tenas metallurgical coal project definitive feasibility

37
Allegiance Coal Limited: Suite 107, 109 Pitt Street, Sydney NSW 2000 ABN 47 149 490 353 T: +61 2 9233 5579 F: +61 2 9233 1349 E: [email protected] W: www.allegiancecoal.com.au 18 March 2019 TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY STUDY RESULTS ________________________________________________________________________________ The Tenas Project DFS reinforces the potential of the Telkwa metallurgical coal complex with excellent results highlighting an extremely robust project, and significant improvements on the Company’s two pre-feasibility studies undertaken in 2017. __________________________________________________________________________ DFS HIGHLIGHTS § 750,000 tonnes per annum of saleable coal. § 22 year mine life extracting just 15% of the entire Telkwa coal resource. § 3.6:1 BCM/ROMt strip ratio. § 75% average yield for all metallurgical saleable coal. § US$49.7 per tonne average all-in FOB cash cost (ex-port) before interest and tax. § A$121.3M average revenue per annum. § A$63.7M EBITDA average per annum at a ratio to revenue of 53%. § US$54.3M start-up capital expenditure. § A$407.3M NPV8% pre-tax. § 56.9% IRR pre-tax. § 2.5 years capital payback after commencement of production. _______________________________________________________________________________________ Mr David Fawcett, Non-Executive Chairman, commented: “The Tenas project is truly unique. Our two pre-feasibility studies completed in 2017 highlighted to us that this project has the potential to be a very low cost producer of a product highly sought after by the steel mills. But to achieve a cash cost of US$49.7/t, for coal loaded on a vessel at Ridley Coal Terminal is quite extraordinary. I commend our DFS team, including SRK Consulting (Canada) Inc. and Sedgman Canada for the excellent work they have done to optimize the mining potential of the Tenas deposit. We look forward to working closely with our joint venture partner, Itochu Corporation, in securing permits to mine over the next 18 months and bringing the Tenas Project into production”.

Upload: others

Post on 16-Oct-2021

9 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

Allegiance Coal Limited: Suite 107, 109 Pitt Street, Sydney NSW 2000 ABN 47 149 490 353 T: +61 2 9233 5579 F: +61 2 9233 1349 E: [email protected] W: www.allegiancecoal.com.au

18March2019TENASMETALLURGICALCOALPROJECTDEFINITIVEFEASIBILITYSTUDYRESULTS________________________________________________________________________________The Tenas Project DFS reinforces the potential of the Telkwa metallurgical coal complex withexcellent results highlighting an extremely robust project, and significant improvements on theCompany’stwopre-feasibilitystudiesundertakenin2017.__________________________________________________________________________DFSHIGHLIGHTS§ 750,000tonnesperannumofsaleablecoal.

§ 22yearminelifeextractingjust15%oftheentireTelkwacoalresource.

§ 3.6:1BCM/ROMtstripratio.§ 75%averageyieldforallmetallurgicalsaleablecoal.§ US$49.7pertonneaverageall-inFOBcashcost(ex-port)beforeinterestandtax.§ A$121.3Maveragerevenueperannum.

§ A$63.7MEBITDAaverageperannumataratiotorevenueof53%.§ US$54.3Mstart-upcapitalexpenditure.§ A$407.3MNPV8%pre-tax.§ 56.9%IRRpre-tax.§ 2.5yearscapitalpaybackaftercommencementofproduction._______________________________________________________________________________________MrDavidFawcett,Non-ExecutiveChairman,commented:“TheTenasprojectistrulyunique.Ourtwopre-feasibilitystudiescompletedin2017highlightedtousthatthisprojecthasthepotentialtobeaverylowcostproducerofaproducthighlysoughtafterbythesteelmills.But to achieve a cash cost of US$49.7/t, for coal loaded on a vessel at Ridley Coal Terminal is quiteextraordinary.IcommendourDFSteam,includingSRKConsulting(Canada)Inc.andSedgmanCanadafortheexcellentworktheyhavedonetooptimizetheminingpotentialof theTenasdeposit.We lookforwardtoworkingcloselywithourjointventurepartner,ItochuCorporation,insecuringpermitstomineoverthenext18monthsandbringingtheTenasProjectintoproduction”.

Page 2: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

2

AllegianceCoalLimited(AllegianceortheCompany)ispleasedtopresenttheresultsoftheTenasProjectDefinitive Feasibility Study (DFS). TheDFS follows twopre-feasibility studiesundertakenbyAllegiance in2017,firstinrelationtotheentireTelkwametallurgicalcoalcomplex(publishedon3July2017),andsecondinrelationtoastandaloneTenasProject(publishedon11September2017).Significantly,theDFSconcludedthattheTenasProjectislikelytobeoneof,ifnot,thelowestcostproducersofmetallurgical coalon theglobal seabornemarket.Theseabornemarketcomprisesaround325milliontonnesofmetallurgicalcoalperannum,withsemi-cokingcoalsaccountingforaround60milliontonnesofthattrade.Thevastmajorityofsemi-cokingcoalsontheseabornemarketcomefromtheHunterValleycoalminesinNewSouthWalesfromcompaniessuchasGlencore,Yancoal,andWhitehaven.

Source:WoodMackenzieseabornemetallurgicalcoalcostcurveasatNovember2018SRKConsulting(Canada) Inc. (SRK)andSedgmanCanada(Sedgman)werethe leadDFSconsultantsalongwithanextensiveteamoftechnicalexpertsandAllegianceManagement.TheDFSteamislistedbelow.Company AreaofresponsibilitySRK GeotechnicalengineeringSRK GeochemistrySRK CoalreservesandminingSRK WatermanagementSRK HydrogeologySedgman CoalprocessingSedgman CoalqualityRonParent,Independentgeologist GeologyandresourceMCAEngineeringLtdandBVElectric PowerHooperEngineeringandMorchEngineeringLtd RailloopDWBEngineering MineaccessroadandbridgesKobieKoornhof&AssociatesInc CoalanalysisandmarketingAlltheabove CapitalandoperatingcostsDanFarmer,ChiefOperatingOfficer,Allegiance AncillaryinfrastructureAngelaWaterman,DirectorEnvironment&Govt.Relations,Allegiance Environment,socialandpermittingJonathanReynolds,ChiefFinancialOfficer,Allegiance Financialmodel&economicanalysisDavidFawcett,Non-ExecutiveChairman,Allegiance Technicalreview

Page 3: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

3

LocatedinthenorthwestofBritishColumbia,Canada,theTenasProjectenjoysexceptionallocationtorailandport.SimplelogisticsisakeyfactorcontributingtotheTenasProjectasalowcostproducer.

Addedtothis,itisashortershippingdistancetotargetmarkets,inparticulartheJapaneseandSouthKoreansteelmills,thanfromitsmaincompetitorofsemi-softcokingcoalsinHunterValleyviatheportofNewcastle.Itis3,800nauticalmilesfromRidleyTerminalstoTokyo,whereasitis4,300nauticalmilesfromNewcastle.

Equally importantly, there is no congestion at Ridley Terminals with no delays in ships berthing; unlikeNewcastle(andQueensland)whereshipsoftenwaittwotofourweeksbeforetheycanberth.Mineownersincurexpensivedemurrageandsteelmillssufferadelayinthesupplyofrawmaterialsfortheircokeovensandblastfurnaceswhichdisruptssteelproduction.

Page 4: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

4

FirstNationsAllegianceacknowledgestheuncededrightsoftheWet’suwet’ennationto22,000squarekmsoftraditionalterritorywithinwhichtheTenasProjectsits.AllegiancehasandcontinuestoengagewiththeOfficeoftheWet’suwet’en (OW) in respect of all Tenas Project activities. The OW is the central office for theWet’suwet’enfocusingonthemanagementoftheirlandsandresources,fisheriesandwildlife,humanandsocialservices,andtreatynegotiations.TheOWisgovernedbytheWet’suwet’enHereditaryChiefsresidingthroughouttheirtraditionalterritories.InApril2017,aCommunicationandEngagementAgreementwas signedbetweenAllegiance’s subsidiarycompanyTelkwaCoalLtdandtheOW.TheTenasProjectminesiteareaiswithinthetraditionalterritoryoftheCas’Yex(GrizzlyHouse)oftheGitdumdenclanoftheWet’suwet’enandtherailloadoutislocatedwithinLaksilyuterritoryoftheWet’suwet’en.PermittingScheduleThepermittingprocessfirstinvolvesthecollectionofenvironmentalbaselinedata(overatleasttwoyears),and then an environmental impact assessment of the Project on the baseline data collected. The TenasProjectfortuitouslyhasbaselinedataacrossmostenvironmentaldisciplinesdatingbacktothe1990s.Thisprovidesmoresubstancetothemodellingofenvironmentalimpactassessment.ThemapbelowillustratesAllegiance’sbaselinemonitoringactivitiesoverthelast2years.

Themainareasoffocus(notlimitedto),arelistedbelow:§ Geochemistry;

Page 5: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

5

§ Surfacewaterqualityandquantity;§ Groundwaterquality;§ SoilandTerrain;§ Noise;§ Airquality;§ Vegetation;§ Fishandaquaticspecies;and§ Wildlife.Allegianceisinthepre-applicationphaseofpermitting,andonschedulewiththetimelinebelow.

InadditiontoconstantengagementanddialoguewiththeWet’suwet’en,Allegiancehasbeenveryactiveinwidercommunityconsultation,meetingfrequentlywitharangeofstakeholderandspecialinterestgroups,and having organised and held to date, two of five planned community open houses. BC Governmentguidelinesrecommendtwocommunityopenhouses.ToreinforceAllegiance’scommitmenttothecommunity,CompanyCEO,MarkGray,relocatedtoTelkwa12monthsagoandisnowresidentthere.Thishasproventobeveryvaluable,enablinginformal,daily,adhoccommunityconsultationwiththeCompany.Environmental baseline programmes are now largely complete. Less intensive environmentalmonitoringcontinues during the permitting phase and into production. Allegiance has prepared and submitted theValuedComponentSelectionSummarydocumenttotheEnvironmentalAssessmentOfficeforreview,andisnow preparing the Application Information Requirements document. Target period for lodgement ofapplicationsforanEACertificateandMinesActPermitsremainsQ32019.

Page 6: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

6

SummaryofDFSResultsAsummaryofthekeyresultsoftheDFSaresetoutinTables1to4below.Table1:CoalResourceandProductionParametersLifeofMine Units TotalTelkwacoalcomplexcoalresourceacross3deposits MTonnes 148.1TotalTenasdepositcoalresource MTonnes 36.5DFSlife-of-mineROMcoalproduction MTonnes 22.0DFSlife-of-minesaleablecoalproduction(at10%moisture) MTonnes 16.5DFSaverageROMcoalproduction(at5%moisture) MTonnesperannum 1.0DFSaverageproductcoalyield % 75DFSaveragesaleablecoal KTonnesperannum 750DFSaveragestripratio BCM/ROMt 3.6:1DFSminelife(incl.pre-production) Years 22Table2:Start-upCapital LeasefinanceUS$M OwnerfinanceUS$MPre-productionactivities 4.2CHPPandassociatedplantinfrastructure 3.3 14.0Minesiteinfrastructure 12.5Watermanagement 17.3Railloopandloadout 5.4Mobileequipment 32.9 0.9TotalStart-upCapital(excludescontingency) 36.2 54.3Table3:OperatingCostsLifeofMine US$/SaleabletSiteCosts Mining–wasteremovalandcoalrecovery 19.5Coalprocessing 6.3Generalandadministration 4.2Reclamation 0.9TransportationandMarketing Marketingcosts 1.9Haulage(CHPPtoRailSiding) 3.8Railtoportandloaded 13.1Totalall-incashcostFOBpre-interestandtax 49.7Table4:KeyPerformanceIndicatorsLifeofMine Units Value2021and2022averagecoalprice US$/t 1202023onwardsaveragecoalprice US$/t 114ExchangerateCanadiandollarstoUSdollars CAD:USD 1.33ExchangerateAustraliandollarstoUSdollars AUD:USD 1.41ExchangerateCanadiandollarstoAustraliandollars AUD:CAD 1.06Pre-taxnetpresentvalue@8% A$M 407.3Pre-taxInternalrateofreturn % 56.9Paybackfromcommercialproduction Years 2.5ProductionTargetsandForecastFinancialInformationAllegiancenotesthefollowinginrelationtotheproductiontargetsdisclosedinthisannouncement:

Page 7: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

7

§ Allmaterialassumptionsonwhichtheproductiontargetsandforecastfinancialinformationarebasedaredisclosedintheannouncement;

§ The coal resources and reserves onwhich the production targets are based have been prepared bycompetentpersonsinaccordancewiththerequirementsofthe2012editionoftheJORCCode;and

§ Theproductiontargetsandforecastfinancialinformationinthisannouncementareunderpinnedsolelybyacombinationofcoalreservesandmeasuredandindicatedcoalresources.Therelevantproportionsofprobablecoalreservesandprovencoalreservesis12:78.

TelkwaCoalResources&ReservesTheTelkwametallurgicalcoalcomplexhashadseveraldrillingandbulksampleprogrammescompletedbypreviousownersbetween1980and1997,andmost recentlybyAllegiance in2018.Other thanthe2018Allegiancedrillprogramme,all coal resourcedataandqualityanalysiswasundertakenduring theperiodillustratedinthetablebelow,anestimatedA$40Mworthofhistoricalexplorationdata.

