©the mcgraw-hill companies, inc. 2008mcgraw-hill/irwin chapter 8 timeliness: scheduling and project...

66
©The McGraw-Hill Companies, Inc. 2008 McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

Upload: abraham-hodge

Post on 13-Dec-2015

223 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin

Chapter 8

Timeliness: Scheduling and Project Management

Page 2: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-2

Learning Objectives

• Explain the effect time has on each profitability measure.• Describe the impact of feedback delay on quality.• Explain the common time reduction strategies.• Construct a Gantt chart.• Sequence orders using the traditional sequencing rules.• Describe the physical features of queues and describe how they affect

queue performance.• Compute the probability of x arrivals per unit time for a queue.• Describe the psychological approaches to managing perception of queue

length.• Construct a network diagram for a project.• Identify the critical path for a project using CPM calculations• Calculate the likelihood of completing a project in a specified time.• Complete the calculations necessary to effectively crash a project.

Page 3: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-3

• Time is money– It affects customer perceived value– It affects Net Income – It affects Return on Assets

Operations Management Framework

Page 4: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-4

Time and Customer Value

• Speed and flexibility– Faster processes allow greater flexibility

• Deliver more options in the same amount of time– Customers will only wait so long.

• Start later, closer to demand– Better predictions of what will be needed

Page 5: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-5

Time Really Is Money

• Time affects profitability through net income– Time-based value attributes - Increasing net sales

• Response time

• Delivery dependability

Page 6: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-6

Time Really Is Money

• Managing timing of payments to make money (managing “float”)– Example. . . .Travel Agents

• You pay right away (on a credit card)– They pay in 30 days (business billing cycle)

They deep the interest

– Example . . . . .Insurance companies– Collect only as much as (or less than) they will eventually pay in claims

– Invest money while they are waiting to pay out claims

Page 7: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-7

The Effect of Time on ROA

• The cash-to-cash cycle

• Not just production time. . .– Waiting for supplies to arrive -- Opportunity cost of sales

– Waiting to sell product -- Delay of return on investment in inventory and production

– Waiting to collect from customer -- Financing the customer’s purchase

Page 8: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-8

The Effect of Time on ROA

Suppose the transaction in exhibit 8.1 netted a $200 return on total expenditures of $1000 (a 20% return). What would happen to ROA if the cash-to-cash cycle went from 17 weeks to 13 weeks?

With a 17 week cash-to-cash cycle, there are approximately three transactions per year for a return of $600 (60%).

Reducing the cash-to-cash cycle time to 13 weeks results in the $1000 being turned over four times instead of three. $800 will now be generated. The yield shifts from 60% to 80%.

A 23.5% reduction in time results in a 33% increase in return financial return

Page 9: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-9

The Effect of Time on ROA

• Shorter delivery lead-times from suppliers mean lower inventory requirements

Weekly DeliveryAverage Inventory (Cases) = 400 casesAverage Inventory (Investment) = $106,000

Daily DeliveryAverage Inventory (Cases) = 80 casesAverage Inventory (Investment) = $21,200

Example from Chapter 2• Deliveries of 800 cases weekly (all are consumed)• Cases cost $265, Sell for $300• Weekly Net Income is $28,000

ROA = $28,000/$106,000 = 26.42%

ROA = $28,000/$21,200 = 132.08%

As inventory is reduced to 1/5, ROA increases five-fold

Page 10: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-10

Feedback Delay. . . Another benefit of time reduction.

• Elimination of causes of quality problems depends on timely information.

• The greater the elapsed time between producing a defect and discovering it, the less likely the defects cause will be found.

Page 11: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-11

General Time Reduction Strategies

• Two general approaches:– Compressing time of activities

– Making tasks concurrent instead of sequential

Page 12: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-12

General Time Reduction Strategies

Insert exhibit 8.3

Page 13: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-13

General Time Reduction Strategies

Insert exhibit 8.4

Page 14: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-14

General Time Reduction Strategies

Insert exhibit 8.5

Page 15: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-15

Scheduling

• Definition: Determination of when something is to be done and the tasks and activities required to do it– Scheduling aids in on-time completion

• Direct link to value perceived by customers

– Scheduling improves the utilization of the firm’s resources• Direct link to productivity

• Forward scheduling– When start date is known and completion needs determination

• Backward scheduling– When completion date is known and start date needs determination

Page 16: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-16

Scheduling

• Gantt Charts– The layout of steps within a process

– The layout of multiple tasks that utilize a single resource.

