Texas Nodal Market Participant SCED Workshop 24 th May 1007. Workshop Agenda - AM. Workshop Agenda - PM. Workshop Objective and Future Plans. Start the collaboration process to develop MP Handbooks for all EDS testing activities Share the draft Market Participant Handbook for SCED testing - PowerPoint PPT Presentation

TRANSCRIPT

http://nodal.ercot.com 1Lead from the front

Texas Nodal

Texas Nodal

Market Participant SCED Workshop

24th May 1007

http://nodal.ercot.com 2Lead from the front

Texas Nodal

Workshop Agenda - AM

Agenda for EDS 3 SCED Testing Planning Workshop Thursday – May 24, 2007- 9:00pm-4:00pmLocation: ERCOT Austin MetCenterWebEx Conference (https://ercot.webex.com/ercot) Teleconference: TBD Meeting number: TBD Meeting password: TBD

Thursday May 24th

1. Meeting KickoffoWorkshop ObjectiveoReview AgendaoRollcalloMeeting LogisticsoTeam IntroductionoEDS Overview

J. Hall 9:00 am

2. EDS Readiness ActivitiesoRegistration & Qualification activities for EDS 3 oNodal Sandbox

M. Mereness 9:15 am

3. Walkthrough of Market Participant Handbook (EDS 3 initial draft)oEDS July - September ActivitiesoParticipant Handbook Feedback commentsoGroup questions and discussions

K. KasparianK. Sumanam

9:30 am

4. Break 10:45 am

5. Walkthrough of Market Participant Handbook (EDS 3 initial draft)oEDS October - December ActivitiesoParticipant Handbook Feedback commentsoGroup questions and discussions

C. GamokeJ. Hall

11:00 am

6. Lunch Break (60 min)

http://nodal.ercot.com 3Lead from the front

Texas Nodal

Workshop Agenda - PM

7. EDS 3 Entry & Exit Criteria Discussion C. Gamoke 1:00 pm

8. Technical Questions & AnswersoMMS Project TeamsoExternal Web Services oReview Questions from Handbook FeedbackoDiscuss Written Questions from Audience

EDS TeamMMS TeamScott EIP TeamMedhi AsadhianEIP Team

1:30 pm

10. Discuss ongoing planning forumsoIdentify itemsoWebEx & conference call datesoFuture workshops (alignment with Web Services)

J. Hall 3:45 pm

Adjourn

End by 4pm

http://nodal.ercot.com 4Lead from the front

Texas Nodal

Workshop Objective and Future Plans

• Start the collaboration process to develop MP Handbooks for all EDS testing activities

• Share the draft Market Participant Handbook for SCED testing

• Answer any planning or testing questions from MPs

• Provide a roadmap for future collaborative workshops

http://nodal.ercot.com 5Lead from the front

Texas Nodal

Meeting Logistics

• Question cards• Breaks• Lunch

http://nodal.ercot.com 6Lead from the front

Texas Nodal

Team introduction

• Matt Mereness - IRT• Ken Kasparian- IRT• Craig Gamoke- IRT• Kalyan Sumanam- IRT• John Hall- IRT• Gary Macomber - IDA• Resmi Surendran- MMS• Xingwang Ma- MMS• Ranjit Kumar- MMS• Scott Neumann - EIP• Mehdi Assadian - EIP

http://nodal.ercot.com 7Lead from the front

Texas Nodal

Texas NodalEarly Delivery System Overview

http://nodal.ercot.com 8Lead from the front

Texas Nodal

Texas Nodal Program Summary Release Schedule High Level Version 2.0

ED

S 4

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Alarms Processing

FAT

EMS 2A

ED

S 1

ED

S 2

ED

S 3

FAT – Rel 3

EMS 2B EDW 1

FAT – Release 4

NMMS 1 NMMS 2 EIP 1

FAT – Release 5

REG 1 MMS 1

EMS 2C

EIP 2 S&B 1MIS 1EIP 3

EDW 2

FAT – Release 6

EMS 3EDW 3

EIP 4

FAT – Release 7

EDW 4CRR 1CMM 1 EIP 5

FAT – Release 8

MMS 2S&B 2

EDW 5 EIP 6

FAT – Release 9

MMS 2S&B 2

OS

NMMS 3 EMS 4EDW 6

EIP 7EMS 5 DIS

P2P Checkout

SE Verification

ITEST

RTM Go-Live

DAM Go-Live

EDS 2 Release 3: SE VerEMS- State Estimator & Tel Perf Stds,NSA, SPS/RAP, SCADA and DynRatings for Single Model

