the use of future first planning, the triad, and performance … · 2009. 5. 23. · fuel hydrant...

30
The Use of Future First Planning, the Triad, and Performance-Based Contracting to Accelerate Site Closure at Seymour Johnson AFB

Upload: others

Post on 16-Feb-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

  • The Use of Future First Planning, the Triad, and Performance-Based Contracting to Accelerate

    Site Closure at Seymour Johnson AFB

  • Contract Overview

    NOV 2011Landfill No. 3

    NOV 2011Landfill No. 2

    DEC 2010Landfill No. 1

    DEC 2010Landfill No. 4

    DEC 2010Old Entomology Shop

    DEC 2010Fire Training Area No. 2

    NOV 2011Fire Training Area No. 1

    NOV 2011Fire Training Area No. 3

    NOV 2011BX Service Station

    DEC 2010KC-135 Ramp

    DEC 2010

    DEC 2010

    DEC 2010

    DEC 2010

    Bulk Fuel Storage Area (BFSA)

    MAY 2010Radar Tower Site

    MAY 2010F-15 Ramp

    CURRENT STATUSSITE CLOSURE

    DEADLINESITE NAME

    SITE CLOSURE MAY 2006

    REMEDIAL ACTION OPERATIONS

    SITE CLOSURE MAY 2006

    SITE CLOSURE NOV 2008

    SITE CLOSURE FEB 2007

    SITE CLOSURE JULY 2007SITE CLOSURE OCT 2006

    SITE CLOSURE NOV 2008SITE CLOSURE NOV 2007SITE CLOSURE NOV 2007SITE CLOSURE NOV 2007

    SITE CLOSURE NOV 2007

    REMEDIAL ACTION OPERATIONS

    REMEDIAL ACTION OPERATIONS

    REMEDIAL ACTION OPERATIONS

    REMEDIAL ACTION OPERATIONS

  • Regulatory Framework

    Regulatory oversight performed through Regulatory oversight performed through three NCDENR regulatory programs:three NCDENR regulatory programs:

    Underground Storage Tank (UST) Program: SS-04, SS-12, ST-14 and BFSA (ST-01, SD-02, SD-03, ST-05)

    Inactive Hazardous Sites Branch (IHSB) Program:FT-07, FT-19, FT-20, OT-21, OT-29

    RCRA Program (Landfill) Sites:LF-06, LF-08, LF-15, LF-16

  • Site Closure Strategy

    Site Closure Strategy Based on a Marriage of:Site Closure Strategy Based on a Marriage of:Future First Planning

    Triad

    Innovative Technologies

    Remedial Process Optimization

    Decision-Based Partnering

  • Future First Planning

    Future First Planning (F2P):Future First Planning (F2P):A process that fuses Base development planning with environmental cleanup to optimize land use.

    Represents a shift in policywhere environmental restoration sites are viewed as potential assets instead of liabilities.

  • The Triad

    Uncertainty Management through the Triad:Uncertainty Management through the Triad:Systematic Project Planning

    Dynamic Work Strategies

    Real Time Measurement Technologies

  • SJAFB Triad ElementsSystematic Project Planning:Systematic Project Planning:

    Developed preliminary Conceptual Site Model (CSM) using data from past investigations

    Evaluated real time analytics and feasibility of use based on anticipated in-field decisions

    Incorporated potential remediation approaches into data collection techniques

    Cost savings realized through reduced mobilizations

  • SJAFB Triad Elements (cont.)

    Dynamic Work Strategies:Dynamic Work Strategies:Decision Trees allowed in field decision-making, preventing equipment down-time and reducing fixed-lab costs

    Flexible work plan allowed changes to occur when the CSM changedIteratively updating the CSM and continuously adapting the investigative strategy helped to reduce uncertainty and allow for full characterization of the site

  • SJAFB Triad Elements (cont.)

    Real Time Measurement Technologies:Real Time Measurement Technologies:Real time data used to update the CSM throughout the investigation for continuous use to direct additional data collection

    Electronic data (CPT data, stratigraphic logs, LIF data) produced/transmitted daily and posted to Bay West’s web site for access/review by Client

    Real Time Measurement allowed the Team and stakeholders to make informed, quantitative site decisions while in the field

  • OT-29Former Radar Tower Site

    Original SystemBiosparge/biovent wells and groundwater extraction trench2018 projected cleanup

    Pending Mission Critical fuel hydrant systemMixed plume of petroleum hydrocarbons and chlorinated hydrocarbonsOriginal system installed as Interim Remedial Action1998 construction completed and system started

    Overview

    Proposed Hydrant Proposed Hydrant System ConstructionSystem Construction

    ΟΤ−29

  • OT-29Cleanup Strategy

    Site characterization utilizing the TriadRemoval of residual LNAPL using surfactant flush and recoveryExcavation of contaminated soilsGroundwater treatment through chemical oxidation events

