texas nodal market participant sced workshop 24 th may 1007
DESCRIPTION
Texas Nodal Market Participant SCED Workshop 24 th May 1007. Workshop Agenda - AM. Workshop Agenda - PM. Workshop Objective and Future Plans. Start the collaboration process to develop MP Handbooks for all EDS testing activities Share the draft Market Participant Handbook for SCED testing - PowerPoint PPT PresentationTRANSCRIPT
http://nodal.ercot.com 1Lead from the front
Texas Nodal
Texas Nodal
Market Participant SCED Workshop
24th May 1007
http://nodal.ercot.com 2Lead from the front
Texas Nodal
Workshop Agenda - AM
Agenda for EDS 3 SCED Testing Planning Workshop Thursday – May 24, 2007- 9:00pm-4:00pmLocation: ERCOT Austin MetCenterWebEx Conference (https://ercot.webex.com/ercot) Teleconference: TBD Meeting number: TBD Meeting password: TBD
Thursday May 24th
1. Meeting KickoffoWorkshop ObjectiveoReview AgendaoRollcalloMeeting LogisticsoTeam IntroductionoEDS Overview
J. Hall 9:00 am
2. EDS Readiness ActivitiesoRegistration & Qualification activities for EDS 3 oNodal Sandbox
M. Mereness 9:15 am
3. Walkthrough of Market Participant Handbook (EDS 3 initial draft)oEDS July - September ActivitiesoParticipant Handbook Feedback commentsoGroup questions and discussions
K. KasparianK. Sumanam
9:30 am
4. Break 10:45 am
5. Walkthrough of Market Participant Handbook (EDS 3 initial draft)oEDS October - December ActivitiesoParticipant Handbook Feedback commentsoGroup questions and discussions
C. GamokeJ. Hall
11:00 am
6. Lunch Break (60 min)
http://nodal.ercot.com 3Lead from the front
Texas Nodal
Workshop Agenda - PM
7. EDS 3 Entry & Exit Criteria Discussion C. Gamoke 1:00 pm
8. Technical Questions & AnswersoMMS Project TeamsoExternal Web Services oReview Questions from Handbook FeedbackoDiscuss Written Questions from Audience
EDS TeamMMS TeamScott EIP TeamMedhi AsadhianEIP Team
1:30 pm
10. Discuss ongoing planning forumsoIdentify itemsoWebEx & conference call datesoFuture workshops (alignment with Web Services)
J. Hall 3:45 pm
Adjourn
End by 4pm
http://nodal.ercot.com 4Lead from the front
Texas Nodal
Workshop Objective and Future Plans
• Start the collaboration process to develop MP Handbooks for all EDS testing activities
• Share the draft Market Participant Handbook for SCED testing
• Answer any planning or testing questions from MPs
• Provide a roadmap for future collaborative workshops
http://nodal.ercot.com 5Lead from the front
Texas Nodal
Meeting Logistics
• Question cards• Breaks• Lunch
http://nodal.ercot.com 6Lead from the front
Texas Nodal
Team introduction
• Matt Mereness - IRT• Ken Kasparian- IRT• Craig Gamoke- IRT• Kalyan Sumanam- IRT• John Hall- IRT• Gary Macomber - IDA• Resmi Surendran- MMS• Xingwang Ma- MMS• Ranjit Kumar- MMS• Scott Neumann - EIP• Mehdi Assadian - EIP
http://nodal.ercot.com 8Lead from the front
Texas Nodal
Texas Nodal Program Summary Release Schedule High Level Version 2.0
ED
S 4
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Alarms Processing
FAT
EMS 2A
ED
S 1
ED
S 2
ED
S 3
FAT – Rel 3
EMS 2B EDW 1
FAT – Release 4
NMMS 1 NMMS 2 EIP 1
FAT – Release 5
REG 1 MMS 1
EMS 2C
EIP 2 S&B 1MIS 1EIP 3
EDW 2
FAT – Release 6
EMS 3EDW 3
EIP 4
FAT – Release 7
EDW 4CRR 1CMM 1 EIP 5
FAT – Release 8
MMS 2S&B 2
EDW 5 EIP 6
FAT – Release 9
MMS 2S&B 2
OS
NMMS 3 EMS 4EDW 6
EIP 7EMS 5 DIS
P2P Checkout
SE Verification
ITEST
RTM Go-Live
DAM Go-Live
EDS 2 Release 3: SE VerEMS- State Estimator & Tel Perf Stds,NSA, SPS/RAP, SCADA and DynRatings for Single Model