EDW– SE Statistics

EDS 2 Release 4: NM VerNMMS- Network Model, NOMCR

EMS- EMS /NMMS Interface

EIP

EDS 3 Release 5: LMPsMMS– SCED

EMS- NSA, RLC

COMS- S&B (FIP, FOP,Ver Costs)- Registration

EIPMISEDW

EDS 3 Release 6: LFC TestingEMS- LFC

EIPEDW

EDS 3 Release 7: CRRCRRCOMS- CMM

EIPEDW

EDS 4 Release 8: RT SettlementsMMS- RT Settlements InterfaceS&BEIP, EDWEDS 4 Release 9: DAM, RUCMMS- All Markets- OSEMS – Load Forecast, Out EvalNMMSS&BEIP, EDW

ITEST

ITEST

LegendIntegration TestingProject FAT Activities

Settlements Statements

Upload Bids

Test Settlements

Outages DAM, RUC, SASMFull Nodal Functionality

24*7 Operation 168 Hr Test

NOMCR Chk out Network Model Verification

Rel 1

Rel 2

EDS 1 Release 1:EMS COTS

EDS 1 Release 2:ICCP Upgrade

Rel 3

FAT

EDS

FAT

ITEST

EDS

FAT

ITEST

EDS

SCED TestingRegUpload Offers

Rel 4

Rel 5

Rel 7

Rel 6

6 month LMP Posting

CRR Data Validation Trial Ops of CRR

LFC Comms Testing

ITEST

EDS

FAT

FAT

EDS

ITEST

ED

S 4 Go-Live

Activities

EDS 1 EDS 2 EDS 3 EDS 4

MP Interface Spec

Start of EDS activities

FAT milestones

EDS Preparatory Milestones

Rel 8

Rel 9

LFC Testing

ReadinessDeclaration

Readiness Declarations

http://nodal.ercot.com 9Lead from the front

Texas Nodal

EDS Testing Artifacts

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov DecE

DS

3

LMP Data ValidationRegUpload OffersRel 5

Rel 7

Rel 6

6 month LMP Posting

CRR Data Validation Trial Ops of CRR

LFC COMs TestingEDS

EDS 3

LFC Testing

ED

S 4

RTM Go-Live

DAM Go-Live

Legend

Settlements Statements

Upload Bids

Test Settlements

Outages DAM, RUC, SASMFull Nodal Functionality

24*7 Operation 168 Hr Test

EDS

Go-LiveActivities

EDS 4

MP Interface Spec

Major milestones

EDS Preparation Milestones

Rel 8

Rel 9

EDS Approach

EDS 3 Approach

SCED Handbook

LFC Handbook

EDS 4 Approach

CRR Handbook

S&B Handbook

DAM Handbook

168 Hour Test

Handbook

Nodal Cutover

Handbook

ERCOT & MP Readiness Reporting

EDS Testing Status Reporting

Zonal Wind Down

Handbook

TPTF Approval

http://nodal.ercot.com 10Lead from the front

Texas Nodal

Release Overview

• EDS 1 Release 1 – Alarm Processing

• EDS 1 Release 2 – Point-to-Point Checkout

• EDS 2 Release 3 – State Estimator & Network Security Analysis

• EDS 2 Release 4 – Network Model Validation

• EDS 3 Release 5 – SCED execution and posting LMP’s

• EDS 3 Release 6 – Load Frequency Control

• EDS 3 Release 7 – Settlement Statements, CRR Allocation & Auction

• EDS 4 Release 8 – RT Settlements (no Shadow Settlements)

• EDS 4 Release 9 – DAM, RUC, SASM, Full Settlements, EDW Extracts

http://nodal.ercot.com 12Lead from the front

Texas Nodal

Early SCED Release Timeline

Objectives • Enable MPs (limited) to upload

offers to SCED (API or UI)• Scripted testing with limited

QSEs• Enable MPs to review LMPs • Obtain feedback on user

experience• Test MP ability to submit offers

through API into SCED

System Needs MMS• SCED• SCED UI (As Is)• LMP Output (CSV)EIP• Three Part Offer• Offer Acceptance• Error notification*Data / Stubs • Registration (QSE, Resources)• EMS (Telemetry Simulator,

