the worlds leading sustainability consultancy boiler gact update georgia awma conference october...
TRANSCRIPT
The world’s leading sustainability consultancy
Boiler GACT UpdateGeorgia AWMA Conference
October 2013
The world’s leading sustainability consultancy
Agenda - NESHAP Anatomy
Applicability and Affected Sources
Subcategories
and
Emission Limits
Compliance OptionsCompliance Assurance
Requirements
Schedule and Definitions
Boiler MACT and
GACT Structure
Very Similar -
More/Different
Requirements
for Major Sources
The world’s leading sustainability consultancy
The “Final” Combustion Source Rules
40 CFR 63 Subpart DDDDD – Major Source Boiler MACT
40 CFR 63 Subpart JJJJJJ – Area Source Boiler GACT
40 CFR 60 Commercial and Industrial Solid Waste Incineration (CISWI) Rule
40 CFR 241 Non-Hazardous Secondary Materials (NHSM) Solid Waste Identification Rule
To gather data, assess applicability, determine emission limits, review compliance status/options, and implement compliance strategy
Promulgated again by US EPA on January 31 and February 1, 2013
Includes four (4) Interrelated Rules
Detailed Site-specific Action Plan Needed
The world’s leading sustainability consultancy
The Solution is a Process Issue…
Point of Compliance
Fuel Spec
Supply
Longevity
Cost
Fan Modification
Combustion Mod
Operating Flexibility
Retrofit
Addition
Permitting
Compliance Testing
Cost
Each part of the process may be part of the answer!
The world’s leading sustainability consultancy
Boiler Area Source GACT Rule (Boiler GACT)
GACT = Generally Available Control Technology
Applicability - Applies to boilers that:
■ Burn a “fuel” material, not a “waste” as defined by US EPA (“Fuel” = coal, oil, gas, biomass, tire-derived fuel, others)
■ Located at an industrial, institutional, commercial facility that is an “area source” (any source not major) of Hazardous Air Pollutants (HAP)*
■ Does not include process heaters
*Note: A facility is an Area Source of HAP emissions if it emits less than 10 TPY of any single regulated HAP, and less than 25 TPY of any combination of HAP’s
The world’s leading sustainability consultancy
Boiler GACT Applicability
Applies to HAP Area Sources
“Natural Gas” Boilers are Exempt
Existing Sources (Commenced Construction Prior to 6/4/10)
Emission Limits Set Only for Coal Boilers Fuel Oil and Biomass Units Only Subject to Work Practice
Standards Fuel Switching After 6/4/10 May No Longer Trigger New Source
Status
Initial Compliance Date 3/21/14 for existing sources
The world’s leading sustainability consultancy
Natural Gas Curtailment
Period of gas curtailment or supply interruption means a period of time during which the supply of gaseous fuel to an effected boiler is restricted or halted for reasons beyond the control of the facility.
The act of entering into a contractual agreement with a supplier of natural gas established for curtailment purposes does not constitute a reason that is under the control of a facility for the purposes of this definition.
An increase in the cost or unit price of natural gas due to normal market fluctuations not during periods of supplier delivery restriction does not constitute a period of natural gas curtailment or supply interruption.
On-site gaseous fuel system emergencies or equipment failures qualify as periods of supply interruption when the emergency of failure is beyond the control of the facility.
The world’s leading sustainability consultancy
Fuel Switching Improvement
63.11194(e) - An existing dual-fuel fired boiler meeting the definition
of gas-fired boiler, as defined in § 6.11237, that meets the
applicability requirements of this subpart after June 4, 2010 due to a
fuel switch from gaseous fuel to solid fossil fuel, biomass, or liquid fuel
is considered to be an existing source under this subpart as long as the
boiler was designed to accommodate the alternate fuel.
The world’s leading sustainability consultancy
Significant Improvements/Changes
■ Many Emissions Limits are Now Higher
■ Initial Tune-Up Deadline Delayed to 3/21/14
■ Tune-Ups Conducted Using Primary Fuel Over the Prior 12 Months
■ Natural Gas Curtailment Now Includes On-Site Fuel System Failures
■ Temporary, Seasonal and Limited Use Boiler Relaxation
■ CO Emission Limit and Potential CEMS for Oil Sources Removed
■ New Oil Sources Burning < 0.5 % Sulfur Are Exempt from PM Limit
■ Start-Up & Shutdown Definitions Changed and 25% “Bright Line” Removed
■ Potential Hg Fuel Analysis Relaxation
The world’s leading sustainability consultancy
Initial and Continuous Compliance
Initial Notification(s)
Work Practice Standards (Tune-Ups,
Energy Assessment,
etc.)
Periodic Performance
Tests
Notification of Compliance
Status Report(s)
Monitoring of Operating Parameters for Control Devices
Stack O2 Monitor for CO Limits
Stack Testing or Fuel
Analysis for Hg
The world’s leading sustainability consultancy
Boiler GACT Compliance
Existing Source Initial Compliance Deadline 3/21/14
Initial Tune-Up and One Time Energy Assessment
Stack Testing for Applicable Boilers Due by 9/17/14
Notification of Compliance Status Report(s) (7/19/14 and/or 11/17/14)
Ongoing Compliance Assurance – Testing, Monitoring, Recordkeeping and Reporting
SSM Requirements ???
