The Marmaray Project –and it’s Management

10th May 2005

Page 2: The Marmaray Project – and it’s Management

The Speaker

• Steen Lykke, Project Manager,Avrasyaconsult Joint Venture– 27 years experience civil/structural works– 13 years in tunneling works

• Pacific Consultant International (PCI)

Page 3: The Marmaray Project – and it’s Management

Presentation

Overview

Page 4: The Marmaray Project – and it’s Management

Overview

• Introduction to the Project• Special Challenges• Management and Organisation• Contract strategies

Page 5: The Marmaray Project – and it’s Management

Introduction to the Project

Page 6: The Marmaray Project – and it’s Management

19.6 km to Halkalı 43.4 km

to Gebse

13.3 km Tunnel

The Marmaray Project

Page 7: The Marmaray Project – and it’s Management

The Project Logo

www.marmaray.com

Page 8: The Marmaray Project – and it’s Management

Crossing Bosphorus

Page 9: The Marmaray Project – and it’s Management

The Visions

Historic developments of crossing

Page 10: The Marmaray Project – and it’s Management

The Vision 1860

Page 11: The Marmaray Project – and it’s Management

Per Hall Vision 1976-77

Road-Rail on piles or fill, 1976

Rail only, 1977

Page 12: The Marmaray Project – and it’s Management

PBI Concepts

2000

1985

Page 13: The Marmaray Project – and it’s Management

Schematics of Project

• Black: on surface• Green: sub-surface

Halkali Atakoy Yedikule Haydarp. Pendik Gebze1

2

3

1

2

3

Page 14: The Marmaray Project – and it’s Management

Functionality

• Capacity not less 75.000 pphpd

• 10 car trains, each car 5 doors

• Eaquals 8 bridges

Page 15: The Marmaray Project – and it’s Management

Visions become real

Page 16: The Marmaray Project – and it’s Management

Special Challenges

Highlights

Page 17: The Marmaray Project – and it’s Management

Special Challenges

• Deepest Immersed tunnel

• Seismic• Bosphorus Strait• Safety• Historical Heritage

Page 18: The Marmaray Project – and it’s Management

Organisation

In Brief

Page 19: The Marmaray Project – and it’s Management

The Organisation

BC1CR1

CR2

Contract

EmployerEmployer’s

Representative

Day to Day management as

delegated

Contractors

Page 20: The Marmaray Project – and it’s Management

The Contracts

From Halkali to Gebze

• BC1, tunnels and stations including E&M• CR1, Commuter Rail Infrastructure and all

Systems including OCC• CR2, Rolling Stock

Page 21: The Marmaray Project – and it’s Management

The Avrasyaconsult JV

• Pacific Consultant International, Japan– Lead partner

• Yuksel Proje, Turkey– Local Joint Venture Partner

• Oriental Consultants, Japan– Joint Venture Partner

• Japan Railways Technical Services,– Joint Venture Partner

Page 22: The Marmaray Project – and it’s Management

The Avrasyaconsult JV

Associated Companies:• Parsons Brinckerhoff, or PBI, USA• Terzibasioglu Musavir Muhendislik Ltd.Sti,

or TMM, Turkey• Yerbilimleri Etud ve Musavirlik Ltd.Sti, or

SIAL, Turkey

Page 23: The Marmaray Project – and it’s Management

Avrasyaconsult

Project Management

Bosphorus CrossingDivision

Commuter RailDivision

ContractsDivision Experts

Page 24: The Marmaray Project – and it’s Management

Management Principles

Page 25: The Marmaray Project – and it’s Management

Management

• By Objectives, delegation and follow up

• By acting Pro-actively and via Controlled Processes

BC1CR1

CR2

Page 26: The Marmaray Project – and it’s Management

Management

• By observing priority

T

Q

C T

T

Q

Q

C

CT: TimeQ: QualityC: Costs

Page 27: The Marmaray Project – and it’s Management

Management

• By observing the ”7 C’s”

Clarity Commu-nication

Coordination Cooperation

Consistancy CommitmentContinuity

Page 28: The Marmaray Project – and it’s Management

Contract Strategies

Page 29: The Marmaray Project – and it’s Management

Type of Contract

Define project purpose and functional requirements

Conceptual design

Basic Design

Detailed Design

Construction

Employer’s Design

Design & Build

Employer / ContractorInterface

Page 30: The Marmaray Project – and it’s Management

How many contracts ?

• One extreem: 1 Contract• Another extreem: 25 Contracts

• Must match type of Contract• Must match Management Strategy

• Balance chosen on this Project:

Three Contracts

Page 31: The Marmaray Project – and it’s Management