Resource Limit Calculator, Shift Factors, Constraints)

• SCED Input data Creation / Submission Tool

Testing Tools• Defect tracking &

communication process / tool

* Interface may be delivered in next phase

Objectives (Incremental)• Test MP ability to utilize API’s

- Output Schedules- COP- Inc/Dec Offers

System Needs MMS• No ChangeMIS• Portal with all portlets configured

(Minimal data / linkable apps)EIP• Output Schedule• COP• Inc/Dec Offer*Data / Stubs• No ChangeTesting Tools• No Change

* Interface may be delivered in next phase

Objectives (Incremental)• Execute SCED utilizing Real-

Time ICCP data• All MPs to participate together• Publish LMPs and Base points

via MIS

System Needs MMS• SCED UI UpgradeEMS• SE, Transmission Constraint

Manager, Resource Limit Calculator

S&B• FIP, FOP, Heat Rate CurvesNMMS• Network ModelMIS• Data and linkable apps

incorporated as availableEDW• LMP Reports (MIR)EIP• EMS-to-MMS• MMS-to-EMS• NMMS-to-MMS• REG-to-MMS• S&B-to-MMS• PLATT-to-MMS Data / Stubs• No ChangeTesting Tools• No Change

Objectives (Incremental)• Publish all SCED reporting per

Nodal Transition Plan

System Needs MMS• Hub & Load Zone Price

CalculationsMIS• Full System• SCED Reporting (Graphical)EIP• MMS-to-MISData / Stubs• No ChangeTesting Tools• No ChangeInfrastructure• No Change

Objectives (Incremental)• Stable & quality SCED • Begin publishing of LMPs for 6

months as required by Nodal Transition Plan

System Needs MMS• Bug fix onlyMIS• Bug fix onlyEMS• Bug fix onlyEIP• Bug fix onlyNMMS• Bug fix onlyMIS• Bug fix onlyEDW• Bug fix onlyData / Stubs• No ChangeTesting Tools• No ChangeInfrastructure• No Change

Support levels:

The quality, system availability and support levels during early stages may not match production standards. ERCOT will ramp up to 8*5 support for SCED operations by Jan 08

July Aug Sep Oct Nov Dec Jan2007 2008

http://nodal.ercot.com 13Lead from the front

Texas Nodal

July SCED Configuration – Standalone SCED with required stubs

Nodal – EMS Stub

NMMS Stub

EDW

Reporting

MMS

SCED Offers

COP

COMS

Registration Stub

EWSSCED UIMP

System Needs MMS1• SCED• SCED UI (As Is)• LMP Output (CSV?)EIP• Three Part Offer• Bid Set Acceptance• Bid Set Errors*Data / Stubs • Registration (QSE, Resources)• EMS (Telemetry Simulator, RLC, Shift

Factors, Constraints)• SCED Input data Creation / Submission

Tool

http://nodal.ercot.com 14Lead from the front

Texas Nodal

October SCED Configuration – Integrated with relevant applications

EMS 2.3

Nodal – EMS

OAG 2.4

Map

Telemetry

OAG 2.4

Map

TSP

QSE

NMMS

ICCP

EDW

Reporting

MMS

SCED Offers

COP

Customs

NSA

SESCADA

Telemetry Standards

State Estimator Standards

Constraint Management Dyn

amic

Rat

ings

FO

D –

Act

ual

Out

age

Det

ectio

n

CIM

Network Model

SCADA Model

COMS

Registration

FIP, FOP, HRC

S&B

RLC

EWSSCED UIMP

TCM

PTC / NOMCR

System Needs MMS1• SCED UI UpgradeEMS 2C• SE, TCM, RLCS&B• FIP, FOP, HRC, …NMMS• Network ModelEDW• LMP Report Extracts (MIR)EIP• EMS-to-MMS• MMS-to-EMS• NMMS-to-MMS• REG-to-MMS• S&B-to-MMS• PLATT-to-MMS ?Data / Stubs• No Change