On3July2017,Allegiancepublishedtheresultsofthefirstoftwopre-feasibilitystudies(PFS)inrelationtotheTelkwametallurgicalcoalcomplex(3July2017Announcement).InthatPFS,SRKpreparedastatementofresourcesandreservesinaccordancewithJORC2012Edition(JORCCode)andNationalInstrumentNI43-101‘StandardsofDisclosureforMineralProjects’(NI43-101),asissetoutinthe3JulyAnnouncement.Foreaseofreference,asummaryofthePFSresourcesandreservesisrepeatedinTables5and6below.Table5:Resources MeasuredMt IndicatedMt InferredMt TotalMt(adb)Tenasdeposit 58.8 - - 58.8Goathorndeposit 59.5 9.2 0.2 68.9TelkwaNorthdeposit 15.7 3.7 1.0 20.4Total 134.0 12.9 1.2 148.1

Table6:Reserves ROMCoalMt CleanCoalMt SaleableCoalMtTenasProven 29.1 20.6 21.0TenasProbable - - -TenasTotal 29.1 20.6 21.0GoathornProven 22.1 12.6 18.8GoathornProbable 0.2 0.1 0.1GoathornTotal 22.3 12.7 13.9TelkwaNorthProven 10.8 6.4 7.0TelkwaNorthProbable 0.7 0.4 0.5TelkwaNorthTotal 11.5 6.8 7.5GrandTotal 62.9 40.1 42.5

0

20

40

60

80

100

120

140

160

1979

1981

1983

1985

1987

1989

1991

1993

1995

1997

Exploration Year

Numb

er of

Dril

l Hole

s

ROTARY

CORE

Intotal,826drillholesrecoveredcorefrom91,000mofdrilling;plus,a208tbulksamplein1983,anda80tbulksamplein1996.Fromthis,coalwasrecoveredtoundertakecoalwashabilityandqualitytestsandpetrographicanalysis.

Page 8: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

8

ThecoalresourcesincludingdrillholelocationsoftheTelkwametallurgicalcoalcomplex,aslistedinTables5and6above,areillustratedinthemapthatfollows.

Following a 34-hole drill programme in the Tenas deposit undertaken by Allegiance in 2018, the Tenasgeologywasre-interpretedandthecoalresourcesupdatedbasedontheidentificationofaseriesoffaults.In addition, non-continuous, thin and high ash coal seams were excluded from the resource statementreducingthenumberofcoalseamsfrom13tojustthree,oneofwhichwassplitintoalowerandupperply.The updated resource statement for Tenaswas publishedbyAllegiance on 18 June 2018 (18 June 2018Announcement).Foreaseofreference,18June2018AnnouncementstatementofresourcesisrepeatedinTable7below.

Page 9: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

9

Table7:TenasResources MeasuredMt IndicatedMt InferredMt TotalMt(adb)cSeam 4.5 1.4 - 5.91lowerseam 8.1 2.7 - 10.91upperseam 4.5 1.6 - 6.21Seam 9.9 3.5 - 13.5Total 27.1 9.4 - 36.5

EstimationMethodologyCoalqualityandseamthicknessparameterswereestimatedusinginversedistancesquaredwithintheseamwireframeswhichcontrolthedistributionofinterpolatedvaluesin3D.Themodelisofthecoalseamsonlyand the interburden has been modelled by default but to sufficient detail to assist with waste rockcharacterisationandwasterockmanagement.Themodelblocksizerangesfrom5to25malongstrike,5to10mdowndipand5minheight.AveragedrillholespacingforTenasis110mandtheaveragecoreholespacing(withqualitydata)is237m.Akeyassumptionutilizedintheresourceestimatewastherelationshipbetweenashcontentonanairdriedbasisandbulkdensityusedforconversionofvolumetotonnes.Thegeologicalinterpretationisbasedonthe“stacking”ofseambottomsalong25mspacedcrosssectionsfromthelowermostseamupward.Themainvalidationmethodusedwasacomparisonbetweenwireframesolidsvolumeandvolumegeneratedfromthe3Dblockmodelaftercoding.Themodelaccuratelyrepresentsthedrilledseamtruethicknessesto+/-0.1matagivenXYlocation.Theelevationsmayvaryupto3matanydrillholeintercept.Thisisduetothesectionalnatureof themodellingprocess,projectingall seam intersectionsamaximumof12.5mto thenearestcrosssection.UpdatedTenasReserveStatementIn theDFS, SRK updated the Tenas reserves in accordancewith the JORC Code andNI 43-101,which issummarised in Table 8 below. The DFS accounts for just 15% of the entire coal resource of the Telkwametallurgicalcoalcomplex.Table8:TenasReserves ROMCoalMt SaleableCoalMtTenasProven 17.1 12.9TenasProbable 4.9 3.7TenasTotal 22.0 16.5TheproductiontargetsandforecastfinancialinformationoutlinedinthisannouncementinrelationtothenewTenasReserves,arebasedsolelyontheProvenandProbableReserves inTable8.Modifyingfactorssuchasminingdilution,mining recovery, rawashanddensity,andcoalyieldhavebeenestimatedusingacceptedtechniquesconsideredbyAllegianceandSRK.TheaccuracyoftheTenasReserveestimateissubjectto geological data and modelling procedures to estimate the coal resource and to modifying factorassumptionsfordilutionandloss.WhiletheTenasProjectisnotinproductionandsuchreconciliationisnotpossible,theassumptionsarebasedonsoundprinciplesandexperiencefrommineswithsimilarconditions.AllTelkwaReserveestimatesarebasedon:minimumseamthicknessof0.8m;maximumashcontentof50%;dilutionof0.15m(unlessblastingthroughseams,whereitis0.25m)andcoallossof0.10m(0.20mwhereblastingthroughseams)percoalseam;ROMcoalandsaleableproductbases,withamoisturecontentsof5%and10%respectively;andcoalyieldsarebasedonwashabilitiesatafloat-sinkspecificgravityof1.6.

Page 10: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

10

TenasProjectComponentsTheTenasProjectislocated7kmsouthwestofthesmalltownofTelkwa(population~2,000),and25kmsouthofthelargertownofSmithers(population~6,000)whichhasanairportwithdailydirectflightstoVancouver.The townofTelkwahasa longhistoryofcoalminingdatingback to the late1800swithcoalproductionceasingasrecentlyas1985.TheTenasProjecthasaccesstoexcellentroadinfrastructuredevelopedbytheforestryindustry,isjust3kmfrompower,and16kmfromtheproposedCHPPtotheproposedrailloadoutalongagentledecliningprivatedesignated haul road (to be constructed). The excellent existing infrastructure has kept the cost ofinfrastructureconstructionlowhelpingtominimizestart-upcapitalexpenditure.

Page 11: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

11

TheTenasProjectcomponents,highlightedonthemapabove,willinclude,amongstotherthings:§ Onesingleopenpitmine;§ Typicalopenpitmineoperationsequipmentincluding91tdumptrucks,excavatorsanddozers;§ Wasterockdumpsoutsidethepitaswellasback-filldumpsduringminingwithinthepit;§ Diversionditchestodivert‘contact’waterintothewatermanagementponds;§ Watermanagementpondstosubmergeunderwaterpotentiallyacidleachingwasterockduringmining;§ Sedimentationpond;§ Dedicatedpipelinefromthesedimentationpondtoawatercoursefordischarge;§ ROMcoalhaulroadsfrompitoperationstothecoalhandlingandpreparationplant(CHPP);§ TheCHPPitselfandassociatedinfrastructure;§ Mineinfrastructureincludingamongstotherthingsequipmentmaintenanceshop;§ 3kmpowerlineconnectingtheminetoalocal25kVpowerline;§ Adedicated16kmprivatecleancoalhaulroadfromtheCHPPtotherailloadout;§ Severalsmallbridgesalongthecleancoalhaulroad;§ ArailloopandloadoutfacilityadjacenttoCanadianNationalRail’s(CNRail)mainlinetoRidleyTerminals.MiningMethodandScheduleTheTenasdepositisasynclinebasinwiththecoalseamsgentlydippingfromthewestmeetingthesynclineontheeast.Thedepositistobeminedbyopenpitminingmethodsinvolvingninephases.Miningcommenceswithphase1intheshallowestareatothesouthwest,thenprogressivelyminingtowardsthesynclinetotheeast,northandsouth,asillustratedbelow.

MultipleminingapproachescanbedeployedtotakeadvantageoftheuniquegeologicalandtopographicsettingoftheTenasdeposit.Shallowdippingcoalstrata,andreasonablynearsurfacecoalstrataallowforabottom-upminingapproach.

Page 12: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

12

Forthis,abox-cutisestablishedatthelowerendofaphaseandsuccessivecutsadvanceup-dip,progressivelyexpandingavailablebackfillspacedown-dipfromtheactivecuts.Hydraulicexcavatorsminethebulkofthewaste,withtrackdozerspushingsomeofthewasteabove1U-seamontofinalpitbottom.Coalisalsominedbyhydraulicexcavator.Blasting is inbenchesaboveC-seam,andthen throughC-seamstandingoff from1U/1-seam.Notallphasesareamenabletothismethodduetosteeperseamdipsnearerthesyncline,relyinginsteadonmoreconventionaltop-downbenchmining.Theup-dipminingisillustratedbelow.

ThemineproductionschedulefortheTenasProjectisnominally1,050,000ROMtonnesperannumfora22-yearminelifeincludingconstruction,producingonaverage750,000saleabletonnesperannum,atastripratioof3.6:1BCM/ROMt,andatayieldof75%(at10%moisturewhenloadedontoavessel).EquipmentRequirementsTheprimaryfleetatfullproductionwillinclude:§ Twoproductiondrills(one250mmandone140mmbitdiameter);§ Threehydraulicbackhoes(12m3);§ Onebackhoeexcavator(6m3);§ 12rigidframehaultrucks(91t);§ Fourtrackdozers(3.9mblade);§ Threegraders(4.26mblade);and§ Twowatertrucks(91t).The production fleetwill be supportedwith ancillary equipment similar to other open pit operations inwesternCanada.LabourRequirementsTheminewilloperate24/7withfourcrewsonasevenshifton,sevenshiftoffrotation,alternatingdaysandnights,whilethemaintenanceworkforceisassumedtolargelyworkadayshiftfour-on/four-offschedulewithtwotradespeopleworkingnightshifttosupportmineoperations.Atfullproduction,themineaverages95mineworkers, 29minemaintenanceworkers alongwith technical support and supervisory staff.TheneighbouringtownsofTelkwa,Smithers,and50kmsouthofTelkwa,Houston,allhouseskilledmineworkers

Page 13: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

13

whosupportthehardrockminingindustry intheregion. Inaddition,theprimaryindustry intheregionisforestry,whereskilledequipmentoperatorsprovideareadilyavailablelabourpool.CoalHandlingandPreparationPlantTheCHPPconfigurationwillbeaDMC/flotationplantdesignedandconstructedtoprocess145t/hofrawcoal (ROM)over themine’s life.A key factor to this processing ratewas adesirebyAllegiance touse aSedgman modular plant with minimal upfront capital expenditure. However, to allow for increasedproductiononcecashflowisestablished,theCHPPhasbeendesignedtobeabletoexpandto190t/hofROMcoal(equivalentto1.35MtofannualROMproduction)byaddingasecondaryfloatcellandbeltfilterpressfor finerockdewatering.TheCHPPcanbefurtherexpandedto350t/h(equivalentto2.5MtannualROMproduction)byaddingarefluxclassifiercircuit,arejectdrainandrinsescreen,flotationcell,beltfilterpressmodule and increasing the size of the building. The images that follow illustrate the Sedgman designedmodularCHPPandrelatedinfrastructure.

Page 14: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

14

TheCHPPislocatedapproximately2kmtothenortheastoftheTenaspit.ThislocationwasselectedasithasarelativelyflatprofilewhichminimisesbulkearthworkcostsrequiredtoconstructthepadrequiredforboththeCHPPandancillaryinfrastructure.Theplantlocationalsoallowsforanyfutureexpansionofthepitasthereareknowncoalresourcesresidinginthe2kmbetweentheselectedplantlocationandTenaspit.TheCHPPflowsheetincorporatesthefollowingprocessstages:§ Rawcoalreclaimingandsizereduction;§ Coarse coal (DMC) circuit for coal between 50.0 by 0.50 mm with horizontal basket centrifuge for

dewatering;§ Magnetiterecoverycircuit;§ Finecoalflotationforcoal<0.50mmwithscreenbowlcentrifugefordewatering;§ Finerockthickeninganddewateringusingabeltpressfilter;§ Washedcoalloadoutattheplantviaan8,400-tonneopenairstockpile;§ PlantRockloadoutviaa6,600-tonneopenairstockpile;§ 16kmon-highwaytruckhaultotheRailLoadout;§ Washedcoalloadoutviaa30,000-tonneopenairstockpile;§ 375kmrailtransportusing116carunittrainstoRidleyTerminals.InfrastructureThe construction of the infrastructure required to support themining operation will occur in stages tominimizetheupfrontcapitalbutalsoallowforexpansion:§ 2020/21–Infrastructureconstructedtosupporttheimmediateoperationalneedsareconstructed;§ 2022–Maintenanceinfrastructureupgraded;and§ 2023–Stacker/reclaimerupgradetobemoreefficientattherailloadout.TheInfrastructurefacilitiesoutlinedbelowwillbeconstructedinyears2020and2021oftheoperation:§ One50,000Ldieselfueltankanddispensingstationformineandlightvehicles;§ Electricalsubstationandsitedistribution;§ Improvementsto6.0kmofexistingforestryaccessroadthroughtheGoathornCreekValley;§ Afitforpurpose110tonnesinglelanebridgeoverGoathornCreek;§ Anewlyconstructed10.0kmaccessroadtothetrainloadout;§ Atrainloadoutpadwithsprayerapparatus;§ 2.5kmrailloopwhichincludes500metresfortheleadtieintracktosupporta116-carunittrain;§ 3.6kmof25kVtransmissionlinetosite;§ Anew25kVto600Vsubstationandelectricalroomsonsite;§ Apolemounted25kVto600VtransformeratGoathornCreek;§ AsecondpolemountedtransformerlocatedattheExplosivestoragefacility;§ Communicationsystem;§ ExplosiveFacilitiesandmagazines;§ Flocculantshedsattherailloadoutandthemainsedimentationpondatsite;and§ Administrationandminedrybuilding.TheInfrastructurefacilitiesoutlinedbelowwillthenbeaddedin2022tosupporttheoperation:

