topic 6 (2012-13a)mp

Upload: jessica-adharana-kurnia

Post on 03-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/29/2019 Topic 6 (2012-13A)MP

    1/71

    Corporate Financial Policy

    Semester A 2012-13City University of Hong Kong

    AC4331 Topic 6

  • 7/29/2019 Topic 6 (2012-13A)MP

    2/71

    Topic 6

    .

  • 7/29/2019 Topic 6 (2012-13A)MP

    3/71

    1-2

    Introduction to Financial Management

    Free Cash Flow

    Financial Planning and Forecasting

    Financial Assets and Time Value of Money

    Risk and Return Bond and Stock Valuation

    Cost of Capital

    Cash Flow Estimation and Risk Analysis Capital Structure and Leverage

    Treasury and Valuation

    Enterprise Risk Management Dividends and Share Repurchase

    Merger and Acquisitions

    Working Capital Management

  • 7/29/2019 Topic 6 (2012-13A)MP

    4/71

    Extra Ref:Financial Management, Theory and Practice, 12eEugene and

    Brigham

    Topic 6:Cash Flow Estimation

    And Risk Analysis

  • 7/29/2019 Topic 6 (2012-13A)MP

    5/71

    Chapter 12

    Should webuild thisplant?

    12-4

  • 7/29/2019 Topic 6 (2012-13A)MP

    6/71

    Analysis of potential additions to fixedassets.

    Long-term decisions; involve large

    expenditures. Very important to firms future.

    12-5

  • 7/29/2019 Topic 6 (2012-13A)MP

    7/71

    1. Estimate CFs (inflows & outflows).

    2. Assess riskiness of CFs.

    3. Determine the appropriate cost of capital.

    4. Find NPV and/or IRR.5. Accept if NPV > 0 and/or IRR > WACC.

    12-6

  • 7/29/2019 Topic 6 (2012-13A)MP

    8/71

    Independent projects if the cash flows ofone are unaffected by the acceptance of theother.

    Mutually exclusive projects if the cash flowsof one can be adversely impacted by theacceptance of the other.

    12-7

  • 7/29/2019 Topic 6 (2012-13A)MP

    9/71

    Normal cash flow stream Cost (negative CF)followed by a series of positive cash inflows.One change of signs.

    Nonnormal cash flow stream Two or morechanges of signs. Most common: Cost(negative CF), then string of positive CFs,then cost to close project. Nuclear power

    plant, strip mine, etc.

    12-8

  • 7/29/2019 Topic 6 (2012-13A)MP

    10/71

    Sum of the PVs of all cash inflows andoutflows of a project:

    12-9

    N

    0tt

    t

    )r1(CFNPV

  • 7/29/2019 Topic 6 (2012-13A)MP

    11/71

    NPVS = $19.98

    12-10

    Year CFt PV of CFt

    0 -100 -$100

    1 10 9.09

    2 60 49.593 80 60.11NPVL = $ 18.79

  • 7/29/2019 Topic 6 (2012-13A)MP

    12/71

    Enter CFs into the calculators CFLO register. CF0 = -100 CF1 = 10 CF2 = 60 CF3 = 80

    Enter I/YR = 10, press NPV button to getNPVL = $18.78.

    12-11

  • 7/29/2019 Topic 6 (2012-13A)MP

    13/71

    NPV = PV of inflows Cost

    = Net gain in wealth

    If projects are independent, accept if the

    project NPV > 0. If projects are mutually exclusive, accept

    projects with the highest positive NPV, thosethat add the most value.

    In this example, accept S if mutuallyexclusive (NPVS > NPVL), and accept both ifindependent.

    12-12

  • 7/29/2019 Topic 6 (2012-13A)MP

    14/71

    IRR is the discount rate that forces PV ofinflows equal to cost, and the NPV = 0:

    Solving for IRR with a financial calculator: Enter CFs in CFLO register.

    Press IRR; IRRL = 18.13% and IRRS = 23.56%.

    N

    0tt

    t

    IRR)(1CF0

    12-13

  • 7/29/2019 Topic 6 (2012-13A)MP

    15/71

    They are the same thing.

    Think of a bond as a project. The YTM onthe bond would be the IRR of the bond

    project. EXAMPLE: Suppose a 10-year bond with a 9%

    annual coupon and $1,000 par value sells for$1,134.20.

    Solve for IRR = YTM = 7.08%, the annual return forthis project/bond.

    12-14

  • 7/29/2019 Topic 6 (2012-13A)MP

    16/71

    If IRR > WACC, the projects return exceedsits costs and there is some return left over toboost stockholders returns.