EDW– SE Statistics
EDS 2 Release 4: NM VerNMMS- Network Model, NOMCR
EMS- EMS /NMMS Interface
EIP
EDS 3 Release 5: LMPsMMS– SCED
EMS- NSA, RLC
COMS- S&B (FIP, FOP,Ver Costs)- Registration
EIPMISEDW
EDS 3 Release 6: LFC TestingEMS- LFC
EIPEDW
EDS 3 Release 7: CRRCRRCOMS- CMM
EIPEDW
EDS 4 Release 8: RT SettlementsMMS- RT Settlements InterfaceS&BEIP, EDWEDS 4 Release 9: DAM, RUCMMS- All Markets- OSEMS – Load Forecast, Out EvalNMMSS&BEIP, EDW
ITEST
ITEST
LegendIntegration TestingProject FAT Activities
Settlements Statements
Upload Bids
Test Settlements
Outages DAM, RUC, SASMFull Nodal Functionality
24*7 Operation 168 Hr Test
NOMCR Chk out Network Model Verification
Rel 1
Rel 2
EDS 1 Release 1:EMS COTS
EDS 1 Release 2:ICCP Upgrade
Rel 3
FAT
EDS
FAT
ITEST
EDS
FAT
ITEST
EDS
SCED TestingRegUpload Offers
Rel 4
Rel 5
Rel 7
Rel 6
6 month LMP Posting
CRR Data Validation Trial Ops of CRR
LFC Comms Testing
ITEST
EDS
FAT
FAT
EDS
ITEST
ED
S 4 Go-Live
Activities
EDS 1 EDS 2 EDS 3 EDS 4
MP Interface Spec
Start of EDS activities
FAT milestones
EDS Preparatory Milestones
Rel 8
Rel 9
LFC Testing
ReadinessDeclaration
Readiness Declarations
http://nodal.ercot.com 9Lead from the front
Texas Nodal
EDS Testing Artifacts
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov DecE
DS
3
LMP Data ValidationRegUpload OffersRel 5
Rel 7
Rel 6
6 month LMP Posting
CRR Data Validation Trial Ops of CRR
LFC COMs TestingEDS
EDS 3
LFC Testing
ED
S 4
RTM Go-Live
DAM Go-Live
Legend
Settlements Statements
Upload Bids
Test Settlements
Outages DAM, RUC, SASMFull Nodal Functionality
24*7 Operation 168 Hr Test
EDS
Go-LiveActivities
EDS 4
MP Interface Spec
Major milestones
EDS Preparation Milestones
Rel 8
Rel 9
EDS Approach
EDS 3 Approach
SCED Handbook
LFC Handbook
EDS 4 Approach
CRR Handbook
S&B Handbook
DAM Handbook
168 Hour Test
Handbook
Nodal Cutover
Handbook
ERCOT & MP Readiness Reporting
EDS Testing Status Reporting
Zonal Wind Down
Handbook
TPTF Approval
http://nodal.ercot.com 10Lead from the front
Texas Nodal
Release Overview
• EDS 1 Release 1 – Alarm Processing
• EDS 1 Release 2 – Point-to-Point Checkout
• EDS 2 Release 3 – State Estimator & Network Security Analysis
• EDS 2 Release 4 – Network Model Validation
• EDS 3 Release 5 – SCED execution and posting LMP’s
• EDS 3 Release 6 – Load Frequency Control
• EDS 3 Release 7 – Settlement Statements, CRR Allocation & Auction
• EDS 4 Release 8 – RT Settlements (no Shadow Settlements)
• EDS 4 Release 9 – DAM, RUC, SASM, Full Settlements, EDW Extracts
http://nodal.ercot.com 12Lead from the front
Texas Nodal
Early SCED Release Timeline
Objectives • Enable MPs (limited) to upload
offers to SCED (API or UI)• Scripted testing with limited
QSEs• Enable MPs to review LMPs • Obtain feedback on user
experience• Test MP ability to submit offers
through API into SCED
System Needs MMS• SCED• SCED UI (As Is)• LMP Output (CSV)EIP• Three Part Offer• Offer Acceptance• Error notification*Data / Stubs • Registration (QSE, Resources)• EMS (Telemetry Simulator,
Resource Limit Calculator, Shift Factors, Constraints)
• SCED Input data Creation / Submission Tool
Testing Tools• Defect tracking &
communication process / tool
* Interface may be delivered in next phase
Objectives (Incremental)• Test MP ability to utilize API’s
- Output Schedules- COP- Inc/Dec Offers
System Needs MMS• No ChangeMIS• Portal with all portlets configured
(Minimal data / linkable apps)EIP• Output Schedule• COP• Inc/Dec Offer*Data / Stubs• No ChangeTesting Tools• No Change