Page 15: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

15

§ Minetruckshopfacilityincludingawarehousewithaloadingdock;§ Coldstoragefacility;§ Lightvehicleshopandemergencyrescuefabricstructure;§ Second50,000Ldieselstoragetank;§ Bulklubefacilityatthetruckshop;and§ Dustsuppressionsystemattherailloadoutandplantsite.TheInfrastructurefacilitiesoutlinedbelowwillthenbeaddedin2023tosupporttheoperation:§ StackingandReclaimingsystemattherailloadout;§ Additionalconveyorantifreezesystem;and§ AutomatedsignalsatTelkwaCrossing.Itisestimatedthatthefacilitiesconstructedin2020/2021willtakeuptoeightmonthstodeliverwiththerailloopandaccessroadbeingthelongestleaditems.CoalQualityTelkwacoalwillbewashedatanSGof1.6toproduceatarget9%ash,mid-volatilesemi-softcokingcoal,atasaleablecoalyieldof75%.Table9:TelkwaCoalQuality Units Tenas NSWHVSSCC QLDMVSSCCInherentmoisture % 1.1 2.5-4.5 2-2.5Volatilematter % 25.8 33-38 25-27Ash % 9.0 5-9.5 9.5-10Sulphur % 0.98 0.35-0.85 0.35-0.55Fixedcarbon % 65.3 50-60 55Freeswellindex 3-4 3-6 3-3.5HGI 63 40-52 70-80Reflectance % 0.96 0.65-0.85 0.99-1.06Maximumfluidity Ddpm 6 10-500 15-50Baseacidratio 0.15 0.10-0.20 0.12-0.21

The quality parameters for Telkwa coal are summarized in Table 9 above, and are compared to similarproductsexportedfromNewSouthWalesandQueensland.CoalPricingKobieKoornhof&AssociatesInc(Koornhof),arespectedcoalmarketspecialistwithparticularexpertiseinNorthAmericancoals,providedAllegiancewithamarketoutlookformetallurgicalcoalalongwithapriceguideforTelkwacoalasamid-volatilesemi-softcokingcoal,andamid-volatilePCI.TheDFShasreliedonKoornhof’spricingguidanceforaTelkwamid-volatilesemi-softcokingcoal.According to Koornhof, demand for hard coking coal is continuing at robust levels as steel industryfundamentals remaina strongdriver for seabornecokingcoal imports.Thecurrentconstraints to supplyavailabilityforhighqualitycokingcoalsislikelytoremainfortheforeseeablefuture,sinceglobalcokingcoalsupplyisnotcomingonlineatapacethatwillupsetthecurrentsupply/demandbalance.Inthemediumterm,thebiggestrisktometallurgicalcoalpricingliesinapossibleglobaleconomicslowdown,fuelledbythefearofburgeoningtradewars.

Page 16: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

16

IndeterminingasuitablepricepointforTelkwasemi-softcokingcoal,KoornhofnotesTelkwaSSCCisaclosermatchwiththeQueenslandmediumvolatileSSCC(MVSSCC),thanNewSouthWaleshighvolatileSSCC(HVSSCC).TheneteffectivecarboncontentoftheMVSSCC,whichisconsiderablyhigherthanthatoftheHVSSCC,resultsinapremiumofUS$2-3/tonnefortheMVSSCC.KoornhofnotedthatAustralianSSCCforQ42018wassettledonJanuary29,2019atUS$135pertonne.ThenetresultforTelkwaSSCC,consideringasulphurpenalty/ashpremium,andfactoringintheUS$2.50/tonnepremium for MV SSCC over HV SSCC, is a US$2.05/tonne discount to HV SSCC pricing. Based on thesettlementsforQ42018,thatwouldindicateapriceofUS$132.95pertonneforTelkwaSSCCtoday.Koornhofassumedapricerangeforpremiumbenchmarkcokingcoalforthemediumterm(2020to2022)and long term (2023 onwards), againstwhich it then applied the current trend discount forHV SSCC tobenchmarkhardcokingcoal.ThebenchmarkparametersusedforpricingaresummarizedinTable10below.Table10:Benchmarking Priceas%ofHCC MediumtermpriceUS$/t LongtermpriceUS$/t Years2020-2022 Years2023onwardsPremiumlowvolcokingcoal 100% 185-210 175-210Semi-softcokingcoal 66% 122-139 116-139Usingavalueinusemethodology,KoornhofprovidedapricerangeforecastforTelkwacoalsummarisedinTable11below.ForthepurposesoftheDFS,AllegianceassumedthelowestpriceofUS$120/tforcoalsoldin2021and2022,andthelowestpriceofUS$114/tforcoalsoldfrom2023onwards.Table11:Priceforecast MediumtermpriceUS$/t LongtermpriceUS$/t Years2020-2022 Years2023onwardsTelkwaMVSSCCpricerange 120-137 114-137

CoalMarketsAllsteelmillsuseablendofcokingcoalsrangingfromhardcokingcoalstosemi-cokingcoalstofeedtheircokeovens.Generally,thesteelmillsblendataratioof70:30hardcokingcoaltosemi-cokingcoal.Insomeinstances,semi-cokingcoalistheprimaryfeedforacokeoven.Tenas Project’s target customers are the north Asian steelmills. Using coal derived from the 2018 drillprogramme,AllegianceprovidedbulksamplecoaltothethreeJapanesesteelmillsandoneSouthKoreansteelmill,allofwhomundertookcoalqualitytests.Followingthetestresults,expressionsofinterestwerelodgedforthepurchaseofTelkwacoaloncetheTenasProject is in production. Feedback from the steelmills emphasised the scarcity ofmid-volatile semi-softcokingcoalsontheseabornemarket.Theyadvisedthatthesemi-softmarketisdominatedbythesupplyofhighvolatilesemi-softcokingcoalsfromtheHunterValleyandthatthereonlyafewmines,producinglowvolumes,ofmid-volatile semi-cokingcoal fromcentralQueensland.Theyalsoadvised therewasnonon-Australiansupplierofmid-volatilesemi-softcokingcoal to theseabornemarket,placingTelkwacoal inauniqueposition.Koornhofalsonotedinhisreport,that“TelkwaSSCCisexpectedtobewellreceivedduetolimitedavailabilityofmidvolSSCContheseabornemarket, incontrasttothemorereadilyavailablehighvolatileSSCCcoalsfrom NSW. The market should react favourably to the introduction of a newmidvol SSCC, not only as

Page 17: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

17

diversification from Australia, but also due to the fact that Canadian SSCC supplies have largely beeneliminatedwiththeclosureoftheCoalMountainoperation.”CapitalThestart-upcapitalexpenditureissummarizedinTable12below.Table12:Start-upCapital LeasefinanceUS$M OwnerfinanceUS$MPre-productionactivities 4.2CHPPandassociatedplantinfrastructure 3.3 14.0Minesiteinfrastructure 12.5Watermanagement 17.3Railloopandloadout 5.4Mobileequipment 32.9 0.9TotalStart-upCapital(excludescontingency) 36.2 54.3Pre-productionactivitiesincludeslandclearing,logging,topsoilsalvageandpre-strip.Minesiteinfrastructureprimarilyincludes:§ Earthworks;§ Connectingtopowerincludingsub-station;§ Upgradingexistingforestryroads;§ ROMandcleancoalhaulroadconstructionincludingseveralsmallbridges;§ Rawwatersystem;§ Fueltanks;and§ Fencing.Asdiscussedpreviously,theCHPPisaSedgmandesignedmodularwashplantwhichwillhaveafeedcapacityonstart-upof145t/handthepotentialwithexpansiontofeed350t/h.Thewashplantconfigurationwasdriven by a desire to minimise start-up capital expenditure without materially compromising yield andperformance,aswellasallowinganincreaseinproductioninduecourse.Effectiveandreliablewatermanagement iscritical foranymineoperation inBritishColumbia.Managingsurfacewaterfromrainandsnowmeltthatcontactsmineoperations isveryimportant.Contactwater isdivertedviaditchestopondswherethewaterisheldallowingsedimenttosettlepriortothewaterbeingdischargedintothecatchmentarea.TheDFSalsoassumesthewaterwillbedischargedintotheTelkwaRiver(alargewatercourse)viaapipe.Waterisdischargedinspringandsummeroncethepondshavethawedafterthespringmeltandduringhighwaterflows.Inaddition,someofthewasterockminedhasthepotentialtoleachacidwhenexposedtoairandwater,whichtheDFSassumeswillbesubmergedunderwaterinmanagementpondsconstructedduringthefirst10yearsofproductioneliminatingtheopportunityfortherocktoacidise.TheDFS assumes that start-upproductionequipmentwill involvenewequipment.Attractive equipmentfinancingtermswereofferedbyseveralwellknownequipmentbrandsforfleetsofnewequipment.ThesustainingcapitalexpenditureissummarizedinTable13below.

Page 18: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

18

Table13:SustainingCapital LeasefinanceUS$M OwnerfinanceUS$MProductionmilestonepaymentsrelatingtoprojectacquisition 5.6Mining 8.1CHPPandassociatedplantinfrastructure 11.4Minesiteinfrastructure 4.4Watermanagement 52.4Railloopandloadout 2.8Mobileequipment 10.8 21.6Administrationinfrastructure 0.7TotalSustainingCapital(excludescontingency) 10.8 107.0ThemilestonepaymentsaretoAltiusMineralsCorporationinthefirsttwoyearsafterthecommencementofproductionandrepresentthemajorityofthepurchasepricepaidbyAllegiancefortheacquisitionoftheTelkwacoalexplorationtenements.TheDFSassumesUS$10.8Mofthemobileequipmentwillbeleasefinancedandthebalancefundedfromcashflow.As discussed above, on going water management, and mitigating the risk of environmental impact isimportantandrequiressignificantongoingcapitalinvestmentduringthelifeofmine.ThisisnotuncommoninBritishColumbia,andCanadagenerally,andreflectsthehighstandardsthatCanadasetsfortheprotectionoftheenvironmentfromindustry,notjustmining.OperatingCostsTheDFSoperatingcostsaresummarizedinTable14below.Table14:OperatingCostsLifeofMine US$/SaleabletSiteCosts Mining–wasteremovalandcoalrecovery 19.5Coalprocessing 6.3Generalandadministration 4.2Reclamation 0.9TransportationandMarketing Marketingcosts 1.9Haulage(CHPPtoRailSiding) 3.8Railtoportandloaded 13.1Totalall-incashcostFOBpre-interestandtax 49.7TheTenasProjectenjoysrelativelyeasyminingconditionswith flatgentledippingcoalseams,anda lowaveragelife-of-minestripratioof3.6:1BCM/ROMt,or4.8:1BCM/PRODt.Thisalongwithdozerpushingandbackfillingasignificantamountofwasterockmaterialduringmineoperations,hascontributedtoverylowminingcosts.ItochuCorporationaretheappointedsalesagentforTelkwacoal,andreceiveasalescommissionof3percentoftheFOBprice,ofwhich1.5%ispaidonsale,and1.5%ispaidasaprofitshareafterEBITDA,assumingEBITDA ispositive.TheEBITDAmarketing fee isnot included in theall in cashcost/tabovebecause it issubjecttoprofitability,notrevenue.

Page 19: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

19

AroyaltyisalsopayabletoAltiusMineralsCorporationforthelifeofmineaspartoftheprojectacquisitionpurchaseprice,equalto3%oftheFOBprice,andpaidquarterlyaftersales,whichroyaltyisnotincludedintheallincashcost/tabove.FinancingThe Board of Allegiance considers that there is a reasonable basis to assume the necessary funding fordevelopmentoftheTenasProjectwillbeabletobeobtainedwhenrequired,becauseof(butnotlimitedto)thereasonsoutlinedbelow.FundingfromcompletedDFStocompletionofpermittingAspreviouslyannouncedbyAllegianceon5November2018,ItochuCorporationofJapan(Itochu)hasagreedtoinvestC$6.6M(A$6.9M)intoTelkwaCoalLtd(TCL),subscribingforsharesinTCLrepresenting20percentoftheissuedsharecapitalofTCL,asfollows:§ C$1.5Mfora5.3%interestinTCL,completedinJanuary2019,followingtheissueofasection10order

undertheEnvironmentalAssessmentActofBritishColumbia(whichformallyacknowledgestheTenasProject has been accepted for environmental review and permitting and was received by TCL earlyNovember2018);

§ C$1.5M for a further 4.8% interest in TCL, following completion of the Tenas Project DFS to thesatisfactionofItochu;and

§ C$3.6Mforafurther9.9%interestinTCL,followinglodgementofanapplicationforanEnvironmentalAssessmentCertificate,targetedforQ32019;and

§ InadditiontothesharesthatItochureceivesinTCL,ItochuhasbeengrantedtheexclusiverighttomarketandsellallcoalminedatTelkwa,includingfromtheTenasProject.

It isanticipatedthattheItochuinvestmentwill fundTCLthroughtothecompletionofpermitting.Totheextent that itdoesnot,Allegiancemayhave to raiseadditional capital for thatpurpose. If required, it ispresentlyanticipatedthatsuchcapitalwouldmostlikelyberaisedthrough:§ Equitycapitalmarkets;and/or§ Furtherfarm-outofparticipatinginterestsintheTenasProjecttoItochu,orotherpotentialinvestors.MinedevelopmentfundingpostpermittingItochuhastheright,afterpermitstominetheTenasProjectaregranted,tosubscribeforadditionalsharesinTCLonthebasisofavaluationwhereallpermitstominearegranted.Thatvaluationistobedeterminedbetweentheparties,orfailingthatbyanindependentexpert.ItisAllegiance’sviewthatavaluationoftheTenasProjectwhereallpermitstominearegranted,willproperlyreflectvalueandthatItochuislikelytobepreparedtoinvestfurtherequitytowardsTenasProjectconstructioninordertomonetisethevalueoftheircoalmarketingrights.TheBoardconsidersthisviewreasonable.Withoutthisfurtherinvestment,andintheabsenceofalternativefunding,thecoalmarketingrightswillnotbeofvalue.Two major equipment suppliers have offered favourable financing terms for the supply of newminingequipmentduringtheminestart-upphase.TheDFShasassumedthatthemajorequipmentsuppliedfromthepreferredsupplierwillbeleasefinancedfromthatsupplierattheofferedinterestrateof5.6%pa,andrepaid in full over five years from the commencementof production. In addition, theDFS assumed thatancillarymobileequipmentwillalsobeleasefinancedandassumedthesamefinanceleaserateofferedbythesamepreferredsupplier.

