the naes way - rmel
TRANSCRIPT
The NAES Way
2
Plains End Generating Station
3
Plains End Overview cont…
• Plains End, LLC (Commercial May 2002)20 Wartsila 18VG 34SG, Lean Burn, Reciprocating Engines, 5.65 MW/Engine; 54.2 MMBtu/hr natural gas fuel input
• Plains End II, LLC (Commercial May 2008)14 Wartsila 20VG 34SG, Lean Burn, Reciprocating Engines, 8.25 MW/Engine; 73.6 MMBtu/hr natural gas fuel input
• Common Pipeline Natural Gas• Peaking plant• Plains End II, LLC is a black start facility
4
Plains End Overview cont…
• Plains End, LLC• Siemens Catalytic Emission Control System
• Oxidation Catalyst first• SCR Catalyst second (40% urea injection)• Separate chambers
• Plains End II, LLC• Hug Catalytic Emission Control System
• SCR Catalyst first (40% urea injection)• ROM Catalyst (ammonia slip) second• Oxidation Catalyst last• Combined chamber
5
• 2010 Title V Air Permit (combined for both facilities)• Basis of permit primarily “manufacturer guaranties”• Major source of priority pollutants; minor source of HAP’s
• No CEMS or PEMS at either facility• NOx monitors installed solely as primary devices for
controlling urea injection.• Six (6) hour compliance tests for all priority pollutants
required every 3-5 years for each engine• Semi-annual 21-minute compliance tests required semi-
annually for NOx and CO for all engines (other than those undergoing full compliance tests)
• No NPDES or Stormwater Permits required; conditionally exempt small quantity generator of hazardous wastes
Plains End Overview cont…
6
7
8
9
10
11
12
13
• Based on our experience, Plains End has several “lessons learned” we’d like to share
• This presentation will focus on many of these in the areas of:• Construction development;• Operations and maintenance considerations;• Safety and security; and• Environmental compliance.
Introduction
14
Lessons Learned: Construction Development
• Consider major maintenance (costs, manufacturer support, logistics) from initial design basis- not down the road.
• Consider if your initial investment takes advantage of all current manufacturer recommendations; avoid surprises and/or costly retrofits
• Consider if you will be able to operate and maintain the plant that you’re handed following construction, with full accessibility (e.g. catalyst maintenance); flexibility (e.g., fall protection); adaptability to local conditions (wind, rain/snow, temperatures, e.g., cooling water/glycol system)
• Consider options to manage parasitic load (e.g., solar)• Consider your location/operation and adjacent areas (now
and in 10 years); neighbors, schools, etc. How will you be viewed/accepted? Are you glad you avoided things like ammonia and chlorine?
15
Lessons Learned: Operations/Maintenance Considerations
• Consider your ability to capture meaningful history/trends, and to manage run hour versus time-based maintenance. How prepared is the plant to forecast and schedule major maintenance.
• Consider your manning. What if you are challenged with reductions? Do you have data to support your recommendations that support both safety/risks and potential/hidden costs? Have you reached out to experts to prepare?
• Consider your current systems (e.g., DCS)-are you prepared for obsolescence?
16
Lessons Learned: Safety/Security
• Plains End is a VPP Star Site. It is a mature safety management system that mandates team work, sets the tone for operations, and puts safety at the forefront where it belongs.
• Consider plant and cyber security. As an example for cyber security, consider necessity for remote access to DCS and potential security risks; consider robustness of all firewalls; and consider any and all links between business and control networks and how security is maintained. Do not rely solely on “read-only” capability as a means of maintaining security!!
17
Lessons Learned: Environmental Compliance
• Pay attention to language in environmental permits (Plains End only has a Title V Air Permit)
• Pay attention to “manufacturer’s guaranties” or realistic operating parameters relative to environmental limits, when developing initial permits
• Be proactive in managing wastes! Try to eliminate hazardous wastes with equivalent substitutions; aim toward waste minimization.
18
Questions????????
19
NAES Corporation1180 NW Maple StreetSuite 200Issaquah, WA 98027
425.961.4700
www.naes.com