Thomas Anthony, P.E.Industry Intelligence
ManagerOncor Electric Delivery Co.
USA
Thomas DamonAssistant VP–Smart Grid
Science Applications International Corporation
USA
![Page 2: Thomas Anthony, P.E. Industry Intelligence...Failure Detection and Predictive Analytics System • Tom Anthony • Industry intelligence manager with a U.S.-based electric utility](https://reader034.vdocuments.net/reader034/viewer/2022051322/602e275c4f1fd2784d2e87fb/html5/thumbnails/2.jpg)
Failure Detection and Predictive Analytics System
• Tom Anthony
• Industry intelligence manager with a U.S.-based electric utility
• Currently deploying 3.1 million smart meters
• Tom Damon
• System developer who uses power system engineering expertise to assist utilities in optimizing business processes by leveraging their technology investments
![Page 3: Thomas Anthony, P.E. Industry Intelligence...Failure Detection and Predictive Analytics System • Tom Anthony • Industry intelligence manager with a U.S.-based electric utility](https://reader034.vdocuments.net/reader034/viewer/2022051322/602e275c4f1fd2784d2e87fb/html5/thumbnails/3.jpg)
Project Background
• U.S. Department of Energy’s Modern Grid Initiative
• Knowledge transfer opportunities
• Leverage existing data sources to improve analytics and predictive capabilities
• Use the cloud to control data processing costs
![Page 4: Thomas Anthony, P.E. Industry Intelligence...Failure Detection and Predictive Analytics System • Tom Anthony • Industry intelligence manager with a U.S.-based electric utility](https://reader034.vdocuments.net/reader034/viewer/2022051322/602e275c4f1fd2784d2e87fb/html5/thumbnails/4.jpg)
Experience on Smart Grid Technology Demonstration and R&D Project
• Located in West Virginia
• Integration of distributed resources and advanced technologies
• Included fault location and prediction• Advanced fault location
• Neural network methodologies to identify pre-fault conditions and anticipate failures
Feeders and zones
![Page 5: Thomas Anthony, P.E. Industry Intelligence...Failure Detection and Predictive Analytics System • Tom Anthony • Industry intelligence manager with a U.S.-based electric utility](https://reader034.vdocuments.net/reader034/viewer/2022051322/602e275c4f1fd2784d2e87fb/html5/thumbnails/5.jpg)
The Utility Found the Effort Promising
• Continue enhancing its smart grid abilities
• Collaborate with a company that could develop needed algorithms and software for the fault detection and prediction system
• Analyze existing data from the utility’s broadband-over-powerline (BPL) system to automatically identify pattern interruptions and threshold breaches that might indicate incipient customer issues within the distribution system
![Page 6: Thomas Anthony, P.E. Industry Intelligence...Failure Detection and Predictive Analytics System • Tom Anthony • Industry intelligence manager with a U.S.-based electric utility](https://reader034.vdocuments.net/reader034/viewer/2022051322/602e275c4f1fd2784d2e87fb/html5/thumbnails/6.jpg)
A Two-Phase Project
1. Develop an initial “proof-of-concept” data analysis application and build a prototype
2. Develop a functioning data analysis tool and install it in the utility’s data center
![Page 7: Thomas Anthony, P.E. Industry Intelligence...Failure Detection and Predictive Analytics System • Tom Anthony • Industry intelligence manager with a U.S.-based electric utility](https://reader034.vdocuments.net/reader034/viewer/2022051322/602e275c4f1fd2784d2e87fb/html5/thumbnails/7.jpg)
Phase 1: Develop Prototype
![Page 8: Thomas Anthony, P.E. Industry Intelligence...Failure Detection and Predictive Analytics System • Tom Anthony • Industry intelligence manager with a U.S.-based electric utility](https://reader034.vdocuments.net/reader034/viewer/2022051322/602e275c4f1fd2784d2e87fb/html5/thumbnails/8.jpg)
Phase 2: Develop and Install Tool
![Page 9: Thomas Anthony, P.E. Industry Intelligence...Failure Detection and Predictive Analytics System • Tom Anthony • Industry intelligence manager with a U.S.-based electric utility](https://reader034.vdocuments.net/reader034/viewer/2022051322/602e275c4f1fd2784d2e87fb/html5/thumbnails/9.jpg)
Data Analysis Tool: Issues Screen
![Page 10: Thomas Anthony, P.E. Industry Intelligence...Failure Detection and Predictive Analytics System • Tom Anthony • Industry intelligence manager with a U.S.-based electric utility](https://reader034.vdocuments.net/reader034/viewer/2022051322/602e275c4f1fd2784d2e87fb/html5/thumbnails/10.jpg)
Data Analysis Tool: Work Request Screen
![Page 11: Thomas Anthony, P.E. Industry Intelligence...Failure Detection and Predictive Analytics System • Tom Anthony • Industry intelligence manager with a U.S.-based electric utility](https://reader034.vdocuments.net/reader034/viewer/2022051322/602e275c4f1fd2784d2e87fb/html5/thumbnails/11.jpg)
Data Analysis Tool: Details Screen
![Page 12: Thomas Anthony, P.E. Industry Intelligence...Failure Detection and Predictive Analytics System • Tom Anthony • Industry intelligence manager with a U.S.-based electric utility](https://reader034.vdocuments.net/reader034/viewer/2022051322/602e275c4f1fd2784d2e87fb/html5/thumbnails/12.jpg)
What the Future Holds
• Both the utility and the tool development company will continue to invest resources to develop the data analysis tool, part of an overall smart grid deployment program
• The utility plans to install the data analysis tool in the second quarter of 2011, after completion of its data center move
• Once the tool is installed and operational, the process of automating the recognition of actual issues on the BPL system will begin
• If the tool proves its value on the BPL system, it should easily be able to be adapted to other future remote data acquisition platforms
![Page 13: Thomas Anthony, P.E. Industry Intelligence...Failure Detection and Predictive Analytics System • Tom Anthony • Industry intelligence manager with a U.S.-based electric utility](https://reader034.vdocuments.net/reader034/viewer/2022051322/602e275c4f1fd2784d2e87fb/html5/thumbnails/13.jpg)
What We Have Learned
• The value of applying analytic algorithms to grid data analysis has been proven
• Predictive analytics is a core ingredient in future system integration programs
• Real-time analysis is necessary for high-value devices