the long thermopile
TRANSCRIPT
The Long Thermopile
Ed Yarmak, P.E.
Arctic Foundations, Inc.
Kotzebue – Maniilaq Health Center (1993) Fairbanks – FAA Flight Service Center (1987)
Program
• Introduction to the “Long Thermopile”
• Brief Bio of the Inventor
• The First Thermopiles
• Notable Early Projects using Thermopiles
• Aurora Tower – 1st Commercial Thermopiles (56 years and counting)
• Bethel OMS Building – Early At-Grade w/Passive Subgrade Cooling
• Thermopiles, Thermo Ring-Piles & Thermo Helix-Piles
• Thermoprobes; Straight, Sloping Evaporator and Flat-Loop Evaporator
• Thermopile Conversions
• Hybrid Thermosyphons
• Buried Condenser Thermosyphons
• Coupled Thermosyphons
• Wellhead Thermosyphons
• Projections
The Long Thermopile
Passive Two-Phase Freezing System
Two-phase thermosyphons are passive refrigeration devices that transfer heat
against gravity. Construction is typically a closed ended tubular vessel
charged with a two-phase working fluid. The vapor phase of the working
fluid fills the majority of interior of the vessel with the liquid phase filling the
minority of the volume. Typically, a thermosyphon is installed with a portion
of the vessel above ground and the remainder buried. When the above
ground portion is cooled below the saturation temperature of the vapor, the
vapor condenses on the interior of the cooled portion of the vessel and
releases its latent heat of vaporization. This slightly decreases the interior
pressure and initiates boiling and vaporization of the liquid whereby heat is
absorbed from the ground. The condensate in the upper portion of the vessel
flows via gravity to the lower portion of the vessel. Whenever the
condensate comes in contact with a warmer portion of the vessel, it
evaporates and causes that area of the vessel to cool. The cycle continues as
long as the above ground portion is colder than the below ground portion of
the thermosyphon
The Long Thermopile
Abbreviated Biography of the InventorErv Long was born to a farm family in Minnesota in 1920. He attended the University of Minnesota and earned a
bachelors degree in aeronautical engineering. His university time was interrupted by service in the US Army Air Corp
where he was a multi-engine pilot (B-17). While in school, he worked at for Strato Equipment Company specifically on
some of the early pressure suits and oxygen supply systems for high altitude pilots. Erv came to Alaska from Minnesota
in 1947 to sell an aircraft and ended up being a bush pilot for two years. Bush flying wasn’t paying the bills, so Erv
found a job as an engineering technician at the soils laboratory of the COE Alaska District. His work with the Corps
took him all over Alaska. He retired from the Corps in 1976 as the Chief of Foundations and Materials, Alaska District.
Erv started Arctic Foundations, Inc. in 1972 and lead the company until he passed away in June of 2012 at the age of
91.
The Long Thermopile
The Long Thermopile is a two-phase thermosyphon that moves heat
against gravity with no external power input. When the air is colder than
the soil, the system withdraws heat from the soil. When the air is warmer
than the soil, they system is dormant.
“The system is thermally self-regulating so that all heat travels upward
except for the normal thermal conduction of the soil materials” - ELL
Mr. Long granted the COE royalty-free use of his method while he was in
their employ. He proposed the method as a solution to problems at the
Bethel White Alice site in 1958, but was told that “it sounds too simple to
work”.
When a thawed aquifer was found at the 13 foot depth at the site of the
Aurora communications site in the Copper River Valley, the Corps opted
to try Long’s method because it was relatively inexpensive and could be
converted to a conventional mechanically refrigerated system if it didn’t
prove satisfactory. A test pile was installed to prove the refrigeration
system, and then, the first commercial thermopiles were installed in 1960.
Data from the instrumented test pile was reported by Erv Long at the
International Conference on Permafrost in 1963 at Purdue University.Aurora Test Pile (1960)
The First Commercial Long Thermopiles
Aurora Tower thermopile being installed and Aurora Com
building with installed thermopiles and steel framing (1960).
The First Commercial “Long Thermopiles”
Aurora Tower under Construction (1960)
The Aurora Tower
The Aurora Tower Thermopiles (1989)
The Aurora Tower
The Aurora Tower Thermopiles (2007)
Bethel National Guard OMS Building
Bethel National Guard OMS Building Constructed 1978-1979
Bethel National Guard OMS Building
Bethel National Guard OMS Building 1979
Thermopiles
Thermopiles are load bearing two-phase thermosyphons that are
generally used to found structures where permafrost soils exist.
Typical Thermopile applications follow:
Installation at sites with a frost susceptible active layer where heave
and pile jacking are problems. Thermo-cycling reduces frost heave
forces to negligible quantities.
Installation in marginal permafrost where pile creep rates are high.
Thermo-cycling reduces soil temperatures and subsequently
reduces creep rate.
Installation at sites with saline permafrost where allowable stresses
are reduced due to substantial quantities of unfrozen water in the
soil matrix. Thermo-cycling freezes water near piles and pushes
salts away. Also proven effective for moving glycol from a piling
face.