Page 20: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

20

Table15below lists themajormineequipment, for thestart-upphase,with indicativepriceand financetermsfromthepreferredsupplier,andsummarisestheancillarymobilemineequipmentassumingthesamefinancerate.Table15:Equipmentleasefinancedonstart-up Numberofunits C$’000Crawler-mountedRotaryDrill6.00-9.88inchdiameter 1 2,662Crawler-mountedRotaryDrill4.5inchdiameter 1 778Diesel15.7cubicyardBackhoe 2 7,366Diesel7cubicyardBackhoe 1 1,228100-tonclassHaulTruck 10 20,354D8class12.9inchbladeDozer 3 2,98814Hclass14inchbladeGrader 3 1,608100-tonclass75,000LWaterTruck 1 2,335ArticulatedHaulTruck43st30yd 2 1,902988classFrontEndLoader 4 4,335Ancillarymobileequipment 3,664Inadditiontotheabove,minedevelopmentfundingoptionswillbeexploredduringthepermittingphaseoftheTenasProjectandinclude:§ Projectfinance;§ Vendorfinance;§ Customerfinance;and/or§ Equitycapitalmarkets.ProjectEconomicsInadditiontothecoalproductioninputsdiscussedthroughoutthisannouncement,additionalinputsintothekeyperformanceindicatorsoftheProjecteconomicsaresetoutinTable16below.Table16:AdditionalinputstoKeyPerformanceIndicators Units ValueAverageCoalpriceforTenasproductcoal–2021and2022 US$/t 120AverageCoalpriceforTenasproductcoal–2023onwards US$/t 114BCMineralstaxrate(deductiblefromcorporatetaxes)* % 2or13BCCorporatetaxrate % 11FederalCorporatetaxrate % 15

*BCMineralstaxratecomprisesanetcurrentproceedstaxrateof2%oranetrevenuetaxrateof13%dependingontaxableincome.

TheProjectkeyperformanceindicatorsaresummarizedinTable17below.Table17:KeyPerformanceIndicators Units ValuePre-taxNPV8% A$M 407.3Pre-taxIRR % 56.9Post-taxNPV8% A$M 260.5Post-taxIRR % 47.0Paybackfromcommencementofproduction Years 2.5Allegiancecurrentlyowns95%ofTCL.TCLowns100%oftheTenasProject.Theremaining5%ofTCLisownedbyItochu.Onthatbasis,Allegiance’scurrent95%shareofProjectNPVissummarizedinTable18below:

Page 21: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

21

Table18:Allegiance’sshareofNPV Units ValuePre-taxNPV8% A$M 386.9Post-taxNPV8% A$M 247.5Sensitivityanalysiswasundertakentodeterminetheeffectonthepost-taxNPV8%andtheIRR.TheresultsofthesensitivityanalysisaresetoutinTables19and20below.Table19: OperatingandCapitalCosts(US$M)NPV(US$M) 185 944 1,079 1,213 1,348 1,483 1,618 1,753

PriceUS$/Producttonne

84.0&79.8 130 95 59 22 -18 -61 -11096.0&91.2 182 148 114 78 41 3 -39

108.0&102.6 234 200 166 133 97 61 23120.0&114.0 286 252 219 185 152 116 80132.0&125.4 338 304 271 237 203 170 135144.0&136.8 390 356 323 290 256 222 189156.0&148.2 442 408 375 342 308 275 241

Table20: OperatingandCapitalCosts(US$M)IRR(%) 47 944 1,079 1,213 1,348 1,483 1,618 1,753

PriceUS$/Producttonne

84.0&79.8 47% 31% 19% 12% 6% 2% 0%96.0&91.2 69% 47% 32% 22% 14% 9% 4%

108.0&102.6 93% 66% 47% 34% 24% 17% 11%120.0&114.0 118% 87% 64% 47% 35% 26% 19%132.0&125.4 147% 108% 82% 62% 47% 36% 27%144.0&136.8 179% 132% 101% 78% 61% 47% 37%156.0&148.2 215% 158% 121% 95% 75% 59% 47%

Tables19and20showthattheTenasProjectperformanceindicatorsaresensitivetochangesincommoditypriceandoperatingandcapitalcosts.TheProjectcansustaina30%decreaseinproductsellingpriceresultinginaposttaxNPV8%ofUS$22Mand12%posttaxIRR.TheProjectcansustaina30%increaseincapitalandoperatingcostsresultinginaposttaxNPV8%ofUS$80Mand19%posttaxIRR.RisksThekeyrisksinrelationtotheTenasProjectaresummarisedbelow:§ Environment:The impactofminingontheenvironment isalwaysan issue irrespectiveofthetypeof

mineand its location.OncetheCompanyhascompleted itsenvironmentalaffectsassessmentof theProject,targetedforQ22019,theCompanywillhaveasolidunderstandingofwhattheimpactsmightbe.

§ WaterManagement:Relatedtothefirstpointofenvironmentalimpact,oneareaofparticularconcerntotheCompanyiswatermanagement.TheProjecthasseveralstreamswithinitsvicinitywhichallfeedintoamajorriversystem.EnsuringthattheProjectdischargescleansurfacewaterbackintotheriversystemisamatterofhighprioritytotheCompany.

§ AcidRockManagement:TheProjecthassomewasterockthathaspotentialtogenerateacidleachingofmetalswhenminedandexposedtoairandwater.TheDFSassumesthisrockwillbepermanentlystoredunder water cover inmanagement ponds constructed in the first 10 years ofmining. This planwillpreventoxidisationoftherockwhichinturnwilleliminatetherequirementfortreatmentofacidicwater.

Page 22: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

22

There is a risk that the water balance will not be positive requiring water to be pumped from awatercoursetomaintainthewatercover,oractiveongoingwatertreatment.

§ Water Discharge Quality: The Government provides thresholds for water quality discharge. Until an

effectsassessmentoftheProjectonwaterqualitybeingdischargedintothecatchmentiscompleted,andwhichispartoftheenvironmentalassessmentprocess,itwillnotbeknownforcertainwhetherthetreatmentofwaterpriortodischargeisrequired.

§ Permitting:ThereisnoguaranteethattheProjectwillbegrantedallpermitsrequiredtooperateamineatwhateverstageofplannedproduction.WhilstBritishColumbiaisinafirstworldcountry,withaveryprescriptiveminepermittingregime,thereisalwaysuncertaintyanddoubtastowhetherGovernmentministrieswillsupportaparticularminingactivity.

§ Finance:Notwithstanding theCompany’s confidence in this regard, there isnoguarantee that if andwhentheProjectispermittedandreadyfordevelopment,therewillbefundingavailabletodoso.WhilsttheProjectisverylowdownthecostcurveandcanwithstandamaterialdropinthepriceofcoal,thevolatilityofcommoditypricesinadownwardtrendoftendampenstheinterestofinvestorsinaparticularcommodity,suchthatfundingmaybedifficulttosecure.

§ Coal performance: unless and until a particular coal has been tested for its performance in a blast

furnace,thereremainsanuncertaintyastohowitwillactuallyperform,andthismayhaveanimpactoncoalpricing.

_______________________________________________________________________________________Formoreinformation,pleasecontact:MrDavidFawcett MrMarkGrayChairman,AllegianceCoalLimited ManagingDirector,AllegianceCoalLimitedMobile:+16046122376 Mobile:+61412899979Email:[email protected] Email:mgray@allegiancecoal.com.auAboutAllegianceCoalAllegianceCoalisapubliclylisted(ASX:AHQ)AustraliancompanyadvancingametallurgicalcoalmineintoproductioninBritishColumbia,Canada.TheTelkwametallurgicalcoalcomplex(Project)includesthreepitareascomprising125.8MtofJORCcompliantcoalresourceofwhich102.3MtisintheMeasuredCategory;22.3MtisintheIndicatedCategory;and1.2MtisintheInferredCategory.TheTenasProjectthesubjectofthisDFSrepresentsthefirstdevelopmentofthecomplexandcomprises36.5MtoftheProjectresourceand16.5MtoftheProjectreserves.CoalResources&Reserves:GoathornDeposit&TelkwaNorthDepositTheestimatesofcoalresourcesorcoalreservesinthisannouncementinrespectoftheGoathornDeposit&theTelkwaNorthDeposit,werefirstreportedintheCompany’sannouncementof3July2017.TheCompanyconfirmsthatitisnotawareofanynewinformationordatathatmateriallyaffectstheinformationincludedin the announcement of 3 July 2017 insofar as it relates to the coal resources or coal reserves for theGoathornDeposit&theTelkwaNorthDepositandthatallmaterialassumptionsandtechnicalparametersunderpinningtheestimatesintheannouncementof3July2017continuetoapplyandhavenotmateriallychanged.

Page 23: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

23

CoalResources&Reserves:TenasProjectTheestimateofcoalresourcesinthisannouncementinrespectoftheTenasProjectwasfirstreportedintheCompany’s announcement of 18 June 2018. The Company confirms that it is not aware of any newinformationordatathatmateriallyaffectstheinformationincludedintheannouncementof18June2018insofarasitrelatestothecoalresourcefortheTenasProjectandthatallmaterialassumptionsandtechnicalparametersunderpinningtheestimatesintheannouncementof18June2018continuetoapplyandhavenotmateriallychanged.CompetentPersonsStatementTheestimateofcoalreserves inthisannouncementinrespectoftheTenasProject isbasedonandfairlyrepresents, information and supporting documentation prepared by by Mr Ron Parent and Mr RobertMcCarthy.MrParent isaProfessionalGeologistregisteredwiththeAssociationofProfessionalEngineersandGeoscientistsofBritishColumbia.MrMcCarthyisaProfessionalEngineerregisteredwiththeAssociationofProfessionalEngineersandGeoscientistsofBritishColumbia.MrParentandMrMcCarthyareindependentconsultantstotheCompany,andhavesufficientexperiencewhichisrelevanttothestyleofmineralisationandthetypeofdepositunderconsiderationandtotheactivitywhichtheyundertooktoqualifyasCompetentPersons as defined in the JORCCode (2012 Edition of the “Australian Code for Reporting of ExplorationResults,MineralResourcesandOreReserves”).MrParentandMrMcCarthyascompetentpersonsforthisannouncement have consented to the inclusion of the information in the form and context in which itappearsherein. ______________________________________________________________________________________

Page 24: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

24

APPENDIX-JORCTABLE1Section1 SamplingTechniquesandDataCriteria JORCCodeexplanation CommentarySamplingtechniques

• Natureandqualityofsampling(e.g.,cutchannels,random chips, or specific specialised industrystandard measurement tools appropriate to theminerals under investigation, such as down holegammasondes,orhandheldXRFinstruments,etc.).Theseexamplesshouldnotbetakenaslimitingthebroad meaning of sampling.

• Include reference to measures taken to ensuresample representativeness and the appropriatecalibration of anymeasurement tools or systemsused.

• AspectsofthedeterminationofmineralisationthatareMaterialtothePublicReport. Incaseswhere‘industrystandard’workhasbeendonethiswouldberelativelysimple(eg‘reversecirculationdrillingwasusedtoobtain1msamples fromwhich3kgwas pulverised to produce a 30g charge for fireassay’). In other casesmore explanationmayberequired, suchaswhere there is coarsegold thathas inherent sampling problems. Unusualcommoditiesormineralisationtypes(egsubmarinenodules) may warrant disclosure of detailedinformation.

• Allboreholes,whereconditionspermitted,weregeophysicallyloggedwithsomeorallofthefollowingtools:deviation,gamma,density,caliper,neutron,dip.

• Geophysicalloggingoperatorsroutinelycalibratedtheirtoolsbetweenprograms.

• Coreholesweresampled,wherecorerecoverypermitted,aswholecorecollectedforcoalqualityanalysisandrockgeochemistry.

• Theresultsfromthegeophysicalloggingwereusedtodeterminethelithologyofthestratainthehole.

• Thecoredintervalsarecomparedtothegeophysicalloginordertodeterminesampleintervalsandcoreloss.

• SamplesfromtheseprogramsweresenttotheCrowsnestResourcesLimited(CNRL)companylaboratoryandtoLoringLaboratoriesinCalgary.

• Abulksamplingtestpitwasalsoexcavatedwitha219tonnesamplecollectedfrom7seams.ThesamplesfromthistestpitweretestedbyBirtleyLaboratoryinCalgary.

• Afurthercoalqualitydrillingprogramwasconductedin2018thatconsistedoffourPQcoreholesandabulksamplecomprisedof14,6inchcoreholes.ThePQholesweretestedattheBirtleyLabortoryinCalgary,ABwhilethe6inchholesweretestedbytheSGSLaboratoryinDelta,BC

Drillingtechniques

• Drilltype(e.g.,core,reversecirculation,open-holehammer,rotaryairblast,auger,Bangka,sonic,etc.)anddetails(e.g.,corediameter,tripleorstandardtube,depthofdiamondtails, face-samplingbitorothertype,whethercore isorientedand ifso,bywhatmethod,etc.).

• Avarietyofdrillingtechniqueswereutilizedonthisprojectincludingmainlycore,airrotaryoracombinationofboth.

• From1979to1989thedrillingwasdoneforCNRLusingtop-headdriveIngersollRand(IR)rotaryrigsandLongyear38diamondcorerigs.Corediameterwas17/8”NQcoreplussome6”diametercores.

• From1992to1998thedrillingwasdoneforManaltausingtop-headdriveFailing1250andIRrotaryrigsandanAckerdiamondcorerig.Corediameterwas17/8”NQcore.Samplingofcoalwasdonebythediamondcorerig.Rotarycoringtoobtain10cm(4”)diametercorewasalsoused.

