thermal design project final report john wallerich principal engineer wallerich group, llc

35
Thermal Design Project Final Report John Wallerich Principal Engineer Wallerich Group, LLC

Upload: evelyn-mathews

Post on 04-Jan-2016

213 views

Category:

Documents


0 download

TRANSCRIPT

Thermal Design ProjectFinal Report

John WallerichPrincipal EngineerWallerich Group, LLC

Agenda 1. Introduction2. Executive Summary 3. Project Summary4. Recommendations5. CFD models

22009 - Wallerich Group, LLC

1. Introduction

3

statistical analysis

actual experiences in building and testing

data centers

CFD modeling

[customer]

Wallerich Group, LLC

Datacenter design standards

Most efficient cooling design

Develop and Provide

Project tasks

2009 - Wallerich Group, LLC

3. Project Summary• Computer Room layout• Rack Optimization• Horizontal cabling distribution• Airflow design• Rack Power Distribution• CRAC design• Raised Floor design• Diffusers (perforated floor tiles)

4

Electro-mechanical infrastructure

UPS

Generator

PDU

Rack power distribution systems

Chilled water generation

Chilled water distribution system

Network infrastructure

Infrastructure management

Building structural design

In-Scope

Out-of-Scope

2009 - Wallerich Group, LLC

Design Components Analysis results

5

Design Components ReccomendationA1 Airflow Design ROWA2 Cooling Architecture Primary CoolingA3 Primary Cooling Architecture Chilled WaterA4 Supplemental Cooling Design N/A (Outside Air)A5 CRAC Grouping No GroupingB1 Cold Air Supply Under FloorB2 Raised Floor Height 900mm / 36inchB3 Perforated Tile type FixedB4 Perforated Tile opening >50% OpenB5 Rack Configuration Ho Aisle & Cold AisleB6 Rack Air Control Blank Panels & Side PanelsB7 Perforated Tile location Determined by CFD modelB8 Return Air Design PlenumB9 Plenum Design Hot Ailse EnclosureB10 Rack Door (Ft & Bk) High Flow Rack DoorsB11 CRAC Position OppsiongB12 CRAC Location Outside RMFB13 CRAC Design Off ther Shelf / CustomB14 Tile Size 600mm sqB15 Network Cable Location OverheadB16 Power cable location Under FloorB17 Rack Width 600mmB18 Rack Depth 1.2mB19 Rack Height 2mB20 Rack-Ceiling Distance >460mm

The letter/number designations and solution consensus came from the initial analysis session documents and are maintained for the sake of document continuity. These design decisions were agreed to by consensus and are incorporated into the CFD modeling analysis.

2009 - Wallerich Group, LLC

A1:Airflow Design Diagram Option Pros and Cons

Room Merit:Assure N+1 configuration. Room level cooling was adequate for mainframe environments,

Demerit:but is not cost effective to cool high density equipment cost effectively.Very inefficient and will not deliver sufficient cooling for high density environments.

Row

Merit:Assure N+1 configuration. Optimize capital investment and available space. Reduce maintenance time and facilitate maintenance work. Quantify the cooling system performance. Maximize the operational efficiency by matching capacity to load.Maximizes efficiency of cooling system infrastructure 

Rack

Merit:Assure N+1 configuration.

Merit:Rack level cooling devices are much more expensive than Row type cooling, and lower revenue potential. N+1 configuration reduces # of productive racks.  

62009 - Wallerich Group, LLC

A2:Cooling Architecture Diagram Option Pros and Cons

Primary cooling

Merit:Centralized chilled water system ensures maximum efficiency and redundancy that supports Tier 3.

Demerit:Must support entire critical load with full redundancy (chiller, plumbing, CRAC)

Primary Cooling&Supplemental Cooling

Merit:Supplemental cooling is designed to provide options for datacenters who have exhausted their primary cooling capacity.

Demerit:Full critical load must be supported with supplemental option disabled, or supplemental cooling design must also support critical load without use of primary cooling system..Supplemental cooling is designed to provide options for datacenters who have exhausted their primary cooling capacity and voids Tier 3 capability. It is more costly and may reduce cabinet count.