* Interface may be delivered in next phase
Objectives (Incremental)• Execute SCED utilizing Real-
Time ICCP data• All MPs to participate together• Publish LMPs and Base points
via MIS
System Needs MMS• SCED UI UpgradeEMS• SE, Transmission Constraint
Manager, Resource Limit Calculator
S&B• FIP, FOP, Heat Rate CurvesNMMS• Network ModelMIS• Data and linkable apps
incorporated as availableEDW• LMP Reports (MIR)EIP• EMS-to-MMS• MMS-to-EMS• NMMS-to-MMS• REG-to-MMS• S&B-to-MMS• PLATT-to-MMS Data / Stubs• No ChangeTesting Tools• No Change
Objectives (Incremental)• Publish all SCED reporting per
Nodal Transition Plan
System Needs MMS• Hub & Load Zone Price
CalculationsMIS• Full System• SCED Reporting (Graphical)EIP• MMS-to-MISData / Stubs• No ChangeTesting Tools• No ChangeInfrastructure• No Change
Objectives (Incremental)• Stable & quality SCED • Begin publishing of LMPs for 6
months as required by Nodal Transition Plan
System Needs MMS• Bug fix onlyMIS• Bug fix onlyEMS• Bug fix onlyEIP• Bug fix onlyNMMS• Bug fix onlyMIS• Bug fix onlyEDW• Bug fix onlyData / Stubs• No ChangeTesting Tools• No ChangeInfrastructure• No Change
Support levels:
The quality, system availability and support levels during early stages may not match production standards. ERCOT will ramp up to 8*5 support for SCED operations by Jan 08
July Aug Sep Oct Nov Dec Jan2007 2008
http://nodal.ercot.com 13Lead from the front
Texas Nodal
July SCED Configuration – Standalone SCED with required stubs
Nodal – EMS Stub
NMMS Stub
EDW
Reporting
MMS
SCED Offers
COP
COMS
Registration Stub
EWSSCED UIMP
System Needs MMS1• SCED• SCED UI (As Is)• LMP Output (CSV?)EIP• Three Part Offer• Bid Set Acceptance• Bid Set Errors*Data / Stubs • Registration (QSE, Resources)• EMS (Telemetry Simulator, RLC, Shift
Factors, Constraints)• SCED Input data Creation / Submission
Tool
http://nodal.ercot.com 14Lead from the front
Texas Nodal
October SCED Configuration – Integrated with relevant applications
EMS 2.3
Nodal – EMS
OAG 2.4
Map
Telemetry
OAG 2.4
Map
TSP
QSE
NMMS
ICCP
EDW
Reporting
MMS
SCED Offers
COP
Customs
NSA
SESCADA
Telemetry Standards
State Estimator Standards
Constraint Management Dyn
amic
Rat
ings
FO
D –
Act
ual
Out
age
Det
ectio
n
CIM
Network Model
SCADA Model
COMS
Registration
FIP, FOP, HRC
S&B
RLC
EWSSCED UIMP
TCM
PTC / NOMCR
System Needs MMS1• SCED UI UpgradeEMS 2C• SE, TCM, RLCS&B• FIP, FOP, HRC, …NMMS• Network ModelEDW• LMP Report Extracts (MIR)EIP• EMS-to-MMS• MMS-to-EMS• NMMS-to-MMS• REG-to-MMS• S&B-to-MMS• PLATT-to-MMS ?Data / Stubs• No Change
• What happened to the line from MMS to EDW
• Highlight the lines that are new
http://nodal.ercot.com 15Lead from the front
Texas Nodal
Fully ITESTed SCED for January 2008 Release
EMS 2.3
Nodal – EMS
OAG 2.4
Map
Telemetry
OAG 2.4
Map
TSP
QSE
NMMS
ICCP
EDW
Reporting
MMS
SCED Offers
COP
Customs
NSA
SESCADA
Telemetry Standards
State Estimator Standards
Constraint Management Dyn
amic
Rat
ings
FO
D –
Act
ual
Out
age
Det
ectio
n
CIM
Network Model
SCADA Model
COMS
Registration
FIP, FOP, HRC
S&B
RLC
EWSMISMP
TCM
PTC / NOMCR
http://nodal.ercot.com 16Lead from the front
Texas Nodal
Web Service Implementation Timeline
Objectives • The following Web Services
should be available by June 30th, 2007
Web Services – EIP
• Three Part Offer• Incremental/Decremental
Offers• Congestion Revenue Rights• Current Operating Plan• Energy-Only Offer• Output Schedule• Bid Set Acceptance• Bid Set Errors• Get mRID• System Status
Jun Jul Aug Sept Oct Nov Dec
Objectives • The following Web Services