• Corewasnotorientated.• Adrillingprogramwascompletedin2018consistingofPQ

diamondcoreholeswhichwereloggedplusabulksampleobtainedfrom6inchairrotaryholes.

• Drill samplerecovery

• Methodof recordingandassessing coreand chipsample recoveries and results assessed.

• Measurestakentomaximisesamplerecoveryandensure representative nature of the samples.

• Whether a relationship exists between samplerecoveryandgradeandwhethersamplebiasmayhave occurred due to preferential loss/gain offine/coarsematerial.

• Thecoredintervalswerecomparedtothegeophysicalloginordertodeterminesampleintervalsandcoreloss.

• Thedrillingcontractorwasresponsibleforensuringthatcorerecoverywasmaximized.

• Duetothenatureofthedeposit,corequalitywasgenerallynotaffectedbycoalrecovery.

• Corerecoveryrecordswerereportedonthewrittencoredescriptionsheetsforeachcorehole.Theaveragerecoveryfrom1992to1998wastypicallyinthe80%to100%rangeandwastypicallybetterthanthatachievedduringtheCNRLtenureperiod

• Corerecoveryforthe2018programwasbetween80and100%forthePQcoreholesand95to100%forthe6inchcoreholes.

Logging • Whether core and chip samples have beengeologicallyandgeotechnicallyloggedtoalevelofdetail to support appropriate Mineral Resource

• Allcorewasloggedusingsimilarloggingcriteriaincludedlithology,weathering,corequality/hardnessandobservationofstructuralfeatures.

Page 25: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

25

Criteria JORCCodeexplanation Commentaryestimation, mining studies and metallurgicalstudies.

• Whether logging is qualitative or quantitative innature.Corephotography.

• The total length and percentage of the relevantintersectionslogged.

• Theloggingwithrespecttothedownholelogsisquantitativeandcorephotographsareavailableinsomeinstances.

• Allboreholes,whereconditionspermitted,weregeophysicallyloggedwithsomeorallofthefollowingtools:deviation,gamma,density,caliper,neutron,dip.

• Geophysicalloggingoperatorsroutinelycalibratedtheirtoolsbetweenprograms.

• Thegeophysicallogswereusedtodeterminethelithologicalintervalsinrotaryholeswherenocorewasretrieved.Ingeneral,coalwasdeterminedbyitslowresponseonthedensitytool(~<1.8g/cc).Oncedeterminediftheintervalwascoalornot,alithotypeforrockintervalswasdeterminedbyobservingthegammalogresponse,whichhadthelowestresponseincleansandstoneswithlittleclaycontentandthehighestresponseinshalesduetothehighclaycontent,whichcontainedKthatemitsradiation.

• Allholesin2018wereloggedgeophysicallyanddipmeterwasrunonholes.The6inchcoreholeswereonlyloggedgeologically.

Sub-samplingtechniques andsamplepreparation

• Ifcore,whethercutorsawnandwhetherquarter,halforallcoretaken.

• Ifnon-core,whether riffled, tube sampled, rotarysplit,etcandwhethersampledwetordry.

• For all sample types, the nature, quality andappropriateness of the sample preparationtechnique.

• Quality control procedures adopted for all sub-samplingstagestomaximiserepresentativenessofsamples.

• Measures taken to ensure that the sampling isrepresentative of the in situ material collected,including for instance results for fieldduplicate/second-halfsampling.

• Whethersamplesizesareappropriatetothegrainsizeofthematerialbeingsampled.

• Allsamplestakenwereofwholecore.• Ofthefewrotarysampledholes,noneoftheanalytical

datawereusedintheresourceestimate.• Qualitycontrolwasprovidedviareferencingthe

geophysicallog.Theanalyticalresultswerecheckedforreasonablenessagainstthegammaanddensityresults.Thereshouldbeadirectrelationshipbetweendensityandashcontent.

• Wholecorematerialofeachseamorply,eitherassinglesamplesoraseriesofsamplesbydepthincrements,weresenttothelaboratoryforanalysis.AllcoalcoresampleswerebaggedonsitebeforebeingtransportedtoLoringandBirtleyLaboratoriesinCalgaryforcoalqualitytestwork.

Qualityofassaydata andlaboratorytests

• The nature, quality and appropriateness of theassaying and laboratory procedures used andwhether the technique is considered partial ortotal.

• For geophysical tools, spectrometers, handheldXRF instruments, etc, the parameters used indetermining the analysis including instrumentmake and model, reading times, calibrationsfactorsappliedandtheirderivation,etc.

• Natureofquality controlproceduresadopted (egstandards, blanks, duplicates, external laboratorychecks)andwhetheracceptablelevelsofaccuracy(ie lack of bias) and precision have beenestablished.

• Loring,SGS,andBirtleyLaboratoriesareISO9001certified,adheretoASTMpreparationandtestingspecificationsandhavequalitycontrolprocessesinplace.

Verification ofsampling andassaying

• The verification of significant intersections byeither independent or alternative companypersonnel.

• Theuseoftwinnedholes.• Documentation of primary data, data entry

procedures, data verification, data storage(physical and electronic) protocols.

• Discussanyadjustmenttoassaydata.

• Theverificationintermsofcoalqualitywasbycomparisonofanalyticalresultswiththegeophysicallog.Thesamplingandanalyticalresultswereoverseenandreviewedbyqualifiedgeologists.

• Anomalouslythickintersectionsinthedatasetwerecheckedtoensurecorrectness.

• Twinningofholesisgenerallynotrequiredexceptintheabsenceofageophysicallog.

• Ingeneralallcorelogsandintervalswererecordedusinghandwrittenlogs,someofwhichweretranscribedintospreadsheetsorothersoftware.

Page 26: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

26

Criteria JORCCodeexplanation Commentary

• Datapriorto1992havepapergeophysicallogs,howeverallholedrilledfrom1992–1998havelogasci(.las)filesindigitalformat.

• AllofthedatahasbeenstoredinanMSAccessdatabase.• 2018datawascomparedtohistoricalinformationandthe

geophysicallogstovalidatetheresultsobtainedLocationofdatapoints

• Accuracyandqualityofsurveysusedtolocatedrillholes (collar and down-hole surveys), trenches,mineworkingsandotherlocationsusedinMineralResourceestimation.

• Specificationofthegridsystemused.• Qualityandadequacyoftopographiccontrol.

• Allhistoricaldrillholeshavebeensurveyedusingtotalstationsurveyequipment.Extensivedocumentationofsurveytraversesisavailableaspartoftherecord.

• AllhistoricaldatapointsusedintheresourceestimateweresurveyedinNAD27.ThesewereconvertedtoNAD83forthepurposesofthisstudyandfuturework.

• Topographiccontoursat2mintervalsprovideappropriatetopographiccontrol.

• 2018drillholesweresurveyedusingGPSwithRTKcorrectionsresultinginaccuraciesof+/-5cminNAD83

Data spacinganddistribution

• DataspacingforreportingofExplorationResults.• Whether the data spacing and distribution is

sufficienttoestablishthedegreeofgeologicalandgrade continuity appropriate for the MineralResourceandOreReserveestimationprocedure(s)andclassificationsapplied.

• Whethersamplecompositinghasbeenapplied

• AveragedrillholespacingforTenasis110m,125mforGoathornand135mforTelkwaNorth.Theaveragecoreholespacing(withqualitydata)is237minTenas,173minGoathorn,and157minTelkwaNorth.

• Theresourceclassificationisbasedonanassessmentofthegeological(seamthickness)andcoalqualitycontinuity.Thishasthenbeensummarisedusingthedistancefromnearestacceptabledatapoint(drillhole)forcoalseamthicknessidentificationandanassessmentoftheconfidenceincoalseamcontinuity/correlation.ThedrillholespacingandcontinuitiesareconsideredappropriatetodefineMeasured,IndicatedandInferredResourcesonthefollowingbasis:

o Measured=within75mofdrillholeutilizedinthemodel(thatis,holesidentifiedasappropriateforuseinthecurrentresourceestimate);

o Indicated=within75mto150mofdrillhole;o Inferred=within150mto300mofdrillhole.

Orientation ofdata in relationto geologicalstructure

• Whether the orientation of sampling achievesunbiased sampling of possible structures and theextent to which this is known, considering thedeposittype.

• Iftherelationshipbetweenthedrillingorientationandtheorientationofkeymineralisedstructuresisconsideredtohaveintroducedasamplingbias,thisshouldbeassessedandreportedifmaterial.

• Drillingwasorientedoncrosssectionsat25mspacingorientedperpendiculartolocaltrend.

• Drillingwasverticalandcoalseamsdipatbetween0and65degrees.Seamthicknessinterceptsarecorrectedtotruefromapparentthicknessusingthelocallyinterpretedseamdip.

Samplesecurity • Themeasurestakentoensuresamplesecurity. • Noknownspecialsamplesecuritymeasureswereappliedatthetimeofsamplesubmissiontothelaboratories,

Audits orreviews

• The results of any audits or reviews of samplingtechniquesanddata.

• Extensivechecksandcomparisonsbetweendatahasbeenundertaken to verify and validate data for this resourceestimate

Section2 ReportingofExplorationResults

Criteria JORCCodeexplanation CommentaryMineraltenement andland tenurestatus

• Type, reference name/number, location andownershipincludingagreementsormaterialissueswith third parties, such as joint ventures,partnerships, overriding royalties, native titleinterests, historical sites, wilderness or nationalparkandenvironmentalsettings.

• The security of the tenure held at the time ofreporting along with any known impediments toobtainingalicensetooperateinthearea.

• Coaltenureisheldintheformofcoallicenses(22parcelsfor5579Ha)andfreeholdcoal(5parcelsfor1301Ha).ThecoallicensesareheldbyTelkwaCoalLimitedandBulkleyValleyCoalLimited(BVCL).

• TheBVCLlicenseownershipareunderanagreementsignedbetweenCDCandBVCLandthisagreementhasbeenassignedtoTelkwaCoalLimited..

• Thetenureissecureandmaintenancepaymentsarealluptodate.

• ThefreeholdareasareownedbyTelkwaCoalLimited

Page 27: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

27

Criteria JORCCodeexplanation Commentary

• Theonlyknownimpedimenttoobtainingalicensetooperatewillbenegotiationswithselectprivatelandholdersintheareafordevelopment.

Explorationdonebyotherparties

• Acknowledgment and appraisal of exploration byotherparties.

• Intheperiodfrom1979to1998atotalof867documenteddrillholeswerecompletedontheTelkwapropertybyCNRLandManalta.Ofthose,525weredrilledusingconventionalrotary methods, while 310 were cored. In 47 of the drill-holes, 59 piezometers were selectively installed at variousstratigraphic levels. 32 surficial bore-holes have also beencompleted to date on the property. In addition, there arereportsofabout30holesbeingdrilledbyCyprusandCanexsporadically intheperiodfrom1969to1978; thisdatahasnotbeencompiledduetothepoorqualityoftherecords.

• Additionally, surface geophysics has been conductedperiodicallybybothCNRLandManaltawiththeintentionoftracingcoalseamsonsurface.

Geology • Deposit type, geological setting and style ofmineralisation.

• ThesemediumtohighvolatilebituminouscoaldepositsarepartoftheRedRoseformationoftheSkeenaGroup.

• TheSkeenaGroupsedimentsoftheTelkwaCoalfieldareanerosional remnant of Lower Cretaceous sedimentary rockwhichwereinitiallydepositedwithinalargedeltaiccomplexalongthesouthern flanksof theBowserBasin.ThroughoutlateJurassicandearlyCretaceoustimetheBowserBasinwasthefocusofrapidsedimentation,subsidenceandincreasedtectonic activity, which resulted in thick accumulations ofcoal-bearingsedimentaryrock.

• ThegeologytypeclassificationforCanadiancoaldepositsis“complex”. Minimum open pit mineable thickness forcomplexcoaldepositsis0.8m.

• Themaineconomicseamsrangefromaminimummineablethicknessof0.8mto9minthickness.

Drill holeInformation

• A summary of all information material to theunderstandingoftheexplorationresults, includinga tabulation of the following information for allMaterialdrillholes:

• EastingandNorthingofthedrillholecollar• Elevation or RL (Reduced Level – elevation above

sealevelinmetres)ofthedrillholecollar• Dipandazimuthofthehole• Downholelengthandinterceptiondepth• Holelength• Iftheexclusionofthisinformationisjustifiedonthe

basisthattheinformationisnotMaterial,andthisexclusiondoesnotdetractfromtheunderstandingofthereport,theCompetentPersonshouldclearlyexplainwhythisisthecase.

• Modern exploration of the Telkwa Project started withCyprus Anvil Mining in 1978 and since then over 800explorationdrillholesand3bulksampleshavebeencarriedoutontheproperty.

• Other ancillary activities such as trenching, geologicalmappingandsurfacegeophysicshavealsobeencarriedout.

Dataaggregationmethods

• In reporting Exploration Results, weightingaveraging techniques,maximum and/orminimumgradetruncations(e.g.cuttingofhighgrades)andcut-off grades are usuallyMaterial and should bestated.

• Where aggregate intercepts incorporate shortlengthsofhighgraderesultsandlongerlengthsoflow grade results, the procedure used for suchaggregation should be stated and some typicalexamplesofsuchaggregationsshouldbeshownindetail.

• The assumptions used for any reporting of metalequivalentvaluesshouldbeclearlystated.

• Allcompositingwaslengthbased.• Seams consist of minimum 2:1 coal to rock ratio with a

maximuminternal“parting”of0.3mforTenascomplexand0.5mforGoathornandTelkwaNorthcomplex.

• Seam composites were made from compositing oflithological intervals (Coal or Parting) honouring the seamcode.

• Coal quality intervals are cross referenced with the seamcomposites

Relationshipbetweenmineralisationwidths andinterceptlengths

• TheserelationshipsareparticularlyimportantinthereportingofExplorationResults.

• If thegeometryof themineralisationwithrespecttothedrillholeangleisknown,itsnatureshouldbereported.