7

Primary cooling system

Primary cooling system

Supplemental cooling system

2009 - Wallerich Group, LLC

A3:Primary cooling Architecture

Diagram Option Pros and Cons

Air Conditioner

Demerit:This design does not provide N+1 redundancy.Instead of assessing heat rise characteristicsthere are other issues regarding using AC units that need to be decided first.One of those assumption is that racks will never exceed 2.5KW over the life of facility (.10 to 12 years).Initial investment is less than chilled water system, but may not support Tier 3 for the life of the facility (2.5kW may increase)

Chilled Water/AHU

Merit:Supports Tier 3 requirements for all computing models.Provides high availability option when using excess chilled water storage and achieves required cooling capacity for all rooms.Provides most cost effective solution while supporting Tier 3 specification. Allows for use of outside cold air to reduce energy consumption.

8

Chiller

CRAC

Cooling Medium

Cooling Tower

CRAC

Chilled Water

2009 - Wallerich Group, LLC

A4:Supplemental cooling Diagram Option Pros and Cons

XD

Merit:XD is used when primary cooling system is exhausted and provides cold air to a very small area

Demerit:XD is a Liebert solution that does not support Tier 3 availability.More costly to operate and provides cold air to a very small area. Cannot provide total cooling and is used when primary cooling system is exhausted.

Water to Rack

Merit:Cools hot air as it exits equipment

Demerit:Tier 3 capability assumes redundant chilled water system. May be required for very high density, but at higher risk and costs.. Makes accessing equipment more difficult, and is typically vendor specific.

Rack Cooling

Merit:Cools hot air as it exits rack.

Demerit:Rack cooling devices must support entire room if primary CRAC failed, however they can not support this requirement. Rack cooling replaces a revenue generating rack and replaces it with a device that only cools racks on either side. Not cost effective.

Outside Air

Merit:No risk to Tier 3.Can have a significant impact on energy consumption during cold days. Options are being evaluated.

9

Rack

RackRack

RackRack

Water

Chilled Water

Cooling Tower

Rack Rack Rack Rack

inside Room

outside

2009 - Wallerich Group, LLC

A5:CRAC Grouping

Diagram Option Pros and Cons

No Grouping

Merit:Assure “Concurrently Maintainable” and “Redundancy N+1”configuration. Reduce maintenance time and facilitate maintenance work

Grouping

Merit:Assure “Concurrently Maintainable” and “Redundancy N+1”configuration.

Demerit:Recommended when using single chilled water supply (not recommended)

10

Group A

Group B

Group C

2009 - Wallerich Group, LLC

B1:Cold Air Supply

Diagram Option Pros and Cons

Under Floor

Merit:Supports Tier 3 model.Optimize cooling capacity by supplying cold air efficiently. Allows flexibility of air delivery and cable plenum.

Overhead

Merit: Supports Tier 3 model

Demerit:Less flexible to change. More cost to install.Use when building height is limited.

Side Feed

Merit: Supports Tier 3 model

Demerit:Interrupts controlled airflow. Used only as supplemental cooling when unable to used under-floor plenum

Combination

Merit: Supports Tier 3 model

Demerit:No advantage, and would be used when primary cooling design is inadequate.

11

CRAC rack

CRAC rack

2009 - Wallerich Group, LLC

B2:Raised Floor HeightDiagram Option Pros and Cons

600mm /24inch Demerit:Volume of air required for high density and uneven pressure distribution inhibits high efficiency cooling model. With underfloor power cabling, obstacles have more impact on airflow and cooling delivery.

750mm /30inch

Demerit:Typical Raised Floor Height is 30-36inch which is most directly correlated to power density. May need custom design to control air pressure distribution and avoid hot spots.

900mm /36inch

Merit:Typical Raised Floor Height is 30-36inch which is most directly correlated to power density. Provides more even pressure distribution and higher volume.

12

Rack

Rack

Rack

600mm

750mm

900mm

2009 - Wallerich Group, LLC

B3:Perforated Tile type Diagram Option Pros and Cons

Center cut

Demerit:Only for specific rack (ex: Verari)

Fixed

Merit:Reduce maintenance timePrevent human error

Variable Damper

Demerot:Increase possibility of human error that could damage equipment and increases costs (each tile costs more)

132009 - Wallerich Group, LLC

B4:Perforated Tile opening

Diagram Option Pros and Cons

20-50% open

Merit:Perforated tile openings will be determined by CFD modeling. Range likely to be 40-50% open.

