

    More space requested

    High maintance cost

    Heat pump cannot 365 days operate to provide lower hot water production cost

    Weaknesses

  • Any other choice?

  • There is a new equipment

  • Hot water energy cost comparison

    (based on hotel in Kowloon, average temperature rise at 35 degree year round)electric tariff 1.0/KWH, diesel $8.2/litre, town gas $0.265/MJ

  • Multi –function Heat Pump SeminarCIBSE Hong Kong Branch / HKIE Building Services Division /

    ASHRAE Hong Kong Chapter / Boka Cool Factory

  • ZhuHai Holiday Resort Hotel (珠海渡假村)

  • Water Type (Dual Function) Heat Pump / Chiller(Cool only OR Cool/Heat Simultaneously)

  • Technical Talk - Multi-Function Heat Pump

  • Photos of Doctor Wang (Boka Factory)Mr. M.K. Liu (CIBSE Hong Kong Branch)

    Mr.Roger Lee (ECO Green Energy Saving)

  • Multi-Function Heat Pump, R134a(Cool only OR Cool/Heat Simultaneously OR Heating only)

  • • Cooling mode only (act as an air cooled chiller) to provide 7℃ chilled water supply

    • Cooling & Heating mode (act as water to water heat pump)to provide 7℃ chilled water supply and 50℃ hot water supply

    • Heating mode only (act as air to water heat pump) to provide 50℃ hot water supply

    It integrates an air cooled chiller, water to water heat pump and air to water heat pump into one body to perform :

  • Job Reference

  • Job Reference

    真善美大酒店4星级 江門逸豪五星級酒店

    萬方金莎酒店(河南焦作)

  • 序號 用戶名稱 地區

    1 珠海市婦幼保健院

    醫院項目

    2 珠海市香洲區人民醫院

    3 中山三鄉人民醫院

    4 廣州醫學院第一附屬醫院

    5 廣西富川縣人民醫院

    6 珠海北京酒店

    廣東珠海

    7 珠海南灣國際大酒店

    8 珠海南油大酒店

    9 珠海益健假日酒店

    10 珠海鄉泉酒店

    11 珠海金口岸假日酒店

    12 珠海金域酒店

    13 海灣大酒店

    14 珠海益健保健中心

    15 珠海太平洋保健中心

    16 珠海華駿酒店天富健康中心

  • 序號 用戶名稱 地區

    17 香港珀麗酒店 香港

    18 澳門皇都酒店 澳門

    19 廣州珀麗酒店

    廣東廣州20 廣州歐亞酒店

    21 廣州鄉土華豐酒店

    22 廣州醫學院第一附屬醫院

    23 中山古鎮國貿大酒店

    廣東中山

    24 中山三角真善美大灑店

    25 中山東升匯景酒店

    26 中山市富華酒店

    27 中山小欖皇冠假日酒店

    28 中山市星寶休閒中心

    29 中山大三角酒店

    30 中山世紀廣場

    31 中山麗閣商務酒店

    32 中山坦洲豪益假日酒店

    33 深圳富臨酒店

    廣東深圳34 深圳麗灣酒店

    35 深圳百合酒店

    36 深圳金帝都酒店

  • How does it work?

  • Multi-function heat pump system

  • Multi-function heat pump system(MFH)

    Condensing FinHeat Exchanger

    HeatRecovery

    Condenser

    EvaporatorCompressor

    Storage Hot Water Tank

    Guest Room

    Fan Coil

    Air source multi-function heat pump Hot water system

  • Mode of Operation

    Mode A:Cooling and hot water supply in Summer

    (Partially heat (sensible heat) recovery)

    (for non-peak hot water demand period)

    Mode B:Cooling and hot water supply in Summer

    (Fully heat (sensible & latent heat) recovery)

    (for peak hot water demand period)

    Mode C:Hot water supply only in Intermittent Weather

    Mode D:Heating and hot water supply in Winter

  • Partly heat recovery(sensible waste heat recovery)

    Feature:

    In Summer, MFH operate to provide 7 degree chilled water & 50-60 degree hot water to meet the non-peak hour (00:00-19:00) hot water demand.

    Condensing Fin release waste latent heat to ambient

    Sensible heat recovered to provide

    hot water supply

    To provide chilled water supply

  • Fully heat recovery(sensible & latent heat recovery)

    Feature:

    In Summer, MFH operate to provide 7 degree chilled water & 50-60 degree hot water to meet the peak hour (19:00-00:00) hot water demand.

    Condensing Fin stop working, no

    heat will emit ambient

    Sensible & latent heat recovered to provide

    hot water supply

    To provide chilled water supply

  • Hot water supply only(for Intermittent Weather)

    Features:To produce 50-60 degree hot water supply. Reduced hot water energy cost up to 60%against electric/town gas/diesel boiler

    Condensing Fin absorbed heat from ambient.

    ambient heat (3/4) and compressor

    heat (1/4)are recovered to provide hot water

    supply

    No Cooling and Heating

  • Heating and Hot water supply(In Winter)

    Condensing Fin absorbed heat from ambient

    ambient heat (3/4) and compressorheat (1/4)are recovered to provide hot water supply

    Part of heating energy to provide

    space heatingt

    Features:To produce 50-60 degree hot water supply for portable use & 45-50 degree hot water supply for space heating. Reduced hot water energy cost up to 60% against electric/town gas/diesel boiler

  • Say a Hongkong hotel,cooling period is 10 month, daily hot water demand is 100 m3.

    Annual hot water demand:

    Case Study

  • Case Study

  • Case Study

  • Case Study

  • Besides, it reduce Carbon Emission up to 1000 Ton annually

    (compare to electric boiler, 100m3 daily hot water demand)

  • Chiller+Heat Pump+BoilerMulti-function Heat Pump VS

    Can operate 365 days year round

    Overall COP higher

    Save more than 50% annual energy cost than traditional

    Can provide stable chilled water & hot water supply

    Without disturbance to the central A/C system

    Reduce operating hours of the main chiller plant

    Provide higher hot water temperature (up to 60 degree)

    No need boiler to back up especially in Winter

    Less maintenance cost

  • Conclusion

    - Environmental Friendly

    - Reliable & Convenience

    - Energy saving

    - Save Investment & Space

    - Less Maintenance

    During selection of Equipment, it shall be taken into consideration

  • Enquiries

    Mr. Roger LeeECO Green Energy Saving CompanyProject DirectorContact Telephone 3691-8549 / 60776087Contact Email [email protected]

    Doctor WangBoka Cool Source Equipment Co.LtdGeneral ManagerContact Telephone 86-15018914061Contact Email [email protected]

  • Thanks