town of waddington municipal building site …goo2 c103 c505 m104 scope of work phase 1: 6. town...
TRANSCRIPT
124 M
ILL R
D,
NO
RF
OL
K,
NY
SMIT
H CIVIL E
NGIN
EE
RIN
GP
H#: (3
15) 276-8
056
EM
AIL: S
MIT
HC
E.P
LL
C@
GM
AIL.C
OM
SITE IMPROVEMENTS
TOWN OF WADDINGTON MUNICIPAL BUILDING
SHEET NO. DRAWING N0. DRAWING TITLE
COVER PAGE
SHEET INDEXlocation map
1 OF 5
2 OF 5
3 OF 5
4 OF 5
5 OF 5
site plan
general notes
snow melt system design
details
goo2
c103
c505
m104
scope of work
phase 1:
town will finish grade and re seed disturbed areas.6.
concrete for radiant heat as shown on sheet m104 per detail a on sheet c505.sidewalk as shown on sheet c103 per detail a on sheet c505. Pex tubing shall be installed in contractor shall furnish and install all materials necessary to construct 187 linear feet of new 5.
feet of new sidewalk. town will supply subbase material.place subbase material as indicated by detail a on sheet c505 for construction of 187 linear 4.
sheet c505.REpair existing column footings at locations shown on sheet c103 in accordance with detail c on 3.
c505. town will dispose of material removed.remove unsuitable soil and prep site for placement of subbase as indicated by detail a on sheet 2.
of demolished concrete.demolish 170 linear feet of existing 6ft wide concrete sidewalk. Town will remove and dispose 1.
c505.construct new asphalt parking lot as shown on sheet c103 in accordance with detail b on sheet 1.
phase 2: ((not included IN this bid))
general notes
construction sequence
to normal operations.
contractor shall coordinate their activities with the town, with the goal of avoiding unforeseen disruptions2.
plan, along with a proposed construction schedule, to the owner for approval.
prior to the start of construction, the contractor shall prepare and submit a sequencing of construction1.
out the construction work in accordance with the contract documents.
the construction work; nor will the engineer be responsible for the contractors failure to carry
techniques, sequences or procedures, or for safety precautions and programs in connection with
The engineer is not responsible for, and will not have control of, construction means, methods,7.
by all contractors and on site personnel throughout the project.
CONTRACTOR shall maintain the existing facility drive to allow access to all areas of construction6.
daily dpw operations.
as possible. The contractor shall utilize every effort to minimize disturbance to normal
contractors shall limit the extent of disturbance for each area of construction as much5.
permanently seeded at the end of construction, by the CONTRACTOR, unless otherwise noted.
all areas of site disturbed during construction shall be graded, top soiled, prepared and 4.
respective utility owners.
of all utilities exposed and support systems shall be utilized as recommended by the
excavation or site work. the contractor shall be responsible for the support and protection
contractor shall be responsible for calling dig Safely NY (1-800-962-7962) prior to any3.
etc, that is damaged during construction.
responsible for repair or replacement of any new or existing structures, piping, equipment,
shall be adequately supported and protected during construction. the contractor shall be
existing structures, equipment, and piping adjacent to proposed construction or improvements2.
and all discrepancies between the contract documents and existing conditions.
piping, ETC, as shown on the drawings. immediately report to the owner or engineer any
The contractor shall verify all conditions, dimensions, and elevations of existing structures,1.
concrete sidewalk notes
G002
2 OF 5
machinery, tools, surplus materials, temporary buildings and other temporary structures from the site.
surface, walks, and building, leaving them in as good condition as originally found, and shall remove all
clean-up shall be completed before final acceptance of the work. the contractor shall clean the street 12
compacted and trimmed to conform the cross section shown on the plans.
then be removed. the space on both sides of the walk shall be backfilled with sound ear ht which shall be
backfilling shall be performed after the concrete has gained sufficient strength. the fixed forms may 11.