    If IRR > WACC, accept project.If IRR < WACC, reject project.

    If projects are independent, accept bothprojects, as both IRR > WACC = 10%.

    If projects are mutually exclusive, accept S,because IRRs > IRRL.

    12-15

  • 7/29/2019 Topic 6 (2012-13A)MP

    17/71

    A graphical representation of project NPVs atvarious different costs of capital.

    12-16

    WACC NPVL NPVS

    0 $50 $40

    5 33 29

    10 19 20

    15 7 1220 (4) 5

  • 7/29/2019 Topic 6 (2012-13A)MP

    18/71

    -10

    0

    10

    20

    30

    40

    50

    60

    5 10 15 20 23.6

    NPV($)

    Discount Rate (%)

    IRRL = 18.1%

    IRRS = 23.6%

    Crossover Point = 8.7%

    SL

    .

    .

    12-17

    .

    ..

    ..

    ... .

  • 7/29/2019 Topic 6 (2012-13A)MP

    19/71

    If projects are independent, the two methodsalways lead to the same accept/rejectdecisions.

    If projects are mutually exclusive If WACC > crossover rate, the methods lead to thesame decision and there is no conflict.

    If WACC < crossover rate, the methods lead todifferent accept/reject decisions.

    12-18

  • 7/29/2019 Topic 6 (2012-13A)MP

    20/71

    Size (scale) differences the smaller projectfrees up funds at t = 0 for investment. Thehigher the opportunity cost, the morevaluable these funds, so a high WACC favorssmall projects.

    Timing differences the project with fasterpayback provides more CF in early years for

    reinvestment. If WACC is high, early CFespecially good, NPVS > NPVL.

    12-19

  • 7/29/2019 Topic 6 (2012-13A)MP

    21/71

    NPV method assumes CFs are reinvested at theWACC.

    IRR method assumes CFs are reinvested at IRR.

    Assuming CFs are reinvested at theopportunity cost of capital is more realistic, soNPV method is the best. NPV method shouldbe used to choose between mutually exclusive

    projects. Perhaps a hybrid of the IRR that assumes cost

    of capital reinvestment is needed.

    12-20

  • 7/29/2019 Topic 6 (2012-13A)MP

    22/71

    Yes, MIRR is the discount rate that causes thePV of a projects terminal value (TV) to equalthe PV of costs. TV is found bycompounding inflows at WACC.

    MIRR assumes cash flows are reinvested atthe WACC.

    12-21

  • 7/29/2019 Topic 6 (2012-13A)MP

    23/71

    12-22

    66.012.1

    10%

    10%

    -100.0

    0 10%

    PV outflows-100.0 $10

    0

    MIRR = 16.5%158.1

    TV inflows

    MIRRL = 16.5%

    $158.1

    (1 + MIRRL)3=

    321

    10.0 60.0 80.0

  • 7/29/2019 Topic 6 (2012-13A)MP

    24/71

    MIRR assumes reinvestment at theopportunity cost = WACC. MIRR also avoidsthe multiple IRR problem.

    Managers like rate of return comparisons,and MIRR is better for this than IRR.

    12-23

  • 7/29/2019 Topic 6 (2012-13A)MP

    25/71

    The number of years required to recover aprojects cost, or How long does it take toget our money back?

    Calculated by adding projects cash inflowsto its cost until the cumulative cash flow forthe project turns positive.

    12-24

  • 7/29/2019 Topic 6 (2012-13A)MP

    26/71

    30 80PaybackL= 2 + /

    = 2.375 years

    PaybackS= 1.600 years

    12-25

    CFt

    Cumulative

    0 1 2 3

    -30

    Project Ls Payback Calculation

    -100 50-90

    80-100 6010

  • 7/29/2019 Topic 6 (2012-13A)MP

    27/71

    Strengths Provides an indication of a projects risk and

    liquidity.

    Easy to calculate and understand.

    Weaknesses Ignores the time value of money.

    Ignores CFs occurring after the payback period.

    12-26

  • 7/29/2019 Topic 6 (2012-13A)MP

    28/71

    Uses discounted cash flows rather than rawCFs.

    12-27

    41.32 60.11Disc PaybackL = 2 + / = 2.7 years

    CFt

    Cumulative

    0 1 2 3

    -41.32-100 18.79-90.91

    80-100 6010

    10%

    PV of CFt -100 9.09 49.59 60.11

  • 7/29/2019 Topic 6 (2012-13A)MP

    29/71

    Enter CFs into calculator CFLO register.

    Enter I/YR = 10. NPV = -$386.78.

    IRR = ERROR Why?