>50% Open

Merit:Perforated tile openings will be determined by CFD modeling

<20% open

Merit:Perforated tile openings will be determined by CFD modeling

142009 - Wallerich Group, LLC

B5:Rack Configuration

Diagram Option Pros and Cons

Random

Very poor control of hot air, increased likelihood of overheating equipment and higher energy costs

Hot Aisle / Cold Aisle

Maximize efficiency of cooling system through isolation of cold and hot air.

152009 - Wallerich Group, LLC

B6:Rack Air Control Diagram Option Pros and Cons

Blank Panels

Merit:Maximize CRAC cooling capability. Required to isolate hot air and cold air.

Side Panels

Merit:Maximize CRAC cooling capability and required for cabinet level security

16

X

X

Rack side

Blank Panels

Rack side

Side Panels

2009 - Wallerich Group, LLC

B7:Perforated Tile location

Diagram Option Pros and Cons

Cold Aisle

Merit:Required for efficient delivery of cold air to equipment.

Under rack

Demerit:Only required by specific rack manufacturer.

Other

Demerit:May be required for room air supply if cold aisle enclosure selected

17

Rack RackRack

Rack RackRack

Rack RackRack

2009 - Wallerich Group, LLC

B8:Return Air Design Diagram Option Pros and Cons

Open

Merit:Unclosing return air flow is used when floor height is low to obtain plenum area.

Demerit:Hot and cold air are allowed to mix lowering the thermal load that room can support and increases costs of operation.

Plenum

Merit:Maximize CRAC cooling capability and increase thermal load that room can support.

18

CRAC rack rack rack

CRAC rack rack rack

2009 - Wallerich Group, LLC

B9:Plenum Design Diagram Option Pros and Cons

Cold Aisle

Merit:Improves cooling efficiency and load that can be supported.

Demerit:No as efficient as hot aisle enclosure.

Hot Aisle

Merit:Recommended by Intel. Internal tests show as being most efficient and effective airflow design.

No enclosure

Demerit:Not Recommended

Hot and Cold Aisle(20KW Only)

Demerit:Not recommended: blocks access to network infrastructure, adds costs with no real benefit.

19

Rack

Rack

Rack

Rack

Enclosure

ラッ

ラッ

Rack

Rack

Enclosure

Rack

Rack

ラッ

Rack

Rack

ラッ

クR

ack

Rack

Rack

Rack

Enclosure

Rack

Rack

2009 - Wallerich Group, LLC

B10:Rack Doors (Front & Back)

Diagram Option Pros and Cons

No Door

Merit:Maximize cooling efficiency.

Demerit:no server access control. May be OK for some racks.

<50%

Demerit:There is no necessity to recommend.

50-70% open

Demerit:There is no necessity to recommend.

80% open

Merit:Accelerate cooling efficiency with server access controlPrevent human error

20

Rack

Rack

Rack

Rack

2009 - Wallerich Group, LLC

B11:CRAC Position Diagram Option Pros and Cons

Opposing

Merit:Maximize CRAC cooling efficiency for typical rectangular room

Multi-Wall

Demerit:Can be used, but only if total capacity requires it.

Mid-Floor

Demerit:Not recommended as it introduces water to the RMF area, exposing equipment to possible water contamination

21

CRAC

CRAC

CRAC

2009 - Wallerich Group, LLC

B12:CRAC Location Diagram Option Pros and Cons

Inside RMFDemerit:Not recommended due to noise and security requirements.

Outside RMF

Merit:Reduce maintenance time and facilitate maintenance work with server access controlPrevent human error

OverheadDemerit:Not recommended due to building height limitations.

22

CRAC

CRAC

Rack

CRAC

Rack

Rack

2009 - Wallerich Group, LLC

B13:CRAC Design

Diagram Option Pros and Cons

Off the ShelfMerit:to be determined by CFD tool and available CRAC designs in Japan.

CustomMerit:May be required due to high air volume. Likely to be more expensive.

232009 - Wallerich Group, LLC

B14:Tile Size Diagram Option Pros and Cons

600mm sq

Merit::Widely distributed in Japan and Easy to purchase

700mm sq

Demerit:Odd Size, no value.