• What happened to the line from MMS to EDW

• Highlight the lines that are new

http://nodal.ercot.com 15Lead from the front

Texas Nodal

Fully ITESTed SCED for January 2008 Release

EMS 2.3

Nodal – EMS

OAG 2.4

Map

Telemetry

OAG 2.4

Map

TSP

QSE

NMMS

ICCP

EDW

Reporting

MMS

SCED Offers

COP

Customs

NSA

SESCADA

Telemetry Standards

State Estimator Standards

Constraint Management Dyn

amic

Rat

ings

FO

D –

Act

ual

Out

age

Det

ectio

n

CIM

Network Model

SCADA Model

COMS

Registration

FIP, FOP, HRC

S&B

RLC

EWSMISMP

TCM

PTC / NOMCR

http://nodal.ercot.com 16Lead from the front

Texas Nodal

Web Service Implementation Timeline

Objectives • The following Web Services

should be available by June 30th, 2007

Web Services – EIP

• Three Part Offer• Incremental/Decremental

Offers• Congestion Revenue Rights• Current Operating Plan• Energy-Only Offer• Output Schedule• Bid Set Acceptance• Bid Set Errors• Get mRID• System Status

Jun Jul Aug Sept Oct Nov Dec

Objectives • The following Web Services

should be available by July 30th, 2007

Web Services – EIP

• Forecasted Load• Market Totals• Market LMPs and SPPs• Binding Constraints• Active Contingencies in

SCED• Voltage Profiles• Shift Factors• Proxy Curves• Mitigated Curves

Objectives • The following Web Services

should be available by August 30th, 2007

Web Services – EIP

• Energy Bid• PTP Obligation• Self Schedule• Real-Time System Load• Total Regulation• Load Ratio Share• Load Distribution Factors• Unit Availability• Startup and Shutdown

Instructions• CRR Awards

Objectives • The following Web Services

should be available by September 30th, 2007

Web Services – EIP

• Self Arranged Ancillary Services

• Ancillary Service Offers• Ancillary Service Trades• Capacity Trade• DC Tie Schedule• Energy Trade• Get Award Set• Market MCPCs• Ancillary Service Schedule

Obligations• Customer Load Profile• PTP Obligation Awards

Objectives • The following Web Services

should be available by October 30th, 2007

Web Services – EIP

• Dynamic Ratings• Competitive Constraints• Aggregated Ancillary Service

Offer Curves• Ancillary Service System

Plan• Pending Trade• Energy Offer Awards• Energy Only Offer Awards• Energy Bid Awards• Ancillary Service Awards• Outage Creation

Objectives • The following Web Services

should be available by November 30th, 2007

Web Services – EIP

• Total Ancillary Service Offers

• Total DAM Energy• Derated CRRs• Notices and Alerts• Outage Notifications• Alert Acknowledgement• Outage Query• Outage Cancellation

http://nodal.ercot.com 17Lead from the front

Texas Nodal

Texas Nodal Program Summary Release Schedule

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

ED

S 3

Legend

LMP Data ValidationRegUpload OffersRel 5

Rel 7

Rel 6

6 month LMP Posting

CRR Data Validation Trial Ops of CRR

LFC COMs TestingEDS

EDS 3Major milestones

FAT milestones

EDS Preparation Milestones

LFC Testing

Web Services

Three Part Offer (1) Incremental / Decremental Offers (1) Current Operating Plan (1) Output Schedule (1) Bid Set Acceptance (1) Bid Set Errors (1) Market LMPs and Spps (2) Binding Constraints (2) Active Contingencies in SCED (2) Proxy Curves (2) Real Time System Load (3) Competitive Constraints (5) Unit Availability (3) Get mRID (1) System Status (1) Mitigated Curve (2)

Web Services

Shift Factors (2) Voltage Profiles (2) Load Distribution Factors (3) Total Regulation (3)

http://nodal.ercot.com 18Lead from the front

Texas Nodal

ED

S 4

Texas Nodal Program Summary Release Schedule

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

RTM Go-Live

DAM Go-Live

Legend

Settlements Statements

Upload Bids

Test Settlements

Outages DAM, RUC, SASMFull Nodal Functionality

24*7 Operation 168 Hr Test

EDS

Go-LiveActivities

EDS 4

MP Interface Spec

Major milestones EDS Preparation Milestones

Rel 8

Rel 9

Web Services

Self Arranged Ancillary Services (4) Ancillary Service Offers (4) Aggregated AS Offer Curves (5 Ancillary Service Trades (4) Ancillary Service Schedule Obligations (4) Capacity Trade (4) Congestion Revenue Rights (1) DC Tie Schedule (4) Energy Bid (3) Energy Only Offer (1) Energy Trade (4) PTP Obligation (3) Self Schedule (3) Load Ratio Share (3) Dynamic Ratings (5) Total AS Offers (6) Derated CRRs (6) Customer Load Profiles (4) Pending Trade (5) AS System Plan (5)