    -800 5,000 -5,000

    0 1 2WACC = 10%

    12-28

    Project P has cash flows (in 000s): CF0 = -$0.8 million, CF1 = $5 million, and CF2 = -$5 million.

  • 7/29/2019 Topic 6 (2012-13A)MP

    30/71

    450

    -800

    0400100

    IRR2 = 400%

    IRR1 = 25%

    WACC

    NPV

    12-29

  • 7/29/2019 Topic 6 (2012-13A)MP

    31/71

    At very low discount rates, the PV of CF2 islarge and negative, so NPV < 0.

    At very high discount rates, the PV of both

    CF1 and CF2 are low, so CF0 dominates andagain NPV < 0.

    In between, the discount rate hits CF2 harderthan CF1, so NPV > 0.

    Result: 2 IRRs.

    12-30

  • 7/29/2019 Topic 6 (2012-13A)MP

    32/71

    When there are nonnormal CFs and morethan one IRR, use MIRR. PV of outflows @ 10% = -$4,932.2314.

    TV of inflows @ 10% = $5,500.

    MIRR = 5.6%.

    Do not accept Project P. NPV = -$386.78 < 0.

    MIRR = 5.6% < WACC = 10%.

    12-31

  • 7/29/2019 Topic 6 (2012-13A)MP

    33/71

    Chapter 13

    Relevant Cash Flows

    Incorporating Inflation

    Types of Risk Risk Analysis

    13-32

  • 7/29/2019 Topic 6 (2012-13A)MP

    34/71

    Total depreciable cost Equipment: $200,000

    Shipping and installation: $40,000

    Changes in working capital Inventories will rise by $25,000

    Accounts payable will rise by $5,000

    Effect on operations

    New sales: 100,000 units/year @ $2/unit Variable cost: 60% of sales

    13-33

  • 7/29/2019 Topic 6 (2012-13A)MP

    35/71

    Life of the project Economic life: 4 years

    Depreciable life: MACRS 3-year class

    Salvage value: $25,000

    Tax rate: 40%

    WACC: 10%

    13-34

  • 7/29/2019 Topic 6 (2012-13A)MP

    36/71

    Estimate relevant cash flows

    Calculating annual operating cash flows.

    Identifying changes in working capital.

    Calculating terminal cash flows: after-tax salvagevalue and return of NWC.

    13-35

    Initial OCF1 OCF2 OCF3 OCF4Costs +

    TerminalCFs

    NCF0 NCF1 NCF2 NCF3 NCF4

    0 1 2 3 4

  • 7/29/2019 Topic 6 (2012-13A)MP

    37/71

    Find NWC. in inventories of $25,000

    Funded partly by an in A/P of $5,000 NWC = $25,000 $5,000 = $20,000

    Combine NWC with initial costs.

    Equipment -$200,000

    Installation -40,000

    NWC -20,000Net CF0 -$260,000

    13-36

  • 7/29/2019 Topic 6 (2012-13A)MP

    38/71

    Year Rate x Basis Deprec.1 0.33 x $240 $ 792 0.45 x 240 1083 0.15 x 240 364 0.07 x 240 17

    1.00 $240

    Due to the MACRS -year convention, a3-year asset is depreciated over 4 years.

    13-37

  • 7/29/2019 Topic 6 (2012-13A)MP

    39/71

    1 2 3 4

    Revenues 200.0 200.0 200.0 200.0

    Op. costs -120.0 -120.0 -120.0 -120.0

    Deprec. expense -79.2 -108.0 -36.0 -16.8

    Operating income (BT) 0.8 -28.0 44.0 63.2

    Tax (40%) 0.3 -11.2 17.6 25.3

    Operating income (AT) 0.5 -16.8 26.4 37.9

    + Deprec. expense 79.2 108.0 36.0 16.8

    Operating CF 79.7 91.2 62.4 54.7

    (Thousands of dollars)

    13-38

  • 7/29/2019 Topic 6 (2012-13A)MP

    40/71

    Q. How is NWC recovered?

    Q. Is there always a tax on SV?Q. Is the tax on SV ever a positive cash flow?

    13-39

    Recovery of NWC $20,000Salvage value 25,000Tax of SV (40%) -10,000

    Terminal CF $35,000

  • 7/29/2019 Topic 6 (2012-13A)MP

    41/71

    No, dividends and interest expense shouldnot be included in the analysis.

    Financing effects have already been taken

    into account by discounting cash flows at theWACC of 10%.

    Deducting interest expense and dividendswould be double counting financing costs.

    13-40

  • 7/29/2019 Topic 6 (2012-13A)MP

    42/71

    No, the building improvement cost is a sunkcost and should not be considered.

