test module in the lab accelerating structure mechanical design update
DESCRIPTION
TEST Module in the LAB Accelerating structure Mechanical design update. Input from: A. Samoshkin, C. Garion, L. Faisandel. Dmitry Gudkov BE/RF . Updates. New design of manifolds. 2. Integration of “Unisex” vacuum flanges. 3. New assembly strategy. 4. AS-AS intermodule interconnection. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: TEST Module in the LAB Accelerating structure Mechanical design update](https://reader036.vdocuments.net/reader036/viewer/2022062812/5681627b550346895dd2ea65/html5/thumbnails/1.jpg)
TEST Module in the LABAccelerating structure Mechanical design update
Dmitry Gudkov BE/RF 1
Input from: A. Samoshkin, C. Garion, L. Faisandel
![Page 2: TEST Module in the LAB Accelerating structure Mechanical design update](https://reader036.vdocuments.net/reader036/viewer/2022062812/5681627b550346895dd2ea65/html5/thumbnails/2.jpg)
1. New design of manifolds
Updates
2
2. Integration of “Unisex” vacuum flanges3. New assembly strategy4. AS-AS intermoduleinterconnection
![Page 3: TEST Module in the LAB Accelerating structure Mechanical design update](https://reader036.vdocuments.net/reader036/viewer/2022062812/5681627b550346895dd2ea65/html5/thumbnails/3.jpg)
Manifold design
Manifold consists of 4 parts joined together by brazing or bonding:
3
Parts with deep rectangular holes are machined by wire cutting.
![Page 4: TEST Module in the LAB Accelerating structure Mechanical design update](https://reader036.vdocuments.net/reader036/viewer/2022062812/5681627b550346895dd2ea65/html5/thumbnails/4.jpg)
Accelerating structure assembly
4
1. Brazing of AS-bars 2. Brazing of manifolds 3. Brazing of bars and manifoldstogether
![Page 5: TEST Module in the LAB Accelerating structure Mechanical design update](https://reader036.vdocuments.net/reader036/viewer/2022062812/5681627b550346895dd2ea65/html5/thumbnails/5.jpg)
Accelerating structure assembly
5
4. Brazing of splittersand WGs with vacuumflanges
5. Brazing of WGs and splitters to accelerating structure
![Page 6: TEST Module in the LAB Accelerating structure Mechanical design update](https://reader036.vdocuments.net/reader036/viewer/2022062812/5681627b550346895dd2ea65/html5/thumbnails/6.jpg)
Accelerating structure assembly
6
Damping material installation
2 x
per manifold
![Page 7: TEST Module in the LAB Accelerating structure Mechanical design update](https://reader036.vdocuments.net/reader036/viewer/2022062812/5681627b550346895dd2ea65/html5/thumbnails/7.jpg)
Accelerating structure assembly
7
Damping material installationInstallation of single damping loads to the interface covers:
![Page 8: TEST Module in the LAB Accelerating structure Mechanical design update](https://reader036.vdocuments.net/reader036/viewer/2022062812/5681627b550346895dd2ea65/html5/thumbnails/8.jpg)
EBW
Accelerating structure assembly
8
Damping material installationSealing the manifolds by EB welding of the covers
![Page 9: TEST Module in the LAB Accelerating structure Mechanical design update](https://reader036.vdocuments.net/reader036/viewer/2022062812/5681627b550346895dd2ea65/html5/thumbnails/9.jpg)
AS-AS IntermoduleInterconnection
9
1. Brazing of cover on the end of the structure
2. Brazing of special SS piece (gray)
3. EB welding of bellow and vacuum flange