The Priority Environmental Investment Programme for South Eastern Europe – PEIP National Workshop Developing Environmental Infrastructure Projects in the WASTE Sector in Serbia The Regional Solid Waste Management Scheme Duboko (Uzice/Cacak) Mr Cok van Schooten, Team Leader MISP - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: The Priority Environmental Investment Programme for South Eastern Europe – PEIP National Workshop](https://reader036.vdocuments.net/reader036/viewer/2022062519/5681500a550346895dbde4b4/html5/thumbnails/1.jpg)
The Priority Environmental Investment Programme for South Eastern Europe – PEIP National Workshop
Developing Environmental Infrastructure Projects in the WASTE Sector in Serbia
The Regional Solid Waste Management Scheme Duboko (Uzice/Cacak)
Mr Cok van Schooten, Team Leader MISPMay 9, 2008, Belgrade
![Page 2: The Priority Environmental Investment Programme for South Eastern Europe – PEIP National Workshop](https://reader036.vdocuments.net/reader036/viewer/2022062519/5681500a550346895dbde4b4/html5/thumbnails/2.jpg)
Part 1. MUNICIPAL INFRASTRUCTURE SUPPORT PROGRAM (MISP)
Part 2. DUBOKO REGIONAL SOLID WASTE MANAGEMENT SCHEME
![Page 3: The Priority Environmental Investment Programme for South Eastern Europe – PEIP National Workshop](https://reader036.vdocuments.net/reader036/viewer/2022062519/5681500a550346895dbde4b4/html5/thumbnails/3.jpg)
PART 1MUNICIPAL INFRASTRUCTURE SUPPORT PROGRAM (MISP)
MAJOR GOAL :
Assistance to Serbian municipalities in preparing infrastructure projectsfor financing (NIP, EU/IPA, EBRD, KFW, ...) and construction.
![Page 4: The Priority Environmental Investment Programme for South Eastern Europe – PEIP National Workshop](https://reader036.vdocuments.net/reader036/viewer/2022062519/5681500a550346895dbde4b4/html5/thumbnails/4.jpg)
Serbian communities will benefit by having better quality of services in:
- Environmental Infrastructure
- Social Infrastructure
- Economic Infrastructure
![Page 5: The Priority Environmental Investment Programme for South Eastern Europe – PEIP National Workshop](https://reader036.vdocuments.net/reader036/viewer/2022062519/5681500a550346895dbde4b4/html5/thumbnails/5.jpg)
OBJECTIVES
Strengthening the capacity of municipalities in preparation and implementation of infrastructure projects.
Enabling municipalities and public utility companies to access financial funds for infrastructure projects.
![Page 6: The Priority Environmental Investment Programme for South Eastern Europe – PEIP National Workshop](https://reader036.vdocuments.net/reader036/viewer/2022062519/5681500a550346895dbde4b4/html5/thumbnails/6.jpg)
THREE COMPONENTS(2/3)
1. Policy dialogue and PUC transformation Working groups (SCTM, Serbian Ministries) prepare policy recommendations (‘Green Paper’). Review of inter-municipal co-operation models.
2. Programming and Project Preparation MISP supports the Serbian Government on the preparation of infrastructure projects for funding (NIP, IPA, ..) through the SCTM’s SLAP pipeline of projects. MISP will execute Feasibility studies and recommend on Design and Tender Documents.
>> WE ARE LOOKING FOR YOUR PROJECTS !
![Page 7: The Priority Environmental Investment Programme for South Eastern Europe – PEIP National Workshop](https://reader036.vdocuments.net/reader036/viewer/2022062519/5681500a550346895dbde4b4/html5/thumbnails/7.jpg)
THREE COMPONENTS(3/3)
3. Project implementationTendering and supervision in the regional solid waste management projects in Uzice (Duboko) and Pirot, and monitoring of projects in Subotica (waste water treatment), Indjija (water supply) and the M25 Regional Road rehabilitation.
Plus: MISP provides training for the municipalities and PUCs in multi annual planning and FIDIC contracting.