inspection. subsequent inspection of the finished sidewalks will be made at the discretion of the owner.
inspection of the work to be made before concrete is placed. each job will require the above mentioned
after forms have been set, the owner shall be notified either by telephone or in person, for an 10.
weather and any concrete injured by frost action shall be removed and replaced at their expense.
protection form cold weather -- the contracture shall be responsible for the concrete placed during cold
excessive moisture levels.
portions of the base, subbase, or subgrade layer are frozen, or if the grade exhibits poor stability from
away form artificial heat is at least 35f and rising unless specifically approved. do not place concrete if
cold weather limitations -- no concrete shall be placed unless the temperature of the air in the shade and
concrete at time of placing. concrete shall not be cast when the temperature of the concrete exceeds 90f.
hot weather limitations -- casting of concrete during hot weather shall be limited by the temperature of the
concrete from damage.
protection against rain -- the contractor shall take such precautions as are necessary to protect the
cured. walk must be properly barricaded.
the contractor shall be responsible for the proper protection of the sidewalk until it has sufficiently
protection of concrete shall be performed in the following manner:9.
hold its shape, but shall be removed while the forms are still in place.
inch nor more than 1/4 inch thick. they shall be left in place until the concrete has set sufficiently to
extending the full depth of the concrete. these slab division templates shall be of steel not less than 1/8
square feet and not more than 36 square feet. the unit areas shall be produced by slab division templates
unless otherwise shown on the plans. insofar as feasible, the unit areas shall be square of not less than 16
contraction joints shall be constructed by dividing the sidewalk into areas of approximately 25 square feet
concrete extends from a building or other rigid structure to the curb at intervals no greater than 50 feet.
concrete and the back of the abutting curb or gutter at intersections and at those locations where the
expansion joints, 1/2 inch thick, extending to the full depth of the concrete, shall be placed between the
transverse joints located at 5 foot intervals.
placed in line with the like joints in the existing sidewalk. all standard linear sidewalk shall have
like joints in the adjacent slab. in the case of widening an existing sidewalk, transverse joints shall be
constructed in partial-width slabs, transverse joints in the succeeding slab shall be placed in line with
joints shall be constructed parallel to the centerline, unless otherwise required. when sidewalk is
transverse joints shall be constructed at right angles to the centerline of a sidewalk, and longitudinal
joints shall be constructed true to line, with their faces perpendicular to the surface of the concrete.
8. Joints shall be constructed to provide for expansion and contraction of the concrete as follows:
texture the surface of sidewalk ramps with a coarse broom transverse to the ramp slope.
surface shall be brushed lightly to produce a slightly roughened surface and remove the finishing tool marks.
joints shall be rounded with an approved double edging tool having a radius of 1/4 inch on each side. the
all edges on all sidewalks shall be rounded to a radius of 1/4 inch with an approved finishing tool. all 7.
with a steel float just enough to produce a smooth surface free from irregularities.
voids are removed and the surface has the required grade and cross section. the surface shall be floated
started. the concrete shall be alternately tamped and struck off with a proper strike board until all the
the concrete shall be thoroughly spaded along the forms and joints before finishing operations are 6.
from foreign material. flexible steel or wood forms may be used for sharp curves or special sections.
the required line and grade, and be held in place by adequate stakes, and shall be thoroughly clean and free
the fixed forms shall be the full depth of the concrete. they shall be set firmly on the subgrade, true to
and of sufficient strength to resist springing during the process of depositing and finishing the concrete.
use either slip-form or fixed-form. the fixed forms shall be of metal, straight and free from distortion, 5.
subbase shall be placed under the structure to the thickness shown on the plans.4.
without forming wet or muddy spots. no concrete shall be placed on frozen subgrade.
before concrete is placed, the subgrade shall be thoroughly wetted so that the subgrade is uniformly moist,
material after trenching or before filling. the subgrade shall be thoroughly tamped or otherwise compacted.
to the bottom of the subbase. all unsuitable material under the concrete shall be replaced with granular
the subgrade shall be formed by trenching or filling to the required elevation for bottom of concrete or 3.
and composed of fiber of a cellular nature and asphalt, ground cork or other approved materials.
expansion joint material shall be a non-extruding and resilient type. this material shall be pre molded 2.
concrete shall have a minimum compressive strength of 4000psi at 28 days.1.