The world’s leading sustainability consultancy
Existing Coal Boilers
Subject to Mercury (Hg) and CO Emission Limits
Hg Compliance Based as Fuel Analysis or Stack Testing
CO Compliance Typically Based Only on Stack Testing
Stack Testing Includes: Both Initial and Ongoing Testing Test Plan Approval by GA EPD Monitoring and Establishing Hg, CO and Capacity Operating Limits Developing/ Implementing a Site Specific Monitoring Plan Conduct Initial and Periodic Continuous Parameter Monitoring
System Performance Evaluations – May Need a RATA!? Need to Run at Maximum Capacity – 110% Operating Limit Report Results Via New US EPA WebFire Database
The world’s leading sustainability consultancy
One-time Energy Assessment (EA) Required for All Existing Affected Boilers > 10 MM Btu
Except Limited Use
Higher Fuel Efficiency means Reduced Air Pollutants Emitted to the Atmosphere
EA to Identify and Evaluate Cost Effective Energy Conservation Measures – Not a Regulatory “Deliverable”
EA will cover the Boilers and the Energy Use System within the Sources’ property (compressed air, machine drive, process cooling, hot water, HVAC, building envelope)
Requires an evaluation of the facilities “energy management practices” and required EA Duration is dependent on total heat input capacity
EA to follow prescribed procedures and assessor qualifications relaxed, and existing assessments can now be amended as needed to comply.
The world’s leading sustainability consultancy
Permitting Considerations■ Will Generic Placeholder Conditions Suffice?
Trade-off of Generic vs. Specific Conditions Approach
■ Typical Issues With Agencies: Approval of Alternative Operating Limits Approval of Multiple Compliance Options Testing of Worst Case Fuel for Each Pollutant Title V Versus GACT Inconsistencies Verify if Site Specific Monitoring Plan Needs to be Submitted Need for Multiple NOCSR Submittals Does Annual Compliance Report Need Submittal
The world’s leading sustainability consultancy
Permitting Considerations (continued)
■ What Permit Applications are Needed and When? < 10/25 TPY HAP Emission Limits New/Modified Emission Control Device Construction, Operation,
and/or Operating Limits New Boiler(s) and/or Fuel Switching Compliance Option Definition
■ Need to Ensure Compliance Plan is Enforceable! Solid Fuel Variability is a Challenge/Risk for Both Area Source
Status and Boiler GACT Compliance
■ Request to See a “Pre-Public” Draft Amendment
■ Other Potential Implications– NSR, NAAQS, NSPS, GHG, etc.
The world’s leading sustainability consultancy
Case Study ExampleMajor HAP Source With One Large Coal Boiler, Four Natural Gas Boilers and Very Low Process HAP’s
■ Looking at Area Source HAP Status Via Limiting Boiler HCl Emissions■ Lime Injection Into Baghouse or Add-On Wet Scrubber
■ Potential Fuel Switching From Coal
■ Addition of Fuel Oil to Manage Natural Gas “Risk”
■ Conducting Stack Testing and Fuel Analysis■ Completing “What If” Emission Testing
■ Setup Ongoing Hg Fuel Analysis
■ Evaluating Hg and/or CO Compliance Options■ Fuel Vendor Contract Limits and Operating Restriction/Controls
■ Trade off of CO Management Versus NOx Permit Limits
■ Development of Long Term Compliance Strategy and Schedule■ Operating Costs, Impacts and Uncertainties
■ Build Results Into Site Budgeting Cycle
■ Ongoing GA EPD discussions/negotiations
The world’s leading sustainability consultancy
Boiler MACT Planning Timeline Based on January, 2016 Initial Compliance Date
Now 3/2014 9/2014 1/2015 3/2015 9/2015 1/2016
Data Gathering and Initial Planning
Boiler Stack Testing
Completed
Engineering Evaluation and Fuel Supplier
Review
Technology/ Vendor
Selection and Design
Permitting and Regulatory
Negotiations
Fabrication, Construction, Check Out and
Training
Ongoing NESHAP
Compliance Activities
The world’s leading sustainability consultancy
What’s Next for You?
Assess if you have boilers/process heaters potentially subject to CISWI versus MACT/GACT
Identifyapplicable emission limits and if you can comply with these limits
Gather needed fuel analysis and/or stack test data (develop/implement test plan)
Evaluatethe need for additional emissions controls, perform economic analyses and plan for future budget cycles
Determine if need additional monitoring systems
Consider operational, process and/or fuel changes to reduce the regulatory burden
Develop an overall compliance strategy and schedule
Plan for tune-ups and facility-wide energy assessment
The world’s leading sustainability consultancy
Questions?
The world’s leading sustainability consultancy
Contact Information
ERM 3200 Windy Hill Road SE
Suite 1500WAtlanta, GA 30339
678.486.2700
David Dunn [email protected]