• Ifitisnotknownandonlythedownholelengthsarereported,thereshouldbeaclearstatementtothis

• Composited seam intervals were assigned a dip from ageologicalsectionandthetruethicknessoftheintervalswasestablished

Page 28: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

28

Criteria JORCCodeexplanation Commentaryeffect (e.g. ‘down hole length, true width notknown’).

Diagrams • Appropriate maps and sections (with scales) andtabulationsofinterceptsshouldbeincludedforanysignificantdiscoverybeing reported. These shouldinclude,butnotbe limited to, aplan viewofdrillhole collar locations and appropriate sectionalviews.

• Diagrams have been developed for the project by TelkwaCoalLimitedinaccordancewithJORCCoderequirements.

• Diagramsincludelocationmaps,drillholeplotsandgeologycross-sections.

Balancedreporting

• Where comprehensive reportingof all ExplorationResultsisnotpracticable,representativereportingofboth lowandhighgradesand/orwidthsshouldbe practiced to avoid misleading reporting ofExplorationResults.

• Notapplicable.Whilefulldetailsofalltheexplorationresultshavenotbeenreleased,therearenosignificantormaterialissuesnotsummarisedinthisTable1.

Othersubstantiveexplorationdata

• Otherexplorationdata,ifmeaningfulandmaterial,shouldbereported,including(butnotlimitedto):

• Geologicalobservations• Geophysicalsurveyresults• Geochemicalsurveyresults• Bulksamples–sizeandmethodoftreatment• Metallurgicaltestresults• Bulk density, groundwater, geotechnical and rock

characteristics• Potentialdeleteriousorcontaminatingsubstances

• Bulk samples have contributed considerably to theunderstanding of the quality characteristics of the Telkwacoalsandhavebeenextractedfromeachofthethreemainresource areas. On each, a complete suite of coal qualityanalyses was performed, including testing on a variety ofsimulatedpreparationplantproducts.

• In1983,a219tonnebulksamplewascollectedfrom7majorseamswithintheGoathornEast(Pit3)area.In1989,abulksamplewasextractedfromtheBowser(TelkwaNorth–EastPit)areaviaalarge-diametercoringprogram.And,in1996,an 80 tonne bulk sample was collected from the threemineableseamsinTenasarea.

• Totalsulphurandthreeformsofsulphur(organic,inorganic,andsulphate)havebeenestimatedforthevariousseamssoastodeterminethepotentialforwatertreatment.

Futurework • Thenatureandscaleofplannedfurtherwork(e.g.testsforlateralextensionsordepthextensions,orlarge-scalestep-outdrilling).

• Any additional future work will involve drilling mainly insupport of acid rock drainage, structural understanding,hydrogeology,andgeotechnicalevaluations.

• Some2dseismicprogramsmayalsohappentoaidwithfaultlocationsandoverburdendepthsandmaterialtypes.

Section3 EstimationandReportingofMineralResources

Criteria JORCCodeexplanation CommentaryDatabaseintegrity

• Measurestakentoensurethatdatahasnotbeencorruptedby, forexample, transcriptionorkeyingerrors,betweenitsinitialcollectionanditsuseforMineralResourceestimationpurposes.

• Datavalidationproceduresused.

• By overlaying the geophysical log density data on thelithological intervals, the coal intercepts were assigned adensityvaluewhichwasthencheckedforreasonableness(i.e.density from geophysics should be between 1.30 and 1.80g/cc).

• Downholegeophysicaldatawasused tovalidateandverifyseam intercepts and to assist with seam correlation andstratigraphy.

• Otherdatavalidationincludedvisualinspectionofeveryseamintersection on cross section to allow for proper seamcorrelations and to look for anomalies in the stratigraphicinterval.

• ForDatacaptureandcurrentdatabasestorageMSAccessisutilized, along with cataloguing and electronic filing of allpertinentdatastoredontheSRKserver.

Sitevisits • Comment on any site visits undertaken by theCompetentPersonandtheoutcomeofthosevisits.

• AsitevisitwasconductedonApril11,2017by:o Ron Parent – Resource Competent Person

(Independent)o BobMcCarthy–ReserveCompetentPerson(SRK)o EdSaunders–Geotech(SRK)o DavidMaarse–WaterLead(SRK)o KarlHaase–Processing(Sedgman)

• The visit consisted of an aerial tour via helicopter and agroundtouronaccessibleroads.Thecorestoragefacilitywasobservedaswellasseveraloutcrops.

• RonParentalsospentfiveweeksonsitesupervisingthe2018explorationprogram.

Geologicalinterpretation

• Confidence in (or conversely, the uncertainty of)thegeologicalinterpretationofthemineraldeposit.

• There is a high level of confidence in the geologicalinterpretation,especially inareasof theresourcethathavebeenincludedinthereserves.

Page 29: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

29

Criteria JORCCodeexplanation Commentary

• Nature of the data used and of any assumptionsmade.

• Theeffect,ifany,ofalternativeinterpretationsonMineralResourceestimation.

• The use of geology in guiding and controllingMineralResourceestimation.

• Thefactorsaffectingcontinuitybothofgradeandgeology.

• Stratigraphicsequenceiswellunderstoodandcorrelationsarerelativelystraightforward:thecurrentinterpretationhasmodifiedtheseamnomenclatureinplaces.

• Structureandfaultingarecommonlyshallowdippingwithpredominantlynormalfaultingupto100mdisplacement.LocalthrustfaultingisobservedintheGoathornarea.

• Limitsofthedepositsneedtobebetterdefined;sincesomeofthesub-croporstructurallycontrolledboundarieshavenotbeenfullydefined.

• Noalternativeinterpretationsareconsideredasthecurrentinterpretationiswellsupportedbyavailabledata.

• Thegeologicalmodelisathicknessmodel,whosedataiscompositedfromdrillholeseamintersectionsandconfirmedbygeophysicallogintercepts.

• Thecoalqualityparametersdonotaffectthequantityofcoal,buttherecoveryandgenerationofasuitableproduct.

Dimensions • TheextentandvariabilityoftheMineralResourceexpressedaslength(alongstrikeorotherwise),planwidth,anddepthbelowsurface to theupperandlowerlimitsoftheMineralResource.

• TheTenasdepositisapproximately3kmnorth-southby2kmeast-west, reaching a maximum depth of 400 m for thelowermost1LeSeam.

• GoathornEastis5kmby2kmreachingamaximumdepthof650mforlowermost1Seam.

• GoathornWestis1.5kmby800mreachingamaximumdepthof300mlowermost1Seam.

• TelkwaNorthis1.6kmby3.6kmreachingamaximumdepthof300mforthelowermost2Seam.

Estimationand modellingtechniques

• Thenatureandappropriatenessoftheestimationtechnique(s) applied and key assumptions,including treatment of extreme grade values,domaining, interpolation parameters andmaximum distance of extrapolation from datapoints. Ifacomputerassistedestimationmethodwas chosen include a description of computersoftwareandparametersused.

• The availability of check estimates, previousestimates and/or mine production records andwhether the Mineral Resource estimate takesappropriateaccountofsuchdata.

• The assumptionsmade regarding recovery of by-products.

• Estimation of deleterious elements or other non-grade variables of economic significance (egsulphurforacidminedrainagecharacterisation).

• Inthecaseofblockmodelinterpolation,theblocksizeinrelationtotheaveragesamplespacingandthesearchemployed

• Any assumptions behind modelling of selectiveminingunits.

• Coalqualityandseamthicknessparameterswereestimatedusing inversedistance squaredwithin the seamwireframeswhichcontrolthedistributionofinterpolatedvaluesin3D

• Themodelisofthecoalseamsonlyandtheinterburdenhasbeenmodelledbydefaultbuttosufficientdetailtoassistwithwasterockcharacterisationandwasterockmanagement.

• The current resourceestimate is comparablewithpreviousresourceestimatescompletedin1989,1997,and2015

• Sulphur (total, organic, inorganic, and sulphate) have beeninterpolatedinthemodelwheredatawasavailable

• The model block size ranges from 5 to 25 m along strike(TenasandTelkwaNortharerotated),5to10mdowndipand5minheight.

• Average drillhole spacing for Tenas is 110 m, 125 m forGoathornand135mforTelkwaNorth.Theaveragecoreholespacing(withqualitydata)is237minTenas,157minTelkwaNorthand173minGoathorn.

Estimationand modellingtechniques(continued)

• Any assumptions about correlation betweenvariables.

• Description of how the geological interpretationwasusedtocontroltheresourceestimates.

• Discussion of basis for using or not using gradecuttingorcapping.

• The process of validation, the checking processused, the comparison ofmodel data to drill holedata,anduseofreconciliationdataifavailable.

• Akeyassumptionutilized in the resourceestimatewas therelationshipbetweenashcontentonanairdriedbasisandbulkdensityusedforconversionofvolumetotonnesusingthe formula 1.2713+0.0092*ash% (adb), which wasdeveloped from the relationship between ash and bulkdensitypresentedinGSCPaper88-21.

• The geological interpretation is based on the “stacking” ofseam bottoms along 25 m spaced cross sections from thelowermostseamupward.

• Themainvalidationmethodusedwasacomparisonbetweenwireframesolidsvolumeandvolumegeneratedfromthe3Dblockmodelaftercoding.

• The model accurately represents the drilled seam truethicknessesto+/-0.1matagivenXYlocation.Theelevationsmayvaryupto3matanydrillholeintercept.Thisisduetothesectionalnatureofthemodellingprocess,projectingallseamintersectionsamaximumof12.5mtothenearestcrosssection.

Page 30: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

30

Criteria JORCCodeexplanation CommentaryMoisture • Whetherthetonnagesareestimatedonadrybasis

or with natural moisture, and the method ofdeterminationofthemoisturecontent.

• Thetonnagesareestimatedonanair-driedbasis,whilethemoisturecontentmeasurementsareavailablewithinthecoalqualitytestingresults.

Cut-offparameters

• Thebasisoftheadoptedcut-offgrade(s)orqualityparametersapplied.

• All coal quality parameters modelled were on an air-driedbasis.

• To assist in developing the coal reserves, coal yields werebasedonwashabilitytestingatacut-pointof1.65g/cc.

• Cleancoalobjectiveoftheprocesswillbe9.50%withatargetsaleableproductattheportat10%moisture.

Mining factorsorassumptions

• Assumptions made regarding possible miningmethods,minimumminingdimensionsandinternal(or, if applicable, external) mining dilution. It isalways necessary as part of the process ofdetermining reasonable prospects for eventualeconomic extraction to consider potential miningmethods, but the assumptions made regardingminingmethodsandparameterswhenestimatingMineral Resources may not always be rigorous.Wherethisisthecase,thisshouldbereportedwithan explanation of the basis of the miningassumptionsmade.

• Minimum coal ply thickness = 0.80m for Tenas,Goathorn,andTelkwaNorth.

• Maximumincludedpartingthickness=0.30mforTenasand0.50mforGoathornandTelkwaNorth

• Minimumcoal:rockratio=2:1• Theresourcesareallconsideredpotentiallysurfacemineable,

andrestrictedtoa20:1BCM:inplacecoaltonnecut-offstripratio depth. Despite there being previous undergroundmining on the property, no underground resources areconsideredatthistimeforthistable.

Metallurgicalfactors orassumptions

• Thebasisforassumptionsorpredictionsregardingmetallurgicalamenability.Itisalwaysnecessaryaspart of the process of determining reasonableprospects for eventual economic extraction toconsiderpotentialmetallurgical methods,buttheassumptions regarding metallurgical treatmentprocesses and parameters made when reportingMineral Resources may not always be rigorous.Wherethisisthecase,thisshouldbereportedwithan explanation of the basis of the metallurgicalassumptionsmade.

• Metallurgicalamenabilitywassimulatedfromtestworkusingindustrystandardmodelsforcoalbeneficiation

• Ashcontentofdilutionisassumed80%,sizingofAshissimilarto sizing of coal andwith a density of 2.50 g/cc. Thiswasbasedoffresultsofthebulksamplecompletedin1996whichusedcompleteddilutionanalysis.

Environmentalfactors orassumptions

• Assumptions made regarding possible waste andprocess residue disposal options. It is alwaysnecessary as part of the process of determiningreasonable prospects for eventual economicextractiontoconsiderthepotentialenvironmentalimpacts of the mining and processing operation.Whileat thisstagethedeterminationofpotentialenvironmental impacts, particularly for agreenfields project, may not always be welladvanced,thestatusofearlyconsiderationofthesepotential environmental impacts should bereported. Where these aspects have not beenconsidered this should be reported with anexplanation of the environmental assumptionsmade.

• Potential for ARD was studied extensively in the 1990s tosupportfeasibilitystudiesandenvironmentalassessments

• ThePropertyhostsbothnon-PAGandPAGseaminterburdenand overburden rock. Tenas, Goathorn and Telkwa Northhavebeencharacterizedtoestimatenon-PAGandPAGrockineachphase.

• The ratio of NP to MPA, NPR was used as the basis forclassifyingeachinterburdenandtheoverburdenzoneasnon-PAGorPAG. Muchof the rock isnon-PAGwhileall of theoverburden material and material excavated in themanagementpondsisnon-PAG

• Methods used to estimate NP and MPA in the 1990s aredifferent from thoseused currently and to varyingdegreesover-estimate bothNP andMPA resulting in uncertainty inthethresholdNPRusedtodelineatePAGandnon-PAGstrata.Based on the exploration program conducted in 2018,moderntestingmethodswereusedtomeasureNPandMPAand also allowed the historical data to be correlated tomodernvalueswhichallowedareduction intheamountofuncertainityinNPandMPAvaluesandwhichthresholdNPRvaluetouse.

• TheratioselectedtodefinePAGrock isNPR<2.0whichstillallows for the uncertainty in NP. A lower value may besuitableasunderstandingofthemineralogicalcharacteristicsoftherockimproves.

• Toassignestimatedvolumestonon-PAGorPAG,thesampleswithineachphaseandseaminterburden/overburdenwerebinnedintotwoNPRgroups,<2.0,and>2.0.