    This analysis should only include incremental

    investment.

    13-41

  • 7/29/2019 Topic 6 (2012-13A)MP

    43/71

    Yes, by accepting the project, the firmforegoes a possible annual cash flow of$25,000, which is an opportunity cost to becharged to the project.

    The relevant cash flow is the annual after-taxopportunity cost. A-T opportunity cost:

    = $25,000(1 T)= $25,000(0.6)

    = $15,000

    13-42

  • 7/29/2019 Topic 6 (2012-13A)MP

    44/71

    Yes. The effect on other projects CFs is anexternality.

    Net CF loss per year on other lines would bea cost to this project.

    Externalities can be positive (in the case ofcomplements) or negative (substitutes).

    13-43

  • 7/29/2019 Topic 6 (2012-13A)MP

    45/71

    Enter CFs into calculator CFLO register, andenter I/YR = 10%.

    NPV = -$4.03 million

    IRR = 9.3%

    MIRR = 9.6%

    Payback = 3.3 years

    13-44

    0

    -260

    1 2 3 4

    79.7 91.2 62.4 89.7

  • 7/29/2019 Topic 6 (2012-13A)MP

    46/71

    Yes, the old equipment would be sold, andnew equipment purchased.

    The incremental CFs would be the changes

    from the old to the new situation. The relevant depreciation expense would

    be the change with the new equipment.

    If the old machine was sold, the firm would

    not receive the SV at the end of themachines life. This is the opportunity costfor the replacement project.

    13-45

  • 7/29/2019 Topic 6 (2012-13A)MP

    47/71

    Stand-alone risk

    Corporate risk

    Market risk

    13-46

  • 7/29/2019 Topic 6 (2012-13A)MP

    48/71

    The projects total risk, if it were operatedindependently.

    Usually measured by standard deviation (orcoefficient of variation).

    However, it ignores the firms diversificationamong projects and investors diversificationamong firms.

    13-47

  • 7/29/2019 Topic 6 (2012-13A)MP

    49/71

    The projects risk when considering thefirms other projects, i.e., diversificationwithin the firm.

    Corporate risk is a function of the projectsNPV and standard deviation and itscorrelation with the returns on other firmprojects.

    13-48

  • 7/29/2019 Topic 6 (2012-13A)MP

    50/71

    The projects risk to a well-diversifiedinvestor.

    Theoretically, it is measured by the projectsbeta and it considers both corporate andstockholder diversification.

    13-49

  • 7/29/2019 Topic 6 (2012-13A)MP

    51/71

    Market risk is the most relevant risk forcapital projects, because managementsprimary goal is shareholder wealthmaximization.

    However, since corporate risk affectscreditors, customers, suppliers, andemployees, it should not be completely

    ignored.

    13-50

  • 7/29/2019 Topic 6 (2012-13A)MP

    52/71

    Stand-alone risk is the easiest to measure.Firms often focus on stand-alone risk whenmaking capital budgeting decisions.

    Focusing on stand-alone risk is nottheoretically correct, but it does notnecessarily lead to poor decisions.

    13-51

  • 7/29/2019 Topic 6 (2012-13A)MP

    53/71

    Yes, since most projects the firm undertakesare in its core business, stand-alone risk islikely to be highly correlated with itscorporate risk.

    In addition, corporate risk is likely to behighly correlated with its market risk.

    13-52

  • 7/29/2019 Topic 6 (2012-13A)MP

    54/71

    Sensitivity analysis measures the effect ofchanges in a variable on the projects NPV.

    To perform a sensitivity analysis, all variablesare fixed at their expected values, except forthe variable in question which is allowed tofluctuate.

    Resulting changes in NPV are noted.

    13-53

  • 7/29/2019 Topic 6 (2012-13A)MP

    55/71

    Advantage Identifies variables that may have the greatest

    potential impact on profitability and allowsmanagement to focus on these variables.

    Disadvantages Does not reflect the effects of diversification.

    Does not incorporate any information about thepossible magnitudes of the forecast errors.

    13-54

  • 7/29/2019 Topic 6 (2012-13A)MP

    56/71

    Yes, inflation causes the discount rate to beupwardly revised.

    Therefore, inflation creates a downward biason PV.

    Inflation should be built into CF forecasts.

    13-55

  • 7/29/2019 Topic 6 (2012-13A)MP

    57/71

    13-56

    1 2 3 4Revenues 210 220 232 243

    Op. costs (60%) -126 -132 -139 -146

    Deprec. expense -79 -108 -36 -17

    Oper. income (BT) 5 -20 57 80

    Tax (40%) 2 -8 23 32

    Oper. income (AT) 3 -12 34 48

    + Deprec. expense 79 108 36 17Operating cash flows 82 96 70 65

  • 7/29/2019 Topic 6 (2012-13A)MP

    58/71

    Enter CFs into calculator CFLO register, and

    enter I/YR = 10%. NPV = $15.0 million.

