the tunnelling for the “metro do porto” by alex wilson & frances coker singhateh
TRANSCRIPT
The tunnelling for the The tunnelling for the “Metro do Porto“Metro do Porto””
By Alex Wilson & Frances Coker By Alex Wilson & Frances Coker SinghatehSinghateh
Where is Porto?Where is Porto?
North-west coast of Portugal, North-west coast of Portugal, on the mouth of the river on the mouth of the river
DouroDouro
The The metro metro lineslines
Metro FormatMetro Format Comprises 70km of light railway, of which roughly 6.1km Comprises 70km of light railway, of which roughly 6.1km
is in bored tunnel.is in bored tunnel. 12 stations are located underground and were excavated 12 stations are located underground and were excavated
for using the NATM tunnelling system.for using the NATM tunnelling system. Original Budget was 750 million Euros (55million euros Original Budget was 750 million Euros (55million euros
allocated to tunnelling)allocated to tunnelling) Tunnelling started in June 2000 and finished 42 months Tunnelling started in June 2000 and finished 42 months
later.later.
Tunnel – standard underground line
Surface –urban areas with crossroads and traffic lights
Surface – segregated channel with level crossings
PMO GUIFÕES
Airport
Pedras Rubras
Póvoa do Varzim
Trofa
Hosp. São João
Campanhã
Sr. Matosinhos
ISMAI
Fonte de Cuco
Sra. da Hora
Trindade
Casa da Música
Sto Ovideo
Estádio do
Dragão
Major constraint was in the CBDMajor constraint was in the CBD
Porto is Porto is built on built on a a relatively relatively high high gradient gradient river river valleyvalley..
Porto’s GeologyPorto’s Geology Porto is built on a highly variable granite Porto is built on a highly variable granite
Batholith.Batholith. Medium grained 2 mica (igneous rock) granite, Medium grained 2 mica (igneous rock) granite,
which has undergone deep weathering due to which has undergone deep weathering due to the help of tectonic movements, such that the help of tectonic movements, such that decomposed granite are felt next to fresh granite decomposed granite are felt next to fresh granite at various depths and locations.at various depths and locations.
Tunnels pass through ~ 6 grades of weathering Tunnels pass through ~ 6 grades of weathering (W1-W6) and alteration ranging from fresh (W1-W6) and alteration ranging from fresh granite to cohisionless granular soil.granite to cohisionless granular soil.
High water levels , man made ‘minas’ and deep High water levels , man made ‘minas’ and deep wells increased the challenge ahead.wells increased the challenge ahead.
MAN MADE WATER MINESMAN MADE WATER MINES
A typical distribution of weathered granite taken found at the
face of the EPB driven Tunnel.
The different degrees of weathering of the granite taken from a borehole. The
weathered granite on the left side is at a depth of 24m under the sound granite of
the right.
TunnelingTunneling 3 tunnels were to be 3 tunnels were to be
excavated by a TBM excavated by a TBM EPBM boring at up to three EPBM boring at up to three bar pressure .bar pressure .
They were lined with pre-They were lined with pre-cast concrete segments of cast concrete segments of 7-9 m internal diameter7-9 m internal diameter
The machine had a The machine had a nominal face opening of nominal face opening of 20% to allow excavated 20% to allow excavated material to flow through the material to flow through the machine face.machine face.
A continuous conveyor belt A continuous conveyor belt was used to remove the was used to remove the soil before trucks took it soil before trucks took it away.away.
COLLAPSE OF TUNNELCOLLAPSE OF TUNNEL
No sooner had the boring started work on the No sooner had the boring started work on the tunnel, it was stopped as two houses collapsed tunnel, it was stopped as two houses collapsed resulting in the death of one.resulting in the death of one.
This was the third and largest collapse till the This was the third and largest collapse till the surface and it left a 250m³of hole. surface and it left a 250m³of hole.
This happened due to the over excavation and This happened due to the over excavation and face collapse in the extremely heterogeneous face collapse in the extremely heterogeneous geology. geology.
THE COLLAPSE HOUSESTHE COLLAPSE HOUSES
First ActionFirst Action
A commission of inquiries was set up by A commission of inquiries was set up by the government.the government.
16 recommendations were concluded as a 16 recommendations were concluded as a specification guide. specification guide.
The Engineer, Construction manager and The Engineer, Construction manager and the contractor were forced re-think their the contractor were forced re-think their roles.roles.
First Action (cont.d)First Action (cont.d) It concluded that the accident could have It concluded that the accident could have
been avoided. been avoided. Reinforcing team with trained geotechnical Reinforcing team with trained geotechnical
engineers.engineers. Advance knowledge of area to be drilled Advance knowledge of area to be drilled
before the boring is used.before the boring is used. Investigation of the ground structure Investigation of the ground structure
resulted in an additional machine, in resulted in an additional machine, in preparation for advance tunnelling. preparation for advance tunnelling.
SolutionsSolutions Panel of experts after reviewing came up Panel of experts after reviewing came up
with two proposals about the EPBMswith two proposals about the EPBMs
- The use of an automatic bentonite - The use of an automatic bentonite injection system.injection system.
- An additional double piston pump. - An additional double piston pump.
Herrenknecht EPB TBM and Pressure Mechanism
CONTRACTOR’S MODIFICATIONCONTRACTOR’S MODIFICATION
10 independent foam generators.10 independent foam generators. New rotary fluid joint.New rotary fluid joint. New twin belt weighing system.New twin belt weighing system. An early alert system in place when an An early alert system in place when an
operator reaches any critical level.operator reaches any critical level.
CONCLUSIONCONCLUSION
Despite the safety precautions in place the Despite the safety precautions in place the use of TBM was recommended. use of TBM was recommended.
Daily meetings held with management Daily meetings held with management team to share information and any team to share information and any problem that may arise.problem that may arise.
Could have tried other tunneling methodsCould have tried other tunneling methods
(i.e.Cut-and-cover method, Drill and blast, Immersed (i.e.Cut-and-cover method, Drill and blast, Immersed tube method, Lunardi Method, Slurry-shield machine, tube method, Lunardi Method, Slurry-shield machine, Wall-cover construction method )Wall-cover construction method )
ReferencesReferences http://http://www.rocscience.comwww.rocscience.com/ hoek/references/H2004e.pdf/ hoek/references/H2004e.pdf
http://http://users.ntua.gr/marinusers.ntua.gr/marin os/downloads/conference_inaveiro.pdfos/downloads/conference_inaveiro.pdf
http://http://www.rocscience.comwww.rocscience.com/ hoek/references/H2005c.pdf/ hoek/references/H2005c.pdf
http://www.iom3.org/materi alsworld/feature-pdfs/jul06/Porto%20pressure.pdfhttp://www.iom3.org/materi alsworld/feature-pdfs/jul06/Porto%20pressure.pdf
http://www.ita-aites.org/chttp://www.ita-aites.org/c ms/ ms/fileadmin/filemounts/gefileadmin/filemounts/ge neral/pdf/ItaAssociation/ProductAndPublication/Trainneral/pdf/ItaAssociation/ProductAndPublication/Train ing/Seminars/2006-lisbon/Cunha_abstract.pdfing/Seminars/2006-lisbon/Cunha_abstract.pdf
http://http://www.efrtc.org/htdocwww.efrtc.org/htdoc s/newsite/events/Genmeet_2 s/newsite/events/Genmeet_2 005_Marques.ppt#685,28,II005_Marques.ppt#685,28,II. Engineering . Engineering