tranning pptdadd
TRANSCRIPT
-
7/28/2019 TRANNING PPTdadd
1/17
DEPARTMENT OF CIVIL ENGINEERING
PRESENTATION
ON
VIVEKANANDA INSTITUTE OF TECHNOLOGY(EAST)
BUILDING CONSTRUCTION
PRESENTED TO:- PRESENTED BY:
Dr. SUDHIR KUMAR TEWATIA PAWAAN Kr. MEENA
HOD CIVIL ENGINEERING Roll no. 09EVVCE033
4th year ,7th semester
-
7/28/2019 TRANNING PPTdadd
2/17
About the project
Project name :
Project location:
Construction agency :
Total area : 7 acare
Total cost : 13 crores
Earthquake zone : 7th
Type of foundation : RAFT FOUNDATION 60cm (16 mm steel bar )
Construction of class A type of school building and
9 unit staff qtrs for kendriya vidyalya at karauli .
at karauli (city)
Construction under cpwd (jaipur)
-
7/28/2019 TRANNING PPTdadd
3/17
-
7/28/2019 TRANNING PPTdadd
4/17
Material used at site
Steel reinf. :- HYSD Fe-500 TMT of SAIL STEEL company.
Cement :- cement is of 53 grade of ULTRA TECH company.
Bricks:- The bricks are used of first class.
Admixture:- The admixture is used of SIKA COMPANY.
WATER:- Drinking water is used which has pH 6.5 to 8.0.
-
7/28/2019 TRANNING PPTdadd
5/17
Steps involved in Construction of building
SITE CLEARANCEPOSITIONING AND LAYOUT
EXCAVATION
PLAIN CEMENT CONCRETE (P.C.C)
LAYINGOF FOUNDATION
CASTINGOFBEAM ,COLUMNANDSLAB
BRICKWORK
PLASTERING
-
7/28/2019 TRANNING PPTdadd
6/17
SITE CLEARANCE:
The very first step is site clearance which involves
removal of grass and vegetation along with anyother objections which might be there in the site
location.
POSITIONING AND LAYOUT:The centre point was marked with the help of a
thread and plumb bob as per the grid drawing. With
respect to this center point, all the other points of
columns were to be decided so its exact position isvery critical.
-
7/28/2019 TRANNING PPTdadd
7/17
LAYOUT
-
7/28/2019 TRANNING PPTdadd
8/17
EXCAVATION:
Excavation was carried out both manually as well
as mechanically. Normally 1-2 earth excavators
(JCBs) andpoclain were used for excavating thesoil. Adequate precautions are taken to see that
the excavation operations do not damage the
adjoining structures. Excavation is carried out
providing adequate side slopes and dressing ofexcavation bottom
-
7/28/2019 TRANNING PPTdadd
9/17
PLAIN CEMENT CONCRETE (P.C.C):
After the process of excavation, laying of plain
cement concrete that is PCC is done. A layer of 4
inches was made in such a manner that it was notmixed with the soil. It provides a solid base for the
raft foundation and a mix of 1:5:10 that is, 1 part of
cement to 5 parts of fine aggregates and 10 parts
of coarse aggregates by volume were used in it.Plain concrete is vibrated to achieve full
compaction. Concrete placed below ground should
be protected from falling earth during and after
placing. Concrete placed in ground containing
deleterious substances should be kept free from
contact with such a ground and with water draining
there from during placing and for a period of sevenda s.
-
7/28/2019 TRANNING PPTdadd
10/17
LAYING OF FOUNDATION
This term includes the portion of the structure below the plint
level as well as the artificial arrangement of concrete blocks,
piles, raft, grillage etc. Which are provided to transmit theloads of the structure (including the dead weight of the
structure itself) to the soil below.
Classification of Foundation :
1. Simple, Shallow and Deep foundation2. Pad /strip type and piled foundation
Purpose of foundation:1. To distributes the loads of the structure over large soil area so as to
avoid over loading of the soil beneath.
2.To load every the sub-stratum and thus prevent unequal settlement.3.To provide a level surface for building and thus increase its stability,
preventing, overturning and instability.
-
7/28/2019 TRANNING PPTdadd
11/17
RAFT FOUNDATION
-
7/28/2019 TRANNING PPTdadd
12/17
COLUMN:
A column or pillar in andstructural engineering is a vertical
structural element that transmits, through compression, the
weight of the structure above to other structural elements
below.
BEAM:-
A structural member of reinforced concrete, placed
horizontally over openings to carry loads. A bar is actedupon by forces or couples or both in axial plane, which
cause bending of bar, is known as a beam.
Types of beam:
Singly reinforced beam
Doubly reinforced beam
-
7/28/2019 TRANNING PPTdadd
13/17
SLAB:
A concrete slab is a common structural element of modern
buildings. Horizontal slabs of steelreinforced concrete,
typically between 10 and 50 centimeters thick, are mostoften used to construct floors and ceilings, while thinner
slabs are also used for exterior paving.
-
7/28/2019 TRANNING PPTdadd
14/17
BRICKWORK:
Brickwork is masonry done with bricks and mortar and is
generally used to build partition walls. In our site, all the
external walls were of concrete and most of the internalwalls were made of bricks. English bond was used and a
ratio of 1:4 (1 cement: 4 coarse sand) and 1:6 were used
depending upon whether. The wall is 4.5 inches or 9 inches
-
7/28/2019 TRANNING PPTdadd
15/17
PLASTERING:
At site plastering was done and bricks work as well as
stone work and other vertical part of building surface. At our
site the ratio for plaster is taken as 1:6 for half brick
masonry and 1:3 for columns and bottom are slab. Mortar
used for plastering was cement, sand, mortar. Fine sand
was used for preparing mortar. It was not fine so that it canpass more than 5% through a 50-mesh sieve.
Plastering was done only the internal surface of the room.
At external surface there was stone masonry. Plastering
thickness was 10 mm. on brickwork and 15 mm. on stonework some place cement coating was used.
-
7/28/2019 TRANNING PPTdadd
16/17
-
7/28/2019 TRANNING PPTdadd
17/17
Thank You
Kingsoft OfficeMake Presentation much more fun
ANY QUARIES