    IRR = 12.6%.

    0 1 2 3 4

    13-57

    Terminal CF =

    -260 82.1 96.1 70.0 65.1

    35.0

    100.1

  • 7/29/2019 Topic 6 (2012-13A)MP

    59/71

    Suppose we are confident of all the variableestimates, except unit sales. The actual unitsales are expected to follow the followingprobability distribution:

    13-58

    Case Probability Unit Sales

    Worst 0.25 75,000

    Base 0.50 100,000

    Best 0.25 125,000

  • 7/29/2019 Topic 6 (2012-13A)MP

    60/71

    All other factors shall remain constant andthe NPV under each scenario can bedetermined.

    13-59

    Case Probability NPV

    Worst 0.25 ($27.8)

    Base 0.50 15.0

    Best 0.25 57.8

  • 7/29/2019 Topic 6 (2012-13A)MP

    61/71

    13-60

    0.15$

    )8.57($25.0)0.15($5.0)8.27$-(25.0E(NPV)

    3.30$

    ])0.15$0.25($57.8

    )0.15$0.5($15.0)0.15$.8[0.25(-$27

    1/22

    22NPV

    2.00$30.3/$15.CVNPV

  • 7/29/2019 Topic 6 (2012-13A)MP

    62/71

    With a CVNPV of 2.0, this project would beclassified as a high-risk project.

    Perhaps, some sort of risk correction isrequired for proper analysis.

    13-61

  • 7/29/2019 Topic 6 (2012-13A)MP

    63/71

    We would expect a positive correlation withthe firms aggregate cash flows.

    As long as correlation is not perfectlypositive (i.e., 1), we would expect it tocontribute to the lowering of the firmsoverall risk.

    13-62

  • 7/29/2019 Topic 6 (2012-13A)MP

    64/71

    The projects corporate risk would not bedirectly affected. However, when combinedwith the projects high stand-alone risk,correlation with the economy would suggest

    that market risk (beta) is high.

    13-63

  • 7/29/2019 Topic 6 (2012-13A)MP

    65/71

    Reevaluating this project at a 13% cost ofcapital (due to high stand-alone risk), theNPV of the project is -$2.2.

    If, however, it were a low-risk project, wewould use a 7% cost of capital and theproject NPV is $34.1.

    13-64

  • 7/29/2019 Topic 6 (2012-13A)MP

    66/71

    Numerical analysis sometimes fails tocapture all sources of risk for a project.

    If the project has the potential for a lawsuit,it is more risky than previously thought.

    If assets can be redeployed or sold easily, theproject may be less risky than otherwisethought.

    13-65

  • 7/29/2019 Topic 6 (2012-13A)MP

    67/71

    Machines A and B are mutually exclusive,and will be repurchased. If WACC = 10%,which is better?

    Expected Net CFsYear Machine A Machine B

    0 ($50,000) ($50,000)

    1 17,500 34,000

    2 17,500 27,500

    3 17,500

    4 17,500

    13-66

  • 7/29/2019 Topic 6 (2012-13A)MP

    68/71

    Enter CFs into calculator CFLO register forboth projects, and enter I/YR = 10%. NPVA = $5,472.65 NPVB = $3,636.36

    Is Machine A better? Need replacement chain and/or equivalent annual

    annuity analysis.

    13-67

  • 7/29/2019 Topic 6 (2012-13A)MP

    69/71

    Use the replacement chain to calculate anextended NPVB to a common life.

    Since Machine B has a 2-year life andMachine A has a 4-year life, the common life

    is 4 years.

    13-68

    NPVB = $6,641.62 (on extended basis)

    -50,000 34,000 27,500 34,000 27,500

    -50,000

    -22,500

    0 1 2 310%

    4

  • 7/29/2019 Topic 6 (2012-13A)MP

    70/71

    Using the previously solved project NPVs, theEAA is the annual payment that the projectwould provide if it were an annuity.

    Machine A Enter N = 4, I/YR = 10, PV = -5472.65, FV = 0;

    solve for PMT = EAA = $1,726.46.

    Machine B Enter N = 2, I/YR = 10, PV = -3636.36, FV = 0;

    solve for PMT = EAA = $2,095.24. Machine B is better!

    13-69

  • 7/29/2019 Topic 6 (2012-13A)MP

    71/71

    To be posted in the blackboard after the topicis taught.