Web Services

Outage Creation (5) Outage Query (6) Outage Cancellation (6) Outage Notification (6)

Web Services

Energy Bid Award (5) Energy Offer Award (5) Energy Only Offer Award (5) Ancillary Service Awards (5) PTP Obligation Awards (4) CRR Awards (5) Get Award Set (4) Forecasted Load (2) Market Totals (2) Market MCPCs (4) Total DAM Energy (6) Startup / Shutdown Instructions (3) Notices and Alerts (6) Alert Notification (6)

http://nodal.ercot.com 19Lead from the front

Texas Nodal

What should QSE’s have in place?

Release 5 - SCED• Personnel have attended Nodal Training Courses• Provided new and updated Registration data to ERCOT• QSE ability to create and submit offer curves to ERCOT • QSE Interactions with Interface Testing

– Obtained digital certificates – Connectivity and ID Authentication – Offer submissions capability demonstrated

• QSE ability to receive Base Points and other data• Market Participant operators available 8 to 5

Release 6 - LFC• QSE EMS Nodal system changes complete to support LFC • QSE Ancillary Service Qualification complete

Release 7 - CRR• CRR Digital Certificate access requested• CRR Account Holder:  Completed Registration with ERCOT and Application

Process • CRR Account Test Credit Limit established

http://nodal.ercot.com 20Lead from the front

Texas Nodal

Participation in the EDS 3 Testing Phases (Section 1.4 – EDS 3 Plan)

Market Participant Type Activities Timeframe Expectation

QSEs with resources planning on utilizing API’s in production

MP Development Connectivity Testing (Sandbox)

July - September Strongly Recommended

MP Connectivity Testing (EDS Environment)

July - September Strongly Recommended

MP Connectivity Testing (EDS Environment)

October Mandatory *

MP Input Validation – SCED Aug – September Strongly Recommended

MP Input Validation – SCED October Mandatory *

MP Input using SCED User Interface October Recommended **

All QSEs with resources

MP Input using SCED User Interface July – September Recommended **

MP Input for SCED Execution October – December Mandatory for designated EDS testing days

MP Input for 6 month LMP Period January – June 2008 Mandatory based on define scenarios and methodology

QSEs with resources not planning on utilizing API’s in production

MP Input using SCED User Interface October Mandatory *

* Starting in October Market Participant involvement is critical to begin producing “Reasonable” LMPs. During this period the Market Participants should have a partial EDS system in place to support the activities and functionality being demonstrated. The EDS team will provide workshops during this time to support Market Participants. Required Market Participants that are not able to participate will have to still perform these activities by requesting a ‘make-up’ workshop prior to involvement in later EDS activities. There will be limited opportunities for support due to focus on other EDS functionality.** The EDS team recommends that all QSEs with resources schedule some time to get familiar with the SCED user interface even if they are planning on utilizing APIs in production. This will help ensure that Market Participants have a second method for accessing the EDS systems if their APIs are not functioning correctly.

http://nodal.ercot.com 25Lead from the front

Texas Nodal

Transition Plan Details Development Schedule

Transition Plan Requirement Presentation to TPTF

Approval by TPTF

Develop a method for Market Participants to create and provide individual Resource offer curves to SCED

Identify MIS reporting requirements – “posting LMPs and other data available on the EDS…” if required in NP 6.3.2

Define LMP posting requirements – what does “at least six months” mean? What LMP analysis and feedback requirement?

Define a method for Load Frequency Control Testing, including the plan for settlement of nodal testing periods (Compliance involvement)

Create a CRR detailed test plan describing each step of trial allocation & auction

Define PCRR / CRR allocation process for testing

Draft of Entry / Exit criteria

http://nodal.ercot.com 26Lead from the front

Texas Nodal

Registration and Qualification

EDS Readiness Activities to Support EDS3

Registration and Qualification

&

Nodal Sandbox/Interface Testing EnvironmentMatt Mereness

Integrated ERCOT Readiness and Transition

http://nodal.ercot.com 27Lead from the front

Texas Nodal

Readiness Activities for EDS3

• High Level View of EDS Schedule

• High Level View of Registration and Qualification

– Registration (the paperwork)

– Qualification (the testing and verification)

• What Data is needed to support EDS3?