Page 17: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-17

Traditional Job Shop Sequencing

• Sequencing rules for scheduling multiple jobs at a single resource– First Come, First Served

– Earliest Due Date

– Shortest Processing Time

– Critical Ratio• Time Remaining/effort remaining

• C.R. < 1 means there is no way to complete the job on time

Page 18: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-18

Example 8.1 Job Sequencing Using EDD

Page 19: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-19

Example 8.1 Job Sequencing Using EDD

Page 20: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-20

Example 8.2 Job Sequencing Using SPT

Page 21: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-21

Example 8.3 Job Sequencing Using Critical Ratio

Page 22: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-22

Traditional Job Shop Sequencing

• Most traditional sequencing rules assume a single operation.

• Slack Time Remaining– Slack = Days to due date - Total processing time (all operations)

– Slack per remaining operation = Slack / Number of remaining operations

Exhibit 8.12: Slack per Remaining Operations

Page 23: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-23

People Are Not Products:People Expect To Be Treated “Fairly”

• Queue configuration: The physical design of the lines and servers in a queuing system.

• Server: A resource that is able to complete the process or service that customers or jobs wait in queue for.

• Phase: A distinct step in a process that requires a separate queue.• Jockeying: When customers switch lines hoping to move faster.• Queue Discipline: The rules that management enforces to

determine the next customer served in a queue.• Calling Population: the population of arriving customers or

orders.

Page 24: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-24

The Queue Arrival Process: Determining the Probability of x arrivals in a time period

• Queue arrivals follow a Poisson distribution.

• P(x) = the probability of x arrivals in a time period

• x = the number of arrivals per unit time

• λ = the average arrival rate in a certain time increment

• e = 2.7283 (the base of the natural logarithms)

( )!

xep x

x

Page 25: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-25

Managing Queue Arrivals

• A Call center receives 36 calls per hour, Poisson distributed. What is the probability of receiving 41 calls?

• λ = 36• x = 41• e = 2.7283 (the base of the natural logarithms)

36 4136( )

41!

4.46%

ep x

( )!

xep x

x

Page 26: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-26

People Are Not Products:Treating People “Fairly”is Important

• First Come, First Served seems the most fair

Page 27: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-27

People Are Not Products:Serving Customers in Queue

• Psychological features of queues• Make the wait seem less be . . .

– Keeping customers busy– Keeping customers informed– Treating customers fairly– Starting the service as soon as possible– Exceeding the customer’s expectations

Page 28: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-28

People Are Not Products:Queue Alternatives

• Avoid Queues: Developing Alternate Procedures– Express check-in and check-out (hotels, rental cars)– Pay bills by mail and online, not in person

• Parking tickets paid online

– Automatic Checking Account Debits• Phone,Utilities, Credit Cards, Mortgages

Page 29: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-29

Project Management

• A project is a set of activities aimed at meeting a goal, with a defined beginning and end.

Page 30: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-30

Project Management with Certain Time Estimates

• Summary of steps:– Determine activities that need to be accomplished– Determine precedence relationships and completion

times– Construct network diagram– Determine the critical path– Determine early start and late start schedules

Page 31: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-31

• Create Network Diagram– Based on order of precedence

among activities

Project Management: Scheduling Projects with Certain Time Estimates

Page 32: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-32

Calculation of the Critical Path

• Network approach helps calculate project duration

• A “path” is a sequence of activities that begins at the start of the project and goes to the end of the project– 1,2,3,5,6,7,8

– 1,2,4,6,7,8

– The “critical path” is the path that takes the longest to complete• and thus determines the minimum duration of the project

1 2

4

3 5

6 7 8

Page 33: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-33

Calculation of the Critical Path

Exhibit 8.17: Project Detail

Page 34: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-34

Calculation of the Critical Path

• Critical Path– The path that takes

the longest to complete

1 2

4

3 56 7 8

4 weeks 10 weeks

4 weeks

2 weeks 3 weeks

16 weeks 4 weeks 1 week

Exhibit 8.17: Project Detail

Page 35: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-35

Calculation of the Critical Path

• Critical Path– The path that takes the

longest to complete

C.P. = 40 weeks

Exhibit 8.17: Project Detail

1 2

4

3 56 7 8

4 weeks 10 weeks

4 weeks

2 weeks 3 weeks

16 weeks 4 weeks 1 week

Page 36: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-36

Calculation of the Critical Path

• It is possible for multiple Critical Paths to exist

• Suppose new information suggested that Activity 4 would take 5 weeks instead of 4. . .