800mm sq

Demerit:Odd size, no value.

24

600mm

700mm

800mm

2009 - Wallerich Group, LLC

B15:Network Cable Location

Diagram Option Pros and Cons

Overhead

Merit:Reduce maintenance time and facilitate maintenance work.Maximize CRAC cooling efficiency by avoiding under-floor air blockage

Under Floor

Demerit:Twisted-pair cable (network cable)become obstacle for efficient airflow

25

Rack

Rack

2009 - Wallerich Group, LLC

B16:Power cable location Diagram Option Pros and Cons

Overhead

Merit:Separated distance from network cable must be 50-300mm

Under Floor

Merit:Reduce maintenance time and facilitate maintenance work to keep distance from network cable as 50-300mm *3

Thin bus power cable affect a little to airflow

26

Rack

Rack

2009 - Wallerich Group, LLC

B17:Rack Width

Diagram Option Pros and Cons

600mm / 24”

Merit:Utilizing cable mgmt system, revenue target requires maximum rack count. Increase number of racks per room.

700mm / 30”

Demerit:No clear advantage, and reduces overall rack count. Can be used with 600mm if needed. Reduce number of racks per roomthan 600mm

800mm / 36”

Demerit:No clear advantage, and reduces overall rack count. Can be used with 600mm if needed. Reduce number of racks per roomthan 600mm

 

27

600mm

700mm

Rack

800mm

Rack

Rack

2009 - Wallerich Group, LLC

B18:Rack Depth

Diagram Option Pros and Cons

1mMerit:Should be less than twice tile size for maintenance access

1.2m

Merit:Should be less than twice of tile size for maintenance efficiency

> 1.2m

Demerit:Not recommended – rack will overlap tile edge making access impossible.

28

Rack

1m

Rack

1.2m

Rack

2m

2009 - Wallerich Group, LLC

B19:Rack Height

Diagram Option Pros and Cons

1.8m

Merit:Lower rack can reduce number of servers per rack

2m

Merit:Typical rack size, creates no op issues. Will support up to 42 1U servers

2.2m

Merit:Higher rack can increase number of servers per rack  

Demerit:Will limit space available for overhead network cabling

29

Rack 1.8m

Rack2m

Rack

2.2m

2009 - Wallerich Group, LLC

B20:Rack-Ceiling Distance

Diagram Option Pros and Cons

<460mm

Demerit:A minimum clearance between ceiling to rack shall be 460mm

>460mm

Merit:A minimum clearance between ceiling to rack shall be 460mm*4

30

Rack

Rack

<460mm

>460mm

2009 - Wallerich Group, LLC

Design Elements Diagram (1/4)

31

CRAC CRAC

Air Flow=ROW

CRAC Grouping=No Grouping

Supplemental Cooling Design

Primary Cooling Architecture=Chilled Water

Cold Air Supply=Under Floor

Raised Material Floor(RMT)

Dropped Ceiling

Raised Floor Height=900mm

(36inch)

Rack

Cooling Architecture=Primary Cooling

2009 - Wallerich Group, LLC

Design Elements Diagram (2/4)

32

CRAC CRAC

Rack

Perforated Tile

Perforated Tile type=Fixed

Perforated Tile opening= >50%open

Rack Configuration= Hot Aisle & Cold Aisle

Rack Air Control=

Blank Panels & Side Panels

Return Air Design= Plenum

Plenum Design= Hot Aisle

Tile Size= 600mm

Perforated Tile location= Cold Aisle

2009 - Wallerich Group, LLC

Design Elements Diagram (3/4)

33

RackRack

CRAC

CRAC

CRAC Position= Opposing

CRAC Location= Outside RMF

Dry Wall

CRAC Design= Off the Shelf/Custom

2009 - Wallerich Group, LLC

Design Elements Diagram (4/4)

34

Rack

Building DesginBuilding Design

Raised Floor Height = 900mm(36inch)

Rack Height = 2m

Rack-Ceiling Distance= >460mm

Rack

Rack Width = 600mm

Rack Depth = 1.2m

Network Cable Location=Overhead

Power Cable Location=Under Floor

2009 - Wallerich Group, LLC

352009 - Wallerich Group, LLC