• Nodal Sandbox/Interface Testing Environment– Description and Benefits of accessing interface testing system

http://nodal.ercot.com 28Lead from the front

Texas Nodal

High Level View of EDS ScheduleE

DS

4

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Alarms Processing

FAT

EMS 2A

ED

S 1

ED

S 2

ED

S 3

FAT – Rel 3

EMS 2B EDW 1

FAT – Release 4

NMMS 1 NMMS 2 EIP 1

FAT – Release 5

REG 1 MMS 1

EMS 2C

EIP 2 S&B 1MIS 1EIP 3

EDW 2

FAT – Release 6

EMS 3EDW 3

EIP 4

FAT – Release 7

EDW 4CRR 1CMM 1 EIP 5

FAT – Release 8

MMS 2S&B 2

EDW 5 EIP 6

FAT – Release 9

MMS 2S&B 2

OS

NMMS 3 EMS 4EDW 6

EIP 7EMS 5 DIS

P2P Checkout

SE Verification

ITEST

RTM Go-Live

DAM Go-Live

EDS 2 Release 3: SE VerEMS- State Estimator & Tel Perf Stds,NSA, SPS/RAP, SCADA and DynRatings for Single Model

EDW– SE Statistics

EDS 2 Release 4: NM VerNMMS- Network Model, NOMCR

EMS- EMS /NMMS Interface

EIP

EDS 3 Release 5: LMPsMMS– SCED

EMS- NSA, RLC

COMS- S&B (FIP, FOP,Ver Costs)- Registration

EIPMISEDW

EDS 3 Release 6: LFC TestingEMS- LFC

EIPEDW

EDS 3 Release 7: CRRCRRCOMS- CMM

EIPEDW

EDS 4 Release 8: RT SettlementsMMS- RT Settlements InterfaceS&BEIP, EDWEDS 4 Release 9: DAM, RUCMMS- All Markets- OSEMS – Load Forecast, Out EvalNMMSS&BEIP, EDW

ITEST

ITEST

LegendIntegration TestingProject FAT Activities

Settlements Statements

Upload Bids

Test Settlements

Outages DAM, RUC, SASMFull Nodal Functionality

24*7 Operation 168 Hr Test

NOMCR Chk out Network Model Verification

Rel 1

Rel 2

EDS 1 Release 1:EMS COTS

EDS 1 Release 2:ICCP Upgrade

Rel 3

FAT

EDS

FAT

ITEST

EDS

FAT

ITEST

EDS

SCED TestingRegUpload Offers

Rel 4

Rel 5

Rel 7

Rel 6

6 month LMP Posting

CRR Data Validation Trial Ops of CRR

LFC Comms Testing

ITEST

EDS

FAT

FAT

EDS

ITEST

ED

S 4 Go-Live

Activities

EDS 1 EDS 2 EDS 3 EDS 4

MP Interface Spec

Start of EDS activities

FAT milestones

EDS Preparatory Milestones

Rel 8

Rel 9

LFC Testing

ReadinessDeclaration

Readiness Declarations

http://nodal.ercot.com 29Lead from the front

Texas Nodal

High Level View of Registration and Qualification

CRR = CRR Acct Holder X= Required, X* = Required only for new MP, O= Optional

Q = QSE without Resources (formerly Level 1 & 2 QSEs)

QR= QSE with Resources (formerly Level 3 & 4 QSEs)

TD =TSP and/or DSP

http://nodal.ercot.com 30Lead from the front

Texas Nodal

High Level View of Registration and Qualification (cont’d)

Calendar of Registration Documentation• Aligning Registration Dates to coordinate with EDS

Milestones:• Resource Registration data (fully-certified version)

– Provide to ERCOT by 9/1/07– In time for 10/1/07 mandatory EDS3/SCED testing

• Attestation for Qualification of Ancillary Services– Provide to ERCOT by 9/1/07– In support of LFC testing preparation/scheduling

1/1/08• Sign MP Standard Form Agreements

– Time of BOD approval for PRR/NPRR, not EDS– Estimate BOD approval in place by 10/1/07– Target completion 60-90 days later

• CRR Account Holder Application– Provide to ERCOT by 3/1/08– In time for 4/1/08 testing of CRR Auction

• QSE Application (new QSEs)– QSEs with Resources (August 2007)– QSEs without Resources provide to ERCOT by

3/1/08– Receive by 3/1/08, in time for 4/1/08 testing of DAM

http://nodal.ercot.com 31Lead from the front

Texas Nodal

What is Data is needed to support EDS3?