SMITH CIVIL ENGINEERING, PLLC
124 MILL ROAD, NORFOLK, NY 13667
EMAIL: [email protected]: (315 276-8056
SHALL STAMP THE DOCUMENT AND INCLUDE THE NOTATION "ALTERED BY" FOLLOWED BY THEIR SIGNATURE, THE DATE OF SUCH ALTERATION, AND A SPECIFIC DESCRIPTION OF THE ALTERATION. TO ALTER AN ITEM IN ANY WAY. IF AN ITEM BEARING THE STAMP OF A LICENSED PROFESSIONAL IS ALTERED, THE ALTERING ENGINEER, ARCHITECT, LANDSCAPE ARCHITECT, OR LAND SURVEYOR IT IS A VIOLATION OF LAW FOR ANY PERSON, UNLESS THEY ARE ACTING UNDER THE DIRECTION OF A LICENSED PROFESSIONAL ENGINEER, ARCHITECT, LANDSCAPE ARCHITECT, OR LAND SURVEYOR,
DRAWING NO.
SHEET NO.
PARCEL NO. UNLESS OTHERWISE NOTEDALL DIMENSIONS IN ft
AFFIX SEAL ON:
TOWN OF WADDINGTON
MUNICIPAL BUILDING SITE IMPROVEMENTS
48 MAPLE STREET, WADDINGTON, NY 13694
9/8/2019
KE
Y:
PR
OP
ER
TY
LI
NE
PE
RC
TES
T
LO
CA
TI
ON
PO
WE
R
LO
CA
TI
ON
W
EXIS
TI
NG
WE
LL (
NO
T S
HO
WN)
C103
3 OF 5
SMITH CIVIL ENGINEERING, PLLC
124 MILL ROAD, NORFOLK, NY 13667
EMAIL: [email protected]: (315 276-8056
SHALL STAMP THE DOCUMENT AND INCLUDE THE NOTATION "ALTERED BY" FOLLOWED BY THEIR SIGNATURE, THE DATE OF SUCH ALTERATION, AND A SPECIFIC DESCRIPTION OF THE ALTERATION. TO ALTER AN ITEM IN ANY WAY. IF AN ITEM BEARING THE STAMP OF A LICENSED PROFESSIONAL IS ALTERED, THE ALTERING ENGINEER, ARCHITECT, LANDSCAPE ARCHITECT, OR LAND SURVEYOR IT IS A VIOLATION OF LAW FOR ANY PERSON, UNLESS THEY ARE ACTING UNDER THE DIRECTION OF A LICENSED PROFESSIONAL ENGINEER, ARCHITECT, LANDSCAPE ARCHITECT, OR LAND SURVEYOR,
DRAWING NO.
SHEET NO.