• TheintentofthemineplanwastoscheduleandplaceallPAGrock into designated management ponds that are floodedwithwatertopreventrockoxidationandacidgeneration.

• ThereisnoTailingsManagementFacility.BothCCRandfinesrejectswillbeplacedindesignatedsurfacestoragepiles,andperiodically capped with compacted overburden covers topreventacidrockdrainage.

Page 31: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

31

Criteria JORCCodeexplanation Commentary

• Aflocculationsystemwillbeusedforwaterpriortodischargetomeetregulatoryrequirmentsfortotalsuspendedsolids.

• FurtheroptimizationofPAGmanagementincludingblendingPAGrockintonon-PAGrockand/orusingalowercutofftosegregatePAGrockfronnon-PAGrockshouldbeinvestigatedintheoperationsphaseoftheproject.

Bulkdensity • Whetherassumedordetermined.Ifassumed,thebasis for the assumptions. If determined, themethodused,whetherwetordry,thefrequencyofthe measurements, the nature, size andrepresentativenessofthesamples.

• Thebulkdensityforbulkmaterialmusthavebeenmeasuredbymethodsthatadequatelyaccountforvoid spaces (vugs, porosity, etc), moisture anddifferences between rock and alteration zoneswithinthedeposit.

• Discuss assumptions for bulk density estimatesused in the evaluation process of the differentmaterials.

• The bulk density (BD) was assumed based on an empiricalrelationshipwiththeairdriedashforhighvolatilebituminouscoal. Thisempirical formulawasextracted fromTable1ofGeologicalSurveyofCanadaPaper88-21:

BD(adb)=1.2713+0.0092xASH(adb)

Classification • The basis for the classification of the MineralResourcesintovaryingconfidencecategories.

• Whetherappropriateaccounthasbeentakenofallrelevant factors (ie relative confidence intonnage/gradeestimations,reliabilityofinputdata,confidence in continuity of geology and metalvalues, quality, quantity and distribution of thedata).

• Whether the result appropriately reflects theCompetentPerson’sviewofthedeposit.

• Theresourceclassificationisbasedonanassessmentofthegeological(seamthickness)andcoalqualitycontinuity.

• This has then been summarised using the distance fromnearest acceptable data point (drillhole) for coal seamthicknessidentificationandanassessmentoftheconfidenceincoalseamcontinuity/correlation.

• The drillhole spacing and continuities are consideredappropriate to define Measured, Indicated and InferredResourcesonthefollowingbasis:

o Measured=within75mofdrillholeutilizedinthemodel (that isholes identifiedasappropriateforuseinthecurrentresourceestimate);

o Indicated=75mto150mofdrillhole;o Inferred=150mto300mofdrillhole.

• The surface resources (those resources considered to haveprospectstobeopenpitmineable)arerestrictedtowithina20:1COSRbcm/tonnecoalfromsurface,whichisconsideredreasonableforcoalofthistype.

Audits orreviews.

• The results of any audits or reviews of MineralResourceestimates.

• Peer review by SRK personnel was carried out on thegeologicalinterpretation.Noexternalauditorreviewoftheresource estimate for this model was carried out. Theresourceestimatesaresimilartothosefrompreviousstudiesperformedwith the samedataandanydifferencesarenotdeemedtobematerial.

Discussion ofrelativeaccuracy/confidence

• Where appropriate a statement of the relativeaccuracy and confidence level in the MineralResourceestimateusinganapproachorproceduredeemedappropriatebytheCompetentPerson.Forexample, the application of statistical orgeostatistical procedures to quantify the relativeaccuracyof theresourcewithinstatedconfidencelimits, or, if such an approach is not deemedappropriate,aqualitativediscussionofthefactorsthat could affect the relative accuracy andconfidenceoftheestimate.

• Thestatementshouldspecifywhetheritrelatestoglobal or local estimates, and, if local, state therelevant tonnages, which should be relevant totechnicalandeconomicevaluation.Documentationshould include assumptions made and theproceduresused.

• These statements of relative accuracy andconfidence of the estimate should be comparedwithproductiondata,whereavailable.

• Theresourcesestimatesareassumedtobewithin+/-10%to15% on a global basis (or over an assumed annual miningvolume)andthisaccuracyisconsideredappropriatefortheclassification classes of Indicated and Measured CoalResources,andappropriatetosupportat leastaFS levelofstudyandreserveassessment.

Page 32: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

32

Section4 EstimationandReportingofOreReserves

Criteria JORCCodeexplanation Commentary

MineralResourceestimateforconversiontoOreReserves

• DescriptionoftheMineralResourceestimateusedasabasisfortheconversiontoanOreReserve.

• Clear statement as to whether the MineralResourcesare reportedadditional to,or inclusiveof,theOreReserves.

• TheTenas,GoathornandTelkwaNorth resourceestimateswerecarriedout followingtheguidelinesof theJORCCode(2012)bySRKConsulting(Canada)Ltd.andreportedinJune2017. The Tenas resource estimate was updated andreportedbyTelkwaCoalLtd.inOctober2018

• TheMineralResourcesareinclusiveoftheOreReserves.

Sitevisits • Comment on any site visits undertaken by theCompetentPersonandtheoutcomeofthosevisits.

• Ifnositevisitshavebeenundertaken,indicatewhythisisthecase.

• TheCompetentPersonfortheOreReservesestimationisBobMcCarthy.Mr.McCarthy visited the site on April 11, 2017alongwithAllegianceCoalpersonnel.

• Thevisitconsistedofanaerialtourviahelicopterandagroundtouronaccessibleroads.Thecorestoragefacilitywasobservedaswellasseveraloutcropsandwatercourses.

Studystatus • Thetypeand levelofstudyundertakentoenableMineral Resources to be converted to OreReserves.

• The Code requires that a study to at least Pre-Feasibility Study level has been undertaken toconvertMineral Resources toOreReserves. Suchstudies will have been carried out and will havedetermined a mine plan that is technicallyachievable and economically viable, and thatmaterialModifyingFactorshavebeenconsidered.

• TelkwaCoalLimitedcompletedtwoprefeasibilitystudiesontheTelkwaCoalProjectin2017.

• TheOreReserveswere reported in conjunctionwith thosestudiesinJuneandSeptember2017.

• AnupdatedorereservefortheTenasdepositisbasedupona feasibility level study where geological confidence issufficientandmineplanninghasbeencompletedtoa levelrequiredtodeterminetechnicalandeconomicviability.

• Modifying factors consideredmaterial to the developmentand economic extraction of the coal resource have beentakenintoaccount.

Miningfactorsorassumptions

• Themethodandassumptionsusedasreportedinthe Pre-Feasibility or Feasibility Study to converttheMineralResourcetoanOreReserve(i.e.eitherby application of appropriate factors byoptimisationorbypreliminaryordetaileddesign).

• The choice, nature and appropriateness of theselected mining method(s) and other miningparametersincludingassociateddesignissuessuchaspre-strip,access,etc.

• The assumptions made regarding geotechnicalparameters(e.g.pitslopes,stopesizes,etc.),gradecontrolandpre-productiondrilling.

• The major assumptions made and MineralResourcemodelusedforpitandstopeoptimisation(ifappropriate).

• Theminingdilutionfactorsused.• Theminingrecoveryfactorsused.• Anyminimumminingwidthsused.• Themanner inwhich InferredMineral Resources

areutilisedinminingstudiesandthesensitivityoftheoutcometotheirinclusion.

• The infrastructure requirements of the selectedminingmethods.

• TheTenasprojectusesacombinationtruckandshovelopencut mining as well as dozer pushing to execute an up-dipmining method for areas of shallower dipping coal seam(<22°). At steeper dips (three of the nine phases), moreconventionalbenchminingofwasteandcoalisperformed.

• The basis of design is a lerch-grossman economic pitoptimization combinedwitha cut-off strip ratioanalysis todeterminetheultimatepitlimits.Theultimatepitshellwasthen developed into a detailed pit design and broken intopracticalpitphasesandminingcuts.

• Conventionalmobileequipment(excavatorsandhaultrucks)is used for overburden and waste rock mining. non-PAGinterburden is dozer pushed on to mined out footwallswheneverpossible.

• For the Tenas project, water management ponds areexcavatedtoallowsub-aqueousstorageofPAGrockhauledfromthepit.

• Coallossanddilutionweremodelledasskinsonthehangingwall and footwall of each seam. The total coal loss anddilutionskinthicknessappliedtotheTenasdepositwas15cmfor1/1U-seamand20cmforC-seam(through-seamblastinginvolved).DilutionandcoallossfortheGoathornandTelkwaNorthpitweresetat20cmtotal.

• Theminimumseamthicknessforminingwassetat0.80mforalldeposits.

• PitslopecriteriawereupdatedbySRKaspartoftheFSforTenas andwere largelydrivenby the slopeof thebeddingseamsineachsectorofthepit.Manypitwallsaresimplyfootwallsdaylightingintotheoverburdenandtopography.Wherehigh wall benching is required the bench face angles aredetermined by the slope of the bedding plane and 8mbenchesarerequiredoveramaximumheightof45m.Thus,pit slopes vary between 35-60 degrees. Pit slopes in areaswithidentifiedfaultsthatreducetherockmassstrengthwereadjustedappropriately.

• Coalresourceswithlimitedgeologicalcertaintyareclassifiedasinferredandcannotbeconvertedtocoalreserves.Thus,any inferredcoal resourcesare consideredaswaste in thisstudy and there are no inferred resources included in theproduction schedule or coal reserve estimate. The TenasdeposithasnoInferredresources

Page 33: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

33

Criteria JORCCodeexplanation Commentary

• Thefinancialevaluationoftheproposedmineplanissufficienttosupporteconomicviabilityofthecoalreserve.

• TheprimaryinfrastructurerequiredforthedevelopmentoftheopencutsatTelkwaarewatercontainmentandmanagementfacilities.Numerousditchesarerequiredforbothcontainingcontactwateranddivertingsomenon-contactwaterfromtheminingareas.Contactwateriscollectedinsedimentationpondsbeforedischarge.

Metallurgicalfactorsorassumptions

• The metallurgical process proposed and theappropriateness of that process to the style ofmineralisation.

• Whether the metallurgical process is well-testedtechnologyornovelinnature.

• The nature, amount and representativeness ofmetallurgical testworkundertaken, thenatureofthe metallurgical domaining applied and thecorresponding metallurgical recovery factorsapplied.

• Any assumptions or allowances made fordeleteriouselements.

• Theexistenceofanybulksampleorpilotscaletestwork and the degree to which such samples areconsidered representative of the orebody as awhole.

• Formineralsthataredefinedbyaspecification,hasthe ore reserve estimation been based on theappropriatemineralogytomeetthespecifications?

• Process flowsheet is a traditional 2-circuit approach withcustomisedequipmentsizingtoallowfornominalthroughputforthisspecificcoal

• Allmetallurgical processes and technologyhavebeenusedextensivelywithinthecoalindustryworldwide

• TestworktodatewascompletedunderAustralianStandardmethodsatthetimeofthetestworkandissuitableforthislevelofstudy

• Ithasbeenassumedthattheorganic liquidsusedforfloat-sinkhashadnoeffectonthecoalproperties

• 2 Bulk samples have been completed in the pastwith onepilot scale testwork being completed. Pilot testwork wascompletedona19mmx0mmsizefractionusingaDSMheavymediaconefor19mmx0.6mmand2stagespiral/wateronlycyclone for below 0.6mm fraction. Due to the testworkpractices this pilot wash was not suitable for use as aframeworkforthisstudyandtheresultswerenotusedintheanalysis.

• A further coal quality and washability program wascompleted in2018usingcurrent lab techniquesandabulksample wash was performed by SGS at their Lakefield lablocatedinOntairio,Canada.

• 1998,1996Bulksamplesand2018testworkwereusedintheprocesssimulationsanditisbelievedfromtheseresultsthatthecoalisfairlyhomogeneouswithinseams.

• Thecurrentproposedplantwillproduceacleancoalwhichisofmarketablespecification

Environmental • The status of studies of potential environmentalimpacts of the mining and processing operation.Details of waste rock characterisation and theconsideration of potential sites, status of designoptions considered and, where applicable, thestatusofapprovalsforprocessresiduestorageandwastedumpsshouldbereported.

• Forgeochemistrydata,refertosectiontitled“Environmentalfactorsorassumptions”

• Existingdataonbackgroundsurfaceandgroundwaterqualityand flowhasallowed for thedevelopmentof a conceptualsitewaterbalanceandpreliminarywaterqualitymodelling.Thesewillberevisedtoadetailedsitewaterbalanceandfinalwaterqualitymodellingpriortothesubmissionofregulatoryapplications.

• The results indicate that due to background levels alreadyexceedingBCWQGthatasite-specificwaterqualityobjectivewillneedtobedevelopedforaluminium.

• Inaddition,duetotheconservativenessofthewaterqualitymodelutilizingMDLwheremeasurementswerebelowMDL,anumberofparameterswerepredictedtoexceedBCWQG.It is anticipated that with better water quality data usinglower MDLs that the model can be refined and theparameterscouldachievecompliance

• If necessary, a water treatment plant may need to beintroducedfortheco-precipitationofelements.

Infrastructure • The existence of appropriate infrastructure:availabilityof land forplantdevelopment,power,water, transportation (particularly for bulkcommodities),labour,accommodation;ortheeasewithwhich the infrastructurecanbeprovided,oraccessed.

• TheTelkwaSiteisservedbythefollowinginfrastruceforthedevelopment:o A138-kVpowerlinetotheeastanda25-kVpowerline

tothenorthofthepropertyo Ahighcapacitymainrail lineownedandoperatedby

CNrailwhichisalreadyinuseforthetransportofcoalunit trains is approximately 7 kilometers east of theproperty.InitialdiscussionbetweenAllegianceandCNrail have occurred and CN has agreed that the railcapacityissufficientforthisproject

o TheportofPrinceRupertislocated375kmtothewestandhassufficientcapacityforthisproject

Page 34: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

34

Criteria JORCCodeexplanation Commentary

• Theprojectis locatedtonearbytownsofSmithers,Telkwa,andHoustonforthesupplyandaccommodationoflabour

• ThesiteiscurrentlyservicedbyaForestryServiceRoadandcurrenttopographywillallowtheconstructionofadedicatedcoalhaulroadbetweentherailandtheproposedplantsite

• The proposed plant sitewill be on crown landwith a coallicenseownedbytheproponent

Costs • Thederivationof,orassumptionsmade,regardingprojectedcapitalcostsinthestudy.