Resource Data is needed for EDS3-SCED Testing

• What ERCOT has:– Zonal Generation Asset Registration Forms (GARFs on file at ERCOT)

• What ERCOT does not have:– Subset of new resource parameters for nodal market (not on file at ERCOT)

• ERCOT’s plan to get EDS3 Resource Data established in nodal systems– In the short term (for pre-EDS3 testing), ERCOT is to release a

spreadsheet to QSEs and/or Resource Entities to complete the “bare-bones” list of Resource data needed for data entry validation

• ERCOT will upload data into Market Management System (MMS)

– In the longer term (for mandatory EDS3 activities), ERCOT is to release a new version of the Resource Asset Registration Form to Resource Entities to have completed and on file at ERCOT

• ERCOT will release new Resource Asset Registration Form (and upon request can provide the zonal GARF that is on file)

• New form will highlight new data elements needed

http://nodal.ercot.com 32Lead from the front

Texas Nodal

Nodal Sandbox/Interface Testing Environment

• Purpose of Sandbox

– Allow Market Participant developers (and vendors) to access ERCOT programmatic interfaces and test code for data submission

• Limitations/advantages of sandbox

– Not an EDS environment

– No data validation, only technical validation of code and format

Market Participant Systems

ERCOT WebServices

Nodal Application Databases

Market Participant Systems

ERCOT WebServices

Sandbox/Interface Testing Environment

(no application behind web interface)

EDS

Environment

http://nodal.ercot.com 33Lead from the front

Texas Nodal

Nodal Sandbox/Interface Testing Environment (cont’d)

• Limitations/advantages of sandbox (cont’d)– Environment is already available to the market for testing– Developer can use Sandbox to shake-out coding issues– Developer can use Sandbox to resolve security/digital certificate issues

• Allows technical testing prior to pre-EDS and EDS activities• Market Interface document available as Machine-to-Machine Interface (

http://nodal.ercot.com/docs/pd/ida/index.html#oth)

Market Participant Systems

ERCOT WebServices

Nodal Application Databases

Market Participant Systems

ERCOT WebServices

Sandbox/Interface Testing Environment

(no application behind web interface)

EDS

Environment

http://nodal.ercot.com 34Lead from the front

Texas Nodal

Summary and Questions

Readiness Summary:• Sandbox/Interface Testing Environment is already available to test

submission of some transactions– No Resource data needed as there is no data validation

• To obtain Resource Registration Data, ERCOT is planning to release draft of Resource data to TPTF by June 1, and plans formal release of registration forms to market by June 28.

– Pre-EDS3 participants will need to provide “bare-bones” list of Resource data

– Mandatory EDS3 will require full completion of Resource Registration Forms (9/1/07)

Questions before getting into more details of EDS3?

http://nodal.ercot.com 35Lead from the front

Texas Nodal

Handbook Walkthrough

http://nodal.ercot.com 36Lead from the front

Texas Nodal

Break

http://nodal.ercot.com 37Lead from the front

Texas Nodal

Handbook Walkthrough

http://nodal.ercot.com 38Lead from the front

Texas Nodal

Lunch

http://nodal.ercot.com 39Lead from the front

Texas Nodal

Entry & Exit Criteria

http://nodal.ercot.com 40Lead from the front

Texas Nodal

Technical Questions &

Answers

http://nodal.ercot.com 41Lead from the front

Texas Nodal

Ongoing Planning Forums &

Workshops

http://nodal.ercot.com 42Lead from the front

Texas Nodal

Future workshops

• Frequency of workshops?• Frequency of WebEx?• SCED, LFC, CRR etc

http://nodal.ercot.com 43Lead from the front

Texas Nodal

Have a safe trip home