PARCEL NO. UNLESS OTHERWISE NOTEDALL DIMENSIONS IN ft
AFFIX SEAL ON:
TOWN OF WADDINGTON
MUNICIPAL BUILDING SITE IMPROVEMENTS
48 MAPLE STREET, WADDINGTON, NY 13694
9/8/2019
GRID
NO
RT
H
SITE PLAN
13
7’-
0"
55’
10’-
0"
36’-0"61’-0"
100’
20’-0"
6’-
0"
municipal building
detail c
c505
SCALE: 1"=10’
36’-0"55’-0"
36’-0"
60’-
0"
72’-
0"
42’-0"
18’
MAPLE STREET
Total:172.3 Btu/hr•ft†
Backloss:11.1 Btu/hr•ft†
Design:161.3 Btu/hr•ft†
Snow Melt
Total:172.3 Btu/hr•ft†
Backloss:11 Btu/hr•ft†
Design:161.3 Btu/hr•ft†
Snow Melt
˛�T: 3
Flow: 2.41 USGPM
254 ft @ 9 in
Circuit A-1
˛�T: 3
Flow: 2.52 USGPM
264 ft @ 9 in
Circuit A-2
˛�T: 3
Flow: 3.09 USGPM
324 ft @ 9 in
Circuit A-3
˛�T: 3
Flow: 2.64 USGPM
268 ft @ 9 in
Circuit A-4
˛�T: 3
Flow: 2.64 USGPM
282 ft @ 9 in
Circuit A-5
˛�T: 3
Flow: 2.65 USGPM
283 ft @ 9 in
Circuit A-6
(132.9 °F)
Manifold 1
(132.9 °F)
Manifold 2
42’-0"
72’-
0"
36’-0"
6’-
0"
61’-0"
6’-
0"
36’-0"55’-0"
60’-
0"
36’-0"
6’-
0"
M104
4 OF 5
SMITH CIVIL ENGINEERING, PLLC
124 MILL ROAD, NORFOLK, NY 13667
EMAIL: [email protected]: (315 276-8056
SHALL STAMP THE DOCUMENT AND INCLUDE THE NOTATION "ALTERED BY" FOLLOWED BY THEIR SIGNATURE, THE DATE OF SUCH ALTERATION, AND A SPECIFIC DESCRIPTION OF THE ALTERATION. TO ALTER AN ITEM IN ANY WAY. IF AN ITEM BEARING THE STAMP OF A LICENSED PROFESSIONAL IS ALTERED, THE ALTERING ENGINEER, ARCHITECT, LANDSCAPE ARCHITECT, OR LAND SURVEYOR IT IS A VIOLATION OF LAW FOR ANY PERSON, UNLESS THEY ARE ACTING UNDER THE DIRECTION OF A LICENSED PROFESSIONAL ENGINEER, ARCHITECT, LANDSCAPE ARCHITECT, OR LAND SURVEYOR,
DRAWING NO.
SHEET NO.
PARCEL NO. UNLESS OTHERWISE NOTEDALL DIMENSIONS IN ft
AFFIX SEAL ON:
TOWN OF WADDINGTON
MUNICIPAL BUILDING SITE IMPROVEMENTS
48 MAPLE STREET, WADDINGTON, NY 13694
9/8/2019
SCALE: 1/4"= 1’
snow melt system design
total flow rate
design temp drop
total manifolds
total btu/hr 211,930
total heated area 1230 sf
fluid type 50% propylene glycol
max head loss
30 f
total circuit lengths
total circuits 6
2
total tubing volume 30.76 gal
glycol volume
circuit schedule
circuit
a1
a2
a3
a4
a5
length
254’
264’
324’
268’
282’
manifold
manifold 1
manifold 1
manifold 1
manifold 2
manifold 2
tube type
34" barrier pex
34" barrier pex
34" barrier pex
34" barrier pex
34" barrier pex
manifold schedule
summary
manifold name
manifold 2
circuits flow rate supplied
temp
max temp
drop
manifold type manifold
head loss
total
head loss
3 133 31 copper 1-12" w/ shut off
and balancing valves
1.0 17.3 18.3
manifold 1 3 133 31 copper 1-12" w/ shut off
and balancing valves
1.0 26.0 27.0
total 5 15.95 ----- ----- ----- ----- ----- 27.0
9"
total
manifold 1
circuit
a1
a2
total
length
254’
tube
spacing
area
covered
185 sf 34" barrier pex
tubing
2.41
head
loss
13.1
flow
rate
temp
drop
30
load
btu/hr
31,962
