title of session line 1 title of session line 2 · gsm-r. budget = 52.4 m ... adif. bidding and...
TRANSCRIPT
3
High speed projects are usually divided into
Infrastructure
Track (usually without supplies -different bid-)
Substations (including maintenance for two years)
Catenary (including maintenance for two years)
Signaling (including maintenance for two years)
Communications (including maintenance for two years)
Technical and administrative aspects
4
Cartography
3 contracts
Average length: 150 km (93 mi)
Practical Case: High Speed Railway betweenMadrid and Valencia (II)
Technical and administrative aspects
5
Geological Studies
28 contracts
Average length: 14 km (9 mi)
Practical Case : High Speed Railway between Madrid and Valencia (II)
Technical and administrative aspects
6
35 contracts for Basic Projects and Construction Projects
Average length: 11 km (7 mi)
Infrastructure
Practical Case : High Speed Railway between Madrid and Valencia (II)
Technical and administrative aspects
7
5 contracts
Average length: 75 km (46.9 mi)
Track
Practical Case : High Speed Railway between Madrid and Valencia (II)
Technical and administrative aspects
TRACKBudget = 29.6 M€
41.7 M$Construction period = 12 months
TRACKBudget = 34.1 M€
48.0 M$Construction period = 14 months
TRACKBudget = 14.4 M€
20.3 M$Construction period = 8 months
TRACKBudget = 42.9 M€
60.4 M$Construction period = 18 months
TRACKBudget = 29.4 M€
41.4M$ Construction period = 14 months
8
Electrification
Catenary2 contracts
Average length: 160 km (100 miles)
Substations2 contracts
Average length: 160 km (100 miles) CATENARY
Budget = 121.9 M€171.7 M$
Construction period = 14 months
SUBSTATIONSBudget = 112.9 M€
159.0 M$Construction period = 24 months
CATENARYBudget = 74.5 M€
104.9 M$Construction period = 24 months
SUBSTATIONSBudget = 68.6 M€
96.6 M$Construction period = 24 months
Practical Case : High Speed Railway between Madrid and Valencia (II)
Technical and administrative aspects
9
Installations
Signaling and communication
1 contract
380 km (236 miles) length
GSM-R
1 contract
380 km (236 miles) length
SIGNALING AND COMMUNICATIONBudget = 552.3 M€
777.9 M$Construction period = 30 months
GSM-R
Budget = 52.4 M€73.80 M$
Construction period = 30 months
Practical Case : High Speed Railway between Madrid and Valencia (II)
Technical and administrative aspects
10
CONTRACT
ADJUDICATION OR TENDER
RESTRICTED PROCEDURE OPEN TENDERING PROCEDURE
BID SUBMISSION
MINISTRY OF PUBLIC WORKS
ADIF
BIDDING AND DRAFTING OF SPECIFICATIONS
(Technical and Administrative Sheets)
ADVERTISING: OFFICIAL GAZZETTES AND PRESS
AWARD
BID EVALUATION
TENDERING COMPANIES
PRE-CONSTRUCTION REVIEW DOCUMENT
11
Real costs in Spanish HSL opened between 2003 and 2008:
67%
12% 7%
14%
Infrastructure:
Track:
Electrification:
An idea of costs
Unit Cost for large and medium-sized stations
Medium-sized 15-50 M€21.1-70.4 M$
Large 50-200 M€70.4-281.7 M$
Infrastructure: 5.4 – 14.6 M€/km 12.2 – 32.9 M$ per
mile
Track: 1.3 – 1.7 M€/km 2.9 – 3.8 M$ per mile
Electrification: 0.8 – 1.3 M€/km 1.8 – 2.9 M$ per mile
Signaling and telecom: 1.1 – 3.3 M€/km 2.5 – 7.4 M$ per mile
Total Cost: 9.4 – 20.9 M€/km 21.2 – 47.1 M$ per
mile
Technical and administrative aspects
13
Technology
Preventive Process General Chart
Superstructure maintenance related activities
Preventive maintenance planning and performance phases
Inspection and examination. Knowledge of track state
Diagnostic and Actuations Planning
Weekly Works ProgrammingPerformance of programmed activities
Record and Follow-up Certification. Check of efficiency-performance
deviations.Closing
Track state analisys , diagnosis and pre-planning
To this end a Data Inventory, an Specific Track Treatment Plan andseveral Management Systems based on Aplications Software allowingthe recording and treatment of the obtained data has been created
Planning and Management: Time-resources-budget
Work reports fulfillment : Asking for intervals and own and
external resources
14
Technology
VISUAL (ON FOOT WALKS)INSPECTIONS
AND AUTOMATED ONES
TRACK, POINTS ANDCROSSING TESTS
TRACK INSPECTION(GEOMETRIC AND DYNAMIC)
TRAVELLING IN DRIVER’S CAB
DEFECT DETECTIONDIAGNOSIS
DEFECT LOCALIZATIONIN THE FIELD.
INSPECCTION ANDTOPOGRAPHY
CAUSESIDENTIFICATION.
WORKS PROGRAMMING:
-URGENT
-SHORT TERM
-MEDIUM/ LONG TERM
-USING OWN RESOUCES
-USING EXTERNAL RESOURCES
- IMPROVEMENT ACTUATIONSPROPOSAL
ACTIONS STUDY
CORRECTIVE ACTIONSDETERMINATION
URGENCY DEGREE OFACTUATION DETERMINATION
NECESSARY RESOURCESDETERMINATION
AVAILABLE RESOURCES
WORK INTERVALS
Superstructure maintenance related activitiesPlanning, Programming and Performance Basis
15
Technology
Times to be considered:
Efficiency indexes:
Service Quality Indexes:Availability: Total number of hours out of service
Cancelled trains-delayed trains-number of delayed minutes
Reliability: Number of incidents/breakdowns due to own reasons
Geometric Quality Indexes of Track ZUT
Effective conservation time
Waiting time
Agreed maintenance band time
Granted maintenance band time
Band adjustment: Granted band time/Agreed band time
Waiting: Waiting time/granted band time
Real exploitation: Efective construction time/granted band time
Variation indexes:Variation from initial planning (time/economy)
Variation from Weekly Delivery Programme (time)
Activities related with superstructure maintenancePrevention Indicators
16
TechnologyMaintenance structuringActivities related to civil works maintenance
Maintenance agreements €-year/
km of line
$-year/
mile of line
Infrastructure and track maintenance
20,000 45,070
Turnout maintenance 3,771 8,497.9
Specific monitoring in tunnels
215 484.5
Specific monitoring in factory works
486 1,095.2
Specific monitoring in earthworks
489 1,102
Herbicide treatment 667 1,503.1
Technical assistance for maintenance
4.145 9,340.8
Breakdown of track and infrastructure maintenance
costs
Infrastructure and track maintenance 20.000€ (66%)
Technical assistance for maintenance 4.145€(14%)
Treatment with herbicide 667€ (2%)
Specific monitoring of earthworks 489€ (2%)
Turnout maintenance 3.771€ (13%)
Specific monitoring in tunnels 215€ (1%)
Specific monitoring of factory works 486€ (2%)