should be available by July 30th, 2007
Web Services – EIP
• Forecasted Load• Market Totals• Market LMPs and SPPs• Binding Constraints• Active Contingencies in
SCED• Voltage Profiles• Shift Factors• Proxy Curves• Mitigated Curves
Objectives • The following Web Services
should be available by August 30th, 2007
Web Services – EIP
• Energy Bid• PTP Obligation• Self Schedule• Real-Time System Load• Total Regulation• Load Ratio Share• Load Distribution Factors• Unit Availability• Startup and Shutdown
Instructions• CRR Awards
Objectives • The following Web Services
should be available by September 30th, 2007
Web Services – EIP
• Self Arranged Ancillary Services
• Ancillary Service Offers• Ancillary Service Trades• Capacity Trade• DC Tie Schedule• Energy Trade• Get Award Set• Market MCPCs• Ancillary Service Schedule
Obligations• Customer Load Profile• PTP Obligation Awards
Objectives • The following Web Services
should be available by October 30th, 2007
Web Services – EIP
• Dynamic Ratings• Competitive Constraints• Aggregated Ancillary Service
Offer Curves• Ancillary Service System
Plan• Pending Trade• Energy Offer Awards• Energy Only Offer Awards• Energy Bid Awards• Ancillary Service Awards• Outage Creation
Objectives • The following Web Services
should be available by November 30th, 2007
Web Services – EIP
• Total Ancillary Service Offers
• Total DAM Energy• Derated CRRs• Notices and Alerts• Outage Notifications• Alert Acknowledgement• Outage Query• Outage Cancellation
http://nodal.ercot.com 17Lead from the front
Texas Nodal
Texas Nodal Program Summary Release Schedule
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
ED
S 3
Legend
LMP Data ValidationRegUpload OffersRel 5
Rel 7
Rel 6
6 month LMP Posting
CRR Data Validation Trial Ops of CRR
LFC COMs TestingEDS
EDS 3Major milestones
FAT milestones
EDS Preparation Milestones
LFC Testing
Web Services
Three Part Offer (1) Incremental / Decremental Offers (1) Current Operating Plan (1) Output Schedule (1) Bid Set Acceptance (1) Bid Set Errors (1) Market LMPs and Spps (2) Binding Constraints (2) Active Contingencies in SCED (2) Proxy Curves (2) Real Time System Load (3) Competitive Constraints (5) Unit Availability (3) Get mRID (1) System Status (1) Mitigated Curve (2)
Web Services
Shift Factors (2) Voltage Profiles (2) Load Distribution Factors (3) Total Regulation (3)
http://nodal.ercot.com 18Lead from the front
Texas Nodal
ED
S 4
Texas Nodal Program Summary Release Schedule
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
RTM Go-Live
DAM Go-Live
Legend
Settlements Statements
Upload Bids
Test Settlements
Outages DAM, RUC, SASMFull Nodal Functionality
24*7 Operation 168 Hr Test
EDS
Go-LiveActivities
EDS 4
MP Interface Spec
Major milestones EDS Preparation Milestones
Rel 8
Rel 9
Web Services
Self Arranged Ancillary Services (4) Ancillary Service Offers (4) Aggregated AS Offer Curves (5 Ancillary Service Trades (4) Ancillary Service Schedule Obligations (4) Capacity Trade (4) Congestion Revenue Rights (1) DC Tie Schedule (4) Energy Bid (3) Energy Only Offer (1) Energy Trade (4) PTP Obligation (3) Self Schedule (3) Load Ratio Share (3) Dynamic Ratings (5) Total AS Offers (6) Derated CRRs (6) Customer Load Profiles (4) Pending Trade (5) AS System Plan (5)
Web Services
Outage Creation (5) Outage Query (6) Outage Cancellation (6) Outage Notification (6)
Web Services