![Page 8: The Priority Environmental Investment Programme for South Eastern Europe – PEIP National Workshop](https://reader036.vdocuments.net/reader036/viewer/2022062519/5681500a550346895dbde4b4/html5/thumbnails/8.jpg)
EU/EAR funded program (history 2003-2007: 46 M€ invested incl. 18 M€ EAR grants)
Current project partners:
National Investment PlanEnvironmental Protection Fund Water DirectorateDirectorate of Roads
![Page 9: The Priority Environmental Investment Programme for South Eastern Europe – PEIP National Workshop](https://reader036.vdocuments.net/reader036/viewer/2022062519/5681500a550346895dbde4b4/html5/thumbnails/9.jpg)
Plus the municipal line up:SuboticaIndjijaUzicePirotKrusevacLeskovacSremska MitrovicaVrbasSabacProkuplje
![Page 10: The Priority Environmental Investment Programme for South Eastern Europe – PEIP National Workshop](https://reader036.vdocuments.net/reader036/viewer/2022062519/5681500a550346895dbde4b4/html5/thumbnails/10.jpg)
Time span :
28 January 2008 – 27 January 2010
MISP: Technical Assistance 3,0 M€ Consortium managed by Eptisa, Spain. 15 experts in Belgrade/10 short term experts
![Page 11: The Priority Environmental Investment Programme for South Eastern Europe – PEIP National Workshop](https://reader036.vdocuments.net/reader036/viewer/2022062519/5681500a550346895dbde4b4/html5/thumbnails/11.jpg)
WHICH FIELDS OF MUNICIPAL INFRASTRUCTURE ?
![Page 12: The Priority Environmental Investment Programme for South Eastern Europe – PEIP National Workshop](https://reader036.vdocuments.net/reader036/viewer/2022062519/5681500a550346895dbde4b4/html5/thumbnails/12.jpg)
ENVIRONMENT Water supply, wastewater, solid waste management and district heating
SOCIAL Sheltered housing, facilities for the disabled and education facilities
ECONOMY Tourist sites, urban renewal and industrial parks.
![Page 13: The Priority Environmental Investment Programme for South Eastern Europe – PEIP National Workshop](https://reader036.vdocuments.net/reader036/viewer/2022062519/5681500a550346895dbde4b4/html5/thumbnails/13.jpg)
Part 2.
DUBOKO REGIONAL SOLID WASTE MANAGEMENT SCHEME
An excellent project example………
![Page 14: The Priority Environmental Investment Programme for South Eastern Europe – PEIP National Workshop](https://reader036.vdocuments.net/reader036/viewer/2022062519/5681500a550346895dbde4b4/html5/thumbnails/14.jpg)
REGIONAL SOLID WASTE MANAGEMENT SCHEME DUBOKO
![Page 15: The Priority Environmental Investment Programme for South Eastern Europe – PEIP National Workshop](https://reader036.vdocuments.net/reader036/viewer/2022062519/5681500a550346895dbde4b4/html5/thumbnails/15.jpg)
![Page 16: The Priority Environmental Investment Programme for South Eastern Europe – PEIP National Workshop](https://reader036.vdocuments.net/reader036/viewer/2022062519/5681500a550346895dbde4b4/html5/thumbnails/16.jpg)
![Page 17: The Priority Environmental Investment Programme for South Eastern Europe – PEIP National Workshop](https://reader036.vdocuments.net/reader036/viewer/2022062519/5681500a550346895dbde4b4/html5/thumbnails/17.jpg)
Including the closure of existing dumpsites.