• Themethodologyusedtoestimateoperatingcosts.• Allowances made for the content of deleterious

elements.• The derivation of assumptionsmade of metal or

commodityprice(s),fortheprincipalmineralsandco-products.

• Thesourceofexchangeratesusedinthestudy.• Derivationoftransportationcharges.• The basis for forecasting or source of treatment

andrefiningcharges,penaltiesforfailuretomeetspecification,etc.

• The allowances made for royalties payable, bothGovernmentandprivate.

• ThecostingoftheTenasFShasassumedanowner-operatedapproach,wherein,allinfrastructureandequipmentisleasedorpurchasedbyTCLandoperatedbyTCL.

• Costsaredevelopedfromfirstprincipleswhereverpossible,utilizing inputs from engineering firms and vendors. Thedesignsuponwhichthesecostsarebasedaretofeasibility/class3level.

• Engineering work has been undertaken to establish thecapitalcostrequirementfortheproject,includingthemine,processingplant,railandroads,aswellasothersupportinginfrastructure.

• Capitalcostsfortheprojectaresupportedbyworkby:o SRK Consulting – mining, geochemistry, water

management,hydrogeologyo Sedgman–processplanto HooperEngineeringandMorchEngineeringInc.–rail

infrastructureo Bulkley Electric – powerline and substation

construction• Operatingcostsarebasedonworkby:

o SRK Consulting – allmining costs inclusive ofmobileequipment,supportservicesandlabour

o SRKConsulting–watermanagemento Sedgman–processingandcoalhandlingo TCL–sitegeneral&administrativecosts,o HooperEngineering–railo IEG-relamation

Revenuefactors

• Thederivationof,orassumptionsmaderegardingrevenue factors including head grade, metal orcommodityprice(s)exchangerates,transportationand treatment charges, penalties, net smelterreturns,etc.

• The derivation of assumptionsmade of metal orcommodity price(s), for the principal metals,mineralsandco-products.

• ACLplanstoproduceamid-volatilesemi-softcokingqualitycoalsatanominalrateof750,000cleantonnesperannum.

• Mid-volatile semi-coking coals are scarce in supply andarepricedatapremiumtothemorecommonhigh-volatilesemi-cokingcoals.

• CommoditypricingfortheprojectwasadvisedbyACLbasedonthestudyconductedbyKobieKoornhof&Associates.

• AnaveragepriceofUS$120/tcoalproductwasassumedforthe Tenas project for 2021 and 2022, and 2023 onwards,US$114/t

• According toKobieKoornhofandAssoc, currentpricing forTelkwacoalisUS$132.5/t.

• Anexchangerateof1.33CA$:US$wasapplied tocalculatetherevenue.

• PrivateroyaltytoAltiusMineralwasappliedatarateof3.0%onrevenue.

• ItochuCorporationofJapanisthecompany’ssolesalesandmarketingagentand receivesa sales feeof3%of theFOBprice,1.5%onsale,and1.5%afterEBITDAassumingEBITDAispositive.

Marketassessment

• The demand, supply and stock situation for theparticular commodity, consumption trends andfactorslikelytoaffectsupplyanddemandintothefuture.

• Acustomerandcompetitoranalysisalongwiththeidentification of likely market windows for theproduct.

• Priceandvolumeforecastsandthebasisfortheseforecasts.

• Forindustrialmineralsthecustomerspecification,testing and acceptance requirements prior to asupplycontract.

• PerKobieKoornhofandAssoc,demandforhardcokingcoaliscontinuingatrobustlevelsassteelindustryfundamentalsremainastrongdriverforseabornecokingcoalimports.Thecurrentconstraintstosupplyavailabilityforhighqualitycokingcoalsislikelytoremainfortheforeseeablefuture,sinceglobalcokingcoalsupplyisnotcomingonlineatapacethatwillupsetthecurrentsupply/demandbalance.Inthemediumterm,thebiggestrisktometallurgicalcoalpricingliesinapossibleglobaleconomicslowdown,fuelledbythefearofburgeoningtradewars.

• PerKobieKoornhofandAssoc.,thecoaltobeproducedatTelkwacanbeclassifiedasamediumvolatilesemi-soft

Page 35: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

35

Criteria JORCCodeexplanation Commentary

cokingcoal(MVSSCC)andassuchisexpectedtofindamarketintheinternationalsteelindustry.

• TelkwaMVSSCCisexpectedtobewellreceivedduetolimitedavailabilityofMVSSCContheseabornemarket,incontrasttothemorereadilyavailablehighvolatileSSCCcoalsfromNSW.ThemarketshouldreactfavourablytotheintroductionofanewMVSSCC,notonlyasdiversificationfromAustralia,butalsoduetothefactthatCanadianSSCCsupplieshavelargelybeeneliminatedwiththeclosureoftheCoalMountainoperation.

• Competitorcoalsare:o HVSSCCfromHunterValleyinNSW,Australia;ando MVSSCCfromCentrlQueensland,Australia.

Economic • Theinputstotheeconomicanalysistoproducethenet present value (NPV) in the study, the sourceandconfidenceoftheseeconomicinputsincludingestimatedinflation,discountrate,etc.

• NPV ranges and sensitivity to variations in thesignificantassumptionsandinputs.

• Anafter-taxeconomicmodelwaspreparedbytheCompany,substantiallyatmonthlyrests,totesttheeconomicviabilityoftheCoalReserve.

• Theeconomicmodeltookintoaccountprojectrevenue,freightandsellingcosts,marketingfeetoItochu,royaltytoAltiusMinerals,capitalcosts,operatingcostsandadministrativecosts.

• Allowancewasmadeintheeconomicmodelforfinancingthemobilefleetbywayofleaseforthestart-upandearlyoperationalphases.

• Theprojecteconomicswereevaluatedusingastandarddiscountedcashflowmethodatanominalmid-perioddiscountrateof8%.Noallowancewasmadeforinflation.

• TheeconomicanalysiswasconductedinCanadiandollars.• ResultsarereportedinUSdollarsusinganexchangerateof

1.33CAD:USDandinAustraliandollarsusinganexchangerateof1.06AUD:CAD..

• Basedontheeconomicanalysis,thecurrentmineplanresultsinapositivepost-taxNPV8%ofUS$185MandanIRRof45%.

• Sensitivityanalysesshowedthattheprojectcanwithstanda30%decreaseincommoditypricesresultinginpositiveposttax NPV8% of $22M and post tax IRR of 12%. The projectwouldalsosustainpositivereturnwitha30%increaseofbothcapitalandoperatingcostsresultinginapost-taxNPV8%of$80Mand19%post-taxIRR.

Social • The status of agreements with key stakeholdersandmattersleadingtosociallicencetooperate.

• The Property is within the traditional territory of theWet’suwet’en (OW). In April 2017, the company signed aCommunicationandEngagementAgreementwiththeOW.

• The company shares all its raw data collected byenvironmentalmonitoringwiththeOW,andactivelyinvolvestheOWinallkeydecisionsanddevelopments.

• The companyhas commencedengagementwith several ofthelandowners,stakeholdergroupsandlocalandprovincialgovernment. A comprehensive community engagementstrategyhasbeendevelopedandbeingimplemented.

• The company has engaged local community (includingholding two public open houses in Telkwa), Smithers andTelkwa environmental expertise to carry out the baselinedataprograms

• Thecompanyhasestablishedcommunicationprotocolswiththe Government regulators as it progresses through theenvironmentalassessmentandpermittingstage.

Other • Totheextentrelevant,theimpactofthefollowingon the project and/or on the estimation andclassificationoftheOreReserves:

• Anyidentifiedmaterialnaturallyoccurringrisks.• The status of material legal agreements and

marketingarrangements.• The status of governmental agreements and

approvalscriticaltotheviabilityoftheproject,such

The key risks in relation to the Tenas Project are summarizedbelow:• Environment:Theimpactofminingontheenvironmentis

alwaysanissueirrespectiveofthetypeofmineanditslocation.OncetheCompanyhascompleteditsenvironmentalaffectsassessmentoftheProject,targetedforQ32019,theCompanywillhaveasolidunderstandingofwhattheeffectsmightbe.

Page 36: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

36

Criteria JORCCodeexplanation Commentary

asmineral tenementstatus,andgovernmentandstatutory approvals. There must be reasonablegrounds toexpect that all necessaryGovernmentapprovalswill be receivedwithin the timeframesanticipated in the Pre-Feasibility or Feasibilitystudy.Highlightanddiscussthematerialityofanyunresolved matter that is dependent on a thirdparty on which extraction of the reserve iscontingent.

• WaterManagement:Relatedtothefirstpointofenvironmentalimpact,oneareaofparticularconcerntotheCompanyiswatermanagement.TheProjecthasseveralcreekswithinitsvicinitywhichallfeedintoamajorriversystem.EnsuringthattheProjectdischargescleansurfacewaterbackintotheriversystemisamatterofhighprioritytotheCompany.

• AcidRockManagement:TheProjecthassomewasterockandrockseparatedincoalwashingprocessthathaspotentialtogenerateacidleachingofmetalswhenminedandexposedtoairandwater.TheDFSassumesthisrockwillbepermanentlystoredunderawatercoverinmanagementpondsconstructedinthefirst10yearsofmining.Thisplanwillpreventoxidizationoftherockwhichinturnwilleliminatetherequirementfortreatmentofacidicwater.Thereisariskthatthewaterbalancewillnotbepositiverequiringwatertobepumpedfromawatercoursetomaintainthewatercover,and/oractiveongoingwatertreatmentand/orliningofthemanagementponds.

• WaterDischargeQuality:TheGovernmentprovidesthresholdsforwaterqualitydischarge.UntilaneffectsassessmentoftheProjectonwaterqualitybeingdischargedintothereceivingenvironmentiscompleted,andwhichispartoftheenvironmentalassessmentprocess,itwillnotbeknownforcertainwhetherthetreatmentofwaterpriortodischargeisrequired.

• Permitting:ThereisnoguaranteethattheProjectwillbegrantedallpermitsrequiredtooperateamineatwhateverstageofplannedproduction.WhilstBritishColumbiaisinafirstworldcountry,withaveryprescriptiveminepermittingregime,thereisalwaysuncertaintyanddoubtastowhetherGovernmentministrieswillsupportaparticularminingactivity.

• Finance:NotwithstandingtheCompany’sconfidenceinthisregard,thereisnoguaranteethatifandwhentheProjectispermittedandreadyfordevelopment,therewillbefundingavailabletodoso.WhilsttheProjectisverylowdownthecostcurveandcanwithstandamaterialdropinthepriceofcoal,thevolatilityofcommoditypricesinadownwardtrendoftendampenstheinterestofinvestorsinaparticularcommodity,suchthatfundingmaybedifficulttosecure.

• Coalperformance:unlessanduntilaparticularcoalhasbeentestedforitsperformanceinablastfurnace,thereremainsanuncertaintyastohowitwillactuallyperform,andthismayhaveanimpactoncoalpricing.

Classification • ThebasisfortheclassificationoftheOreReservesintovaryingconfidencecategories.

• Whether the result appropriately reflects theCompetentPerson’sviewofthedeposit.

• TheproportionofProbableOreReservesthathavebeenderivedfromMeasuredMineralResources(ifany).

• ProvedandprobableorereservesaredeclaredbasedonthemeasuredandindicatedmineralresourcescontainedwithinthepitdesignandscheduledintheLOMplan.

• The financial analysis showed that the economics of theTenasprojectarepositive.

• Noprobableorereserveshavebeenderivedfrommeasuredmineralresources.

Auditsorreviews

• TheresultsofanyauditsorreviewsofOreReserveestimates.

• Noexternal reviewor audits have been completed on thiscoalreserveestimateasoftheissuedateofthistable1.

Discussionofrelativeaccuracy/confidence

• Where appropriate a statement of the relativeaccuracyandconfidence level in theOreReserveestimateusinganapproachorproceduredeemedappropriate by the Competent Person. Forexample, the application of statistical orgeostatistical procedures to quantify the relativeaccuracy of the reserve within stated confidencelimits, or, if such an approach is not deemedappropriate,aqualitativediscussionofthefactorswhich could affect the relative accuracy andconfidenceoftheestimate.

• Therelativeaccuracyandconfidenceleveloftheorereserveestimateisinherentinthereserveclassification.

• Theaccuracyofthereserveestimateissubjecttogeologicaldataandmodellingprocedurestoestimatethecoalresourceandtomodifyingfactorassumptionsfordilutionandloss.Theaccuracycanonlytrulybeconfirmedwhenreconciledagainstactualproduction.WhileTelkwaisnotinproductionandsuchreconciliationisnotpossible,theassumptionsarebasedonsoundprinciplesandexperiencefrommineswithsimilarconditions.

Page 37: TENAS METALLURGICAL COAL PROJECT DEFINITIVE FEASIBILITY

37

Criteria JORCCodeexplanation Commentary

• Thestatementshouldspecifywhetheritrelatestoglobal or local estimates, and, if local, state therelevant tonnages, which should be relevant totechnical and economic evaluation.Documentationshould includeassumptionsmadeandtheproceduresused.

• Accuracyandconfidencediscussionsshouldextendto specific discussions of any applied ModifyingFactors that may have a material impact on OreReserveviability,orforwhichthereareremainingareasofuncertaintyatthecurrentstudystage.

• It is recognised that this may not be possible orappropriateinallcircumstances.Thesestatementsofrelativeaccuracyandconfidenceoftheestimateshouldbecomparedwithproductiondata,whereavailable.

• Modifying factors suchasminingdilution,mining recovery,ROM ash and density, and coal yield have been estimatedusingacceptedtechniques.