Project Management Plan for TMTA Integrated Training Management System prepared by Msc IT Student UiTM Shah Alam, Malaysia

TRANSCRIPT

Page 1: TMTA Integrated Training Management System

NIK AINI RASHIDA NIK MAN 2011415354NUR ILYANA NOR AZMAL 2010909069NIK NOOR NADIAH MD IBRAHIM 2011822516

Advanced Information Technology Project

Management

TITLE: TMTA INTEGRATED TRAINING MGMT SYSTEM

SYS750

Page 2: TMTA Integrated Training Management System

i. Introduction• Background• Current situation• Description of the problem or opportunity• Project’s measurable organizational value• How achieving the project’s MOV will support the

organization’s goal and strategy• Objectives of writing the business case

ii. Objectiveiii. Scopeiv. Work Breakdown Structure (WBS)v. Rolesvi. Schedulevii. Budgetviii. Key Issues/Risks/Assumptionsix. Change Control x. Administration

Contents

Page 3: TMTA Integrated Training Management System

INTRODUCTION

Page 4: TMTA Integrated Training Management System

Background

The proposal of developing an ‘TMTA Integrated Training Management System’ for the TM BERHAD.

Page 5: TMTA Integrated Training Management System

TM Technical Academy: Background

i. TM Technical Academy (TMTA) is responsible to conduct training for all employees of Telekom Malaysia Berhad and their contractors. Currently TMTA implement two types of training delivery method called Instructor Led Training (traditional classroom) and e-Learning.TMTA is formerly known as TM Training Centre.

ii. TMTA provide technical training for TM staffs and also the vendors. To enable TMTA achieve the mission and vision to enhance their overall corporate culture by developing and enhancing employee’s skills with the effective training programs. For that, TMTA have to improve the quality of training lab to replace existing training lab as well as to have a good ICT infrastructure.

iii. Currently, the existing management system at TMTA was obsolete where by following the standard of ICT guideline for government agency, any ICT asset with years of usage more than 5 years will be considered as obsolete. Part of it, existing servers and equipment also has limited storage. To assist TMTA in achieving mission and vision of the TMTA Top management, they have to improve the capability of their basic ICT infrastructure as well as having one integrated IT management system covering all training process in TM network environment.

Page 6: TMTA Integrated Training Management System

Existing hardware in the TMTA IT system have insufficient capacity (e.g.: processor and storage capacity) to meet the needs of the current systems and under development.

For the long run, TMTA have to upgrade their ICT infrastructure for better service to Telekom Malaysia Staff and TM contractors.

Current Situation

Existing standalone systems is not capable to fulfill TMTA need in the long run.

Page 7: TMTA Integrated Training Management System

1. Existing standalone system to manage training record, training invitation and TMTA committee not capable to fulfill needs of TMTA training in the long run.

2. Future ICT plan require TMTA to have good ICT infra to fulfill needs from TM Staff and TM Contractors.

Problem / Opportunity

Page 8: TMTA Integrated Training Management System

1. Better ICT support and services from TMTA will help to encourage TMTA Staff to manage the training reporting more efficient.

2. Help Telekom Malaysia to maintain and improve the quality of Training environment and management system.

Project Measurable Organization Value (MOV)

Page 9: TMTA Integrated Training Management System

These values help TMTA to achieve their goal to help TM as an organization to achieve corporate objective and enhance their overall corporate culture by developing and enhancing employee’s skills with the effective management training through the enhancement of the use of Information and communication Technology (ICT).

How achieving the project’s MOV will support the organization’s goal & strategy

Page 10: TMTA Integrated Training Management System

1. To enhance training environment of TMTA by developing Integrated Management system that cover up all training needed and training task compliant with current network which performed as of now.

2. To upgrade the infrastructure of ICT at TMTA. To upgrade the infrastructure of ICT at TMTA.

Objectives

Page 11: TMTA Integrated Training Management System

The system comprises 2 major modules. They are:

1. Integrated Information System: The IT information system is a complete workflow design and management solution to meet all training process modeling needs. Build on an expandable and extensible industry-leading open architecture, it comes complete with graphical mapping utilities to help build TMTA training workflow processes and set up the framework for delivering, processing and tracking training and submission of data between TM staff and TMTA.

2. TMTA Training Reporting: The TMTA Lab Integrated Information System is a comprehensive with Web-based tool system to create, extract, view, manipulate and perform data mining on server in carrying out daily training report. It will be a specialized, custom subsystem specifically designed to tailor to TM Berhad and consultancy backend requirements.

Scope of Work / Deliverables

Page 12: TMTA Integrated Training Management System

Server for Web Server/Application Server - 3 unitsServer for Database Server -2 unitsLoad Balancer Appliances ( AX2000 Series) – 1 Unit

Technical Services:i. Installation, Configuring, Testing and Commissioning of Hardware and System

Softwareii. Database Migration Services

Project Management Documentation - Training :iii. MySQL Administrator Modules iv. MySQL Developer Modules v. Transfer of Technology (Hardware Appreciation)

SAN Switch – 2 UnitsMYSQL Enterprise Gold Edition – 2 UnitsStorage Area Network - 1 Unit42U Rack – 1 UnitKVM Switch - 1 Unit

Infrastructure to Support the System

Scope of Work / Deliverables (cont)

Page 13: TMTA Integrated Training Management System

Role Project Responsibility

System Analyst Analyze existing business process and convert into physical and logical design.

Software Engineer Transform physical design and logical design into code.

Network Engineer Hardware configuration, specification

Testing Engineer Implement Unit Test, User Acceptance Test, Hardware Test

Database Administrator Design database structure

PMO Officer/ QA Team Control and ensure the completeness of report for each implementation

Roles

Organization chart: organization chart.docx

Page 14: TMTA Integrated Training Management System

Schedule

Page 15: TMTA Integrated Training Management System

Schedule (cont.)

Page 16: TMTA Integrated Training Management System

Project Budget SummaryProject Deliverable Percentage (%) Cost (RM)Infrastructure 100 300,000Phase 1Preliminary & kick-off meetingInfrastructure deliverables and installationDevelopment tools & installationGather information of required system

Integrated Information System TMTA Training Reporting

20 / RM 1m 200,000

Phase 2 :Project Development Testing Phase : UAT AND LIVE

30 / RM 1m 300,000

Phase 3 :Implementation Post Implementation AssessmentMaintenance

50 / RM 1m 500,000

Total Cost 1,300,000

Page 17: TMTA Integrated Training Management System

1. The appointed working committee members are attached permanently until the end of the project.

2. The agreed scheduled is strictly followed by both parties.

3. The requirements are clearly defined and endorsed.

4. The change request is properly controlled by Change Management Plan.

5. The availability of the sites for hardware setup and installation.

Key Issues/Risks/Assumptions

Page 18: TMTA Integrated Training Management System

Change Control

Process flow for Change Control Management as below diagram :