Energy Bid Award (5) Energy Offer Award (5) Energy Only Offer Award (5) Ancillary Service Awards (5) PTP Obligation Awards (4) CRR Awards (5) Get Award Set (4) Forecasted Load (2) Market Totals (2) Market MCPCs (4) Total DAM Energy (6) Startup / Shutdown Instructions (3) Notices and Alerts (6) Alert Notification (6)
http://nodal.ercot.com 19Lead from the front
Texas Nodal
What should QSE’s have in place?
Release 5 - SCED• Personnel have attended Nodal Training Courses• Provided new and updated Registration data to ERCOT• QSE ability to create and submit offer curves to ERCOT • QSE Interactions with Interface Testing
– Obtained digital certificates – Connectivity and ID Authentication – Offer submissions capability demonstrated
• QSE ability to receive Base Points and other data• Market Participant operators available 8 to 5
Release 6 - LFC• QSE EMS Nodal system changes complete to support LFC • QSE Ancillary Service Qualification complete
Release 7 - CRR• CRR Digital Certificate access requested• CRR Account Holder: Completed Registration with ERCOT and Application
Process • CRR Account Test Credit Limit established
http://nodal.ercot.com 20Lead from the front
Texas Nodal
Participation in the EDS 3 Testing Phases (Section 1.4 – EDS 3 Plan)
Market Participant Type Activities Timeframe Expectation
QSEs with resources planning on utilizing API’s in production
MP Development Connectivity Testing (Sandbox)
July - September Strongly Recommended
MP Connectivity Testing (EDS Environment)
July - September Strongly Recommended
MP Connectivity Testing (EDS Environment)
October Mandatory *
MP Input Validation – SCED Aug – September Strongly Recommended
MP Input Validation – SCED October Mandatory *
MP Input using SCED User Interface October Recommended **
All QSEs with resources
MP Input using SCED User Interface July – September Recommended **
MP Input for SCED Execution October – December Mandatory for designated EDS testing days
MP Input for 6 month LMP Period January – June 2008 Mandatory based on define scenarios and methodology
QSEs with resources not planning on utilizing API’s in production
MP Input using SCED User Interface October Mandatory *
* Starting in October Market Participant involvement is critical to begin producing “Reasonable” LMPs. During this period the Market Participants should have a partial EDS system in place to support the activities and functionality being demonstrated. The EDS team will provide workshops during this time to support Market Participants. Required Market Participants that are not able to participate will have to still perform these activities by requesting a ‘make-up’ workshop prior to involvement in later EDS activities. There will be limited opportunities for support due to focus on other EDS functionality.** The EDS team recommends that all QSEs with resources schedule some time to get familiar with the SCED user interface even if they are planning on utilizing APIs in production. This will help ensure that Market Participants have a second method for accessing the EDS systems if their APIs are not functioning correctly.
http://nodal.ercot.com 25Lead from the front
Texas Nodal
Transition Plan Details Development Schedule
Transition Plan Requirement Presentation to TPTF
Approval by TPTF
Develop a method for Market Participants to create and provide individual Resource offer curves to SCED
Identify MIS reporting requirements – “posting LMPs and other data available on the EDS…” if required in NP 6.3.2
Define LMP posting requirements – what does “at least six months” mean? What LMP analysis and feedback requirement?
