th1.l10.2: tandem-x commissioning phase status
TRANSCRIPT
IGARSS 2010, Honolulu, 29th July
TanDEM-X Commissioning Phase Status
J. Hueso Gonzalez, M. Bachmann, H. Hofmann and
DLR commissiong phase team
IGARSS 2010, Honolulu 29.07.2010
Slide 2
New Challenges TanDEM-X Mission
Two satellites
System complexity increased
Close formation flying
Coordination TanDEM-X and TerraSAR-X mission acquisitions
Bi-static acquisitions and processing chain
Requirements for a high quality global DEM
Short duration of commissioning phase required
Limited nominal overlap
2.5 years for the DEM
TerraSAR-X2007 2008 2009 2010 2011 2012 2013 2014 2015
TanDEM-X
DEM Acquisition
CP
IGARSS 2010, Honolulu 29.07.2010
Slide 3
Overview TanDEM-X Commissioning Phase Plan
20 km Formation Close Formation
TDX monostaticcommissioning phase
LEOP and GS checkout
Orbit drift
1 month 2,5 months
Launch 21.06.2010
Transition 20km 07.2010
Transition close formation 10.2010
2 months
Operational01.2011
Bistaticcommissioning phase
• Make satellite operational – monostatic and bistatic
• Verify specifications
• Ensure satellite safety in close formation
IGARSS 2010, Honolulu 29.07.2010
Slide 4
Launch and Early Orbit Phase (LEOP) &Ground Segment Checkout
IGARSS 2010, Honolulu 29.07.2010
Slide 5
TanDEM-X Launch – June 21st 2010
TanDEM-X launch video
IGARSS 2010, Honolulu 29.07.2010
Slide 6
LEOP – Orbit configurations
TDX-1 insertion 15700 km behind TSX-1
Earth rotation and time delay: both satellites acquire different regionson the same pass
Approximation of TDX-1 640km/day
Objective: reach 20 km along track separation
Allows repeat pass interferograms
No interferences for monostatic calibration
510-515 kmHeight
~95 minPeriod
11 daysRepeat cycle
97.4°, polarInclination
TSX-1 and TDX-1reference orbit characteristics
TSX-1
TDX-1
15700 km20 km
IGARSS 2010, Honolulu 29.07.2010
Slide 7
LEOP & Ground Segment Checkout
Space segment checkout
Satellite activation
Boom deployment
First contacts, telemetry
Ground station checkout
Tracking, downlink, data distribution
Verification of orbit products: orbit position, attitude, baseline
Product ordering chain: planning, commanding and data dump
Thermal behaviour instrument
SAR processor checkout
required before starting the SAR system calibration
IGARSS 2010, Honolulu 29.07.2010
Slide 8
First SAR Images of TDX-1 – Ukraine
River Donets
Agricultural land types↕
Polarization response
24/06/2010; dual-pol SAR image; ascending orbit, right looking
IGARSS 2010, Honolulu 29.07.2010
Slide 9
First SAR Images of TDX-1 – Ukraine
vTDX-1
vTRAIN
Azimuth displacement moving target~ vTRAIN range
azimuth
range
IGARSS 2010, Honolulu 29.07.2010
Slide 10
TDX-1 Monostatic Commissioning –Pursuit Monostatic Formation
20 km
IGARSS 2010, Honolulu 29.07.2010
Slide 11
TDX-1 Monostatic Commissioning Phase
Profit from TSX-1 mission
Experience commissioning phase
TSX-1 with outstanding performance
Successful integration and verification of ground and space segment
Characteristics orbit
20 km along track separation: allow monostatic calibration
Helix formation – 300 m radial, 1305 m horizontalto compensate residual Earth rotation
Repeat pass acquisitions, same coverage,very small baseline
Duration 2.5 months
IGARSS 2010, Honolulu 29.07.2010
Slide 12
Mono-CP: Safety Aspects
Safe Formation Flight
Collision avoidance mechanisms
Maneuver execution, 1st helix formation
Acquisition Safe Mode (ASM): magnetic torquer mode
Exclusion Zone
Prevent mutual SAR illumination: damage electronics
Failure detection, isolation and recovery
Sync Warning & Inter-Satellite Link
TSX-1 – TDX-1 real time mutual health check
Contingency handling in ASM
Disable transmission when neighbor satellite is not nominal
IGARSS 2010, Honolulu 29.07.2010
Slide 13
Mono-CP: Calibration and Performance
SAR External Calibration
Campaigns for deploying point targets and rainforest acquisitions
Geometric, antenna model, radiometric
Internal Calibration
TRM accuracy and stability
Monitor instrument drift, replica quality
Overall SAR Performance
Commanding, timing, instrument settings
Radiometric parameters: NESZ, ASR, resolution
Product Verification
Doppler centroid and pointing verification
Image quality, coverage
Ensure quality for TerraSAR-X mission products
IGARSS 2010, Honolulu 29.07.2010
Slide 14
Bistatic Commissioning –Close Formation
IGARSS 2010, Honolulu 29.07.2010
Slide 15
Bi-static Commissioning Phase
Duration: 55 days
Close formation 0m average along track 500m cross-track baseline
First bistatic cycle
Ground stations network
Roll steering
Complete bistatic chain: order, commanding, processor
Baseline offset calibration
DEM calibration tests
Flight Qualification Review
Nominal DEM acquisition should begin
IGARSS 2010, Honolulu 29.07.2010
Slide 16
TanDEM-X Global Test Sites
0° - Equator
30°N
60°N
30°S
60°S
IGARSS 2010, Honolulu 29.07.2010
Slide 17
Highlights
IGARSS 2010, Honolulu 29.07.2010
Slide 18
Highlights
• Accurate injection in orbit
• Satellite control High attitude and orbit stability Successful Acquisition Safe Mode test
• First SAR image three days after launch
• First interferogram incorporating both satellites after 26 days
• Excellent status of the ground segment chains for TerraSAR-X and TanDEM-X acquisitions
CommandingProcessingDownlink
220 m± 2 kmAltitude
TDX-1ExpectedInjection parameter
0.0095 deg± 0.04 degInclination
No showstoppers at all!
IGARSS 2010, Honolulu 29.07.2010
Slide 19
TanDEM-X first interferogram and DEM (I)
Repeat pass on 15/07/2010: 48s/370 km separationLarge along track distance: different coverage due to Earth rotation
Convergence at the poles angular velocity Earth is reduced there
TSX-1
TDX-1
Ground tracks crossat the poles
IGARSS 2010, Honolulu 29.07.2010
Slide 20
TanDEM-X first interferogram and DEM (II)
Rotation of range-azimuth coordinatesGround spectra can be aligned by applying squint during acquisition
Observe the same portion of the azimuth spectrum
x (range)
y (a
zim
uth)
x‘
y‘
kx
k y Ground spectraacquired at zero-Doppler
Squint correction applied
Rotated SAR coordinates Rotated ground spectrum
-0.058º bkw squintdoppler -500 Hz
0.93º fwd squint
doppler 800 Hz
IGARSS 2010, Honolulu 29.07.2010
Slide 21
Results over October Revolution Island (Russian Arctic)
Coherence
DEM
SAR Image
Coherence
Interferogram
* Baseline: ~2600 m* hamb = 3m* DEM accuracy ≈ 10cm
No azimuth filter needed in interferometricprocessing
IGARSS 2010, Honolulu 29.07.2010
Slide 22
Questions?
THE END