tranning pptdadd

Upload: abhishek-meena

Post on 03-Apr-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 TRANNING PPTdadd

    1/17

    DEPARTMENT OF CIVIL ENGINEERING

    PRESENTATION

    ON

    VIVEKANANDA INSTITUTE OF TECHNOLOGY(EAST)

    BUILDING CONSTRUCTION

    PRESENTED TO:- PRESENTED BY:

    Dr. SUDHIR KUMAR TEWATIA PAWAAN Kr. MEENA

    HOD CIVIL ENGINEERING Roll no. 09EVVCE033

    4th year ,7th semester

  • 7/28/2019 TRANNING PPTdadd

    2/17

    About the project

    Project name :

    Project location:

    Construction agency :

    Total area : 7 acare

    Total cost : 13 crores

    Earthquake zone : 7th

    Type of foundation : RAFT FOUNDATION 60cm (16 mm steel bar )

    Construction of class A type of school building and

    9 unit staff qtrs for kendriya vidyalya at karauli .

    at karauli (city)

    Construction under cpwd (jaipur)

  • 7/28/2019 TRANNING PPTdadd

    3/17

  • 7/28/2019 TRANNING PPTdadd

    4/17

    Material used at site

    Steel reinf. :- HYSD Fe-500 TMT of SAIL STEEL company.

    Cement :- cement is of 53 grade of ULTRA TECH company.

    Bricks:- The bricks are used of first class.

    Admixture:- The admixture is used of SIKA COMPANY.

    WATER:- Drinking water is used which has pH 6.5 to 8.0.

  • 7/28/2019 TRANNING PPTdadd

    5/17

    Steps involved in Construction of building

    SITE CLEARANCEPOSITIONING AND LAYOUT

    EXCAVATION

    PLAIN CEMENT CONCRETE (P.C.C)

    LAYINGOF FOUNDATION

    CASTINGOFBEAM ,COLUMNANDSLAB

    BRICKWORK

    PLASTERING

  • 7/28/2019 TRANNING PPTdadd

    6/17

    SITE CLEARANCE:

    The very first step is site clearance which involves

    removal of grass and vegetation along with anyother objections which might be there in the site

    location.

    POSITIONING AND LAYOUT:The centre point was marked with the help of a

    thread and plumb bob as per the grid drawing. With

    respect to this center point, all the other points of

    columns were to be decided so its exact position isvery critical.

  • 7/28/2019 TRANNING PPTdadd

    7/17

    LAYOUT

  • 7/28/2019 TRANNING PPTdadd

    8/17

    EXCAVATION:

    Excavation was carried out both manually as well

    as mechanically. Normally 1-2 earth excavators

    (JCBs) andpoclain were used for excavating thesoil. Adequate precautions are taken to see that

    the excavation operations do not damage the

    adjoining structures. Excavation is carried out

    providing adequate side slopes and dressing ofexcavation bottom

  • 7/28/2019 TRANNING PPTdadd

    9/17

    PLAIN CEMENT CONCRETE (P.C.C):

    After the process of excavation, laying of plain

    cement concrete that is PCC is done. A layer of 4

    inches was made in such a manner that it was notmixed with the soil. It provides a solid base for the

    raft foundation and a mix of 1:5:10 that is, 1 part of

    cement to 5 parts of fine aggregates and 10 parts

    of coarse aggregates by volume were used in it.Plain concrete is vibrated to achieve full

    compaction. Concrete placed below ground should

    be protected from falling earth during and after

    placing. Concrete placed in ground containing

    deleterious substances should be kept free from

    contact with such a ground and with water draining

    there from during placing and for a period of sevenda s.

  • 7/28/2019 TRANNING PPTdadd

    10/17

    LAYING OF FOUNDATION

    This term includes the portion of the structure below the plint

    level as well as the artificial arrangement of concrete blocks,

    piles, raft, grillage etc. Which are provided to transmit theloads of the structure (including the dead weight of the

    structure itself) to the soil below.

    Classification of Foundation :

    1. Simple, Shallow and Deep foundation2. Pad /strip type and piled foundation

    Purpose of foundation:1. To distributes the loads of the structure over large soil area so as to

    avoid over loading of the soil beneath.

    2.To load every the sub-stratum and thus prevent unequal settlement.3.To provide a level surface for building and thus increase its stability,

    preventing, overturning and instability.

  • 7/28/2019 TRANNING PPTdadd

    11/17

    RAFT FOUNDATION

  • 7/28/2019 TRANNING PPTdadd

    12/17

    COLUMN:

    A column or pillar in andstructural engineering is a vertical

    structural element that transmits, through compression, the

    weight of the structure above to other structural elements

    below.

    BEAM:-

    A structural member of reinforced concrete, placed

    horizontally over openings to carry loads. A bar is actedupon by forces or couples or both in axial plane, which

    cause bending of bar, is known as a beam.

    Types of beam:

    Singly reinforced beam

    Doubly reinforced beam

  • 7/28/2019 TRANNING PPTdadd

    13/17

    SLAB:

    A concrete slab is a common structural element of modern

    buildings. Horizontal slabs of steelreinforced concrete,

    typically between 10 and 50 centimeters thick, are mostoften used to construct floors and ceilings, while thinner

    slabs are also used for exterior paving.

  • 7/28/2019 TRANNING PPTdadd

    14/17

    BRICKWORK:

    Brickwork is masonry done with bricks and mortar and is

    generally used to build partition walls. In our site, all the

    external walls were of concrete and most of the internalwalls were made of bricks. English bond was used and a

    ratio of 1:4 (1 cement: 4 coarse sand) and 1:6 were used

    depending upon whether. The wall is 4.5 inches or 9 inches

  • 7/28/2019 TRANNING PPTdadd

    15/17

    PLASTERING:

    At site plastering was done and bricks work as well as

    stone work and other vertical part of building surface. At our

    site the ratio for plaster is taken as 1:6 for half brick

    masonry and 1:3 for columns and bottom are slab. Mortar

    used for plastering was cement, sand, mortar. Fine sand

    was used for preparing mortar. It was not fine so that it canpass more than 5% through a 50-mesh sieve.

    Plastering was done only the internal surface of the room.

    At external surface there was stone masonry. Plastering

    thickness was 10 mm. on brickwork and 15 mm. on stonework some place cement coating was used.

  • 7/28/2019 TRANNING PPTdadd

    16/17

  • 7/28/2019 TRANNING PPTdadd

    17/17

    Thank You

    Kingsoft OfficeMake Presentation much more fun

    ANY QUARIES