Define a method for Load Frequency Control Testing, including the plan for settlement of nodal testing periods (Compliance involvement)
Create a CRR detailed test plan describing each step of trial allocation & auction
Define PCRR / CRR allocation process for testing
Draft of Entry / Exit criteria
http://nodal.ercot.com 26Lead from the front
Texas Nodal
Registration and Qualification
EDS Readiness Activities to Support EDS3
Registration and Qualification
&
Nodal Sandbox/Interface Testing EnvironmentMatt Mereness
Integrated ERCOT Readiness and Transition
http://nodal.ercot.com 27Lead from the front
Texas Nodal
Readiness Activities for EDS3
• High Level View of EDS Schedule
• High Level View of Registration and Qualification
– Registration (the paperwork)
– Qualification (the testing and verification)
• What Data is needed to support EDS3?
• Nodal Sandbox/Interface Testing Environment– Description and Benefits of accessing interface testing system
http://nodal.ercot.com 28Lead from the front
Texas Nodal
High Level View of EDS ScheduleE
DS
4
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Alarms Processing
FAT
EMS 2A
ED
S 1
ED
S 2
ED
S 3
FAT – Rel 3
EMS 2B EDW 1
FAT – Release 4
NMMS 1 NMMS 2 EIP 1
FAT – Release 5
REG 1 MMS 1
EMS 2C
EIP 2 S&B 1MIS 1EIP 3
EDW 2
FAT – Release 6
EMS 3EDW 3
EIP 4
FAT – Release 7
EDW 4CRR 1CMM 1 EIP 5
FAT – Release 8
MMS 2S&B 2
EDW 5 EIP 6
FAT – Release 9
MMS 2S&B 2
OS
NMMS 3 EMS 4EDW 6
EIP 7EMS 5 DIS
P2P Checkout
SE Verification
ITEST
RTM Go-Live
DAM Go-Live
EDS 2 Release 3: SE VerEMS- State Estimator & Tel Perf Stds,NSA, SPS/RAP, SCADA and DynRatings for Single Model
EDW– SE Statistics
EDS 2 Release 4: NM VerNMMS- Network Model, NOMCR
EMS- EMS /NMMS Interface
EIP
EDS 3 Release 5: LMPsMMS– SCED
EMS- NSA, RLC
COMS- S&B (FIP, FOP,Ver Costs)- Registration
EIPMISEDW
EDS 3 Release 6: LFC TestingEMS- LFC
EIPEDW
EDS 3 Release 7: CRRCRRCOMS- CMM
EIPEDW
EDS 4 Release 8: RT SettlementsMMS- RT Settlements InterfaceS&BEIP, EDWEDS 4 Release 9: DAM, RUCMMS- All Markets- OSEMS – Load Forecast, Out EvalNMMSS&BEIP, EDW
ITEST
ITEST
LegendIntegration TestingProject FAT Activities
Settlements Statements
Upload Bids
Test Settlements
Outages DAM, RUC, SASMFull Nodal Functionality
24*7 Operation 168 Hr Test
NOMCR Chk out Network Model Verification
Rel 1
Rel 2
EDS 1 Release 1:EMS COTS
EDS 1 Release 2:ICCP Upgrade
Rel 3
FAT
EDS
FAT
ITEST
EDS
FAT
ITEST
EDS
SCED TestingRegUpload Offers
Rel 4
Rel 5
Rel 7
Rel 6
6 month LMP Posting
CRR Data Validation Trial Ops of CRR
LFC Comms Testing
ITEST
EDS
FAT
FAT
EDS
ITEST
ED
S 4 Go-Live
Activities
EDS 1 EDS 2 EDS 3 EDS 4
MP Interface Spec
Start of EDS activities
FAT milestones
EDS Preparatory Milestones
Rel 8
Rel 9
LFC Testing
ReadinessDeclaration
Readiness Declarations
http://nodal.ercot.com 29Lead from the front
Texas Nodal
High Level View of Registration and Qualification
CRR = CRR Acct Holder X= Required, X* = Required only for new MP, O= Optional
Q = QSE without Resources (formerly Level 1 & 2 QSEs)
QR= QSE with Resources (formerly Level 3 & 4 QSEs)
TD =TSP and/or DSP
http://nodal.ercot.com 30Lead from the front
Texas Nodal
High Level View of Registration and Qualification (cont’d)
Calendar of Registration Documentation• Aligning Registration Dates to coordinate with EDS
Milestones:• Resource Registration data (fully-certified version)
– Provide to ERCOT by 9/1/07– In time for 10/1/07 mandatory EDS3/SCED testing
• Attestation for Qualification of Ancillary Services– Provide to ERCOT by 9/1/07– In support of LFC testing preparation/scheduling