Installation at sites where development has increased the heat load
to the subgrade. Heat transfer rates of the Thermopiles need to be
sized to balance or exceed heat load.
Gakona HAARP (2003)
Top Left • Bethel, Alaska; Main Post Office
Bottom Left • Bethel, Alaska; Nexrad
Bottom Right • 12” Thermopiles
Thermopiles
Gakona Senior Center Thermo Ring-Piles
Thermopiles Loaded for Delivery in Erv Long’s Driveway (1979)
Thermo Helix-PilesThermo Helix-Piles are Thermopiles with helical shear rings
attached and can be used in all applications where Thermopiles
are appropriate. At one time, individual rings were used instead
of the helix. Most applications use a helix that has a strip width
of 2 inches (50mm). Typical Thermo Helix-Pile applications
follow:
Generally, Thermo Helix-Piles support greater loads than
adfreeze piles. Shear loading in lieu of adfreeze allows higher
unit stresses that equate to shorter embedment depths.
Thermo Helix-Piles are used when high transient loads are
expected. The flexibility of the helix allows a uniform load
distribution along the pile.
Thermo Helix-Piles are used to support critical structures where
consequences of foundation movement are high. Thermo Helix-
Piles offer high redundancy.
Thermo Helix-Piles are used when the installation must be
optimized for the lightest pile to carry the heaviest load.
Thermo Helix-Piles loaded for shipment to Kotzebue, Alaska
Thermo Helix-Piles supporting K-12 School at St. Michael, Alaska
Thermo Helix-Piles
RCMP Detachment, Inuvik, NWT, Canada – 2014
Thermo Helix-Piles
RCMP Detachment, Inuvik, NWT, Canada – 2014
Thermo Helix-Piles
Kwigillingok – 18”Ø Thermo Helix-Piles for K-12 School Addition (2013)
Thermo Helix-Piles
Bethel – Yukon Kuskokwim Aquatic Health and Sefety Center (2013)
Thermoprobes
Thermoprobes are non-structural high-capacity two-phase
thermosyphons that are used to provide passive refrigeration to maintain
or create permafrost. Thermoprobes are used to allow heated structures
to be constructed at-grade on permafrost. Additionally, they are used to
passively refrigerate the soil around buried heat sources - i.e. pipelines,
wells, utilidors, etc. - to preclude thawing and subsequent settlement of
the permafrost. Thermoprobes are also used to create frozen barriers for
hazardous materials, to create impervious frozen dams for water control,and to provide frozen encapsulation of hazardous materials.
Thermoprobes loaded onto flatbed at plant for transport.
Thermoprobes for
tunnel portal
cooling in
Kyrgyz Republic
(2009)
Retrofit Existing Structure (2011)
Frozen Core Dams
Leslie Long Lake Dam, Ekati
Diamond Mine, NWT, Canada
Hybrid thermosyphons for dike cooling, Diavik
Diamond Mine, NWT, Canada
Arctic Bridge Pier Thermosyphons (2014)
Straight thermosyphons inside bridge piers, North Slope, Alaska (2014)
Sloping Evaporator Thermoprobes
Sloping evaporator Thermoprobes are found on the majority of existing
passive subgrade cooling system installations beneath slab on grade
structures. These units utilize a sloped evaporator to insure that the
condensate will flow from the condenser to the lowest portion of the
evaporator. Typically, evaporator slopes are between 10% and 3% with
the median being 5%.
Structures founded on grade over permafrost utilizing Thermoprobes for
subgrade cooling also have two other very important components of
design: subgrade insulation and NFS fill. The typical thermal design
methodology for this type foundation economically balances the three
major components. The insulation reduces the heat load on the subgrade
and limits the thawing of the underlying NFS fill during the summer
season when the Thermoprobes are dormant. The NFS fill contains the
seasonal thaw and provides a heat sink beneath the structure. The
Thermoprobes remove heat from beneath the structure primarily during
the freezing season and refreeze the NFS fill so that it is completely
frozen at the beginning of the thawing season.
Sloping evaporator Thermoprobe in typical subgrade
cooling installation beneath slab on grade structure.
Sloping Evaporator Thermosyphons
Thule, Greenland - Power Plant Subgrade Cooling System (1985)
Sloping Evaporator Thermosyphons
Evaporator Installation (2012) Condenser Installation (2013)
Thule, Greenland – New Tracking Station (Under Construction)
Flat-Loop Thermoprobes
Thermoprobes with flat-loop evaporators utilize
proprietary internal components within the riser to
force the working fluid to travel in one direction
within the evaporator. As the working fluid absorbs
heat, it vaporizes and expands. The expansion helps
to push the working fluid around the loop. The
working fluid moves around the loop in two-phase
flow, increasing in velocity as it proceeds around the
loop. This allows the loop to be placed on a
“relatively” flat plane. The term “relatively” means
that there can be some undulations in the vertical
profile of the loop. Typical designs allow for as
much as 150mm (6 inches) amplitude in the
undulations with no detrimental effects on the system.