![Page 18: The Priority Environmental Investment Programme for South Eastern Europe – PEIP National Workshop](https://reader036.vdocuments.net/reader036/viewer/2022062519/5681500a550346895dbde4b4/html5/thumbnails/18.jpg)
(1) Present landfills
(Semi) illegal dumpsites Some sites have lawsuits pending No alternative Uncontrolled Problems with: leachate, fires, smell Strong need for “Duboko” regional landfill No closure plans / after care present
![Page 19: The Priority Environmental Investment Programme for South Eastern Europe – PEIP National Workshop](https://reader036.vdocuments.net/reader036/viewer/2022062519/5681500a550346895dbde4b4/html5/thumbnails/19.jpg)
(2) Transfer stations
Foreseen in every municipality (ex Uzice)
Not all sites selected yet
![Page 20: The Priority Environmental Investment Programme for South Eastern Europe – PEIP National Workshop](https://reader036.vdocuments.net/reader036/viewer/2022062519/5681500a550346895dbde4b4/html5/thumbnails/20.jpg)
(3) Waste separation lines
Uzice (Duboko site)Cacak (existing)
![Page 21: The Priority Environmental Investment Programme for South Eastern Europe – PEIP National Workshop](https://reader036.vdocuments.net/reader036/viewer/2022062519/5681500a550346895dbde4b4/html5/thumbnails/21.jpg)
Proposed set up
A Weighbridge
A ramp towards an unloading platform
A drum screen with an integrated plastic bags opener. The waste is separated in a fine and coarse fraction
Two sorting lines consisting of a conveyor belt with handpicking
A magnetic separator
![Page 22: The Priority Environmental Investment Programme for South Eastern Europe – PEIP National Workshop](https://reader036.vdocuments.net/reader036/viewer/2022062519/5681500a550346895dbde4b4/html5/thumbnails/22.jpg)
Planned recycle rates >>
PET bottles separated on colour
Paper/carton and (when technical possible) plastic fraction shall be compacted
The recycle line requires a plot of at least 2 ha
For internal transport purposes 2 shovels are required.
![Page 23: The Priority Environmental Investment Programme for South Eastern Europe – PEIP National Workshop](https://reader036.vdocuments.net/reader036/viewer/2022062519/5681500a550346895dbde4b4/html5/thumbnails/23.jpg)
Duboko sanitary landfill
Compliance with EU DirectiveBottom liner and top linerDe-gassing (venting) foreseenLandfill gas utilization foreseen in future
![Page 24: The Priority Environmental Investment Programme for South Eastern Europe – PEIP National Workshop](https://reader036.vdocuments.net/reader036/viewer/2022062519/5681500a550346895dbde4b4/html5/thumbnails/24.jpg)
Financing
Estimated investment costs 12,6 M€
Municipalities 2,5 M€Environmental Protection Fund 1,5 M€NIP 0,6 M€Grant by EAR 3,0 M€Loan by EBRD 5,0 M€
![Page 25: The Priority Environmental Investment Programme for South Eastern Europe – PEIP National Workshop](https://reader036.vdocuments.net/reader036/viewer/2022062519/5681500a550346895dbde4b4/html5/thumbnails/25.jpg)
Time lines for construction
Waste separation line Duboko: 2008Land fill body: 2008/2009Transfer stations: 2009
![Page 26: The Priority Environmental Investment Programme for South Eastern Europe – PEIP National Workshop](https://reader036.vdocuments.net/reader036/viewer/2022062519/5681500a550346895dbde4b4/html5/thumbnails/26.jpg)
Additional activities :
- Setting up the PUC including the PIU - Setting the Regional Solid Waste Management Policy- Maintaining the waste separation and waste collection policies- Master Plan for the Closure of the land fills.
![Page 27: The Priority Environmental Investment Programme for South Eastern Europe – PEIP National Workshop](https://reader036.vdocuments.net/reader036/viewer/2022062519/5681500a550346895dbde4b4/html5/thumbnails/27.jpg)
![Page 28: The Priority Environmental Investment Programme for South Eastern Europe – PEIP National Workshop](https://reader036.vdocuments.net/reader036/viewer/2022062519/5681500a550346895dbde4b4/html5/thumbnails/28.jpg)
![Page 29: The Priority Environmental Investment Programme for South Eastern Europe – PEIP National Workshop](https://reader036.vdocuments.net/reader036/viewer/2022062519/5681500a550346895dbde4b4/html5/thumbnails/29.jpg)
Contact:
Cok van Schooten, Team Leader MISPDeli Radivoja 15 11000 Belgrade+381-64-392 [email protected] www.misp-serbia.rs
![Page 30: The Priority Environmental Investment Programme for South Eastern Europe – PEIP National Workshop](https://reader036.vdocuments.net/reader036/viewer/2022062519/5681500a550346895dbde4b4/html5/thumbnails/30.jpg)
Contact:
Cok van Schooten, Team Leader MISPDeli Radivola 15 11000 Belgrade+381-64-392 [email protected]