X5

Exhibit 8.17: Project Detail

1 2

4

3 56 7 8

4 weeks 10 weeks

4 weeks

2 weeks 3 weeks

16 weeks 4 weeks 1 week

Page 37: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-37

Calculation of the Critical Path

X5

Exhibit 8.17: Project Detail

1 2

4

3 56 7 8

4 weeks 10 weeks

5 weeks

2 weeks 3 weeks

16 weeks 4 weeks 1 week

There are now two critical paths, each one is 40 weeks.

Page 38: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-38

Calculation of the Critical Path

• The Critical Path may also shift if non-critical activity is lengthened or Critical Path activity is shortened

• Suppose another update indicates

that it will actually take 6 weeks for Activity 4

The Critical Path becomes 41 days.

4 weeks

1 2

4

3 5

6 7 8

10 weeks

6 weeks

2 weeks 3 weeks

16 weeks 4 weeks 1 week

X6

Exhibit 8.17: Project Detail

Page 39: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-39

Determining Slack

• Slack - The amount of time an activity on a non-critical path can be delayed without affecting the duration of the project (i.e., without putting it on the critical path)– Four values are used

• Early start - Earliest an activity can start (based on prerequisites)

• Early finish - Earliest it can finish (based on prerequisites & duration)

• Late start - Latest an activity can start and not delay the project

• Late finish - Latest an activity can finish and not delay the project

Page 40: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-40

Calculating Early Start (ES) and Early Finish (EF)

• The process moves from left to right in network

The ES for the 1st activity is usually zero

The EF equals the ES plus activity duration

ES is the latest of the EF times

of an activity’s predecessors

Exhibit 8.17: Project Detail

Page 41: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-41

• This process moves from right to left in the network

Calculating Late Start (LS) and Late Finish (LF)

LF for the last activity equals the EF for the last activity

LS equals LF minus the activity durationLF is the earliest

of the LS times of an activity’s followers

Page 42: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-42

Calculating Slack

• Slack - The amount of time an activity on a non-critical path can be delayed without affecting the duration of the project (i.e., without putting it on the critical path)

• Can be computed by either:

Late Start - Early Start

or

Late Finish - Early Finish

• Activities that have zero slack form the critical path

Exhibit 8.21: ES, EF, LS, LF, and Slack Values

Page 43: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-43

Project Scheduling When the Times of Activities are Uncertain

• Summary of steps:– Determine the activities that need to be accomplished

– Determine the precedence relationships and completion times

– Construct the network diagram

– Determine the critical path

– Determine the early start and late start schedules

– Calculate the variances for the activity times

– Calculate the probability of completing by the desired due date

Page 44: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-44

Project Scheduling with Time Uncertainty

• The “Heuristic” approach to dealing with timing uncertainty– Based on understanding of individual activities as conforming to a “beta” distribution

• Take three time estimates– Optimistic - What is the (realistic) fastest we can get an activity done?

– Pessimistic - What is the (realistic) worst case scenario for delay?

– Most likely - What is our “most likely” estimate?

Page 45: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-45

Project Scheduling with Time Uncertainty

• Calculate the “expected time” for the activity

Where:

t = Expected Time

o = Optimistic estimate

m = Most likely estimate

p = Worst-case (pessimistic) estimate

4

6

o m pt

Page 46: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-46

Project Scheduling with Time Uncertainty

3 4(4) 54.00

6t

8 4(10) 1210.00

6t

Estimates Activity # Optimistic Most Likely Pessimistic

1 3 4 5 2 8 10 12 3 1 2 4

Activity #1 weeks

Activity #3 weeks

Activity #2 weeks

1 4(2) 42.17

6t

Page 47: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-47

1 2

4

3 5

6 7 8

4 weeks 10 weeks

4.17 weeks

2.17 weeks 3 weeks

16.17 weeks 4.17 weeks 1.17 weeks

C.P. = 40.68 weeks

How do we interpret this estimate???

There is a 50% chance we will finish faster, and a 50% chance that we will finish slower than our estimate

We assume that finish times across the entire project are distributed normally.