    OT-29 Site Boundary

    OT-29 Site Boundary

  • OT-29Dynamic Work Strategies

    Delineation Decision Tree

  • OT-29Characterization Actions Performed

    Membrane Interface Probe Characterization

    55 points analyzedMIP enabled determination of source area and extents

    Rapid AnalysisSoil and groundwater samples used to correlate data with MIP PID headspace analysis performed on potentially contaminated soil

    June 2005 Benzene Plume35,000 ft2

  • OT-29Surfactant Injection

    Field Activities:Field Activities:Installed temporary injection points within targeted LNAPL area based on Triad resultsInjected 10,000 gal of 1.6% non-ionic surfactant (1,250 gal/well)Used MMPE to recover surfactant and >700 gal of petroleum productWork completed in 2 weeks

  • OT-29“Hot Spot” Excavation

    TCE Source Removal adjacent to Radar Tower

    Source removal of 2,000 tonsof impacted soilExcavation extents based onTriad delineation results – soilremoved from 2 areas

  • OT-29Biopile Construction

    Actions Completed:Actions Completed:Constructed biopile to treat petroleum/VOC-impacted soil on-site

    Biopile actively vented and moisture content managed

    Highly-impacted soil amended with approx 1,000 gal hydrogen peroxide (12 wt %) and tilled

    Beneficial reuse of cover material for local landfill following treatment

    35581934Arom. C9-C22

    71271--Aliph. C19-C36

    9104843,260Aliph. C9-C18

    2865972Aliph. C5-C8

    0.0331.95Xylenes

    0.0025.140.24Ethylbenzene

    ND0.57.3Toluene

    ND0.0030.006Benzene

    Oct. 2005

    (mg/kg)

    Jan. 2005

    (mg/kg)

    NCDENR Unrestricted

    (mg/kg)

  • ISCO #1 LocationsNov 2005

    ISCO #2 LocationsJan 2006

    OT-29In Situ Chemical Oxidation

    Actions Completed:Actions Completed:ISCO Bench Scale Tests (modified Fenton’s)3 ISCO events w/287 injection points and approx 75,000 gal oxidizer/catalyst over 50,000 ft2 area

    ISCO #3 LocationsApr 2006

    0

    100

    200

    300

    400

    500

    600

    MW-14 MW-15 MW-17cis

    -DC

    E C

    once

    ntra

    tion

    (ug/

    L)

    Apr. 05:cis-DCE Pre-ISCO #1Dec. 05:cis-DCE Post-ISCO #1Feb. 06:cis-DCE Post-ISCO #2May. 06:cis-DCE Post-ISCO #3

  • OT-29Current Status

    Site remediation activities completed with no impact to the mission-critical fuel hydrant system construction

    Awaiting NCDENR concurrence on No Further Active Remediation Status

    Cleanup timeframe reduced from 20+ years to 4 yearsProjected Savings to Government in excess of $1.5M

  • Bulk Fuel Storage Area (BFSA)Setting:Setting:

    400,000-gal jet fuel (JP-4) release (>50,000 gal in subsurface requiring cleanup)

    Estimated 29,000 ft2LNAPL plume

    Estimated 395,000 ft2dissolved plume

    Legacy treatment system installed in 1998

  • BFSA Cleanup Strategy

    Optimize legacy treatment system to maximize performance prior to design and installation of updated recovery system

    Perform Triad-based characterization to expedite plume definition

    Design, install, and operate enhanced recovery system

  • BFSATriad LIF/CPT ROST Investigation

    Rapid Optical Screening Tool (ROST) used forsimultaneous collection of LIF and CPT data

    Data collection provided integrated 3Dinvestigation and mapping of LNAPL andsmear-zone vadose soils

    9-day field effort with collection of 98 boringswith minimal disturbance to AF mission

    Decision Tree utilized to direct field activities

  • BFSAReal Time Data Collection

  • BFSAData Rendering

    CPT & LIF Data

    ROST Data

  • BFSAUpdating the Conceptual Site Model

    Estimated Pre-Triad LNAPL

    Estimated Post-Triad LNAPL

    Estimated Pre-Triad LNAPL

  • BFSATreatment System Expansion

    Installation of 65 MPE wells in target areas identified during the Triad investigation

    Horizontal drilling and installation of systempiping (~3,000 linear ft) to minimize impact tohigh-traffic, mission critical site area

    Installation/Integration of 650-cfm extractionskid to increase recovery volume as estimatedfrom the 3D site models