The subgrade can just be graded to a near flat
condition and the loops then placed directly on the
graded material. Typically the level of the loops is
approximately 0.5m to 1.0m (1.5 feet to 3 feet) below
the base of the subgrade insulation. Loop lengths of
220m (720 feet) are not uncommon.
Deadhorse – Baker Hughes Facility
(2008/2009)
86m x 102.2m At-Grade Structure Over Insulated Subgrade on Permafrost.
Basic Details:
150mm insulation beneath slab
Thermosyphon evaporators on 1.2m spacing
1.07m NFS fill beneath insulation over tundra
Interior Design Temperature is 21°C
Deadhorse – Baker Hughes Facility
(2008/2009)
Air and Evaporator Temperatures
Deadhorse – Baker Hughes Facility
(2008/2009)
Air and Evaporator Temperatures
Deadhorse – NSB Service Area 10 WWWTP
Flat-Loop Evaporator Thermosyphon System for 252’ x 252’ (77m x 77m) At-Grade Building
October 12, 2013
Deadhorse – NSB Service Area 10 WWWTP
Completed Building
Prudhoe Bay – Thermopile Conversions (1981)
Central Compressor Plant – 474 Standard Piles were converted to Thermopiles
Hybrid Thermosyphons
Hybrid thermosyphons are designed so that they can
be cooled actively as well as passively. Active
cooling means some external energy must be
expended to promote cooling and mechanical
refrigeration is typically used. Most any of the
thermosyphons manufactured by AFI can be built as
hybrid units with the addition of an internal heat
exchanger. A hybrid unit does not have to be
actively cooled. The hybrid portion of the design
might be to provide a higher redundancy factor over
the life of the project. A typical application for
hybrid thermosyphons is to accelerate construction
on a project by active freezing. In 1984, hybrid
thermosyphons were first used to actively freeze
Thermopile foundation for a communications site in
Galena, Alaska. Prior to that time, blowing chilled
air across the condensers was the method used for
actively cooling thermosyphons. Thermosyphon
evaporators had also been used as evaporators for
active refrigeration, however, the working fluid had
to be evacuated for refrigeration to occur and then
replaced afterward.
Hybrid Heat Exchanger
Galena – First Hybrid Thermosyphons (1984)
Thermo Helix-Piles were fitted with internal heat exchangers and refrigerated to allow full load 2 weeks after installation
Hybrid Thermosyphons
Hybrid flat-loop evaporator type Thermoprobes being refrigerated during building construction to accelerate construction of
a service building for the new Denali Canyon Lodge located just outside the entrance to Denali National Park (2005).
Hybrid Thermosyphons
Hybrid Thermo HelixPiles for Wind Tower Foundation, Deering, Alaska (2015)
Oak Ridge National Laboratory – HRE PondHybrid Thermosyphons for Containment (1997)
Created Permafrost to Contain Sr90 and Cs137 for 7 ½ Years
Oak Ridge National Laboratory – HRE PondHybrid Thermosyphons for Containment (1997)
Created Permafrost to Contain Sr90 and Cs137 for 7 ½ Years
Fairbanks (UAF) – Thompson Drive (2003)Buried Hairpin Thermosyphons
This infrared image shows heat from the condensers of
totally buried Thermoprobes radiating to the cold
ambient air at Thompson Drive in Fairbanks, Alaska.
(Photo courtesy of Doug Goering, UAF)
Thermoprobes with buried condensers are designed to release
the heat picked up from the subgrade through the near surface
soils or embankment. A typical application for these units is in
roadway or airfield sections where heat is released just under
the pavement. The condensers can be coupled to either vertical
or sloping evaporators. The system is designed to provide a net
cooling below the embankment section to preserve the
permafrost. Because the condensers release heat through the
surface, insulation can be used in the design without the icing
effects that are typical of insulated sections. In cold climates,
this system is generally not designed to thaw ice and snow on
the pavement, however, it will cause sublimation that will
loosen the bond between the pavement and the ice. The closer
the condensers are to the surface, the better this system will
work. The standard finned condenser will out-perform a buried
condenser in most cases, however, the standard condensers are
prone to damage and can be inundated in snow, rendering them
inoperative.
Coupled Thermosyphons (2011)
Wellhead Thermosyphons (2014)
“Alpine-Style” thermosyphons with condensers offset 100’ for well bore cooling, North Slope, Alaska (2014)
Projections
Crystal Ball (2015)
• There are new extraction,
transportation and infrastructure
projects in cold regions. To adapt to
climate change, more passive freezing
technology will be used in places it’s not
been used before.
• Likewise, hybrid (passive/active)
freezing systems will be used for
facilities.
• Foundation retrofits to stabilize existing
infrastructure so that it can last another
30 or 40 years.
Thank You!
Thermopile Fence Posts – Gakona HAARP Project (2004)