Using Variation in Time Estimates to Assess Duration Probabilities

Page 48: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-48

• So, if the “expected” duration (t) of the project is 40.68 weeks, how do we determine the probability of finishing it in 39 weeks (or less)?– Take advantage of the estimates of t and make an estimate of 2… – … draw on knowledge of statistics (especially Normal distributions),… – … and use the “standard normal probability” table along with the following equation:

Using Variation in Time Estimates to Access Duration Probabilities

Page 49: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-49

Where:

Z = Number of standard deviations D is from Te

t = Expected Time

D = Project duration I am thinking about

Note that this is , not 2 ,We have to take the square root of the “variance” to get the standard

deviation

D tZ

Using Variation in Time Estimates to Determine Duration Probabilities

Page 50: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-50

• We recognize that there is variation around our estimates– We are estimating “most likely” or “expected” not “exact”– Commonly assume to be a “Beta” distribution

• Calculating variance of the activity’s duration estimate:

22

6

op

Using Variation in Time Estimates to Access Duration Probabilities

Page 51: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-51

Estimates Activity # Optimistic Most Likely Pessimistic

1 3 4 5 2 8 10 12 3 1 2 4

Activity #1 weeks11.06

352

2

Activity #2 weeks44.06

8122

2

Activity #3 weeks25.06

142

2

Using Variation in Time Estimates to Access Duration Probabilities

Page 52: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-52

Using Variation in Time Estimates to Assess Duration Probabilities

• Calculate Critical Path using t

• Accumulate the variances of the individual activities

• Apply formula to estimate project duration probabilities

Where:

Z = Number of standard deviations D is from t

t = Expected Time

D = Activity duration I am thinking about

D tZ

Page 53: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-53

Using Variation in Time Estimates to Assess Duration Probabilities

Exhibit 8.22: Expected Values and Variances of Time Estimates

Page 54: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-54

1 2

4

3 5

6 7 8

4 weeks 10 weeks

4.17 weeks

2.17 weeks 3 weeks

16.17 weeks 4.17 weeks 1.17 weeks

Using Variation in Time Estimates to Assess Duration Probabilities

What is the probability of finishing in 39 weeks or less?

Exhibit 8.22: Expected Values and Variances of Time Estimates

Page 55: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-55

1 2

4

3 5

6 7 8

4 weeks 10 weeks

4.17 weeks

2.17 weeks 3 weeks

16.17 weeks 4.17 weeks 1.17 weeks

C.P. = 40.68 weeksSum of Variances = 2.56 weeks

Using Variation in Time Estimates to Assess Duration Probabilities

What is the probability of finishing in 39 weeks or less?

Exhibit 8.22: Expected Values and Variances of Time Estimates

Page 56: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-56

Using Variation in Time Estimates to Assess Duration Probabilities

• Look up the cumulative probability of the activity being completed before -1.05 standard deviations (Appendix B, near the center)

• There is a 14.686% chance of finishing in 39 weeks or less.

Where:

Z = Number of standard deviations D is from t

t = Expected Time

D = Activity duration I am thinking about

05.16.1

68.4039

Z

D tZ

USE:

Page 57: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-57

Crashing Projects

• A methodical approach to reducing project duration– Focus on the time of activities on the critical path– Looking for greatest improvement with least cost

• Additional labor, machinery• Overtime and temporary employees• Premiums paid to outside contractors for early delivery

• Steps– Create network– Identify critical path– Identify costs of reducing each activity on path– Reduce most cost effective activity– Look for critical path changes

• Beware of multiple critical paths

– Crash next activity

Page 58: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-58

Crashing Projects: Create the Network

Exhibit 8.24: Network to Crash

Page 59: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-59

A8

B7

D10

E12

C7

F8

G9

H5

Crashing Projects: Identify the Critical Path

C.P. = 35 days

Page 60: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-60

Crashing Projects:Identify Costs of Crashing Each Activity

Exhibit 8.25: Crash Time and Costs

Page 61: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-61

A8

B7

D10

E12

C7

F8

G9

H5

Crashing Projects:Reduce Most Cost Effective Activity

6

X

Critical path starts out at 35 days

Page 62: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-62

A8

B7

D10

E12

C7

F8

G9

H5

Crashing Projects:Look for Critical Path Changes

6

X

Critical path now= 35 days

Page 63: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-63

A8

B7

D10

E12

C7

F8

G9

H5

Crashing Projects:Look for Critical Path Changes

6

X

There are now 2 critical paths, so reducing the project length will require shortening each

Page 64: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-64

Crashing Projects:Crash Next Activity

Both C.P. Path 1 Only Path 2 Only

Exhibit 8.25: Crash Time and Costs

Page 65: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-65

Crashing Projects: Summary

Solution Exhibit 8.26: Crashing Summary

Page 66: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 8 Timeliness: Scheduling and Project Management

8-66

Caveats

• Time estimates are frequently wrong• Early finishes are absorbed• Cushions get wasted• Resources aren’t always available when needed