  • BFSA System Enhancement

    Basic Process Diagram for MPE System

    ROST Point, used to locate contamination and evaluate

    soil characteristicsExtraction well point installed

    based on ROST data

    Bottom of smear zone based on

    ROST data

    Static WT

    Post-MPE WT

  • BFSAExtraction Well and Manifold Pipe

    Isolation/Bypass Valve

    Well Field Operation Valve

    Air Velocity Site Tube

  • 8"METAL

    15"RCP

    8"METAL

    STORAGEBUILDING

    STORAGEBUILDING

    STORAGESHELTER

    STORAGEBUILDING

    OIL-WATERSEPARATOR

    OIL-WATERSEPARATOR

    EYE WASHSTATION

    FUELSTORAGE

    TANK

    FUELSTORAGE

    TANK

    FUELSTORAGE

    TANK

    FUELSTORAGE

    TANKFUEL

    STORAGETANK

    STORAGEBUILDING

    MW-26

    EW 14-17

    EW 14-04

    MW-1414S

    MW-1401

    MW-21

    MW-25

    MW-96-09

    30MW-28

    MW-23

    MW-24

    MW-1409

    MW-27

    MW-1408

    MW-1407

    MW-1405

    MW-96-11

    MW-96-10

    MW-1404

    MW-1403

    MW-1402

    MW-1413

    EW14-08

    MW-1418S

    EW14-13

    EW14-11

    MW-1416S MW-1411

    MW-22

    EW 14-01

    FUEL TANKPAD

    RECOVERYTANK PAD

    CONTAMINATEDWATER TANK

    PAD

    GENERATORPADTRANSFORMERPAD

    MW-1415S

    MW-1417S

    INV.79.6

    INV.82.8

    NON ACCESSIBLEINVERT

    INV.75.5

    INV.79.3

    INV.81.8

    INV.83.6

    INV.84.5

    INV.83.2FULL OFDIRT

    INV.84.9

    INV.84.6

    INV.83.9

    INV.82.3

    INV.82.7INV.83.2

    INV.84.3INV.84.8

    INV.IN 80.9INV.80.7

    INV.IN 81.4INV.80.8

    INV.84.2

    INV.83.8

    INV.88.1

    INV.86.6 INV.85.9

    INV.85.4

    INV.84.5

    INV.90.2

    INV.89.3

    INV.89.5

    INV.87.6

    INV.87.1

    INV.IN 83.6INV.IN 85.4INV.82.7

    INV.83.2

    INV.80.2

    INV.IN 80.1

    INV 86.4

    CO

    MBI

    NE

    D F

    ACTO

    R =

    0.9

    9987

    48

    ABANDONEDWELL

    IRSN584011.859800E2307098.856490ELEV.= 92.27

    IRSN583911.368710E2307290.049400ELEV.= 97.64

    EX.NAILN583590.970310E2307225.070870ELEV.= 95.59

    IRSN583467.981580E2306838.595080ELEV.= 83.59

    IRSN583470.171040E2307464.662900ELEV.= 96.31

    IRSN583400.533889E2307057.177740ELEV.= 85.92

    IRSN583295.751364E2307084.574720ELEV.= 86.22

    IRSN583016.472718E2307082.094370ELEV.= 84.75

    NA

    D 8

    3

    GR

    ID N

    OR

    TH

    MW 96-12

    EW 96-13

    RW 14-02

    RW 14-01

    RW 14-03

    RW 14-04

    RW 14-05

    RW 14-09RW 14-07

    MW 96-14

    EW 14-14

    EW 14-12

    EW 14-10

    EW 14-09

    RW 14-10

    RW 14-11

    RW 1412EW 14-19

    EW 14-18

    EW 14-16

    EW 14-02

    EW 14-03

    EW 14-05

    EW 14-06

    EW 14-07

    MW 96-15

    EW 14-15

    60 120

    APPROXIMATE SCALE (FEET)

    ZONE 1

    ZONE 2

    ZONE 3

    ZONE 4

    ZONE 5

    ZONE 5

    BFSATreatment Zone Configuration

    MPE Trailer

    Zone Zone 55

    Zone Zone 44

    Zone Zone 33

    Zone Zone 22

    Zone Zone 11

    Trailer Manifold Piping

  • BFSA Current Status

    MPE targeting of Triad-defined LNAPL removed approx 50,000 gal of LNAPL in 12-month period

    Cleanup timeframe estimated to be reduced from 10+ years to 3.5 years

  • Summary

    TRIAD reduced:Number of mobilizations & fixed-base lab costsField and reporting effortsTime to design and implement remedial action enhancements

    Provided data to revise CSM reflecting:More accurate LNAPL distribution (vertical and horizontal)Soil impacts below regulatory criteriaRole of stratigraphy in contaminant transport/recovery

    Resulted in a design targeting source and “hot-spot” areas, reducing cleanup time