Technology Department

LSS2 modifications

Impact on the vacuum systems

LTEX - 18/01/2011

Eric PAGE – TE-VSC

Page 2: Technology Department LSS2 modifications Impact on the vacuum systems LTEX - 18/01/2011 Eric PAGE – TE-VSC

Technology Department

Introduction

Feasibility - Integration

Production planning

Installation planning

Conclusion

Page 3: Technology Department LSS2 modifications Impact on the vacuum systems LTEX - 18/01/2011 Eric PAGE – TE-VSC

Technology Department

Current situation 4L2, part of VACSEC A4L2.C

Insertion of a TCTVA

Arc 1-2

IP2: ALICE

Introduction

Collimator area ID800 area

Page 4: Technology Department LSS2 modifications Impact on the vacuum systems LTEX - 18/01/2011 Eric PAGE – TE-VSC

Technology Department

Current layout 4L2, part of VACSEC A4L2.C

Insertion of a TCTVA

Constraint:1. D acceptable is 1360 mm maximum2. Collimators should move along their 5th axis

Arc 1-2

IP2: ALICE

Introduction

Page 5: Technology Department LSS2 modifications Impact on the vacuum systems LTEX - 18/01/2011 Eric PAGE – TE-VSC

Technology Department

Current layout 4R2, part of VACSEC A4R2.C

Arc 2-3

IP2: ALICE

Introduction

Page 6: Technology Department LSS2 modifications Impact on the vacuum systems LTEX - 18/01/2011 Eric PAGE – TE-VSC

Technology Department

Collimator area on 4L2 side, identical on 4R2 side (outer)

new issue to solve: supports collision

Feasibility - Integration

New TCTVA

New module

New module

New chamber

Arc 1-2 IP2: ALICE

Page 7: Technology Department LSS2 modifications Impact on the vacuum systems LTEX - 18/01/2011 Eric PAGE – TE-VSC

Technology Department

ID800 area on 4L2 side, identical on 4R2 side

Feasibility - Integration

Arc 1-2 IP2: ALICE

Page 8: Technology Department LSS2 modifications Impact on the vacuum systems LTEX - 18/01/2011 Eric PAGE – TE-VSC

Technology Department

Vacuum elements necessary for inserting the new TCTVA: 4 modules and 2 chambers. Most of the components is available from the stock which needs to be completed.

Time necessary to produce these elements (from the drawings to the reception): 3 months.

Collimator area

Production Planning

TypeCorpsSouffl etSouffl etBrideBrideBrideBrideBrideInserts RFInserts RFInserts RFInserts RFInserts RFInserts RFInserts RFInserts RFInserts RFVisserie

VSR__0127VSR__0135

VSR__0011

VSR__0120

VSR__0041 OUIOUI1504

4

8

42

22

Matériel nécessaire et disponibleDisponible

10OUIOUIOUIOUIOUIOUI

4VBU__0013VBU__0060

44

VCD__0269

VMTIA0006 4 3VMTIA0002

Désignation

VBU__000284

VBU__0008 4VBU__0018

2VSR__0239

Quantité totaleA fabriquer

Quantité1010

OUIM3*6

A ouvrir

8

OUIOUI

1002VSR__0005

2VSR__0057

VSR__0137 2

OUI

Page 9: Technology Department LSS2 modifications Impact on the vacuum systems LTEX - 18/01/2011 Eric PAGE – TE-VSC

Technology Department

Fabrication of 2 new VCDG_ vacuum chamber andconsolidation of spare elements:

Time necessary to produce these elements(from the drawings to the reception):

4.5 months (the design office and the workshop should be informed 3 months in advance).

Processes:LHC database modificationDesign OfficeMechanical machining3 thermal treatmentsDegreasing before firingFinal cleaningLeak detectionMetrologyInternal transportsValidation test

Material: 4 flanges Ø 90910 m tubes ID8006 Helicoflex® gaskets4 DN150 CF4 supports for 2 tubes

Production Planning

ID800 area

Page 10: Technology Department LSS2 modifications Impact on the vacuum systems LTEX - 18/01/2011 Eric PAGE – TE-VSC

Technology Department

Steps necessary for the installation for one sector: Venting of the vacuum sector, Displacement of the moving elements (TCTH, modules, VCTY_, VCTCR, VCDGA + supports), Installation of the old support to the new location + installation of new supports (new modules), Installation of the new modules + new VCDG_ chamber, Survey of the moved and installed elements, Closing of the sector, Pumping and leak detection of the sector, Bakeout installation, Bakeout and NEG activation, Bakeout desinstallation and cleaning of the area

Time and TE-VSC team necessary to ensure the work (on one side): 1.5 months with 3 people (helped punctually by a transport team). Another team will pull the cables for controlling the new vacuum pumps + pumps and instrumentation moving (done in parallel).