9"264’ 34" barrier pex 2.52 14.7 30 33,425
841’
194 sf
618 sf 106,503----- -----
9"
total
manifold 2
circuit
a4
a5
total
length
tube
spacing
area
covered
204 sf 34" barrier pex
tubing
2.64
head
loss
16.3
flow
rate
temp
drop
30
load
btu/hr
35,106
9"282’ 34" barrier pex 2.64 17.2 30 35,141
612 sf 105,427----- ----- -----
a6 9"283’ 34" barrier pex 2.65 17.3 30204 sf
tubing coil schedule
coil
coil 1
coil 2
length
800’
tube type
34" barrier pex
34" barrier pex
length used
889’
786’
summary
length
254’
circuits cut
circuit location coil
manifold 1 coil 2a1
264’ manifold 1 coil 2a2
324’ manifold 2 coil 1a3
268’ manifold 2 coil 2a4
282’ manifold 2 coil 1a5
circuit
head loss
15.95
27
1674
15.38 gal
8.02
7.94
a3 9"324’ 34" barrier pex 3.09 30 41,116239 sf
8.02 26.0
26.0
----
268’
204 sf
35,180
833’ 7.94 ----
a6 283 manifold 2 34" barrier pex
1,000’
283’ manifold 2 coil 1a6
snow melt design
C505
5 OF 5
SMITH CIVIL ENGINEERING, PLLC
124 MILL ROAD, NORFOLK, NY 13667
EMAIL: [email protected]: (315 276-8056
SHALL STAMP THE DOCUMENT AND INCLUDE THE NOTATION "ALTERED BY" FOLLOWED BY THEIR SIGNATURE, THE DATE OF SUCH ALTERATION, AND A SPECIFIC DESCRIPTION OF THE ALTERATION. TO ALTER AN ITEM IN ANY WAY. IF AN ITEM BEARING THE STAMP OF A LICENSED PROFESSIONAL IS ALTERED, THE ALTERING ENGINEER, ARCHITECT, LANDSCAPE ARCHITECT, OR LAND SURVEYOR IT IS A VIOLATION OF LAW FOR ANY PERSON, UNLESS THEY ARE ACTING UNDER THE DIRECTION OF A LICENSED PROFESSIONAL ENGINEER, ARCHITECT, LANDSCAPE ARCHITECT, OR LAND SURVEYOR,
DRAWING NO.
SHEET NO.
PARCEL NO. UNLESS OTHERWISE NOTEDALL DIMENSIONS IN ft
AFFIX SEAL ON:
TOWN OF WADDINGTON
MUNICIPAL BUILDING SITE IMPROVEMENTS
48 MAPLE STREET, WADDINGTON, NY 13694
9/8/2019
n.t.s.
1.5% cross slope
heated concrete sidewalk detaildetail A
A107
5"
asphalt pavement
3/4" pex tubing
1’-
0"
6" compacted 2" minus subbase
dot approved support chairs
at all curb and building interfaces
Provide 1/2" bituminous expansion joint
note:
2" rigid foam insulation
6’-0"
400opsi concrete with W2.9x6x6 sheet mesh
n.t.s.
detail b
A107
existing asphalt
asphalt sealant at all joints
1-1/2" top course
3-1/2" binder course
2" minus compacted fill
6" minus compacted fill
woven geotextile fabric
material in place
or compacted granular
Undisturbed earth
1’-
0"
4"
3
1/
2 "
1
1/
2 "
asphalt pavement detail
26’-6"
18’-8 7/8 "
10’-0"
7’- 27/32 "
45°0’0.0"
PARKING SPACE DIMENSIONS
n.t.s.
detail c
c103
existing steel column and base plate
new concrete to be placed
existing steel reinforcement
existing concrete
column footing repair
load column and re-anchor to new concrete4.
3. place 4000psi concrete to original height of footing.
to expose existing steel reinforcement.
remove deteriorated concrete extending below grade2.
unload existing column1.
repair procedure