1/1/08• Sign MP Standard Form Agreements
– Time of BOD approval for PRR/NPRR, not EDS– Estimate BOD approval in place by 10/1/07– Target completion 60-90 days later
• CRR Account Holder Application– Provide to ERCOT by 3/1/08– In time for 4/1/08 testing of CRR Auction
• QSE Application (new QSEs)– QSEs with Resources (August 2007)– QSEs without Resources provide to ERCOT by
3/1/08– Receive by 3/1/08, in time for 4/1/08 testing of DAM
http://nodal.ercot.com 31Lead from the front
Texas Nodal
What is Data is needed to support EDS3?
Resource Data is needed for EDS3-SCED Testing
• What ERCOT has:– Zonal Generation Asset Registration Forms (GARFs on file at ERCOT)
• What ERCOT does not have:– Subset of new resource parameters for nodal market (not on file at ERCOT)
• ERCOT’s plan to get EDS3 Resource Data established in nodal systems– In the short term (for pre-EDS3 testing), ERCOT is to release a
spreadsheet to QSEs and/or Resource Entities to complete the “bare-bones” list of Resource data needed for data entry validation
• ERCOT will upload data into Market Management System (MMS)
– In the longer term (for mandatory EDS3 activities), ERCOT is to release a new version of the Resource Asset Registration Form to Resource Entities to have completed and on file at ERCOT
• ERCOT will release new Resource Asset Registration Form (and upon request can provide the zonal GARF that is on file)
• New form will highlight new data elements needed
http://nodal.ercot.com 32Lead from the front
Texas Nodal
Nodal Sandbox/Interface Testing Environment
• Purpose of Sandbox
– Allow Market Participant developers (and vendors) to access ERCOT programmatic interfaces and test code for data submission
• Limitations/advantages of sandbox
– Not an EDS environment
– No data validation, only technical validation of code and format
Market Participant Systems
ERCOT WebServices
Nodal Application Databases
Market Participant Systems
ERCOT WebServices
Sandbox/Interface Testing Environment
(no application behind web interface)
EDS
Environment
http://nodal.ercot.com 33Lead from the front
Texas Nodal
Nodal Sandbox/Interface Testing Environment (cont’d)
• Limitations/advantages of sandbox (cont’d)– Environment is already available to the market for testing– Developer can use Sandbox to shake-out coding issues– Developer can use Sandbox to resolve security/digital certificate issues
• Allows technical testing prior to pre-EDS and EDS activities• Market Interface document available as Machine-to-Machine Interface (
http://nodal.ercot.com/docs/pd/ida/index.html#oth)
Market Participant Systems
ERCOT WebServices
Nodal Application Databases
Market Participant Systems
ERCOT WebServices
Sandbox/Interface Testing Environment
(no application behind web interface)
EDS
Environment
http://nodal.ercot.com 34Lead from the front
Texas Nodal
Summary and Questions
Readiness Summary:• Sandbox/Interface Testing Environment is already available to test
submission of some transactions– No Resource data needed as there is no data validation
• To obtain Resource Registration Data, ERCOT is planning to release draft of Resource data to TPTF by June 1, and plans formal release of registration forms to market by June 28.
– Pre-EDS3 participants will need to provide “bare-bones” list of Resource data
– Mandatory EDS3 will require full completion of Resource Registration Forms (9/1/07)
Questions before getting into more details of EDS3?
http://nodal.ercot.com 42Lead from the front
Texas Nodal
Future workshops
• Frequency of workshops?• Frequency of WebEx?• SCED, LFC, CRR etc