Installation Planning

Collimator and ID800 area on one side

Page 11: Technology Department LSS2 modifications Impact on the vacuum systems LTEX - 18/01/2011 Eric PAGE – TE-VSC

Technology Department

Conclusion

• The new vacuum layout ensures the ZDC movement (1360 mm down to the IP).

• The new vacuum layout and special fabricated components allow the 2 collimators 5th axis motion.

Integration

• Collimators area: 3 months.• ID800 area: 4.5

months.Production Planning

• 1.5 months for vacuum sector A4L2.C.• 1.5 months for vacuum sector A4R2.C.Installatio

n Planning

Page 12: Technology Department LSS2 modifications Impact on the vacuum systems LTEX - 18/01/2011 Eric PAGE – TE-VSC

Technology Department

SPARE SLIDES

Page 13: Technology Department LSS2 modifications Impact on the vacuum systems LTEX - 18/01/2011 Eric PAGE – TE-VSC

Technology Department

4L2, database configuration, B1 (external beam line):

Current database

Modified database

New vacuum elements

Feasibility

Page 14: Technology Department LSS2 modifications Impact on the vacuum systems LTEX - 18/01/2011 Eric PAGE – TE-VSC

Technology Department

4L2, database configuration, B2 (internal beam line):

Current database

Modified database

New vacuum element

Feasibility

Page 15: Technology Department LSS2 modifications Impact on the vacuum systems LTEX - 18/01/2011 Eric PAGE – TE-VSC

Technology Department

Current situation of 4L2 and 4R2 concerning the TCTH collimator bakeout

NO JACKET

REMARK #1

Page 16: Technology Department LSS2 modifications Impact on the vacuum systems LTEX - 18/01/2011 Eric PAGE – TE-VSC

Technology Department

4L2 and 4R2 are symmetric for the integration but…The mechanical aperture is different between 4L2 and 4R2 around Y chambers:

REMARK #2.1

VMGAB

VCTNP

Apertures are 80 to 80mm

Apertures are 65 to 80 mm

VTCYD chamber

VTCYB chamber

B1 B2

4L2 4R2

IP2

Page 17: Technology Department LSS2 modifications Impact on the vacuum systems LTEX - 18/01/2011 Eric PAGE – TE-VSC

Technology Department

4L2 and 4R2 are symmetric for the integration but…The mechanical aperture is different between 4L2 and 4R2 around BPMs:

REMARK #2.2

Apertures are 80 to 80 mm

Apertures are 80 to 63 mm

4L2 4R2

VAMTKB1VAMTJ

BPMWI TCTH BPMWB

IP2

TCTH

B2

Page 18: Technology Department LSS2 modifications Impact on the vacuum systems LTEX - 18/01/2011 Eric PAGE – TE-VSC

Technology Department

How does a vacuum module (VM) looks like internally:

Page 19: Technology Department LSS2 modifications Impact on the vacuum systems LTEX - 18/01/2011 Eric PAGE – TE-VSC

Technology Department

Creation of new vacuum elements for 4L2:

• VMTBA: Collimator Module - DN100/QCF100 - 80/80 aperture is 80 mm, L=220 mm, the bellow connected on the collimator side accepts the 5th axis motion.• VMTQC: Collimator Pumping Module - DN100/QCF100 - 80/80 aperture is 80 mm, L=460 mm, the bellow connected on the collimator side accepts the 5th axis motion.• VCRLP: Vacuum - Chamber - Circular - Long Straight Section - ID67 - OD70- Type LP - QCF100/QCF100 aperture is 67 mm, L=3800 mm.

Integration issues:

• The connections of QCF100 (DN100 conical flanges) require space for a MKT collar: Ø is 230 and thickness is 35 mm.• The thickness of the bakeout (PI thin layer) envelop for the VCRL% chamber is 5 mm which means a total outer diameter of 70+10=80 mm.

Page 20: Technology Department LSS2 modifications Impact on the vacuum systems LTEX - 18/01/2011 Eric PAGE – TE-VSC

Technology Department

Creation of new vacuum elements for 4R2:

• VMTBB: Collimator Module - QFC100/DN100 - 80/63R aperture is 80 to 63 mm, L=220 mm, the bellow connected on the collimator side accepts the 5th axis motion.• VMTQD: Collimator Pumping Module - QFC100/DN100 - 80/63 aperture is 80 to 63 mm, L=460 mm, the bellow connected on the collimator side accepts the 5th axis motion.• VCRLP: Vacuum - Chamber - Circular - Long Straight Section - ID67?? - OD70?? - Type LP -

QCF100/QCF100 aperture is 67 mm??, L=3800 mm, same chamber as 4L2.

Page 21: Technology Department LSS2 modifications Impact on the vacuum systems LTEX - 18/01/2011 Eric PAGE – TE-VSC

Technology Department

ID800 area on 4L2 side